Checklist Mannual
Checklist Mannual
1 Are the Safety norms being covered as per HSEM Process? Yes No
3 Sanctioned layout plan matches with the actual boundaries of the plot. Yes No
5 Initial level survey conducted (survey record maintained) & RL shifted. Yes No
Permissions for shifting of utility lines, other structures, cutting of trees Yes
6 No
obtained from concerned authorities.
8 Unsuitable material for road construction removed and neatly stacked. Yes No
1 Are the Safety norms being covered as per HSEM Process? Yes No
A Prior To Surveying
6 The accuracy of reference points and Existing bench marks is ok? Yes No
Observations:-
B During Surveying
a Piles Yes No
b Piping Yes No
c Cable/Duct Yes No
d Sewers Yes No
Observations:-
C After Surveying
1 Are the Safety norms being covered as per HSEM Process? Yes No
1 Are the right tools for the work available in site? Yes No
Observations:-
Is the setting out distance ensured at all the sides of the building as pe the Yes No
3
setting out drawing?
4 Are the step down pillar built properly where ever the ground is sloping? Yes No
5 Are spacing between the grid pillars maintained as per the drawing? Yes No
6 Have the top level of all the pillars maintained in same level? Yes No
Observations:-
2 Check if the column/footings marked properly with the line dori? Yes No
A Prior To Excavation
8 Are the proper access and exit provided from the work area? Yes No
Observations:-
B During Excavation
C After Excavation
Has the required ground bottom been covered with polythene sheet to avoid the Yes No
1
slush formation?
2 Are joint inspections done & record maintained? Yes No
1 Are the Safety norms being covered as per HSEM Process? Yes No
A Prior To Application
3 Check for strata and removal of all loose material before treatment Yes No
Observations:-
B During Application
Observations:-
C After Application
1 Is the treated area exposed to atmosphere for long periods of time? Yes No
1 Are the Safety norms being covered as per HSEM Process? Yes No
A Prior To Backfilling
2 Has the layer-by layer marking done ? (300MM) or as per specification Yes No
Has the area cleared from debris/dried concrete/ steel/ boulders & slush Yes No
3
before initiate the back filling?
The area to be backfilled dewatered completely before starting the activity Yes No
4
of backfilling?
Deshuttering is complete and shuttering material is cleared from the area of Yes No
5
backfilling.
Has all the pre activities ( water proofing, plumbing & electrical line etc) Yes No
6
completed ?
Observations:-
B During Backfilling
Yes No
1 Has the layer height maintained as per the specification/method statement?
Are the stone free materials been used for layerwise backfilling to avoid Yes
2 No
damage to water proofing?
Is the appropriate equipment employed for each layer of compaction as per Yes No
3
specification/BOQ?
Is the Compaction ensured where the compacting equipment cannot be Yes No
4
accessed?
5 Compaction test done on every layer of back filling and recorded? Yes No
6 Is the number of core cut taken for compaction test is as per specification? Yes No
Observations:-
C After Backfilling
Compaction test conducted (prior placing next layer) and the results Yes No
1
observed above 95 % of Maximum Dry Density (by Proctor Test)
Earth filled compacted in layers not more than 300 mm with optimum water Yes No
2
content or as recommended in contract specification.
3 Backfilling is completed & the area is cleaned & tidy. Yes No
2 Are all the precedings activities been completed for the area? Yes No
4 Has the area been compacted well & test records mainatained? Yes No
6 Check whether the shuttering dimensions and supports are proper? Yes No
Observations:-
B During PCC
1 Is the grade of concrete recommended by the structural engineer? Yes No
2 Is the top finished level checked when the concrete is fresh? Yes No
Observations:-
C After PCC
1 Is curing been followed properly to the minimum curing period? (7 day's) Yes No
Observations:-
Pile penetration ratio recorded at depth specified and checked with Yes No
7
requirement given by geotech consultant
8 Has steel casing anchored well with in the stable strata? Yes No
12 Has the depth of bedrock compared with Bore Hole Data? Yes No
Reinforcement cut to the length & shape as per drawing, the depth of pile Yes No
15
bore with provision of cover blocks in spiral pattern at the bottom & sides.
Observations:-
5 Rig movement not allowed over fresh cast pile for atleast 72 hrs. Yes No
Boring activity not allowed near & around freshly cast pile Yes No
( atleast for a period of 4 hrs i.e. till initial setting time)
6
( preferably alternate pile to be bored)
2 Concrete Grade
B Reinforcement Details
2 Lap Length:-
3 Concrete Cover:-
Has the column reinforcement checked for size ,diameter & no of Yes No
7
reinforcements?
8 Have the cover block of required size been placed at require interval? Yes No
Observations:-
B During Formwork
1 Has the shuttering board been cleaned neat & oiled properly? Yes No
3 Have the tie rods& side supports been fixed properly? Yes No
2 Check right angle and diagnols of thecolumn from the top Yes No
4 Check for alignment or C/C distance with respect to adjacent Column Yes No
6 Check cover patti provided at top to maintain uniform cover for all sides Yes No
Observations:-
B During Formwork
Is the shuttering oil applied properly & shuttering board been erected Yes No
1
without any gap?
Is the water stopper provided at the construction joint coming below the Yes No
2
ground level?
