Thesis: Cost-Effective Insulation Coordination Design of 115 KV Transmission Line For Lightning Back-Flashover
Thesis: Cost-Effective Insulation Coordination Design of 115 KV Transmission Line For Lightning Back-Flashover
PHONESAVANH SENGMANIVANH
THESIS ADVISOR
(Assistant Professor Komsan Hongesombut, Ph.D.)
DEPARTMENT HEAD
(Assistant Professor Nithiphat Teerakawanich, Ph.D)
DEAN
(Associate Professor Srijidtra Charoenlarpnopparut, Ph.D.)
THESIS
PHONESAVANH SENGMANIVANH
ABSTRACT
This thesis presents a method to design the insulation coordination for the
Electricité Du Laos (EDL) transmission line due to the back-flashover phenomenon
under cost constraints. Although the transmission line is initially well designed and
calculated, it can reduce the effectiveness of protection because of a lifetime,
contamination, and heavy operation. As a result, the withstand capability cannot keep
at complete as in the beginning. Therefore, improvements need to be made to ensure
the insulation coordination is always readily available and sufficiently effective. In
this research, the transmission line, lightning surge, and the different protection are
modeled on PSCAD/EMTDC software. Then, the total costs of the transmission line
design are calculated. This thesis aims to achieve the lowest cost of design. Therefore,
the multi-objective optimization method is used to find the best design satisfying the
transmission line design’s technical and economic aspects.
ACKNOWLEDGEMENTS
ACKNOWLEDGEMENTS
This thesis would not be possible without direct and indirect supports from these
people. Firstly, I appreciate my advisor, Assistant Professor Komsan Hongesombut, for
providing support and guidance; his knowledge and experience were extremely helpful in
this research. Secondly, I am eternally grateful to Assistant Professor Dulpichet
Rerkpreedapong from Kasetsart University and Associate Professor Pramuk
Unahalekhaka from the Rajamangala University of Technology Suvarnabhumi, have
taken their valuable time to become the examination committees and kindly given the
advice to make this thesis more complete.
PHONESAVANH SENGMANIVANH
TABLE OF CONTENTS
Page
ABSTRACT .................................................................................................................. C
ACKNOWLEDGEMENTS .......................................................................................... D
TABLE OF CONTENTS .............................................................................................. E
LIST OF TABLES ........................................................................................................ G
LIST OF FIGURES ...................................................................................................... H
INTRODUCTION ......................................................................................................... 1
OBJECTIVE .................................................................................................................. 4
LITERATURE REVIEW .............................................................................................. 5
MATERIALS AND METHODS ................................................................................. 13
Materials .................................................................................................................. 13
Methods ................................................................................................................... 13
1. Power system network ......................................................................................... 15
2. PSCAD/EMTDC modelling and simulation........................................................ 15
2.1. Electromagnetic transient modelling for Nammang3-Nabong .................. 15
2.1.1 Transmission line model.................................................................. 16
2.1.2 Tower model.................................................................................... 19
2.1.3 Footing resistance model ................................................................. 24
2.1.4 Insulator and back-flashover model ................................................ 25
2.1.5 Line terminal model ........................................................................ 29
2.1.6 Substation equipment "Autotransformer" model ............................ 29
2.1.7 Line surge arrester model ................................................................ 30
2.1.8 Lightning stroke model.................................................................... 33
2.2 Method of simulation .................................................................................. 36
2.2.1 Simulation variable settings ............................................................ 36
2.2.2 Simulation criteria ........................................................................... 36
F
Page
Page
Cause types
No. Line description Natural
Tree Lightning Accident Animal Unknown
disaster
1 KhoksaAd - Nabong1 2 0 2 1 0 1
2 KhoksaAd - Nabong2 2 0 2 1 0 1
3 KhoksaAd - Viengkeo 2 2 0 1 0 2
4 Nammang3 – Lao steel factory 0 0 0 0 0 0
5 Nammang3 - Nabong Line1 1 2 4 0 0 1
6 Nammang3 - Nabong Line2 1 2 4 1 0 0
7 Naxaythong - Donkoi 0 0 0 0 0 0
8 Naxaythong - Namnguem1 Line1 0 2 0 0 1 3
9 Naxaythong - Namnguem1 Line2 2 2 1 0 1 3
