Slope Stability Report
Slope Stability Report
www.caenz.com
Slope Stability & Landuse
September 2009
www.caenz.com
Approved by:
RJ (George) Hooper
Recommended Citation
CAENZ 2009b
ISBN 978-0-908993-05-5
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system, transmitted,
or otherwise disseminated, in any form or by any means, except for the purposes of research or private study,
criticism or review, without the prior permission of the Centre for Advanced Engineering.
Copyright
©2009 New Zealand Centre for Advanced Engineering
CAENZ would like to acknowledge the time and American Planning Association
support given in contributing to this project; James Schwab
specifically
Riley Consultants Limited
The term landslide refers to “the movement of a mass of rock, debris or earth (soil) down a slope” (AGS,
2007a). The term ‘natural landslip’ is a term defined by the Earthquake Commission Act 1993 as “the
movement (whether by way of falling, sliding or flowing, or by a combination thereof ) of ground-forming
materials composed of natural rock, soil, artificial fill, or a combination of such materials, which before
movement, formed an integral part of the ground; but does not include the movement of the ground due
to below-ground subsidence, soil expansion, soil shrinkage, soil compaction, or erosion.”
In this report the term landslip is used in preference to landslide when referring specifically to slope
failure, the exception being when referencing other documents that use the term landslide.
An essential element in determining whether The lessons are simple; improved information
land use planning and consenting processes sharing, better communication about potential
meet good practice expectations is the hazards and new frameworks that extend
degree to which professional knowledge accountability to those best able to manage the
and institutional processes are aligned. risks of inadequate assessment or ill-informed
Participants in the planning process need to action. In drawing together the experience of a
be aware of the critical points for intervention wide range of practitioners and the experience
and their respective roles in managing relevant of two territorial authorities this study offers an
knowledge and its application to decision objective view of the issues that New Zealand
outcomes. faces in planning future land use in the presence of
natural hazards.
This study has taken an important step in
trying to delineate where that balance might Adoption of the study recommendations would
lie and in building a “process map” of the undoubtedly contribute to more effective
steps and factors influencing consented land management of slope stability risk and the
use activity as applied to landslip prone land. advancement of professional practice in this area.
Through this approach the study team has set
out to demystify professional practice and to I commend the report to you.
provide practical suggestions for improving
current approaches to slope stability risk
assessment in New Zealand.
Richard Westlake
Chairman Standards New Zealand
Preface............................................................................................................................5
Executive Summary........................................................................................................9
1. Introduction.................................................................................................................11
1.1 Background....................................................................................................................................... 11
1.2 Understanding the problem.............................................................................................................. 13
1.3 Study objectives............................................................................................................................... 14
2. Methodology...............................................................................................................15
2.1 Approach........................................................................................................................................... 15
2.2 Case studies..................................................................................................................................... 16
2.3 Integrating the outcomes................................................................................................................. 17
3. Research Findings.......................................................................................................19
3.1 Overview of the case studies........................................................................................................... 19
3.2 Survey Results.................................................................................................................................. 20
5. Conclusions.................................................................................................................33
5.1 Short term/immediate implementation opportunities...................................................................... 33
5.2 Longer term implementation opportunities..................................................................................... 33
The New Zealand Earthquake Commission Key findings of this study are that:
(EQC) provides national disaster insurance to • There is a view that all land can be
residential properties throughout New Zealand. safely engineered to make it suitable for
This includes damage caused by landslips. EQC development. This view is not consistent
exposure to natural disaster claims arising from with reality;
landslips is significant, for example amounting • While the understanding of how to reduce
to some $18 million in the 2008 year, with an landslip risk has increased over time, many
average annual cost over the last five years of professionals employed by developers
$16.6 million. and councils have not kept up with these
advances;
As part of its active role in advancing New • Geotechnical information pertaining to
Zealand resilience to natural disaster damage, various regions is held by a number of
EQC supports research and education about organisations without all parties being aware
matters relevant to reducing natural disaster of, or having access to it;
damage, and in particular the adoption of • Accountability for ensuring effective decision-
relevant new research by practitioners. Thus, making methods of the consenting process
whilst not an EQC issue alone, the Commission does not always lie where the advice that
saw advantage in bringing a study together to the process depends upon is given;
address the quality of decision making for the • A raised awareness that slope stability
use of landslip prone land and, in particular, is an issue, and improved education and
to give consideration to improving land use information sharing, is a prerequisite to
planning practices for those parts of New improved land use planning.
