5.2 STATCOM System Functional Requirements
5.2 STATCOM System Functional Requirements
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
Table of contents
3.2.4 Running operation and control mode................................... ................................... 10 3.2.5 Protective relay
I
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
4.1 Interface between STATCOM system and the power system of the temporary bidding project............ 25
4.2 Interface between STATCOM system and civil engineering and ancillary electromechanical engineering............ 26
II
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
This specification is applicable to the 161kV static synchronous compensator of Zhanggong Booster Station and Yongxing Switching Station
STATCOM equipment, cable equipment, ancillary equipment related to each equipment) construction, including system model
Party B shall implement the provisions of the contract and the instructions of Party A/Engineering Department to perform relevant work, except for the contract and requirements
Request (1) In addition to the relevant regulations, Party B shall be responsible for the survey, design, manufacture, and test of the project.
Inspection, supply, transportation, storage, installation, inspection, testing, training and maintenance and other related work.
The main equipment and work items of the STATCOM system are as follows, and the relevant system architecture is shown in Figure 1.2-1.
(1) Protection relay board for 161kV terminal equipment used by Zhanggong step-up station STATCOM (including
50BFÿÿ
E. Protection system
(7) SCADA and IEC 61580 system (detailed requirement book (4)). (8) Auxiliary equipment
1
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
work required for STATCOM parallel trial operation and joining the system.
Among them, the rated voltage of STATCOM equipment may be determined by Party B according to the planned STATCOM system
system to adjust.
If there is any conflict or inconsistency between the provisions of the specification, unless otherwise specified,
The priority order of application shall be determined according to the following order:
For the above-mentioned same document or illustration, the order of priority adopted shall be the one with the latest issuance time.
use.
2
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
The installation, manufacture, testing and provision of materials of all equipment shall comply with the relevant standards of the Requirements (1)
It is required that if the above regulations and standards are not specified, the following latest laws, standards, testing rules or regulations shall be used
All equipment and materials provided by Party B must be in accordance with the latest
Edition and the most applicable Ministry of Economic Affairs user electrical equipment installation rules, power transmission and distribution equipment installation rules, Taipower
The company's relevant specifications, the National Standards of the Republic of China (CNS), the International Electrotechnical Commission (IEC), the United States
National Electrical Code (NEC), American National Standards (ANSI or IEEE Std.), industry associations
Will set standards (such as NEMA, IPCEA, ISO, ASTM, UL, etc.) and other regulations and standards
The equipment provided by the electrical system that implements this specification shall comply with the user's electrical equipment installation rules,
Power transmission and distribution equipment installation rules, domestic environmental quality regulations (such as noise, non-ionizing radiation environment
recommended values, etc.), and relevant EN, CNS, IEC, NFPA or ANSI/NEMA standards and other
(1) Comply with the relevant design guidelines of each unit of Taipower Corporation
technology (4) Main points of power dispatching by Taiwan Power Co., Ltd.
2.3 Abbreviations
3
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
POCÿPoint Of Connection
(1) PCC (Point of Demarcation of Responsibilities): The point of connection between the STATCOM system and the power system.
(2) POC (parallel point): The parallel connection position of the STATCOM system in the power system.
The voltage/current (V/I) characteristic point at which reactive power output is provided.
(4) Static Synchronous Compensator (STATCOM): Parallel reactive power compensation equipment that can provide or
absorb reactive power, and its capacitive or inductive output current can pass through
Power electronic switching elements, gate drive elements, power supplies, controllers, resistors, etc.
Equipment, together with the voltage source converter equipment composed of DC capacitors and related auxiliary equipment.
(7) Response Time (Reaction Time): Refers to the response time from the control signal before the maximum overshoot occurs
The time required for the voltage to change to 90% of the target value after the signal input step changes.
(8) Settling Time (stabilization time): After STATCOM is started, the voltage is stable at ±5%
(9) Slope (change rate): the control range under the nominal voltage, the change ratio of voltage and current
Rate.
(10) VSC (Voltage Source Converter): The DC voltage through the DC capacitor is passed through the power electronics
4
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
(1) Before designing, Party B shall carry out survey and relevant data collection of Zhanggong Booster Station and Yongxing Opening and Closing Station
(also known as Yongxing S/Y), including "Civil Engineering Design/Construction Turnkey New Project of Zhanggong Booster Station" (hereinafter
referred to as Zhanggong Step-Up Station New Project) and "Yongxing Opening and Closing Station New Project" (hereinafter referred to as Yongxing
Xing S/Y new project) underground cable layout space and route, switchgear number,
And contacts, etc., according to the design of STATCOM system related equipment.
(2) Party B shall properly review the space configuration of the equipment selected for the detailed design and provide civil works
(3) There must be good insulation coordination between the related equipment of the STATCOM system.
