PSOC Notes EEE PDF
PSOC Notes EEE PDF
This document is confidential and intended solely for the educational purpose of
RMK Group of Educational Institutions. If you have received this document
through email in error, please notify the system manager. This document
contains proprietary information and is intended only to the respective group /
learning community as intended. If you are not the addressee you should not
disseminate, distribute or copy through e-mail. Please notify the sender
immediately by e-mail if you have received this document by mistake and delete
this document from your system. If you are not the intended recipient you are
notified that disclosing, copying, distributing or taking any action in reliance on
the contents of this information is strictly prohibited.
POWER SYSTEM OPERATION AND CONTROL
Department: EEE
2 Course objectives 6
3 Pre Requisites 7
4 Syllabus 8
5 Course outcomes 9
6 CO-PO/PSO Mapping 13
7 Lecture Plan 14
8 Activity based learning 16
9 Lecture Notes 17
10 Assignments 66
11 Part A Q & A 67
16 Assessment Schedule 77
SCADA and its application for real time operation and control of power systems
Prerequisites
CO2 Ability to analyse the control actions to be implemented on the system to meet
the minute-to-minute variation of system demand.
CO3 Ability to understand the significance of power system operation and control.
CO6 Ability to design SCADA and its application for real time operation.
PROGRAMME OUTCOMES
c. Come out with solutions for the complex problems and to design system
components or process that fulfill the particular needs taking into account public
health and safety and the social, cultural and environmental issues.
e. Form, select and apply relevant techniques, resources and Engineering and IT
tools for Engineering activities like electronic prototyping, modeling and control
of systems and also being conscious of the limitations.
10
PROGRAMME OUTCOMES
l. Recognize the need for self and life-long learning, keeping pace with
technological challenges in the broadest sense.
11
PROGRAM SPECIFIC OUTCOMES
PSO 1 Analyze, design and implement control, instrumentation and power systems for
satisfying industry needs.
PSO 2 Use modern tools and appropriate solutions for the real time problems for promoting
energy conservation and sustainability.
12
CO-PO /PSO mapping
CO/ a b c d e f g h i j k l PS PS PS
PO, O O O
PSO 1 2 3
co1 - 2 - 3 3 - - - - - - - 3 - 3
co2 - 2 - 3 3 - - - - - - - 3 - 3
co3 - 2 - 3 3 - - - - - - - 3 - 3
co4 - 2 - 3 3 - - - - - - - 3 - 3
co5 - 2 - 3 3 - - - - - - - 3 - 3
co6 - 2 - 3 3 - - - - - - - 3 - 3
Lecture plan Unit I
Sl Topic No Prop Actu Pertaining Taxon Mod
No of ose al dt CO omy e of
Peri d dt level deliv
ods ery
1 Power scenario in CO1, CO2 K2 PPT
Indian grid – National
and Regional load
dispatching centers –
requirements of good
power system
2 Necessity of voltage CO1, CO2 K2 PPT
and frequency
regulation - real power
vs frequency and
reactive power vs
voltage control loops
3 System load variation CO1, CO2 K2 PPT
Load Curve: EEE Block daily load curve Ground floor, I floor, II floor
Lecture notes
Sector MW % of Total
Central Sector 93,477 25.2
State Sector 1,03,322 27.9
1,73,549 46.9
Total 3,70,348
Fuel MW % of Total
Total Thermal 2,30,600 62.8
Coal 1,98,525 54.2
Lignite 6,610 1.7
Gas 24,955 6.7
Diesel 510 0.1
Hydro(Renewable) 45,699 12.4
Nuclear 6,780 1.9
RES (MNRE) 87,269 23.6
Total 3,70,348
It was earlier a wholly owned subsidiary of Power Grid Corporation of India Limited
(PGCIL). It was formed in March 2009 to handle the power management functions
of PGCIL.
National Load Despatch Centre (NLDC) has been constituted as per Ministry of
Power (MOP) notification, New Delhi dated 2 March 2005 and is the apex body to
ensure integrated operation of the national power system.
Function: for optimum scheduling and despatch of electricity among the Regional
Load Despatch Centres.
-To exercise supervision and control over the inter-state transmission system
-To keep accounts of quantity of electricity transmitted through the regional grid.
-To carry out real time operations of grid control and dispatch of electricity within the
region in accordance with the Grid Standards and Grid Code.
Regional Load Dispatch Centers Rids
The five RLDCs in India are owned, operated and maintained by Power Grid
Corporation of India Limited (POWERGRID) which is the Central Transmission Utility
(CTU) of the country
Northern grid: Delhi, Haryana, Himachal Pradesh, Jammu and Kashmir, Punjab,
Rajasthan, Uttar Pradesh, Uttarakhand 99376.93MW
iii) The States are inter connected with each other through 765/400/220 kV network.
Southern Region is connected to Western region through HVDC Back-to-back (2x500
MW) link at Bhadrawathi in WR and to Eastern regions through HVDC back-to-back
link (2x500 MW) at Gazuwaka in SR and ±500 kV Bipolar HVDC link (2x1000 MW)
from Talcher in ER to Kolar in SR as well as 765 kV 2 x Single Circuit Sholapur-
Raichur Interconnector to facilitate exchange of power from surplus to deficit region
/ State as well as wheeling of power.
iv) For the year 2015 – 16 had seen Southern Region in meeting a maximum
demand of 40899 MW and average daily energy consumption of 780 MUs which are
7.3% and 4.7% respectively higher than the previous year. There was about 6800
MW generation addition during the year. During the year 2015-16 the Southern
Region has witnessed a maximum consumption of energy of 929.57 MUs on 22nd
March'16 (4.13% rise compared to 2014-15) and the maximum peak demand of
40899 MW on 21st March'16 (7.3% rise compared to 2014-15) as against the
respective maximum values 892.70 MU and 38090 MW met last year.
v) Southern Region has met a maximum demand of 41,607 MW on 7th April 2016
Tamil Nadu State Load Despatch Centre (SLDC)
Functions of SLDCs
Grid Operation in TN started by November 1964.The first Load Despatch Centre was
operated from Erode.
Subquently, the main Load Despatch Centre was formed in 1986 at Chennai and
Sub Load Despatch Centre at Madurai.
In accordance with section 32 of Electricity Act, 2003 roles and functions of SLDCs
are as under :
The SLDCs shall be the Apex Body to ensure integrated operation of the Power
system in a State.
SLDCs shall :Be responsible for optimum scheduling and dispatch of electricity within
a state in accordance with the contracts entered into with the licensees or the
generation companies operating in that State.
Monitor grid operation
Keep accounts of the quantity of electricity transmitted through State Grid.
Exercise supervision and control over the inter-state transmission system.
Be responsible for carrying out real time operation for grid control and dispatch of
electricity within the State through secure and economic operation of the State Grid
in accordance with the grid standards and state grid code
Requirements Of Good Power System
In general, each generation plant in any power may have more than one generating
units. Each of the unit may have identical or different capacities. A number of power
plants can be tied together to supply the system load by means of interconnection
of the generating stations.
Interconnected electric power system is more reliable and convenient to operate and
also offers economical operating cost.
The function of an electric power system is to convert energy from one of the
naturally available forms to electrical from and to transport it to points of
consumption.
A properly designed and operated power system should meet the following
fundamental requirement.
1. Adequate spinning reserve must be present to meet the active and reactive
power demand.
3. The power quality must have certain minimum standards within the tolerance or
limit such as,
Constancy of frequency:
Level of reliability.
Constant frequency
Constant frequency is to be maintained for the following functions:
All the AC motors should require constant frequency supply so as to maintain speed
constant.
In continuous process industry, it affects the operation of the process itself.
For synchronous operation of various units in the power system network, it is
necessary to maintain frequency constant.
Frequency affects the amount of power transmitted through interconnecting lines.
Frequency fluctuations are harmful to electrical appliances.
Speed of three phase ac motors proportional to the frequency.
(N=120f/p)
The blades of turbines are designed to operate at a particular speed. Frequency
variation leads to speed variation and results in mechanical vibration
Constant voltage
Over voltage and under voltage
Electric motors will tend to run on over speed when they are fed with higher
voltages resulting vibration and mechanical damage.
Over voltage may cause insulation failure.
For a specified power rating, lower voltage results in more current and this results in
heating problems. (P=VI)
Kinetic energy= 1/ 2 J w 2
P–f control
The Load Frequency Control (LFC), also known as generation control or P–f control,
deals with the control of loading of the generating units for the system at normal
frequency. The load in a power system is never constant and the system frequency
remains at its nominal value only when there is a match between the active power
generation and the active power demand. During the period of load change, the
deviation from the nominal frequency, which may be called frequency error (Δf), is
an index of mismatch and can be used to send the appropriate command to change
the generation by adjusting the LFC system. It is basically controlling the opening of
the inlet valves of the prime movers according to the loading condition of the
system. In the case of a multi-area system, the LFC system also maintains the
specified power interchanges between the participating areas. In a smaller system,
this control is done manually, but in large systems automatic control devices are
used in the loop of the LFC system
Q–V Control
In this control, the terminal voltage of the generator is sensed and converted into
proportionate DC signal and then compared to DC reference voltage. The error in
between a DC signal and a DC reference voltage, i.e., Δ |V | is taken as an input to
the Q–V controller. A control output ΔQ is applied to the exciter
Generator Controllers (p–f and Q–V Controllers)
The active power P is mainly dependent on the internal angle δ and is independent of the
bus voltage magnitude |V|. The bus voltage is dependent on machine excitation and hence
on reactive power Q and is independent of the machine angle δ. Change in the machine
angle δ is caused by a momentary change in the generator speed and hence the frequency.
Therefore, the load frequency and excitation voltage controls are non-interactive for small
changes and can be modeled and analyzed independently. Figure gives the schematic
diagram of load frequency (P–f) and excitation voltage (Q–V) regulators of a turbo-
generator. The objective of the MW frequency or the P–f control mechanism is to exert
control of frequency and simultaneously exchange of the realpower flows via
interconnecting lines. In this control, a frequency sensor senses the change in frequency
and gives the signal Δf . The P–f controller senses the change in frequency signal (Δ f) and
the increments in tie-line real powers (ΔP ), which will indirectly provide information about
the incremental state error (Δδ ). These sensor signals (Δf and ΔP ) are amplified, mixed,
and transformed into a real-power control signal ΔP . The valve control mechanism takes ΔP
as the input signal and provides the output signal, which will change the position of the inlet
valve of the prime mover. As a result, there will be a change in the prime mover output and
hence a change in real-power generation ΔP . This entire P–f control can be yielded by
automatic load frequency control (ALFC) loop.
The objective of the MVAr-voltage or Q–V control mechanism is to exert control of the
voltage state |Vi |. A voltage sensor senses the terminal voltage and converts it into an
equivalent proportionate DC voltage. This proportionate DC voltage is compared with a
reference voltage Viref by means of a comparator. The output obtained from the
comparator is error signal Δ|Vi | given as input to Q–V controller, which transforms it to a
reactive power signal command ΔQci and is fed to a controllable excitation source. This
results in a change in the rotor field current, which in turn modifies the generator terminal
voltage. This entire Q–V control can be yielded by an automatic voltage regulator (AVR)
loop.
Schematic diagram of P–f controller and Q–V controller
System Load
From systems point of view, there are 5 broad category of loads:
1. Domestic
2. Commercial
3. Industrial
4. Agriculture
5. Others - street lights, traction.
Domestic:
Lights,
Fans,
domestic appliances like heaters,
refrigerators, air conditioners,
mixers,
ovens,
small motors etc.
1. Demand factor = 0.7 to 1.0;
2. Diversity factor = 1.2 to 1.3;
3. Load factor = 0.1 to 0.15
Commercial:
Lightings for shops, advertising hoardings, fans, AC etc.
1. Demand factor = 0.9 to 1.0;
2. Diversity factor = 1.1 to 1.2;
3. Load factor = 0.25 to 0.3
Industrial:
Small scale industries: 0-20kW
Medium scale industries: 20-100kW
Large scale industries: above 100kW
System load-continue
Industrial loads need power over a longer period which remains fairly uniform
throughout the day.
For heavy industries:
1. Demand factor = 0.85 to 0.9;
2. Load factor = 0.7 to 0.8
Agriculture:
Supplying water for irrigation using pumps driven by motors
1. Demand factor = 0.9 to 1;
2. Diversity factor = 1.0 to 1.5;
3. Load factor = 0.15 to 0.25
Other Loads:
a) Bulk supplies,
b) street lights,
c) traction,
d) government loads
which have their own peculiar characteristics
System Load Characteristics
a) Connected Load
b) Maximum Demand
c) Average Load
d) Load Factor
e) Diversity Factor
f) Plant Capacity Factor
g) Plant Use Factor
System load- continue
Plant use factor = Station output in kWh / Plant capacity * Hours of use
When the elements of a load curve are arranged in the order of descending
magnitudes.
Economic of Generation
1. Load curves
The curve showing the variation of load on the power station with respect to time
The curve drawn between the variations of load on the power station with reference
to time is known as load curve. Fig shows the load curve
There are three types, Daily load curve, Monthly load curve, Yearly load curve .
Load Curve-continue
Monthly load curve–Load curve obtained from the daily load curve
Yearly load curve-Load curve obtained from the monthly load curve
The curve drawn between the variations of load with reference to various time
period of day is known as daily load curve.
Average value of the power at a month for a different time periods are calculated
and plotted in the graph which is known as monthly load curve.
It is obtained from monthly load curve which is used to find annual load factor.
Load duration curve
The load duration curve gives the data in a more presentable form
The area under the load duration curve is equal to that of the
corresponding load curve
The load duration curve can be extended to include any period of time
Connected load
It is the sum of continuous ratings of all the equipments connected to supply
systems.
Maximum demand
It is the greatest demand of load on the power station during a given period.
Demand factor
It is the ratio of maximum demand to connected load.
Demand factor= (max demand)/ (connected load)
Average demand
The average of loads occurring on the power station in a given period (day or month
or year) is known as average demand
Daily average demand = (no of units generated per day) / (24 hours)
Monthly average demand = (no of units generated in month) / (no of hours in a
month)
Yearly average demand = (no of units generated in a year) / (no of hours in a year)
Load factor
The ratio of average load to the maximum demand during a given period is known
as load factor.
Load factor = (average load)/ (maximum demand)
Diversity factor
The ratio of the sum of individual maximum demand on power station is known
as diversity factor.
Diversity factor = (sum of individual maximum demand ) / (maximum demand).
Capacity factor
This is the ratio of actual energy produced to the maximum possible energy that
could have been produced during a given period.
Capacity factor = (actual energy produced) / (maximum energy that have been
produced)
It is the ratio of units generated to the product of plant capacity and the number
of hours for which the plant was in operation.
= 8,760 hours
Load (M W) 40 50 60 50 70 40
Draw the load curve and find (i) maximum demand (ii) units generated per day (iii)
average load and (iv) load factor.
Solution.
Daily curve is drawn by taking the load along Y -axis and time along X-axis. For the
given load cycle, the load curve is shown in Fig.
(i) It is clear from the load curve that maximum demand on the power station is 70
MW and occurs during the period 16— 20 hours. Maximum demand = 70 MW
(ii) Units generated per day = Area (in kWh) under the load curve
= 103 [40 × 6 + 50 × 4 + 60 × 2 + 50 × 4 + 70 × 4 + 40 × 4]
= 12 × 105 kWh
Electrical energy cannot be stored. It has to be generated whenever there is a demand for
it. It is, therefore, imperative for the electric power utilities that the load on 3 6 their
systems should be estimated in advance. This estimation of load in advance is commonly
known as load forecasting. It is necessary for power system planning. Power system
expansion planning starts with a forecast of anticipated future load requirements. The
estimation of both demand and energy requirements is crucial to an effective system
planning. Demand predictions are used for determining the generation capacity,
transmission, and distribution system additions, etc. Load forecasts are also used to
establish procurement policies for construction capital energy forecasts, which are needed to
determine future fuel requirements. Thus, a good forecast, reflecting the present and future
trends, is the key to all planning
(i) For Proper Planning of Power System To determine the potential need for additional new
generating facilities; To determine the location of units; To determine the size of plants; To
determine the year in which they are required; To determine that they should provide
primary peaking capacity or energy or both; To determine whether they should be
constructed and owned by the Central Government or State Government or Electricity
Boards or by some other autonomous corporations.
Load Forecasting
(ii) For Proper Planning of Transmission and Distribution Facilities For planning the
transmission and distribution facilities, the load forecasting is needed so that the
right amount of power is available at the right place and at the right time. Wastage
due to misplanning like purchase of equipment, which is not immediately required,
can be avoided.
(iii) For Proper Power System Operation Load forecast based on correct values of
demand and diversity factor will prevent overdesigning of conductor size, etc. as well
as overloading of distribution transformers and feeders. Thus, they help to correct
voltage, power factor, etc. and to reduce the losses in the distribution system.
(iv) For Proper Financing The load forecasts help the Boards to estimate the future
expenditure, earnings, and returns and to schedule its financing program
accordingly.
(v) For Proper Manpower Development Accurate load forecasting annually reviewed
will come to the aid of the Boards in their personnel and technical manpower
planning on a long-term basis. Such a realistic forecast will reduce unnecessary
expenditure and put the Boards’ finances on a sound and profitable footing.
(vi) For Proper Grid Formation Interconnections between various state grids are now
becoming more and more common and the aim is to have fully interconnected
regional grids and ultimately even a super grid for the whole country. These
expensive high-voltage interconnections must be based on reliable load data,
otherwise the generators connected to the grid may frequently fall out of step
causing power to be shut down.
(vii) For Proper Electrical Sales In countries, where spinning reserves are more,
proper planning and the execution of electrical sales program are aided by proper
load forecasting.
Classification of load forecasting
The load forecasting can be classified as: (i) demand forecast and (ii) energy
forecast.
Energy Forecast :This is used to determine the type of facilities required, i.e., future
fuel requirements
Loading of units are allocated to serve the objective of minimum fuel cost is known
as load scheduling. Load scheduling problem can be divided into:
i. Thermal scheduling.
i. Thermal scheduling.
The loading of steam units are allocated to serve the objective of minimum fuel cost.
Thermal scheduling will be assumed that the supply undertaking has got only form
thermal or from steam stations.
Loading of hydro and thermal units are allocated to serve the objective of minimum
fuel cost is known as hydrothermal scheduling.
During rainy season, we can utilize hydro generation to a maximum and the
remaining period, hydro generation depends on stored water availability. If
availability of water is not enough to generate power, we must utilize only thermal
power generation. Mostly hydroelectric generation is used to meet out peak loads.
There are two types of hydrothermal scheduling.
Long range hydro scheduling problem involves the long range forecasting of water
availability and the scheduling of reservoir water releases for an interval of time that
depends on the reservoir capacities. Long range hydro scheduling involves
from I week to I year or several years. Long range hydro scheduling involves
optimization of statistical variables such as load, hydraulic inflows and unit
availabilities.
Short range hydro scheduling involves from one day to one week or hour-by-hour
scheduling of all generation on a system to achieve minimum production cost foe a
given period.
Assuming load, hydraulic inflows and unit availabilities are known, for a given
reservoir level, we can allocated generation of power using hydro plants to meet out
the demand, to minimize the production cost.
The speed governor is the main primary tool for the LFC, whether the machine is
used alone to feed a smaller system or whether it is a part of the most elaborate
arrangement. A schematic arrangement of the main features of a speed-governing
system of the kind used on steam turbines to control the output of the generator to
maintain constant frequency is as shown in Fig.1
This is the heart of the system which senses the change in speed (frequency).As the
speed increases the fly balls move outwards and the point B on linkage mechanism
moves downwards. The reverse happens when the speed decreases.
(ii)Hydraulic Amplifier:
It comprises a pilot valve and main piston arrangement. Low power level pilot valve
movement is converted into high power level piston valve movement. This is necessary in
order to open or close the steam valve against high pressure steam.
(iii)Linkage Mechanism:
ABC is a rigid link pivoted at B and CDE is another rigid link pivoted at D. This link
mechanism provides a movement to the control valve in proportion to change in speed. It
also provides a feedback from the steam valve movement.
Basics of Speed Governing Mechanisms and Modelling
(iv)Speed Changer: It provides a steady state power output setting for the
turbine. Its downward movement opens the upper pilot valve so that more steam
is admitted to the turbine under steady conditions (hence more steady power
output). The reverse happens for upward movement of speed changer.
Steam enters into the turbine through a pipe that is partially obstructed by a steam
admission valve. In steady state the opening valve is determined by the position of a
device called the speed changer (upper left corner in Fig.1), fixes the position of the
steam valve through two rigid rods ABC and CDE. The reference value or set point of
the turbine power in steady state is called the reference power
When the load on the bus suddenly changes, the shaft speed is modified, and a device
called speed regulator acts through the rigid rods to move the steam valve. A similar
effect could be produced by temporarily modifying the reference power (which justifies
the name speed changer). In practice, both control schemes are used simultaneously.
Amplifying stages (generally hydraulic) are introduced to magnify the output of the
controller and produced the forces necessary to actually move the steam valve.
In this section, we develop the mathematical model based on small deviations around
a nominal steady state. Let us assume that the steam is operating under steady state
and is delivering power P0G from the generator at nominal speed or frequency fo.