3 Have the tie rods& side supports been fixed properly? Yes No
C After Formwork
2 Check right angle and diagnols of the vertical member from the top Yes No
Check alignment of all vertical members at floor level with respect to grid Yes No
3
lines
4 Check plumb for vertical members(min. 2 sides) Yes No
Is the 1 meter marking been transferred in all the columns & TBM ensured Yes No
3
near the lift/staircase column prior to start scaffolding?
Are the materials used for stagging & scaffolding in good workable Yes No
5
condition and as per shuttering drawing?
Check whether the base surface is well compacted/PCC laid before raise Yes No
6
the stagging work in case of basement?
Are the ply board been used for shuttering is as per specification/ BOQ (film Yes No
7
face not damaged/not too often used)?
Observations:-
B During Formwork
Is the supports being used for the slab is as per approved shuttering Yes No
3
drawing?
4 Are foams strip provided at column junctions to avoid slurry leakage? Yes No
Observations:-
7 Check for sealing of gaps, joints, holes and tie rods Yes No
9 Check if there are any gaps in the beam & column junctions? Yes No
10 Are the masking tapes provided properly at all joints & oiled properly? Yes No
Check whether the template is made & placed in position to ensure Yes No
11
required structural drop at bathroom/balconies/toilet etc?
Check whether the tie rods are provided if the beam depth exceeds Yes No
12
600mm?
13 Are the dowel holes covered properly? Yes No
15 Are the extra supports not removed within 24 hrs of concreting? Yes No
16 Have the supports been erected verticality for the beams & slab? Yes No
Are the outer/phriperal beams tie rod supports provided and supported Yes No
17
adquately to avoid bulging?
Signature : Site Engineer
Observations:
Whether the above points checked and in order? YES NO
Corrective Action Proposed
4 Are the reinforcement free from oil, rust, soil & grease etc? Yes No
Check whether the required shuttering oil applied to slabs,beam and beam Yes No
5
bottom?
6 Is the excess shuttering oil wiped out before laying the reinforcement? Yes No
Observations:-
B During Reinforcement
Yes No
1 Is the lapping length ensured as per the structural consultant instructions?
C After Reinforcement
Check if adequate anchorage lengths are provided at the bottom of the Yes No
1
column reinforcement
Is the lapping ensured in the staggered manner at the specified location as Yes No
2
per approved drwaings?
Are the dowels left in sufficient development length at appropriate Yes No
3
locations?
Is the pin rod of sufficient diameter ensured between two layers of Yes No
4
reinforcements to ensure easy flow of concrete?
Check if U rod placed of required size & interval to maintain the gap in Yes No
7
RCC wall work?
Check if corner (extra) reinforcement provided around the cut out as per Yes No
8
the details in slab & wall?
Check if the cover blocks are of correct sizes & placed at correct spacings Yes No
9
Check if the position of chairs are not disturbed due to movement of Yes No
11
labour?
12 Has the dowel bars tied properaly to maintain the spacing and allignment? Yes No
13 Has the electrical conduiting work completed as per the drawing? Yes No
Is the area checked & certified by the consultant & documents available at site? Yes No
2
4 Are the required no. of cube moulds available & has it cleaned & oiled for casting? Yes No
5 Is the reference level marked to cross check the concrete top level finishing? Yes No
Check for completion of preceding activities such as fixing of inserts & embedments Yes No
6 and service conduits,etc
7 Is the total area checked for proper size of cover blocks & chair rods in position? Yes No
8 Are the vibrators been checked for workable condition before concreting? Yes No
Observations:-
B During RCC
Is the cement slurry poured at all the construction joints and column junctions No
1 Yes
before concreting?
Has the construction joint surface cleaned and treated as per the specification / Yes No
2 WMS before concreting?
3 Is the grade of concrete as per the approved design mix by consultant? Yes No
Has the slump checking been carried out at regular intervals for adherence of No
4 Yes
standards?
5 Is the concreting sequence been followed(beams are concreted before slab)? Yes No
6 Are all foremen present at the work location to carry out the maintenance if any? Yes No
Has the higher grade of concrete been poured prior to lower grade of concrete at
8 Yes No
column junctions if any?
9 Has the top level maintained as per the concrete level marking? Yes No
10 Is the early curing starts in summer season, to avoid shrinkage cracks. Yes No
Is the temporary stoppers at beam / column junctions for different grades of Yes No
11 concerete are removed?
Observations:-
C After RCC
Has the area finished properly without undulation &covered with wet hessian Yes No
1 cloth/spray curing done after 4hrs of concreting?
Check whether inserts which are embedded with concrete surface are exposed Yes No
4 properly.
Drawing No.
Drawing No.
Not REMARKS
SR NO. Description Deviations At Actual Ok
Ok
Pour card for concreting work is duly signed & documented.
1
Deshuttering & curing is done.
I) Column covered with wet hessian cloth.
2 II) Ponding done on slab by making bunds
III) Curing of slab done from floor below (after de- shuttering) by
spraying water on ceiling.
Any left out shuttering pieces, masking tape or external
3
undesirable materials left on surface.
Location of member w.r.t grid and level is as per drawings.
