Method of Statement For Bored Piles
Method of Statement For Bored Piles
Method statement of bored piles is a construction procedure which includes hole boring into the
ground, installing steel reinforcement and casting with concrete to form a pile, etc. Bored piles are
constructed in the ground by boring in the circular shape of designed diameters to transfer load
from the superstructure into the ground through friction and end bearing.
I. Description of Works
1. Introduction
This Method Statement defines the sequence and describes the control procedures to be
followed for Construction of Bored Piles for (Name of Project).
In the course of the method statement, the construction of cased bored piles with a diameter of
1200 mm and pile lengths ranging from 15.1 m to 33.6 m is described in details.
The scope comprises of:
Construction of Soldier Piles including Drilling, Installation of Reinforcement Cages and Pouring of
Concrete
2. Definitions
xxxx: Developer / Client
xxxx: Project Management
xxxx: Supervising Consultant
xxxx: Main Contractor
CM: Construction Manager
QC: Quality Control
HSE: Health Safety & Environment
PPE: Personal Protective Equipment
PMV: Plants, Machinery & Vehicles
GIS: Geographical Information System
3. References
Information sources may include, but not be limited to, verbal or written and
graphical instructions, signage, work schedules/ drawings/specifications, work
bulletins, charts and hand sketches, and Material Safety Data Sheets (MSDS).
Excavation Specification, (Reference goes here)
Concreting Specification, (Reference goes here)
Project Specifications
Baseline Program, (Reference goes here)
Construction Environmental Management Plan, (Reference goes here)
Concrete Mix Design (C50/60 OPC 70%+PFA 25%+MS 5%), (Reference goes here)
Grout Mix Design for Shoring, (Reference goes here)
Polymer, Bentonite & Soda Ash, (Reference goes here)
Steel Reinforcement, (Reference goes here)
General Lifting Plan, (Reference goes here)
Specification for Carbon Steel Bars for the Reinforcement of Concrete, BS 4449-2005
Geotechnical Interpretative Report, (Reference goes here)
Calibration Certificates for Survey Equipment, (Reference goes here)
Shop drawings: (Reference goes here)
Material References:
Bonding Agent (Reference goes here)
Method Statement for Slope Protection Measures (Drop Chain Link, Rock Bolting & Shotcrete)
Polymer, Bentonite & Soda Ash
Monitoring Instruments
Galvanized Pipe for Inclinometer
Galvanized Pipe for Crosshole
Sonic Logging
Plastic Spacer
Document References:
Monitoring Plan References (Reference goes here)
GIR Reference (Reference goes here)
Slope Inspection and Surface (Reference goes here)
Protection Procedure (Reference goes here)
Plot Limits Setting Out (Reference goes here)
Installation of Inclinometer in Pile and Borehole and Type of Inclinometer (Reference goes here)
4. Responsibilities
Project Manager
Responsible for accomplishing the stated project objectives which include creating clear and
attainable project objectives, building the project requirements, and managing the constraints of the
project management triangle, which are cost, time, scope, and quality.
Operations Manager
Overseeing and having responsibility for all the activities which contribute to the effective work
products and services. His main role is to understand strategic objectives, developing an operations
strategy, designing operation’s services and processes, planning and controlling and improving the
performance of the operation.
Superintendent
Organizes coordinates and supervises the work of the
Foreman, Sub- Foreman and/or craft employees on construction. Determines work priorities,
schedule jobs and operations and coordinates work activities within the design area. Exercises
control over the rate of construction progress in order to complete the construction project within
time limits.
Site Engineer
Supervise operations in accordance with the approved Method Statement, shop drawings,
specifications, material submittals and schedules to achieve the acceptance of the
project deliverables.
Site Supervisor
Supervise closely, the activities designated to them and ensure that all instructions and safety
procedure are followed and strictly adhered to.
Site Foreman
To liaise with the Site Engineer and Supervisor for the work execution.
QA/QC Manager
Responsible for all aspects related to the Project’s Quality Assurance and Quality Control. QA
Manager Prepares the detailed Project Quality Plan and ensuring that it is understood,
implemented and maintained at all levels of the project organization. QC Manager is in charge of the
preparation of the Inspection and Test Plan (ITP) and liaising with Third Party Inspectors,
Subcontractor’s Quality Personnel, and Independent Testing Laboratories for quality related matters.