Under this condition, the prime mover valve has a constant setting χ0E, the pilot valve
is closed, and the linkage mechanism is stationary. Now, we will increase the turbine
power by ΔPC with the help of the speed changer. For this, the movement of linkage
point A moves downward by a small distance ΔxA and is given by
Fig.1 Schematic diagram of speed governing mechanism
The link point ‘C’ will move upward because of linkage (A-B-C) action. Let it be
further, the link point ‘D’ moves the piston in pilot servo (V), resulting in higher
pressure oil flow in the upper part of the main piston. The piston moves
downward by an amount ΔXD and the steam valve opening increases. It
increases the torque developed by the turbine. This increased torque increases
the speed of generator, i.e., frequency (Δf). This change of speed results in the
outward movement of fly ball of the speed regulator. Thus the link ‘B’ moves
slightly downward a small distance ΔXB. Due to the movement of link point B,
the link point ‘C’ also moves downward by an amount ΔXC’’ which is also
proportional to Δf. Thus the net movement of link point C is
ΔXC = ΔXC’ + ΔXC’’ ……………. (2)
(lBC)
(-) ΔXC’ = ΔXA ………… (3)
(lAB)
(lBC)
K1 = (lAB)
and ΔXC “ = K2 Δf
lCD + lDE
ΔXD’ = ΔXC ……………… (7)
(lDE)
lCD + lDE
ΔXD’’ = ΔXE
(lCD)
Now, if an assumption is made that the flow of oil into the servo-motor is
proportional to position ΔXD of the pilot valve V, then the movement ΔXE of the
piston can be expressed as
1
ΔXE(s) = K5 ΔXD (s) ………………………. (13)
𝑠
𝐾4 𝐾5 −𝐾5 𝐾3
ΔXE(s) 1 + = −𝐾1 𝐾𝑐 ΔP𝑐 (s) + 𝐾2 Δf(s)
𝑠 𝑠
𝑘2
𝑘5𝑘3𝑘1𝑘𝑐 ΔPC (s) − Δf(s)
ΔXE(s) = 𝑠
𝑘1𝑘𝑐
𝑘4𝑘5 1+
𝑘4𝑘5
𝑘2
𝐾3𝐾1𝐾𝐶 ΔPC (s) − Δf(s)
ΔXE(s) = 𝑘1𝑘𝑐
𝑠
𝐾4 1+
𝑘4𝑘5
𝐾3𝐾1𝐾𝐶 1 1 𝑘2
KG = ; TG = ; = ;
𝐾4 𝐾4𝐾5 𝑅 𝑘1𝑘𝑐
Value of TG < 100 m sec
1 𝐾𝐺
ΔXE(s) = ΔPC s − 𝑅 Δf(s) x ………… (14)
1+𝑆𝑇𝐺
Steam turbine or hydro turbine act as a prime mover driving a generator unit. At
present, we can assume that the voltage level is constant and the torque variations
are small. Then an incremental analysis will give a relatively simple dynamic
relationship between ΔXE and ΔPG. Such an analysis reveals considerable difference,
not only between steam turbines and hydro- turbines, but also between various types
(reheat and non-reheat) of steam turbines. Therefore, the transfer function, relates
the change in the generated power output with respect to the change in the valve
position, varies with the type of the prime mover.
Fig.3 shows a Single-stage Non-reheat type steam turbine. In this model, the
turbine can be characterized by a single gain constant Kt and and a single time
constant Tt and ΔPv is per unit change in valve position from nominal value.
ΔPT(s) 𝐾𝑡
Gt(s) = =
ΔXE(s) 1+𝑆𝑇𝑡
Generator Load Model
𝑑(𝑊𝑘𝑖𝑛)
1. By increasing the kinetic energy Wkin in the rotor generator at the rate 𝑑𝑡
𝜕𝑃𝐷
B= where B is called Damping Coefficient in MW/HZ.
𝜕𝑓
𝑑(𝑊𝑘𝑖𝑛)
ΔPT - ΔPD = + B Δf
𝑑𝑡
𝑓 2
Wkin = W0kin 𝑓0
Δf
Wkin = W0kin 1 + 2 𝑓0
0
𝑑(𝑊𝑘𝑖𝑛) 𝑊𝑘𝑖𝑛 𝑑Δf
=2
𝑑𝑡 𝑓0 𝑑𝑡
𝑊𝑘𝑖𝑛
H= 𝑃𝑟
Change in turbine power= Change in load power + Change in KE + Change in power due
to change in frequency of active load.
𝐻𝑃𝑟 𝑑Δf
ΔPT – ΔPD = 2 + B Δf
𝑓0 𝑑𝑡
Dividing by Pr we get,
𝐻 𝑑Δf
ΔP𝑇𝑝.𝑢 - ΔP𝐷𝑝.𝑢 = 2 + B𝑝.𝑢 Δf
𝑓0 𝑑𝑡
ΔP𝑇𝑝.𝑢 = ΔP𝐺𝑝.𝑢
𝐻𝑠
ΔP𝐺 (𝑠) - ΔP𝐷 (s) = 2 Δf (s) + B Δf(s)
𝑓0
Or it can be written as
𝐻 𝑑Δf
ΔP𝑇𝑝.𝑢 - ΔP𝐷𝑝.𝑢 = 2 + B𝑝.𝑢 Δf
𝑓0 𝑑𝑡
ΔP𝑇𝑝.𝑢 = ΔP𝐺𝑝.𝑢
𝐻𝑠
ΔP𝐺 (𝑠) - ΔP𝐷 (s) = 2 Δf (s) + B Δf(s)
𝑓0
Or it can be written as
Hs
Δf (s) 𝐵 + 2 𝑓 = ΔP𝐺 (𝑠) - ΔP𝐷 (s)
0
𝐾𝑝
Δf (s) = [ΔP𝐺 (𝑠) - ΔP𝐷 (s)] 1+𝑆𝑇𝑝
2𝐻
TG = = Power system time constant
𝐵𝑓0
1
Kp = = Power system gain
𝐵
Speed droop is a governor function which reduces the governor reference speed as fuel
position (load) increases. All engine controls use the principle of droop to provide stable
operation. The simpler mechanical governors have the droop function built into the
control system, and it cannot be changed.
The ability to return to the original speed after a change in load is called
isochronous speed control. All electronic controls have circuits which effectively
provide a form of temporary droop by adjusting the amount of actuator position change
according to how much off speed is sensed. Without some form of droop, engine-speed
regulation would always be unstable. A load increase would cause the engine to slow
down. The governor would respond by increasing the fuel position until the reference
speed was attained. However, the combined properties of inertia and power lag would
cause the speed to recover to a level greater than the reference.
Droop is a straight-line function, with a certain speed reference for every fuel position.
Normally, a droop governor lowers the speed reference from 3 to 5 percent of the
reference speed over the full range of the governor output. Thus a 3% droop governor
with a reference speed of 1854 rpm at no fuel would have a reference speed of 1800 rpm
at max fuel (61.8 Hz at no fuel and 60 Hz at max fuel).
Most complex hydraulic governors have adjustable droop. In these cases, droop may be
set between 0% and 5%. Droop is not adjustable in most mechanical governors,
Percentage speed regulation or droop
The value of R determines the steady-state speed versus load characteristic of the
generating unit as shown in fig.5. The ratio of speed deviation (∆ωr) or frequency
deviation (∆f) to change in valve/gate position or power output (∆P) is equal to R. The
parameter R is referred to as speed regulation or droop. It can be expressed in
percent as
𝜔𝑁𝐿 − 𝜔𝐹𝐿
%R = x 100
𝜔𝐹𝐿
When two generating units are operating in parallel on the system, their speed-droop
characteristics low load changes are shared among them in the steady state and to
operate to a common frequency.
−𝑃𝑟1 ∆f
Unit-1, (∆PG1) = x
𝑅𝑝.𝑢1 𝑓𝑟
−𝑃𝑟2 ∆f
Unit-2,( (∆PG2) = x
𝑅𝑝.𝑢2 𝑓𝑟
−∆P .fr
The system frequency change ∆f = 𝑃𝑟1 𝑃𝑟2
+
𝑅𝑝.𝑢1 𝑅𝑝.𝑢2
−∆P
∆f = 𝟏 𝟏
+
𝑹𝟏 𝑹𝟐
Fig.5 Ideal steady state characteristics of a governor with
speed droop
Two different controls are carried out on the governor characteristics. The
parameter R is adjusted during off-line condition of the unit to ensure its proper
coordination with the other units, the second control shifts the straight line
characteristic parallel to itself to change the load distribution among the generators
connected in parallel as well as to maintain the system frequency.
It is to be noted that if the frequency of two areas are to be controlled, the static
frequency drop is 50% of the isolated operation of two systems. Also, if there is change
in load in any area, half of it shared by other area.
Problems in Load Sharing of Two Alternators
50−OD
= 0.03
OD
50-OD = 0.03 OD
1.03 X OD = 50
OD = 48.543 Hz
50−OF
= 0.04
OF
50-OF = 0.04 OF
1.04 OF = 50
OF = 48.0769 Hz
𝐶𝐷 𝐴𝐵
=
𝐸𝐷 𝐴𝐷
𝑋 50−𝑓
=
400 50−48.543
50−𝑓
X = 400 (1.457)
X = 274.5367 50 − 𝑓
𝐵𝐻 𝐴𝐵
=
𝐹𝐺 𝐴𝐹
1000−𝑋 50−𝑓
=
700 50−𝑂𝐹
1000−𝑋 50−𝑓
=
700 50−48.0769
1000−𝑋 50−𝑓
= 1.9231
700
50−𝑓
1000-X = 700 (1.9231)
638.5323 f = 30926.6166
f = 48.4339 Hz
Substitute ‘f’ value in eq-1
X = 13726.835 – 13296.8831
X = 429.952 MW
Result
𝐵𝐶 𝐴𝐶
=
𝐷𝐸 𝐴𝐸
𝑋 2−𝑓
25
= 50−48
𝑋 2−𝑓
=
25 2
X = 25 – 12.5 h ……………….(1)
𝐶𝐻 𝐴𝐶
=
𝐹𝐺 𝐴𝐹
30−𝑋 𝐴𝐹−𝐹𝐶
=
25 𝐴𝐹
30−𝑋 1.5−(ℎ−0.5)
=
25 1.5
h = 0.9712
X = 25 – 12.5 x (0.9712)
X = 12.85MW
Extend BC to B’F
𝐵"𝐹 𝐴𝐹
=
𝐷𝐸 𝐴𝐸
𝐵"𝐹 50−48.5
=
25 50−48
B’F = 18.75MW
It is the ratio of units generated to the product of plant capacity and the number of
16 hours for which the plant was in operation. K1 CO1
The need for voltage regulation in power system is to maintain the voltage at
17 K1 CO1
the load terminals within prescribed limits under fluctuating load conditions
by employing suitable voltage control equipment.
Part A (Q & A)
Hydraulic amplifier consists of main piston and pilot valve. Low power level
19 pilot valve movement is converted into high power level piston valve K1 CO1
movement which is necessary to open or close the steam valve against high
pressure steam.
20 The real power in a power system is being controlled by controlling the K1 CO1
driving torque of the individual turbines of the system.
State why P–f and Q–V control loops can be treated as non-interactive?
The active power P is mainly dependent on the internal angle δ and is
independent of bus voltage magnitude |V|. The bus voltage
is dependent on machine excitation and hence on reactive power Q and is
independent of the machine angle δ. The change in the machine angle δ is
28 caused by a momentary change in the generator speed and hence the K1 CO2
frequency. Therefore, the load frequency and excitation voltage controls are
non-interactive for small changes and can be modeled and analyzed
independently.
Two generators rated 400MW and 700 MW are operated in parallel. The
droop characteristics of their governors are 3% and 4% respectively from
no-load to full –load. Assuming that the governors are operating in 50HZ
2 at no load, how would a load of 1000MW be shared between them?. K2 CO1
What will be the system frequency at this load? Assume linear governor
operation; determine the full load speed for each machine.
Why is the load on the power system is variable? What are the effects of
4 K2 CO1
variable load in power system?
03.08.2020
17 Prescribed Text Books & Reference Books
TEXT BOOKS:
2. Allen. J. Wood and Bruce F. Wollen berg, ‘Power Generation, Operation and
Control’, John Wiley & Sons, Inc., 2016.
3. Abhijit Chakrabarti and Sunita Halder, ‘Power System Analysis Operation and
Control’, PHI learning Pvt. Ltd., New Delhi, Third Edition, 2010.
REFERENCES
1. Kothari D.P. and Nagrath I.J., ‘Power System Engineering’, Tata McGraw-Hill
Education, Second Edition, 2008.
2. Hadi Saadat, ‘Power System Analysis’, McGraw Hill Education Pvt. Ltd., New
Delhi, 21st reprint, 2010.
3. Kundur P., ‘Power System Stability and Control, McGraw Hill Education Pvt. Ltd.,
New Delhi, 10th reprint, 2010.
18 Mini project suggestions
Disclaimer:
This document is confidential and intended solely for the educational purpose of RMK Group of
Educational Institutions. If you have received this document through email in error, please notify the
system manager. This document contains proprietary information and is intended only to the
respective group / learning community as intended. If you are not the addressee you should not
disseminate, distribute or copy through e-mail. Please notify the sender immediately by e-mail if you
have received this document by mistake and delete this document from your system. If you are not
the intended recipient you are notified that disclosing, copying, distributing or taking any action in
reliance on the contents of this information is strictly prohibited.
Please read this disclaimer before proceeding:
This document is confidential and intended solely for the educational purpose of
RMK Group of Educational Institutions. If you have received this document
through email in error, please notify the system manager. This document
contains proprietary information and is intended only to the respective group /
learning community as intended. If you are not the addressee you should not
disseminate, distribute or copy through e-mail. Please notify the sender
immediately by e-mail if you have received this document by mistake and delete
this document from your system. If you are not the intended recipient you are
notified that disclosing, copying, distributing or taking any action in reliance on
the contents of this information is strictly prohibited.
POWER SYSTEM OPERATION AND CONTROL
Department: EEE
2 Course objectives 6
3 Pre Requisites 7
4 Syllabus 8
5 Course outcomes 9
6 CO-PO/PSO Mapping 13
7 Lecture Plan 14
8 Activity based learning 16
9 Lecture Notes 17
10 Assignments 56
11 Part A Q & A 57
16 Assessment Schedule 66
SCADA and its application for real time operation and control of power systems
Prerequisites
CO2 Ability to analyse the control actions to be implemented on the system to meet
the minute-to-minute variation of system demand.
CO3 Ability to understand the significance of power system operation and control.
CO6 Ability to design SCADA and its application for real time operation.
PROGRAMME OUTCOMES
c. Come out with solutions for the complex problems and to design system
components or process that fulfill the particular needs taking into account public
health and safety and the social, cultural and environmental issues.
e. Form, select and apply relevant techniques, resources and Engineering and IT
tools for Engineering activities like electronic prototyping, modeling and control
of systems and also being conscious of the limitations.
10
PROGRAMME OUTCOMES
l. Recognize the need for self and life-long learning, keeping pace with
technological challenges in the broadest sense.
11
PROGRAM SPECIFIC OUTCOMES
PSO 1 Analyze, design and implement control, instrumentation and power systems for
satisfying industry needs.
PSO 2 Use modern tools and appropriate solutions for the real time problems for promoting
energy conservation and sustainability.
12
CO-PO /PSO mapping
CO/ a b c d e f g h i j k l PS PS PS
PO, O O O
PSO 1 2 3
co1 - 2 - 3 3 - - - - - - - 3 - 3
co2 - 2 - 3 3 - - - - - - - 3 - 3
co3 - 2 - 3 3 - - - - - - - 3 - 3
co4 - 2 - 3 3 - - - - - - - 3 - 3
co5 - 2 - 3 3 - - - - - - - 3 - 3
co6 - 2 - 3 3 - - - - - - - 3 - 3
Lecture plan
Sl Topic No Prop Actu Pertaining Taxo Mode
N of osed al dt CO nom of
o Peri dt y deliver
ods level y
1 Load Frequency Control CO1, CO2 K2 PPT
(LFC) of single area
system-
2 Static Analysis of CO1, CO2 K2 PPT
uncontrolled and
controlled cases -
Problems
3 Dynamic analysis of CO1, CO2 K2 PPT
uncontrolled and
controlled cases
4 LFC of two area system - CO1, CO2 K2 PPT
tie line modelling
5 block diagram CO1, CO2 K2 PPT
representation of two area
system - static Analysis
6 Dynamic Analysis of two CO1, CO2 K2 PPT
area system
7 Tie line with frequency K3 PPT
bias control
8 State variability model CO1, CO2 K2 PPT
Load frequency control (LFC) is the basic control mechanism in the power system operation.
Whenever there is a variation in load demand on a generating unit, there is momentarily an
occurrence of unbalance between real-power input and output. This difference is being
supplied by the stored energy of the rotating parts of the unit.
The kinetic energy of any unit is given by
1
KE = 2
I ω2
where I is the moment of inertia of the rotating part and ω the angular speed of the rotating
part. If KE reduces, ω decreases; then the speed falls, hence the frequency reduces. The
change in frequency Δf is sensed and through a speed governor system, it is fed back to
control the position of the inlet valve of the prime mover, which is connected to the
generating unit. It changes the input to the prime mover suitably and tries to bring back the
balance between the real-power input and output. Hence, it can be stated that the frequency
variation is dependent on the real-power balance of the system. The LFC also controls the
real-power transfer through the interconnecting transmission lines by sensing the change in
power flow through the tie lines.
.
Prime movers driving the generators are fitted with governors, which are regarded as
primary control elements in the LFC system. Governors sense the change in a speed control
mechanism to adjust the opening of steam valves in the case of steam turbines
1. Most AC motors run at speeds that are directly related to frequency. The speed and
induced electro motive force (e.m.f) may vary because of the change of frequency of the
power circuit.
2. When operating at frequencies below 49.5 Hz; some types of steam turbines, certain
rotor states undergo excessive vibration.
3. The change in frequency can cause mal operation of power converters by producing
harmonics.
4. For power stations running in parallel it is necessary that frequency of the network
must remain constant for synchronization of generators.
Previous chapter derived the modelling of speed governor, turbine, and generator load
model. Combining the governor model, turbine model and generator load model, we get
the complete block diagram representation of LFC of an isolated power system which is
shown in fig.10
The basic objective of the primary ALFC loop is to maintain constant frequency in spite of
changing loads. The primary ALFC loop as shown in the fig. has one output and two
inputs. ΔPref(s) and ΔPD(s)
Consider the speed changer has a fixed setting. Under this condition ΔPC =0 and the load
demand changes. This is known s free governor operation. The block diagram is shown in
fig drawn from substituting ΔPC =0.
Fig.2
Fig.3
𝐾𝑝
ΔF(s) = [-ΔPD(s)]
1+𝑠𝑇𝑝
𝐾𝑝 𝐾𝑔𝐾𝑡
1+ 𝑥
1+𝑠𝑇𝑝 𝑅(1+𝑠𝑇𝑔)(1+𝑠𝑇𝑡)
𝐾𝑝
ΔF(s) = 𝐾𝑝𝐾𝑔𝐾𝑡 [-ΔPD(s)]
1+ 𝑠𝑇𝑝 +
𝑅(1+𝑠𝑇𝑔)(1+𝑠𝑇𝑡)
−𝐾𝑝 ΔPD
ΔF(s) = 𝐾𝑝𝐾𝑔𝐾𝑡 [ ]
1+ 𝑠𝑇𝑝 + 𝑠
𝑅(1+𝑠𝑇𝑔)(1+𝑠𝑇𝑡)
Practically Kg Kt =1
−𝐾𝑝
Δfstat = 𝐾𝑝 ΔPD
1+
𝑅
1
Kp = and ΔPD = M
𝐵
1
−
Δfstat = 𝐵
1 ΔPD
1+
𝐵𝑅
−𝑀 𝑀 1
Δfstat = 1 = (-) - ; 𝛽 = 𝐵 +
𝐵+ 𝛽 𝑅
𝑅
1
In practice B<< , neglecting B,
𝑅
Δfstat
= (-)R Hz/MW
ΔPD
When several generators with governor speed regulations R1,R2…..Rn are connected to the
system the steady state deviation in frequency is given by
−ΔPD
Δfstat = 1 1 1
𝐵+ + +⋯⋯
𝑅1 𝑅2 𝑅𝑛
In this case, there is a step change ΔPC force for speed changer setting and the load demand
remains fixed i.e ΔPD =0.
Fig.5
Fig.6
𝐾𝑔𝐾𝑡𝐾𝑝
ΔF(s) = 𝐾𝑔𝐾𝑡𝐾𝑝 x ΔPC (s)
1+𝑠𝑇𝑔 1+𝑠𝑇𝑡 1+𝑠𝑇𝑝 +
𝑅
Practically Kg Kt =1 ; Tg =Tt = 0
𝐾𝑝
ΔF(s) = 𝐾𝑝 x ΔPC
1+𝑠𝑇𝑔 1+𝑠𝑇𝑡 1+𝑠𝑇𝑝 +
𝑅 𝑠
Δfstat 1
= 1 Hz/MW
ΔPC 𝐵+𝑅
Fig.7
𝐾𝑝
ΔF(s) = [-ΔPD(s)]
1+𝑠𝑇𝑝
𝐾𝑝 𝐾𝑔𝐾𝑡
1+ 𝑥
1+𝑠𝑇𝑝 𝑅(1+𝑠𝑇𝑔)(1+𝑠𝑇𝑡)
Taking inverse Laplace transform for an expression ΔF(s) is tedious, because the
denominator will be third order. We can simplify the analysis by making the following
assumptions.
1. The action of speed governor and turbine is instantaneously compared with rest of the
power system.