The failure caused an accident in Taipower's power system. Protective equipment shall not be caused by improper misoperation
(4) STATCOM system-related equipment can be controlled in case of low voltage, overload, etc.
Conditions, or operation under the condition of partial equipment failure. If the system operates beyond the above conditions,
The STATCOM system should have relevant system and equipment protection measures.
(5) The operation of STATCOM equipment should comply with the noise control regulations of the local county and city government (if the local county
and city government has no noise control law, refer to the noise control standards of the Environmental Protection Agency of the Executive Yuan
handle).
(6) In addition to the following requirements on the design drawings of this project, relevant requirements should be drawn according to the illustrations of Taipower Corporation
A. The configuration diagram of STATCOM system-related equipment should be drawn in elevation for clear labeling
B. The configuration of STATCOM system-related equipment needs to indicate the relative position of the building and
distance, and select the appropriate column center for its configuration datum reference point.
C. The connection of power cables for GIS, transformers, reactors, switchgear, etc. should be clearly marked
The location and phase sequence of the points, and the name of each circuit must also be marked.
D. According to the equipment required for the project drawn on the drawing, the equipment should be listed in detail in the equipment list
5
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
Material number, equipment name, specification, brand, quantity, unit, etc., the equipment must be numbered,
And there must also be a corresponding number on the electrical equipment diagram to indicate the installation location of the equipment.
UHV cable-related equipment only indicates the name and specification of the equipment, and the quantity is separate from the power supply.
E. All designs must be represented by drawings, but if the drawings cannot be clearly marked, words can be used
Supplementary explanation.
F. Party B shall submit the list of cable numbers in accordance with Party A’s cable numbering principles, and shall be reviewed and approved
Only then can it be implemented. And according to the application of the cable marking label, mark the end of each cable
G. Party B shall draw up the switch number in accordance with the principle of Party A’s equipment switch number, and after review and verification
H. The wiring method of the switchboard adopts the bottom incoming line in principle.
(7) The 161kV power cables and ancillary equipment used in this project must comply with the TPC specification for 161kV cross-
The supply of all equipment and equipment must be products protected by the localization policy.
(9) The medium and high voltage switches used in this project shall not adopt the armored switch box type.
3.2.1 Architecture
(1) The rated capacity of the STATCOM system is ±200 Mvar, two sets are respectively connected to the 161kV UHV system busbar
(2) The STATCOM system must provide at least 20 sets of other inactive power equipment (such as MSC,
MSR, etc.) and reserve system hardware and software capacity, related graphic control screen, connection interface, etc.
For subsequent expansion and integrated control, its control has automatic/remote operation mode. If the warranty period
, when Party A adds MSC or MSR equipment, Party B must cooperate to modify STATCOM
6
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
System graphic control software and add related lines to MSC or MSR equipment, and connect to
SCADA system, the fee has been included in the total contract price, and the completion date shall be specified by Party A
It is known that the detailed requirements for overdue penalties (1) stipulate the relevant penalties (15) in Chapter 11.
(3) The STATCOM system of the two case sites must be installed with 2 bays (bay) 161kV GIS, namely the line bay and the transformer
bay. Among them, the Zhanggong step-up station of the line stall is connected to Zhanggong
Newly established 161kV GIS for the new construction of the booster station; Yongxing S/Y connects to Yongxing S/Y new
(1) According to Taipower Corporation's transmission system planning guidelines, not limited to the following items.
A. Voltage stability standard: under normal power supply conditions, the power system should maintain
The current converges and the voltage operation is between 0.95 pu and 1.03 pu, and the accident is between 0.9 pu and
1.05 puÿ
D. Voltage change rate: the voltage change rate of the responsibility demarcation point caused by connecting to the Taipower company system,
In addition, the impact of the same step-up station/switching station or the same transformer or the same feeder has been approved for
grid-connected power generation equipment, and does not consider other system background values, such as loads, energy storage systems
E. System stability: UHV system above 161kV is connected in parallel, and the parallel contact belongs to
The busbar of the booster station/switching station shall not reduce the transient stability of the Taipower company system to
Below the specified value: 161kV system three-phase fault critical clearing time takes 12 cycles as
Standard, if eight to twelve cycles should use two sets of full-line section fast main protection relay.
(3) Fault current at 161kV busbar terminal at Zhanggong step-up station terminal: the maximum three-phase fault current is 50kA;
The minimum three-phase fault current is 37.046 kA; the maximum single-phase fault current is 39.644 kA; the maximum
Small single-phase fault current 36.577 kA (Party B shall provide Party A with the latest
material).
7
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
(4) Fault current at 161kV busbar terminal at Yongxing switching station: maximum three-phase fault current 50kA; minimum three-
phase fault current 22.722 kA; maximum single-phase fault current 30.699 kA; maximum
Small single-phase fault current 22.317 kA (Party B shall provide Party A with the latest
material).