10 Naxaythong - Phonsoung 2 1 1 0 0 6
11 Naxaythong - Pakthang 1 0 2 0 2 2
12 Naxaythong - Thangon 1 2 1 0 0 3
13 Naxaythong - Viengkeo 3 1 3 0 2 19
14 Phontong - Donkoi 4 2 0 1 3 6
15 Phontong - Nongkhai Line1 2 3 3 1 0 9
16 Phontong - Nongkhai Line2 0 3 3 1 0 5
17 Phontong - Naxaythong Line1 12 10 5 4 2 18
18 Phontong - Naxaythong Line2 6 4 4 2 2 7
19 Phontong - Naxaythong Line3 4 4 1 3 1 7
20 Phontong - Pakthang 2 2 1 2 1 6
21 Thanaleng - Donkoi 2 2 0 0 1 3
22 Thanaleng - KhoksaAd 1 2 1 1 0 3
23 Thanaleng - Nongkhai3 3 3 2 1 1 11
Total 53 49 40 21 17 116
3
18%
38%
17%
6%
7% 14%
OBJECTIVE
LITERATURE REVIEW
The lightning surges on OHTL depend on how surges are caused and describe
the shape of the lightning current wave as usual; they can be classified broadly into five
types: The first is lightning strikes directly to phase conductor without flashover. The
second is an attack to phase conductor followed by a flashover. The third is an attack
to the transmission tower or overhead ground wire (OHGW) followed by a back
flashover (BFO) to a phase conductor through an insulator string due to the ground
potential. The fourth is the third type BFO but followed by flashover along the ground
to a conductor of the previous or nearby tower, stepped if subsequent flashover to earth
occurs at more than one tower. Finally, the fifth is lightning that strikes the ground
nearby a transmission tower and induces through the tower footing system.
A solution effort to reduce lightning faults from past to present has produced
many new methods. For instance, (Mobarakei, Sami, & Porkar, 2012) analyzed the
BFO mechanism and the high-efficiency parameter introduced, and these efficiency
parameters are determined to decrease back flashover rated. There are also simulations
involving the protection performance of a gas-insulated substation regarding the BFO
and evaluating the breakdown voltage and the effectiveness of LA. The proposed
methods to reduce BFO has suggested in the literature are as follows:
Additionally, the LA analysis for OHTL due to BFO and shielding failure is
another condition considered; this approach focuses on estimating the arrester energy
of the BFO phenomenon due to shielding failure by using the PSCAD/EMTDC
program. The model uses to simulate the event of the discharged energy of LA. In this
case, the engineers are interested in LA only and behavior of the LA such as strokes to
8
tower or OHGW, strokes to the phase conductors, and the effect of footing resistance
(Nor Hidayah Nor, Bakar, Mokhlis, & Illias, 2012).
The design for improving the transmission line performance due to lightning
overvoltage (Franc, Filipovic-Grcic, & Milardic, 2016) has presented a combination of
LA with different rated voltages for use in 110kV air-insulated substations connected
with HPP. It is a model on EMTP-ATP software.
From a survey of the existing, most research works are devoted to finding new
technical methods only, disregarding resultant costs of required infrastructure.
However, some researchers are interested in the economic viewpoint. For instance,
(Katic & M.S.Savic, 1998) presented an optimization of technic with concern financial
for lightning protection on overhead power distribution. This work estimated a
lightning flashover rate in both direct and indirect surges.
The part of the economic analysis is the total value on the distribution line
consisting of the line building, the maintenance, energy loss, and outage costs.
9
In the protection design for the transmission line, (De Oliveira-De Jesus,
Hernandez-Torres, & Urdaneta, 2018) presented a way to specify the proper insulation
and the specific footing resistance of each supports for the outage rate requirement by
using EMTP software with constraints the lowest cost by optimization method. Finding
a suitable insulation design was divided into three parts: cost optimization, outage cost
of the design methodology, and expert system. The optimization and outage cost from
insulation and tower footing resistance costs. The expert system for comparison
analysis was used linear programming integer by a general algorithm.
As previously reviewed in the literature above, the methods for analyzing and
evaluating lightning protection performance and design have used computer simulation
to solve problems. The most favorite tool for analyzing the fast-front transient is the
electromagnetic transient program (EMTP) expanded in the USA. These programs have
three types: ATP, RV, and PSCAD. The EMTP instrument was adopted by the theory
10
PSCAD or power systems computer aid design is a graphic user interface for
the EMTDC, analyze the results and manage data in a fully functional graphically. It
has plotting, controls, and gauge functions are included. Allows the user to modify
system parameters during simulation operations and watch the effects while the
simulation progresses. While running the simulation, users can edit parameters and see
the effects along the way. PSCAD has many objects tested in the master library. From
simple elements and control functions to more complicated models as rotating
machines, full FACTS devices. If the desired model is unavailable, PSCAD can provide
11
This program uses the new Fortran 90/95 standard, allowing dynamic
memory allocation at the start of each run.