QA/QC Engineer
Ensure the proper implementation of the Quality system and monitor the overall quality of the work
is maintained. Conduct inspection and monitor tests. Determine and report any nonconformance
and recommended corrective actions. Ensure that all personnel is aware of the quality requirement.
Training of relevant personnel.
Conduct surveillance and inspection duties at various stages
to ensure compliance to QA/QC Plan.
HSE Manager
Health, safety, and environmental (HSE) managers generally plan, coordinate and implement issues
and directives within the organization. They ensure safe environmental working conditions for all
employees.
HSE Engineer
Ensure enforcement of safety procedures in accordance with the approved HSE Plan. Will be closely
monitoring the site engineer’s strict implementation of the MS and Risk Assessment, the use of
proper tools and equipment to maintain safety, certifications of equipment and their adherence to
safety regulations, reporting of any unsafe work or stopping work that does not comply with ES&H
procedures. Will advise for Health & Safety requirements and monitor the Hazard
controls implemented on site as per the Method Statement/Risk assessment.
Mechanic
Responsible for the repair and maintenance of all machinery equipment and plants involved in the
project execution.
Electrician
Responsible for connecting and testing all electrical contacts and system during plant assembly.
Ensure that all electrical works are in compliance with the Electrical Standards.
Welder
Responsible for all welding works needed for the work performing a variety of welding functions.
Reads and interprets blueprints and machine drawings to determine specific welding requirements.
Equipment Operator
The only authorized person to operate any equipment to be used in the project.
Rigger
The rigger assists in movement of heavy equipment and loads to be lifted. A rigger setups machinery
and secures it in place and signal or verbally direct workers engaged in hoisting and moving loads, in
order to ensure the safety of workers and materials.
7. List of Subcontractors
Main Contractor:
xxxxxx
Subcontractors for Piling:
xxxxx
II. Resources
1. Plant and Equipment
Note:
All 3rd Party Certificates shall be inspected prior to commence lifting operation.
All machines shall fulfill Project Specifications requirements if required.
Calibration Certificates for Survey Equipment, (Reference goes here)
Kelly bars are key components in the execution of boreholes with hydraulic rotary drilling rigs. The
Kelly bar consists of 2 – 5 telescopic tubular sections with a system of 6 drive keys and lock recesses,
welded onto their outer surfaces. Additional shock absorbers prevent the Kelly bar from damages
during the excavation process. Kelly bars transfer the torque of the rotary drive and the crowd
pressure of the crowd system concurrently to the drilling tool at the bottom of the borehole where
the drilling tool will loosen the material by rotation.
A pin-system at the bottom of the Kelly bar allows for fast changing of drilling tools.
1.3 Drilling Tools
The drilling tools are loosening the subsoil and capture loosened material. They are equipped with a
so-called Kelly box (on top of the tool) and attached to the Kelly pin at the bottom of the Kelly bar by
means of a bolted connection.
According to the existing type of soil or rock different tools with different type of teeth are used.
All tools have to be supplied with sufficient teeth. The quality and wear on the teeth have to
be checked regularly and teeth have to be replaced if they are worn out or lost to ensure
sufficient working progress.
The pictures below provide an overview of some typical drilling tools and their principal
application.
1.4 Casings
Due to the presence of rock directly below the starting level of the drilling a short casing of <10.0 m
is required only. In order to penetrate firm soils, rock or artificial obstacles a casing shoe/starter
casing, equipped with a ring of cutting teeth, is attached to the lower end of the casing string. The
starter casing will be equipped either with replaceable or weld on teeth.
2. Work Force
3. Light Tools
Description No. of Units Application
As per
Power Tools (Various) Construction
Site requirement
As per
Hand Tools (Various) Construction
Site requirement
III. Materials
a. Concrete
Concrete for bored piles shall be composed in accordance to BS EN 1536 “Execution of Special
Geotechnical Works – Bored Piles” in order to have:
– a good ability to flow
– the ability to pass reinforcement without segregation
– a high resistance to wash out and segregation
– a sufficient degree of self-compaction
The final mix design(s) will be tested and shall be approved by the client prior to the commencement
of the works on site. Refer to approved Concrete Mix Design (C50/60 OPC 70%+PFA 25%+MS 5%),
(Reference goes here).