(5) Harmonic current: merged into the system's responsibility demarcation point end, the responsibility demarcation point end,
continuous operation must comply with the standard harmonic current control standard of IEEE 519 (2nd to 50th).
(6) The continuous negative sequence voltage unbalance rate (Voltage Unbalance Factor) shall not be greater than
1%, where the negative sequence voltage unbalance rate = negative sequence component size / positive sequence component size × 100%.
The unbalance rate of negative sequence voltage in a short time (15 minutes) shall not exceed 1.2%.
(7) STATCOM is connected to the 60Hz three-phase of the step-up station/switching station of the Taipower Company to which it belongs
Operational capability of STATCOM (excluding MSC and MSR) integrated into the system
At least the following requirements should be met, and the system voltage should be determined according to the voltage of each system grid-connected point
Reference.
A. The STATCOM system must be able to adjust the grid-connected point voltage to the system voltage reference value (this function
The maximum continuous output capacitive reactance (capacitive reactive power) is 200Mvar (1.0pu) at a system
B. The maximum continuous output inductive reactive power of the STATCOM system at rated voltage 1.0 pu, system
C. The slope range of VI characteristic curve under the capacity of 400 MVA (Figure 3.2.2-1 A+B)
D. The STATCOM system must be capable of continuous operation down to 0.3 pu and continue until
8
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
E. The STATCOM system must be able to achieve a maximum overvoltage of 1.3pu in a short period of time through the control system
It will trip out after running continuously for at least 2 seconds under the same conditions.
The inductive rated current at point D (at point B) extends upwards until the allowable upper limit of overvoltage
Extension of capacitive rated current at point E (at point A) and maximum reference voltage (at point K)
The maximum reference voltage at point F (point K) and the extension of the maximum voltage control slope
Extension of minimum reference voltage at point H (at point M) and maximum voltage control slope
Extension of line ILrated-B at point J at minimum reference voltage (M) and minimum slope
Response time is defined as a step change from the control signal input before maximum overshoot occurs
After that, the time required for the voltage to change to 90% of the target value.
For the control device of the STATCOM system, the voltage response of the STATCOM system
It should be 2.3% for Zhanggong booster station when the reference voltage is measured, and Yongxing S/Y is
After a 2.2% step change, the required change must be achieved within 40ms (initial voltage
9
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
90% of the difference from the steady-state voltage). The maximum overshoot should not exceed
Over 110%, the settling time should not exceed 100ms, and the voltage stabilization should be within ±5% of
the final value. Restart time (re-start time) should be less than 100ms
Restart time is defined as when the system fails, the output of STATCOM is
The output of reactive power is limited due to undervoltage. When the system voltage recovers, STATCOM
Time for the reactive power output capability to return to normal. Restart time (re-start time) is not
A. Normal Operation
(A) The STATCOM system shall be capable of normal and continuous operation of capacitive and inductive
(B) Party B shall provide power system stabilizer (PSS or POD (Power
Oscillation Damper), the control system design must be carried out and submitted to Taipower Company
for review, and the STATCOM model and parameters applicable to the PSS/E software must be provided
number.
(C) The voltage reference value of the STATCOM system is under the rated capacity of the system, and the slope can be
10
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
(D) The STATCOM system shall, under dynamic conditions, vote for all MSCs and MSRs
(E) The control system must adopt programmable editing, and allow Taipower Company to connect to the grid according to
For the compilation of the change adjustment program of the point power system, the interface of the operating system must be
(F) Party B shall provide the start and stop operation sequence of STATCOM system to confirm
(G) The STATCOM system shall be capable of being activated and deactivated after a signal has been sent locally or remotely
Automatic operation.
(A) The STATCOM system needs to maintain the output capability continuously at a parallel contact voltage of 1.1 pu.
(B) The STATCOM system needs to maintain the output capability for 2 seconds at a parallel contact voltage of 1.3 pu.
(C) The STATCOM system needs to be in the operating range to operate the inductive and capacitive
(D) The STATCOM system must continue to operate normally at 58.5Hz~61Hz in accordance with the technical points of
parallel connection of renewable energy power generation systems promulgated by Taipower Corporation;
Must run continuously for 20 seconds at 57.5Hz; allowed when frequency is lower than 57.0Hz
C. Undervoltage Operation (A) The STATCOM system needs to maintain the output
(B) The STATCOM system needs to maintain the output capability for 2 seconds at a parallel contact voltage of 0.3 pu.
The control system must be able to adjust the grid-connected point voltage and incorporate the existing MSC and MSR
In addition to control, at least 20 sets of other invalid power equipment are provided for subsequent expansion of the whole
11
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
The STATCOM system must switch between MSCs and MSRs under dynamic conditions
For the compilation of changing and adjusting programs, the interface of the operating system must be WINDOWS
B shall provide at least the following STATCOM control modes and their operation priority
order, and the control between modes must be able to switch smoothly.