Fig.8
𝐾𝑝
ΔF(s) = 𝐾𝑝 [-ΔPD(s)]
1+ 𝑠𝑇𝑝 +
𝑅
−ΔPDkp 𝐴 𝐵
ΔF(s) = + 𝑅+𝐾𝑝
𝑇𝑝 𝑠 𝑠 +
𝑅𝑇𝑝
A+ B = 0
𝑅𝑇𝑝 −𝑅𝑇𝑝
A= ;B=
𝑅+𝐾𝑝 𝑅+𝐾𝑝
−ΔPDkp 𝑅𝑇𝑝 1 1
ΔF(s) = [ − 𝑅+𝐾𝑝 ]
𝑇𝑝 𝑅+𝐾𝑝 𝑠 𝑠 +
𝑅𝑇𝑝
𝑅𝐾𝑝 𝑅+𝐾𝑝
Δf(t) = (-)M 1 − 𝑒 −(𝑡 𝑅𝑇𝑝 )
𝑅+𝐾𝑝
ΔPCRK𝑝 𝑅+𝐾𝑝
Δf(t) = 1 − 𝑒
−(𝑡
𝑅𝑇𝑝 )
𝑅+𝐾𝑝
1.By reducing value of R it is possible to increase AFRC. Hence static frequency error may be
reduced.
2. With smaller time constant Tg and Tt, the system response shows some oscillations before
settling down with a drop in frequency. But if these time constants are neglected, response is
purely exponential.
3. If the overall closed loop system time constant is calculated from the response curve, it is
found to be much smaller than the open loop time constant of the power system.
4. For the uncontrolled system there exists a steady state frequency error as a result of increase
in load demand, however small it may be.
5. When the load demand increases speed or frequency of the system drops though initially
kinetic energy of rotating inertia may be used to meet up the demand. Eventually it will be
balanced by an increase in system generation and decrease in load as associated with the
dropping frequency.
Problems in LFC single Area
Example 1: Find the static frequency drop if the load is suddenly increased by 25 MW on a
system having the following data:
Rated capacity Pr = 500 MW
Operating Load PD = 250 MW
Inertia constant H = 5 s
Governor regulation R = 2 Hz p.u. MW
Frequency f = 50 Hz
Also find the additional generation.
Solution :
Assuming the frequency characteristic to be linear, we have
𝜕𝑃𝑑 250
B= = MW/Hz
𝜕𝑓 50
250
∂PD/∂f expressed in p.u., B= = 0.01 pu MW/Hz
50𝑥500
25
ΔPD in p.u = = 0.05
500
1 1
𝛽=𝐵+ = 0.01 + = 0.51
R 2
The static frequency drop
−𝑀 −0.05
Δfstat = 1 = =(-)0.09803 Hz.
𝐵+ 0.51
𝑅
The load varies by 0.8 percent for a 1 percent change in frequency; determine the steady
state frequency deviation in Hz. (June 2016 AU)
Solution :
H=5
Tt = 0.5 sec
TG = 0.2 sec
60
ΔPD = 60MW = = 0.2 p.u
300
B = 4.8 MW/Hz
4.8
B = = 0.016 p.u MW/Hz
300
1 1
𝐾𝑝 = = = 62.5 Hz/p.u MW
B 0.016
2𝐻 2𝑥5
Tp = = = 12.5 sec
𝐵𝑓0 0.016𝑥50
𝐾𝑝
ΔF(s) = [-ΔPD(s)]
1+𝑠𝑇𝑝
𝐾𝑝 𝐾𝑔𝐾𝑡
1+ 𝑥
1+𝑠𝑇𝑝 𝑅(1+𝑠𝑇𝑔)(1+𝑠𝑇𝑡)
0.2
For a step load change ΔPD(s) = ΔPD = 𝑆
𝑠
−0.2
𝑠𝑥62.5𝑥0.1 𝑠 2
+7𝑠+ 10 ( 𝑠 )
Δfstat = lim 2 2
𝑠→0 1.25(𝑠 +7.08𝑠 +10.64𝑠+20.8)
Δfstat = (-)0.48 Hz
Here, the control objective is to regulate the frequency of each area and
to simultaneously regulate the power flow through the tie line according to an inter
area power agreement.
Tie Line Modeling
In the case of an isolated control area, the zero steady state error in
frequency (i.e., Δf = 0) can be obtained by using a proportional plus integral
controller, whereas in two-control area case, proportional plus integral controller will
be installed to give zero steady state error in a tie-line power flow (i.e., ΔPTie = 0) in
addition to zero steady-state error in frequency.
For the sake of convenience, each area can be represented by an
equivalent turbine, generator, and governor system. In the case of a single control
area, the incremental power (ΔPG −ΔPD) was considered by the rate of increase of
stored KE and increase in area load caused by the increase in frequency. But as in
the case of a two-area, the tie-line power must be accounted for the incremental
power balance equation of each area, since there is power f low in or out of the area
through the tie line.
Power flow out of area 1 is given by
V1 V2
Ptie,1 = Sin(δ10 − δ02 )
X12
𝜕Ptie,1 V1 V2
= Cos δ10 − δ02 (Δδ1 − Δδ2 )
𝜕δ12 X12
Divide the above equation by rated power Pr1 to convert into per unit
V1 V2
∆Ptie,1 p.u = Cos δ10 − δ02 (Δδ1 − Δδ2 )
X12 Pr1
V1 V2
Where T12 = Cos δ10 − δ02
X12 Pr1
i.e., slope of the power angle curve at the initial operating angle 𝛿120
ω = 2πf
ω
f = 2π
1 dδ
f=
2π dt
1 d
Δf = (∆δ)
2π dx
∆δ = 2π න ∆F dt
Where ΔF1 and ΔF2 are incremental frequency changes of area 1 and 2 respectively
Similarly,
∆Ptie,2 p.u = 2π T21 ΔF2 dt − ΔF1 dt
V2 V1 Pr1
Where T21 = X21 Pr2
Cos δ02 − δ10 x Pr1
Pr1
T21 = T
Pr2 21
Pr1
T21 = a12 T12 Where a12 = (3)
Pr2
The incremental power balance equation for area 1 can be written as,
2H1 d
∆PG1 − ∆PD1 = f0 dt
(∆F1 ) + B1 ∆F1 + ∆Ptie,1 (4)
(In the above equation all quantities are in P.U except frequency)
Taking Laplace transform on equation 4,
2H1
∆PG1 (s) − ∆PD1 (s) = s ∆F1 (s) + B1 ∆F1 (s) + ∆Ptie,1 (s)
f0
On rearranging the above equation
2H1
∆PG1 s − ∆PD1 s − ∆Ptie,1 s = ∆F1 s { s + B1 }
f0
1
B1
∆F1 s = [∆PG1 s − ∆PD1 s − ∆Ptie,1 s ]
2H s
1+ 01
f B1
K ps1
∆F1 s = ∆PG1 s − ∆PD1 s − ∆Ptie,1 s (5)
1 + s Tps1
1 2H1
K ps1 ; Tps1 =
= B1 f0 B 1
2π T12
∆Ptie,1 s = [ΔF1 𝑠 − ΔF2 𝑠 ] (6)
𝑠
For the control area 2,
2π T21
∆Ptie,2 s = [ΔF2 𝑠 − ΔF1 𝑠 ]
𝑠
2π 𝑎12 T12
∆Ptie,2 s = − 𝑠
ΔF1 𝑠 − ΔF2 𝑠 7
Here the changes or deviation which result in the frequency and the
tie line power under steady state conditions following sudden step changing in
the loads in the two areas are determined.
In an uncontrolled case the control input value is zero i.e., no need
to change the speed changer position ΔPc1= ΔPc2 = 0
Suppose there is sudden increase in load demand in the two areas
by incremental steps ΔPd1 and ΔPd2. Frequency drops in the steady state and
these drops are equal
∆𝐹1 𝑠𝑡𝑎𝑡 = ∆𝐹2 𝑠𝑡𝑎𝑡 = ∆𝐹𝑠𝑡𝑎𝑡
At steady state condition, we will have incremental tie line power.
1
∆𝑃𝐺1,𝑠𝑡𝑎𝑡 = − ∆𝐹𝑠𝑡𝑎𝑡 (1)
𝑅1
1
∆𝑃𝐺2,𝑠𝑡𝑎𝑡 = − ∆𝐹 (2)
𝑅2 𝑠𝑡𝑎𝑡
From the two area system block diagram
K ps1
∆F𝑠𝑡𝑎𝑡 = ∆PG1,stat − ∆PD1 − ∆Ptie,1,stat
1 + s Tps1
1
B1
∆F stat = [∆PG1,stat − ∆PD1 − ∆Ptie,1,stat ]
2H s
1+ 01
f B1
2H1
∆PG1,stat − ∆PD1 − ∆Ptie,1,stat = ∆Fstat s + B1
f0
2H1 𝑑
= B1 ∆Fstat + ∆𝐹
f 0 𝑑𝑡 𝑠𝑡𝑎𝑡
𝑑
𝑃𝑢𝑡 ∆𝐹 = 0 𝑓𝑜𝑟 𝑎𝑟𝑒𝑎 1 𝑤𝑒 𝑔𝑒𝑡
𝑑𝑡 𝑠𝑡𝑎𝑡
1 𝑎12
− ∆𝐹𝑠𝑡𝑎𝑡 − ∆PD2 = B2 ∆Fstat + ∆Fstat + 𝑎12 ∆PD1 + 𝑎12 B1 ∆Fstat
𝑅2 𝑅1
1 𝑎12
∆𝐹𝑠𝑡𝑎𝑡 − − B2 − − 𝑎12 B1 = 𝑎12 ∆PD1 + ∆PD2
𝑅2 𝑅1
1
=− ∆𝐹 − B1 ∆Fstat − ∆PD1
𝑅1 𝑠𝑡𝑎𝑡
1
= − ∆Fstat 𝐵1 + − ∆PD1 (6)
𝑅1
Substitute equation (5) in (6)
1 1 1
[𝑎12 ∆PD1 + ∆PD2 ] 𝐵1 + − ∆PD1 𝐵2 + − 𝑎12 ∆PD1 𝐵1 +
𝑅1 𝑅2 𝑅1
=
1 1
𝐵2 + + 𝑎12 𝐵1 +
𝑅2 𝑅1
1 1
∆PD2 𝐵1 + − ∆PD1 𝐵2 +
𝑅1 𝑅2
=
1 1
𝐵2 + + 𝑎12 𝐵1 +
𝑅2 𝑅1
1 1
𝑙𝑒𝑡 𝛽1 = 𝐵1 + 𝑎𝑛𝑑 𝛽2 = 𝐵2 +
𝑅1 𝑅2
𝛽1 ∆PD2 − 𝛽2 ∆PD1
∆Ptie,1,stat =
𝛽2 + 𝑎12 𝛽1
From Equation 5,
𝑃𝑟1
𝑎12 = =1
𝑃𝑟2
(Since Pr1 = Pr2)
∆PD2 + ∆PD1
∆𝐹𝑠𝑡𝑎𝑡 = −
2𝛽
∆PD2 − ∆PD1
∆Ptie,1,stat = − ∆Ptie,2,stat =
2
∆PD2 = 0
∆PD1
∆𝐹𝑠𝑡𝑎𝑡 = −
2𝛽
−∆PD1
∆Ptie,1,stat =
2
Suppose a step load change occurs at area 2,
∆PD1 = 0
∆PD2
∆𝐹𝑠𝑡𝑎𝑡 = −
2𝛽
∆PD2
∆Ptie,1,stat =
2
For an interconnected power system thee steady state frequency error is
reduced by 50% and change in tie line power also reduced by 50%
Advantage of Interconnected Power System
• Half of the added load in area 2 will be shared by area 1 through the tie line
• Frequency drop will be only half when compared to single area
−K p1 ∆𝐹1 𝑠
∆𝐹1 𝑠 = + ∆PD1 𝑠 + ∆Ptie,1 𝑠 1
1 + s Tp 𝑅1
−K p2 ∆𝐹2 𝑠
∆𝐹2 (𝑠) = + ∆PD2 𝑠 − ∆Ptie,1 𝑠 (2)
1 + s Tp 𝑅2
2π T12
∆Ptie,1 s = ΔF1 𝑠 − ΔF2 𝑠 (3)
𝑠
For Identical two areas
∆𝑃𝑡𝑖𝑒 2 = −∆𝑃𝑡𝑖𝑒 1 ; 𝑎12 = 1
𝑅2 = 𝑅1 = 𝑅 ; 𝐾𝑝1 = 𝐾𝑝2 = 𝐾𝑝
From Equation 1
Kp −K p
∆𝐹1 (𝑠) 1 + = ∆PD1 𝑠 + ∆Ptie,1 𝑠
R(1 + s Tp ) 1 + s Tp
𝑅 + 𝑠𝑅𝑇𝑝 + K p −K p
∆𝐹1 (𝑠) = ∆PD1 𝑠 + ∆Ptie,1 𝑠
R(1 + s Tp ) 1 + s Tp
−K p 𝑅
∆𝐹1 (𝑠) = ∆PD1 𝑠 + ∆Ptie,1 𝑠
𝑅 + 𝑠𝑅𝑇𝑝 + K p
Similarly from equation 2,
−K p 𝑅
∆𝐹2 (𝑠) = ∆PD2 𝑠 + ∆Ptie,1 𝑠
𝑅 + 𝑠𝑅𝑇𝑝 + K p
Sub the value of ∆𝐹1 (𝑠) and ∆𝐹2 (𝑠) in equation 3 we get as,
2π T12 −K p 𝑅
∆Ptie,1 s = X ∆PD1 𝑠 − ∆PD2 𝑠 + 2 ∆Ptie,1 s
𝑠 𝑅 + 𝑠𝑅𝑇𝑝 + K p
4𝜋𝑇12 K p 𝑅 − 2π T12 K p 𝑅
∆Ptie,1 s 1 + = X ∆PD1 𝑠 − ∆PD2 𝑠
𝑅 + 𝑠𝑅𝑇𝑝 + K p 𝑠(𝑅 + 𝑠𝑅𝑇𝑝 + K p )
𝑇𝑝 𝑅𝑠 2 + 𝑠 𝑅 + 𝐾𝑝 + 4𝜋𝑇12 K p 𝑅
∆Ptie,1 s
𝑠 𝑅 + K p + 𝑠𝑅𝑇𝑝
2π T12 −K p 𝑅
= ∆PD1 𝑠 − ∆PD2 𝑠
𝑠 𝑅 + 𝑠𝑅𝑇𝑝 + K p
−2π T12 K p
∆Ptie,1 s = ∆PD1 𝑠 − ∆PD2 𝑠
2
𝑅 + 𝐾𝑝 4𝜋𝑇12 𝐾𝑝
𝑇𝑝 𝑠 + 𝑠+
𝑇𝑝 𝑅 𝑇𝑝
1
We know 𝐾𝑝 = 𝐵
Hz / p.u MW
2𝐻
Power system time constant 𝑇𝑝 =
𝐵𝑓0
𝑠 2 + 2𝛼𝑠 + 𝜔2 = (𝑠 + 𝛼)2 + 𝜔2 − 𝛼 2
𝑓𝑜 1
Where 𝛼= 𝐵+
4𝐻 𝑅
2𝜋𝑇12 𝑓 𝑜
2
𝜔 =
𝐻
Since 𝛼 and 𝜔2 are positive therefore the system is stable and damped
The roots of the characteristics equation are
−2𝛼 ± 2𝛼 2 − 4𝜔 2
𝑆1,2 =
2
= −𝛼 ± 𝛼 2 − 𝜔 2
We have three conditions
1. If 𝛼 = 𝜔 , the system is critically damped, the roots becomes 𝑆1,2 = −𝜔
2. If 𝛼 > 𝜔, the system becomes underdamped , the roots becomes
𝑆1,2 = −𝛼 ± 𝛼 2 − 𝜔 2
𝑆1,2 = −𝛼 ± 𝑗 𝜔 2 − 𝛼 2
= −𝛼 ± 𝑗𝜔𝑑
𝛼 = 𝐷𝑎𝑚𝑝𝑖𝑛𝑔 𝐹𝑎𝑐𝑡𝑜𝑟
𝜔𝑑 = 𝐷𝑎𝑚𝑝𝑙𝑒𝑑 𝐴𝑛𝑔𝑢𝑙𝑎𝑟 𝐹𝑟𝑒𝑞𝑢𝑒𝑛𝑐𝑦
𝜔𝑑 = 𝜔2 − 𝛼2
2
2𝜋𝑇12 𝑓 𝑜 𝑓𝑜 1
= − 𝐵+
𝐻 4𝐻 𝑅
𝑓𝑜
Assume the load not varying with frequency B = 0, 𝑠𝑖𝑛𝑐𝑒 𝛼 = 4𝜋𝑅
The system damping is strongly depend on the parameter 𝛼. Since 𝑓 𝑜 and H are
constant, the damping will be function of R.
Low Value of R will give strong damping
High value of R will give weak damping
If R = 𝛼 , 𝜔𝑑 = 𝜔, where 𝜔 = Natural Angular Frequency
i.e., there is no speed governor action. Therefore the system will perform undamped
oscillations.
Fig.16. Dynamic response of two identical area
system
From the response curve the following conclusions can be drawn.
Static change in tie line flow corresponding to load change in area 2 is positive
and is equal to ΔPd / 2 for two identical two area system
Static change in frequency for the same case is negative and equal to (-ΔPd/2)
Change in frequency in area 2 under transient state is not identical
Maximum deviation of frequency occurs in the area in which disturbance has
taken place
𝐴𝐶𝐸2 ≜ ∆𝑃𝑡𝑖𝑒 2
The ACE’s would be fed via integrators on to the respective speed
changer. This arrangement would work but not well. The problem with this
arrangement proved to be that the central frequency controlling station tended to
regulate for everybody trying to absorb everybody’s else’s error and offsets. As a
result it would swing widely between the generating limits.
To avoid such error a control strategy that has been adopted by most
operating systems. The control strategy is termed “tie line bias control” and it is
based upon the principle that “all operating pool members must contribute their
share to frequency control in addition taking care of their own net interchange”.
Tie Line Bias Control of Two Area System
In this reset control method to our two area system we would add dashed
loops in two area system as shown in fig.
From the block diagram of two area system as shown in fig, ACE is the
change in area frequency which, when used in integral loop forced the steady state
frequency error to zero.
In order to make the steady state tie line power to zero another integral
control one for each area must be introduced to integrate the incremental tie line
power signal feed it back to the speed changer
The constants K11 and K12 are integrator gains and the constants b1 and b2
are frequency bias parameters. The minus sign is included since each area should
increase its generation if either its frequency error or its tie line power increment is
negative
Fig 17 Block diagram of two area LFC with tie line bias control
Static System Response
The chosen strategy will eliminate the steady state frequency and tie line
deviations for the following reasons
Following a step load change in either area, a new static equilibrium, if
such an equilibrium exists can be achieved only after the speed changer commands
have reached constant values. But it is evidently requires that both integrands
∆𝑃𝐶1 𝑎𝑛𝑑 ∆𝑃𝐶2 are zero.
∆𝑃𝑡𝑖𝑒 1 + 𝑏1 ∆𝐹1 = 0
∆𝑃𝑡𝑖𝑒 2 + 𝑏2 ∆𝐹2 = 0
∆𝐹1 − ∆𝐹2 = 0
∆𝑃𝑡𝑖𝑒 1
= −𝑎12 = 𝐶𝑜𝑛𝑠𝑡𝑎𝑛𝑡
∆𝑃𝑡𝑖𝑒 2
The above conditions can be met only if,
∆𝐹1 = ∆𝐹2 = 0
Note that this result is independent of B1 and B2. In fact, one of the bias
parameter (but not both) can be zero, and we still have a guarantee that the above
conditions is satisfied.
The question what best value to choose for the parameters B parameters
has been hotly debated. It shown that choosing B = β (i.e., AFRC) produces
satisfactory overall performance of interconnected power system.
𝐾𝑝𝑠1
∆𝐹1 𝑠 = ∆𝑃𝑔1 𝑠 − ∆𝑃𝑑1 𝑠 − ∆𝑃𝑇𝐿1 𝑠
1 + 𝑠𝜏𝑝𝑠1
𝐾𝑝𝑠2
∆𝐹2 𝑠 = ∆𝑃𝑔2 𝑠 − ∆𝑃𝑑2 𝑠 − ∆𝑃𝑇𝐿2 𝑠
1 + 𝑠𝜏𝑝𝑠2
1
∆𝑋𝐸1 𝑠 = ∆𝑃𝐶1 𝑠 − 𝐹1 (𝑠)/𝑅1
1 + 𝑠𝜏𝑠𝑔1
1
∆𝑋𝐸2 𝑠 = ∆𝑃𝐶2 𝑠 − 𝐹2 (𝑠)/𝑅2
1 + 𝑠𝜏𝑠𝑔2
1
∆𝑃𝐺1 𝑠 = ∆𝑋𝐸1 𝑠
1 + 𝑠𝜏𝑡1
1
∆𝑃𝐺2 𝑠 = ∆𝑋𝐸2 𝑠
1 + 𝑠𝜏𝑡2
2π T12
∆PTL1 s = [ ΔF1 𝑠 − ΔF2 𝑠 ]
𝑠
Where XE1 (s) and XE2 (s) are the Laplace transforms of the movements of
the main positions in the speed governing mechanism of the two areas.
By taking inverse Laplace transform for the above equations, we get a set of
seven differential equations. These are the time-domain equations, which describe the
small-disturbance dynamic behavior of the power system.