4
Columns:
i) Dimensions
5 ii) Verticality
iii) Squareness
Beam:
i) Dimensions
6 ii) Depth
iii) Level
iv) Straightness
Wall:
i) Dimensions
7 ii) Verticality
iii) Offset or deviation in continuous surface.
iv) Straightness
Slab:
i) Dimensions
8 ii) Thickness
iii) Level
9 Opening size
Footing:
i) Dimensions
10 ii) Thickness or Heights
iii) Eccentricity.
iv) Squareness
Stairs:
i) Length of clear span
11 ii) Width of flight
iii) Trade and Riser width.
iv) Waist thickness
12 Lift: Verticality
Grouting of tie rod and wall tie holes within 3 days or before
17
removal of staging.
Contractor Client
SHAPOORJI PALLONJI REAL ESTATE
SPRE/QA-QC/CH-015 Checklist For Line out of Bricks and Block Masonary
Site Work Activity
Has the Proper housekeeping and cleaning of all loose materials and dead Yes No
5
concrete, shuttering material, reinforcements are removed?
Has the removal of masking tape, nails on ceiling, beam and hacking of Yes No
6
concrete surfaces wherever masonry touches concrete surface is done?
Removal and finishing of all reinforcement, wall ties/tie rods used for
Yes No
7 support system (wherever masonry touches column/shearwall) as per
approved methodology.
Check the mortar mixing being done in MS tray with measurement box for Yes No
9
right mix proportions?Mixing on the floor is not permitted.
10 check the water used for mortar mixing is potable Yes No
Yes No
12 Has the 1 metre marking done in all the RCC elements?
RCC slab O.K. for loading with masonry ( Min.67 % of concrete strength Yes No
13
achieved )
Observations:-
Is the line out done as per the specifications and relevant architectural Yes No
5
drawing?
6 Is the gap maintained between two Bricks/ Blocks min. 10mm? Yes No
Is the architectural GFC drawing and work process displayed in respective Yes No
8
flat
Observations:-
Is the layer wise marking of Bricks/Blocks done on the RCC member like
5 Yes No
Column, core wall, shear wall etc.
8 Is the grade of cement approved & not more than 90 days old? Yes No
9 Has the 1 metre marking done in all the RCC elements? Yes No
Observations:-
Is the Bond maintained as per the specifications? (like English bond / Yes No
4
Flemish bond etc)
5 Are the sizes of the mortar joints uniform & not more than 10mm? Yes No
Is height of the construction not more than 1.2 metre in a day or as per Yes No
8
specification?
Has the RCC band , been done at every 1 metre interval of masonry for 100 Yes No
9
mm thick walls?
Observations:-
Is the architectural GFC drawing and work process displayed in respective Yes No
5
flat
Observations:-
4 Is the Chat coat/ Cement slurry applied on the RCC member? Yes No
6 Are the sizes of the mortar joints uniform & not more than 10mm? Yes No
Is the course under the beam bottom built with full blocks/bricks after No
9 Yes
construction of masonry at immediate above floor till lintel bottom?
10 Has the lintel concreted with sufficient bearing/anchoring at required level? Yes No
Observations:-
Courses laid horizontal, in line, perfectly vertical , no continuous vertical joint. Yes No
4
5 Is the full block placed below the beam bottom? ( Top course) Yes No
6 Dimensions of rooms & passages are checked & found as per drawing? Yes No
7 Is the spilled mortar and masonry waste are removed from working place Yes No
Has the construction date been marked to follow up the curing min.of 7 No
8 Yes
days?
Has chicken mesh provided on the electrical conduits & junction of Yes No
3
masonry& RCC members?
4 Check for Raking of masonary joints and hacking on RCC Surfaces Yes No
6 Check for cleaning and washing of masonary & RCC surfaces Yes No
9 Ensure electrical conduit boxes matches with the level pads Yes No
10 Check for availability of materials required for respective type of plastering Yes No
11 Whether all the lintel/lofts been completed & hacked properly? Yes No
12 Yes No
Ensure the conduit box filled/covered with gunny bag or sand
Check the unfinished sizes of the room as is satisfactory with respect to Yes No
13
Drawing
Observations:-
B During Plastering
1 Cement Sand mortar Proportion
2 Check for true level surface, right angle, plumb, edge, sharp corners Yes No
6 If plaster bull thickness is more, has it finished by two coats of plaster? Yes No
Has the second/successive coat of plaster being carried out after allowing Yes No
7
1 day of curing to the previous day work?
Check the Opening dimensions for the doors and windows as per the Yes No
8
drawing
Observations:-
C After Plastering
1 Check for Removal of Dead Mortar and Debris Yes No
Check whether top course of block/brick work been packed properly without No
2 Yes
any hollowness in the mortar joint?
If any projection like rod, concrete is observed , has it been cut flush to the Yes No
3
beam prior to start plastering?
Is the tie rod holes/tie pin hole filled as per the specification prior to start Yes No
4
plastering?
Is the surface preparation (like cleaning of efflorescence, Hacking on RCC
Yes No
5 surface, packing of plumbing cut outs & covering of window grills etc)
done?
If any concrete band/chejja/elevation features is coming, have they been Yes No
6
constructed & cured properly prior to start plastering?
Has the GI chicken mesh fixing works completed at the junction of Yes No
7
masonry& RCC members?
