Virtual Testing of Protection Systems Using Digital Twin Technology - Paper
Virtual Testing of Protection Systems Using Digital Twin Technology - Paper
net/publication/359617800
CITATIONS READS
0 1,179
5 authors, including:
Some of the authors of this publication are also working on these related projects:
IEC Relay Protection Standardisation - TC 95/MT4 and IEC TC 95/WG 2 View project
All content following this page was uploaded by Andrea Bonetti on 31 March 2022.
1
With this technology, every stage of the process flow right from normally must be handled on-site are eliminated. Testing can be
the inception of a project to its execution and delivery can be divided into two prime categories – Open Loop and Closed
made more efficient by finding the errors early in the process Loop.
and having them fixed. Engineering services can hop on the
A. Open Loop Testing
project, create it based on customer requirements, implement
settings, perform validation, and show the outcome and results Open loop testing refers to a method of virtual testing where the
to the customers before even taking the charge. Customers can test sequence is performed without monitoring relay’s reaction.
always observe the work online and adjust if necessary. In Instead of waveform generation from physical amplifiers,
cooperation with the client, commissioning coaching and signals are generated in the test software tool and sent digitally
training can also be designed in the commissioning phase. This to the virtual analog and binary inputs of the digital twin of
makes it much easier for employees to start up later. relay. The digital data that was sent from the digital twin of test
The story does not end here. Digital twin technology can be system is stored as a COMTRADE file. COMTRADE files are
extremely valuable during the maintenance phase as well. The predominantly used in the industry and is a widely accepted
ability to test new firmware versions of various IEDs, updates format. These files have also been standardized by IEC 61850
and adjustments to the settings as well as constant optimization for disturbance recorders, thereby making them the perfect
of the substation can prove to be praiseworthy. Due to the real- solution for virtual testing platform. For a COMTRADE file to
time data flowing between the physical asset and its Digital twin, be used in virtual testing, it must be possible to acquire the data
fast and superior technical support on equipment from from the file and process it as if it was real time, but in the
manufacturers can be expected. Local support team can reach virtual time associated with the virtual relay. This means that
out to engineering experts in no time irrespective of their the tests can be faster or slower than real time, but the file
location. Problems at hand can be better explained and root processor needs to interact with the virtual relay so that the
cause investigation of events can be reported back to response time reflects that of the real relay. Once the file is
users/system operators without unnecessary delays. processed, the relay’s response is analyzed using the relay event
data, disturbance recorder, or by simply monitoring the virtual
Digital twin can foresee defects and damage in the relay HMI, depending on the test’s complexity. [1] [3]
manufacturing -machine or system and thus can schedule the
III. TEST SYSTEM
maintenance of the product in advance. By simulating different
scenarios, digital twin provides the best possible solution or In this section, the system under test consideration,
maintenance strategy that makes the maintenance of the protection relay settings, and different functions considered for
product/system much easier. In addition, the constant feedback testing for various types of faults are discussed.
loop between the digital twin and its physical twin can be used
to validate and optimize the system’s process all the time.
2
Figure 3 - Relay Settings - CT, PT and Line Information
3
IV. TEST SETUP voltage and current signals from digital twin equipment were
In this section, the test setup for virtual testing as well as the mapped to the digital twin relay terminals. Once the mapping
setup for physical relay testing is discussed. was done, the digital twin relay was energized. The tests were
selected one at a time and executed to validate fault locator
A. Digital Twin Test Setup algorithm, distance zone trip times, undervoltage and
The test setup for digital twin platform was performed in two overvoltage trip times, and POTT scheme. Specifically,
phases. The first phase involved creating the relay settings in following tests were created – L1N at 10%, L1N at 20%, L1N
the relay software. The relay settings were exported in the form at 25%, L1N at 50%, L1N at 75%, L1N at 90%, Z1 Timing, Z2
of SIMulation data format (SIM) file from software tool of the Timing, Z3 Timing, 27 Timing, and 59 Timing.
protection relay. This SIM file was then imported to the digital
twin platform to simulate the relay under test. Figure 7 shows the
SIM file after it is imported in the digital twin platform.
Figure 10 - Signal mapping between digital twin relay and test equipment
Figure 7 - SIM file import in digital twin platform
4
Table 1 - Comparison of operate time and indications given by HMI of digital
twin relay and physical twin relay
The trip times for each test was captured from the HMI both
during virtual test as well as physical test. As Table 1 shows,
there is full consistency in the data. This means that no
significant differences have been noticed between virtual
testing and physical testing results. For a deeper investigation
in this comparison, the event records were examined to confirm
the trip times recorded on HMI on both the cases.
5
The results prove that virtual testing, where a digital twin relay
Average Operate Time is tested by means of a digital twin test set, provides test results
consistent with the physical tests, where the physical twin relay
(HMI) - Fault Locator is tested with the physical twin test set, with the consideration
that the twins share the same data (i.e. relay setting files and test
plans as shown in Figure 5 and Figure 13).
14
13
B. Virtual Testing of POTT scheme using Local and Remote
Digital Twins
It can be noted from Figure 15 that the average operate times for
the tests between virtual and physical tests were within 1 ms Figure 17 - POTT Scheme
difference. Also, average operate times were recorded for the
zone operation trip and plotted as shown in the Figure 16. The Physical test setup to test a communication based scheme could
average operate times difference for the zone operation trip be complicated to arrange due to the requirement of multiple
between virtual and physical tests were 1.2 ms for zone 1, 1.6 test equipments and relays. Trusting the results obtained with
ms for zone 2, and 3.2 ms for zone 3 as seen in Figure 16. virtual testing, a POTT distance protection scheme was
configured and tested in virtual environment. Both local and
remote digital twin relays were simulated in the digital twin test
AVERAGE OPERATE TIME environment at the same time for the virtual POTT scheme test.
