Progress Report Project

1) Drilling for dowell bar in the Production area's slab-on-grade (SOG) is in progress. 2) The cooling tower foundation excavation, leveling, and compaction is complete. 3) Excavation of the condenser deck foundation is currently underway.

Uploaded by

Bilal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
141 views2 pages

Progress Report Project

1) Drilling for dowell bar in the Production area's slab-on-grade (SOG) is in progress. 2) The cooling tower foundation excavation, leveling, and compaction is complete. 3) Excavation of the condenser deck foundation is currently underway.

Uploaded by

Bilal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

CIVIL WORKS FOR NEW PET LINE AT KPGF CCI PLANT

Daily Progress Report


REPORTED BY AREAA BANU MUKHTAR CONSTRUCTION -LLP
REPORT NO 12
DATE 2-Dec-2022
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Skilled Labour Steel Fixer


Skilled Labour Carpenter

Mechanical Supervisor
Machinery Operators
Skilled Labour Mason
Admin and Account
QS/ Office Engineer

Dismentaling team
Staff &
Project Manager

Workers
Supervisor Civil
Site in Charge

HSE Engineer

Electician
Surveyor

Drivers

Total
Strength 0 1 0 1 1 1 1 2 0 0 0 1 1 1 0 10
TODAY WEATHER oC

Drilling for dowell bar in Production area SOG is in progress. Morning 9


Cooling tower foundation excavation,leveling and compaction is complete. Afternoon 19

Condensser deck foundation excavation is in progress. EQUIPMENT


No Equipment Required Current
1 Excavator/Jack Hammer 1 0
2 Plate Compactor 1 1
3 Asphalt concrete cutting machine 2 2
4 Hilti drill machine 1 1
5 Tractor with Trolly 4 4
6 Grinder 4" 1 1
7 Grinder 9" 1 1
8 Power cutter 14" 1 1
9 Concrete Breaker (Hilti) 1 1
10 Double Cabine 1 1
11 Suzukai carry 1 0
12 Level Machine 2 2
13 Fire Extinguisher 4 4
14 Vibrator and Convertor 1 0
15 Welding Plant 1 1
16 Generator 6KVA 1 1

TOMORROW MATERIAL DETAIL


Removal of excavated material. No Material Unit In Stock
Drilling for dowell bar in Production area SOG. 1 Tarpulin Sheet no 15.00
Condenser deck foundation excavation. 2 Polythene Sheet rolls 4.00
3 Wooden Planks 13'x12"x2" no 40.00
4 XPS insulation Board 38mm S.ft 270.00
5 UPVC beta pipe dia 250mm Rft 65.00
6 UPVC beta pipe dia 300mm Rft 91.00
7 Fibre Kg 550.00
No Description Unit W. Done
1
2
3
4
5
6
7
8
9
10
11
12
13
NOTES/REMARKS
Work of WTP & Ammonia foundation is still on hold. Waiting for Client & Consultant decision.

Contractor Project Consultant Client


CIVIL WORKS FOR NEW PET LINE AT KPGF CCI PLANT
DAILY PROGRESS PICTURES
Date: 12/2/2022

5. 6.