04 Chapter 4 - Leveling
04 Chapter 4 - Leveling
Chapter 4
Leveling
Dr. Sari Abusharar
Associate Professor
Civil Engineering Department
Faculty of Applied Engineering and Urban Planning 1
Outline of Presentation
Introduction
Basic Definitions
Basic Principles of A Level
Bubble Tube
Equipment Used in Differential Leveling
Measuring Elevation Difference
Procedure in Differential Leveling
General Notes
Common Mistakes
Errors
Reciprocal Leveling
Closure Error
Classes and Accuracy of Leveling
Applications of Leveling
Introduction
cross-sections
contour lines
longitudinal sections
Introduction
Chain surveying
Barometric leveling
Trigonometric Leveling
Photogrammetric Leveling
Hydrostatic leveling
GPS Leveling
Differential Leveling
Introduction
D S. cos α
h S . sin α
Clinometer
Introduction
Barometric leveling التسوية البارومترية
By measuring the atmospheric pressure using barometer or an
altimeter, and is based on the principle that atmospheric pressure
decreases with increase in elevation. This method is not highly
accurate and is therefore restricted to situations where high accuracy
is not required.
Barometer/altimeter
مقياس الضغط الجوي
Introduction
Zenith angle
Vertical angle
Zenith Angles
Zenith angles are referenced to a 0° value straight up.
Vertical Angles
Vertical angles are referenced to a 0° value on the horizontal plain.
Introduction
Vertical Line
The vertical line at a point is the line formed by the string of
a plumb bob when the tip is located directly over the point.
Horizontal Line
The horizontal line at a point is the straight line perpendicular
to the vertical line at that point.
Horizontal Plane
The plane passes through all the horizontal lines at a
particular point. It is perpendicular to the vertical line at this
point.
Level Surface
The continuously curved surface that is perpendicular to the
direction of gravity at all points.
Level Line
A line that lies on the level surface.
Basic Definitions
Bench Mark
A marked point whose elevation has been accurately
measured.
Height of Instrument
The line of Collimation ( )خط التسديدabove the datum after setting
up the level above a certain point.
Level
The basic instrument used in differential leveling to measure
elevation or height differences.
The Level
Tripod
Rod Level
Equipment Used in Differential Leveling
(1) A Level
عدسة شيئية
Equipment Used in Differential Leveling
(2) Tripod
This is a three-legged stand used to support a level. It consists
of a head and three legs that are fitted with pointed metal
shoes. The legs could be made of aluminum or hard wood, and
are either with fixed length or adjustable length depending on
the height of the user. A survey instrument is usually secured to
the tripod head by a threaded.
Telescopic staff
Bubble Tube
Folding staff
Bubble Tube
One-piece staff
Bubble Tube
2.56 0.93
C
B
0.64 2.97
C
A
Calculation of Elevation
(A) The height of instrument method
Assume that elevation of Point A
= 520.43 m AMSL
a. Height of Instrument HI =
Elevation Of A + Staff
Reading = 520.43 + 2.56
= 522.99 m AMSL
b. Elevation of B = HI –
Staff Reading at B = 522.99
– 0.93 = 522.06 m AMSL
Calculation of Elevation
(A) The height of instrument method
Assume that elevation of Point A
= 520.43 m AMSL
a. Height of Instrument HI =
Elevation Of A + Staff
Reading = 520.43 + 0.64
= 521.07 m AMSL
b. Elevation of B = HI –
Staff Reading at B = 521.07
– 2.97= 518.10 m AMSL
Measuring Elevation Difference
Calculation of Elevation
(B) The rise and fall method
Assume that elevation of Point A
= 520.43 m AMSL
a. Elevation Difference =