Starting the system with a snapshot file, this start-up technique is rapid
and implemented on massive systems. It is the only practical method for
displaying highly non-linear systems.
Manitoba HVDC Research Centre provides full-time professional
support services for EMTDC.
Materials
1. Personal Computer
2. Microsoft Window 7 Operation
3. PSCAD/EMTDC Simulation Program
4. MATLAB
5. Microsoft Office 2013
Methods
1) The technical objectives are to analyze the overvoltage rate and magnitude
of a lightning strike on OHTL, design of insulation coordination in other case schemes
on PSCAD. The LA, insulator string, and tower footing resistance are the main factors
to assess lightning withstand based on the BIL standard, which of this step requires
iteration until the overvoltage is lower than BIL. The parameter used in PSCAD
modeling obtains from the operation & maintenance manual, drawing, and single line
diagram.
2) The economic objectives are to calculate the overall investment cost of the
design, including equipment material and installation, transportation adopted by actual
price of projects. In addition, other cost factors are taken into consideration, such as
maintenance and energy non-supply costs, which involve opportunity and economic
loss.
3) The last objective compares the technical and economic objectives for the
design over necessary but still efficiency; this step uses to find the optimal solution in
the design, then, the multi-objective optimization (MOOP) for decision.
15
The study focuses on the effects of the BFO phenomenon, modeling the 115-
kV transmission line system of Nammang 3 - Nabong. The line has connected between
northern areas to central-1 area transmission systems, as illustrated in Figure 5. The
method comprises HPP at Nammang3 with 20 MW generators, two units, supplied
power in nominal loads about 30 MW, and hard loads about 38 MW transmit power to
Nabong substation to supply power 115 kV for large customers and 22 kV for five
feeders.
The modeling for the fast front surge transmission line implemented in
PSCAD for each component adopts theory (Imece et al., 1996). The complete model
has shown in Figure 6.
- Tower model
- Arrester model
The primary transmission line model has been defined into six segments with
seven transmission towers and a starting point from the line terminal until winding
capacitance. The OHGW and phase conductor used in a wire module are available in
the master library, assigned from top to bottom. Which these studies assume the
lightning has struck near the line incoming substation. The lightning designs to knock
on the OHGW. The lightning model connected in the top line of the last tower incoming
substation as shown above.
The tower parameter for calculating has given from Figure 11.
0.5
ZT 60log[cot{ }] (1)
tan(R/h )
Where:
r1h 2 r2 h r3h1
R (2)
h1 h 2
τ T h/c (3)
Where:
Xi 1
Ri 2ZT ln( ) (4)
h α
Li 2τT R i (5)
Where:
i Number of the tower structure
α Attenuation factor is 0.89
X2 1 3.4 1
R2 2ZTln( ) 2 6.2077 ln( ) 3.6538
h α 29.4 0.89
X3 1 3.4 1
R3 2ZT ln( ) 2 6.2077 ln( ) 3.6538
h α 29.4 0.89
X1 1 17.8 1
R4 2ZTln( ) 2 6.2077 ln( ) 19.129
h α 29.4 0.89
Step 4: Damping inductance calculation
1 E Oρ O
IO (6)
2π R O2
Ro
Rf
I (7)
1 ( )
IO
Where:
RO Grounding resistive, (Ω)
(Imece et al., 1996). A simplified insulator circuit models as Figure 17; a capacitor is a
connected parallel breaker switch with BFO control.
The BFO control module has four inputs signal include (Vstring),
(Vline), and insulator length by meter and flashover (Fin). Vstring and Vline given from
the voltmeter arc-horn gap given from length of number disc insulators and phase
flashover is integer constant value.
Vstring and Vline calculation are based on 1/t 0.75 trigger output
voltage across the string by the range and the 1/t 0.75 as input parameters. The
comparator on the right compares the trigger voltage across and string value and
provides the output with a pulse. The AND component collects output value "1" by
pulse and phase flashover (Fin) value "1", which the output "BRK" formulate shut of
the breaker switch makes an outward induce across the insulator string which imitates
the BFO trigger across the between (ACt) to (ACb). The integer constant value "0" is
needed to reset the breaker switch to open.