Zealand where slope stability is a significant Observations made by the project team during
problem. the course of this study, and direct contributions
from planners and related professionals through
This study, undertaken by the New Zealand
the workshops and survey have identified
Centre for Advanced Engineering (CAENZ),
a range of opportunities for improvements
adopted a two-fold approach to researching
to the planning process. Foremost amongst
current land use practice, and comparing this
them is the need for an integrated approach
with what may be considered good practice.
to the problem and better coordination to
Firstly, documentation held by two case study
improve communication and collaboration.
councils, Far North District and Hutt City, was
Recommendations are made for both near term
examined in order to ascertain the influence
and medium term implementation.
that available tools and their application have
had on improving professional practice and, The recommendations focus on three key areas
second, a series of surveys and workshops for action:
were held in order to provide context to the • Improved information sharing;
relationships between the different disciplines • Raising the profile of slope stability risk,
contributing to the land use decision process. and;
• Extending accountability.
The lessons from these two work streams have
then been synthesised into a ‘process map’ Adoption or action upon these recommendations
illustrating how slope stability information is not the responsibility of any single
gets incorporated into the decision-making organisation or profession. Instead the report
process, and the ways in which these sources suggests a framework for going forward that
of information can contribute to improved encourages all stakeholders to take a proprietary
understanding and a higher quality of decision interest in dealing with and improving
making. approaches to slope stability risk throughout the
country.
“Experience shows that despite engineering opportunities for improvement and ultimately;
solutions, natural processes ultimately will lead to a reduction in the exposure to
determine whether a structure and the land it landslip risk.
stands on fails or not. Determining the balance
In reviewing land use planning several statutes
between allowing people to develop or use
need to be considered. Each can be linked
land and restricting their exposure to natural
through the Regional Policy Statement from
hazards in a sometimes rapidly changing
which are devised both Regional and District
landscape is complex” (CAENZ, 2007).
Plans (as shown in Figure 1). And thus,
how these statutes are interpreted in the
1.1 Background appropriate plans adds to the complexity of
addressing slope stability through normal land
Slope stability is an issue for many parts of
use planning channels. These can be differently
New Zealand. Steep slopes, tectonics and
applied across the country.
rainfall are the main causes of slope failure.
However, the vulnerability of the land to slope Of these statutes, three feature prominently:
failure can be increased by inappropriate
use; thereby exposing people, property, and • The Resource Management Act 1991 (RMA)
infrastructure to increased risk. has as its purpose to promote sustainable
management of natural and physical
Landslips, the result of slope failure, represent resources. Under the RMA, local authorities
one of the most frequently experienced natural are tasked to control land for the purpose
hazards in New Zealand. Last year alone, of avoidance of natural hazards and control
the Earthquake Commission (EQC) received the actual or potential affects of land use
through the avoidance of natural hazards.
over 1300 landslip natural disaster claims
(Earthquake Commission, 2008). • The Civil Defence Emergency Management
Act 2002 (CDEM Act) was written as a
This study extends upon two previous studies result of reviews of the 1983 Civil Defence
that addressed the improvement of practice Act, in part so as to ensure the effective
in the management of landslip risk; (Riddolls management of all hazards facing New
& Grocott Ltd., 1999), (CAENZ, 2007). Like Zealand. This includes the reduction of risk
these previous two studies, this study was exposure.
commissioned by EQC as part of its active • The Building Act 2004 outlines
role in advancing New Zealand’s resilience to requirements for the construction of
natural disaster damage. structures. Protection from, and not
worsening the effect of natural hazards are
The focus of this study is to understand how considered as part of these requirements.
slope stability is considered in current land use
and planning practice. Sections 31-39 detail requirements of project information
memorandum (PIMs) and that special features, including
For the management of landslip risks to natural hazards are included (Section 35) as information
relevant to proposed building work. Under Section 41 an
be improved, it is necessary to have an exemption to the requirement to obtain building consents
understanding of how actual planning practice may be applied to urgent work such as could occur follow-
ing a natural hazard event if it is for the purpose of saving
is influenced by considerations of slope or protecting life or serious damage to property. Sections
71-74 of the Building Act 2004 detail the limitations and
stability. The need to consider natural hazards restrictions on building consents: Construction of building
in land use planning is well recognised. on land subject to natural hazards. Once an event has
impacted a building it may be subject to requirements
However, the degree to which such knowledge under subpart 6 of the Act - Special provisions for certain
is translated into effective land use planning categories of buildings addresses dangerous, earthquake
prone and insanitary buildings, with Sections 121-123
is commonly acknowledged to be variable. defining these categories of building, while Sections 124-
Gaining a greater understanding, therefore, of 130 provide the powers of territorial authorities in respect
of dangerous, earthquake-prone, or insanitary buildings.
why practice varies provides useful insight into Sections 131 and 132 provide the requirements for policy
on dangerous, earthquake-prone and insanitary buildings.
