100% found this document useful (2 votes)
1K views186 pages

Telecommunications Distribution Design Guide

This document provides guidelines for telecommunications infrastructure design for GSA projects. It outlines policies, procedures, and design criteria that designers must follow, including requirements for different project phases and reviews. Adherence to the standards ensures proper installation and operation of low voltage systems across GSA facilities.

Uploaded by

afouda
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (2 votes)
1K views186 pages

Telecommunications Distribution Design Guide

This document provides guidelines for telecommunications infrastructure design for GSA projects. It outlines policies, procedures, and design criteria that designers must follow, including requirements for different project phases and reviews. Adherence to the standards ensures proper installation and operation of low voltage systems across GSA facilities.

Uploaded by

afouda
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 186

This page intentionally left blank.

Document Intent

Please be advised that this document is intended to serve only the purposes of GSA. It
does not apply to non-GSA tenants.
The requirements described in this document apply only to spaces and systems for
which the GSA IT has stewardship. Some departments within GSA may have their own
telecommunications standards. The Designer shall communicate with each GSA
department that will occupy space in the building to obtain their potentially unique
requirements for telecommunications infrastructure for spaces and systems under their
stewardship.
Other non-GSA tenants may also occupy space in a building. The Designer shall inquire
whether a facility will serve non-GSA tenants, and if so will work with the GSA PBS PM
to obtain tenant-specific telecommunications infrastructure requirements for non-GSA
tenants.
Other building tenants (both within GSA and non-GSA) may choose to adopt these
standards for their purposes on a given project. However, this document does not
require that they do so.
This document describes contractually binding requirements with which technology
infrastructure designers, architects, engineers, and design-build contractors/installers
must comply.

1 Telecommunications Distribution Design Guide [ Version 8 ]


Table of Contents
Document Intent ........................................................................................................... 1

Table of Contents .......................................................................................................... 2

Table of Figures ............................................................................................................. 6

1 Preface ..................................................................................................................... 9
1.1 Low Voltage Systems ...................................................................................... 10
1.2 Outside Plant Infrastructure ............................................................................. 11
1.3 Document Context ........................................................................................... 12
1.4 Document Structure ........................................................................................ 15
1.5 Construction Type ........................................................................................... 16
1.6 Building Types ................................................................................................. 17
1.7 Tenant Specific Requirements ........................................................................ 17
1.8 GSA Departments ........................................................................................... 18
1.9 GSA Personnel ................................................................................................ 18
1.10 Key Terms and Abbreviations ..................................................................... 19

2 GSA Telecommunications Policies ...................................................................... 21


2.1 GSA Personnel ................................................................................................ 22
2.1.1 GSA Personnel Installations .................................................................... 22
2.2 Initiating New Projects – General .................................................................... 23
2.2.1 New Construction .................................................................................... 23
2.2.2 Modernization of Existing Structures ....................................................... 23
2.2.3 Minor Remodel (workspace remodel) ...................................................... 23
2.2.4 Upgrading Telecommunications Infrastructure to Support New
Technology .......................................................................................................... 23
2.2.5 Upgrading Telecommunications Infrastructure to Meet New Standards . 24
2.2.6 Infrastructure to Support Other Tenants at GSA Facilities ...................... 24
2.2.7 Damage to Existing Telecommunications Infrastructure ......................... 24
2.3 Initiating New Projects – Specific .................................................................... 25
2.3.1 Telecommunications Room Work ............................................................ 25
2.3.2 Horizontal Cabling ................................................................................... 27
2.3.3 Regional Information Center (RIC) .......................................................... 27
2.4 Procurement and Installation Policy ................................................................ 28
2.4.1 Procurement Policy for Information Technology Infrastructure ............... 28
2.5 Telecommunications Projects ......................................................................... 30
2.5.1 Externally Designed................................................................................. 30
2.5.2 Internally Designed Telecommunications Projects .................................. 31
2.6 Reviewing Telecommunications Designs ........................................................ 32
2.6.1 Standards Variance Requests (SVR) ...................................................... 32
2.6.2 Design Review......................................................................................... 32
2.7 Telecommunications Operation and Maintenance .......................................... 33
2.7.1 GSA Telecommunications Infrastructure Responsibilities ....................... 33
2.7.2 Service Provider Responsibilities ............................................................ 33
2.7.3 Manufacturer-Certified Installation........................................................... 33
2.7.4 GSA Telecommunications Technicians ................................................... 34
2.7.5 Moves, Adds, and Changes .................................................................... 34
2.7.6 Electrical Power in Telecommunications Rooms ..................................... 35
2.7.7 Telecommunications Administration ........................................................ 35

3 Project Procedures ................................................................................................ 37


3.1 Designer Qualifications ................................................................................... 37
3.2 Architect/Engineer Teams ............................................................................... 39
3.2.1 Cross-Discipline Coordination ................................................................. 39
3.3 General Procedures ........................................................................................ 39
3.3.1 CAD Files ................................................................................................ 39
3.3.2 Standards Variance Request (SVR) ........................................................ 40
3.4 Procedures Related to Project Phases ........................................................... 41
3.4.1 Schematic Design and Fieldwork ............................................................ 41
3.4.2 Design Development ............................................................................... 42
3.4.3 Construction Documents ......................................................................... 42
3.4.4 Bidding..................................................................................................... 43
3.4.5 Construction Observation ........................................................................ 44
3.4.6 Post-Construction .................................................................................... 46
3.5 Design Review Process .................................................................................. 47
3.5.1 RCDD Review Consultant ....................................................................... 52
3.5.2 Design Review Checklist ......................................................................... 53
3.6 Field Investigation Activities ............................................................................ 53
3.7 Designing for Demolition ................................................................................. 53
3.7.1 Site Specific Code Requirements ............................................................ 53
3.7.2 Salvage Objectives .................................................................................. 53
3.7.3 Preservation Objectives........................................................................... 54