Check whether the plaster bull thickness is sufficient to cover the mesh Yes No
8
packing & placed at appropriate intervals (≤ 6feet distance) w.r.t plumb?
9 Has the wall prewetted one day before prior to start the plastering? Yes No
Observations:-
B During Plastering
1 Cement Sand mortar Proportion
2 Is the grade of cement used as per specification? Yes No
Is the mortar mixing been done in the MS tray with measurement box for Yes No
3
right mix proportion?
4 Are the number of coat of plaster followed as per the specified thickness? Yes No
5 Is the waterproof admixtures mixed as per dosage rate for plaster? Yes No
Is the finishing coat being carriedout with minimum 4days curing of rough Yes No
6
coat of plaster?
8 Check for Right Angles & Plumb for the jambs Yes No
Are the approved dimensions plaster grooves made when the mortar is in
9 Yes No
fresh condition?
Observations:-
C After Plastering
1 Check for Removal of Dead Mortar and Debris Yes No
If any leakages found or cracks identified on concrete surface and open 6mmx6mm
V groove and fixing PVC nozzles at 1.0 m c/c as per site condition.Fill the V groove Yes No
3
with Polymer modified mortar GP2
Pressure grouting where ever necessary ,by cement slurry admixed with integral
waterproof compound @ 225 gms per bag of cement of 50 Kg at pressure 2-4 Yes No
4
kg/cm2 as per specification
Is the chemical coat applied at junction of minimum 100mm width on both side i.e Yes
5 No
horizontal and vertical portion
Coving at all around the junctions of min 50x50 mm or as per site condition vertical
and horizontal with Cement sand mortar 1:4 and admixed with integral waterproof Yes No
6
compound at dosage of 200ml per bag of cement and embeed 20mm aggregate in
to it as per specifications.
where ever required bore packing to be checked ,surface to be roughned,apply of
Yes No
7 one coat SBR Latex or equivalent to enhance adhesion, and providing and laying of
GPI/GP2/micro concrete for entaire depth of slab/ width of beam.
Check for availability of material and tools as per procedure /method statement.
8 Yes No
Observations:-
Check Mixing of Acralic polymer cementatious base chemical and cement with 1:1
proportions need uniform mix by mechanical stirrer as per manufacturer guidelines Yes No
2
before ready to use on substrate
check application of 1 st coat of Acralic polymer base chemical on substrate as per Yes No
3
manufacturer guidelines
Check application of 2 nd coat or subsequent coat after 4hrs perpendicular in the
4 Yes No
direction of 1st coat
Check chemical application minimum upto 300 mm height or as per site engg
5 Yes No
instruction on parapet wall
Observations:-
Remarks:
Waterproofing work done is found Satisfactory/Non-Satisfactory ( Put )
Check drain out of water and Bull marks as per slope shown in drawing Yes No
2
Remarks:
Waterproofing work done is found Satisfactory/Non-Satisfactory ( Put )
Yes No
2 Check drain out of water and Bull marks as per slope shown in drawing
2 Is the slope maintained towards the drain outlet as per shown in drawing. Yes No
Remarks:
Waterproofing work done is found Satisfactory/Non-Satisfactory ( Put )
5 Is the Tie rod holes if any filled with GP2 after removal of inserted PVC Pipe Yes No
Ponding test shall be carried out for complete capacity of the tank for mimimum of Yes No
6 3 days
Dampness/minor leaking points found if any,to be pressure grouted after fixing the
Yes No
7 PVC nipples and grout using with cement slurry admixed with non shrink
compound @ rate 225 gms per bag of cement or as per specification
Yes No
8 Check for availability of material and tools as per procedure /method statement.
Observations:-
check Mixing of Acralic cementatious polymer base chemical and cement with 1:1
proportions as per manufacturer guidelines and need uniform mix by mechanical Yes No
2
stirrer before ready to use on substrate
Check application of 1st coat of acralyc cementatious polymer base chemical coat Yes No
3
is as per manufacturer guidelines
Check application of 2 nd coat or subsequent coat after 4-6 hrs perpendicular in Yes No
4
the direction of 1st coat
Protective plastering with CM 1:4 of thickness 15mm for walls admixed with
Yes No
5 Dr.Fixit pidiproof LW/ Sunanda NGT or equivalent at rate of 200 ml for 50 Kg bag
of cement.
Check for protection plaster of 40mm or screed of M20 with thickness of 60 mm to Yes No
6 slope for floor
Observations:-
Remarks:
Waterproofing work done is found Satisfactory/Non-Satisfactory ( Put )
Refer to the Approved Work Method Statement and relevant drawings or Mock up
S.No Description Detail Remarks
1 Are the Safety norms being covered as per HSEM Process? Yes No
2 Check for availability of material and tools as per procedure /method statement. Yes No
Observations:-
Remarks:
Waterproofing work done is found Satisfactory/Non-Satisfactory ( Put )
Check for availability of material and tools as per procedure /method statement.