710L
Vv t 400L (8)
t 0.75
Where:
Vv t Voltage across insulator, (kV)
L Arc horn gap, (m)
t Time, (s)
The insulator string design of 115-kV for the simulation increases the
number of disc insulators from 8 to 11, represented by length 1.168 m to 1.606 m. The
voltage-time curve between old and new designs has been calculated and plotted on
MATLAB:
The line terminal is the start point of the model connected to the line's
ground and ground. The ground impedances are established in the line terminal module
connected with the transmission line configuration component on the top left side, as
shown in Figure 6. OHGW assigned grounded through 426 Ω equivalent impedances
for two top interfaces, and the rest phase conductors are 354 Ω at all six interfaces.
The last point of the model is similar to the line terminal model,
determined by the phase conductors connected with the autotransformer. An
autotransformer is indicated by its capacitances to the ground, assigned ground through
3,500 pF equivalent capacitances (Imece et al., 1996).
L0 L1
R0 R1
C A0 A1
L0 0.2d/n (9)
R 0 100d/n (10)
L1 15d/n (11)
R1 65d/n (12)
C 100n/d (13)
Where:
n Column of LA parallel
31
The non-linear resistor is given from the graph in Figure 25, it use to
specify a parameter crossover between a voltage and current. This value is then
multiplied by (V10/1.6) for calculating a discharge voltage in A0 and A1.
The steps and equations used in a model for surge arrester calculations are as follows:
Surge arrester use in this work has selected PEXLIM R-Y, line surge
arrester rated voltage 96 kV, discharge voltage 249 kV, and d = 1.216 m [Appendix -
section 4].
For A0:
Discharge kV = 1.10×155.62 = 171.19 kV
For A1:
Discharge kV = 0.72×155.62 = 112.05 kV
Where:
α and β for 8/20 s and 1.2/50 s has been determined in reference (Das, 2010)
For the front wave of 8/20 µs, the origin starts from zero to 10 % and
leads to 90 %. The duration of the tail wave is determined time between virtual origins
to the time of 50 % point.
For the front wave of 1.2/50 µs, the origin starts from zero to 30 %
and leads to 90 %. The duration of the tail wave is determined time between virtual
origins to the time of 50 % point.
35
Case (1): This case is used to compare with other cases; therefore no
protection design in this case.
Case (3): This case uses the improved tower resistance following a
case (2). More is the adding a lightning protector of 96 kV for the tower front of the
substation in all phases.
Case (4): This case is the same design of insulator in case (2) and
lightning protector of case (3) is installed.
Case (5): This case combines three variable factors: tower footing
resistance, insulator, and LA.
The runtime simulation has been specifying the time settings follow:
3. Economical objective
total investment cost, given in equation (17). The various expenses used in the
calculation are derived from the bill of quantities and the bidder contractor in the actual
prices EDL.
CT = CI + CM - CL (17)
Where:
Investment charges are used to purchase equipment for the design, including
construction and portage costs. The leading equipment used includes an insulator with
arc-horn, LA, and grounding, detail presented in Table 8.
Maintenance charges are used to repair the damaged equipment when outage,
which has been different by causes of each case. Due to differences, the costs in this
section cannot be set equally. This section's cost is determined to be the same in all
cases to simplify calculations.
Where:
The cost of electricity per kilowatt-hour for a 115-kV transmission line has used
the prices during the rainy season. It is 5.5 Cent/kWh accounted for 0.06 USD/kWh.
39
Table 8 List and price of EDL 115 kV transmission line of financial proposal
Supply Construction
component component
(SC) (CC)
No. Description Unit Qty
Unit Total Unit Total
price price price price
(USD) (USD)
115kV Lightning arrester with
1 pcs 6 892 5,352 418 2,508
counter & support structure
String suspension insulator
2 with arcing horn & armor rods set 6 164 984 23 1,122
fpr DARKE conductor
3 5×2m earthing rod Each 3 83 249 15 294
4 5×60m C/Tape Each 3 240 720 15 765
5 Additional earthing C/Tape m 3 4 12 1 15
6 Additional earthing rod m 3 11 33 8 57
7 Insulator 70kN set 36 10.07 362.52 1.12 402.84
8 Insulator 120kN set 36 7.10 255.60 0.79 284.04
The calculations of the cost of energy non-supply assume the power interruption
in one hour in all cases based on the same rate of power supply at 30 MW.
