0% found this document useful (0 votes)
249 views

5.2 STATCOM System Functional Requirements

This document outlines the requirements for a STATCOM system project in Taiwan including: 1. The scope of work is for STATCOM equipment and related systems at two substations. 2. The contractor shall be responsible for design, supply, installation, testing and training. 3. The main STATCOM equipment includes protection relays, gas insulated switchgear, transformers, reactors, charging resistors, voltage source converters, cooling systems, cables and auxiliary equipment. 4. Requirements are provided for the system architecture, specifications, operation modes, protection, control systems, loss calculations, testing procedures and maintenance.

Uploaded by

Yinwu Zhao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
249 views

5.2 STATCOM System Functional Requirements

This document outlines the requirements for a STATCOM system project in Taiwan including: 1. The scope of work is for STATCOM equipment and related systems at two substations. 2. The contractor shall be responsible for design, supply, installation, testing and training. 3. The main STATCOM equipment includes protection relays, gas insulated switchgear, transformers, reactors, charging resistors, voltage source converters, cooling systems, cables and auxiliary equipment. 4. Requirements are provided for the system architecture, specifications, operation modes, protection, control systems, loss calculations, testing procedures and maintenance.

Uploaded by

Yinwu Zhao
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 34

Machine Translated by Google

Central District Construction Division, Power Transmission

and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static

synchronous compensator (STATCOM) turnkey new project

Requirements Book (2)

STATCOM System Functional Requirements

December 111, Republic of China


Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

Table of contents

Chapter 1 Scope of work and content of work..................................................... ................1

1.1 Scope of work................................................ ...............................................1

1.2 Job content................................................... ................................................1

1.3 Specification documents and their order of priority................................................... .............................2

Chapter II Relevant Guidelines................................... ...................................3

2.1 Guidelines for reference................................................ ................................................3

2.2 Reference Specifications ................................................ ................................................3

2.3 Abbreviations................................................ ................................................... ......3

2.4 Definition of terms................................................ ................................................4

Chapter Three Engineering Requirements................................... ...................................5

3.1 Design requirements................................................... ...................................5

3.2 system requirement................................................ ................................................6

3.2.1 Architecture................................................... ................................................... 6

3.2.2 Taipower system conditions................................................... ...................................7

3.2.3 STATCOM System Feature Requirements................................... ...................8

3.2.4 Running operation and control mode................................... ................................... 10 3.2.5 Protective relay

system........... ................................................... ................... 13 3.2.6 Control

system................................... ................................................... ....14

3.2.7 Calculation of the overall loss of the system................................... ................................... 14

3.3 System and equipment capacity analysis................................... ................................................ 16

3.4 File submission................................................... ................................................ 18

3.5 Troubleshooting operations................................... ....................................... twenty two

I
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

3.6 Maintenance................................................... .............................................. twenty three

3.7 Supply of spare parts and tools................................... .................................... twenty four

3.8 Education and training................................... .............................................. twenty four

Chapter 4 Engineering Interface................................... ...................................25

4.1 Interface between STATCOM system and the power system of the temporary bidding project............ 25

4.2 Interface between STATCOM system and civil engineering and ancillary electromechanical engineering............ 26

4.3 Engineering interface between STATCOM system and SCADA system............ 28

Chapter Five Functional Requirements of Main Materials and Equipment................................... ..........29

Chapter 6 Inspection and Test................................... ...................................30

6.1 Factory test..................................................... ................................................ 30

6.2 Field testing................................................... ................................................ 30

6.3 System Integration Test................................................... ................................................ 31

6.3 Debugging test (COMMISSIONING TESTS) ................................... .......... 31

6.4 Parallel test run performance verification of STATCOM system................................... ...... 31

6.5 Cooperate with joining the system operations................................... ................................... 31

II
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

Chapter One Scope and Content of Work

1.1 Project scope

This specification is applicable to the 161kV static synchronous compensator of Zhanggong Booster Station and Yongxing Switching Station

(STATCOM) STATCOM system-related equipment (including power equipment,

STATCOM equipment, cable equipment, ancillary equipment related to each equipment) construction, including system model

drafting, detail design, supply, test and installation, etc.

1.2 Job Content

Party B shall implement the provisions of the contract and the instructions of Party A/Engineering Department to perform relevant work, except for the contract and requirements

Request (1) In addition to the relevant regulations, Party B shall be responsible for the survey, design, manufacture, and test of the project.

Inspection, supply, transportation, storage, installation, inspection, testing, training and maintenance and other related work.

The main equipment and work items of the STATCOM system are as follows, and the relevant system architecture is shown in Figure 1.2-1.

But not limited to:

(1) Protection relay board for 161kV terminal equipment used by Zhanggong step-up station STATCOM (including

50BFÿÿ

(2) 161kV gas insulated switchgear (GIS). (3) Cable equipment.

(4) Indoor oil-immersed transformer (Coupling transformer). (5)

Medium voltage gas insulated switchgear.

(6) STATCOM equipment:

A. Reactor (air-core type) B. Charging resistor

(including bypass switch)

C. Voltage Source Converter (VSC) and Control System

D. Valve cooling system equipment

E. Protection system

F. Related Cable Materials

(7) SCADA and IEC 61580 system (detailed requirement book (4)). (8) Auxiliary equipment

required to protect the relay and various equipment.

1
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

(9) Supply of spare parts and tools.

(10) Maintenance. (11) Education and

training. (12) Handle the relevant

work required for STATCOM parallel trial operation and joining the system.

Among them, the rated voltage of STATCOM equipment may be determined by Party B according to the planned STATCOM system

system to adjust.

Figure 1.2-1 System interface of this project

1.3 Specification documents and their order of priority

If there is any conflict or inconsistency between the provisions of the specification, unless otherwise specified,

The priority order of application shall be determined according to the following order:

(1) Demand letter (2). (2) Technical

specifications for electrical equipment.

For the above-mentioned same document or illustration, the order of priority adopted shall be the one with the latest issuance time.

use.

2
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

Chapter II Relevant Guidelines

The installation, manufacture, testing and provision of materials of all equipment shall comply with the relevant standards of the Requirements (1)

It is required that if the above regulations and standards are not specified, the following latest laws, standards, testing rules or regulations shall be used

The applicable part of Fan et al. is its standard.

2.1 Reference Guidelines

All equipment and materials provided by Party B must be in accordance with the latest

Edition and the most applicable Ministry of Economic Affairs user electrical equipment installation rules, power transmission and distribution equipment installation rules, Taipower

The company's relevant specifications, the National Standards of the Republic of China (CNS), the International Electrotechnical Commission (IEC), the United States

National Electrical Code (NEC), American National Standards (ANSI or IEEE Std.), industry associations

Will set standards (such as NEMA, IPCEA, ISO, ASTM, UL, etc.) and other regulations and standards

The relevant regulations shall be handled.