Collectively these Acts place a significant duty • Planning for Natural Hazard Risk in the
on local authorities, and others, to apply rigour Built Environment (CAENZ, 2004) addressed
to land use planning where natural hazard risk key factors and considerations deemed
is present. to be important for good decision making
around natural hazard issues. In particular,
Local authorities implement these requirements the report identified issues such as
through Civil Defence Emergency Management storage of, and access to, publicly funded
(CDEM) Group Plans and Long-Term Council information and the capacity for improved
Community Plans (LTCCPs). It is imperative that interaction between local authorities,
sound risk reduction policies are prominent science providers and other experts. This
study emphasised the importance of
in these plans. Consistency between CDEM
ensuring that qualified expertise, sound
Group Plans and the LTCCPs is crucial to
processes and readily accessible data and
the implementation of successful reduction
information are used to inform decision-
measures. Recognition of this requirement making.
has led to a number of studies and guidance
• Managing Landslip Risk: Improving Practice
documents within the last decade.
(CAENZ, 2007) was a broad based study
The following is a brief summary of studies commissioned by EQC, that extended upon
that have improved and informed planning for the earlier work. It identified how current
slope stability in recent years. investments and practices in landslip risk
management could be improved across
• Assessment of Geotechnical and the range of government, private and
Development Factors involved in EQC professional organisations involved. A
landslip Claims (Riddolls & Grocott Ltd, suggested integrated risk management
1999) was an EQC commissioned study of framework (Appendix 1) that could allow
the geotechnical and regulatory aspects all participants to better approach landslip
of landslip risk. This research found that risk assessment and mitigation was
40% of the landslip claims analysed proposed. The report stated the need
involved slopes that had been modified for a collective approach involving EQC,
by engineering works. It also identified councils, knowledge providers, professional
some deficiencies in both professional associations and consultants.
practice and local government regulatory
• Concurrently with the CAENZ 2007 study,
control of the building consent process.
GNS Science released its Guidelines for
The study offered a possible process for
Assessing Planning Policy, and Consent
the systematic administration of building
Requirements for Landslide Prone Land
approvals.
(Saunders & Glassey, 2007), commonly
In seeking to present practical ways to improve The two areas adopted for case studies were
planning for the management and use of land the Far North District Council and Hutt City.
subject to slope stability, the study therefore The case studies were developed in a way
sought to: that would allow the work undertaken to be
extended to include a larger number of local
• Measure existing effectiveness of landslip authorities in the future, if deemed desirable.
risk reduction through land use planning,
The long term objective would be to produce a
• Identify barriers to good practice, and systematic national assessment of:
• Identify examples where appropriate • Current capability with regard to policy and
solutions to reducing those barriers have practice in land use planning for landslips;
been implemented to reduce risk exposure.
• Sharing of opportunities and knowledge to
In particular, the intent of this study was to: improved practice.
• Determine practitioners’ views on the use
Where appropriate, the Landslide Guidelines
and effectiveness of existing landslip risk
were used as a reference in determining
policy and practice;
the extent to which land use planning and
• Present recommendations for practical ways consenting documentation met with good
by which planning for the management and practice expectations.
Figure 2: Geographic density of EQC claims were used to define case study areas for analysis (Red represents
areas of greatest claim density)
• Council capacity and capability Far North District is the northern most district
• Internal council processes in support of of New Zealand and is frequently subject to
land use weather events resulting in both saturated
soils and considerable storm water run off,
• Awareness of and compliance with legisla-
which contribute to landslips. As a result it
tion and council policies.
has experienced a large proportion of New
Questionnaires, along with supporting material, Zealand’s landslip events. Far North District
were provided to land use planners, building Council participated in this project as an
certifiers, geotechnical specialists, civil defence opportunity to enhance its ability to address
officers and others identified within the pilot slope stability risk through improved land use
study areas in advance of two workshops planning and consenting approaches.