Consider the first equation,
(1 + 𝑠𝜏𝑝𝑠1 ) ∆𝐹1 𝑠 = 𝐾𝑝𝑠1 ∆𝑃𝑔1 𝑠 − ∆𝑃𝑑1 𝑠 − ∆𝑃𝑇𝐿1 𝑠
1
𝑠∆𝐹1 𝑠 = −∆𝐹1 𝑠 + 𝐾𝑝𝑠1 ∆𝑃𝑔1 𝑠 − ∆𝑃𝑑1 𝑠 − ∆𝑃𝑇𝐿1 𝑠
𝜏𝑝𝑠1
Taking the inverse Laplace transform of the above equation, we get
𝑑 1
[∆𝐹1 ] = {−∆𝐹1 + 𝐾𝑝𝑠1 ∆𝑃𝑔1 − 𝐾𝑝𝑠1 ∆𝑃𝑑1 − 𝐾𝑝𝑠1 ∆𝑃𝑇𝐿1 }
𝑑𝑡 𝜏𝑝𝑠1
In a similar way, the remaining equations can be rearranged and an inverse
Laplace transform is found. Then, the entire set of differential equations is
𝑑 1
[∆𝐹2 ] = {−∆𝐹2 + 𝐾𝑝𝑠2 ∆𝑃𝑔2 − 𝐾𝑝𝑠2 ∆𝑃𝑑2 − 𝐾𝑝𝑠2 ∆𝑃𝑇𝐿1 𝑎12 }
𝑑𝑡 𝜏𝑝𝑠2
𝑑 1
(∆𝑋𝐸1 ) = −∆𝑋𝐸1 + ∆𝑃𝐶1 − ∆𝐹1 /𝑅1
𝑑𝑡 𝜏𝑠𝑔1
𝑑 1
(∆𝑋𝐸2 ) = −∆𝑋𝐸2 + ∆𝑃𝐶2 − ∆𝐹2 /𝑅2
𝑑𝑡 𝜏𝑠𝑔2
𝑑 1
(∆𝑃𝐺1 ) = −∆𝑃𝐺1 + ∆𝑋𝐸1
𝑑𝑡 𝜏𝑡1
𝑑 1
(∆𝑃𝐺2 ) = −∆𝑃𝐺2 + ∆𝑋𝐸2
𝑑𝑡 𝜏𝑡2
𝑑
(∆PTL1 ) = 2π T12 [ ΔF1 − ΔF2 ]
𝑑𝑡
𝑥1 ∆𝐹1
𝑥2 ∆𝐹2
𝑥3 ∆𝑋𝐸1
𝑋 = 𝑥4 = ∆𝑋𝐸2
𝑥5 ∆𝑃𝑠𝐺1
𝑥6 ∆𝑃𝑠𝐺2
𝑥7 ∆𝑃𝑇𝐿1
𝑢1 ∆𝑃𝑐1
𝑢= 𝑢 ≡
2 ∆𝑃𝑐2
𝑝1 ∆𝑃𝐷1
𝑝= 𝑝 ≡
2 ∆𝑃𝐷2
0 0 𝐾𝑝𝑠1
− 0
0 0 𝜏𝑝𝑠1
1
0 𝐾𝑝𝑠1
𝜏𝑠𝑔1 0 −
𝑢1 𝜏𝑝𝑠1 𝑝1
+ 1 𝑢2 + 𝑝2 (1)
0 0 0
𝜏𝑠𝑔2 0 0
0 0 0 0
0 0 0 0
0 0 0 0
𝑑𝑥𝑖
Where 𝑥ሶ 1 = ; i =1,2,3…,7
𝑑𝑡
𝑥ሶ = 𝐴 𝑥 + 𝐵 𝑢 + 𝐽 𝑃 (2)
Where [A] is called the system matrix, [B] the input distribution matrix, and [J] the disturbance
distribution matrix.
In the present case, their dimensions are (7 × 7), (7 ×2), and (7 × 2),
respectively. Equation (2) is a shorthand form of Equation (1), and Equation (1)
constitutes the dynamic ‘state-variable model’ of the considered two-area system.
The differential equations can be put in the above form only if they are
linear. If the differential equations are non-linear, then they can be expressed in the
more general form as
𝑋ሶ = 𝑓(𝑥, 𝑢, 𝑝)
1. A two area has two identical areas whose data are given below.
Rated Capacity of area (Pr) = 1500 MW
Nominal Operating Load = 750 MW
Nominal Frequency = 50 Hz
Inertia Constant = 5.0
Speed Regulation = 3 %
Governor time constant=0.06 s
Turbine Time Constant = 0.25 s
A load increase M1 =30 MW occurs in area 1. Determine (i) Δfstat & ΔP12 (ii) Compare
Δfstat obtained in the single area and comment on the support.
Pr1 = 1500; Pr2 = 1500
𝑃𝑅1 1500
𝐴12 = = =1
𝑃𝑅2 1500
𝜕𝑃𝐷 750
𝐵 = 𝐵1 = 𝐵2 = = = 15 𝑀𝑊Τ𝐻𝑧
𝜕𝐹 50
15
= = 0.01 𝑝. 𝑢 𝑀𝑊Τ𝐻𝑧
1500
3
𝑥 50
𝑅 = 𝑅1 = 𝑅2 = 1500 𝐻𝑧Τ𝑀𝑊
1500
30
∆𝑃𝐷1 = 𝑀1 = = 0.02 𝑝. 𝑢 𝑀𝑊
1500
𝛽2 = 𝛽1 = 𝛽
𝑅2 = 𝑅1 = 𝑅
𝐵2 = 𝐵1 = 𝐵
𝑃𝑟1
𝑎12 = =1
𝑃𝑟2
∆PD2 + ∆PD1
∆𝐹𝑠𝑡𝑎𝑡 = −
2𝛽
∆PD2 = 𝑀2 = 0
𝑀1
∆𝐹𝑠𝑡𝑎𝑡 = −
2𝛽
1 1
𝛽2 = 𝛽1 = 𝐵 + = 0.01 + = 0.6766 𝑝. 𝑢 𝑀𝑊Τ𝐻𝑧
𝑅 1.5
30
−
∆𝐹𝑠𝑡𝑎𝑡 = 1500 = −0.0147 𝐻𝑧
2 𝑋 0.6766
− 𝛽2 𝑀1 −𝑀1
∆𝑃12 = = = −0.01 𝑝. 𝑢 𝑀𝑊 = −15 𝑀𝑊
2𝛽 2
A 10 MW 2.5 % 7 MW
B 2 MW 4% 2 MW
Calculate the generator output of each station, power transmitted by the interconnector and operator
frequency.
Full load capacity of station A is Pr1 = 10 MW
Load of station A, PD1 = 7 MW
Change in load of station ΔPD1 = 3 MW
∆𝑃𝐷1 3
Per unit value of change in load demand ΔPD1 = = = 0.3 𝑝𝑢 𝑀𝑊
∆𝑃𝑅1 10
Full load capacity of station A is Pr2 = 2 MW
Load of station A, PD2 = 2 MW
Change in load of station ΔPD2 = 0
We know that for two area system, change in tie line power transferred from area A to B
𝛽1 ∆PD2 − 𝛽2 ∆PD1
∆Ptie,1,stat =
𝛽2 + 𝑎12 𝛽1
Change in static frequency
1
𝛽1 = 𝐵 +
𝑅
2.5 50
𝑅1 = 𝑥 = 0.125 𝐻𝑧Τ𝑀𝑊
100 10
𝐵2 = 𝐵1 = 0
1 1
𝛽1 = = = 0.8
𝑅1 1.25
1 1
𝛽2 = = = 0.5
𝑅2 2
𝑃𝑟1 10
𝑎12 = = =5
𝑃𝑟2 2
1. A single-area system has the following data: Speed regulation, R = 4 Hz/p.u. MW;
Damping coefficient, B = 0.1 p.u. MW/Hz; Power system time constant, Tp = 10 s;
Power system gain, Kp = 75 Hz/p.u. MW; When a 2% load change occurs,
determine the AFRC and the static frequency error. What is the value of the steady-
state frequency error if the governor is blocked?
(β = 0.35 MW/Hz ; ΔF = -0.571 Hz; β = 0.1 p.u MW/Hz ; ΔF = -0.2 Hz)
3. Two generating units having the capacities 600 and 900 MW and are operating at
a 50 Hz supply. The system load increases by 150 MW when both the generating
units are operating at about half of their capacity, which results in the frequency
falling by 0.5 Hz. If the generating units are to share the increased load in
proportion to their ratings, what should be the individual speed regulations? What
should the regulations be if expressed in p.u. Hz/p.u. MW?
(R1 = 0.1 p.u ; R2 =0.1 p.u Hz/ p.u MW)
S.No Part A (Q & A) K Level COs
Explain the control area concept.
It is possible to divide a very large power system into sub-areas in
which all the generators are tightly coupled such that they swing in unison
with change in load or due to a speed-changer setting. Such an area, where
1 all the generators are running coherently, is termed the control area. In this K2 CO2
area, frequency may be same in Steady-state and dynamic conditions. For
developing a suitable control strategy, a control area can be reduced to a
single generator, a speed governor, and a load system.
Solve to determine the change in frequency that occurs in this time for
100 MVA synchronous generator is running on full load at 50 Hz
12 frequency. A 40 MW Loads is suddenly removed. Due to lag in governor K3 CO2
system, the steam valve of the turbine begins to close after 0.5 sec..
Given H = 5 MW sec/ MVA of generator rating
Solve for steady-state change in frequency and tie-line power of 10 MW
change in load occurs in both areas where two control areas of 1,000 and
2,000 MW capacities are interconnected by a tie line. The speed regulations
13 K3 CO2
of the two areas, respectively, are 4 Hz/p.u. MW and 2.5 Hz/p.u. MW.
Consider a 2% change in load occurs for 2% change in frequency in each
area.
Solve to find power generation at each station and power transfer through
the line if the load on the bus of each station is 200 MW. And the two
generating stations A and B having capacities 500 and 800 MW, respectively,
are interconnected by a short line. The percentage speed regulations from
14 no-load to full load of the two stations are 2 and 3, respectively. K3 CO@
S.No Part C K Level COs
Apply the load frequency dynamics of this area and determine the steady
state frequency deviation in Hz using Area frequency response
characteristics .The load frequency dynamics of a single area power
system whose data are given below.
Rated Capacity of area (Pr)= 1500 MW ;Nominal Operating Load = 750
1 K3 CO2
MW ; Nominal Frequency = 50 Hz ;Inertia Constant = 5.0
Speed Regulation = 3 % ;Governor time constant & Turbine constant = 0
Assume linear load frequency Characteristics which means the
connected system load is increases by 1 % if the system frequency
increases by 1 %. The area is subjected to a load increase of 30 MW.
Apply the load frequency dynamics of a single area power system whose
data are given below. Rated Capacity of area (Pr)= 1000 MW; Nominal
Operating Load = 500 MW; Inertia Constant = 5.0; Regulation = 5 Hz/ p.u
MW; Frequency = 50 Hz Load decrease by 1 % for a decrease in
frequency by 1 %
2 a. Find gain and time constant of a power system. If it is an K3 CO2
uncontrolled area then find out the change in frequency due to an
increase of load by 75 MW
b. Determine the steady state frequency by changing regulation = 4
Hz/ p.u MW nominal operating load is 750 MW and compare with
the results ‘a’
Supportive Online Certification Courses
Integral control
16 Assessment Schedule
03.08.2020
17 Prescribed Text Books & Reference Books
TEXT BOOKS:
2. Allen. J. Wood and Bruce F. Wollen berg, ‘Power Generation, Operation and
Control’, John Wiley & Sons, Inc., 2016.
3. Abhijit Chakrabarti and Sunita Halder, ‘Power System Analysis Operation and
Control’, PHI learning Pvt. Ltd., New Delhi, Third Edition, 2010.
REFERENCES
1. Kothari D.P. and Nagrath I.J., ‘Power System Engineering’, Tata McGraw-Hill
Education, Second Edition, 2008.
2. Hadi Saadat, ‘Power System Analysis’, McGraw Hill Education Pvt. Ltd., New
Delhi, 21st reprint, 2010.
3. Kundur P., ‘Power System Stability and Control, McGraw Hill Education Pvt. Ltd.,
New Delhi, 10th reprint, 2010.
18 Mini project suggestions
Disclaimer:
This document is confidential and intended solely for the educational purpose of RMK Group of
Educational Institutions. If you have received this document through email in error, please notify the
system manager. This document contains proprietary information and is intended only to the
respective group / learning community as intended. If you are not the addressee you should not
disseminate, distribute or copy through e-mail. Please notify the sender immediately by e-mail if you
have received this document by mistake and delete this document from your system. If you are not
the intended recipient you are notified that disclosing, copying, distributing or taking any action in
reliance on the contents of this information is strictly prohibited.
Please read this disclaimer before proceeding:
This document is confidential and intended solely for the educational purpose of
RMK Group of Educational Institutions. If you have received this document
through email in error, please notify the system manager. This document
contains proprietary information and is intended only to the respective group /
learning community as intended. If you are not the addressee you should not
disseminate, distribute or copy through e-mail. Please notify the sender
immediately by e-mail if you have received this document by mistake and delete
this document from your system. If you are not the intended recipient you are
notified that disclosing, copying, distributing or taking any action in reliance on
the contents of this information is strictly prohibited.
POWER SYSTEM OPERATION AND CONTROL
Department: EEE
2 Course objectives 6
3 Pre Requisites 7
4 Syllabus 8
5 Course outcomes 9
6 CO-PO/PSO Mapping 13
7 Lecture Plan 14
8 Activity based learning 16
9 Lecture Notes 17
10 Assignments 71
11 Part A Q & A 72
16 Assessment Schedule 80
SCADA and its application for real time operation and control of power systems
Prerequisites
CO2 Ability to analyse the control actions to be implemented on the system to meet
the minute-to-minute variation of system demand.
CO6 Ability to design SCADA and its application for real time operation.
PROGRAMME OUTCOMES
c. Come out with solutions for the complex problems and to design system
components or process that fulfill the particular needs taking into account public
health and safety and the social, cultural and environmental issues.
e. Form, select and apply relevant techniques, resources and Engineering and IT
tools for Engineering activities like electronic prototyping, modeling and control
of systems and also being conscious of the limitations.
10
PROGRAMME OUTCOMES
l. Recognize the need for self and life-long learning, keeping pace with
technological challenges in the broadest sense.
11
PROGRAM SPECIFIC OUTCOMES (PSOS)
• Use the modern tools for implementing the solutions to engineering problems that
can arise in the fields of Electrical, Electronics and Telecommunication Engineering
along with Information Technology Services.
11
CO-PO /PSO mapping
CO/ a b c d e f g h i j k l PS PS PS
PO, O O O
PSO 1 2 3
co1 - 2 - 3 3 - - - - - - - 3 - 3
co2 - 2 - 3 3 - - - - - - - 3 - 3
co3 - 2 - 3 3 - - - - - - - 3 - 3
co4 - 2 - 3 3 - - - - - - - 3 - 3
co5 - 2 - 3 3 - - - - - - - 3 - 3
co6 - 2 - 3 3 - - - - - - - 3 - 3
Lecture plan Unit I
Sl Topic No Prop Actu Pertaining Taxon Mod
No of ose al dt CO omy e of
Peri d dt level deliv
ods ery
1 Generation and CO5 K2 PPT
absorption of reactive
power - basics of
reactive power control
2 Automatic Voltage CO5 K2 PPT
Regulator (AVR) –
brushless AC excitation
system – block diagram
representation of AVR
loop
3 AVR -static analysis CO5 K2,K3 PPT
Synchronous Generators:
Synchronous generators can be used to generate or absorb reactive
power. An over-excited machine, that is, one with greater than nominal excitation,
generates reactive power whilst an under-excited machine absorbs it. Synchronous
generators are the main source of supply to the power system of both positive and
negative VARs.
The ability to absorb reactive power is determined by the short-circuit
ratio (1/synchronous reactance)
1
𝑆𝐶𝑅 =
𝑋𝑠
Shunt Capacitor:
A capacitor bank is very essential equipment of an electrical power
system. The power required to run all the electrical appliances is the load as useful
power is active power. The maximum load connected to the electrical power system
is mainly inductive in nature such as electrical transformer, induction motors,
synchronous motor, electric furnaces, fluorescent lighting are all inductive in nature.
In addition to these, inductance of different lines also contributes
inductance to the system. Because of these inductances, the system current lags
behind system voltage. As the lagging angle between voltage and current increases,
the power factor of the system decreases. As the electrical power factor decreases,
for same active power demand the system draws more current from source. More
current causes, more line losses.
Poor electrical power factor causes poor voltage regulation. So to avoid
these difficulties, the electrical power factor of the system to be improved. As a
capacitor causes current to lead the voltage, capacitive reactance can be used to
cancel the inductive reactance of the system
The capacitor reactance is generally applied to the system by using static
capacitor in shut or series with system. Instead of using a single unit of capacitor
per phase of the system, it is quite effective to use a bank of capacitor units, in the
view of maintenance and erection. This group or bank of capacitor units is known as
capacitor bank
Shunt Reactor:
A shunt reactor is a piece of electrical equipment used in high voltage
power transmission systems to stabilize the voltage during load variations. A
traditional shunt reactor has a fixed rating and is either connected to the
transmission line all the time or switched in and out depending on the load.
It offers the cheapest means of reactive power absorption and these are
connected in transmission line during the light load condition because there is huge
amount reactive power generation can be happened due to capacitance effect.
Transformers:
Power transformers ‗consume‘ inductive VARS during operation. This is
due to the reactive power requirement of two separate branches of the transformer
namely:
Shunt Magnetizing Reactance
Series Leakage Reactance
The reactive power drawn by power transformer could be as high as 5% of the
transformer rating when supplying full load current.
Shunt magnetizing reactance is responsible for creating the magnetic flux
in the transformer core. The current required to create this flux in the core is called
exciting current and is relatively independent of the transformer load current.
Exciting current is usually around 0.25-2% of the transformer full load current.
Series leakage impedance indirectly refers to the amount of magnetic flux
that do not link between the primary and secondary winding. The series leakage
reactance (also known as %impedance) is an important transformer parameter that
determines the short circuit contribution, voltage regulation etc.
The total inductive power demand of the power transformer is the
arithmetic sum of the demand due to both the branches above
= 3 𝐾𝑉𝐴 𝑋𝑇 𝐾𝑉𝐴𝑅
Underground Cables:
Cables generate more reactive power than transmission lines because the
cables have high capacitance. The reason for cables having high capacitance than
the transmission line are,
The distance between the conductor is very small.
The distance between the core and earth sheath of the overhead line is very
small.
The permittivity of the cable insulation is usually 3 to 5 times greater than that of
the insulation around the conductors of overhead line.
𝑄𝐴 2𝜋𝜖0
Capacitance of Transmission Line = = 3 𝑑 𝑑 𝑑
𝑉𝐴 1 2 3
𝐿𝑜𝑔𝑒
𝑟
2𝜋𝜖0 𝜖𝑟
Capacitance of Cables = 𝐷
𝐿𝑜𝑔𝑒
𝑑
= 𝐼2 𝜔𝐿
Due to line capacitance of the line, reactive power generated by the line
𝑽𝟐
∆𝑸𝒄 = = 𝑽𝟐 𝝎𝑪
𝑿𝒄
Suppose ∆𝑸𝑳 = ∆𝑸𝒄
𝑰𝟐 𝝎𝑳 = 𝑽𝟐 𝝎𝑪
𝑽 𝑳
= 𝒁𝒏 =
𝑰 𝑪
Where 𝒁𝒏 is called surge impedance of the line
A line is said to be surge impedance loading when it is terminated
by a resistance equal to its surge impedance. The power is transmitted
under this condition is called surge power.
In general
𝑬 𝑽
𝑷= 𝒔𝒊𝒏 𝜹
𝑿
At 𝜹 = 𝟗𝟎, 𝒎𝒂𝒙𝒊𝒎𝒖𝒎 𝒑𝒐𝒘𝒆𝒓 𝒄𝒂𝒏 𝒃𝒆 𝒕𝒓𝒂𝒏𝒔𝒎𝒊𝒕𝒕𝒆𝒅
𝑬 𝑽
𝑷𝒎𝒂𝒙 =
𝑿
By Varying X , 𝜹, 𝑽 , we can get the control of Power transfer
Case (i)
∆𝑸𝑳 > ∆𝑸𝒄
The voltage sags if the voltage at the two ends are maintained constant.
The variation of voltage along the line is shown in the fig
Here the line is loaded below 𝒁𝒏 i.e., light load condition. The net
effect of the line will be absorbed reactive power.
∆𝑸𝑳 < ∆𝑸𝒄
The variation of voltage along the line is as shown in fig. and we find
the voltage rise and maintains constant at the end. Under light load condition
the effect of shunt capacitor is predominating and the line will generate reactive
power.
Loads:
Load absorbs reactive power. Load cannot be constant and it can varies
time to time, season and weather condition. Both active and reactive power of
composite loads vary as a function of voltage magnitudes. Load at low power
factor give Volatge drop in the line and it is uneconomical. Industrial Consumer
are using shunt capacitor to improve the power factor.
Basics of Reactive Power Control:
Shunt compensators:
The device that is connected in parallel with the transmission line is called the shunt
compensator.
A shunt compensator is widely used in transmission system to regulate the voltage
magnitude. It can be provided by either a current source ,or voltage source
The Shunt connected reactors are used to reduce the line over voltages by consuming the
reactive power,
The shunt connected capacitors are used to maintain the voltage levels by compensating
the reactive power to transmission line.