2.2 Reference Specifications

The equipment provided by the electrical system that implements this specification shall comply with the user's electrical equipment installation rules,

Power transmission and distribution equipment installation rules, domestic environmental quality regulations (such as noise, non-ionizing radiation environment

recommended values, etc.), and relevant EN, CNS, IEC, NFPA or ANSI/NEMA standards and other

International standards, including but not limited to the following:

(1) Comply with the relevant design guidelines of each unit of Taipower Corporation

(2) Comply with the relevant operating standards of Taipower Corporation

(3) Main points of renewable energy parallel connection

technology (4) Main points of power dispatching by Taiwan Power Co., Ltd.

2.3 Abbreviations

EMC: Electromagnetic Compatibility Electromagnetic Compatibility

EMI: Electromagnetic Interference Electromagnetic Interference

GIS: Gas Insulated Switchgear Gas Insulated Switchgear

HV: High Voltage high voltage

LV: Low Voltage low voltage

3
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

MDF: Main Distribution Frame Main Distribution Frame

MV: Medium Voltage medium and high voltage

PCCÿPoint of Common Coupling

POCÿPoint Of Connection

STATCOM: Static Synchronous Compensator Static Synchronous Compensator Equipment

TPC: Taiwan Power Company Taiwan Power Company

TR: Transformer Transformer

VSC: Voltage Source Converter Voltage Source Converter

2.4 Definition of terms

(1) PCC (Point of Demarcation of Responsibilities): The point of connection between the STATCOM system and the power system.

(2) POC (parallel point): The parallel connection position of the STATCOM system in the power system.

(3) Reference Voltage (Vref) (reference voltage point): STATCOM system is

The voltage/current (V/I) characteristic point at which reactive power output is provided.

(4) Static Synchronous Compensator (STATCOM): Parallel reactive power compensation equipment that can provide or

absorb reactive power, and its capacitive or inductive output current can pass through

Adjust the independent AC system voltage for control.

(5) Submodule (submodule): Bypass components connected by full-bridge,

Power electronic switching elements, gate drive elements, power supplies, controllers, resistors, etc.

Equipment, together with the voltage source converter equipment composed of DC capacitors and related auxiliary equipment.

(6) VSC valve (valve): It is composed of several sub-modules connected in series.

(7) Response Time (Reaction Time): Refers to the response time from the control signal before the maximum overshoot occurs

The time required for the voltage to change to 90% of the target value after the signal input step changes.

(8) Settling Time (stabilization time): After STATCOM is started, the voltage is stable at ±5%

the time required.

(9) Slope (change rate): the control range under the nominal voltage, the change ratio of voltage and current

Rate.

(10) VSC (Voltage Source Converter): The DC voltage through the DC capacitor is passed through the power electronics

The switching element generates an AC voltage after switching.

4
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

Chapter III Engineering Requirements

3.1 Design Requirements

(1) Before designing, Party B shall carry out survey and relevant data collection of Zhanggong Booster Station and Yongxing Opening and Closing Station

(also known as Yongxing S/Y), including "Civil Engineering Design/Construction Turnkey New Project of Zhanggong Booster Station" (hereinafter

referred to as Zhanggong Step-Up Station New Project) and "Yongxing Opening and Closing Station New Project" (hereinafter referred to as Yongxing

Xing S/Y new project) underground cable layout space and route, switchgear number,

And contacts, etc., according to the design of STATCOM system related equipment.

(2) Party B shall properly review the space configuration of the equipment selected for the detailed design and provide civil works

Foundations, openings, embedded parts, etc. required for engineering.

(3) There must be good insulation coordination between the related equipment of the STATCOM system.

The failure caused an accident in Taipower's power system. Protective equipment shall not be caused by improper misoperation

Expansion of the fault range.

(4) STATCOM system-related equipment can be controlled in case of low voltage, overload, etc.

Conditions, or operation under the condition of partial equipment failure. If the system operates beyond the above conditions,

The STATCOM system should have relevant system and equipment protection measures.

(5) The operation of STATCOM equipment should comply with the noise control regulations of the local county and city government (if the local county

and city government has no noise control law, refer to the noise control standards of the Environmental Protection Agency of the Executive Yuan

handle).

(6) In addition to the following requirements on the design drawings of this project, relevant requirements should be drawn according to the illustrations of Taipower Corporation

Please handle it.

A. The configuration diagram of STATCOM system-related equipment should be drawn in elevation for clear labeling

Cable connection position and equipment configuration height.

B. The configuration of STATCOM system-related equipment needs to indicate the relative position of the building and

distance, and select the appropriate column center for its configuration datum reference point.

C. The connection of power cables for GIS, transformers, reactors, switchgear, etc. should be clearly marked

The location and phase sequence of the points, and the name of each circuit must also be marked.

D. According to the equipment required for the project drawn on the drawing, the equipment should be listed in detail in the equipment list

5
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

Material number, equipment name, specification, brand, quantity, unit, etc., the equipment must be numbered,

And there must also be a corresponding number on the electrical equipment diagram to indicate the installation location of the equipment.

UHV cable-related equipment only indicates the name and specification of the equipment, and the quantity is separate from the power supply.

The cable configuration diagram is indicated.

E. All designs must be represented by drawings, but if the drawings cannot be clearly marked, words can be used

Supplementary explanation.

F. Party B shall submit the list of cable numbers in accordance with Party A’s cable numbering principles, and shall be reviewed and approved

Only then can it be implemented. And according to the application of the cable marking label, mark the end of each cable

Indicates the input and output terminals.

G. Party B shall draw up the switch number in accordance with the principle of Party A’s equipment switch number, and after review and verification

It can only be implemented later.

H. The wiring method of the switchboard adopts the bottom incoming line in principle.

(7) The 161kV power cables and ancillary equipment used in this project must comply with the TPC specification for 161kV cross-

connected PE cable equipment of Taipower Corporation.

A046 (latest version).

(8) If 161kV GIS, 69kV GIS, 23kV GIS, IED etc.

The supply of all equipment and equipment must be products protected by the localization policy.

(9) The medium and high voltage switches used in this project shall not adopt the armored switch box type.

3.2 System Requirements

3.2.1 Architecture

(1) The rated capacity of the STATCOM system is ±200 Mvar, two sets are respectively connected to the 161kV UHV system busbar

(161kV GIS) of Zhanggong booster station and Yongxing S/Y 161kV

UHV system busbar (161kV GIS).

(2) The STATCOM system must provide at least 20 sets of other inactive power equipment (such as MSC,

MSR, etc.) and reserve system hardware and software capacity, related graphic control screen, connection interface, etc.