that were held to address the various study
objectives. Hutt City is characterised by the Hutt River and
the Wellington Fault. It has coastal cliffs and
Supporting material included the Project steep hillsides. Both earthquakes and weather
Overview and the Landslide Guidelines. events contribute to Hutt City’s slope stability
Participants were asked to complete the risk. Several high profile slips have occurred
questionnaires in advance of the workshop. in recent years and Hutt City Council has been
A 78% return rate was obtained for the very active in educating residents on ways to
questionnaire, providing quantifiable data for minimise their risk exposure.
analysis of resource and practice familiarity,
usage and barriers to use. In conjunction with The respective councils have different slope
the two workshops, questionnaire surveys stability risk profiles. Their underlying geology
provided insight into the knowledge of is different, as are their weather patterns and
resources, actual practice and interactions that population profiles. Together they represent the
take place between professions. diversity of those areas in New Zealand that
are subject to slope stability vulnerabilities.
3.1 Overview of the case Overall the Hutt City district plan address land
stability well, with specific issue, objective,
studies policy and standards statements. Suggestions
Both councils’ policies, plans and records, were made on some minor amendments in the
and those of the associated CDEM Groups, future, in order to make them more robust.
demonstrate opportunities for greater
consideration of landslip risk. The Hill Residential Activity Area (Chapter 4D
of the City of Lower Hutt District Plan) com-
The documents reviewed included samples of prises most of the urban areas in the eastern
consent files, and policy documents (district and western hills of the Hutt Valley, including
plans and CDEM Group plans). Supporting those between Point Howard and Eastbourne.
tools such as district maps and consenting Applying the Landslide Guidelines suggests
checklists were also considered. that policy related to this area could be more
prescriptive regarding land stability issues.
The review of consenting files proved more
difficult than expected. Documentation, Within the Wellington CDEM Group Plan (Wel-
particularly relating to older properties, were lington Region Emergency Management Group,
either absent, or difficult to assess due to the 2005), landslides are ranked 8th (medium risk)
substantial changes in council practices and out of 24 hazards in the Wellington region.
legislation that have taken place since the time
at which the consent was issued. Fifty-eight consent files from Hutt City Council
were considered. Of these, twenty-one were
Additionally, a large number of Far North suitable for assessment. Many of the files
District Council files were unable to be contained building consent applications only.
assessed, because emergency works had been Two types of consents were supplied – those
carried out without requiring consents. where an event had not occurred at the time of
application; others post-event, where remedial
The policy documents and consent records
works were required because of slips.
from the two case study councils contrasted
markedly. However, for both councils, review Four characteristics were apparent in the review
of available consent files did not show of these files:
any significant evidence of geotechnical
assessments routinely being undertaken. • An internal policy change within the
consent processing team at the Council
resulted in significant changes to how
Hutt City Council
consent decisions were formatted.
The City of Lower Hutt District Plan (City of The change resulted in the officers
Lower Hutt, 2008, 2003a, 2003b) is fully reporting becoming considerably more
operative; the substantive part of the Plan comprehensive than prior to that change.
became operative from 24 June 2003, with Use of standard condition wording also
remaining parts operative on 18 March 2004. became apparent. This change in policy
The implication of this is that only five years of resulted in a more rigorous written planning
consents have been issued under the operative assessment. This presents substantial
benefit by enabling easier monitoring of
plan.
policies in the future.
The review of the Hutt City district plan • Many consent conditions referred to
provisions addressing land stability for urban a suitably qualified engineer; sound
residential development found good use engineering practices; and poor
of relevant information from the Landslide ground conditions. These three terms
Guidelines. General comments on the policies require qualification in order to ensure
adopted were also included. assessments are of an appropriate
standard.
16
12
0
In-house Records
& Software
Guidance
Documents
Public Domain
Aerial Imagery
Maps
Institutional
Engineer Reports
Acts
Observation
Knowledge
Figure 3: Use of resources in support of decision making by professionals engaged in land use within the Far
North District and Hutt City Council areas
72
Respondents Familiar with Resources
54
36
18
-18
-36
-54
-72
Geological Maps
NZ Landslide Database
Aerial Photos
Field Maps
Other Maps
GNS Guidelines
AGSLRM Guidelines
Usefrequently
Use frequently
Useoccasionally
Use occasionally
Have access
Have accessto,
to, but
but don
don’tt use
use
Know of, but
Know but don
don’tt have access to
Am unfamiliar
Am unfamiliar with
with
Figure 4: Familiarity with available resources that support slope stability consideration of land use indicates a
preference for visual resources
80
60
40
20
0
-20
Major contribution
-40
Moderate contribution
-60 Minor contribution
-80 Did not contribute
Known risk not mitigated
Seismic activity
New development increasing risk
Climate change
Removal of vegetation
Normall meteorological event
Figure 5: Unusual meteorological events were viewed by participants as having the greatest contribution
to landslip occurrence with new development, removal of vegetation and normal meteorological
events also providing significant contribution
Both the Landslide Guidelines and the use practice and in expressing data (often
Integrated Risk Management Framework through the use of GIS) when communicating
advocate collaborative approaches to the context of hazard considerations, such
addressing slope stability in land use planning. as landslips, between stakeholders including
This study identified ways that facilitate officials and owners who may not have a
greater collaboration. In particular the study technical background.
