Sample Questions L4 Module 3
Sample Questions L4 Module 3
Supply
Module 3 – Commercial Contracting
a. Indemnity
b. Intellectual property
c. Liquidated damages
d. Warranty
LO: 3
AC: 3.2
1. Product functions
2. Technical inputs
3. Performance requirements
4. Conformance standards
a. 1 and 2 only
b. 2 and 3 only
c. 1 and 3 only
d. 2 and 4 only
LO: 1
AC: 1.1
2
L4M3 Sample Exam Questions Dec 2018
Q3. A procurement manager has negotiated a firm fixed price throughout the contract duration of two years. Was
this the right thing to do?
a. No, because even with these contracts the pricing can change
b. No, because this is an unfair term and therefore is not legally binding
d. Yes, because this type of pricing will always be better than a spot price
LO: 3
AC: 3.3
Q4. Ace Group is seeking to encourage one of its key suppliers to improve its contract delivery performance. Ace
Group wants to encourage the supplier to identify cost savings and ways to enhance quality. Which of the following
would help?
a. Gainshare
b. Indexation
c. Liquidated damages
d. Service credits
LO: 3
AC: 3.3
Q5. When is the best time for the buyer's express terms to be provided to the supplier in a competitive bidding
process with negotiation?
LO: 3
AC: 3.1
3
L4M3 Sample Exam Questions Dec 2018
Q6. Which of the following are often used in conjunction with service level agreements (SLAs) as part of the
performance management regime to encourage the supplier to meet the buyer's requirements?
a. Service guarantees
b. Service credits
c. Service warranties
d. Service penalties
LO: 2
AC: 2.2
Q7. A major public body maintain a large and diverse property estate comprising more than 100 buildings in multiple
locations around the country. To maintain this property estate, which of the following is likely to be the most
effective arrangement between the organisation and suppliers?
a. Framework agreements
c. Spot transactions
d. Purchase orders
LO: 1
AC: 1.3
Q8. A large manufacturing group is going through a period of investment under which a number of its facilities will
close on a short-term basis for re-fit and upgrade works to be undertaken. The CPO is concerned about the impact
on the organisation's ability to meet customer orders should any of the work carried out by suppliers overrun. In
respect of this particular concern, the CPO should consider using which of the following contractual terms with these
suppliers?
a. Insurance
b. Force majeure
c. Liquidated damages
d. Jurisdiction
LO: 3
AC: 3.2
4
L4M3 Sample Exam Questions Dec 2018
Q9. Which of the following will typically be included with the invitation to tender (ITT)? Select the THREE that apply?
a. Specification
b. Purchase order
d. Requisition
e. Performance measures
f.Mandate
LO: 1
AC: 1.1
Q10. Under general legal principles of contract formation, which of the following will always automatically result in
the termination of an offer? Select TWO that apply.
a. Acceptance
b. Negotiation
c. Variation
d. Non-disclosure
e. Revocation
LO: 1
AC: 1.2
5
L4M3 Sample Exam Questions Dec 2018