# Calculation the total cost of transmission line for each cases design:
Case (2):
CT = CI + CM - CL = 2,939.88 + 60.23 – 1,800 = 1,010.75 USD
Case (3):
CT = CI + CM - CL = 8,991 + 60.23 – 1,800 = 7,251.23 USD
Case (4):
CT = CI + CM - CL = 9,668.88 + 60.23 – 1,800 = 7,739.75 USD
Case (5):
CT = CI + CM - CL = 10,799.88 + 60.23 – 1,800 = 8,870.75 USD
4. Multi-objective optimisation
each other. The best parameters of some objectives did not conduct to the suitability of
others. For instance, we need the best service on vacation. Meanwhile, we wish to pay
as minimum as possible. Therefore, the best service is the first objective. The cost will
unavoidably increase; however, this contradicts other objectives (to minimize costs).
Therefore, we must choose to compromise or achieve an equilibrium objective among
these often adversative goals. If these are not possible, we have to select the setting item
that should be taken first. More importantly, we have to compare different objectives
and reconcile. This often requires reformatting, and one of the most reach to formatting
is discovering a scalar function that shows a weighted intergrade of inclination of all
goals. Such scalar functions are often called preference or utility functions. An easy
way to create a scalar function is to use a weighted sum (Yang, 2014). This method
intergrades all MOOP functions into a single compound scalar objective function using
a weighted sum.
J w1 j1 w 2 j2 ... w m jm (20)
Where:
w Weighting coefficients
j Objective
The MOOP for this work assign the performance is the first objective “j 1”
determined the voltage reduction from section 2. The cost is the second objective, “j2”
from section 3. Weighting coefficients are determined into three cases: high risk,
moderate risk, and low risk, such as the transmission is installed in a mountainous area
that frequency attack by lightning and another factor is the difficulty of access to
maintenance, etc. From (20), the weight of performance of 80% and cost of 20%, the
weight of performance of 50% and cost of 50%, and the weight of performance of 20%
and cost of 80% are defined as follows:
According to simulation criteria, the BIL of the 115-kV transmission lines, the
breakdown voltage is 550 kV. Therefore, the current amplitude for simulation and
design is 40 kA with 1.2/50 µs.
Case (1): Figure 34 shows that the overvoltage at 637 kV exceeds the BIL values
of 550 kV.
Case (2): The design of a new insulator length from 1.168 m to 1.606 m and
the grounding resistive specified at 5-10 Ω can reduce overvoltage at 445 kV.
43
Case (3): LA was installed at all phase conductors in the first incoming tower,
while the ground resistive used is the same as the case (2). It can reduce overvoltage at
355 kV.
Figure 37 Overvoltage with 96 kV line surge arrester and 1.606 m insulator length
Case (4): This case insulator and LA was chosen as a shield against the
lightning BFO phenomenon, both of which are determined based on case (2) and case
(3). It can reduce overvoltage at 360 kV. But it high than the case (3).
44
Case (5): From the combination design between ground resistive, insulator, and
LA, the voltage was reduced to 340 kV. In this case, the voltage was reduced the most.
The results of the experiments in PSCAD and the calculation of overall charges
were summarised in Table 10. In the first case, the voltage is higher than the BIL shown
in the table at 637 kV. In the second case, the voltage is reduced to 445 kV, which
decreases to 192 kV from the first case. In this case, the total price is 1,010 USD. In the
third case, the voltage is reduced to 355 kV, which decreases to 282 kV from the first
case, and the total price is 7,251 USD. However, this case's voltage is lower than the
second case, but the budget is high. In the fourth case, the voltage is reduced to 360 kV,
which decreases to 277 kV from the first case, and the total price is 7,739 USD.
However, this case's voltage and budget are higher than the third one. Finally, in the
last case, the voltage is reduced to 340 kV, which decreases to 297 kV from the first
case, and the total price is 8,870 USD. Although the voltage of this case is lower than
all cases, the total prices are higher than in other cases.
In order to select an optimal solution, MOOP has been used in this process
which explains in section 4. Since the object has a different scale, it is impossible to
compare. Therefore, it is necessary to convert both objectives to a similar scale between
0-1 with normalization. The weighting coefficients of objective assign as follows: (a)
high risk: w1 = 80% and w2 = 20%, (b) moderate risk: w1 = 50% and w2 = 50%, and (c)
low risk: w1 = 20% and w2 = 80%.