highlighted three areas where effort could
be focused in order to produce greater Data sharing
collaboration: The study identified that considerable quanti-
• Sharing of information, ties of data are held and managed by individu-
al organisations. The associated maintenance,
• Raising the profile of slope stability risk, and
in terms of time and resources, is substantial.
• Extending accountability.
Additionally, holding data internally can lead
to multiple organisations maintaining duplicate
4.1 Sharing of information data.
Two main barriers to the use of existing This can lead to under-utilisation of data and
knowledge were identified. The first was that rapid dating. Awareness of either the presence
for information to be readily adopted it needs of existing data sources or means by which
to be presented in an appropriate format. For they can be accessed may be lacking, and
example distribution of large documents to updating of data may not be consistent across
councils did not receive as great attention as organisations.
the provision of checklists or visual references.
The diversity of experience of those that took
The second barrier was a limited awareness part in the workshop proved useful as a means
of the range and volume of information of raising awareness of these issues. The desir-
that is held on slope stability by different ability of sharing existing tools and resources
organisations. This became apparent through held within a particular area and elsewhere
workshop interactions where individuals was indicated, and initial discussions on the
spoke of the resources that they drew upon value of consolidated data repositories were
in considering slope stability. In several also initiated.
instances other participants were unaware of
Specifically, the following data sources were
the existence of these information sources or
identified which, if shared or made more
means by which to access them.
readily accessible, would improve the quality
Presenting information of decisions and may in some cases provide
opportunities to distribute the burden of data
Efforts are required to encourage researchers to
maintenance:
present information and develop tools with a
strong spatial component. Information provided • Composite EQC data (see Appendix 4);
in this form can be integrated more readily into • GNS geological maps;
land use practice than that provided by other • District and Region wide database reports
means. indicating where and what kind of
information is held;
The survey and workshop findings indicated
that those engaged in land use related • Consolidated geographic information.
disciplines are most comfortable employing The value of data sharing could be further
visual and spatial concepts. This needs to be extended to encourage councils to contribute
reflected in the presentation of new tools and file data to centralised repositories such as
information intended to enhance consideration mapping datasets held by GNS Science. Open-
of slope stability. The use of visual tools access would need to be secured to make this
assists in both the implementation of land attractive.
In summary, this study has illustrated that the 5.1 Short term/immediate
greatest opportunities for improving practice
implementation opportunities
in land use planning is through ensuring
a collaborative and informed approach to • Regular multi-disciplinary discussions of
landslip issues and solutions established
balancing development pressure and slope
locally.
stability risk exposure.
• Formation of district or regional databases or
The recommendations arising from the study database directories for hazard information,
focus on three broad concepts; accessible to all, held and managed by local
• information sharing, councils.
• A greater focus by research on presenting
• improved methods of communication about
information with a strong spatial component.
slope stability risk,
• Greater use of Producer Statements with
• extended accountability. accountability requirements could be
These are set out below, with each presenting encouraged.
a number of discrete actions that can be taken. • Regular targeted circulation of public
Some require little cost and have potential to education material to households in
achieve rapid results, others require long-term vulnerable areas, describing how to reduce
commitment and centralised leadership. landslip risk through appropriate property
maintenance.
Few of the recommendations can be
• Greater consideration and promotion of the
implemented by a single organisation or Landslide Guidelines and the Integrated
profession. Virtually all require improved Risk Management Framework by councils
communication and greater collaboration to provide greater consistency in assessing
between disciplines and across organisations. consents and to demonstrate a reasonable
level of duty of care.
What this study has shown is that one of the
simplest, and likely most effective actions 5.2 Longer term
would be regular multidisciplinary discussions
implementation opportunities
of the land use issues encountered in the local
area. • A national benchmarking process to promote
improved practices.