8 Yes No
Observations:-
check Mixing of Acralic polymer base chemical and cement with 1:1 proportions
2 need uniform mix by mechanical stirrer as per manufacturer guidelines before Yes No
ready to use on substrate
check application of 1 st coat of Acralic polymer base chemical on substrate as
3 Yes No
per manufacturer guidelines
Check application of 2 nd coat or subsequent coat after 4hrs perpendicular in the
4 Yes No
direction of 1st coat
Check chemical application upto 300 mm height or as per site engg instruction on
5 Yes No
parapet wall
Observations:-
Remarks:
Waterproofing work done is found Satisfactory/Non-Satisfactory ( Put )
Check drain out of water and Bull marks/Ridge as per slope shown in drawing Yes No
2
Remarks:
Waterproofing work done is found Satisfactory/Non-Satisfactory ( Put )
2 Check drain out of water and Bull marks/Ridge as per slope shown in drawing Yes No
Remarks:
Waterproofing work done is found Satisfactory/Non-Satisfactory ( Put )
Observations:-
2 Check drain out of water and bull marks as per slope shown in drawing Yes No
Trowelled and broomed finish towards drain outlet to receive further activity Yes No
3
Observations:-
Ceilling is throughly brushed and washed with water spray and wire brush to Yes No
5
remove patching tape/ dust
Check Mix contents for Bond IT/ Neurobond or equivalent(for ceiling) Yes No
6
before use
Apply with brush or roller on rcc surface of ceiling only(RCC surface should Yes No
7
be in SSD condition)
Apply Gypsum plaster after 24 hours or after the material (Bond IT) has Yes No
8
dried based on environmental condition
Check for the Level pads,Fibre/pvc or equilent mesh for fixed on RCC and Yes No
9
Brick wall junction
Check Rough plastering in wall ,thickness exceeds 15 mm and on ceilling if Yes No
10 thickness exceeds 10mm
Observations:-
B During Plastering
1 Check for proper mixing of Gypsum plaster Yes No
Check mixed material should be consumed within pot life or as per Yes No
2
manufacturers guidelines
3 Check for true line,level , right angle, plumb, edge, sharp corners Yes No
Check termination of plaster at centre of jamb (connet to external) & for Yes No
6
skirting cutting of 200 mm or as per site engineer instructions
Observations:-
C After Plastering
1 Check for finished surface of plaster Yes No
Check for completion of preceding activities like fixing of doors, electrical, Yes No
4
plumbing, firefighting, HVAC, etc.
5 Check for fixing of Level Pads-(horizontal & vertical surface) Yes No
6 Check for grouting around the electrical conduite pipe at midlanding Yes No
8 Check for size, alignment & level of panels. Is it as per requirement ? Yes No
Observations:-
B During Tiling
1 Mortar mix proportion
2 Check for thickness of mortar bed as per the drawings? Yes No
3 Check for following during laying of Tiles:- Yes No
a Fixing over mortar bed with Cement Slurry Yes No
b Pattern of laying Yes No
c Thickness of joints between Tiles (mm) Yes No
d Slope Yes No
e True level surface (write level) Yes No
f Matching of tile joints Yes No
C After Tiling
1 Check for cleaning of tile joints Yes No
4 Check for fixing of Level Pads-(horizontal surface & vertical surface if any) Yes No
Yes
5 Check for size, alignment & level of panels. Is it as per requirement ? Yes No
Observations:-
d Slope Yes No
Observations:-
4 Check for fixing of Level Pads-(horizontal surface & vertical surface if any) Yes No
Yes
5 Check for size, alignment & level of panels. Is it as per requirement ? Yes No
Observations:-
d Slope Yes No
A Prior to Fixing
1 Is the preceding work completed like internal and external plaster Yes No
Proper housekeeping and cleaning all loose materials and dead concrete or Yes No
4
mortar .
Observations:-
During Fixing
1 Cement Sand mortar ratio as per approved method statement/ Specification
2 Ensure the surface washed and cleaned before laying Yes No
4 Check the fixed granite as per line ,level and drawing Yes No
Ensure Granite edges shall be finished to full rounded edge (bull nosing) as Yes No
5
specified
Observations:-
After Fixing
Observations:-
B During Fixing
1 Check painting of MS brackets as specified Yes No
2 Yes No
Ensure Fixing of MS brackets as specified no's and size with anchor fasteners.
3 Check the fixed MS brackets as per true line ,level and drawing Yes No
4 Ensure fixing of Kadappa stone for supporting as specified (If any) Yes No
5 Check the true line, level of kadappa as per drawing and as specified Yes No
Yes No
6 check the openings to be made in the Granite counter to fix sink/wash basin
Observations:-
After Fixing
1 Check the fixed Granite as per drawing ,true line and level etc. Yes No
Ensure Granite edges shall be finished to full rounded edge (bull nosing) as No
2 Yes
specified
3 Ensure gap around the sink/wash basin to be filled as specified Yes No
Observations:-
Yes
B During Dry Cladding work
Check for fastening of Granite to the wall or RCC work, is it Yes No
1
acceptable?.
2 Are the aluminum clamps fixed to stone before start of cladding? Yes No
Check if the line & level of the cladding matching with the ACP Yes No
3
cladding work/ Existing Groove if any?