The percentage of additives/chemical to be used may refer to the attached Technical Data Sheet in
Appendix E.
Project Requirements
Concrete will be supplied in accordance with applicable standards, specifications, environmental
and pouring conditions as well as the approved pile design.
– Concrete strength: C50/60 (with fc, k, cylinder = 50 MPa and fc, k, cube = 60 MPa
– Maximum aggregate size: 20 mm
– Concrete supply rate: Average 80 m³/hr.
– Slump range: 200 mm +40mm/-20
– Minimum concrete cover for piles: 75mm according to EN 1536:2010
The sampling and testing of concrete prior to pouring will be in accordance with the approved ITP for
Bored Piles.
Trial Mix
Preliminary trial mixes have been executed in order to verify fresh concrete properties in the
laboratory. A large-scale trial mix shall be conducted in order to check;
Fresh Concrete on:
– Slump + Flow over complete retarding time
– Bleeding behavior
– Segregation tendency
Hardening / Hardened Concrete on:
– Initial and final setting time
– Compressive Strength (development) 7and 28 days
b. Reinforcement / Reinforcement Cages
Reinforcement with steel grade and dimensions according to the project specifications will be used
for the fabrication of reinforcement cages, where mill certificates for the steel shall be provided by
the supplier.
According to the design, reinforcement steel of a steel grade BSt 500 A (with a yield strength of 500
N/mm²) will be used.
The reinforcement cages will be pre-fabricated and delivered to the installation location in
accordance with approved construction drawings. The reinforcement cages shall be designed rigid
and stable enough to withstand the forces applied while handling and installation. In case too high
deformations while cage handling or lifting will occur, the designer shall be consulted and additional
stiffening elements added. The type of reinforcement cage to be used at a specific location/section
may refer to the approved shop drawing attachment listed in Appendix A.
Concrete spacers shall be used at proper intervals in height and evenly distributed around the entire
perimeter of the cage to keep the reinforcement in the center of the borehole and thus to ensure
the required concrete cover at all locations (refer to the approved shop drawing).
c. Fly Ash, Sika Intraplast Z, Sikament- 500 and Sika Retarder
The materials which will be used generally may refer to approved Concrete Mix Design (C50/60 OPC
70%+PFA 25%+MS 5%), (Reference goes here).
1. Test Certificates
All Test Certificates for the above materials shall be provided.
V. Methodology
A. Bored Piles Construction
1. Scope
The selection of the technique depends on the prevailing soil conditions, the pile diameter, the pile
depth and the technical specifications (Execution of Special Geotechnical Works-Bored Piles, Ref.: EN
1536:2010). The piles will be executed by the use of a hydraulic rotary drilling rig type BG25, BG28
and BG40 equipped with a telescopic Kelly Bar of a length of 65 m. The soil conditions require casing
of a length of approx. 10 m.
The pile construction shall be done as per approved Shop Drawing.
The scope comprises of:
A. Mobilization of Staff and Equipment to Site
B. Setup of Equipment on Site
C. Construction of Pile Bores including Drilling, Installation of Reinforcement Cages and Pouring of
Concrete
D. Supply of Reinforcement Cages and Concrete
E. Disassembly and Demobilization of Equipment from Site
2. Construction Sequence
A. Casing Installation with the Rotary Drive of the Drill Rig (Pushing and Rotation).
B. Drilling with Bucket, Auger or Core Barrel. Stabilization of the wall of the bore partially with
casings.
C. Installation of reinforcement cage with the auxiliary winch of the drill rig (or alternatively with a
separate service crane) into the borehole.
D. Concrete pour via Tremie Method. The required top of concrete (calculated as per the top level of
casing given by the surveyor) will be monitored using an end-weighted scale. The quantity of
concrete may be increased in order to fill the space created by the insertion of the casing.
E. Extract Casing with the Rotary Drive. The extraction will be done by rotating the casing gradually
on a clockwise and counterclockwise direction until the casing has been completely removed. The
casing can be removed once the concreting has been completed.