Typical Excitation system (OR) Typical Brushless Automatic Voltage
Regulator
The automatic voltage regulator is used to regulate the voltage. It takes the fluctuate
voltage and changes them into a constant voltage. The fluctuation in the voltage
mainly occurs due to the variation in load on the supply system. The variation in
voltage damages the equipment of the power system. The variation in the voltage
can be controlled by installing the voltage control equipment at several places likes
near the transformers, generator, feeders, etc., The voltage regulator is provided in
more than one point in the power system for controlling the voltage variations.
Thus, the amplified error signals control the excitation of the main or pilot exciter
through a buck or a boost action (i.e. controls the fluctuation of the voltage). Exciter
output control leads to the controls of the main alternator terminal voltage.
It controls the voltage of the system and has the operation of the machine nearer
to the steady state stability.
The automatic voltage regulators reduce the overvoltage‘s which occur because of
the sudden loss of load on the system.
It increases the excitation of the system under fault conditions so that the
maximum synchronising power exists at the time of clearance of the fault.
When there is a sudden change in load in the alternator, there should be a change in
the excitation system to provide the same voltage under the new load condition. This
can be done by the help of the automatic voltage regulator. The automatic voltage
regulator equipment operates in the exciter field and changes the exciter output
voltage, and the field current. During the violent fluctuation, the ARV does not give a
quick response.
The main objective of an excitation system is to feed direct current to the field winding
of synchronous alternator. Also excitation system executes control and protective
function for satisfactory performance of the power system by monitoring the field
current and voltage. The control function helps to control the reactive power flow and
hence voltage for enhancement of power system stability. Whereas protective system
assures the capability limits of the alternators, excitation system and other interlinked
components.
From generator considerations, the basic need of excitation system is to supply and
automatically adjust the field current of alternator to maintain terminal voltage as the
output of alternator varies within its capability. Generally rating of exciter varies from
2.0-3.5 kW per MVA rating of alternator. Capabilities of alternator are restricted by
various factors such as: rotor heating due to excessive field current, failure of rotor
insulation due to high rotor field voltage, stator (armature) heating due to high
armature loading, heating at core end due to under excited operation and excess
heating due to rise in volt/Hz ratio. The short term overload capacity may be extended
from 15-60 sec. So for best utilization of excitation system advantage of short term
overload capabilities may be taken without exceeding the limits.
Considering the power system point of view, the excitation system is effective for
voltage control which in turn enhances system stability. Excitation system should be
capable of responding quickly to disturbance in order to improve transient stability and
small signal stability.
Various components of an excitation system
i. DC excitation system
ii. AC excitation system
iii. Static excitation system.
Fast response
Simple
Low cost
Disadvantages
The main disadvantage is the response rate of the thyristor is very low
ii. AC excitation system: Here small alternator which is mounted on same shaft
of the main alternator is used as source of excitation. The AC output power from
exciter is rectified by rectifier unit. Rectifier unit may be static or rotating. In
stationary rectifier, the DC output current is fed to main field winding through slip
rings. But in rotating rectifier, slip ring and brushes are not required. Both
armature of AC exciter and diode rectifier are mounted on main shaft. A small
pilot AC exciter with a permanent magnet rotor as shown by NS in Figure 2.3
which rotates with exciter armature. Rectified output of the pilot exciter stator
feed DC to stationary field of AC exciter. The voltage regulator regulates the field
of AC exciter and in turn regulates the field of the main alternator. This excitation
system is known as brushless excitation system.
Reliability is excellent
The flexibility of operation is good
System responses are good
There is no moving contact in the brushless system, so maintenance is low
Disadvantages
Response is slow
There is no fast de-excitation
iii. Static excitation system: Figure 3 shows the schematic diagram of static
excitation system and demonstrates that main alternator through step down
transformer or station auxiliary bus supplies power to stationary rectifier and is
regulated by a controlled rectifier. Here static rectifier supplies exciting current to
main field winding of alternator through slip rings.
Reliability is good
The flexibility of operation is very good
System responses are excellent
Small in size
Low loss
Simple
High performance
Disadvantages
The main disadvantages of the static system are, it requires a slip ring and
brush
Comparator
The comparator compares the measured signal |V| against the reference D.C.
signal (Vref). The difference between these two signals produce an error
voltage ‗Ve‘ called error signal.
The amplifier amplifies the input error signal depending on the amplification factor.
There are various types of amplifiers used in the excitation system. They are tuned
generator, amplidyne and electronic amplifier.
∆𝑉R ∝ ∆e
kA = Amplifier gain
∆𝑉R(s) = kA ∆𝑒(𝑠)
∆𝑉𝑅 (𝑠)
GA = = kA
∆𝑒(𝑠)
G A = kA
In reality, the amplifier will have a time delay that can be represented by a time
Constant TA shown in fig. and the amplifier transfer function becomes;
∆𝑉𝑅 (𝑠) 𝐾𝐴
GA = ∆𝑒(𝑠)
= 1 + 𝑠𝑇𝐴
……………… (3)
The purpose of the exciter is to supply field current to the rotor field of the
synchronous generator.
𝑑
Input voltage ∆𝑉R = Re ∆ie + Le (∆ie ) ………………..(4)
𝑑𝑡
∆Vf ∝ ∆ie
𝐾𝑒
Ge = 1 + 𝑠𝑇𝑒
𝐾1 𝐿𝑒
Ke = 𝑅𝑒
; Te = 𝑅𝑒
Ke = Gain of the exciter
Te = Time constant of the exciter in sec.
Value of time constant, Te ranges from 0.5 to 1.0 seconds.
Model of Exciter:
Synchronous Generator
The terminal voltage of the generator is maintained constant during its varying load
conditions, with the help of excitation system.
The terminal voltage of the generator equals to difference between induced emf and
drop across the armature
Fig.10. Circuit diagram of a Syn.Generator Fig.11 Eq.Ckt for field winding of Syn.Gen
∆V = ∆E - Vdrop
From fig.
𝑑
∆Vf = Rf ∆if + Lf (∆if)
𝑑𝑡
𝐼𝑓
Emax = 𝜔 Lfa
√2
2 2𝐸
If = ; Erms =
𝜔𝐿𝑓𝑎 𝜔𝐿𝑓𝑎
2
∆Vf (s) = [Rf + s Lf ] ∆E(s)
𝜔𝐿𝑓𝑎
∆V(s) 𝜔 Lfa
= 𝐿𝑓
∆V 𝑓 (𝑠)
2 Rf 1 + 𝑠]
[ 𝑅𝑓
∆V(s) 𝐾𝑓
= ′
∆V 𝑓 (𝑠) 1 + 𝑠𝑇𝑑0
𝜔 Lfa
Where, Kf = 2 Rf
and 𝑇𝑑0
′
= Open circuit direct axis time constant
𝐿𝑓
′
𝑇𝑑0 = 𝑅𝑓
𝐿𝑓𝑎 = Mutual inductance co-efficient between rotor field and stator armature as
measured when magnetic axis coincide.
1. The automatic voltage regulator must regulate the terminal voltage |V|
within the required static accuracy limit.
3. It must be stable.
From Fig.15
𝐾𝐴 𝐾𝑒 𝐾𝑓
Open loop T.F, G(s) = 1 + 𝑠𝑇𝐴 1 + 𝑠𝑇𝑒 ′
1 + 𝑠𝑇𝑑0
Fig.15 AVR block after reduction
𝐺(𝑠)
At initial condition, ∆ |V|0 = 1 + 𝐺(𝑠)
∆|V|ref0 ……………….(1)
∆e0 must be less than some specified percentage P of reference voltage ∆|V|ref0 . The
static accuracy specification is :
𝑃
∴ ∆ e0 < ∆|V|ref0 ………………(2)
100
𝐺(𝑠)
∆ e0 = (∆|V|ref0 ) – (1 + 𝐺(𝑠)
∆|V|ref0 )
1
∆ e0 = ∆|V|ref0 [1 + 𝐺(𝑠)
]
Putting S = 0,
1 ∆|V|ref0
∆ e0 = (∆|V|ref0 ) [1 + lim 𝐺(𝑆)] = 1 + 𝑘𝑝
𝑠→0
Kp = lim 𝐺(𝑆)
𝑠→0
𝐾𝐴 𝐾𝑒 𝐾𝑓
= lim 𝐺(𝑆) = lim ′
𝑠→0 𝑠→0 1 + 𝑠𝑇𝐴 1 + 𝑠𝑇𝑒 1 + 𝑠𝑇𝑑0
Kp = 𝐾𝐴 𝐾𝑒 𝐾𝑓
∆|V|ref0
∆ e0 =
1 + 𝐾
𝑃
∴ ∆ e0 < ∆|V|ref0
100
∆|V|ref0 𝑃 𝑃
< ∆|V|ref0 =
1 <
1 + 𝐾 100 1 + 𝐾 100
100
1+K> 𝑃
100
K> –1
𝑃
𝐾𝐴 𝐾𝑒 𝐾𝑓 ∆V 𝑟𝑒𝑓 (𝑠)
∆𝑉(s) = 1 + 𝑠𝑇𝐴 1 + 𝑠𝑇𝑒 ′ +𝐾 𝐾𝑒 𝐾𝑓
1 + 𝑠𝑇𝑑0 𝐴
1
For a step input ∆V 𝑟𝑒𝑓 (𝑠) = 𝑠
𝐾𝐴 𝐾𝑒 𝐾𝑓
∆Vstat = 𝐾
1 + 𝐴 𝐾𝑒 𝐾𝑓
𝐾
∆Vstat = 1+K
From fig.16
𝐾𝐴 𝐾𝑒 𝐾𝑓
Open loop T.F G(s) = 1 + 𝑠𝑇𝐴 1 + 𝑠𝑇𝑒 ′
1 + 𝑠𝑇𝑑0
𝐺(𝑠)
∆V(s) = 1 + 𝐺(𝑠)
∆V 𝑟𝑒𝑓 (𝑠)
The response depends upon the eigen values or closed loop poles, which are
obtained from the characteristic equation
1+ G(s) = 0.
The open loop transfer function G(s) is of 3rd order. There are three eigen values
s1,s2,s3.
𝑘1 𝑘2 𝑘3
∆V(t) =𝐿−1 [𝑠 − 𝑠1
+ 𝑠 − 𝑠2
+ 𝑠 − 𝑠3
]
For AVR loop to be stable, the transient components must vanish with time.
All the eigen values are located in left half of s-plane. Then the loop possesses
good tracking ability i.e the system is stable.
For high speed response, the loop possesses eigen values located far away to the
left from origin in s-plane.
The closer the eigen value is located to the j 𝜔 axis, the more dominant it
becomes.
The location in the s-plane of eigen values depends upon the open-loop gain ‗K‘
and the three time constants TA,Te and Td0‘ of these parameters only the loop gain
can be considered adjustable.
𝐾𝐴 𝐾𝑒 𝐾𝑓
Open loop T.F = 1 + 𝑠𝑇𝐴 1 + 𝑠𝑇𝑒 ′
1 + 𝑠𝑇𝑑0
K = 𝐾𝐴 𝐾𝑒 𝐾𝑓
𝐾
Open loop T.F = 1 + 𝑠𝑇𝐴 1 + 𝑠𝑇𝑒 ′
1 + 𝑠𝑇𝑑0
1 1 1
∵ Td0‘ > Te > TA = - 𝑇 ′ > - >-
𝑑0 𝑇𝑒 𝑇𝐴
Number of zeros, Z = 0,
1 1 1
i.e; 𝑝1 =- 𝑇 ′ ; p2 = - ; p3 = -
𝑑0 𝑇𝑒 𝑇𝐴
(2𝑞+1)𝜋
Asymtode angles, ∅ = ; q = 0,1,…………..(p-z-1)
𝑝−𝑧
(2+1)
∅2 = 𝜋 =𝜋
3
(4+1) 5𝜋
∅3 = 𝜋 =
3 3
The root loci for AVR loop is shown in fig. The root locus start from open loop poles
and ends at zero or infinity.
Fig.18 Root loci for AVR Control loop
(1) if the roots are far away from the origin means the system may be stable.
(2) For low values of the loop gain k, the eigen values (marked) are located close to
the open loop poles, their positions marked ‗a‘.
100
K> 𝑃 –1
This result in inaccurate static response.
(4) By increasing the loop-gain K the eigen values S2 travels to the left and the loop
response quickens. At a certain gain setting the eigen values S3 and S2 ‗ collide‘.
Further increase in loop gain results in S3 and S1 becoming complex conjugate. This
dominant eigen value pair makes the loop oscillatory, with poor damping. If the gain
is increased further, the eigen values wander into the right-hand s-plane. The loop
now becomes unstable.
Stability compensation
High loop gain is needed for static accuracy, but this causes undesirable dynamic
response i.e possibly instability.
This conflict situation can be avoided by adding series and / or feedback stability
compensation to the AVR loop. Consider the addition of a series phase lead
compensator as shown in Fig.19
Gs = 1 + sTc
𝐾
Open loop T.F = (1+sTc) [ 1 + 𝑠𝑇𝐴 1 + 𝑠𝑇𝑒 ′ ]
1 + 𝑠𝑇𝑑0
Series compensator network will not affect the static loop gain (k).
K = 𝐾𝐴 𝐾𝑒 𝐾𝑓
If we tune TC = Te
𝐾𝐴 𝐾𝑒 𝐾𝑓
G(s) = 1 + 𝑠𝑇𝐴 1 ′
+ 𝑠𝑇𝑑0
Number of zeros, Z = 0,
1 1
i.e p1 =- ; p3 = -
′
’ 𝑇𝐴
𝑇𝑑0
(2𝑞+1)𝜋
Asymtode angles, ∅ = ; q = 0,1,…………..(p-z-1)
𝑝−𝑧
(2+1) 3𝜋
∅2 = 𝜋 =
2 2
Low loop gain still results in negative eigen values, the dominant poles s2 yields sluggish response.
Increasing loop gain results in oscillatory response. The damping of the oscillatory term will however,
not decrease with increasing gain as the case in uncompensated system. So the system is stable.
Even for a small amplifier gain of KA, AVR step response is not satisfactory. Thus, we
must increase the relative stability by introducing a controller, which would add a
zero to the AVR open loop transfer function. The block diagram, of AVR with
feedback stability compensation is as shown in Fig.20. By proper adjustment of Ks
and Ts, a satisfactory response can be obtained.
Now ,
Types of SVC:
Saturated reactors [SR].
Thyristor Controlled Reactor [TCR].
Thyristor Switched Capacitor [TSC].
Thyristor Switched Reactor [TSR].
Thyristor Controlled Transformer [TCT].
Fixed Capacitor and Thyristor Controlled Reactor [FC – TCR].
Thyristor Switched Capacitor and Thyristor Controlled
Reactor [TSC – TCR].
Self or Line Commutated Converter [SCC / LCC].
Fixed Capacitor and Thyristor
Controlled Reactor [FC – TCR]:
The circuit diagrams of a FC – TCR, with switched filters
are as shown in figure. This arrangement provides discrete
leadings VARs from the capacitors and continuously lagging
VARs from thyristor controlled reactor. The capacitors are
used as tuned filters, as considerable harmonics are generated
by thyristor control. The steady state characteristics of a FC –
TCR is shown in figure. The control range is AB with a positive
slope, determine by the firing angle control.
TSC-TCR
Each thyristor switch is built up from two thyristor stacks
connected in anti-parallel. Each single phase thyristor switched
capacitor consists of the capacitor, thyristor switch and reactor
to limit the current through the thyristors and to prevent
resonance with the network as shown in figure.
The problem of achieving transient free switching ON of
the capacitor is overcome by keeping the capacitor charged to
the positive or negative peak value, when they are in the
stand by state. The switching on instinct is then selected at the
time when the network has its maximum or minimum value
and the same polarity as the capacitor voltage. Switching of the
capacitor is accomplished by separation of the firing pulses to
the anti-parallel thyristors so that the thyristors will block as
soon as the current becomes zero.
The capacitor will then remain charged to the positive or
negative peak voltage and be prepared for the new transient
free switching on.
The V-I characteristics is as shown in figure. A certain
short time overload capability id provided both in the
maximum inductive and capacitive regions. Voltage regulation
with a given slope can be achieved in the normal operating
range. The maximum capacitive current decreases linearly with
the system voltage and the SVC becomes a fixed capacitor
when the maximum capacitive output is reached.
The voltage support capability decreases with decrease
in system voltage.
22 K1 CO5
Bus voltage can be controlled. Improves system stability, voltage
stability. Reduces power oscillations. Minimize transmission loss.
What is Brushless Exciter
The exciter consists of an ―inverted‖ 3 phase synchronous generator,
23 that is 3-phase armature on the rotor and field on the stator. Its K1 CO5
armature voltage is rectified in thyristors mounted on the rotating
shaft and then fed directly into the main generator field.
What are the effects of generator loading in AVR loop?
Effects of generator loading in AVR loop is given below. Added load
does not change the basic features of the AVR loop; it will however
affect the values of both gain factor Kf and the field constant. High
loading will make the generator work at higher magnetic saturation
24 levels. This means smaller changes in |E| for incremental increases in K1 CO5
if, translating into the reduction of KF. The field time constant will
likewise decrease as generator loading closing the armature current
paths. This circumstance permits the formation of transient stator
currents the existence of which yields a lower effective field induction.
K
S.No Part B CO5
Level
7 K2 CO5
Part C
https://www.sciencedirect.com/science/article/abs/pii/S0378779620303011
Content beyond the syllabus
A new control design strategy for automatic voltage regulator in power system
https://www.sciencedirect.com/science/article/abs/pii/S0019057819305257
Assessment Schedule
Prescribed Text Books & Reference Books
TEXT BOOKS:
2. Allen. J. Wood and Bruce F. Wollen berg, ‗Power Generation, Operation and
Control‘, John Wiley & Sons, Inc., 2016.
3. Abhijit Chakrabarti and Sunita Halder, ‗Power System Analysis Operation and
Control‘, PHI learning Pvt. Ltd., New Delhi, Third Edition, 2010.
REFERENCES
1. Kothari D.P. and Nagrath I.J., ‗Power System Engineering‘, Tata McGraw-Hill
Education, Second Edition, 2008.
2. Hadi Saadat, ‗Power System Analysis‘, McGraw Hill Education Pvt. Ltd., New
Delhi, 21st reprint, 2010.
3. Kundur P., ‗Power System Stability and Control, McGraw Hill Education Pvt. Ltd.,
New Delhi, 10th reprint, 2010.
Mini project suggestions
Transformerless AVR
Disclaimer:
This document is confidential and intended solely for the educational purpose of RMK Group of
Educational Institutions. If you have received this document through email in error, please notify the
system manager. This document contains proprietary information and is intended only to the
respective group / learning community as intended. If you are not the addressee you should not
disseminate, distribute or copy through e-mail. Please notify the sender immediately by e-mail if you
have received this document by mistake and delete this document from your system. If you are not
the intended recipient you are notified that disclosing, copying, distributing or taking any action in
reliance on the contents of this information is strictly prohibited.
Please read this disclaimer before proceeding:
This document is confidential and intended solely for the educational purpose of
RMK Group of Educational Institutions. If you have received this document
through email in error, please notify the system manager. This document
contains proprietary information and is intended only to the respective group /
learning community as intended. If you are not the addressee you should not
disseminate, distribute or copy through e-mail. Please notify the sender
immediately by e-mail if you have received this document by mistake and delete
this document from your system. If you are not the intended recipient you are
notified that disclosing, copying, distributing or taking any action in reliance on
the contents of this information is strictly prohibited.
POWER SYSTEM OPERATION AND CONTROL
Department: EEE
2 Course objectives 6
3 Pre Requisites 7
4 Syllabus 8
5 Course outcomes 9
6 CO-PO/PSO Mapping 13
7 Lecture Plan 14
8 Activity based learning 15
9 Lecture Notes 16
10 Assignments 66
11 Part A Q & A 68
12 Part B 73
16 Assessment Schedule 79
SCADA and its application for real time operation and control of power systems
Prerequisites
CO2 Ability to analyse the control actions to be implemented on the system to meet
the minute-to-minute variation of system demand.
CO6 Ability to design SCADA and its application for real time operation.
PROGRAMME OUTCOMES
c. Come out with solutions for the complex problems and to design system
components or process that fulfill the particular needs taking into account public
health and safety and the social, cultural and environmental issues.
e. Form, select and apply relevant techniques, resources and Engineering and IT
tools for Engineering activities like electronic prototyping, modeling and control
of systems and also being conscious of the limitations.
10
PROGRAMME OUTCOMES
l. Recognize the need for self and life-long learning, keeping pace with
technological challenges in the broadest sense.
11
PROGRAM SPECIFIC OUTCOMES (PSOS)
• Use the modern tools for implementing the solutions to engineering problems that
can arise in the fields of Electrical, Electronics and Telecommunication Engineering
along with Information Technology Services.
11
CO-PO /PSO mapping
CO/ a b c d e f g h i j k l PS PS PS
PO, O O O
PSO 1 2 3
co1 - 2 - 3 3 - - - - - - - 3 - 3
co2 - 2 - 3 3 - - - - - - - 3 - 3
co3 - 2 - 3 3 - - - - - - - 3 - 3
co4 - 2 - 3 3 - - - - - - - 3 - 3
co5 - 2 - 3 3 - - - - - - - 3 - 3
co6 - 2 - 3 3 - - - - - - - 3 - 3
Lecture plan Unit IV
Sl Topic No Prop Actu Pertaining Taxon Mod
No of ose al dt CO omy e of
Peri d dt level deliv
ods ery
1 Statement of economic CO3 K2 PPT
dispatch problem
2 incremental cost curve CO3 K2 PPT
-–
Activity Based Learning
1. Matlab Code for the flowing Control methods are given Below.
Solve the problem Manually and Cross verify with Practical data
obtained through Matlab code
The fuel cost functions in Rs./hr for two thermal plants are given by
C = 420 + 9.2𝑃1 + 0.004𝑃12 , 100 ≤ 𝑃1 ≤ 200
C = 350 + 8.5𝑃2 + 0.0029𝑃22 , 150 ≤ 𝑃2 ≤ 500
where 𝑃1 , 𝑃2 are in MW and plant outputs are subjected to the
following limits. Determine the optimal scheduling of generation if
the total load is 640.82 MW. Estimate the value of λ = 12 Rs./MWh.