(A) This mode can be controlled by the system operator STATCOM fixed output -200MVAr
Reactive power output to +200MVAr, and manual operation of MSCs and MSRs
do.
(A) The voltage control mode is that the control system detects the grid-connected point voltage, according to the VI characteristic
The slope range of the characteristic curve is used for voltage control, so that the grid-connected power voltage can be stably controlled
(B) The control mode shall be operable under steady state and dynamic operation of the power system.
(C) The error of voltage measurement and signal conversion shall not exceed 0.3%. voltage detection circuit
C. Undervoltage Control
(A) The controller shall detect the voltage before and after the failure of the system.
(B) When the system fails, any phase voltage of the three-phase voltage is lower than 0.3pu,
The undervoltage control mode should be implemented, and the control system turns off the voltage control mode
(VCM), STATCOM does not output any reactive power, if the undervoltage maintains more than
2 seconds, the STATCOM should be closed. When the system voltage detection is higher than 0.4pu,
And the control system can return to normal only after the troubleshooting is confirmed by personnel.
12
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
run.
(C) The control mode must be operable under steady state and dynamic operation of the power system.
D. Overvoltage control
(A) The STATCOM system needs to maintain the output capability for 2 seconds at a parallel contact voltage of 1.3 pu,
If the overvoltage exceeds 2 seconds, the STATCOM should be closed. When the system voltage detection is low
When it is at 1.2pu, the control system can resume normal operation only after the personnel check and
confirm that the fault is eliminated. (or according to the bidding documents)
(B) The control mode shall be operable under steady state and dynamic operation of the power system.
By automatically or manually adjusting the gain of the regulator (regulator) of the control system, the
STATCOM system can reduce oscillation and overshoot during the response process
Gain optimization adjustment control performs gain self-control by detecting the signal of grid response
adjust.
In order to increase the system damping and improve the small signal stability margin of the system, STATCOM
The system must have the power system stabilizer control function.
(1) Protection system planning is based on Taipower Corporation guidelines, power system protection relay planning guidelines, and Taiwan
Gulf Power Company’s transmission and power supply business department’s protection relay standard setting guidelines, UHV user’s power consumption equipment
Prepare design data review operation standard procedures and review requirements, and
After discussing with the relevant units of Taipower Corporation, according to the characteristics of Taipower system at the parallel contact end
Design and protect the electric relay type for planning, and submit the protection electric relay planning and calculation documents.
(2) STATCOM system equipment protection relay equipment includes but not limited to the following:
A. Transformer: overcurrent relay, differential relay, grounding relay, sudden voltage relay, release voltage relay
13
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
Relay, Brinell relay, oil temperature detection, over excitation protection, overload protection, overheat protection
C. VSC valve parts: differential relay, overcurrent relay, overvoltage relay, high temperature detector
(3) Yongxing S/Y Base, 161kV GIS line protection relay at the line end submitted by the manufacturer
The specification must be the protection relay of the 161kV terminal equipment used by Yongxing S/Y end STATCOM
The brand name and specifications must be consistent. The specifications of the rest of the protection relays are detailed in the appendix of the requirements document.
Party B shall carry out the work according to Taipower Corporation's IEC 61850 specification and requirement book (4).
Party B shall provide the design description of the STATCOM control system, including but not limited to: control system
Fault isolation procedures, interlock protection mechanisms and operation procedures of backup systems.
Party B shall calculate the total loss of the power equipment related to the project according to the IEEE 1031 standard.
Among them, high and low voltage switchgear, bus bars, cables, barriers, connectors, etc., are not included in this loss
(1) The total loss must be estimated based on the ambient temperature of 20°C, the grid-connected voltage of 1.0pu and the slope
of 5%. The operating capacity states are 100% inductive, 50% inductive, 0%, 50%
Including power electronic switches, capacitors (DC capacitor), resistors, inductors and
Its conductor elements, and carry out the loss calculation according to IEC 62751-2. Redundancy equipment will still be
14
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
Transformer equivalent resistance should be calculated using its full load condition. Through this resistor and
The STATCOM operation calculates the total loss (including no-load loss, full
The reactor loss shall be calculated according to Annex B.5.7.5 of the IEEE 1052 standard.
Auxiliary equipment is the mechanical and electrical facilities necessary for the operation of STATCOM, including pumps, air
Adjustment, ventilation, etc., the output capacity varies according to the environment, STATCOM output capacity, etc. auxiliary
To assist in the calculation of the loss of power supply, Party B must first estimate the loss based on the capacity of the equipment submitted.
However, the actual measurement and comparison must be carried out after the equipment is installed, and the backup equipment may not be included in the loss
lose.
