INSPECTION & TEST PLAN - STEEL STRUCTURE WORK FOR STEEL BRIDGE AND METRO STATION
SCOPE OF
REFERENCE INSPECTION
SL. DESCRIPTION OF FREQUENCY OF
CHARACTERISTICS TYPE OF CHECK ACCEPTANCE CRITERIA DOCUMENTS / REMARKS
NO. MATERIALS CHECK
SPECIFICATION
SIL RVNL
3 Manufacturing Process
3.2 Cutting Dimension Measurement Random As per approved drawing Dimension Report W R
3.3 Layout of Components & Joints Dimension Visual & Measurement 100% As per approved drawing Inspection Report W W&R
3.4 Jigs, Fixtures & Templates Dimension Visual & Measurement 100% As per approved drawing Approved Drawing W R/W
Edge Preparation of
Visual 100%
Joints
3.5 Fit up Dimension Measurement 100% As per approved drawing Fit up inspection Report W W&R
Temporary Support to
Visual 100%
avoid Distortion
Welding Parameters
Approved WPS / As per
(Current, Voltage, Travel Random
job requirement
Speed etc.)
Consumables
(Electrodes, Filler Wire, Specification 100%
Flux etc.)
3.6 Welding As per approved WPS Internal inspection Report W W&R
Approved Welder's
Welder's Identification 100%
Certificate & ID Card
3.9 Trial Assembly As per approved drawing / IS:7215 Inspection Report / Protocol W W
Primer
Avg. DFT (As per
Minimum 3 point for each
4.1 Painting manufacturer As per contact specification Painting Inspection Report W R
mark No
specification)
Final Coat
Legend :
W – Witness , R – Review, R/W - Review or witness, DFT – Dry Film Thickness, UT – Ultrasonic test, DT-Destructive test, RT – Radiography test, MTC – Manufacturer test Certificates.
DPT – Dye Penetration test, NDT-Non Destructive Test