For subsequent expansion and integrated control, its control has automatic/remote operation mode. If the warranty period

, when Party A adds MSC or MSR equipment, Party B must cooperate to modify STATCOM

6
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

System graphic control software and add related lines to MSC or MSR equipment, and connect to

SCADA system, the fee has been included in the total contract price, and the completion date shall be specified by Party A

It is known that the detailed requirements for overdue penalties (1) stipulate the relevant penalties (15) in Chapter 11.

(3) The STATCOM system of the two case sites must be installed with 2 bays (bay) 161kV GIS, namely the line bay and the transformer

bay. Among them, the Zhanggong step-up station of the line stall is connected to Zhanggong

Newly established 161kV GIS for the new construction of the booster station; Yongxing S/Y connects to Yongxing S/Y new

The newly established 161kV GIS for the construction project.

3.2.2 Taipower system conditions

(1) According to Taipower Corporation's transmission system planning guidelines, not limited to the following items.

A. Voltage stability standard: under normal power supply conditions, the power system should maintain

The current converges and the voltage operation is between 0.95 pu and 1.03 pu, and the accident is between 0.9 pu and

1.05 puÿ

B. In case of N-1 accident, maintain a voltage stability margin of 5%.

C. In case of N-2 accident, maintain a 2.5% voltage stability margin.

D. Voltage change rate: the voltage change rate of the responsibility demarcation point caused by connecting to the Taipower company system,

In addition, the impact of the same step-up station/switching station or the same transformer or the same feeder has been approved for

grid-connected power generation equipment, and does not consider other system background values, such as loads, energy storage systems

System, etc., should be within 3% of the high and low.

E. System stability: UHV system above 161kV is connected in parallel, and the parallel contact belongs to

The busbar of the booster station/switching station shall not reduce the transient stability of the Taipower company system to

Below the specified value: 161kV system three-phase fault critical clearing time takes 12 cycles as

Standard, if eight to twelve cycles should use two sets of full-line section fast main protection relay.

(2) Frequency range: 60±0.2Hz.

(3) Fault current at 161kV busbar terminal at Zhanggong step-up station terminal: the maximum three-phase fault current is 50kA;

The minimum three-phase fault current is 37.046 kA; the maximum single-phase fault current is 39.644 kA; the maximum

Small single-phase fault current 36.577 kA (Party B shall provide Party A with the latest

material).

7
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

(4) Fault current at 161kV busbar terminal at Yongxing switching station: maximum three-phase fault current 50kA; minimum three-

phase fault current 22.722 kA; maximum single-phase fault current 30.699 kA; maximum

Small single-phase fault current 22.317 kA (Party B shall provide Party A with the latest

material).

(5) Harmonic current: merged into the system's responsibility demarcation point end, the responsibility demarcation point end,

continuous operation must comply with the standard harmonic current control standard of IEEE 519 (2nd to 50th).

(6) The continuous negative sequence voltage unbalance rate (Voltage Unbalance Factor) shall not be greater than

1%, where the negative sequence voltage unbalance rate = negative sequence component size / positive sequence component size × 100%.

The unbalance rate of negative sequence voltage in a short time (15 minutes) shall not exceed 1.2%.

(7) STATCOM is connected to the 60Hz three-phase of the step-up station/switching station of the Taipower Company to which it belongs

AC 161kV system, the power supply is an effective grounding system.

3.2.3 STATCOM System Feature Requirements

(1) VI characteristic curve (VI Curve)

Operational capability of STATCOM (excluding MSC and MSR) integrated into the system

At least the following requirements should be met, and the system voltage should be determined according to the voltage of each system grid-connected point

Reference.

A. The STATCOM system must be able to adjust the grid-connected point voltage to the system voltage reference value (this function

The maximum continuous output capacitive reactance (capacitive reactive power) is 200Mvar (1.0pu) at a system

frequency of 60Hz and an ambient temperature of 20°C.

Refer to point A of the VI characteristic curve in Figure 3.2.2-1.

B. The maximum continuous output inductive reactive power of the STATCOM system at rated voltage 1.0 pu, system

frequency 60Hz and ambient temperature 20°C is

200Mvar (1.0pu), refer to point B of the characteristic curve in Figure 3.2.2-1VI.

C. The slope range of VI characteristic curve under the capacity of 400 MVA (Figure 3.2.2-1 A+B)

From 0% to 10%, the adjustable step change is 0.5%.

D. The STATCOM system must be capable of continuous operation down to 0.3 pu and continue until

Jump out after at least 2 seconds.

8
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

E. The STATCOM system must be able to achieve a maximum overvoltage of 1.3pu in a short period of time through the control system

It will trip out after running continuously for at least 2 seconds under the same conditions.

The maximum capacitive reactance value of point A under continuous operation

The maximum inductance value of point B under continuous operation

Points C and C' can allow short-term overrunning

The inductive rated current at point D (at point B) extends upwards until the allowable upper limit of overvoltage

Extension of capacitive rated current at point E (at point A) and maximum reference voltage (at point K)

The maximum reference voltage at point F (point K) and the extension of the maximum voltage control slope

Allowable capacitive current rating for short-term operation at point G

Extension of minimum reference voltage at point H (at point M) and maximum voltage control slope

Extension of line ILrated-B at point J at minimum reference voltage (M) and minimum slope

L point nominal reference voltage

Figure 3.2.2-1 STATCOM system VI characteristic curve

(2) Response time

Response time is defined as a step change from the control signal input before maximum overshoot occurs

After that, the time required for the voltage to change to 90% of the target value.

For the control device of the STATCOM system, the voltage response of the STATCOM system

It should be 2.3% for Zhanggong booster station when the reference voltage is measured, and Yongxing S/Y is

After a 2.2% step change, the required change must be achieved within 40ms (initial voltage

9
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

90% of the difference from the steady-state voltage). The maximum overshoot should not exceed

Over 110%, the settling time should not exceed 100ms, and the voltage stabilization should be within ±5% of

the final value. Restart time (re-start time) should be less than 100ms

Inside. The standard diagram of relevant reaction time is shown in 3.2.2-2.

Figure 3.2.2-2 Response curve of STATCOM system

(3) Restart time (re-start time)

Restart time is defined as when the system fails, the output of STATCOM is

The output of reactive power is limited due to undervoltage. When the system voltage recovers, STATCOM

Time for the reactive power output capability to return to normal. Restart time (re-start time) is not

Should exceed 100ms.

3.2.4 Running operation and control mode

(1) Operating capability

A. Normal Operation

(A) The STATCOM system shall be capable of normal and continuous operation of capacitive and inductive

set the output.

(B) Party B shall provide power system stabilizer (PSS or POD (Power

Oscillation Damper), the control system design must be carried out and submitted to Taipower Company

for review, and the STATCOM model and parameters applicable to the PSS/E software must be provided

number.