Such discussions would enable all professions
• Improvement of future generations of council
to maintain a current knowledge of concerns plans to better reflect and recognize slope
and awareness of good practice, as well stability risks.
as promote new knowledge and particular
• A Landslip Engineering Practice Guide to be
concerns that might arise. developed for New Zealand.
While many of the recommendations require • Known landslip risk areas identified on
local action, national agencies could facilitate public hazard maps and also made available
more effective management of slope stability through LIMs.
risk. • Development of a comprehensive and freely
available national set of large-scale detailed
In conclusion, therefore, we commend the
map sheets consolidating existing landslip
following recommendations for further
information for urban areas.
consideration and possible uptake.
• The development of national standards to
better address landslip risk.
The framework adopted advocates integrated The study, itself, has demonstrated a
management approaches and more specific willingness of all those involved to progress
assessment criteria. However, going forward such an initiative.
Australian Geomechanics Society (ASG), City of Lower Hutt. Hutt City Council
2007b. Practice Note guidelines for Building and Planning Forms http://
landslide risk management. Australian www.huttcity.govt.nz/publications-
Geomechanics 42 (1). forms/Forms/Building-and-Planning-
Forms/ Accessed 2009
Beca Group & Kent Consulting, 2007.
Kerikeri Waipapa Structure Plan: Earthquake Commission, 2008. Annual
Managing growth and heritage. Far Report 2007-2008. Wellington.
North District Council, p61.
Far North District Council, 2008. Far North
Brown, I.R., 2005: A study of issues District Plan http://www.fndc.govt.
affecting the stability of land in Hutt nz/services/environmental-policy-and-
City. Report for Hutt City Council, Ian R forward-planning/the-far-north-district-
Brown Associates Ltd, IRBA Job 817. plan accessed 13 January 2009
CAENZ, 2004. Planning for Natural Hunt, R., 2007. Geologic Hazards: A Field
Hazard Risk in the Built Environment. Guide for Geotechnical Engineers. CRC
New Zealand Centre for Advanced Press.
Engineering. Christchurch.
Hutt City Council, 2008. District Plan
CAENZ, 2007. Managing Landslip Risk: Committee Hearings for Proposed
Improving Practice. New Zealand Centre Plan Change 10 – Amendments to
for Advanced Engineering. Christchurch. subdivision provisions. 28 August
2008.
CAENZ, 2009. CAENZ Comments 05
Land Use Planning for Natural International Society for Soil Mechanics
Hazards: Stewardship for the Future. and Geotechnical Engineering. Technical
New Zealand Centre for Advanced Committee on Risk Assessment and
Engineering. Christchurch. Management (ISSMGE TC32), 2004.
Glossary of Risk Assessment Terms
City of Lower Hutt 2003a. Hutt City Council – Version 1, July 2004.
District Maps http://www.huttcity.govt.
nz/publications-forms/District-Plan/Map- Kliche, C., 1999. Rock Slope Stability,
Appendices/ Accessed 2008 Society for Mining, Metallurgy, and
Exploration, Inc. (SME).
City of Lower Hutt, 2003b. Part 4: Section
32 evaluation http://www.huttcity. Lawrence, J.H, Depledge, D.R., Eyles,
govt.nz/Documents/district-plan/plan- R.J., Oakley, D.J., & M.J. Salinger,
changes/Part%204%20and%204A%20- 1978: Landslip and flooding hazards
%20Section%2032%20Evaluation.pdf. in Eastbourne Borough – A guide for
Accessed 17 December, 2008 planning. Water and Soil Division,
Ministry of Works and Development,
City of Lower Hutt, 2006. Managing the Wellington.
risk of landslides: a guide for people
on hillside properties. Development Northland Region Emergency Management
Services Group, Hutt City Council. Group, 2004. Northland Civil Defence
Emergency Management Group Plan.
City of Lower Hutt, 2008. City of Lower http://www.nrc.govt.nz/upload/1443/
Quality Planning, The RMA Planning Tonkin & Taylor, 2008. EQC maps ‘CAENZ
Resource Natural Hazards Management Research – land use and landslips,
– Research Report http://www. Frequency of EQC landslip claims’.
qualityplanning.org.nz/qp-research/ Figures 1.B, 1.D, 1.H, 1.I, 1.M, rev. 1,
natural-hazards-aug06/html/ Accessed 9 November 2008
May 2009
Wellington Region Emergency Management
Riddolls & Grocott Ltd., 1999. Assessment Group, 2005: Wellington Region Civil
of Geotechnical and Development Defence Emergency Management Group
Factors involved in EQC landslip Plan. Wellington Regional Council.