4 Is the plumb of surface checked & found ok?. Yes No
2 Has the Joints of stone been filled with same color grout? Yes No
Check for cleaning of loose materials, dirt, dust, patch holes if any removed Yes No
11
on plastering surfaces
Opening of major cracks in V shape & filling the same with specified filler Yes No
12
material wherever required
Ensure damaged edges and any plastering work completed prior to Yes No
13
fascade activity
Observations:-
Observations:-
3 Smooth and noise free movement of Openings and locking operation Yes No
Is the Gap between frame and masonry or joints in Glass & ACP Board Yes No
4
filled with approved weather silicon sealant?
5 Cleaning of Glass & Board found satisfactory Yes No
A Prior to Installation
Check for completion of preceding activities like,Plastering of works
Yes No
1 Electrical installation ,HVAC, sprinklers, fixing of service conduits, water
supply and sanitation lines etc.
2 Check for availbility of approved materials & mock up whereever required Yes No
Check for cleaning of RCC Surfaces (I.e.removal of nails, shuttering tape, Yes No
5
laitance, honeycomb, tie rod hole filling etc)
Observations:-
7 Check for screws spacing as per shop drawing and requirement at 230mm Yes No
Check for provision of fixing of A/C grills,electrical fittings, fire sprinklers, Yes No
9
smoke detector & any trap doors
10 Check for matching of joints & closure of gaps Yes No
Is the fibre mesh fixed (Min. 2" width)on joint and fixed with gypsum/putty Yes No
12
Observations:-
Contractor Client
SHAPOORJI PALLONJI REAL ESTATE
SPRE/QA-QC/CH-033 Checklist For POP Cornice works
Site Work Activity
CHECKLIST FOR POP CORNICE WORKS
Site Date
Location Drawing No.
Refer to the approved work method statement, relevant drawings and Mock up
S.No. Description Details
1 Are the Safety norms being covered as per HSEM Process . Yes No
3 Check fire pipe work and sprinkler are in line as per drawing . Yes No
Observations:-
Check POP cornice framing fixing height and level as per drawing/approved Yes No
2
samples.
3 Check outer channel fixing with screws Yes No
Check for provision of fixing of electrical fittings, fire sprinklers, smoke detector
7 Yes No
.
8 Check for matching of joints & closure of gaps Yes No
10 Is the fibre mesh fixed (Min. 2" width)on joint and fixed with gypsum/putty Yes No
Observations:-
5 Check the finishing around the sprinklers and light points Yes No
A Prior to Execution
1 Are the reference drawing/ design pattern available at site? Yes No
Have the proper electrical connections/working platform available for on-site Yes No
3
fabrication?
4 Is the all preceding activities are completed? Yes No
Observations:-
B During Execution
Has the MS grill checked for dimensions & design pattern as per drawing? Yes No
1
Has the MS grill checked for verticality, alignment & rightangle at corners? Yes No
2
5 Are the hold fast provided for sufficient length & number for anchorage? Yes No
Have the uniform gap maintained between the grill & structure on either Yes No
6
side?
Check whether anchor bolt used when structural member comes in Yes No
7
contact?
Is the applied 1 st coat of approved synthetic enamel paint uniformly over Yes
9 NO
the surface
Is the applied 2 nd coat of approved synthetic enamel paint uniformly over Yes No
10
the surface after drying of 1 st coat
Observations:-
C After fixing
1 Has the MS grill welded at both the sides properly? Yes No
Have the metal paste been applied at all welding joints & been grinded
2 Yes No
properly for smooth surface?
Check whether grill is covered by polythene sheet to avoid dead mortar Yes No
3
spillage over that?
Yes No
4 Has the vertical allignment and plumb checked for the fixed grill?
Type of Door
Defects such as bend, twist, scratches etc observed if any & is it Yes No
5
acceptable?
6 Check the verticality of the member Yes No
9 Is the plastered opening to the required size in plumb & right angle? Yes No
10 Is the all preceding activity completed?(Putty, Paint, any touchup etc) Yes No
11 Check for right angle and diagnol alignment of the door frames Yes No
Observations:-
Observations:-
6 Check the specify fixtures being used and fixed as per specification Yes No
Observations:-
A During fabrication
1 Check railing width,Height &size as per approved drawing Yes No
Is the applied 1 st coat of approved synthetic enamel paint uniformly over Yes
6 NO
the surface
Is the applied 2 nd coat of approved synthetic enamel paint uniformly over Yes No
7
the surface after drying of 1 st coat
8 Check dimensions of rail as per drawing Yes No
Observations:-
C After fixing
1 Check railing fixed as per drawing Yes No
2 Are the Safety norms being covered as per HSEM Process? Yes No
Check for RCC rectifications like Honeycomb,tie rod hole, scaffolding hole Yes No
2
is rectified
Check for cleaning of loose materials, dirt, dust, dead mortar on plastering & Yes No
3
RCC surfaces
4 Check proper packing and finishing of sleeves Yes No
Opening of major cracks in V shape & filling the same with specified filler Yes No
5
material wherever required
If floor tiling completed ,ensure proper protection on tiles(rubber Yes No
6
sheet,tarpaulin etc.)