Conclusions
The insulation coordination is critical for the transmission line to ensure that the
system can withstand much energy during abnormal conditions. This transmission line
is modeled according to PSCAD/EMTDC. This program can be used to gain insights
into the system's transient behavior studied during fault conditions; many functions
make sense in the design. Due to operation and this line being connected to a large
customer, the Nammang 3 HPP and Nabong substation network is chosen to study the
operation.
A power system network model focused on the BFO behavior in modeling the
transmission lines, dimensions, calculations, lightning, and protection scheme design
of their transmission line towers have been presented by frequency-dependent phase
model. The simulation results of initial parameters from these transmission line
networks have been compared with an economic viewpoint. Ground resistive,
insulators, and LA are integrated into this study on how the impact of transient behavior
affects the operation of the protection scenario.
This thesis proposes the methodology for selecting the most suitable design to
help reduce transmission line maintenance costs to increase the opportunity to distribute
electricity. Furthermore, it also helps reduce the failure caused by lightning that affects
industries and commercial factors. Different risks can choose each design at the total
prices based on effectively by the lower costs. This methodology can be applied in other
transmission lines of EDL for planning and improvement of the protection.
47
Recommendation
Technical analysis reveal a lack of data on certain factors that may impair
technical aspects' technical performance: The transmission line parameter is the actual
grounding resistance variation of towers due to the soil ionization effect of surge wave
propagation. As a result, the simulation may not be as good as it should be. In addition,
lightning statistical data such as the number of lightning thunderstorms day per year for
calculating the number of cloud to ground flash densities are required. More complete
performance analysis can be done if the data from a lightning location system is
available.
Economic analysis, the parameters of economic analysis still need more data to
make more accurate decisions for appropriate such as transmission line maintenance
costs and transmission line outage costs in each type of risk cases due to this works
assumes that all cases have the same condition. In addition, determining the type of
customers affected by lightning is might one factor that affects the costs, for instance:
an industry, commercial, electric monorail, hospital, etc., that needs more than the
residential.
LITERATURE CITED
LITERATURE CITED
Imece, A. F., Durbak, D. W., Elahi, H., Kolluri, S., Lux, A., Mader, D., . . . Tarasiewicz,
E. (1996). Modeling guidelines for fast front transients. IEEE Transactions on
Power Delivery, 11(1), 493-506. doi:10.1109/61.484134
Ishii, M., Kawamura, T., Kouno, T., Ohsaki, E., Shiokawa, K., Murotani, K., & Higuchi,
T. (1991). Multistory transmission tower model for lightning surge analysis.
IEEE Transactions on Power Delivery, 6(3), 1327-1335.
doi:10.1109/61.85882
Mobarakei, S. T., Sami, T., & Porkar, B. ( 2012). Back Flashover Phenomenon Analysis
in Power Transmission Substation for Insulation Coordination. 2012 11th
International Conference on Environment and Electrical Engineering.
doi:10.1109/EEEIC.2012.6221567
Morched, A., Gustavsen, B., & Tartibi, M. (1999). A universal model for accurate
calculation of electromagnetic transients on overhead lines and underground
cables. IEEE Transactions on Power Delivery, 14(3), 1032-1038.
doi:10.1109/61.772350
Novizon, N., Seftiani, Y. M., & Ahmad, M. H. ( 2019, 22-24 July 2019). Flashover
Phenomenon on 150kV Transmission Line Due to Direct Lightning Strike on the
50
WADHWA, C. L. (2009). Electrical Power Systems: New Age International (UK) Ltd.
Williams, A., Vakilian, M., & Blackburn, T. R. (2015). A Method for Optimal
Coordinated Insulation Design of Transmission Line. Australian Journal of
Electrical and Electronics Engineering, 7(3), 211-224.
doi:10.1080/1448837x.2010.11464273
L=1.168;
K1=400*L;
K2=710*L;
t=(0:1:50)*1e-6;
V=K1+(K2./(t.^0.75))
t1=t;
v1=V;
L=1.606;
K1=400*L;
K2=710*L;
t=(0:1:50)*1e-6;
V=K1+(K2./(t.^0.75))
t2=t;
v2=V;
plot(t1,v1,'r','linewidth',1.5); hold on
plot(t2,v2,'b','linewidth',1.5);
set(gca,'FontSize',15)
xlabel('Time (sec)','FontSize',15);
ylabel('Voltage (Volt)','FontSize',15);
legend('Insulator length 1.168m','Insulator length 1.606m')
grid on
54
CURRICULUM VITAE