𝑃𝐿 𝑝𝑢 = 0.0346 𝑃12𝑝𝑢 + 0.00643 𝑃22 𝑝𝑢
Matlab Code:
https://docs.google.com/document/d/1LGhx4js0KweWC0iTuBxd1Au
6zfurRK8PxlIPEnjNW6o/edit?usp=sharing
2. Role play:
Economic Dispatch without losses
To convert the input–output curves into cost curves, the fuel input per
hour is multiplied with the cost of the fuel (expressed in Rs./million kCal)
𝐶𝑖 𝑃𝐺𝑖 = 𝐾 𝐹𝑖 𝑃𝐺𝑖
Here 𝐶𝑖 is the cost expressed in Rs/hr of producing energy in the generator unit i.
𝐹𝑖 𝑃𝐺𝑖 is the Fuel Energy input
The heat rate curve can be approximated why because the initial portion of curve
decrease, reaches minimum point and then increases.
𝑐′𝑖
𝐻𝑖 𝑃𝐺𝑖 = + 𝑏′𝑖 + 𝑎′𝑖 𝑃𝐺𝑖
𝑃𝐺𝑖
𝑐′𝑖
Input Energy Rate 𝐹𝑖 𝑃𝐺𝑖 = 𝑃𝐺𝑖 𝐻𝑖 (𝑃𝐺𝑖 ) = 𝑃𝐺𝑖 [ + 𝑏′𝑖 + 𝑎′𝑖 𝑃𝐺𝑖 ]
𝑃𝐺𝑖
The economic power system operation needs to satisfy the following types of constraints
1. Equality constraints
The sum of real-power generation of all the various units must always be equal to the total
real-power demand on the system.
PGi − PD = 0
I=1
The above equation is the real power balance equation when losses are neglected
2.Inequality constraints
Each generating unit should not operate above its rating or below some
minimum generation. This minimum value of real-power generation is determined from the
technical feasibility.
𝑃𝐺𝑖𝑚𝑖𝑛 < 𝑃𝐺𝑖 < 𝑃𝐺𝑖 𝑚𝑎𝑥
If a particular generator loading 𝑃𝐺𝑖 reaches the limit 𝑃𝐺𝑖𝑚𝑖𝑛 or 𝑃𝐺𝑖 𝑚𝑎𝑥 its loading from now
on fixed at this value and the balance is then shared between the remaining generators
Cost function
𝑅𝑠
Where 𝐶𝑖 = 𝐹𝑢𝑒𝑙 𝑐𝑜𝑠𝑡 𝑡𝑜 𝑢𝑛𝑖𝑡 𝑖, 𝐻𝑟
𝑅𝑠
𝐶𝑖 = 𝑇𝑜𝑡𝑎𝑙 𝐹𝑢𝑒𝑙 𝑐𝑜𝑠𝑡 ,
𝐻𝑟
Coordination Equation Without Loss
Consider a two bus system having generation and load connected
to the same bus
2
𝑚𝑖𝑛𝑖𝑚𝑖𝑧𝑒 𝐶 = 𝐶𝑖 𝑃𝐺𝑖
𝑖=1
Where C = operating cost
I = no of generator on the bus
Subject to H ( PG1 +PG2 + … … … + PG𝑁 )
𝑵
= 𝑷𝑫 − 𝑷𝑮𝒊
𝒊=𝟏
Using langrangian multiplier λ
Langrangian function C* = C + λH
𝑁 𝑵
∗
𝐿=𝐶 = 𝐶𝑖 𝑃𝐺𝑖 + λ [ 𝑷𝑫 − 𝑷𝑮𝒊 ]
𝑖=1 𝒊=𝟏
For minimum objective function differentiate above equation with respect to 𝑃𝐺𝑖 and equate
to zero
𝜕𝐶 ∗
=0
𝜕𝑃𝑔𝑖
𝜕𝐶 ∗ 𝜕𝐿 𝜕𝐶𝑖
= = +0 −λ
𝜕𝑃𝑔𝑖 𝜕𝑃𝑔𝑖 𝜕𝑃𝑔𝑖
𝜕𝐶𝑖
= λ For i = 1,2, … , 𝑁
𝜕𝑃𝑔𝑖
𝜕𝐶𝑖
Where is the incremental cost of unit i
𝜕𝑃𝑔𝑖
Economic Dispatch Without Loss
Solution of λ iteration method without loss (Algorithm)
Case (i) operating limits of power generation are not specified
Step 1 : Assign the initial values of λ or calculate using
𝑁 𝑏𝑖
𝑃𝐷 + 𝑖=1 2𝑎
𝑖
λ=
𝑁 1
𝑖=1 2𝑎
𝑖
Step 2: compute 𝑃𝑔𝑖 corresponding to λ using the equation
𝐶𝑖 𝑃𝐺𝑖 = 𝑎𝑃2 𝐺𝑖 + 𝑏 𝑃𝐺𝑖 + 𝑐𝑖
𝑑𝐶𝑖 (𝑃𝑔𝑖 )
Incremental cost (IC) = = 2𝑎𝑖 𝑃𝑔𝑖 + 𝑏𝑖 = λ
𝑑𝑃𝑔𝑖
λ − 𝑏𝑖
𝑃𝑔𝑖 =
2𝑎𝑖
Step 3: compute 𝒏
𝒊=𝟏 𝑷𝒈𝒊
The power balance equation is satisfied, then the optimum solution is obtained
otherwise go to next step.
Step 5:
𝑁
𝑖𝑓 𝑃𝑔𝑖 < 𝑃𝐷
𝑖=1
Assign λ + Δ λ (i.e.,) increment λ and go to step 2
𝑁
𝑖𝑓 𝑃𝑔𝑖 > 𝑃𝐷
𝑖=1
Assign λ - Δ λ (i.e.,) increment λ and go to step 2
Where
ΔP
Δ λ=
𝑁 1
𝑖=1 2𝑎
𝑖
Δ 𝑃 is change in demand
Case (ii) operating limits of power generation are specified
Step 1 : Assign the initial values of λ or calculate using
𝑁 𝑏𝑖
𝑃𝐷 + 𝑖=1 2𝑎
𝑖
λ=
𝑁 1
𝑖=1 2𝑎
𝑖
Step 2: compute 𝑃𝑔𝑖 corresponding to λ using the equation
λ − 𝑏𝑖
𝑃𝑔𝑖 =
2𝑎𝑖
And go to step 6
EDC neglecting losses flowchart
1. The fuel cost two units are given by 𝐹1 = 1.6 + 25𝑃𝑔1 + 0.1 𝑃2𝑔1 and 𝐹2 = 2.1 +
32𝑃𝑔2 + 0.1 𝑃2𝑔2 if the demand of the generators are 250 MW. Find the economic
load scheduling of two units.
𝑏𝑖
𝑃𝐷 + 𝑁 𝑖=1 2𝑎
𝑖
λ=
𝑁 1
𝑖=1 2𝑎
𝑖
25 32
250 + 0.2 + 0.2
= = 53.5
1 1
0.2 + 0.2
λ − 𝑏1 53.5 − 25
𝑃𝑔1 = = = 142.5 𝑀𝑊
2𝑎1 0.2
λ − 𝑏2
𝑃𝑔2 = = 107.5 𝑀𝑊
2𝑎2
𝑑𝐹1 𝑅𝑠
(𝐼𝐶)1 = = 0.14𝑃𝑔1 + 21
𝑑𝑃𝑔1 𝑀𝑊𝑟
𝑑𝐹2 𝑅𝑠
(𝐼𝐶)2 = = 0.225𝑃𝑔2 + 16.5
𝑑𝑃𝑔2 𝑀𝑊𝑟
For Economic Dispatch, find the plant λ when the demand equals (i) 45 MW (ii) 125
MW and (iii) 250 MW
(i) When demand = 45 MW
𝑁 𝑏𝑖
𝑃𝐷 + 𝑖=1 2𝑎
𝑖
λ=
𝑁 1
𝑖=1 2𝑎
𝑖
21 16.5
45 + +
0.14 0.225
= = 23.15
1 1
+
0.14 0.225
λ − 𝑏1 23.15 − 21
𝑃𝑔1 = = = 15.41 𝑀𝑊
2𝑎1 0.14
The lower limit value of generation is 20 MW but the generation of unit 1 is 15.41
MW. Since it violates the lower limit we can fix 𝑃𝑔1 =𝑃𝑔1 𝑚𝑖𝑛 = 20 MW
Therefore
𝑃𝑔1 = 20 𝑀𝑊
𝑃𝑔2 = 45 − 20 = 25 𝑀𝑊
(ii) When demand = 125 MW
𝑁 𝑏𝑖
𝑃𝐷 + 𝑖=1 2𝑎
𝑖
λ=
𝑁 1
𝑖=1 2𝑎
𝑖
21 16.5
125 + +
0.14 0.225
= = 30.0616
1 1
+
0.14 0.225
λ − 𝑏1 30.0616 − 21
𝑃𝑔1 = = = 67.726 𝑀𝑊
2𝑎1 0.14
λ − 𝑏2 30.0616 − 16.5
𝑃𝑔2 = = = 60.274 𝑀𝑊
2𝑎2 0.225
Since the generation of unit 1 and unit 2 are within the limits and generation put
together will give a value of 125 MW. So the optimum conditions are satisfied
(ii) When demand = 250 MW
𝑁 𝑏𝑖
𝑃𝐷 + 𝑖=1 2𝑎
𝑖
λ=
𝑁 1
𝑖=1 2𝑎
𝑖
21 16.5
250 + +
0.14 0.225
= = 40.849
1 1
+
0.14 0.225
λ − 𝑏1 40.849 − 21
𝑃𝑔1 = = = 141.78 𝑀𝑊
2𝑎1 0.14
λ − 𝑏2 40.849 − 16.5
𝑃𝑔2 = = = 108.22 𝑀𝑊
2𝑎2 0.225
141.78>135 MW, 𝑃𝑔1 >𝑃𝑔1 𝑚𝑎𝑥 therefore fix 𝑃𝑔1 = 𝑃𝑔1 𝑚𝑎𝑥 = 135 MW
λ − 𝑏2 6.0 − 5.5
𝑃2 = = = 41. 667 𝑀𝑊
2𝑎2 2 (0.006)
λ − 𝑏3 6.0 − 5.3
𝑃3 = = = 11.111 𝑀𝑊
2𝑎3 2 (0.009)
Since 𝑃𝐷 = 975 𝑀𝑊, the error ΔP
ΔP= 975 – (87.50 + 41.667 + 11.111) = 834.777
ΔP
Δ λ=
𝑁 1
𝑖=1 2𝑎
𝑖
834.777
=
1 1 1
+ +
2 (0.004) 2 (0.006) 2 (0.009)
834.777
== 3.1632
263.888
Therefore the new value of λ
λ𝑛𝑒𝑤 = 6.0 + 3.1632 = 9.1632
Continue the process for second iteration
λ − 𝑏1 9.1632 − 5.3
𝑃1 = = = 482.8947 𝑀𝑊
2𝑎1 2 (0.004)
λ − 𝑏2 9.1632 − 5.5
𝑃2 = = = 305.2632 𝑀𝑊
2𝑎2 2 (0.006)
λ − 𝑏3 9.1632 − 5.3
𝑃3 = = = 186.8421 𝑀𝑊
2𝑎3 2 (0.009)
32.8947
Δλ = = 0.2368
1 1
+
2 (0.006) 2 (0.009)
λ − 𝑏2 9.4 − 5.5
𝑃2 = = = 325 𝑀𝑊
2𝑎2 2 (0.006)
λ − 𝑏3 9.4 − 5.3
𝑃3 = = = 200 𝑀𝑊
2𝑎3 2 (0.009)
ΔP= 975 – (450 +325 + 200) = 0.0
The equality constraint is met and 𝑃2 and 𝑃3 are within their
limits, thus the optimal dispatch is
𝑃1 =450 MW
𝑃2 = 325 MW
𝑃3 = 200 𝑀𝑊
λ = 9.4 $/MWh
And the total fuel cost is
𝐶𝑡 = 500 + 5.3(450) + 0.004(4502 ) + 400 + 5.5(325) + 0.006(3252 ) +
200 + 5.8(200) + 0. . 009 (2002 ) = 8,236.25 $/h
Formulation of Optimum Dispatch Problem (Including
Losses)
In case of an urban area where the load density is very high and the
transmission distances are very small, the transmission loss could be neglected and
the optimum strategy of generation could be based on the equal incremental
production cost. If the energy is to be transported over relatively larger distances
with low load density, the transmission losses, in some cases, may amount to about
20–30% of the total load; hence, it is essential to take these losses into account
when formulating an economic load dispatch problem
In a practical system, a large amount of power is being transmitted
through the transmission network, which causes power losses in the network (𝑃𝐿 )
as shown in Fig In finding an optimal solution for economic scheduling problem
(allocation of total load among the generating units), it is more realistic to consider
the transmission line losses, which are about 5–15% of the total generation.
In general, the condition for optimality, when losses are considered, is
different. Equal incremental fuel costs (IFCs) for all generating units will not give an
optimal solution.
𝑪= 𝐶𝑖 (PGi )
I=1
Equality constraint
The real-power balance equation, i.e., total real-power generations minus
the total losses should be equal to the real-power demand:
N
PGi − P𝐿 = 𝑃𝐷 (𝑜𝑟)
I=1
PGi − P𝐿 − 𝑃𝐷 = 0
I=1
Inequality constraints:
Always there will be upper and lower limits for real and reactive-power
generation at each of the stations. The inequality constraints are represented
𝑃𝐺𝑖𝑚𝑖𝑛 < 𝑃𝐺𝑖 < 𝑃𝐺𝑖 𝑚𝑎𝑥
Coordination Equation With Loss
Minimize the cost Function
N
𝑪= 𝐶𝑖 (PGi )
I=1
Subject to the constraint
N N
𝑃𝐷𝑖 + P𝐿 = PGi
I=1 I=1
N N
𝑃𝐷𝑖 + P𝐿 − PGi = 0
I=1 I=1
Where P𝐿 is transmission loss
Using langrangian multiplier λ
Langrangian function C* = C + λH
𝑁 N N
∗
𝐿=𝐶 = 𝐶𝑖 𝑃𝐺𝑖 + λ [ 𝑃𝐷𝑖 + P𝐿 − PGi ]
𝑖=1 I=1 I=1
For minimum objective function differentiate above equation with respect to 𝑃𝐺𝑖 and
equate to zero
𝜕𝐶 ∗
=0
𝜕𝑃𝑔𝑖
𝜕𝐶 ∗ 𝜕𝐶 𝜕𝑃𝐿
= + λ −λ=0
𝜕𝑃𝑔𝑖 𝜕𝑃𝑔𝑖 𝜕𝑃𝑔𝑖
𝜕𝐶 𝜕𝑃𝐿
= λ [1− ]
𝜕𝑃𝑔𝑖 𝜕𝑃𝑔𝑖
𝜕𝑃𝐿
= (𝐼𝑇𝐿)𝑖
𝜕𝑃𝑔𝑖
(𝐼𝐶)𝑖
λ= = 𝐿𝑖 (𝐼𝐶)𝑖
1 − (𝐼𝑇𝐿)𝑖
1
λ=
1 − (𝐼𝑇𝐿)𝑖
𝑁 𝑏𝑖
𝑃𝐷 + 𝑖=1 2𝑎
𝑖
λ=
𝑁 1
𝑖=1 2𝑎
𝑖
Step 2: solve for 𝑷𝒈𝒊 using
𝑏𝑖 𝑁
1− −2 𝑗≠𝑖 𝐵𝑖𝑗
𝜆
𝑗=1
𝑃𝑔𝑖 =
2𝑎𝑖
+ 2𝐵𝑖𝑖
𝜆
𝑁 𝑁
𝑃𝐷 + 𝑃𝐿 − PGi = 0
I=1
Value of generation PGi gives the optimum generation otherwise go to next step.