7 Check for availability of materials required for respective type of painting Yes No
Ensure damaged edges and any plastering work completed prior to white Yes No
8
wash application
Observations:-
B During Painting
1 Check for proper mixing of white wash painting Yes No
2 Ensure paint shade and make as per approved or specified or mock up Yes No
Observations:-
C After Painting
1 Check for finished surface of painting Yes No
Signature:Execution/MEP/QA-Qc Signature:Execution/MEP/QA-QC
Contractor Client
SHAPOORJI PALLONJI REAL ESTATE
SPRE/QA-QC/CH-038 Checklist For Painting works
Site Work Activity
Check for cleaning of loose materials, dirt, dust, patch holes if any removed Yes No
2
on plastering surfaces
Yes
3 Check for availability of materials required for respective type of painting Yes No
Opening of major cracks in V shape & filling the same with specified filler Yes No
4
material wherever required
Are all the floor area, door & windows, fittings, grills &glasses,electrical Yes No
5
switch boxes etc been covered properly?
6 Check surface of cement plaster smoothened Yes No
Ensure damaged edges and plastering work completed prior to texture Yes No
7
application or paint application as per specification
Observations:-
B During Texture/Primer
1 Is the mixing of paint done electronically(not mixed at site)? Yes No
3 Apply texture paint of bubble type or any other as per specifications/BOQ Yes No
Observations:-
C After Texture/Primer
1 Is the Textured/ Primerd surface finishing satisfactory? Yes No
Type of painting
Refer to the approved WMS and relevant drawings (or mock up)
Are all the floor area, door & windows, fittings, grills &glasses,electrical Yes No
4
switch boxes etc been covered properly?
Observations:-
B During Painting
1 Check application of 1 st coat of Acylic/ Apex External emulsion paint Yes No
C After Painting
1 Check for finished surface of painting as per approved Yes No
2 Are the Safety norms being covered as per HSEM Process? Yes No
Opening of major cracks in V shape & filling the same with specified filler Yes No
4
material wherever required
Are all the floor area, door & windows, fittings, grills &glasses,electrical Yes No
5
switch boxes etc been covered properly?
6 Check surface of Gypsum/Neeru plaster smoothened Yes No
Check if any corners and edges damaged and same rectified prior to Yes No
7
painting
8 Check surface sanded properly with sand paper or sanding machine Yes No
Observations:-
2 Is the sanding of surface done properally to render the smooth surface? Yes No
3 Is the dust from the surface wiped throughlly after sanding ? Yes No
2 Are the Safety norms being covered as per HSEM Process? Yes No
Check for availability of materials and color shade required for respective Yes
2 No
type of painting
3 Is the all undulations covered by Putty? Yes No
4 Is the sanding of surface done properally to render the smooth surface? Yes No
5 Is the dust from the surface wiped throughlly after sanding ? Yes No
Are all the floor area, door & windows, fittings, grills &glasses,electrical Yes No
7
switch boxes etc been covered properly?
Observations:-
B During Painting
1 Is the mixing of paint done electronically(not mixed at site)? Yes No
C After Painting
1 Check for finished surface of painting as per approved or mock up Yes No
Check for the stability and rigidity of Formwork / MS Channel and it should be fix one Yes No
4
day prior
5 Check for alignment,level,sealing of joints. Yes No
7 Check for provision of embedments or service conduits etc, prior to concreting Yes No
5 Start early curing by sprinkling for concrete after initial setting of it Yes No
Observations:-
2 Is the guiding channels placed according to the vibrator plate length? Yes No
2 If the area is too large,has it been divided accordingly,to do concreting alternatively? Yes No
4 Has the concreting been done evenly and levelled with vibrating machine? Yes No
5 Has the sucking mat spread evenly to facilitate maximum withdrawal of water? Yes No
9 Is the top surface finished by Broom as per the instructions of site engineer? Yes No
10 Start early curing by sprinkling for concrete after initial setting of it Yes No
Observations:-
Have the guiding channels removed carefully without damaging edges of concrete Yes No
2
after 24 hours??
3 Check groove cutting starts immediate after 7 day's curing Yes No
6 Is the plastered opening to the required size in plumb & right angle? Yes No
7 Is the all preceding activity completed?(Putty, Paint, any touchup etc) Yes No
8 Check for right angle and diagnol alignment of the door frames Yes No
Observations:-
Contractor Signature : Client Signature:
Execution/MEP/QA-QC Execution/MEP/QA-QC
Is the uniform gap maintained (not more than 10mm) all-around the frame Yes No
4
to fill with silicon or foam in later?
Is verticality & inner measurement been checked immediate after Yes No
5
fastening of door frames?
6 Check for fastening of window frames/sub frame to walls by screws. Yes No
Observations:-
Contractor Signature : Client Signature:
Execution/MEP/QA-QC Execution/MEP/QA-QC
1 Check for the provision and proper functioning of the following: Yes No
a Handles
b Hinges
c Bolts
d Peg stays
e Lock
3 Check if there is no gap between window shutter & window frame? Yes No
5 Is the door shutter and frame protected properly after erection ? Yes No
A Prior to Laying
1 Is the Approved drawing available? Yes No
Other supplementary materials like sand and cement of Approved Quality Yes No
3
are available
4 Final Approved drawings (GFC) is available at site Yes No
Level/slope and patterns lay out completed as per drawings and with Yes No
5
adjacent pattern
6 MEP clearance is obtained before bedding. Yes No
9 Is the area cleaned for loose mortar /debris/woods and other organic matter Yes No
Observations:-
Have the paver been laid as direct contact with the edge of adjacent paver Yes No
3
(as per drawing pattern)
4 Is the slope at paver top is being maintained as per the requirement? Yes No
5 Gaps are as per pattern and drawing requirements/or as per locking profile. Yes No
Check weather the outer edge of the paver is packed with cement mortar Yes No
7
rigidity?