(C) The voltage reference value of the STATCOM system is under the rated capacity of the system, and the slope can be

Continuous adjustment between 0~10%.

10
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

(D) The STATCOM system shall, under dynamic conditions, vote for all MSCs and MSRs

All operations can control the stability of the system.

(E) The control system must adopt programmable editing, and allow Taipower Company to connect to the grid according to

For the compilation of the change adjustment program of the point power system, the interface of the operating system must be

The operation is completed under the WINDOWS environment.

(F) Party B shall provide the start and stop operation sequence of STATCOM system to confirm

Ensure the smooth operation of the STATCOM system.

(G) The STATCOM system shall be capable of being activated and deactivated after a signal has been sent locally or remotely

Automatic operation.

B. Overcurrent and Overvoltage Operation

(A) The STATCOM system needs to maintain the output capability continuously at a parallel contact voltage of 1.1 pu.

(B) The STATCOM system needs to maintain the output capability for 2 seconds at a parallel contact voltage of 1.3 pu.

(C) The STATCOM system needs to be in the operating range to operate the inductive and capacitive

110% capacity output capability, maintain for 2 seconds.

(D) The STATCOM system must continue to operate normally at 58.5Hz~61Hz in accordance with the technical points of

parallel connection of renewable energy power generation systems promulgated by Taipower Corporation;

57.5Hz to 58.5Hz must run continuously for 30 minutes; frequency is 57.0Hz to

Must run continuously for 20 seconds at 57.5Hz; allowed when frequency is lower than 57.0Hz

The STATCOM system is separated from the Taipower system.

(E) The maximum frequency change (df/dt) is ±1.3 Hz per second.

C. Undervoltage Operation (A) The STATCOM system needs to maintain the output

capability continuously at the parallel contact voltage of 0.9 pu.

(B) The STATCOM system needs to maintain the output capability for 2 seconds at a parallel contact voltage of 0.3 pu.

(C) Undervoltage operation is not affected by short-term negative sequence voltage.

D. Control and coordination of external virtual power equipment

The control system must be able to adjust the grid-connected point voltage and incorporate the existing MSC and MSR

In addition to control, at least 20 sets of other invalid power equipment are provided for subsequent expansion of the whole

11
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

joint control. Its controls have at least an automatic/remote mode of operation.

The STATCOM system must switch between MSCs and MSRs under dynamic conditions

can control the stability of the system.

The control system must adopt programmable editing, and be able to

For the compilation of changing and adjusting programs, the interface of the operating system must be WINDOWS

The environment operation is completed.

(2) Control mode Party

B shall provide at least the following STATCOM control modes and their operation priority

order, and the control between modes must be able to switch smoothly.

A. Fixed reactive power mode (fixed reactive power mode, FQM).

(A) This mode can be controlled by the system operator STATCOM fixed output -200MVAr

Reactive power output to +200MVAr, and manual operation of MSCs and MSRs

do.

B. Voltage control mode (voltage control mode, VCM).

(A) The voltage control mode is that the control system detects the grid-connected point voltage, according to the VI characteristic

The slope range of the characteristic curve is used for voltage control, so that the grid-connected power voltage can be stably controlled

It is within the conditions of Taipower Grid Regulations.

(B) The control mode shall be operable under steady state and dynamic operation of the power system.

(C) The error of voltage measurement and signal conversion shall not exceed 0.3%. voltage detection circuit

The response time shall not exceed 16ms.

C. Undervoltage Control

(A) The controller shall detect the voltage before and after the failure of the system.

(B) When the system fails, any phase voltage of the three-phase voltage is lower than 0.3pu,

The undervoltage control mode should be implemented, and the control system turns off the voltage control mode

(VCM), STATCOM does not output any reactive power, if the undervoltage maintains more than

2 seconds, the STATCOM should be closed. When the system voltage detection is higher than 0.4pu,

And the control system can return to normal only after the troubleshooting is confirmed by personnel.

12
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

run.

(C) The control mode must be operable under steady state and dynamic operation of the power system.

D. Overvoltage control

(A) The STATCOM system needs to maintain the output capability for 2 seconds at a parallel contact voltage of 1.3 pu,

If the overvoltage exceeds 2 seconds, the STATCOM should be closed. When the system voltage detection is low

When it is at 1.2pu, the control system can resume normal operation only after the personnel check and

confirm that the fault is eliminated. (or according to the bidding documents)

(B) The control mode shall be operable under steady state and dynamic operation of the power system.

E. Supplementary control function (supplementary control)

(A) Gain regulation control (Gain supervision)

By automatically or manually adjusting the gain of the regulator (regulator) of the control system, the

STATCOM system can reduce oscillation and overshoot during the response process

(overshooting) situation occurs.

(B) Gain optimization adjustment control (Gain optimization)

Gain optimization adjustment control performs gain self-control by detecting the signal of grid response

adjust.

F. Power System Stabilizer (PSS) Control Function

In order to increase the system damping and improve the small signal stability margin of the system, STATCOM

The system must have the power system stabilizer control function.

3.2.5 Protection relay system

(1) Protection system planning is based on Taipower Corporation guidelines, power system protection relay planning guidelines, and Taiwan

Gulf Power Company’s transmission and power supply business department’s protection relay standard setting guidelines, UHV user’s power consumption equipment

Prepare design data review operation standard procedures and review requirements, and

After discussing with the relevant units of Taipower Corporation, according to the characteristics of Taipower system at the parallel contact end

Design and protect the electric relay type for planning, and submit the protection electric relay planning and calculation documents.

(2) STATCOM system equipment protection relay equipment includes but not limited to the following:

A. Transformer: overcurrent relay, differential relay, grounding relay, sudden voltage relay, release voltage relay

13
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

Relay, Brinell relay, oil temperature detection, over excitation protection, overload protection, overheat protection

B. AC Busbar: Overcurrent Relay, Differential Relay, Ground Relay

C. VSC valve parts: differential relay, overcurrent relay, overvoltage relay, high temperature detector

D. DC Bus: Overvoltage Relay

E. Controller: control power needle test, synchronous signal detection

(3) Yongxing S/Y Base, 161kV GIS line protection relay at the line end submitted by the manufacturer

The specification must be the protection relay of the 161kV terminal equipment used by Yongxing S/Y end STATCOM

The brand name and specifications must be consistent. The specifications of the rest of the protection relays are detailed in the appendix of the requirements document.

Post equipment specifications.

3.2.6 Control system

Party B shall carry out the work according to Taipower Corporation's IEC 61850 specification and requirement book (4).

Communication transmission planning of STATCOM system and SCADA system.

Party B shall provide the design description of the STATCOM control system, including but not limited to: control system

architecture, function description, detailed start, trip, stop,

Fault isolation procedures, interlock protection mechanisms and operation procedures of backup systems.

