Engineering Construction and Erection Company LLC
Technical Procedure for Fabrication and
Welding of Structural Steel
Client: M/S. AL EZZ CO LLC
Document:
ECE/FP/002
Rev. No.:0
Contract NO. : ECE/262 Prepared by: QA Dep.Technical Procedure for Fabrication and Welding of Structural Steel
FE
CONTENTS
1.0 SCOPE
2.0 DEFINITIONS
3.0 GOVERNING STANDARDS
4.0 MATERIAL CERTIFICATION
5.0 MARKING FABRICATED STEEL
6.0 FABRICATION
7.0 WELDING
8.0 SHOP ASSEMBLY
9.0 PLATFORMS, WALKWAYS, STAIRWAYS & LADDERS
10.0 TOLERANCES
11.0 INSPECTION
1of 9
ECE/FP/002
Rev. No.0Technical Procedure for Fabrication and Welding of Structural Steel
+E
SCOPE
This Procedure establishes the principles to be followed by ECE in the
fabrication structural steelwork and the performance requirements of all
operations necessary to complete this work.
This Procedure is to be read in conjunction with the Scope of Works as
outlined in this document.
DEFINITIONS
* ECE - ENGINEERING CONSTRUCTION AND ERECTION COMPANY LLC
* QA/QC Engineer - QUALITY ASSURANCE / QUALITY CONTROL
« ITP - INSPECTION AND TEST PLAN
* QCF - QUALITY CONTROL FORMATS
* ENGINEER — A DULY DESIGNATED INDIVIDUAL WHO ACTS FOR THE OWNER.
GOVERNING STANDARDS
3.1 General
Except where otherwise stated, the works shall be in accordance with the
relevant AWS D1.1: 2015 Standard. This should include, but not be limited to those
identified.
Except as modified by the requirements specified herein or the details on the
drawings, work included in the Procedure shall conform to the applicable
provisions of these publications.
3.2 Document Precedence
if conflicting requirements occur in the documents; the order of procedure
shall be:
@ AWS D1.1: 2015
@ The Contract Documents
3.4 Documentation by Contractor
The following documentation shall be forwarded to the Engineer.
- Inspection and Test Plan.
- Welding Procedure.
20f 9
ECE/FP/002
Rev. No.: 0Technical Procedure for Fabrication and Welding of Structural Stee!
FE
Welders Qualification Certificates.
Material Certificates.
Non-destructive Examination Records.
Painting / galvanizing Records.
Dimensional Inspections Records.
Release Certificates
MATERIAL CERTIFICATION
4.1 General
All material for fabrication shall be clearly stamped / marked with the
manufacturers’ numbers and cross-referenced fo the certified material
Receiving Inspection report (MRIR).
MTC's from the manufacturer shall show the heat / batch number and
mechanical and chemical properties derived from testing of the steel.
Material received without certificates shall be quarantined, pending
completion of the above.
4.2 Mill Test Certificate (MTC)
Copies of all Mill Test Certificates covering the chemical and physical
properties As BS EN 10204 / Clause 3.1 is the min. requirements of the steel to
be used in the work shall be fumished to the Engineer on request and
records shall be kept for inspection.
4.3 Units of Measurement
alll steelwork plates/sections/members/bolts, shall be metric units.
MARKING OF FABRICATED STEEL
alll marking of steelwork shall comply with the following requirements and shall be
subject to the agreement of the Engineer.
- Each piece of steel work shall be distinctly marked by hard stamping and shall
include orientation marks for ease of erection.
FABRICATION
6.1 General
All fabrication shall be carried out in a workmanlike manner generally in
accordance with the applicable AWS D1.1: 2015 Clause 5.
30f9
ECE/FP/002
Rev. No.:0Technical Procedure for Fabrication and Welding of Structural Stee!
APF
6.2 Cutting
Plates, members, brackets and other steel work shall be cut in compliance with
ECE Fabrication drawing which contains all dimension details clearly.
- All edges shall be smooth profiled, flattened and equalized unless otherwise
shown on the design drawings or agreed by the Engineer.
- The end of tubular or hollow sectians shall be profiled to fit the Snape of the
members to which they connect, and shall not be sheared or flattened unless
otherwise shown on the design drawings or agreed by the Engineer.
6.3 Punching and Drilling of Bolt Holes
- The bolt holes clearance shall not exceeds 3 mm regardless of hole
size/dimension.
- Oversized and slotted holes for high strength bolts will not be permitted unless
shown on the design drawings or otherwise agreed by the Engineer.
6.4 Machined Surfaces
Rockers, rollers or hinge gearing sets shall be machined fo the radii shown on.
the design drawings, with the axis of rotation at right angles to the direction of
the motion of the structural members which they support. Machining tolerances
shall be as shown on the design drawings.
6.5 Splicing in Members
- All structural members shall be single lengths, except where splices are shown
‘on the design drawings, or where the Engineer has given prior written approval.
