Method Adoption Workshop
Method Adoption Workshop
July 2004
2 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Expectations
3 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Tactical Organization Overview
CCS Steering Committee
Dan Benning, Fiona Dias, John Froman,
Chip Molloy, Mike Jones
Project Executives
Nick Otto (CCS)
Richard Baca (IBM)
Project Mgt
Masha (CCS)
Bus. Governance
Bob Manning (IBM)
Mike Beam (CCS)
Steve Schillinger (CCS)
Jennifer Churchil (CCS)
Arch. Governance
Harry Waldo (CCS)
Jack Ehrhardt (CCS)
Todd Mardsen (IBM)
Sunny Mishra (IBM)
4 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Tactical Organization Overview-continued
360Commerce 360Commerce
Jennifer Allen-Butler Sreenath Reddy
Bryna Wortham
TBD Yantra
Phil Tympanick
Yantra
Andy Johnson StreamServe?
TBD
StreamServe?
TBD
5 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
(WIP) Project Plan/Task List
6 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Introduction to IBM’s, IGS METHOD
Method Blue has a Manage Relationship, Project Management, Risk,
Engagement Quality and Communication
Two Domain
Structure to Work Prepare Focus Select Redesign
Prepare Focus Select Redesign
Products:
7 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Work Products: Focused, attainable goals
Prepare Focus Select Re-design
1.5
Assess
1.3 Business
Identify Processes
Strategy &
Business
Environment
1.1 1.6 1.8
Assess
Initiate Case Organization Confirm
for Change & Control Case for
Systems Change
1.4
Assess
Customer
Wants & 1.7
Needs Assess
Information
Systems
1.2
Allocate
Costs to
Processes
WP WP
TASK 01 a TASK 02 TASK 04
c
WP
TASK 06
f
WP
TASK 09 TASK 11
k
8 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
The Work Product Concept
Engagement domain
WP 01-01
30
20
WorkProduct A WPD is divided into 2 main sections:
10
Business domain
0
What to do
Description
83 85 87 89
84 86 88
Estimation
IT domain
9 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Intellectual Capital Databases Organize and Disseminate
the Information
Prepare Focus Select Re-design
Engagement domain
30
20
10
0
Business domain
83 85 87 89
84 86 88
Organisation domain
Application domain
IT domain
10 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Intellectual Capital Databases
11 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Work Product Example
Includes
- Instructions IBM Global Services
- Templates 1 Description
The Master Test Plan is a document of understanding on testing between the various
stakeholders of the project. It documents the “what” (scope and objectives), the “why” (purpose),
the “when” (key milestones), and the “who” (organizational roles and responsibilities) for all levels
of dynamic testing. Full lifecycle testing is an iterative process. The development of the master
test plan is started early in the development lifecycle, and is refined, as more information
becomes available. It ties together all the detailed test plans and points to them. Each testing
level represents a known level of physical integration and quality of the system solution under
development.
The master test plan evolves from the test strategy and is driven by the quality goals contained in
the quality plan. It uses the concepts or organization level standards, and applies them to the
project to identify specific test focus areas, types and levels of testing as they apply to the project.
As the master test plan is developed it is possible that the levels of testing, as prescribed by the
standards, may not be sufficient to meet the test objectives or the quality goals set forth by the
quality plan. In this situation, the base set of test levels may be modified or additional levels of
testing defined to accommodate the project needs. For example, Performance Testing, which is
a type of testing as per IBM’s standard testing methodology, could also occur over a number of
different levels of integration (i.e., at unit, integration, systems integration, operability, etc). It is
possible that there could be a separate detailed (and/or master) test plan for Performance Testing
and that Performance Testing could occur, as a stand-alone test, at different levels of integration.
It is also true for Usability testing that spans the full lifecycle and runs throughout the
development phases. Thus the master test plan needs to be scalable and tailorable, and must be
flexible enough to be used for the small project or the very large projects.
For smaller size projects the master test plan may combine the detailed plans for different levels
of testing into one plan.