Claims. Report for Earthquake
Commission. Legislation
Saunders, W., Forsyth, J., Johnston, Building Act 2004.
D.M., Becker, J., 2007. Strengthening
Civil Defence Emergency Management Act
linkages between land-use planning
2002.
and emergency management in New
Zealand. Emergency Management Earthquake Commission Act 1993.
Australia, 22(1): p36-43.
Privacy Act 1993.
Saunders, W and Glassey, P, 2007.
Guidelines for Assessing Planning Resource Management Act 1991.
Strategic There is a clear understanding of the Review occurrences for number, location,
Awareness causes of risks, their extent, and cause, costs, etc.
future projections, within which to Assess causes and trends (to determine
focus participation. importance of task).
Assess international practice for possible
contributions.
Advocacy Participants are aware of the critical Develop “map” of current roles and
Analysis points to participate in the responsibilities of all those involved, as
development and application of well as understanding their plans and
expertise and knowledge, and in the politics, and how to best interact with
design and management of the each.
regulatory regime utilised by
government.
Risk Participants appreciate the risks Prepare a risk map of the necessary
Assessment associated with participating to participation opportunities in the decision-
ensure the best possible decision- making for the built environment. This
making relating to the built means assessing the possible success of
environment of NZ. each intervention, any barriers, and
options for addressing these.
Then devise a plan to address using the
activities below (and others as required)
3. ADVOCACY STRATEGIES - This step is important for getting the work done.
Methodologies, External professional fraternity has Review existing “tools” for adequacy and
Benchmarking, the appropriate “tools” to address where necessary set out strategy to fill
Standards, and risk management issues critical gaps where these are relevant (what
Guidelines Programme and project managers gaps, who can partner, what priority, etc)
are aware of risk and how best to Establish work plan, contributors, finances,
manage it. partners, etc to update/modify/create
related methodologies, benchmarked
processes and information, standards and
guidelines.
Manage development of work plan
Promote relevant “tools” through
workshops, conferences, etc.
Maintain vigil on adequacy and evolving
needs
Best practise is identified and promoted.
Monitoring of revised standards and
guidelines
Develop risk-based management
methodology to assist managers of
projects/programmes to improve decision
making on risk.
Regulatory Process Local Government planning, Identify critical areas that have to be
Improvement consents, compliance and policy prepared for any revised approach
processes allow for the successful (legislation, planning and policy, etc, human
applications of the risk behaviour, awareness, etc).
management advice. Develop change needs for each critical
area, and how this might be achieved.
Develop a plan to influence these critical
areas (this might include engaging central
government to change legislation or
department polices, some might be done
through awareness initiatives).
GNS Science The Institute of Geological and Nuclear Sciences, a Crown research institute (CRI).
Hazard A potentially damaging event occurring within a given area within a given time.
Landslide The movement of a mass of rock, debris, or earth (soil) down a slope (ISSMGE, 2004)
Landslip The Earthquake Commission Act 1993 defines natural landslip as “the movement (whether by
way of falling, sliding or flowing, or by a combination thereof ) of ground-forming materials
composed of natural rock, soil, artificial fill, or a combination of such materials, which before
movement, formed an integral part of the ground; but does not include the movement of