The total loss is STATCOM. Under the capacity output of (1) and the steady-state operating range of the
system voltage 1.0pu, calculate the above items (2)~(7) and draw the loss curve. The maximum total loss
calculated by the sum of all equipment shall not be higher than that of the STATCOM system
2% of capacity.
A. Definition
Stoppages necessary for preventive maintenance to ensure that the STATCOM system can
Continuous and reliable operation. This outage will result in some or all of the STATCOM system
15
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
unit of time). The following items are covered by this interruption period:
a. To determine the cause of the downtime, to determine the repair or replacement of original parts and
Downtime.
b. The system operator switches off and completes grounding in preparation for maintenance work and
The time required to remove the ground and reconnect the switchgear after repairs have been completed.
Delays caused by maintenance personnel without qualified certificates will not be counted as downtime.
B. Annual availability is the proportion of forced downtime in one year, and the reference formula is as follows: ÿ ÿ ÿ
D ÿ
ÿ
1
ÿÿ 8760
100%
ÿÿ
C. Reliability refers to the normal operation of the STATCOM system, under certain time conditions
The probability of normal performance, usually called the mean time between failure MTBF (Mean
(A) The annual availability of the STATCOM system due to mandatory outages shall be at least 99%.
(B) The number of forced shutdowns of the STATCOM system should be less than 2 times per year.
(C) The number of maintenance shutdowns of the STATCOM system should be less than 1 per year.
(D) If the actual performance is different from the values specified in (A) and (B) above, B
The party shall provide an improvement plan to meet the availability guarantee.
Party B shall provide system simulation, calculation, evaluation and other materials before equipment manufacturing, not limited to the following
List. Power system simulation system analysis, limited to use simulation software of PSS/E V34 or above
analyze. The simulation results must meet the requirements of Taipower system and requirements, and no matter heavy load or light load, normal
And the compensation of reactive power and system stability in abnormal conditions.
16
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
(1) Consider factors such as the maximum allowable error of transformer impedance, continuous negative sequence voltage component, maximum
continuous operating frequency, maximum continuous operating voltage and other factors to calculate the number of sub-modules and the rating of each device
(2) Calculation of the output capacity of the STATCOM system, and the system operation in overvoltage, undervoltage
A. Confirm with PSS/E simulation software based on the actual model of the equipment (not a simplified model)
(A) Analysis of STATCOM system startup (including transformer loading), shutdown or power system N-1, N-2
accidents.
(B) Fault current analysis of high-voltage and low-voltage busbars (including single-phase-to-ground faults,
(C) Analysis of valve mistriggering events under the most severe system conditions.
(4) Analyze the dynamic characteristics of the system to confirm the dynamics of STATCOM when the system is disturbed
A. Analyze and verify that STATCOM can provide proper dynamic control to meet power system
B. Verify STATCOM system response time and power system recovery after failure
ability.
C. Analysis and verification When the power system is disturbed, supplementary control (supplementary
(5) Use the power system analysis software PSS/E to conduct system response analysis, not limited to the following items
simulation:
A. Steady-state simulation
(A) Before and after STATCOM installation, the system is under normal operation under heavy and light loads (N-0)
17
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
(B) Before and after STATCOM installation, when the system is under heavy or light load, the voltage and power
flow detection of N-1 and N-2 accidents occurred in the equipment near the step-up station/switching station
discuss.
B. Dynamic Simulation
(A) For N-1 and N-2 accidents when STATCOM is not installed in the system,
Perform dynamic response analysis for scenarios with the most severe voltage rise/fall across parallel contacts. Re-execute
Perform dynamic response analysis after installing STATCOM, and include MSC, MSR,
(B) The booster station/switching station end connected to the STATCOM system in parallel, under heavy load, light load or occurrence
When the maximum and minimum power generation capacity occurs, the three-phase short-circuit fault analysis of the parallel contact voltage occurs,
If it is an ultra-high voltage substation system, a 345kV three-phase short-circuit fault analysis must be added.
Party B shall formulate the specifications for this project in accordance with the requirements of STATCOM and power system related equipment specifications.
(1) Party B shall prepare according to the contract and demand letter (1) and this demand letter and the requirements of Party A/Engineering Department
(2) The relevant planning documents, drawing materials, reports and various forms submitted by Party B shall be documents in
traditional Chinese (except numbers or English codes), and shall be reviewed in accordance with the relevant regulations.
(3) Party B shall submit the relevant documents required for this project in accordance with the contract, demand document (1) and this demand document.
Basic configuration diagram, grounding system configuration diagram, equipment (machine) configuration diagram,
Cable configuration diagram, cable tray configuration diagram, switchboard layout diagram, control panel
18
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
Configuration diagram, configuration diagram of relay board, detailed diagram of equipment (including size and weight), etc.