Elevation of A - Elevation
of B = 2.56 – 0.93 = 1.63 m
(rise)
b. Elevation of B = Elevation
at A + rise = 520.43 + 1.63
= 522.06 m AMSL
Measuring Elevation Difference
Calculation of Elevation
(B) The rise and fall method
Assume that elevation of Point A
= 520.43 m AMSL
a. Elevation Difference =
Elevation of A - Elevation
of B = 0.64 – 2.97 = - 2.33
m (fall)
b. Elevation of B =
Elevation at A + fall =
520.43 - 2.33 = 518.10 m
AMSL
Measuring Elevation Difference
Calculation of Elevation
Let ΔH AB represents the elevation difference between point
A and B, HA and HB represents the elevations or reduced
levels of point A and B respectively, and rA and rB represent
the staff readings at A and B respectively, then:
ΔH AB H B H A rA rB
Procedures in Differential Leveling
Definitions
Backsight (BS)
This is the first reading taken by the observer at every
instrument station after setting up the level
Foresight (FS)
This is the last reading taken at every instrument station
before moving the level
General Procedure
Producing a longitudinal section (profile)
A B
1 C
P
D G
E F
BM
Q
(RL = 98.76 m AMSL) Plan FS
TP IS
BS IS IS
IS FS / BS
IS
2.787 2.270 1.218
1.946 1.008 1.153 1.585
0.663
G
1, BM Q F
B P C E
A D
0 20 40 60 80 100 120
Longitudinal Section
Procedures in Differential Leveling
b. Elevation of B = HI – Staff
Reading at B = 522.99 – 0.93 =
522.06 m AMSL
a. Height of Instrument HI =
Elevation Of A + Staff Reading
= 520.43 + 0.64
= 521.07 m AMSL
b. Elevation of B = HI – Staff
Reading at B = 521.07 – 2.97=
518.10 m AMSL
A B
1 C
P G
D
E F
BM
Q
(RL = 98.76 m AMSL) Plan
FS
TP IS
BS IS IS
IS FS / BS
IS
2.787 2.270 1.218 0.646
0.663 1.946 1.008 1.153 1.585
G
1 Q F
B P C E
BM A D
0 20 40 60 80 100 120
Longitudinal Section
Procedures in Differential Leveling
Check 3
ΣRL – RLfirst point = [Σ (No. of IS and FS × HI)] - Σ IS - Σ FS
ΣRL – RLfirst point = 788.501-98.760 = 689.741
[Σ (No. of (IS and FS) × HI)] - Σ IS - Σ FS
= [4×99.423 + 3×100.625] – 7.595 – 2.231 = 689.741
Procedures in Differential Leveling
b. Elevation of B = Elevation
at A + rise = 520.43 + 1.63 =
522.06 m AMSL
a. Elevation Difference =
Elevation of A - Elevation of B
= 0.64 – 2.97 = - 2.33 m (fall)
b. Elevation of B = Elevation
at A + fall = 520.43 - 2.33 =
518.10 m AMSL
A B
1 C
P G
D
E F
BM
Q
(RL = 98.76 m AMSL) Plan
FS
TP IS
BS IS IS
IS FS / BS
IS
2.787 2.270 1.218 0.646
1.946 1.008 1.153 1.585
0.663
G
1 Q F
B P C E
BM A D
0 20 40 60 80 100 120
Longitudinal Section
Procedures in Differential Leveling
1 0.663 98.760 - BM
A 1.946 1.283 97.477 0
B 1.008 0.938 98.415 20
C 1.153 0.145 98.270 40
D 2.787 1.585 0.432 97.838 60 TP
E 2.270 0.517 98.355 80
F 1.218 1.052 99.407 100
G 0.646 0.572 99.979 120
SUM 3.450 7.595 2.231 3.079 1.860
Check 1
No. of BS readings = No. of FS readings
2 = 2
Procedures in Differential Leveling
1 0.663 98.760 - BM
A 1.946 1.283 97.477 0
B 1.008 0.938 98.415 20
C 1.153 0.145 98.270 40
D 2.787 1.585 0.432 97.838 60 TP
E 2.270 0.517 98.355 80
F 1.218 1.052 99.407 100
G 0.646 0.572 99.979 120
SUM 3.450 7.595 2.231 3.079 1.860
Check 2
ΣBS - ΣFS = ΣRise – ΣFall = RLlast – RLfirst
3.450 – 2.231 = 3.079 – 1.860 = 99.979 - 98.760
1.219 = 1.219 = 1.219
Scale 1/1000 horizontal, and 1/100 vertical
100.00
99.50
99.00
98.50
Elevation (m)
98.00
97.50
97.00
96.50
96.00
95.50
95.00
0 20 40 60 80 100 120
Distance (m)
Using the data shown in the figure, do the required booking, and
calculate the reduced levels of points A, B, C, and D by both the
height of instrument and rise and fall methods. Make the required
arithmetic checks.