Step 6: Increase λ by ∆λ if 𝑃𝐷 + 𝑃𝐿 − N
I=1 PGi < 0, or
decrease λ by ∆λ if 𝑃𝐷 + 𝑃𝐿 − N
I=1 PGi > 0, or
2 2 2
𝑃1 𝑃2 𝑃3
𝑃𝐿 = 0.0218 + 0.0228 + 0.0179 𝑥 100
100 100 100
λ − 𝑏𝑖
𝑃𝐺𝑖 =
2(𝑎𝑖 + λ𝐵𝑖𝑖 )
8 −7
𝑃𝐺1 = = 51.3136 𝑀𝑊
2(0.008 + 8 𝑥 0.000218)
8 − 6.3
𝑃𝐺2 = = 78.5292 𝑀𝑊
2(0.009 + 8 𝑥 0.000228)
8 − 6.8
𝑃𝐺3 = = 71.1575 𝑀𝑊
2(0.007 + 8 𝑥 0.000179)
The real power loss is
𝑃𝐿 = 0.000218(51.3136)2 +0.000228(78.5292)2 +0.000179 (71.1575)2 = 2.886
Since 𝑃𝐷 = 150 MW the error ΔP is
ΔP = 150+2.8864 – (51.3136+78.5292+71.1575) = - 48.1139
Since generation is more than the demand we need to decrement the value of Lambda
λ = λ − Δλ
Δλ
∆λ =
𝑁 𝜕𝑃𝑖
𝑖=1 𝜕λ
𝑁 𝑁
𝜕𝑃𝑖 𝑎𝑖 + 𝐵𝑖𝑖 𝑏𝑖
=
𝜕λ 2(𝑎𝑖 + λ𝐵𝑖𝑖 )2
𝑖=1 𝑖=1
3
𝜕𝑃𝑖 0.008 + 0.000218 𝑥 7.0 0.009 + 0.000228 𝑥 6.3
= +
𝜕λ 2(0.008 + 8.0 𝑥 0.000218)2 2(0.009 + 8.0 𝑥 0.000228)2
𝑖=1
0.007 + 0.000179 𝑥 6.8
+ = 152.4924
2(0.007 + 8.0 𝑥 0.000179)2
Δλ −48.1139
∆λ = = = −0.31552
𝑁 𝜕𝑃𝑖 152.4924
𝑖=1 𝜕λ
7.6845 − 6.3
𝑃𝐺2 = = 64.3821 𝑀𝑊
2(0.009 + 7.6845 𝑥 0.000228)
7.6845 − 6.8
𝑃𝐺3 = = 52.8075 𝑀𝑊
2(0.007 + 7.6845 𝑥 0.000179)
The real power loss is
𝑃𝐿 = 0.000218(35.3728)2 +0.000228(64.3821)2 +0.000179 (52.8075)2 = 1.717
the error ΔP is
ΔP = 150+1.717 – (35.3728 + 64.3821 + 52.8075 ) = - 0.8395
Since generation is more than the demand we need to decrement the value of Lambda
λ = λ − Δλ
Δλ
∆λ =
𝑁 𝜕𝑃𝑖
𝑖=1 𝜕λ
3
𝜕𝑃𝑖 0.008 + 0.000218 𝑥 7.0 0.009 + 0.000228 𝑥 6.3
= +
𝜕λ 2(0.008 + 7.684 𝑥 0.000218)2 2(0.009 + 7.684 𝑥 0.000228)2
𝑖=1
0.007 + 0.000179 𝑥 6.8
+ = 154.588
2(0.007 + 7.684 𝑥 0.000179)2
Δλ −0.8395
∆λ = = = −0.005431
𝑁 𝜕𝑃𝑖 154.588
𝑖=1 𝜕λ
7.679 − 6.3
𝑃𝐺2 = = 64.1369 𝑀𝑊
2(0.009 + 7.679 𝑥 0.000228)
7.679 − 6.8
𝑃𝐺3 = = 52.4834 𝑀𝑊
2(0.007 + 7.679 𝑥 0.000179)
The real power loss is
𝑃𝐿 = 0.000218(35.0965)2 +0.000228(64.1369)2 +0.000179 (52.4834)2 = 1.699
the error ΔP is
ΔP = 150+1.699– (35.0965+64.13691 +52.4834) = -0.01742
3
𝜕𝑃𝑖 0.008 + 0.000218 𝑥 7.0 0.009 + 0.000228 𝑥 6.3
= +
𝜕λ 2(0.008 + 7.679 𝑥 0.000218)2 2(0.009 + 7.679 𝑥 0.000228)2
𝑖=1
0.007 + 0.000179 𝑥 6.8
+ = 154.624
2(0.007 + 7.679 𝑥 0.000179)2
Δλ −0.01742
∆λ = = = 0 − 0.001127
𝑁 𝜕𝑃𝑖 154.624
𝑖=1 𝜕λ
7.6789 − 7
𝑃𝐺1 = = 35.0907 𝑀𝑊
2(0.008 + 7.6789 𝑥 0.000218)
7.6789 − 6.3
𝑃𝐺2 = = 64.1317 𝑀𝑊
2(0.009 + 7.6789 𝑥 0.000228)
7.6789 − 6.8
𝑃𝐺3 = = 52.4767 𝑀𝑊
2(0.007 + 7.6789 𝑥 0.000179)
The real power loss is
𝐹𝑖 = 𝑎𝑃2 𝐺𝑖 + 𝑏 𝑃𝐺𝑖 + 𝑐𝑖
∆𝐹𝑖
λ𝑖 = = 2𝑎𝑖 𝑃𝑔𝑖 + 𝑏𝑖
∆𝑃𝐺𝑖
∆λ𝑖
= 𝐹𝑖′′ = 2𝑎𝑖
∆𝑃𝐺𝑖
Δλ Δλ
∆𝑃𝐺2 = ′′ … … . ∆𝑃𝐺𝑁 =
𝐹𝑖 𝐹𝑖′′
Let 𝑃𝐷 be the total demand on the generation
The total load in generation = change in total system demand
𝑃𝐷 = 𝑃𝑙𝑜𝑎𝑑 + 𝑃𝐿
Δλ Δλ Δλ
= ′′ + ′′ + ⋯ + ′′
𝐹1 𝐹2 𝐹𝑁
𝑁
1
= Δλ
𝐹𝑖′′
𝑖=1
Participation factor for each unit
1
∆𝑃𝐺𝑖 𝐹𝑖′′
=
∆𝑃𝐷 𝑁 1
𝑖=1 𝐹 ′′
𝑖
Suppose 𝑃𝐷 increases to 𝑃𝐷 + ∆𝑃𝐷 . The new value of generation is calculated using
∆𝑃𝐺𝑖
𝑃𝑛𝑒𝑤,𝑖 = 𝑃𝑏𝑎𝑠𝑒 𝑖 + ∆𝑃𝐷
∆𝑃𝐷
𝑃𝑏𝑎𝑠𝑒 𝑖 = Old value of generation
Advantage of using Participation Factor
• Computer implementation of economic dispatch is straight forward
• Execution time for the economic dispatch is short
• It always gives consistent answers when units reach limits
• It gives linear incremental cost functions or have non convex cost curves
Problem:
The input – output characteristics of three units are
𝐹1 = 940 + 5.46 𝑃1 + 0.0016 𝑃21
𝐹2 = 820 + 5.35 𝑃2 + 0.0019 𝑃2 2
𝐹3 = 99 + 5.65 𝑃3 + 0.0032 𝑃2 3
Total load is 600 MW. Use participation factor method to calculate the dispatch for a
load is reduced to 550 MW
We know 𝑃1 + 𝑃2 + 𝑃3 = 600 (𝐴)
𝑑𝐹1
𝐹1′ = = 5.46 + 0.0032𝑃1 = λ (1)
𝑑𝑃1
𝑑𝐹2
𝐹2′ = = 5.35 + 0.0038𝑃2 = λ (2)
𝑑𝑃2
𝑑𝐹3
𝐹3′ = = 5.65 + 0.0064𝑃3 = λ (3)
𝑑𝑃3
Solve (1) and (2)
5.46 + 0.0032𝑃1 = 5.35 + 0.0038𝑃2
𝑃2 = 244.92 𝑀𝑊
Substitute the value of 𝑃2 in equation (5)
1
∆𝑃𝑖 𝐹𝑖′′
=
∆𝑃𝐷 3 1
𝑖=1 𝐹 ′′
𝑖
1 1 1
∆𝑃1 𝐹1′′ 𝐹1′′ 0.0032
= == = = 0.43
∆𝑃𝐷 3 1 1 1 1 1 1 1
𝑖=1 𝐹 ′′ + + + +
1 𝐹1′′ 𝐹2′′ 𝐹3′′ 0.0032 0.0038 0.0064
1 1 1
∆𝑃2 𝐹2′′ 𝐹2′′ 0.0038
= == = = 0.3595
∆𝑃𝐷 3 1 1 1 1 1 1 1
𝑖=1 𝐹 ′′ + + + +
2 𝐹1′′ 𝐹2′′ 𝐹3′′ 0.0032 0.0038 0.0064
1 1 1
∆𝑃3 𝐹3′′ 𝐹3′′ 0.0064
= == = = 0.2135
∆𝑃𝐷 3 1 1 1 1 1 1 1
𝑖=1 𝐹 ′′ + + + +
1 𝐹1′′ 𝐹2′′ 𝐹3′′ 0.0032 0.0038 0.0064
∆𝑃1
𝑃𝑛𝑒𝑤,1 = 𝑃𝑏𝑎𝑠𝑒 1 + ∆𝑃𝐷 = 254.67 + 0.43 −50 = 234.97
∆𝑃𝐷
∆𝑃2
𝑃𝑛𝑒𝑤,2 = 𝑃𝑏𝑎𝑠𝑒 2 + ∆𝑃𝐷 = 244.92 + 0.3595 −50 = 226.945
∆𝑃𝐷
∆𝑃3
𝑃𝑛𝑒𝑤,3 = 𝑃𝑏𝑎𝑠𝑒 3 + ∆𝑃𝐷 = 98.6 + 0.2135 −50 = 87.925
∆𝑃𝐷
UNIT COMMITMENT
Introduction:
In power systems, demand variation is associated with human activities. Load is always light
during night hours and it starts increasing right from morning and usually readies its peak
level in the evening, and again falls during late evening period. The demand is also affected
during weekends as well as by weather. Hence, many methods have been developed for load
forecasting. The methods for load forecasting can predict the load for period varying from as
small as few seconds to days. Based on these load forecasts, the usual practice is to prepare
a commitment schedule of start-up and shut-down of units. The commission of a generating
unit means to bring it to speed, synchronize it to the system and then connect it to the
system so that it can deliver the load reliably.
In the early stages, the main criteria of unit commitment were efficiency of units. Units used
to be ordered as per efficiencies. The most efficient unit used to be committed first and then
the next unit, if necessary to meet the load demand, from priority list used to be committed.
Soon, it was realized that optimum unit commitment may be obtained using input-output
characteristics, termed as cost curves; and today all commitment techniques are based on
these cost curves. Classically, unit commitment is the determination of optimal schedule and
generation level of each unit over a specific time horizon. Time horizon may be hours or a
week.
Baldwin (Scientist name) was the first to report the study of economic shut down of
generating units. Since then, many optimization techniques have been used to obtain solution
of unit commitment problem prominent among these are dynamic programming, branch and
bound, Lagrangian relaxation.
The unit commitment problem (UC) in electrical power production is a large family
of mathematical optimization problems where the production of a set of electrical generators
is coordinated in order to achieve some common target, usually either match the energy
demand at minimum cost or maximize revenues from energy production.
The total load of the power system is not constant but varies throughout the day and
reaches a different peak value from one day to another. It follows a particular hourly
load cycle over a day. There will be different discrete load levels at each period.
Due to the above reason, it is not advisable to run all available units all the time, and it is
necessary to decide in advance which generators are to start up, when to connect them
to the network, the sequence in which the operating units should be shut down, and for
how long. The computational procedure for making such decisions is called unit
commitment (UC), and a unit when scheduled for connection to the system is said to
be committed.
The problem of UC is nothing but to determine the units that should operate for a
particular load. To ‗commit‘ a generating unit is to ‗turn it on‘, i.e., to bring it up to speed,
synchronize it to the system, and connect it, so that it can deliver power to the
network.
Economic dispatch economically distributes the actual system load as it rises to the
various units that are already on-line. However, the UC problem plans for the best set of
units to be available to supply the predicted or forecast load of the system over a future
time period.
NEED FOR UC
The plant commitment and unit-ordering schedules extend the period of optimization
from a few minutes to several hours.
Weekly pattern scan be developed from daily schedules. Likewise, monthly, seasonal, and
annual schedules can be prepared by taking into consideration the repetitive nature of
the load demand and seasonal variations.
A great deal of money can be saved by turning off the units when they are not needed
for the time. If the operation of the system is to be optimized, the UC schedules are
required for economically committing units in plant to service with the time at which
individual units should be taken out from or returned to service.
This problem is of importance for scheduling thermal units in a thermal plant; as for
other types of generation such as hydro their aggregate costs (such as start-up costs,
operating fuel costs, and shutdown costs) are negligible so that the iron-off status is not
important.
CONSTRAINTS IN UC
Spinning reserve
It is the term used to describe the total amount of generation available from all
Synchronized units on the system minus the present load and losses being supplied.
Here, the synchronized units on the system may be named units spinning on the
system.
Static reserve:
To meet the load demand under contingency of failure of a generator or its derating
caused by minor defect, it is made so that the total installed capacity of the
generating station greater the yearly peak load by certain margin. This is called static
reserve.
Thermal units require crew to operate them especially where turned on or off. A
thermal unit may undergo only gradual temperature changes and this translates into
increased number of hours required to bring it on line. Therefore the various
constraints that arise one.
a) Minimum Up time
c) Crew Constraints
If a plant consists of 2 or more units, they cannot be turned on at the same time
since there are not enough staff to attend all the units at a time.
d) Start Up Cost
A start-up cost is incurred when a generator is put into operation. The cost is
dependent on how long the unit has been inactive. While the start-up cost function
is nonlinear, it can be discretized into hourly periods, giving a stepwise function.
The start-up cost may vary from a maximum ‗cold start‘ value to a very small value
if the unit was only turned off recently, and it is still relatively close to the operating
temperature.
The first approach (cooling) allows the unit‘s boiler to cool down and then heat back
up to a operating temperature in time for a scheduled turn-on.
The second approach (banking) requires that sufficient energy be input to the boiler
to just maintain the operating temperature.
OTHER CONSTRAINTS
In addition to system and unit constraints, there are other constraints that need to
be considered in the UC decision. They are described as follows:
A. Fuel Constraints:
Due to the contracts with fuel suppliers, some power plants may have limited fuel or
may need to burn a specified amount of fuel in a given time. A system in which
some units have limited fuel, or else have constraints that require them to burn a
specified amount of fuel in a given time, presents a most challenging unit
commitment problem.
Some units are given a must-run status during certain times of the year for reason
of voltage support on the transmission network or for such purposes as supply of
steam for uses outside the steam plant itself. The must run units include units in
forward contracts, units in exercised call/put options, RMR units, nuclear power
plants, some cogeneration units, and units with renewable resources such as wind-
turbine units and some hydro power plants.
C. Must-off Units:
Some units are required to be off-line due to maintenance schedule or forced outage.
These units can be excluded from the UC decision.
D. Emission Constraints:
There are some emissions like sulphur dioxide ( SO2 ), nitrogen oxides (NOx), carbon
dioxide ( CO2 ), and mercury which are produced by fossil-fuelled thermal power
plants. The amount of emission depends on various factors such as the type of fuel
used, level of generation output, and the efficiency of the unit. The production cost
minimization may need to be compromised in order to have the generation schedule
that meets the emission constraints.
The Unit commitment problems are very difficult to solve, for that
consider the following situation,
1. A loading pattern for the M periods using load curve must be established.
2. Number of units should be committed and dispatched to meet out the load.
3. The load period and number of units should supply the individual loads and any
combination of loads.
There are many classical approaches have been developed and implemented
successfully. Some of the approaches are
3. Dynamic Programming
4. Lagrange Relaxation
6. Benders decomposition
1. Genetic Algorithms
4. Simulated annealing
Which gives (2N -1) combinations if we consider for M periods, then the
number of combination becomes (2N -1)M
Where,
N – Number of units,
M – Total time period.
If number of units and periods increases, then the combination becomes too
high.
50 ≤ PG2 ≤ 300 MW
S.No U-1 U-2 U-3 Max. Min. PG1 PG2 PG3 Sol. Cost
in Rs.
1 0 0 0 - - - - - INF -
2 0 0 1 500 150 INF
3 0 1 0 300 50 INF
4 0 1 1 800 200 - 300 500 F 9200
5 1 0 0 400 100 INF -
6 1 0 1 900 250 400 400 F 8540
7 1 1 0 700 150 INF
8627.
8 1 1 1 1200 300 335 151 314 F
04
PD = 800 MW
ג − 𝑏2 14 − 8
PG2 = = = 300 MW
2𝑎2 2 𝑥 0.01
ג − 𝑏3 14 − 6
PG3 = = = 500 MW
2𝑎3 2 𝑥 0.008
𝑏𝑖 7 6
𝑃𝐷 + 800 + +
2𝑎𝑖
=ג 1 = 1
2𝑥0.006
1
2𝑥0.008
= 12.057
+
2𝑎𝑖 2𝑥0.006 2𝑥0.008
ג − 𝑏1 12.057 − 7
PG1 = 2𝑎1
= 2 𝑥 0.006
= 421.416 > PG1max
𝑏𝑖 7 8 6
𝑃𝐷 + 800 + + +
2𝑎𝑖
=ג 1 = 1
2𝑥0.006
1
2𝑥0.01
1
2 𝑥 0.008
= 11.02
+ +
2𝑎𝑖 2𝑥0.006 2𝑥0.008 2 𝑥 0.01
ג − 𝑏1 11.02 − 7
PG1 = = = 335 MW
2𝑎1 2 𝑥 0.006
ג − 𝑏2 11.02 − 8
PG2 = = = 151 MW
2𝑎2 2 𝑥 0.01
ג − 𝑏3 11.02 − 6
PG3 = = = 314 MW
2𝑎3 2 𝑥 0.008
Ft = F1 + F2 + F3 = Rs.8627.04
Result :
Total fuel cost for the 6th case is less than that of the other cases of feasible
solution. When the system load level is 800 MW, it is preferable to Keep
units 1 and 3 running.
Priority List Method (Using full load average Production cost
FLAPC)
Priority list method is the simplest unit commitment solution method which consists of
creating a priority list of units.
The priority list can be obtained by noting the full-load average production cost of each
unit.
Full load average Production cost = { Net heat rate at full load} x Fuel cost
𝐶𝑖 (𝑃𝐺𝑖 )
FLAPC = 𝑃𝐺𝑖
Assumptions
Unit input – output characteristics are linear between zero output and full load.
Determine the full load average production cost for each units.
Assume load is dropping or decreasing, determine whether dropping the next unit will
supply generation and spinning reserve.
If not, continue as it is,
Determine the number of hours H, before the unit will be needed again.
Check H < Minimum shut down time
1. Sum of hourly production costs for the next H hours with the unit up.
2. Recalculate the same for the unit down + start-up cost for either cooling or
banking. If the second case is less expensive, the unit should be on.
Merits
Complication reduced.
Demerits
Determine Priority list using full load average production cost for the data
given.
Solution :
𝐻1 (𝑃𝐺1 )
FLAPC1 = K1 x | PGi = PGi max
𝑃𝐺𝑖
𝐻2 (𝑃𝐺2 )
FLAPC2 = K2 x | PG2 = PG2 max
𝑃𝐺2
𝐻3 (𝑃𝐺3 )
FLAPC3 = K3 x | PG3 = PG3 max
𝑃𝐺3
Unit Commitment:
Result :
All the three units would be held on until the load reached 900MW. Units 1 and 3
would be held on until the load reached 500MW, then unit 1 would be dropped.
Dynamic Programming Method
Advantages
Priority 1 unit
Unit input-output characteristics are linear between 0 output and full load
Load shedding
DC line flow.
Assumptions:
Total number of units available, their individual cost characteristics and the load
cycle on the station are assumed priori(previously)
A state consists of an array of units with specified units operating and the rest off-
line.
The start-up cost of a unit is independent of the time it has been off-line(i.e., fixed
amount).
There is a strict priority order and in each interval a specified minimum amount of
capacity must be operating.
Advantages
Algorithm to run forward in time from the initial hour to the final hour.
Algorithm
Conversely, one could set up the algorithm to run forward in time from the
initial hour to the final hour.
The initial conditions are easily specified and the computations can go forward in
time as long as required.
The recursive algorithm to compute the minimum cost in hour K with combination
Where
Fcost(K.I) = R (K,I)
State (K, 1) is the Zth combination in hour K. For the forward dynamic
programming approach, we define a strategy as the transition, or path, from one
state at a given hour to a state at the next hour.
Note that two new variables, X and N, have been introduced in Figure.
These variables allow control of the computational effort (see below Figure).For
complete enumeration, the maximum number of the value of X or N is 2𝑁 – 1
Fig.1 Dynamic programming algorithm
Flow chart
1. Incremental heat rate curves, for thermal generating units, are used to
determine the:
1. Fuel cost in rupees per hour.
2. Values at which the units should be loaded to result in minimum fuel costs.
3. Cost per unit of electrical output.
4. Heat produced per hour.
2.When generating units are loaded to equal incremental costs, it results in:
1. Minimum fuel costs.
2. Fuel costs are at a maximum.
3. Fuel costs are not affected.
4. Maximum loading of generating units
3.Economic operation of power system is:
1. Unit commitment.
2. Load scheduling.
3. Controlling of voltage and its magnitude.
4. Both (a) and (b).
4.Lagrangian multiplier method converts a non-linear constrained optimization
problem into _____ non-linear optimization
problem.
1. Gradient.
2. Linear.
3. Unconstrained.
4. All of these.
5.Unit of heat rate curve is _____.
1. Million kCal/hr.
2. Rs.-hr.
3. Rs./MWh.
4. Rs./hr.
6.Power balance equation is _____ constraint.
1. Equality.
2. Inequality.
3. Security constraints.
4. Branch transfer capacity constraint.
7.Cost curves can be obtained by:
1. Multiply the fuel input with cost of fuel.
2. Subtract the fuel input with cost of fuel.
3. Add the fuel input with cost of fuel.
4. None of these.
8.The curve obtained by considering the change in cost of generation to change in
real-power generation at various points is:
1. Fuel cost curve.
2. Input–output curve.
3. Incremental cost curve.
4. All of these.
9.The optimization problem is:
1. To allocate total load demand among various units such that the cost of
generation is maintained constant.
2. To allocate total load demand among various units such that the cost of
generation is minimized.
3. To allocate total load demand among various units such that the cost of
generation is enormously increased.
4. To allocate total load demand among various units such that there is no effect
with cost of generation.
10. If the real-power inequality constraints are violated for any generator, then:
1. It is tied to the corresponding limit and the rest of the load is economically
distributed among the remaining units.
2. It is tied to the corresponding limit and the total load is economically distributed
among all the units.
3. It is not considered and the total load is economically distributed among all the
units.
4. Any of the above methods
11. In the economic operation of a power system, the effect of increased penalty
factor between a generating plant and system
load center is to:
1. Decrease the load on the generating plant.
2. Increase the load on the plant.
3. Hold the plant load constant.
4. Decrease the load first and then increase
12.Economic dispatch is done first by ___________ and then by___________.
1. Unit commitment and then load scheduling.
2. Load scheduling and then unit commitment.
3. Either (a) or (b).
4. Unit commitment and load frequency control.
13. Transmission losses are about:
1. 50% of the total generation.
2. 100% of the total generation.
3. 5–15% of the total generation.
4. None of these.
14.The condition for optimality with consideration of transmission loss is:
1. The incremental fuel costs in Rs./hr of all the units must be the same.
2. The incremental fuel costs in Rs./hr of all the units must be the same.
3. The incremental transmission losses in Rs./MWh of all the units must be the
same.
4. The incremental fuel cost of each multiplied by its penalty factor must be the
same for all plants.
15.Transmission loss is:
1. A function of real-power generation.
2. Independent of real-power generation.
3. A function of reactive-power generation.
4. A function of bus voltage magnitude and its angle.
16. In solving optimization problem with transmission loss consideration, the
condition for optimality is obtained as:
1. The IC of all the plants must be the same.
2. The IC of each plant multiplied with its penalty factor must be the same for all the
plants.
3. The IC of each plant divided by its penalty factor must be the same for all the
plants.
4. The IC of each plant subtracted from its penalty factor must be the same for all
the plants.
Assignments
1. Determine Priority list using full load average production cost for the data given
2. Obtain the optimum unit commitment using the enumeration technique or brute
force technique for the power demand of 700 MW. The fuel cost equations are as
follows:
𝑑𝐶2
= 0.08 𝑃𝑔2 + 16 𝑅𝑠/𝑀𝑊
𝑑𝑃2
The loss coefficients are given as 𝑩11 = 0.0015/MW, 𝑩12 = − 0.0004/MW, and 𝑩22 =
0.0032/MW for λ = 25 Rs./MWh. Find the real-power generations, total load
demand, and the transmission power loss.
7. The cost curves of two plants are
C = 0.05𝑃𝑔1
2
+ 20𝑃𝑔1 + 150 Rs./hr
C = 0.05 𝑃𝑔2
2
+ 15𝑃𝑔2 + 180 Rs./hr
The loss coefficient for the above system is given as 𝑩11 = 0.0015/MW, 𝑩12 = –
0.0004/MW, and 𝑩22 = 0.0032/MW. Determine the economical generation
scheduling corresponding to λ = 25 Rs./MWh and the corresponding system load
that can be met with. If the total load connected to the system is 120 MW taking
4% change in the value of λ, what should be the value of λ in the next iteration?
Part A (Q & A)
K
S.No Part A (Q & A) COs
Level
What is an incremental fuel cost and what are its units?
Incremental fuel cost is the cost of the rate of increase of fuel input
1 with the increase in power input. Its unit is Rs./MWh. K1 CO3
Write the condition for optimality in allocating the total load demand
among the various units.
6 𝜕𝐶
The condition for optimality is the incremental fuel cost, 𝜕𝑃 𝑖 = λ K1 CO3
𝑔𝑖
What is the need of system variables and what are the variables?