The table of contents of a master test plan includes the following sections, but does not include
detailed testing tasks or tracking of them or test schedules:
Test objectives: describe the tangible goals of testing for this engagement based on solution
objectives.
Risk assessment: detailed risk assessment driven by the business functions and technical
requirements of the solution under development.
12 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Work Product Example
Example: APP 133 1.0 Introduction
1.1 Overview
This document constitutes the Master Test Plan for VMS Release 2.0. It describes the overall
testing strategy. Its purpose is to answer such questions as 'what will be tested?, how will it be
tested?, who will do it and when?'. It documents system objectives, test objectives, test team
roles and responsibilities, resource requirements, the test strategy and methods and standards to
be used for testing. This is a communication vehicle for the entire project team including,
developers, testers and users to get a high level overview of how the application will be tested.
It provides a comprehensive plan for all aspects of testing including, Unit, Integration, System
and Acceptance tests. This master test plan will be used by both the bank and IBM as a joint test
plan. Where differences exist in terms of reference or in levels of testing as used by the two
organizations, adequate care has been taken to ensure that the contents reflect the bank’s
standards.
At this time it is contemplated that the bank and IBM will work towards a common set of testing
standards and possibly a joint System Test Plan for future releases of VMS.
The current system resides on two platforms; IMS host and PC Lan. The PC Lan platform is
further broken down to two types; Vault Lan and Branch Lan.
The branch LAN environment consists of 4702 Controller, FBPS/Powerlan and FBSS/OS2
attached workstations.
13 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Earned Value Tracking
Focused work assignments and work package completion tracking
prevents timeline slippage
• Each phase has defined deliverables and work packages
–IGS METHOD templates logically guide work effort
• Ground rules
15 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Lessons learned from prior projects
Need leadership and drive to complete
- Beyond a sequence of events, Beyond a ‘project plan’
Need continuous, visible completion feedback
- Keep the pace and urgency up front
Need reliable reporting forcing daily accountability
- Fair and respected measurement, everyone understands
- Identify bottleneck tasks between teams, daily
- Provide alternatives to continue instead of excuses to delay
Need clear cut, attainable goals
- Move on to next task, ‘time box’ work effort
Need a repeatable process and discipline to execute to plan
Our project will use IBM’s, IGS METHOD
- Predictable, repeatable delivery
- Reduced Risk, disciplined delivery
- Rapid installation, SPEED
16 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Method Adoption Workshop
Example: Only
Project, all Business Releases= 100%
- BR0=25%, BR1=20%, BR2=30%, BR3=25%
Solutions team=45%, Integration=30, RICE=25%
17 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Earned Value tracking output example
60000
50000
40000
estimated total cum
30000 actual IBM+i2 cum
actual cum i2
20000
10000
0
10/14/2000
11/14/2000
12/14/2000
10/14/2001
11/14/2001
7/14/2000
8/14/2000
9/14/2000
1/14/2001
2/14/2001
3/14/2001
4/14/2001
5/14/2001
6/14/2001
7/14/2001
8/14/2001
9/14/2001
18 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Earned Value detailed tracking example
19 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Earned Value detailed tracking example
20 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004
Project Management Meeting Schedule
Work week pace
- Close of business Thursdays
Weekly team inputs submitted to PMO
Only work product steps completed is reported, no partial completions accepted
- Prior to Tuesday’s Project Status Meeting
Team Lead weekly status review, time and location by team leads
Concurrence of work product status: completions, sign off’s, started, late
- Tuesdays
Project Status
Review new risks and issues
- Weekly 3:30-4:30 pm ET, DR2 5c/d
- Project managers and Team Leads, standard format provided by PMO
- Wednesdays
Risks, Issues Status
Understand, log entries and assign actions items
- Weekly, 2:00-3:00 pm ET, DR2 5c/d
- Project managers and Team Leads
- Thursdays
CIO progress update briefing
Progress report, key issues and risks reviewed
- Project executives and CCS project manager
21 Store of Tomorrow | 4/28/2004 | IBM and CCS Confidential © Copyright IBM Corporation 2004