Single-line diagram, DC low-voltage single-line diagram, cable circuit design diagram, cable circuit
General diagram, grounding design diagram, control logic circuit diagram (hardware and software), electrical
Cable core wire diagram, equipment internal wiring diagram, wiring diagram, etc.
The content includes VI characteristic curve, and system operation data, etc., and provides
c. Coordination analysis of lightning surge and equipment insulation (insulation of each power equipment
and clearance)
f. Simulation analysis of magnetic field strength of air reactor (using finite element method)
g. Harmonic Calculation
i. DC system calculation
b. Noise measurement
19
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
STATCOM and power system equipment specifications and quantity statistical tables, cables
161kV GIS, STATCOM system related equipment and accessories of each equipment
Equipment manufacturing drawing, parts list (including materials), assembly drawing, equipment installation
List of spare parts, consumables, special tools and special testing equipment, etc.
Training materials and handouts (including electronic files), training process video CD, training
20
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
E. Maintenance Documentation
System equipment stability and fault statistics, fault handling report, fault analysis report
Completion charts of each stage, project settlement schedule, equipment delivery list, various verification
The prescribed construction drawings (the standard drawing frame of this project must be applied and signed off), various test reports
report, system guarantee data, operation and maintenance manual, substation equipment history card, etc.
(4) Party B shall handle it according to the relevant documents and delivery time stipulated in the contract and demand letter (1)
Submission matters shall be carried out after review and approval by Party A/Engineering Department. File Category
(D) C.
product test reports (B) Self-inspection test reports Within 7 days before quality inspection
documents System equipment stability and failure Detailed requirements (1) and equipment specifications
the 7th of each month. Submit the data of the previous month before the 7th of each month. Fault handling report.
Fault analysis report within 7 days after the fault. Improvement report
andwithin
acceptance
14 daysdocuments
after the fault
within
. F.the
Completion
previous 7
days
21
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
Party B shall assign the STATCOM system immediately after the parallel test run to the end of the warranty
Maintenance engineers handle troubleshooting operations, and the dispatch and appointment of their personnel must be in accordance with the provisions of the Labor Standards Act
(1) According to the obstacle removal duty plan and power system maintenance and inspection proposed by Party B and reviewed and approved
(2) The obstacle removal duty plan must at least include the following.
B. On-duty maintenance work implementation schedule, including regular maintenance cycle (not lower than Taipower
The standard of the company's relevant specifications), maintenance content, maintenance record form, person in charge, machine
Tools, inspection and repair tools, transportation and spare parts, etc.
According to the regulations of Taiwan Power Company, set up full-time electrical technicians, and participate in this
More than 1 year experience in engineering design or construction, the engineer needs to have independent experience in system troubleshooting
Ability to work.
Troubleshooting and maintenance of equipment after parallel trial operation and before the end of warranty
(5) Scope of obstacle elimination: related equipment of STATCOM system in this project.
The work content includes regular maintenance, inspection, adjustment, troubleshooting, repair, accident
Emergency repair and equipment failure records and failure analysis to maintain the normal operation of the system.
There must be an engineer who is qualified as an obstacle removal duty officer at the base 24 hours a day
22
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
Stationed, and cooperate with the implementation of STATCOM system equipment obstacle elimination. Staff on duty till now
(8) The on-duty personnel should wear professional clothing and wear the unit identification card, armband and Taipower work card, etc.
when on duty.
(9) After the fault is repaired, the inspection and repair process, fault cause, treatment method and improvement plan should be submitted
to Party A/Engineering Department for review. When the failure time exceeds the contract, according to the demand letter (1) related
stipulated.
(10) When Party B receives the notification from Party A or the maintenance and operation unit, Party B shall immediately send personnel to
repair it. For major faults that affect the normal operation of the system, Party B shall repair and resume normal operation within 6 hours.
(11) According to the data recorded by the fault record monitoring device, Party B shall submit abnormal event statistical reports to Party A
before the 5th of each month. If abnormal events can be attributed to failure or damage of equipment, equipment, poor construction,
3.6 Maintenance
(1) Handle in accordance with the reviewed and approved maintenance plan proposed by Party B. (2)
The content of the maintenance plan must at least include the following.
B. Maintenance work implementation schedule, including regular maintenance cycle (not lower than that of Taipower Company)
Standards for relevant power system inspection procedures), maintenance content, maintenance record forms,
who have participated in the design of this project and must receive professional training on the maintenance of original
STATCOM equipment and obtain relevant certificates approved by the original factory. The engineer must have system troubleshooting skills
23
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
The maintenance of the equipment during the warranty period shall be the responsibility of Party B.
(5) Maintenance scope: STATCOM and power system related equipment of this project. (6) Contents of
maintenance work
The operation content includes regular maintenance, inspection, adjustment, obstacle removal, repair, accident
Emergency repair and equipment obstacle analysis to maintain the normal operation of the equipment.