3.2.7 Calculation of the overall loss of the system

Party B shall calculate the total loss of the power equipment related to the project according to the IEEE 1031 standard.

Among them, high and low voltage switchgear, bus bars, cables, barriers, connectors, etc., are not included in this loss

The consumption calculation evaluation range is explained as follows.

(1) The total loss must be estimated based on the ambient temperature of 20°C, the grid-connected voltage of 1.0pu and the slope

of 5%. The operating capacity states are 100% inductive, 50% inductive, 0%, 50%

Capacitive, 100% capacitive output. .

(2) VSC loss

Including power electronic switches, capacitors (DC capacitor), resistors, inductors and

Its conductor elements, and carry out the loss calculation according to IEC 62751-2. Redundancy equipment will still be

included in the loss calculation.

(3) Transformer loss

14
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

Transformer equivalent resistance should be calculated using its full load condition. Through this resistor and

The STATCOM operation calculates the total loss (including no-load loss, full

load loss, auxiliary power loss).

(4) Reactor loss

The reactor loss shall be calculated according to Annex B.5.7.5 of the IEEE 1052 standard.

(5) Loss of auxiliary equipment

Auxiliary equipment is the mechanical and electrical facilities necessary for the operation of STATCOM, including pumps, air

Adjustment, ventilation, etc., the output capacity varies according to the environment, STATCOM output capacity, etc. auxiliary

To assist in the calculation of the loss of power supply, Party B must first estimate the loss based on the capacity of the equipment submitted.

However, the actual measurement and comparison must be carried out after the equipment is installed, and the backup equipment may not be included in the loss

lose.

(6) Control and protection

equipment (7) Valve cooling system

equipment (8) Total loss calculation

The total loss is STATCOM. Under the capacity output of (1) and the steady-state operating range of the

system voltage 1.0pu, calculate the above items (2)~(7) and draw the loss curve. The maximum total loss

calculated by the sum of all equipment shall not be higher than that of the STATCOM system

2% of capacity.

(9) Annual Reliability and Availability

A. Definition

(A) Forced outage

Downtime caused by STATCOM system equipment failure, resulting in

Loss of some or all of the basic functionality of the STATCOM system.

(B) Scheduled outage

Stoppages necessary for preventive maintenance to ensure that the STATCOM system can

Continuous and reliable operation. This outage will result in some or all of the STATCOM system

system temporarily fails.

15
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

(C) Outage duration

Time from STATCOM system shutdown to recovery (in small

unit of time). The following items are covered by this interruption period:

a. To determine the cause of the downtime, to determine the repair or replacement of original parts and

Downtime.

b. The system operator switches off and completes grounding in preparation for maintenance work and

The time required to remove the ground and reconnect the switchgear after repairs have been completed.

Delays caused by maintenance personnel without qualified certificates will not be counted as downtime.

B. Annual availability is the proportion of forced downtime in one year, and the reference formula is as follows: ÿ ÿ ÿ

D ÿ
ÿ
1
ÿÿ 8760
100%
ÿÿ

where D is the duration of the equivalent mandatory shutdown in hours

C. Reliability refers to the normal operation of the STATCOM system, under certain time conditions

The probability of normal performance, usually called the mean time between failure MTBF (Mean

Time Between Failure), the reference definition is as follows:

Annual reliability = number of trips during 12 months of continuous operation

D. Reliability and availability requirements

(A) The annual availability of the STATCOM system due to mandatory outages shall be at least 99%.

(B) The number of forced shutdowns of the STATCOM system should be less than 2 times per year.

(C) The number of maintenance shutdowns of the STATCOM system should be less than 1 per year.

(D) If the actual performance is different from the values specified in (A) and (B) above, B

The party shall provide an improvement plan to meet the availability guarantee.

3.3 System and equipment capacity analysis

Party B shall provide system simulation, calculation, evaluation and other materials before equipment manufacturing, not limited to the following

List. Power system simulation system analysis, limited to use simulation software of PSS/E V34 or above

analyze. The simulation results must meet the requirements of Taipower system and requirements, and no matter heavy load or light load, normal

And the compensation of reactive power and system stability in abnormal conditions.

16
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

(1) Consider factors such as the maximum allowable error of transformer impedance, continuous negative sequence voltage component, maximum

continuous operating frequency, maximum continuous operating voltage and other factors to calculate the number of sub-modules and the rating of each device

Constant voltage, current, frequency, insulation level, etc.

(2) Calculation of the output capacity of the STATCOM system, and the system operation in overvoltage, undervoltage

Time limit analysis under voltage and over-current operation.

(3) Dynamic and stability simulation analysis

A. Confirm with PSS/E simulation software based on the actual model of the equipment (not a simplified model)

VI characteristic curve parameters of STATCOM system.

B. Transient overvoltage analysis and control performance

(A) Analysis of STATCOM system startup (including transformer loading), shutdown or power system N-1, N-2

accidents.

(B) Fault current analysis of high-voltage and low-voltage busbars (including single-phase-to-ground faults,

phase-to-phase fault, three-phase-to-earth fault).

(C) Analysis of valve mistriggering events under the most severe system conditions.

(4) Analyze the dynamic characteristics of the system to confirm the dynamics of STATCOM when the system is disturbed

Yes, its analysis content includes but not limited to:

A. Analyze and verify that STATCOM can provide proper dynamic control to meet power system

System and STATCOM system performance requirements.

B. Verify STATCOM system response time and power system recovery after failure

ability.

C. Analysis and verification When the power system is disturbed, supplementary control (supplementary

controls) power shock suppression function.

(5) Use the power system analysis software PSS/E to conduct system response analysis, not limited to the following items

simulation:

A. Steady-state simulation

(A) Before and after STATCOM installation, the system is under normal operation under heavy and light loads (N-0)

Check the voltage and power flow.

17
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

(B) Before and after STATCOM installation, when the system is under heavy or light load, the voltage and power

flow detection of N-1 and N-2 accidents occurred in the equipment near the step-up station/switching station

discuss.

B. Dynamic Simulation

(A) For N-1 and N-2 accidents when STATCOM is not installed in the system,

Perform dynamic response analysis for scenarios with the most severe voltage rise/fall across parallel contacts. Re-execute

Perform dynamic response analysis after installing STATCOM, and include MSC, MSR,

Perform a comprehensive simulation.

(B) The booster station/switching station end connected to the STATCOM system in parallel, under heavy load, light load or occurrence

When the maximum and minimum power generation capacity occurs, the three-phase short-circuit fault analysis of the parallel contact voltage occurs,

If it is an ultra-high voltage substation system, a 345kV three-phase short-circuit fault analysis must be added.

(C) LVRT and

Voltage response of HVRT.

3.4 File Submission

Party B shall formulate the specifications for this project in accordance with the requirements of STATCOM and power system related equipment specifications.

relevant documents required.