Observations:-
1 Are the Safety norms being covered as per HSEM Process? Yes No
A Prior To WBM
Leveling and rolling of sub-grade as per design using a vibratory compactor
1 Yes No
or roller as per specification.
Are the lay out plan,grade & subgrade sections cross checked with Yes No
3
drawings before spreading of aggregates?
R.L of the covers of inspection chambers and manholes are checked and Yes No
4
found as per the required level.
Are the undulations/irregularities been rectified before aggregates Yes No
5
spreading?
Has the compaction test reports maintained and it is satisfactory? (OMC No
6 Yes
and MDD)
7 Has the subgrade been prepared as per the given camber? Yes No
All materials used for road work received on site is checked and is found
8 Yes No
to be as per the given specifications.
Observations:-
B During WBM
1 Has the aggregates been spreaded for uniform thichness in first layer? Yes No
Screenings & binding materials are spreaded evenly as per the Yes No
3
specifications?
4 Initial level of WBM taken and recorded Yes No
Observations:-
C After WBM
The chamber covers ( if any ) are cleaned checked if they can be easily Yes No
4
opened.
5 Visible voids on finished surface? Yes No
Inspection chamber / manhole cover level checked with respect to the final Yes No
4 level of road and found in order.
R.L of the covers of inspection chambers and manholes are checked and Yes No
5
found as per the required level.
Observations:-
Yes No
5 Mix is homogenous and aggregates are coated uniformly
Rolling & compaction of surface is proper (3 wheel- power roller of minimum Yes No
6
8 -10 tonne load or an equivalent vibratory roller used.)
Rolling operation completed before temperature of mix falls below 100 Yes No
7
deg.C
Observations:-
C After WBM
1 Thickness and camber, super elevation properly adjusted and recorded Yes No
3 Length & width of the road checked and found in order as per the drawings. Yes No
The chamber covers are properly cleaned after completion of the asphalting Yes No
4
work and checked whether the covers can be easily opened.
5 Visible voids on finished surface? Yes No
Check for cleaning of loose materials, dirt, dust, patch holes if any Yes No
6
removed on plastering surfaces
7 Check the FFL marking as per the drawing Yes No
9 Check the surface drainage downtake and path way crossings are cleared Yes No
Observations:-
2 check all the corners and edges to be properly covered with cut piece Yes No
3 Is the geotextile membrane laid over the drain cell as per specification? Yes No
Check the overlapping(Horizontally & Vertically) and pasting as per the Yes
4 No
BOQ?
5 Check laying of irrigation pipe line as per drawing? Yes No
Is the crossing lines in hardscape are completed as per drawing? (like Yes No
6
drainage, electrical)
Check the thickness of washed fine river sand as per the Yes No
7
BOQ/Specification
8 Is the proportion of soil media and manure as per specification/BOQ? Yes No
Observations:-
2 Is the C/C spacing between tree and shrubs as per specification? Yes No
4 Is the rolling done over the lawn slabs as per the standard requirement? Yes No
Is the tile marking done over the wall(referene to be taken form the Yes No
4
bull/button mark)?
Are the right laying tools & sufficient quantity of tiles of same batch Yes No
available at site?
5 Check for fixing of Level Pads Yes No
Are the approved samples of tiles & pattern of laying available for Yes No
6
reference?
7 Check whether application is by mortar or adhesive Yes No
8 Check whether tiles been soaked in water prior to use? Yes No
Observations:-
B During Tiling
Is the mortar been mixed on MS sheets as per the specified mix proportion Yes No
with the help of measurement box ?
Is the defective/shipped/edge damaged tiles been removed during laying? Yes No
Have the precautions been taken for proper cutting & laying of tiles around Yes No
the plumbing & electricalpoints?
Is the Cement Paste spread uniformly on tile during fixing? Yes No
Has wall plastering been done in level incase of using tile adhesive? Yes No
4 Are the reinforcement free from oil, rust, soil & grease etc? Yes No
Observations:-
B During Reinforcement
Is the lapping length ensured as per the structural consultant instructions? Yes No
1
Check if all the reinforcement of the column are cut according to the Yes No
2
drawing?
Column reinforcement supported adequately till the erection of Yes No
3
formwork.
The stirrups of the column are arranged such that the ring closure of Yes
4 No
alternate ring is on same side.
Observations:-
C After Reinforcement
Check if adequate anchorage lengths are provided at the bottom of the Yes No
1
column reinforcement
Is the lapping ensured in the staggered manner at the specified location as Yes No
2
per approved drwaings?
Are the dowels left in sufficient development length at appropriate Yes No
3
locations?
4 Check if the cover blocks are of correct sizes & placed at correct spacings Yes No
7 Check the spacing between stirrups, C bars is as per the drawing? Yes No
Check if U rod placed of required size & interval to maintain the gap in Yes No
8
RCC wall work?
9 Has the electrical conduiting work completed as per the drawing if any? Yes No