The time delay for POTT scheme was set to 60 ms. Test cases
(HMI) - ZONE were generated by the digital twin test set. A single line to
ground fault at 5% on the
OPERATION
Average Trip Time (DT) Average Trip Time (RT)
1000
996.8
400
398.4
1.2
0 Average Trip Time (RT)
Average Trip Time (DT)
Z1 Trip Z2 Trip Z3 Trip
6
but it operated instantaneously on zone 1 and sent the
permissive carrier to the other line-end. The remote relay
started in zone 2 and tripped for permissive overreach function
in 56 ms., because of the reception of the permissive carrier.
7
View publication stats
VII. CONCLUSION
Emergence of digital twin technology which has made virtual Mohit Sharma is currently part of the engineering team at
testing a possibility, is an opportunity to optimize protection Megger where he designs, develops, and validates testing
systems and associated testing processes. Since digital twin is a solutions in the areas of system protection and automation. He
cloud based technology, it provides easy access virtually to the joined Megger in 2015 as an Applications Engineer for
digital assets. In this paper, distance protection, fault locator protective relay products after receiving his MS in electrical
algorithm and voltage protection were validated in both digital power systems engineering from North Carolina State
twin environment as well as physical test environment. The University, Raleigh. Mohit obtained his B.Tech in electrical
results were compared between virtual testing and physical engineering from the National Institute of Technology, Bhopal,
testing to ensure deviation between the two was not significant India, in 2012. He worked with Indiabulls Power, an IPP, as an
as well as adhered to accuracy tolerance for each of those tests. Electrical Maintenance Engineer responsible for the testing and
POTT scheme was validated using local and remote digital twin maintenance of LV and MV switchgear. He is currently a
relays successfully. During the process of POTT scheme member of IEEE-PSRC.
validation, setting errors were found and corrected prior to re-
testing of the scheme. Tests created in the virtual environment Amir Soroush received his B.Eng degree in electrical
was re-used for the physical testing as well making the test engineering from Iran University of Science and Technology.
process efficient. In this paper, open loop testing was performed He started his professional experience with ABB in 2000 as
in both test environments successfully. Various advantages of design Engineer for power utility Protection and Control system
this kind of testing includes time efficient testing process, find in Iran and has been involved with the commissioning, control,
setting errors, and help with troubleshooting, cost effective and protection, monitoring and automation of power system
ease of training. apparatus up to 400 kV for 20 years. His research interests
include power system protection, IEC61850 , Digital Substation
VIII. REFERENCES and SCADA. In 2020 he joined SIEMENS USA as an
[1] A. Bonetti, C. Harispuru, M. Pitzer, M. Pustejovsky, N. Wetterstrand and application engineer where he is responsible for the application
S. Kachelrieß, "Digital twin technology for virtual testing of power and design of protective relays and Substation Automation
system relay protection," 2021 3rd IEEE Global Power, Energy and
Communication Conference (GPECOM), 2021, pp. 154-160, doi:
Systems.
10.1109/GPECOM52585.2021.9587869.
[2] C. Harispuru and S. Roesler, ‘Virtual Testing with a Digital Twin of
protection devices in the cloud’, presented at the PAC World Americas Andrea Bonetti received his MS in electrotechnical
2019, Aug 2019 engineering from Sapienza University in Rome, Italy. He
[3] A. Bonetti, C. Harispuru, M. Pitzer, and N. Wetterstrand, ‘Virtual testing worked for 18 years in ABB Vasteras, Sweden as HV Power
of protection relays is real!’ – Electrical Tester Magazine – Issue 3
System Protection Specialist. He worked for 5 years as
[4] Siemens Siprotec 5 - User Manual
consultant in power system protection and IEC61850
[5] Raqeeb, Abdul, Andrea Bonetti, Andreas Carlsson, Cédric Harispuru,
Mark Pustejovsky, and Niclas Wetterstrand. FUNCTIONAL DIGITAL applications. He worked as product manager for 7 years and is
TWINS OF RELAY PROTECTION AND RELAY TEST EQUIPMENT presently with Megger Sweden as Senior Application Specialist
ENABLING BENEFITS IN TRAINING AND REMOTE SUPPORT, Relay Protection and IEC61850. He holds a patent in the area
2022.
of IEC 61850 testing tools and algorithms. He is a member of
IX. BIOGRAPHIES the IEC TC 95/MT4 and TC 95/WG 2, IEC committees for
standardization of protection functions and IEC 61850
Sughosh Kuber is a Relay & Protection Applications Engineer application for protection. He has received the IEC 1906 award
at Megger North America, where he provides technical support in 2013. He is guest lecturer at KTH (Royal Institute of
to service companies and utilities responsible for reliable Technology, Stockholm) for IEC 61850 for substation
operation of electrical networks. Sughosh brings over 10 years automation applications since 2008. He is teacher for IEC
of field experience and academic research in power systems 61850 for protection and control applications for the private
from protection schemes and testing to data analysis for energy Swedish University Lernia (Yrkeshogskola).
efficiency and sustainability. Sughosh received his MS in
Electrical Engineering from New Mexico State University. Cédric Harispuru graduated from Centrale Supelec and the
Sughosh earned his B.E in instrumentation technology from University of Darmstadt. Cedric joined Siemens AG in 2006.
J.S.S Academy of Technical Education in Visvesvaraya He is product lifecycle manager and senior key expert for
Technological University. He worked at Sentinel Power engineering tools in the energy automation. He is responsible
Services as Project Engineer from 2013 to 2018 before joining for SIPROTEC Digital Twin, SIPROTEC tools and IEC 61850
Megger. He is currently a member of IEEE-PSRC. engineering. He is a member of IEC TC57 WG10.