(1) Party B shall prepare according to the contract and demand letter (1) and this demand letter and the requirements of Party A/Engineering Department

Order and submit relevant documents required for this project.

(2) The relevant planning documents, drawing materials, reports and various forms submitted by Party B shall be documents in

traditional Chinese (except numbers or English codes), and shall be reviewed in accordance with the relevant regulations.

Sequence for review. For English speakers, Chinese-English comparison is required.

(3) Party B shall submit the relevant documents required for this project in accordance with the contract, demand document (1) and this demand document.

Documentation should include but not limited to the following items:

A. Detailed design results

(A) Configuration diagram

Basic configuration diagram, grounding system configuration diagram, equipment (machine) configuration diagram,

Cable configuration diagram, cable tray configuration diagram, switchboard layout diagram, control panel

18
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

Configuration diagram, configuration diagram of relay board, detailed diagram of equipment (including size and weight), etc.

(B) Design drawings

Single-line diagram, DC low-voltage single-line diagram, cable circuit design diagram, cable circuit

General diagram, grounding design diagram, control logic circuit diagram (hardware and software), electrical

Cable core wire diagram, equipment internal wiring diagram, wiring diagram, etc.

(C) Calculated data

a. STATCOM system simulation analysis report (limited to PSS/E software),

The content includes VI characteristic curve, and system operation data, etc., and provides

STATCOM equipment model for reading and editing by PSS/E software.

b. Control procedures for STATCOM, MSRs, MSCs stabilization systems

c. Coordination analysis of lightning surge and equipment insulation (insulation of each power equipment

Class, arrester rating, creepage distances (creepage distances)

and clearance)

d. Grounding system protection and calculation analysis

e. System Protection Coordination Analysis

f. Simulation analysis of magnetic field strength of air reactor (using finite element method)

g. Harmonic Calculation

h. Earthquake calculation of equipment

i. DC system calculation

j. Calculation of cable tension

k. STATCOM system overall loss calculation

l. Power submission materials

m. Relevant calculation documents required in the demand letter

(D) Measurement report

a. Magnetic field strength measurement

b. Noise measurement

19
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

c. Measurement documents required in the demand letter

(E) Other documents related to this project

STATCOM and power system equipment specifications and quantity statistical tables, cables

analysis table etc.

B. Construction Phase Results

(A) Test plan and procedures

Test plan (single equipment and system test), etc.

(B) Product specifications and catalogs

161kV GIS, STATCOM system related equipment and accessories of each equipment

Equipment, wall bushing, cables and others used in this project

related equipment, etc.

(C) Construction drawings

Equipment manufacturing drawing, parts list (including materials), assembly drawing, equipment installation

Installation construction drawings, cable construction drawings, etc.

(D) Suggested list of spare parts and tool supply

List of spare parts, consumables, special tools and special testing equipment, etc.

C. Test report file

(A) Equipment/Product Test Report

Equipment/product factory test report, laboratory test report, etc.

(B) Self-inspection test report

Equipment test report, etc.

(C) System Test Report

System test report, on-site sub-item test report, etc.

D. Education and training documents

Training materials and handouts (including electronic files), training process video CD, training

Course video CDs, training effectiveness reports, etc.

20
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

E. Maintenance Documentation

System equipment stability and fault statistics, fault handling report, fault analysis report

report, deadline improvement report, etc.

F. Completion acceptance documents

Completion charts of each stage, project settlement schedule, equipment delivery list, various verification

The prescribed construction drawings (the standard drawing frame of this project must be applied and signed off), various test reports

report, system guarantee data, operation and maintenance manual, substation equipment history card, etc.

(4) Party B shall handle it according to the relevant documents and delivery time stipulated in the contract and demand letter (1)

Submission matters shall be carried out after review and approval by Party A/Engineering Department. File Category

Submission Review Time Item

A. Detailed design results (A)

Configuration drawings (B) Design

drawings (C) Calculation data B.

Construction stage results (A) Test plans

and procedures (B) Product specifications

and catalogs (C) Construction drawing spare

parts and tools supply suggested list

(D) C.

Test report documents (A) Equipment/

product test reports (B) Self-inspection test reports Within 7 days before quality inspection

(C) System test reports D. Education and training

documents E. Obstacle duty and maintenance

documents System equipment stability and failure Detailed requirements (1) and equipment specifications

statistics per Submit the data of the previous month before

the 7th of each month. Submit the data of the previous month before the 7th of each month. Fault handling report.

Fault analysis report within 7 days after the fault. Improvement report
andwithin
acceptance
14 daysdocuments
after the fault
within
. F.the
Completion
previous 7

days

21
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

3.5 Obstacle removal work

Party B shall assign the STATCOM system immediately after the parallel test run to the end of the warranty

Maintenance engineers handle troubleshooting operations, and the dispatch and appointment of their personnel must be in accordance with the provisions of the Labor Standards Act

For processing, the relevant regulations are as follows.

(1) According to the obstacle removal duty plan and power system maintenance and inspection proposed by Party B and reviewed and approved

Check operating procedures and other regulations.

(2) The obstacle removal duty plan must at least include the following.

A. Roster of maintenance personnel on duty (resume with training records).

B. On-duty maintenance work implementation schedule, including regular maintenance cycle (not lower than Taipower

The standard of the company's relevant specifications), maintenance content, maintenance record form, person in charge, machine

Tools, inspection and repair tools, transportation and spare parts, etc.

C. On-duty maintenance work organization table.

D. Emergency Contact Form.

E. Safety and health management system form.

(3) Qualification of Obstacles Elimination of Duty Personnel

According to the regulations of Taiwan Power Company, set up full-time electrical technicians, and participate in this

More than 1 year experience in engineering design or construction, the engineer needs to have independent experience in system troubleshooting

Ability to work.

(4) Obstacle removal duty schedule

Troubleshooting and maintenance of equipment after parallel trial operation and before the end of warranty

Party B shall be responsible.

(5) Scope of obstacle elimination: related equipment of STATCOM system in this project.

(6) Obstacle removal work content

The work content includes regular maintenance, inspection, adjustment, troubleshooting, repair, accident

Emergency repair and equipment failure records and failure analysis to maintain the normal operation of the system.

(7) The garrison regulations for strongholds are as follows

There must be an engineer who is qualified as an obstacle removal duty officer at the base 24 hours a day

22
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

Stationed, and cooperate with the implementation of STATCOM system equipment obstacle elimination. Staff on duty till now

Field maintenance requires self-provided locomotives or cars as means of transportation.

(8) The on-duty personnel should wear professional clothing and wear the unit identification card, armband and Taipower work card, etc.

when on duty.