To analyze the power system network, there is a need of knowing the
system variables. They are: K1
7. CO3
1. Control variables—Pg and Qg
2. Disturbance variables—Pd and Qd
3. State variables—V and δ.
K
S.No Part A (Q & A) COs
Level
Define the control variables.
8 The real and reactive-power generations are called control variables K1 CO3
since they are used to control the state of the system.
Define the disturbance variables.
The real and reactive-power demands are called demand variables and
9 they are beyond system control and are hence called uncontrolled or K1 CO3
disturbance variables
Define the state variables.
The bus voltage magnitude V and its phase angle δ dispatch the state
10 of the system. They are dependent variables that are being controlled K1 CO3
by the control variables
What is the need of input–output characteristics of a steam unit?
11 It establishes the relationship between the energy input to the turbine K1 CO3
and the energy output from the electrical generator.
Define the incremental fuel or heat rate curve.
12 It is defined as the ratio of a small change in the input to the K1 CO3
corresponding small change in the output
i.e., the product of IC of any unit and its penalty factor gives the
optimum solution.
What do you mean by ITL and penalty factor of the system? Write
expressions for them.
It is defined as the ratio of the change in real-power loss to the change
in real-power generation.
19 K1 CO4
Penalty factor
𝜕𝑃𝐿
= λ [1− ]
𝜕𝑃𝑔𝑖
What is a UC problem?
It is not advisable to run all available units at all times due to the variation of
load. It is necessary to decide in advance:
i. Which generators to start up.
23 ii. When to connect them to the network. K1 CO3
iii.The sequence in which the operating units should be shut down
and for how long.
The computational procedure for making the above such decisions are called
the problem of UC.
As for other types of generation such as hydro, the aggregate costs such as
25 K1 CO3
start-up costs, operating fuel costs, and shut-down costs are negligible so that
their ON–OFF status is not important.
What are the different constraints that can be placed on the uc problem?
Spinning reserve.
27 Thermal unit constraints. K1 CO3
Hydro-constraints.
Must-run constraints.
Fuel constraints.
Part A
A thermal unit can undergo only gradual temperature changes and this
30 translates into a time period of some hours required to bring the unit K1 CO3
on the line. Due to such limitations in the operation of a thermal plant,
the thermal unit constraints are to be considered in the UC problem.
The start-up cost may vary from a maximum cold-start value to a very
small value if the unit was only turned off recently and is still relatively
close to the operating temperature
What are the techniques used for getting the solution to the UC
problem?
1 Build the Coordination equation for the EDC neglecting losses K3 CO4
14 K1 CO3
Part B
K
S.N
Part B Lev COs
o
el
Determine Priority list using full load average production cost for the data
given
Power Demand, PD = 500MW
15 K3 CO3
Supportive Online Certification Courses
https://www.sciencedirect.com/science/article/abs/pii/S0952197620301676
Content beyond the syllabus
TEXT BOOKS:
2. Allen. J. Wood and Bruce F. Wollen berg, ‗Power Generation, Operation and
Control‘, John Wiley & Sons, Inc., 2016.
3. Abhijit Chakrabarti and Sunita Halder, ‗Power System Analysis Operation and
Control‘, PHI learning Pvt. Ltd., New Delhi, Third Edition, 2010.
REFERENCES
1. Kothari D.P. and Nagrath I.J., ‗Power System Engineering‘, Tata McGraw-Hill
Education, Second Edition, 2008.
2. Hadi Saadat, ‗Power System Analysis‘, McGraw Hill Education Pvt. Ltd., New
Delhi, 21st reprint, 2010.
3. Kundur P., ‗Power System Stability and Control, McGraw Hill Education Pvt. Ltd.,
New Delhi, 10th reprint, 2010.
Mini project suggestions
Disclaimer:
This document is confidential and intended solely for the educational purpose of RMK Group of
Educational Institutions. If you have received this document through email in error, please notify the
system manager. This document contains proprietary information and is intended only to the
respective group / learning community as intended. If you are not the addressee you should not
disseminate, distribute or copy through e-mail. Please notify the sender immediately by e-mail if you
have received this document by mistake and delete this document from your system. If you are not
the intended recipient you are notified that disclosing, copying, distributing or taking any action in
reliance on the contents of this information is strictly prohibited.
Please read this disclaimer before proceeding:
This document is confidential and intended solely for the educational purpose of
RMK Group of Educational Institutions. If you have received this document
through email in error, please notify the system manager. This document
contains proprietary information and is intended only to the respective group /
learning community as intended. If you are not the addressee you should not
disseminate, distribute or copy through e-mail. Please notify the sender
immediately by e-mail if you have received this document by mistake and delete
this document from your system. If you are not the intended recipient you are
notified that disclosing, copying, distributing or taking any action in reliance on
the contents of this information is strictly prohibited.
POWER SYSTEM OPERATION AND CONTROL
Department: EEE
2 Course objectives 6
3 Pre Requisites 7
4 Syllabus 8
5 Course outcomes 9
6 CO-PO/PSO Mapping 13
7 Lecture Plan 14
8 Activity based learning 15
9 Lecture Notes 16
10 Assignments 56
11 Part A Q & A 57
12 Part B 60
16 Assessment Schedule 64
SCADA and its application for real time operation and control of power systems
Prerequisites
CO2 Ability to analyse the control actions to be implemented on the system to meet
the minute-to-minute variation of system demand.
CO6 Ability to design SCADA and its application for real time operation.
PROGRAMME OUTCOMES
c. Come out with solutions for the complex problems and to design system
components or process that fulfill the particular needs taking into account public
health and safety and the social, cultural and environmental issues.
e. Form, select and apply relevant techniques, resources and Engineering and IT
tools for Engineering activities like electronic prototyping, modeling and control
of systems and also being conscious of the limitations.
10
PROGRAMME OUTCOMES
l. Recognize the need for self and life-long learning, keeping pace with
technological challenges in the broadest sense.
11
PROGRAM SPECIFIC OUTCOMES
PSO 1 Analyze, design and implement control, instrumentation and power systems for
satisfying industry needs.
PSO 2 Use modern tools and appropriate solutions for the real time problems for promoting
energy conservation and sustainability.
12
CO-PO /PSO mapping
CO/ a b c d e f g h i j k l PS PS PS
PO, O O O
PSO 1 2 3
co1 - 2 - 3 3 - - - - - - - 3 - 3
co2 - 2 - 3 3 - - - - - - - 3 - 3
co3 - 2 - 3 3 - - - - - - - 3 - 3
co4 - 2 - 3 3 - - - - - - - 3 - 3
co5 - 2 - 3 3 - - - - - - - 3 - 3
co6 - 2 - 3 3 - - - - - - - 3 - 3
Lecture plan Unit V
Sl Topic No of Prop Actu Pertaining Taxon Mod
No Perio ose al dt CO omy e of
ds d dt level deliv
ery
1 Need of computer CO6 K2 PPT
control of power
systems-
2 Concept of energy CO6 K2 PPT
control centers and
functions
3 PMU - system CO6 K2 PPT
monitoring,
4 data acquisition and CO6 K2, PPT
controls - System
hardware
5 configurations - CO6 K2 PPT
SCADA
6 EMS functions CO6 K2 PPT
1. Role play:
SCADA
Lecture notes
❖ The multiplicity of monitoring instruments in the control room and their distance apart
make the observation of more than a few vitalises almost impossible, especially during
the intense activity of plant start-up.
❖ These requirements led to the development and application of more advanced solid
❖ state modular electronic instruments, computer based direct control and date
processing systems.
❖ The computer system used at power system has been undergoing continuous
development over the years. Formerly, all the functions such as data acquisition,
logging display, and control and performance calculations were performer by
computer processing unit (CPU).
❖ In such system failure of any of the elegant leads to the total system breakdown.
Thus, the need for a dual computer configuration arose which is quite costly.
Functions
The practice of all communication links between equipment and the control centre
could be interrupted and still, electric service is being maintained. The
generating in the system remains synchronized to the transmission network and
maintains its existing power output level even without signals received from
control centre.
Monitoring
An energy control centre fulfills the function of coordinating their
response of the system elements in both normal operation and emergency
conditions.
The burden of repetitious control in normal situations is delegated to the digital
computer and selective monitoring is performed by human operators.
The digital computer is used to process the incoming stream of data to detect
abnormalities and the human operator via lights, buzzers and CRT presentations.
Many lower level or less serious cases of exceeding normal limits are routinely
handled by digital computer. A more serious abnormality detected by the digital
computer may cause suspension of normal control functions
In emergencies such as loss of a major generator or excess power demands by a
neighboring utility on the tie lines, many alarms could be detected and the system
could enter an emergency state.
A phasor measurement unit (PMU) is a device used to estimate the magnitude and
phase angle of an electrical phasor quantity (such as voltage or current) in
the electricity grid using a common time source for synchronization. Time
synchronization is usually provided by GPS or IEEE 1588 Precision Time Protocol,
which allows synchronized real-time measurements of multiple remote points on the
grid. PMUs are capable of capturing samples from a waveform in quick succession
and reconstructing the phasor quantity, made up of an angle measurement and a
magnitude measurement. The resulting measurement is known as a synchrophasor.
These time synchronized measurements are important because if the grid’s supply
and demand are not perfectly matched, frequency imbalances can cause stress on
the grid, which is a potential cause for power outages.
PMUs can also be used to measure the frequency in the power grid. A typical
commercial PMU can report measurements with very high temporal resolution, up to
120 measurements per second. This helps engineers in analysing dynamic events in
the grid which is not possible with traditional SCADA measurements that generate
one measurement every 2 or 4 seconds. Therefore, PMUs equip utilities with
enhanced monitoring and control capabilities and are considered to be one of the
most important measuring devices in the future of power systems. A PMU can be a
dedicated device, or the PMU function can be incorporated into a protective relay or
other device.
Existing systems in power grid such as Energy Management System (EMS) and
Supervisory Control and Data Acquisition system (SCADA) have the capability to
provide only steady state view of power system with high data flow latency. In
Supervisory Control and Data Acquisition system (SCADA) it was not possible to
measure the phase angles of bus voltages of power system network in real time, due
to technical difficulties in synchronising measurements from distant locations.
Measurements were obtained at slower rates; it was not possible to get dynamic
behaviour of power system as well as limited situational awareness was conveyed
to the operator. Advent of Phasor Measurement Units (PMUs) alleviated this
problem by synchronising voltage and current waveforms at widely dispersed
locations with respect to global positioning system. PMU is superior to SCADA with
respect to speed, performance and reliability.
PMU technology is well suited to track grid dynamics in real time, the data
obtained can be used for wide area monitoring, stability monitoring, dynamic
system ratings and improvement in state estimation, protection and control. It
enables utilities to proactively plan energy delivery and prevent failures.
PMU application
❖ Stability monitoring
❖ State estimation
❖ Adaptive protection
❖ The supervisory control and the data acquisition system allow a few operators to
monitor the generation and HV transmission system. Consistent with principles of
high reliability and fail safe failures, electric utilities have almost universally applied
a redundant set of dual digital computers for the function of remote date
acquisition control, energy management and system security.
❖ Both computers have their own core memory and drive an extensive number of
input-output devices such as printers, teletypes, and magnetic tape drive, disks.
Usually one computer, the on-line units, is monitoring and controlling the power
system. The backup computer may be executing off-line batch programs such as
load forecasting or hydro-thermal allocation
❖ The on-line computer periodically updates a disk memory shared between the two
computers. Upon a fail over or switch-in status command, the stored information of
the common disk is inserted in the memory of the on-line computer.
❖ The information used by the on-line computer has a maximum age of update cycle.
All of the peripheral equipment is interfaced with the computer through input-
output microprocessors that have been programmed to communicate, as well as
pre-process the analog information, check for limits, convert to another system of
units and so on.
❖ The microprocessors can transfer data in and out of computer memory without
interrupting the central processing unit. As a result of these precautions, for all
critical hardware functions, there is often a guaranteed 99.8% or more
availability.
❖ Besides hardware, new digital code to control the system may be compiled and
tested in the backup computer, then switched to on-line status. The digital
computers are usually employed in a fixed cycle operating mode, with priority
interrupts wherein computer periodically performs a list of operations. The most
critical functions have the fastest scan cycle. Typically, the following categories
are scanned every 2 seconds.
The functions
1. Data acquisition
2. Monitoring, sectionalizing switches and create circuit configuration
3. Feeder switch control and preparing distribution map
4. Preparation of switching orders
5. Customer meter reading
6. Load management
7. Fault location and circuit topology configuration
8. Service restoration
9. Power factor and voltage control
10. Implementation time dependent pricing
11. Circuit continuity analysis.
12. To control customer load through appliance switching and indirectly through
voltage control
Power System Data Acquisition and Control
Since the master station is critical to power system operations, its functions are
generally distributed among several computer systems depending on specific
design. A dual computer system configured in primary and standby modes is most
common. SCADA functions are listed below without stating which computer has
specific responsibility.
• Manage communication circuit configuration
• Downline load RTU files
• Maintain scan tables and perform polling
• Check and correct message errors
Convert to engineering units
• Detect status and measurement changes
• Monitor abnormal and out-of-limit conditions
• Log and time-tag sequence of events
• Detect and annunciate alarms
• Respond to operator requests to:
– Display information
– Enter data
– Execute control action
– Acknowledge alarms Transmit control action to RTUs
• Inhibit unauthorized actions
• Maintain historical files
• Log events and prepare reports
• Perform load shedding
Automatic Generation Control
Automatic generation control (AGC) consists of two major and several minor
functions that operate online in real time to adjust the generation against load at
minimum cost.
The major functions are load frequency control and economic dispatch, each of
which is described below.
The minor functions are reserve monitoring, which assures enough reserve on
the system; interchange scheduling, which initiates and completes scheduled
interchanges; and other similar monitoring and recording functions.
There are two parts to the term SCADA Supervisory control indicates that the
operator, residing in the energy control center (ECC), has the ability to control
remote equipment.
Data acquisition indicates that information is gathered characterizing the state of
the remote equipment and sent to the ECC for monitoring purposes.
The monitoring equipment is normally located in the substations and is
consolidated in what is known as the remote terminal unit (RTU).
Generally, the RTUs are equipped with microprocessors having memory and logic
capability. Older RTUs are equipped with modems to provide the communication
link back to the ECC, whereas newer RTUs generally have intranet or internet
capability.
Relays located within the RTU, on command from the ECC, open or close selected
control circuits to perform a supervisory action.
Such actions may include, for example, opening or closing of a circuit breaker or
switch, modifying a transformer tap setting, raising or lowering generator MW
output or terminal voltage, switching in or out a shunt capacitor or inductor, and
the starting or stopping of a synchronous condenser.
Information gathered by the RTU and communicated to the ECC includes both
analog information and status indicators.
Analog information includes, for example, frequency, voltages, currents, and real
and reactive power flows.
Status indicators include alarm signals (over-temperature, low relay battery
voltage, illegal entry) and whether switches and circuit breakers are open or
closed.
Such information is provided to the ECC through a periodic scan of all RTUs. A 2
second scan cycle is typical.
SCADA
SENSORS - Analog and digital sensors are used to interface the systems
RELAYS– Relays are used to sense the abnormal conditions and protect the
system.
REMOTE TERMINAL UNITS – RTU’s are microprocessors controlled electronics
devices which are used to collect various data's and transmit to SCADA system.
MASTER UNIT- Master unit act as a central processor computer.
COMMUNICATION LINKS- It is used to link RTU’s and SCADA system. Satellite
communication, microwave communication, fiber optic communication maybe
used for communication purpose.
AREA CONTROL ERROR
The interchange power Ps, is generally scheduled for periods of the day
and is changed as ‘blocks’ of MWhr are bought or sold to neighboring utilities. A
positive ACE or positive net exchange of power represents a flow out of the area.
11. Multiplexer
REMOTE TERMINAL UNIT
The RTU’S are installed at selected power stations and substations. The
hardware components of RTU may include the following.
1. Transducers
2. A/D and D/A converters
3. Serial Interface
4. Modems
5. Multiplexers
6. Front end Computer
7. Control relays
REMOTE TERMINAL UNITS
The analog quantities like voltage , MW, MVAR and frequency measured
at stations are converted into DC voltage or current signals, through transducers and
fed to the A/D converters with convert the analog signals into digital from suitable
for transmission. The digital signal is fed to the front end computer and modems
through the serial interface . MODEM sends the information to the master unit
through multiplexer. MODEM will also receive commands from master units to
control the station equipment's through the control relays. In addition to measure
quantities, status of various devices is informed to master station.
The master station scans the RTU sequentially and gathers information on
the system operating condition i.e Voltage, Current, line flows, generation, output,
etc as well as equipment status. Computer, using real time data can check operating
limits of various quantities and give an alarm to operator if overloading or any other
abnormal condition is detected, the system real time information is presented to the
operator through CRT, computer graphic terminals, alarm panels, alarm printer so
that the operator can supervise minute by minute, system operating condition and
take control action to prevent system disturbances whenever emergency conditions
and system status at specified interval is printed by data loggers.
MONITORING FUNCTIONS:
PROTECTION FUNCTIONS:
Substation protection functions includes the monitoring of events like start, trip
indication and relay operating time and setting and reading of relay parameters.
Protection of bus bars. Line feeders, transformers, generators.
Protection monitoring (status, events, measurements, parameters, recorders)
Adaptive protection by switch-over of the active parameter set.
STATE ESTIMATION
7.9.3. Errors
In real time control, the measurements like real and reactive line flows,
real and reactive bus injections (P&Q),bus voltage magnitudes are collected
through SCADA (Supervisory control and data acquisition system).The
telemetered data contains error, that may be redundant measurements. The
errors arise from.
➢ Inaccurate transducer calibration.
➢ The effect of analog to digital conversion.
➢ Noise in communication channels.
➢ Unbalanced phase,etc.
➢ These errors are random in nature and the bus voltage magnitudes cannot be
predicted. So, state estimation is to clean up the erroneous data.
➢ If the number of measurements are more, or the redundancy in the measurement
set to determine the condition of the network, a systematic crosschecking should
be able tc eliminate the errors. Then the output data are used in the system
control center to implement security constrained dispatch and control.
The objective is to maximize the probability that the estimate of the state
variables [X], is the true value of the state variable vector [X].
The objective is to minimize the sum of the squares of the deviation of the
estimated components of the state variable vector from the corresponding
components of the true state variable vector.
If the 7th measurement Zi is more reliable and accurate, then larger value should
be assigned for the corresponding weightage Wi matrix is a diagonal matrix .
Let [X] be the vector of estimated current values for the state variables of order
n3x1.
Let [A] be the partial different coefficients of the measurement functions with
respect to the state variables on order nmxn3.
Estimated state vector Let [X] =[X0 ]+[ X]
[ X] =Correction vector.
A power system may be operated in a several different states. These are classified
into five operating states. They are
1. Normal state (Secure state)
2. Alert state
3. Emergency state
4. Extremis state
5. Restorative state
The five operating states and their transitions are shown in fig
S.N
Description Link
o
http://www.freepdfbook.com/pow
E book – Power System Operation and Control by
1 er-system-operation-and-control-
Sivagnanaraju by-sivanagaraju-and-sreenivasan/
http://www.freepdfbook.com/oper
E book – Operation and Control in Power System by
2 ation-and-control-in-power-
PS Murthy systems-by-p-s-r-murty/
http://www.freepdfbook.com/pow
E book - Power System Operation and Control by
3 er-system-analysis-operation-and-
Abhijit and chakrabarthi control-abhijit-chakrabarti-pdf/
https://nptel.ac.in/courses/108/10
4 Video Link –State estimation 5/108105133/
https://nptel.ac.in/courses/108/10
5 Video Link – Load Frequency Control 5/108105104/
K
S.No Part A (Q & A) COs
Level
Define restorative state. (May/June 2014) From this state, the system may be
brought back either to alert state or secure state. The latter is a slow process.
6 Hence, in certain cases, first the system is brought back to alert state and K1 CO6
then to the secure state. This is done using restorative control action
K
S.No Part A (Q & A) COs
Level
Define weighted least-squares criterion?
The objective is to minimize the sum of the squares of the weighted
13 deviations of K1 CO6
the estimated measurements z, from the actual measurement.
Part C
https://www.watelectrical.com/scada-applications-in-power-system/
15 Content beyond the syllabus
TEXT BOOKS:
2. Allen. J. Wood and Bruce F. Wollen berg, ‘Power Generation, Operation and
Control’, John Wiley & Sons, Inc., 2016.
3. Abhijit Chakrabarti and Sunita Halder, ‘Power System Analysis Operation and
Control’, PHI learning Pvt. Ltd., New Delhi, Third Edition, 2010.
REFERENCES
1. Kothari D.P. and Nagrath I.J., ‘Power System Engineering’, Tata McGraw-Hill
Education, Second Edition, 2008.
2. Hadi Saadat, ‘Power System Analysis’, McGraw Hill Education Pvt. Ltd., New
Delhi, 21st reprint, 2010.
3. Kundur P., ‘Power System Stability and Control, McGraw Hill Education Pvt. Ltd.,
New Delhi, 10th reprint, 2010.
18 Mini project suggestions
Disclaimer:
This document is confidential and intended solely for the educational purpose of RMK Group of
Educational Institutions. If you have received this document through email in error, please notify the
system manager. This document contains proprietary information and is intended only to the
respective group / learning community as intended. If you are not the addressee you should not
disseminate, distribute or copy through e-mail. Please notify the sender immediately by e-mail if you
have received this document by mistake and delete this document from your system. If you are not
the intended recipient you are notified that disclosing, copying, distributing or taking any action in
reliance on the contents of this information is strictly prohibited.