Solution
D 1.38
SUM -0.67 -3.52 0.85
Solution
Point BS IS FS Rise Fall HI RL Notes
A 0.60 500.00 BM
Top of concrete wall
B -1.27 -0.53 1.13 (TP)
D 1.38 4.90
SUM -0.67 -3.52 0.85 3.38 4.90
HI method :
HI1 H A rA 500.00 0.60 500.60 m
RL B HI1 rB,(FS) 500.60 (0.53) 501.13 m
HI 2 RL B rB,(BS) 501.13 ( 1.27) 499.86 m
RL C HI 2 rC 499.86 (3.52) 503.38 m
RL D HI 2 rD 499.86 1.38 498.48 m
Solution
Checks
1- # of BS = # of FS = 2 ok
2- (∑BS - ∑FS)=(-0.67-0.85)=-1.52
(∑R - ∑F)=(3.38-4.90) = -1.52 ok
(RL last – RL1st )= (498.48 – 500.00) = -1.52
Random Errors
أخطاء عشوائية
Blunders
أخطاء فادحة
Errors in Differential Leveling
BD 0.0786L2 CD 0.0673L 2
Systematic Errors
(2) Maladjustment of the level (collimation error )خطأ التوجيه
When the line of sight of a level is not perfectly parallel to the axis of
the level bubble due to maladjustment of the level, the line of sight will
be actually inclined from the horizontal even though the level bubble
is perfectly centered.
Systematic Errors
Let
a Actual BS reading with staff held at point A
m Correct BS reading at A if the line of sight was perfectly horizontal
1 Reading error at A due to maladjustment of the level
b Actual FS reading with staff held at B
n Correct FS reading at B if the line of sight was perfectly horizontal
2 Reading error at B due to maladjustment of the level
Angle of inclination of the line of sight from the horizontal.
It is positive if above the horizontal and negative if below the horizontal
Errors in Differential Leveling
Then
ε 1 L1 tanα
ε 2 L 2 tanα
correct elevation difference (H) m - n
(a ε 1 ) (b ε 2 )
(a b) (ε 1 ε 2 )
ΔH (a b) tan (L1 L 2 )
First_Setu p :
ΔH 1 (correct) 1.92 1.4 0.52m
Second_Set up :
ΔH 2 1.75 1.2 0.55m
ΔH 1 ΔH 2 There is a collimation error
ΔH (a b) tan α (L1 L 2 )
0.52 (1.75 - 1.20) - tan α (58 23)
α 0 2 57
o ' ''
• Wind may vibrate the level and the staff and make it difficult to
keep the bubble centered and to read the staff correctly.
Errors in Differential Leveling
• Misreading the staff especially when the marks on the staff are
obscured by a tree , fence and so on.
• Not setting the staff on the same point for a FS and the
subsequent BS readings.
Level line
C A B
ΔH1 ΔH 2 a1 b1 a 2 b 2
ΔH
2 2
Example 4.3
Solution:
ΔH1 ΔH 2 a1 b1 a 2 b2
ΔH
2 2
ΔH AB
1.44 1.90 1.80 2.34
0.50 m
2
The elevation of point B (H B ) H A ΔH AB
917.34 (-0.5) 916.84 m
Example 4.3
Another Solution:
First setup :
elev. of point B 917.34 1.44 1.90 916.88m
Second setup :
elev. of point B 917.34 1.80 2.34 916.80 m
916.88 916.80
The elevation of point B 916.84 m
2
Closure Error خطأ اﻹغﻼق
For the case where leveling starts as a known BM and ends at the
same or at another BM, the calculated elevation for the end
station must be equal to the elevation of the known station if the
leveling is free of errors. However, this case is rarely occurs and
a closure error results.