(9) After the fault is repaired, the inspection and repair process, fault cause, treatment method and improvement plan should be submitted

to Party A/Engineering Department for review. When the failure time exceeds the contract, according to the demand letter (1) related

stipulated.

(10) When Party B receives the notification from Party A or the maintenance and operation unit, Party B shall immediately send personnel to

repair it. For major faults that affect the normal operation of the system, Party B shall repair and resume normal operation within 6 hours.

For other failures, Party B shall repair them within 12 hours.

(11) According to the data recorded by the fault record monitoring device, Party B shall submit abnormal event statistical reports to Party A

before the 5th of each month. If abnormal events can be attributed to failure or damage of equipment, equipment, poor construction,

etc., failure analysis and improvement records should be submitted together.

3.6 Maintenance

(1) Handle in accordance with the reviewed and approved maintenance plan proposed by Party B. (2)

The content of the maintenance plan must at least include the following.

A. Roster of maintenance personnel (resume list with training records).

B. Maintenance work implementation schedule, including regular maintenance cycle (not lower than that of Taipower Company)

Standards for relevant power system inspection procedures), maintenance content, maintenance record forms,

Person in charge, equipment, etc.

C. Maintenance work organization form.

D. Emergency Contact Form.

E. Safety and health management system form.

(3) Qualifications of maintenance personnel

who have participated in the design of this project and must receive professional training on the maintenance of original

STATCOM equipment and obtain relevant certificates approved by the original factory. The engineer must have system troubleshooting skills

Ability to work independently.

23
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

(4) Maintenance schedule

The maintenance of the equipment during the warranty period shall be the responsibility of Party B.

(5) Maintenance scope: STATCOM and power system related equipment of this project. (6) Contents of

maintenance work

The operation content includes regular maintenance, inspection, adjustment, obstacle removal, repair, accident

Emergency repair and equipment obstacle analysis to maintain the normal operation of the equipment.

(7) Party B shall prepare the spare parts and consumable materials required for maintenance operations, and the related costs

Included in the total contract price, no additional payment will be made.

(8) The operation of consumable materials that must be regularly cleaned, inspected, lubricated, adjusted, replaced or added by the

original manufacturer is a regular maintenance, and Party B shall send personnel to carry out the work and complete the execution

The maintenance report shall be sent to Party A/Engineering Department for reference.

3.7 Spare parts and tools supply

Party B shall provide

Supplies, consumables, special tools and special testing equipment.

3.8 Education and training

Party B shall handle the contract in accordance with the contract, demand document (1), this demand document and equipment specifications

STATCOM system education training.

(1) The content of installation training must at least include: pre-installation inspection, installation precautions, adjustment,

Setting, testing, calibration techniques and trial operation methods, etc.

(2) The content of the operation training must at least include: inspection steps, operation inspection, cleaning methods,

Inspection of oil or gas, filling method of lubricating oil, etc. Training materials must provide

Maintenance tool list and maintenance equipment list.

(3) The content of maintenance training must at least include: spare parts list, replacement of various spare parts, installation method

Types, equipment characteristics and maintenance methods.

24
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

Chapter 4 Engineering Interface

This chapter only describes the STATCOM system equipment and construction civil engineering, SCADA system based on past experience.

The interface and scope of work between system engineering to ensure that all system engineering can be coordinated with each other to achieve successful parallel connection

Trial run, adding system operation and complete operational performance. At any stage of work, its interface work division or

If there are any contradictions or omissions in the interface, Party B shall be fully responsible for coordinating and handling them. If Party B fails to properly

Proper handling, or the consequences of project omission or duplication of work due to matters not reminded in this chapter, must be handled by the

Party B is responsible for the completion of the processing, and there is no additional price.

4.1 Interface between STATCOM system and the power system of the temporary bidding project

The interface between this project and the new project of Zhanggong Booster Station is summarized in Table 4.1-1;

Table 4.1-2 shows the relevant interfaces of Xing S/Y new construction project. If Party B damages the

Relevant facilities that have been completed or have been completed by other projects must be restored, and the relevant fees are included in the contract

The total price is not calculated separately.

Table 4.1-1 Interface between this project and Zhanggong Booster Station New

construction of Zhanggong Booster

Station
item project Remarks from Party B

The newly established positions and


The 161kV GIS room of the new construction of Zhanggong booster
switch numbers are provided by
1
station was installed and tested with 161kV GIS switch for STATCOM. THE D
Taipower Corporation. The cable

terminal processing head shall be

161kV terminal equipment protection relay board (including 50BF) for provided by Party B. The installation
2 D THE

STATCOM at Zhanggong step-up station. 161kV GIS cable terminal location must be coordinated with Taipower.

box connection, 161kV cables and various signal lines, and related
3 cable fixing parts, cable racks and other facilities required for leading D THE

to this project. Before construction, Party B shall confirm the setting

space for the cable arrangement room and culvert of the new project

of Zhanggong Booster Substation, so as to plan the distribution path


4 D THE

of 161kV cables.

Note: ÿ is the person in charge of the main work ÿ is the assisting person

25
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

Table 4.1-2 Interface between this project and Yongxing S/Y

Yongxing S/Y
item project Party B Remark
new construction

The newly established positions and switch


Yongxing S/Y new construction 161kV GIS room added 161kV
numbers are provided by Taipower Corporation.
1
GIS switch for STATCOM THE D
The cable terminal processing head shall be
Install and test.
provided by Party B.

The 161kV protection relay at the

161kV terminal equipment protection relay board (including 50BF) STATCOM terminal requires Party B to use
2 THE D
for Yongxing S/Y terminal STATCOM. the same brand and specifications as the

Yongxing S/Y terminal.

161kV GIS cable terminal box connection, 161kV cables and

various signal lines, and related cable fixing parts, cable racks
3 D THE

and other facilities required for leading to this project. Before the

construction, Party B shall confirm the installation space of the

cable arrangement room and culvert of the new construction of

Yongxing switchgear, and plan the distribution route of the 161kV


4 D THE

cables accordingly.

Note: ÿ is the person in charge of the main work ÿ is the assisting person

4.2 Interface between STATCOM system and civil engineering and auxiliary mechanical and electrical engineering

The system shall provide various switchgear, substation equipment and line layout related to civil works

and other detailed diagrams (including grounding system), including related information such as openings, loads, embedded accessories, bolts, etc.

Materials, in order to revise the civil engineering drawings. And in accordance with the civil construction schedule, the construction is pre-embedded or modified and adjusted.

(1) Party B of the STATCOM system shall provide the following works before the construction of each structural unit in civil engineering:

The engineering drawings are used as the construction basis for the civil works:

A. The construction interface drawing of the equipment.

B. The drawings of the pre-embedded objects that must be matched with the walls, columns, and floors of each floor.

C. The construction steps of each floor and the relevant interface diagrams of decoration materials.

D. Before the equipment enters the site, detailed drawings of the conditions that need to be coordinated by the civil engineering.