6.6 Boxed Members
- A butting edges shall be connected and sealed with a continuous welds
- Weld reinforcement ground flush only when shown in the drawings
- Stiffeners and other details that will be enclosed within the box members shall be subject to
inspection by the Engineer before the closure plates are welded into place.
6.7 Connections
= In general, shop connections shall be welded and field connections shall be bolted, unless
otherwise shown on the drawings. All bolting and welding shall conform to steel structures
specifications.
- Unless otherwise noted, only one butt joint connection for each steel assembly (Either tubular or
non-tubular members) shall be allowed per each 10 meters length of the member.
6.8 Shop Errors
Fabrication errors or potential errors resulting from incorrectly detailed components are to be
reported immediately to the Engineer. The Engineer will consider the action required for
correction or modification of the work. Should corrections be necessary, written instructions will
be given to the Contractors to carry out such work to the account of the responsible party.
4of9
ECE/FP/002
Rev. No.:0Technical Procedure for Fabrication and Welding of Structural Steel
FPF
6.9 Inspection during Fabrication
During fabrication, the Contractor shall permit the Engineer or the nominated representative free
access to the Fabricators Works at all reasonable times for the purpose of carrying out
inspections. Units shall be laid out and fabricated as necessary so that all parts are accessible for
final inspection before transportation to the site.
Where steel has been inspected by the Engineer at the shop, before being delivered to the site,
such inspection shall not relieve the Contractor of the responsibility for the correctness of the
fabricated steel.
WELDING
- All welds should conform the Welding procedure Specification arranged by ECE
QA/QC Engineer.
- All welds shall be general purpose (GP) unless noted otherwise on the approved
drawings.
- All welds shall be made with the appropriate grade of electrode suitable for
the grade of steel being welded. Welds shall be thoroughly chipped to remove
slag and shall be the full size specified and/or as shown on approved drawings,
- Unless otherwise noted, all butt welds shall be complete penetration butt welds
and where possible, shall be Single V but! welds except that in the 25 mm base
plate or higher thickness the welds shall be Double V and made with low hydrogen
electrodes. Over reinforcement of butt welds and pronounced bumps shall be of
3mm maximum Height. Subject to the Engineer's approval. Beams, flange plates,
web plates and cord members of long trusses may be butt welded in the shop to
form any long lengths required provided that such splices in the member, in the
case of compound members, the splices in the individual units shall be staggered
by not less than 40 mm weld length As shown in (annex 1- Fig. B)
- Unless otherwise noted, all built up H-Sections with an 8mm web thickness or less
shall be welded by SAW process for only one side of each T-Joint vice-versa as
shown in (annex 1 Fig. C), since the other side shall be intermittent Fillet weld by
not less than 40 mm weld length of FCAW process; in the case of higher web
thicknesses the two-sided corner of each T-oint shall be welded by SAW
continuous weld. The Fillet weld size should comply with (Annex 1 - Fig. A)
-To enable complete assemblies to be erected, site welding of individual members
attached to main shop fabricated pieces shall be permitted as indicated on the
Engineer's /fabrication drawings. The individual members shall be welded to their
main components at ground level.
- Adequate mobile welding facilities shall be provided for this operation.
- Site welding may be used. All relevant details and procedures must be approved
by the Engineer before site welding can commence.
- Qualification of welding procedures and personnel shalll be carried out.
Sof 9
ECE/FP/002
Rev. No.0Technical Procedure for Fabrication and Welding of Structural Stee!
FPF
Weld procedures shall be approved and personnel shall be qualified prior to
commencing welding on structural steel or components.
Documentary evidence of personnel qualifications shall be submitted to the
Engineer for review prior to fabrication.
- Unless noted otherwise on the drawings an attached Annex-2 shall be followed
to provide a general purpose clarification of the commonly used joint details /
schemes illustrated by welding symbols
SHOP ASSEMBLY
Sections of the fabricated steelwork shall be shop assembled when specified on
the drawings. During shop assembly, drifting of misaligned holes shall not be
permilied. Misaligned holes shall be drilled and reamed to a larger size and
larger bolls fitted, subject to the agreement of the Engineer.
PLATFORMS, WALKWAYS, STAIRWAYS AND
LADDERS
The platforms, stainways and ladders and associated attachments shall conform
to: Fixed platforms, walkways and ladders - design, construction and installation
and the following requirements.
9.1 General
All decking shall be firmly fixed to the supporting steelwork.
Shop fixings shall be welded and field connections shall be bolted unless
otherwise shown on the drawings.
Bolts or other fixings on the surfaces of platforms, londings and walkways shall be
countersunk flush with the surfaces.
9.2 Floor Grating
Floor gratings shall be as specified on the approved drawings.
Gratings shall be furnished to be continuous over two spans, or more where
practicable. Grating panels shall be banded. Longitudinal and cross bars in
‘adjacent sections shall be in line when erected end to end.
Where removable grating is required, the maximum grating panel shall be
normally 1500 mm x 1200 mm wide.