While concrete rises inside the bore, the tremie pipe string will be extracted. When shortening the
tremie pipe it has to be assured that the bottom end of the tremie pipe remains in the fresh
concrete by at least 3.0 m length at any time. Casings will only be withdrawn to such levels that
concrete level will be still above the toe of the casing.
For measurement of the level of concrete within the pile, an end-weighted measure tape will be
used. The concrete will be poured above the final pile cut-off level to ensure proper quality and
contamination free concrete at the pile cut-off level. The excess concrete above the cut-off level will
be removed after hardening.
On completion of the concreting operation, the temporary casing will be withdrawn using the piling
rig.
No dewatering operation will be carried out in the area of pile casting. The minimum distance
between running well and pile casting shall not exceed 40 m.
3. Tolerances / Requirements
In accordance with EN 1536:2010 – Execution of Special Geotechnical Works – Bored Piles
Pile Position and Verticality:
Plan position for bored piles at commencing surface will be within 0.05 x d1 with 1.0 m < d1 ≤ 1.5 m
= 60 mm in any direction.
The finished pile shall be within the maximum deviation of 10% of pile diameter. Refer to EN 1536.
The verticality of the piles shall be within 1.0 % in both transverse and longitudinal directions.
Reinforcement Cages:
Reinforcement shall be maintained in its correct position during concreting of the piles within a
vertical tolerance of +150/-150 mm on the level of the reinforcement projecting above the final cut-
off level.
Setting Out:
Setting out pins shall be placed within a tolerance of 2.5 mm in any direction.
4. Specific Requirements
4.1 Verification of Technical Information
Prior to commencing any operations, technical information such as pile coordinates, platform and
cut off levels or validity of drawings will be verified to ensure that the pile will be built in accordance
with the requirements and design.
4.2 Construction of Borehole
a. Excavation Quality
To achieve the required verticality, the accurate set out of the casing is essential.
During installation of the starter casing, its verticality is checked several times. The built-in
inclinometers in the operator’s cabin allow exact verticality control and the rig operator makes
corrections by activating the mast positioning cylinders. Also, the casing itself will be checked
manually using a spirit level.
Upon reaching the designed depth and cleaning the pile base, the final depth will be confirmed by a
manual measurement with a measuring tape.
The excavated material will be continuously checked to confirm the basic soil assumptions and thus
the design premises (Reference goes here)
0). After the final depth is reached, the base will be cleaned with a special cleaning bucket. This
bucket has no teeth at the bottom.
The base will be checked by the client. Loose material on the bottom which has a negative impact of
the bearing capacity may be removed with the cleaning bucket, the air-lift method or submersible
pump.
b. Check of Excavated Soil
The excavated spoil will be continuously checked to confirm the soil report. In case of any variation,
the construction method and the used drilling tools may be adapted to the new soil conditions, if
required.
4.3 Reinforcement
The steel reinforcement will be tested by the supplier and test certificates will be submitted for
approval.
The reinforcement cages are manufactured according to the specifications. Prior to installation cages
are checked, that:
All rebars are installed and fixed according to the shop drawings and specifications.
All spacers, stiffeners, bands, lifting devices, etc. are installed and fixed according to the drawings
and specifications.
All joints of the cage sections are carefully prepared and provide the required lap length.
All starter bars will be protected by using PVC sleeves to eliminate the bonding of concrete and steel
during pile head chipping.
The cages have to be centered with spacers.
4.4 Concreting
a. Concrete Testing
It has to be ensured that the delivered concrete is in compliance with the technical specifications
and the practical requirements for the pouring process.
Before the actual concreting of a pile starts, slump tests will be made by the supplier to confirm the
workability of the concrete.
Test cylinders for drilled shaft concrete in a sequence specified in the contractual documents will be
taken at the place of concreting and should be tested after 7 and 28 days.
b. Pouring of Concrete
The concrete will be delivered to site in ready-mix trucks in accordance of the approved Mix Design
enclosed in Appendix G. The concrete quantity shall be sufficient to guarantee a continuous
concreting procedure without interruption due to non-availability of concrete.