2
Δh2 Δh3
n2 n3
1 3
Δh4
Δh1 n4
n1 : a BM
: a surveystation
BM1 BM2
Assume that the known elevation of BM2 is (h) and the calculated
elevation from leveling is (h’), then the closure error ( ) is:
ε h' h
Closure Error
ni
Closure correction Δh i ε
nj
Corrected Δh i measured Δh i closure correction for Δh i
Given:
n1 = 2, Δh1 = 1.74 m
n2 = 1, Δh2 = 2.13 m BM1 = 761.65 m
n3 = 2, Δh3 = -3.10 m BM2 = 762.38 m
n4 = 4, Δh4 = -0.45 m
Example
Δh1 = 1.74 m
Δh2 = 2.13 m
Δh3 = -3.10 m
Δh4 = -0.45 m
ΣΔh = 0.32 m
n1 = 2, Δh1 = 1.74 m
n2 = 1, Δh2 = 2.13 m
n3 = 2, Δh3 = -3.10 m ε = - 0.41 m
n4 = 4, Δh4 = -0.45 m
Closure corrections
2
Δh 1 (-0.41) 0.09 Corrected Δh 1 1.74 0.09 1.83 m
9
1
Δh 2 (-0.41) 0.05 Corrected Δh 1 2.13 0.05 2.18 m
9
2
Δh 3 (-0.41) 0.09 Corrected Δh 1 - 3.10 0.09 3.01 m
9
4
Δh 4 (-0.41) 0.18 Corrected Δh 2 - 0.45 0.18 0.27 m
9
Check: BM2 (Calculated) = BM1 + ΣΔh
= 761.65 m + 0.73 m
= 762.38 m (ok)
HW # 7
Cross-sections
Contouring
0 20 40 60 80 100 120
Longitudinal Section
Applications of Leveling
(2) Cross-Sections
•Some Engineering works require that cross sections be taken at right
angles to the center line of a proposed or existing project such as a
road.
•The width of these of sections are taken 15 m either side of the
center for a normal road
•Scale 1/50 or 1/100 for both horizontal and vertical axes.
Applications of Leveling
(3) Contouring
A contour is an imaginary
line connecting points on
the ground that have the
same elevation.
Characteristics of Contours
1- Closely contours represent a steep slope, but spaced far contours
represent a flat slope.
2- Contours are perpendicular to the direction of the steepest
slope.
Applications of Leveling
Characteristics of Contours
3- Contours of different values do not cross each other nor do they
merge except in rare situations where there is a cave or a vertically
standing surface such as a wall.
Applications of Leveling
Characteristics of Contours
4- Contours that portray summits (such as hill) or depressions (such
as bottom of a lake) are closed lines.
5- A single contour cannot split two contours of the same value as
itself, and it must make a closed circuits although not within the
area covered by the contour plan.
6- Irregular contours represent a rough and uneven terrain.
Applications of Leveling
Characteristics of Contours
Applications of Leveling
Methods of Contouring
Griding
Radiating lines
Cross-sections method
(1) Griding
This method is most suitable for flat terrain, especially on
comparatively small sites. Rectangular or squares of 5 to 20 m a
side are usually set out on the ground in the form of a grid, and
levels (staff readings) are taken in the corners.
Applications of Leveling
(1) Griding
Assume that the elevations of points D4, D5 and C5 are 13 m, 10 m
and 12 m respectively. The distance between corners D4 and D5 is
12 m and the distance between corners C4 and D5 is 10 m. To draw
the contour line whose elevation is 11 m:
X 1 12
By interpolation: X 4m
12 3 3
Applications of Leveling
Y 1 10
Y 5m
10 2 2
Applications of Leveling
x
h2 h1
ho
h o h1
x (L)
h 2 h1
Applications of Leveling
Elevation
Point
(m)
A1 112.0
A2 112.5
A3 113.5
B1 113.0
B2 114.0
B3 115.5
C1 114.5
C2 114.3
If A1 is located at the top left corner of the grid, draw the grid at a
scale of 1:100, and show all the contour lines at 0.50 m interval
starting from 112.50 m.
Example
1 2 3
A
5m
B
5m
Scale 1:100
Example
Y 0.5
Y 1 .7 m
5 1.5
112.0 112.5 113.5
Y 1
Y 3 .3 m
5 1.5
Y 0.5
Y 1 .3 m
5 2
Y 1
Y 3 .3 m 113.0 115.5
5 1.5 114.0
Y 1
Y 2 .5 m
5 2
X 0.5
Y 1 .7 m
5 1.5
Y 1.5 114.5 114.3
Y 3 .8 m
5 2
X 1
X 3.3 m Scale 1:100
5 1.5
Applications of Leveling
The following levels were taken with a metric staff on a series of pegs at
100-m intervals along the line of a proposed trench. If the trench is to be
excavated from peg A commencing at a formation level of 26.5 m and
falling to peg E at a grade of 1 in 200. Calculate:
BS IS FS remarks
2.10 BM1=28.75 m
2.85 Peg A
1.80 3.51 Peg B
1.58 Peg C
2.24 Peg D
1.68 2.94 Peg E
2.27