TOLERANCES
Tolerances for shop fabricated steel shall comply with the relevant requirements of
AWS D1.1: 2010, unless specified otherwise on the design drawings.
The deviation in pian position of a column shall not exceed 10 mm from its
specified position at any point.
6of 9
ECE/FP/002
Rev. No.:Technical Procedure for Fabrication and Welding of Structural Steel
FE
11.0 INSPECTION
Welding of shop fabricated structural steel and field welding shall be subjected
to Non Destructive Tests (NDT) as follows:
1- Visual inspection of 100% of all welds shall be performed.
2. All welds of all thicknesses range to be tested by 10% of Liquid (Dye) penetrant
test (LPT)
3. Any additional tests can be carried out by a third party based on the contract
documents and/or based on the Engineer requirements. Table | give Us initial
guide to major methods for the nondestructive examination of welds.
or jable tm
inspection Equipment [Enables ‘Advantages |Limitations |Remarks
Method Required Detection of | |
Visual Magnifying Surface flaws- |Low cost. Applicable to ||Should always
lass cracks, Can be surface Ibe the primary
Weld sizing porosity, applied while defects only. method of
gauge unfilled craters, work isin Provides no inspection, no
Pocket rule slag inclusions _|process, permanent |matter what
Straight edge _Warpage, ‘permitting record. Jother
‘Workmanship underwelding, correction of |techniques are
standards ‘overwelding, faults. required,
poorly formed Gives |Is the only
} beads, lindication of "productive"
‘misalignments, incorrect ype of
improper fitup procedures. linspeetion,
| Is the
Inecessary
function of
leveryone who
in any way
‘contributes to
the making of
the weld.
Radiographic Commercial Interior ill X-ray
X-ray or |macroscopie indications i 1g inspection is
gamma units flaws-cracks, larerecorded angles of —_required by
‘made porosity, blow on film, gives exposure, many codes
especially for holes, lapermanent — operating and
inspecting nonmetallic record. equipment, __|specifications.
7of 9
ECE/FP/002
Rev. No.: 0Technical Procedure for Fabrication and Welding of Structural Stee!
FF
welds, inclusions, __|When viewed and |Useful in
castings and incomplete root on a interpreting qualification
forgings. penetration, {fluoroscopic indications. _jof welders and
|Film and |screen,alow- Requires welding
[processing | ‘cost method safety processes.
facilities. |burnthrough. of internal _ precautions. [Because of
Fluoroscopic | inspection _Not generally cost, its use
viewing | suitable for should be
equipment. | fillet weld limited to
, inspection. those areas
| |where other
methods wi
? {fot provide thie
{assurance
|required.
Special Excellent for Simpler to use Applicable to (Elongated
commercial detecting ‘than ferromagnetic defects parallel
equipment, _ surface radiographic materials ‘tothe
Magnetic {discontinuities |inspection. only. magnetic field
powders - dry [especially Permits Requires skill |may not give
or wet form; surface cracks. [controlled in |pattern; for
may be ‘sensitivity, interpretation this reason the
‘fluorescent for ‘Relatively of indications |field should be
‘viewing under low-cost. and lapplied from
lultraviolet method, recognition of |two directions
| irrelevant [at or near right
patiems. _jangles to each
Difficult to other.
use on rough.
i surfaces.
Commercial Surface cracks Applicable to Only surface [In thin-walled
kits not readily |magneticand defects are __|vessels will
containing visible to the nonmagnetic detectable. _[reveal leaks
fluorescent or unaided eye, materials. Cannot be __jnot ordinarily
dye penetrants Excellent for Easy to use. used located by
and locating leaks Low cost. effectively on usual air tests.
developers. in weldments. | hot irrelevant
‘Application assemblies, [surface
‘equipment for iconditions
|the developer. (smoke, slag)
|A source of |may give
80f9
ECE/FP/002
Rev. No.:0Technical Procedure for Fabrication and Welding of Structural Steel
FE
ultraviolet misleading
‘light -if indications,
‘method is
used.
/Special ‘Surface and | Very ‘Requires high |Pulse-echo
[commercial ‘subsurface sensitive. __|degree of skill jequipment is
equipment, flaws including Permits ‘in interpreting {highly
either of the those too small probing of — pulse-echo developed for
|Auorescent |
[pulse-echo or to be detected joints (patterns, |weld |
transmission [by other inaccessible [Permanent inspection
wn YPC. methods. to record is not .purposes...._
Standard Especially for radiography. readily ‘The
reference detecting i ‘obtained. ‘transmission-
patterns for subsurface | | type
interpretation lamination-like equipment
lof RF or video |defects. simplifies
"patterns. pattern
linterpretation
where it is
| applicable,
12.0 ATTACHMENTS
Annex -1: Fillet weld sizes, Built up and intermittent welds configuration.
= Annex.-2: a general purpose joint details.
9of 9
ECE/FP/002
Rev. No.: 0