(7) Party B shall prepare the spare parts and consumable materials required for maintenance operations, and the related costs
(8) The operation of consumable materials that must be regularly cleaned, inspected, lubricated, adjusted, replaced or added by the
original manufacturer is a regular maintenance, and Party B shall send personnel to carry out the work and complete the execution
The maintenance report shall be sent to Party A/Engineering Department for reference.
Party B shall handle the contract in accordance with the contract, demand document (1), this demand document and equipment specifications
(1) The content of installation training must at least include: pre-installation inspection, installation precautions, adjustment,
(2) The content of the operation training must at least include: inspection steps, operation inspection, cleaning methods,
Inspection of oil or gas, filling method of lubricating oil, etc. Training materials must provide
(3) The content of maintenance training must at least include: spare parts list, replacement of various spare parts, installation method
24
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
This chapter only describes the STATCOM system equipment and construction civil engineering, SCADA system based on past experience.
The interface and scope of work between system engineering to ensure that all system engineering can be coordinated with each other to achieve successful parallel connection
Trial run, adding system operation and complete operational performance. At any stage of work, its interface work division or
If there are any contradictions or omissions in the interface, Party B shall be fully responsible for coordinating and handling them. If Party B fails to properly
Proper handling, or the consequences of project omission or duplication of work due to matters not reminded in this chapter, must be handled by the
Party B is responsible for the completion of the processing, and there is no additional price.
4.1 Interface between STATCOM system and the power system of the temporary bidding project
The interface between this project and the new project of Zhanggong Booster Station is summarized in Table 4.1-1;
Table 4.1-2 shows the relevant interfaces of Xing S/Y new construction project. If Party B damages the
Relevant facilities that have been completed or have been completed by other projects must be restored, and the relevant fees are included in the contract
Table 4.1-1 Interface between this project and Zhanggong Booster Station New
Station
item project Remarks from Party B
161kV terminal equipment protection relay board (including 50BF) for provided by Party B. The installation
2 D THE
STATCOM at Zhanggong step-up station. 161kV GIS cable terminal location must be coordinated with Taipower.
box connection, 161kV cables and various signal lines, and related
3 cable fixing parts, cable racks and other facilities required for leading D THE
space for the cable arrangement room and culvert of the new project
of 161kV cables.
Note: ÿ is the person in charge of the main work ÿ is the assisting person
25
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
Yongxing S/Y
item project Party B Remark
new construction
161kV terminal equipment protection relay board (including 50BF) STATCOM terminal requires Party B to use
2 THE D
for Yongxing S/Y terminal STATCOM. the same brand and specifications as the
various signal lines, and related cable fixing parts, cable racks
3 D THE
and other facilities required for leading to this project. Before the
cables accordingly.
Note: ÿ is the person in charge of the main work ÿ is the assisting person
4.2 Interface between STATCOM system and civil engineering and auxiliary mechanical and electrical engineering
The system shall provide various switchgear, substation equipment and line layout related to civil works
and other detailed diagrams (including grounding system), including related information such as openings, loads, embedded accessories, bolts, etc.
Materials, in order to revise the civil engineering drawings. And in accordance with the civil construction schedule, the construction is pre-embedded or modified and adjusted.
(1) Party B of the STATCOM system shall provide the following works before the construction of each structural unit in civil engineering:
The engineering drawings are used as the construction basis for the civil works:
B. The drawings of the pre-embedded objects that must be matched with the walls, columns, and floors of each floor.
C. The construction steps of each floor and the relevant interface diagrams of decoration materials.
D. Before the equipment enters the site, detailed drawings of the conditions that need to be coordinated by the civil engineering.
F. The basic configuration diagram of the reactor and the relative position configuration with the adjacent structures.
26
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
(2) Unless otherwise specified, foundations, floors, walls, roof openings, ground levelling, cable openings
Holes and their covers are within the scope of civil engineering work.
(3) All the embedded objects required by this system, including bolts, embedded iron plates, pipe support frames and embedded bolts of H-shaped steel, shall be
supplied and installed by Party B. All buried objects except warp armor
Unless otherwise agreed by the Party/Engineering Department or otherwise specified, it shall not be painted or coated.
(4) Party B shall mark the position, size and material of the buried objects in detail and completely on the drawing for reference in civil engineering.
(5) The concrete for the buried objects required by this system shall be implemented by civil engineering, and Party B shall assign the staff responsible for this work to
be present, and the foundation of the equipment shall be filled by Party B of this system.
Responsible. The secondary concrete backfill at the reserved hole of the buried object shall be performed by Party B of this system.
Not separately priced. But the secondary concrete of all GIS rooms belongs to the scope of civil engineering construction.
(6) When Party B evaluates and considers it necessary, if it is necessary to excavate pipelines or add culverts and other civil engineering facilities, Party B shall handle
it by itself without additional pricing. However, it is necessary to modify or add related facilities of the completed building or to dismantle the related equipment
of the completed building or to modify the foundation of the substation equipment, cable holes, reserved holes, reserved pipes, etc.
