Re Entry Plan Marking

Mark Anthony M. Floro submitted a re-entry plan to his company with the following activities over the next 3 months: 1) Conduct a site inspection by November 28th to identify hazards and submit accomplishments by November 30th. 2) Hold a toolbox meeting by January 2nd to discuss safety briefings, with accomplishments submitted by January 6th. 3) Request assistance placing safety signage and precautions by January 9th and submit accomplishments by January 14th. 4) Develop an emergency preparedness program including fire, earthquake, and typhoon drills by February 6th and submit accomplishments by February 10th.

Uploaded by

asombrado_jerald
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
270 views

Re Entry Plan Marking

Mark Anthony M. Floro submitted a re-entry plan to his company with the following activities over the next 3 months: 1) Conduct a site inspection by November 28th to identify hazards and submit accomplishments by November 30th. 2) Hold a toolbox meeting by January 2nd to discuss safety briefings, with accomplishments submitted by January 6th. 3) Request assistance placing safety signage and precautions by January 9th and submit accomplishments by January 14th. 4) Develop an emergency preparedness program including fire, earthquake, and typhoon drills by February 6th and submit accomplishments by February 10th.

Uploaded by

asombrado_jerald
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Department of Labor and Employment

Occupational Safety & Health Center

Accreditation Number 1030-042919-101

RE-ENTRY PLAN FORM

NAME Mark Anthony M. Floro DATE November 26, 2022

What do I need to get this


Plan activity in the next 1- When do I submit my
done (consider human and With whom do I will When is the intended
3 months (breakdown into accomplishment to my
financial resources approach for assistance target date
specific steps company
needed)

SITE INSPECTION:  Seek Management Project Manager, Site Engr., Nov. 28, 2022 Nov. 30, 2022
 Conducting an Approval Supervisor, Foreman and
Effective JHA  Propose a schedule Safety officer
 Identify, Evaluate for site Inspection
and Control
Hazards

Conduct Toolbox Meeting:  Seek Management Project Manager Jan. 2, 2023 Jan. 6, 2023
 Prayer before work Approval Site Supervisor
 Exercise  Propose a schedule Safety Officer .
 Safety Briefings for toolbox meeting Foreman and workers

Ask Assistant For Placing:


 Safety Signages  Seek Management
 Warning/ Approval Supervisor, Site Engr, Safety Jan 9, 2023 Jan. 14, 2023
Precautionary  Propose a schedule officer, Foreman and
measure specially Worker
for the Activity
hazardous areas
Department of Labor and Employment
Occupational Safety & Health Center

Accreditation Number 1030-042919-101


Emergency
Preparedness
Program:  Seek Management Project Manager, Site Engr., Feb 6, 2023 Feb. 10, 2023
 Fire Drill Approval Supervisor, Foreman and
 Earthquake Drill Safety officer and Workers
 Proposed a schedule
 Typhoon Drill
for the activity