Gottera site construction of main &pedestrian access road project
INDEX
Appendices
a. Organization Chart
b. Proposed Overall Program
3
Gottera site construction of main &pedestrian access road project
The project locate at around gottera interchange area. The project Contract
amount is ETB 22,895,191.64 including VAT & 10% contingency.
The work consist construction of 2.475 km of asphalt road including earth works, sub-
base, base, drainage and sidewalks. The following major construction activities will be
carried out:
1. Equipment:
As the project is located in the vicinity of the contractor’s existing camp sites, quarry
sites, crusher plants, asphalt plant and etc…, mobilization of resource can be easily
made from the central office following the scheduled commencement date of individual
activities whenever necessary. All equipment shall be kept in a good working condition
and carefully serviced before use in the central garage at Kality. The contractor will also
use its central laboratory at Kality and some instrument for routine site inspection
purposes shall be arranged on site for common use of the Engineer and the contractor.
2. Personnel
The key project management staffs including the project manager would be assigned
4
Gottera site construction of main &pedestrian access road project
within the mobilization period. All other site staff and manpower associated with the
central and common use plant and equipment are still on duty. All remaining technical
staff and skilled workers to be assigned for the project specifically shall be increased
Appropriate and well organized site structure shall be organized under the project
manager’s office. The following sections will be organized and carry out their duty under
Personnel and Accounting Section, Material Procurement Section and General Services.
The construction section shall be further subdivided in to different crews as follows: Earth
works Crew, Pavement Crew, minor and major drainage Crews. The detail organization
1. Before the commencement of the major works, The Contractor will assure
the surveying works with sufficient details. This work consists of traverse,
centerline, level points, check-up the cross section of the roadbed, increase
the number of level points, make sure the level points, structures and
them to engineer or the employer. The precision of surveying shall meet the
relevant specifications.
2. Check the traverse along the centerline and proceed with the stake out
survey works in accordance with design drawings. Check and correct the
surveying equipment. If the construction area exceeds the one that the
existing traverse points surround, the points need shifting, and assure good
3. Fix main controlling stakes. Pay attention to the center of the structures
such as culverts and check whether the centerlines of the adjacent sections
properly close while reinstating the centerline. Report the problems to the
5
Gottera site construction of main &pedestrian access road project
4. The hole work will be divided into three part according to the site condition.
These works shall be carried out under close supervision of the Engineer.
Detail stake out survey of level points shall be set jointly with the Engineer
before commencing the major construction. Complete data of all level points
shall be submitted to the engineer for approval.
a. Clearing and grubbing
This work will proceed following the setting out works. The clearance of the surfacing
shall be carried out using appropriate machinery. The depth of clearing shall be
Unsuitable materials shall be disposed off to a designated spoil area. When executing
the clearing works, the gravel materials which could be used afterwards, would be
Demolition of the existing structures shall be carried out upon the approval of the
engineer. The area shall also be properly backfilled and the recycled materials after the
demolition should be piled at a spot directed by the engineer, and kept in good condition.
The spoiled materials should be transported to a spoil area as directed by the engineer .
b. Roadbed excavation
All the road way excavation shall be carried out using bulldozer and excavators. The
The earth fill roadbed shall be leveled by bulldozers at first, fine leveled by the graders
and rolled by the vibratory rollers. Rock filling shall be leveled by high-power bull dozers,
c. Roadbed embankment
I. The degree of compaction and the minimum strength of the fill materials must
II. Since the thickness of this project is very thin, the fill shall be completed by one
layer. When the slope of the fill embankment is bigger than 1:5, make the original
ground into a step with a width of 2m and tamp it with smaller size machinery.
6
Gottera site construction of main &pedestrian access road project
III. According to the fill thickness and the width of the roadbed, calculate the required fill
quantity on every cross section, and level it with graders. Sampling will be taken to
measure the moisture and compare it with the optimum moisture content.
IV. After each layer is placed, Carry out compaction test following the interval as
specified in the standards and continue the second layer following the test results.
surveying team shall also carry out the detail setting out and control of
with the level at the foundation, take into account the geological and
b. The abutment and wing wall shall be constructed following the levels
a. Metallic adjustable scaffolding and form works shall be used for the
b. Concrete shall be mixed from the central mixing plant and transported
7
Gottera site construction of main &pedestrian access road project
4.4 Sub - Base and Base Construction
Sub base and base production shall be carried out and monitored by the central office for
different projects. The Engineer will have unrestricted access to check and control the
1. Prepare the materials for sub-base and make sure the grading and the quality
2. Setting out the surface along the centerline at intervals of 20m, outside the
edges using side stakes and clearly mark the levels on the side stakes.
4. Check the moisture content and spray it again if the moisture is not sufficient.
5. Dump the sub-base material at uniform interval on the finished sub-grade and
spread to the required thickness and make sure that the surface is even and
6. Check the road crown and traverse slope and continue compaction
7. During the rolling process keep the surface wet, and examine the degree of
traffic will be allowed on the roadbed before the completion of the wearing
courses.
1. Check up the grading & moisture content of the crushed stones, to see if they
2. Carry out leveling surveying following the data indicated in the design.
3. Determine the ratio between the layer thickness before and after compaction.
4. Dump and spread the material, right after unloaded from trucks.
5. Compact the material to the required density and check grade elevation.
8
Gottera site construction of main &pedestrian access road project
2. The limits of spray area have to be clearly marked.
3. The surface must be cleaned against any pollutant foreign matter.
4. The penetration asphalt should be 50-90% bitumen and has to be applied
according to the Specification.
5. Spraying of bitumen should not be allowed during time of strong wind and
rain.
9
Gottera site construction of main &pedestrian access road project
to compact I if the area is not accessible for big rollers.
c. Rolling should be done uniformly from lower side to higher side and conform to
the specification requirement.
d. The rollers should be equipped with water Sprinkler so as to avoid sticking of
asphalt on the roller surface.
10
Gottera site construction of main &pedestrian access road project
Setting -out
Replaced by No
suitable Road bed Material Transport to
materials Treatment Treatment the waste
Yes Yes
Sub-grade tests
Getting engineer’s
approval
11
Gottera site construction of main &pedestrian access road project
Approval by the
Engineer Dump and spread sub-base
material on sub-grade
Water to
Level to the grades and lines optimum
moisture
content
Approval by
Engineer
Water to
Level to the grades and lines optimum
moisture
content
13
Gottera site construction of main &pedestrian access road project
Prime Coat
Trail mixing
Approval by Engineer
Compaction
Approval by Engineer
Design Binder &
wearing course
mixing formula
Curing
Open to Traffic
14
Gottera site construction of main &pedestrian access road project
The quality for the concrete mixing shall be controlled by experienced technicians in accordance
with the Specification. The casting and vibrating of the concrete shall be in accordance with the
Specification.
15
Gottera site construction of main &pedestrian access road project
Transporting
Curing
16
Gottera site construction of main &pedestrian access road project
5.1 Strengthen Construction Management
a. The quality management group shall be led by project manager. It consists of the
survey crew, laboratory technicians, construction supervisors and they will jointly
be responsible to carry out internal supervision and quality assurance works.
b. Experienced and well versed Construction personnel shall be assigned.
The contractor will also arrange night works of some activities such as excavation to
waste, dumping of aggregates and other activities all as per the Engineer’s approval.
Adequate number of reflector signs will be provided on sections where construction is
going on.