The company is responsible, and the material costs, construction wages and storage costs for relevant modifications are included in the project
schedule for the heavy electrical equipment to enter the site, in principle, the indoor decoration is completed and the mobile crane and electric equipment are obtained.
(8) Party B is also responsible for the fire retardant materials and construction required by this system, and the cost has been included in the project
(9) Pipelines or cable brackets pass through floor openings and partition walls, and must be responsible for construction and repairs to comply with
According to the specifications and fire regulations, the relevant costs are already included in the project cost and will not be priced separately.
(10) Party B must provide the cable bracket/tray configuration diagram and be responsible for the supply of materials, and must cooperate with the civil engineering schedule
(11) The temporary lighting, ventilation and drainage equipment necessary for Party B in the workplace shall be provided by Party B
(12) Party B shall provide grounding design and provide civil works for construction.
27
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
(13) Party B must confirm the cable installation space before construction, and plan the configuration of 161kV cables accordingly
path.
The SCADA system reserves at least 2 RJ-45 network communication interfaces, which are connected by the STATCOM system
The system is connected to the reserved interface, and IEC61850 is used as the transmission protocol between them.
28
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project requirement book (2) STATCOM system functional
requirements
The functional requirements of the main materials and equipment of this project are also detailed in the equipment specifications in the appendix of the requirements document.
29
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project
According to the inspection and testing in the demand letter (1), and the specification requirements, among them, the factory test and work
(1) The equipment should be tested according to the standard procedure of the manufacturer. Tests of GIS, transformers,
VSC valves, etc., and all other specific test requirements must be handled in accordance with equipment specifications.
(2) Unless otherwise specified, if the equipment is a standard product or similar to a standard product, or a prototype and
similar in size or capacity, the manufacturer's previous tests for the standard or prototype equipment
The test data can replace the specified test, but it must be approved by Party A/Engineering Department first.
(3) Party B must conduct system simulation verification through RTDS (Real Time Digital Simulator) to prove the correctness
of the control system operation, and provide RTDS that can be read and edited
(1) The test should be performed by qualified personnel in accordance with the approved procedures. All equipment and instruments
required for the test, except for some special equipment (supplied together with the equipment to be tested), should be provided by
provided by Party B.
A. Accuracy: Calibration records for each instrument must be attached to the test, any test instrument
The use should be tested and approved by the authorized unit in advance.
B. Checklist: Each machine part should have a checklist. This checklist should include each control
devices, relays and gauges or instruments, an operational test should be performed first to ensure that all control
(2) Special requirements: After the equipment has been inspected, adjusted and placed in an appropriate operating state, it should be
tested on site. The test proves that the function of the device complies with all the requirements of the specification, and must
A. Continuity Test.
B. Insulation test.
30
Machine Translated by Google
Central District Construction Division, Power Transmission and Transformation Engineering Division, Taiwan Electric Power Co., Ltd.
Zhanggong booster station and Yongxing switching station 161kV static synchronous compensator (STATCOM) turnkey new project
After all the equipment has completed the factory test and site test, the auxiliary power supply system is completed until
The power transmission operation at the interface end is necessary to carry out the system integration test operation to ensure that all equipment is operating normally and
Party B shall test the specified requirements in accordance with other system requirements documents, and handle the STATCOM system and
For other related system integration testing work, the STATCOM system must be tested according to the content of IEEE 1303.
Trial work.
6.3 After the commissioning tests are connected in parallel with the
Taipower grid, the STATCOM system must comply with IEEE 1303 content and technical specifications
(1) In accordance with the relevant approved standards of Taiwan Power Corporation, "Taiwan Power Corporation
"Contact Key Points for Power Transmission and Transformation Projects of the Power Transmission and Power Supply Division" and other regulations.
(2) After the STATCOM system commissioning test, it must operate continuously for 720 hours. (3) After any
interruption, the abnormal situation must be improved, and the test should be continued. The total time is 720 hours.
That is qualified.
(4) For any interruption, Party B must submit an analysis and improvement report within 7 calendar days. (5) After the
commissioning test is completed, the STATCOM system shall operate with 99.9% availability for 30 days.
Taipower has the right to conduct up to 10 tests on the power grid within these 30 days to ensure
Guarantee the performance of STATACOM system. If the maximum MVAR of the STATCOM system during this period
The output (capacitive or inductive) degrades, correct the problem and restart the test until
(1) It must be handled in accordance with the key points of the completion and trial operation of the power transmission and transformation project of Taiwan Electric Power Co.,
Ltd., the key points of contact with the power transmission and transformation project, and the relevant approved standards.
(2) Party B needs to cooperate with Party A to complete the relevant operations of joining the system.
31