E. Strength of secondary concrete.

F. The basic configuration diagram of the reactor and the relative position configuration with the adjacent structures.

26
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

(2) Unless otherwise specified, foundations, floors, walls, roof openings, ground levelling, cable openings

Holes and their covers are within the scope of civil engineering work.

(3) All the embedded objects required by this system, including bolts, embedded iron plates, pipe support frames and embedded bolts of H-shaped steel, shall be

supplied and installed by Party B. All buried objects except warp armor

Unless otherwise agreed by the Party/Engineering Department or otherwise specified, it shall not be painted or coated.

(4) Party B shall mark the position, size and material of the buried objects in detail and completely on the drawing for reference in civil engineering.

(5) The concrete for the buried objects required by this system shall be implemented by civil engineering, and Party B shall assign the staff responsible for this work to

be present, and the foundation of the equipment shall be filled by Party B of this system.

Responsible. The secondary concrete backfill at the reserved hole of the buried object shall be performed by Party B of this system.

Not separately priced. But the secondary concrete of all GIS rooms belongs to the scope of civil engineering construction.

(6) When Party B evaluates and considers it necessary, if it is necessary to excavate pipelines or add culverts and other civil engineering facilities, Party B shall handle

it by itself without additional pricing. However, it is necessary to modify or add related facilities of the completed building or to dismantle the related equipment

of the completed building or to modify the foundation of the substation equipment, cable holes, reserved holes, reserved pipes, etc.

The company is responsible, and the material costs, construction wages and storage costs for relevant modifications are included in the project

Not included in the total price. (7) The time

schedule for the heavy electrical equipment to enter the site, in principle, the indoor decoration is completed and the mobile crane and electric equipment are obtained.

After using the ladder license.

(8) Party B is also responsible for the fire retardant materials and construction required by this system, and the cost has been included in the project

In the journey fee, there is no other price.

(9) Pipelines or cable brackets pass through floor openings and partition walls, and must be responsible for construction and repairs to comply with

According to the specifications and fire regulations, the relevant costs are already included in the project cost and will not be priced separately.

(10) Party B must provide the cable bracket/tray configuration diagram and be responsible for the supply of materials, and must cooperate with the civil engineering schedule

Install the necessary embedded parts.

(11) The temporary lighting, ventilation and drainage equipment necessary for Party B in the workplace shall be provided by Party B

provided by the party itself.

(12) Party B shall provide grounding design and provide civil works for construction.

27
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

(13) Party B must confirm the cable installation space before construction, and plan the configuration of 161kV cables accordingly

path.

4.3 STATCOM system and SCADA system engineering interface

The SCADA system reserves at least 2 RJ-45 network communication interfaces, which are connected by the STATCOM system

The system is connected to the reserved interface, and IEC61850 is used as the transmission protocol between them.

28
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional

requirements

Chapter 5 Functional Requirements of Main Materials and Equipment

The functional requirements of the main materials and equipment of this project are also detailed in the equipment specifications in the appendix of the requirements document.

29
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project

requirement book (2) STATCOM system functional requirements

Chapter VI Inspection and Testing

According to the inspection and testing in the demand letter (1), and the specification requirements, among them, the factory test and work

The ground test is supplemented as follows.

6.1 Factory test

(1) The equipment should be tested according to the standard procedure of the manufacturer. Tests of GIS, transformers,

VSC valves, etc., and all other specific test requirements must be handled in accordance with equipment specifications.

(2) Unless otherwise specified, if the equipment is a standard product or similar to a standard product, or a prototype and

similar in size or capacity, the manufacturer's previous tests for the standard or prototype equipment

The test data can replace the specified test, but it must be approved by Party A/Engineering Department first.

(3) Party B must conduct system simulation verification through RTDS (Real Time Digital Simulator) to prove the correctness

of the control system operation, and provide RTDS that can be read and edited

The model file.

6.2 Site test

(1) The test should be performed by qualified personnel in accordance with the approved procedures. All equipment and instruments

required for the test, except for some special equipment (supplied together with the equipment to be tested), should be provided by

provided by Party B.

A. Accuracy: Calibration records for each instrument must be attached to the test, any test instrument

The use should be tested and approved by the authorized unit in advance.

B. Checklist: Each machine part should have a checklist. This checklist should include each control

devices, relays and gauges or instruments, an operational test should be performed first to ensure that all control

Correct operation of systems and devices.

(2) Special requirements: After the equipment has been inspected, adjusted and placed in an appropriate operating state, it should be

tested on site. The test proves that the function of the device complies with all the requirements of the specification, and must

include but not limited to the following items:

A. Continuity Test.

B. Insulation test.

C. Control, measurement and protection function tests.

30
Machine Translated by Google

Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.

Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project

requirement book (2) STATCOM system functional requirements

6.3 System Integration Test

After all the equipment has completed the factory test and site test, the auxiliary power supply system is completed until

The power transmission operation at the interface end is necessary to carry out the system integration test operation to ensure that all equipment is operating normally and

STATCOM performance meets specified requirements.

Party B shall test the specified requirements in accordance with other system requirements documents, and handle the STATCOM system and

For other related system integration testing work, the STATCOM system must be tested according to the content of IEEE 1303.

Trial work.

6.3 After the commissioning tests are connected in parallel with the

Taipower grid, the STATCOM system must comply with IEEE 1303 content and technical specifications

Fan STC1 handles and tests homework.

6.4 Performance verification of STATCOM system parallel test run

(1) In accordance with the relevant approved standards of Taiwan Power Corporation, "Taiwan Power Corporation

"Contact Key Points for Power Transmission and Transformation Projects of the Power Transmission and Power Supply Division" and other regulations.

(2) After the STATCOM system commissioning test, it must operate continuously for 720 hours. (3) After any

interruption, the abnormal situation must be improved, and the test should be continued. The total time is 720 hours.

That is qualified.

(4) For any interruption, Party B must submit an analysis and improvement report within 7 calendar days. (5) After the

commissioning test is completed, the STATCOM system shall operate with 99.9% availability for 30 days.

Taipower has the right to conduct up to 10 tests on the power grid within these 30 days to ensure

Guarantee the performance of STATACOM system. If the maximum MVAR of the STATCOM system during this period

The output (capacitive or inductive) degrades, correct the problem and restart the test until

The STATCOM system is running at 99.9% availability for 30 days.

6.5 Cooperate with joining the system operation

(1) It must be handled in accordance with the key points of the completion and trial operation of the power transmission and transformation project of Taiwan Electric Power Co.,

Ltd., the key points of contact with the power transmission and transformation project, and the relevant approved standards.

(2) Party B needs to cooperate with Party A to complete the relevant operations of joining the system.

31

You might also like