the ground due to below-ground subsidence, soil expansion, soil shrinkage, soil compaction,
or erosion
RA Regional Authority
Risk The chance of something happening that will be an impact. A risk is often specified in terms
of an event or circumstance and the consequences that may flow from it (Standards Australia
and Standards new Zealand, 2004)
Slope failure The realisation of a landslip or landslide. Slope failures are the result of gravitational
forces acting on a mass which can creep slowly, fall freely, slide along some failure
surface, or flow as a slurry. (Hunt, 2007)
Slope stability The resistance of an inclined surface to failure by sliding or collapsing (Kliche, 1999)
Susceptibility Being prone to. In terms of landslides this refers to a quantitative or qualitative
assessment of the classification, volume (or area) and spatial distribution of landslides,
which exist or potentially may occur in an area (ISSMGE, 2004)
TA Territorial Authority
&ILTER CLOTH WWWHUTTCITYINFODISTRICT PLAN
#OMPACTED BASE
0LEASE NOTE THE RETAINING WALL ILLUSTRATED AT LEFT WOULD REQUIRE A
BUILDING CONSENT AND MAY REQUIRE A RESOURCE CONSENT
*UNE )LLUSTRATION BY $ANIEL -ILLS
$EVELOPMENT 3ERVICES 'ROUP
Page 45
Page 46
$RAINAGE 4OO MUCH WATER IS THE MOST COMMON TRIGGER OF LANDSLIDES
"E PREPARED #ONSIDER DRAINAGE PATTERNS WHEN CHANGING THE SLOPE OF YOUR 6EGETATION 4HINK CAREFULLY BEFORE
,ANDSLIDE RISK PROPERTY 3TORMWATER MUST DRAIN TO APPROVED OUTLETS n DO NOT REMOVING SHRUBS AND TREES 0LANTS
s -AINTAIN AN EMERGENCY PLAN AND SURVIVAL KIT #ONTACT THE PROMOTE STABILITY AS THEY BIND THE
LET IT BUILD UP )F UNCONTROLLED STORMWATER RUNOFF DAMAGES OTHER
#OUNCIL FOR AN %MERGENCY 0LANNING 'UIDE OR SEE THE BACK PAGE PROPERTIES YOU MAY BE LEGALLY LIABLE FOR THE DAMAGE SOIL AND SOFTEN THE IMPACT OF RAIN
OF THE 9ELLOW 0AGES FOR MORE INFORMATION &URTHER INFORMATION FALLING ON THE GROUND #UTTING DOWN
A TREE BUT LEAVING THE STUMP DOES NOT
CAN BE FOUND ON THE #OUNCIL WEBSITE MAINTAIN LONG
TERM STABILITY 4REE
WWWHUTTCITYINFOEMO ROOTS SHRINK AS THEY ROT LEAVING SPACE
4HE STEEPNESS OF HILLS IN THE (UTT AREA PARTICULARLY FOR WATER TO ENTER THE SOIL AND WEAKEN
AROUND 3TOKES 6ALLEY THE %ASTERN "AYS AND THE 7ESTERN s 2EGULARLY INSPECT AND MAINTAIN YOUR PROPERTY 4HE #HECKLIST THE SLOPE $ONT LET GARDEN WASTE PILE
(ILLS MAKES THEM PRONE TO LANDSLIDES (EAVY RAINFALL IN UP AS IT CAN ADD MATERIAL TO DEBRIS
BELOW RIGHT CAN BE USED AS A GUIDE FLOWS )N SOME AREAS VEGETATION
HIGHLIGHTED THE THREAT LANDSLIDES POSE TO PEOPLE AND REMOVAL REQUIRES A RESOURCE CONSENT
PROPERTY SOME HOUSES WERE LEFT UNINHABITABLE s 2EPORT THE LOCATION OF ANY LANDSLIDES THAT YOU lND TO #OUNCIL #HECK WITH #OUNCIL RESOURCE CONSENT
OFlCERS PLANNERS
!REAS OF HIGHEST RISK
4HE AREAS OF HIGHEST RISK FROM LANDSLIDES IN THE 7ELLINGTON 7HAT SHOULD YOU DO IN A LANDSLIDE
REGION ARE
%VACUATE n TAKE YOUR EMERGENCY KIT
s 3TEEP SLOPES GREATER THAN DEGREES
7ARN NEIGHBOURS WHO MIGHT BE AFFECTED %AR THWORK S $IGGING UP THE
s 3LOPES THAT HAVE BEEN ALTERED SUCH AS CUTTINGS ALONG ROADS GROUND CAN CAUSE SLOPE INSTABILITY
#ONTACT THE lRE SERVICE POLICE OR LOCAL CIVIL DEFENCE n ESPECIALLY IF THE TOE OF A SLOPE
AND BEHIND HOUSES OR WHERE VEGETATION HAS BEEN REMOVED EMERGENCY MANAGEMENT OFlCE IS REMOVED #ONSULT A CHARTERED
s 7HERE THE UNDERLYING ROCK IS WEATHERED OR SHATTERED OR $O NOT RE
ENTER YOUR PROPERTY UNTIL IT HAS BEEN INSPECTED PROFESSIONAL GEOTECHNICAL ENGINEER
BEFORE PLANNING ANY EARTHWORKS ON
Figure 10: Total loss summaries by territorial local authority (TLA) illustrate the significance of slope stability impacts
on land use in certain parts of New Zealand (image provided by EQC)
Mail: Private Bag 4800, University of Canterbury Campus, Christchurch 8140, New Zealand
Street Address: 39 Creyke Road, Ilam, Christchurch, New Zealand
Phone: 03 364 2478 Fax: 03 364 2069 e-mail: [email protected] www.caenz.com www.caenz.com