The concreting will be performed by pouring the concrete continuously from the concrete pump
through the tremie pipe, filling the borehole from bottom to top. To avoid segregation, measures
will be taken to minimize excessive contact of fresh concrete with water.
During concreting, the tremie pipe will remain embedded in the fresh concrete by a minimum of 3.0
meters. The total volume of concrete consumed by each pile will be calculated and compared with
the theoretical volume in order to identify the quantity of over-consumption. The concreted level
will be brought to at least 1000mm above the pile cut-off level to ensure good quality and
contamination-free concrete at pile cut-off level. The surplus concrete part will be chipped/trimmed
for the purpose of construction of the capping beam. Trimming will be carried out with a pneumatic
or hydraulic breaker.
5. Records
Pile records shall be kept as indicated in the asterisk in Table 1.1 below, of the installation of each
pile and shall submit 2 signed copies of these records to the Engineer not later than noon of the next
working day after the pile is installed. The signed records will form a record of the work. Any
unexpected driving or boring conditions shall be noted briefly in the records.
Use 3.2 mm diameter drill bit to drill holes in the casing. The riveting should be done at
diametrically opposite points 90° apart. Seal joints between the bottom cap and casing with mastic
waterproof tape. One round of this tape with 10 mm overlap is sufficient. Press the tape firmly after
applying, to remove any air pocket. Additionally, wrap three to four rounds of BOPP tape with a little
force over the mastic tape for additional protection. Proper sealing is necessary to prevent intrusion
of backfill materials inside the casing.
Further, attach a fixed coupling each to one end of casings to be installed in the borehole. Clean
mating surfaces with a moist cloth (isopropyl alcohol can be used if greasy). Push 160 mm long fixed
coupling over the end of casing up to the maximum allowable depth of around 80 mm. Drill holes
with 3.2 mm bit and pop rivet coupling to the casing at four places (position for two pop rivet holes
are marked on coupling the other two holes should be symmetrically drilled). Seal joint between
fixed coupling and casing with mastic waterproof tape and BOPP tape. Proper sealing is necessary to
prevent intrusion of grout inside the casing. The casing assemblies are now ready for installation.
Carefully transport them to site, when required.
2. Information to Personnel
Safety Induction
Job training
Superintendents Notices/Memos
Toolbox talks
STARRT Card
3. Special Safety Requirements:
All necessary personal/protective equipment (PPE), as well as the harness, be provided.
Banksman, wearing distinctive vests, shall be assigned to help operators maneuver their equipment.
The equipment operators shall possess the required licenses and certificates.
Generated dust shall be controlled by periodic water spraying.
The required TSTI will be prepared prior to the commencement of work and positively implemented.
The project safety officer is responsible along with the project zone site engineer for ensuring that all
operations are carried out with due regard to the safety of all project personnel & property.
In case of working at night, please refer to Method Statement for Night Works (Reference goes
here).
4. Emergency Procedures
(Reference goes here)
5. Emergency Contact Numbers
(Reference goes here)
Chief Surveyor
A Chief Surveyor ensures that surveying data are collected and recorded accurately and that all
company procedures are followed by crew members.
XII. Attachments
1. Appendices
Appendix A: List, Sketch, and Drawings
1. Shop Drawing List
2. Shoring Layout
3. Grout Plant
4. Anchor Fabrication Area
Appendix B: Risk Assessment
Appendix C: Permit to Work (Excavation Works) & Lifting Permit
Appendix D: Inspection and Test Plan
Appendix E: Materials
1. Technical Data Sheet & Material Safety Data Sheet
2. Test Certificates and Technical Data Sheet
Appendix F: Equipment Data Sheet & Third Party Certificates
Appendix G: Concrete/Grout Mix Design and Trial Mix Results
1. Concrete
2. Grout
Appendix H: Baseline Programme
Appendix I: Quality Forms
Appendix J: Organizational Chart
Appendix K: Anchor Details
Appendix L: Survey Equipment Calibration Certificate
Appendix M: Rig Stability and Ground Failure Estimation for Working Platforms
Appendix N: Emergency Preparedness
Appendix O: Logistic Plan
Appendix P: Piezometer Layout