4 Design Criteria ...................................................................................................... 55


4.1 Principles of Transmission .............................................................................. 55
4.2 Electromagnetic Compatibility ......................................................................... 55
4.3 Telecommunications Spaces .......................................................................... 56
4.3.1 Telecommunications Room Location ...................................................... 56
4.3.2 Telecommunications Room Sizing .......................................................... 57
4.3.3 Architectural Provisioning ........................................................................ 58
4.3.4 Environmental Provisioning ..................................................................... 59
4.3.5 Fire Suppression ..................................................................................... 61
4.3.6 Equipment Racks and Cabinets .............................................................. 61
4.3.7 Power Requirements ............................................................................... 64
4.3.8 Lighting .................................................................................................... 72
4.3.9 Grounding, Bonding, and Electrical Protection ........................................ 73
4.3.10 Cables Entering Telecommunications Rooms ..................................... 73
4.3.11 Entrance Facilities ............................................................................... 73
4.4 Backbone Distribution Systems ....................................................................... 74
4.4.1 Intra-building Backbone Pathways .......................................................... 75
4.4.2 Intra-building Backbone Cabling .............................................................. 77
4.4.3 Inter-building (Campus) Backbone Pathways ......................................... 80
4.4.4 Inter-building (Campus) Backbone Cabling ............................................. 80
4.5 Horizontal Distribution Systems ...................................................................... 81
4.5.1 Work Areas .............................................................................................. 81
4.6 ITS Cables and Connecting Hardware .......................................................... 104
4.6.1 Copper Cabling...................................................................................... 104
4.6.2 Fiber Optic Cabling ................................................................................ 105
4.6.3 Splicing .................................................................................................. 105
4.7 Firestop Systems ........................................................................................... 112
4.8 Bonding and Grounding (Earthing) ................................................................ 113
4.9 Power Distribution ......................................................................................... 114
4.10 Telecommunications Administration .......................................................... 115
4.10.1 Identification Strategy ........................................................................ 115
4.11 Field Testing of Structured Cabling ........................................................... 119
4.12 Outside Plant ............................................................................................. 120
4.13 Audio/Visual Systems ................................................................................ 121
4.13.1 Private CATV Distribution Systems ................................................... 121
4.13.2 Distributed Paging Systems............................................................... 121
4.14 Building Automation Systems .................................................................... 121
4.15 Data Network Design................................................................................. 123
4.16 Wireless ..................................................................................................... 123
4.17 Electronic Safety and Security................................................................... 124
4.18 Regional Information Centers and Data Centers....................................... 125
4.18.1 Small Scale Equipment Rooms ......................................................... 125
4.18.2 Data Centers ..................................................................................... 125
4.18.3 Regional Information Center (RIC) .................................................... 125
4.19 Health Care ............................................................................................... 143
4.20 Residential Cabling.................................................................................... 144
4.21 Business Development and Project Management..................................... 144
4.22 Codes, Standards, Regulations, and Organizations.................................. 144

5 Construction Document Content ........................................................................ 145


5.1 Plans and Diagrams ...................................................................................... 146
5.1.1 General .................................................................................................. 146
5.1.2 Inside Plant Telecommunications Plan Drawings .................................. 146
5.1.3 Demolition.............................................................................................. 147
5.1.4 Telecommunications Room Plan Details ............................................... 147
5.1.5 Elevation Diagrams ............................................................................... 148
5.1.6 Intra-building Backbone Schematic Diagrams ....................................... 149
5.2 Project Manual .............................................................................................. 149
5.2.1 Specifications ........................................................................................ 149
5.2.2 Cutover Plan .......................................................................................... 150
5.2.3 Fiber Link-loss Budget Analysis ............................................................ 150
5.3 Record Drawings and Documentation ........................................................... 150

6 Appendix .............................................................................................................. 153


6.1 Design Review and Construction Observation .............................................. 153
6.1.1 Sample Review Comment Report ......................................................... 153
6.1.2 Design Review Checklist ....................................................................... 154
6.1.3 Construction Observation Checklist ...................................................... 154
6.1.4 What to Do with the Completed Checklists ........................................... 155
6.2 Sample Telecommunications Room Plan Details.......................................... 156
6.2.1 One-Rack Room .................................................................................... 157
6.2.2 Two-Rack Room .................................................................................... 158
6.2.3 Three-Rack Room ................................................................................. 159
6.2.4 Wall-Mounted Cabinet ........................................................................... 160
6.3 Sample Rack Elevation Detail ....................................................................... 162
6.4 Sample Wall Elevation Detail ........................................................................ 164
6.5 Sample Fiber Optic Link-Loss Budget Analysis............................................. 166
6.6 Cable Color Scheme ..................................................................................... 168
6.7 Standards Variance Request Approval Process ........................................... 169
6.8 Glossary ........................................................................................................ 171

7 Index .................................................................................................................... 181


Table of Figures
Figure 1: The Design Process.................................................................................................. 13
Figure 2: Telecommunications Room Floor Plan Sizing ....................................................... 27
Figure 3: Design Review Process............................................................................................ 49
Figure 4: Design Review Process with Consultant................................................................ 51
Figure 5: Power and Grounding for Telecommunications Rooms with Centralized
UPS Equipment ................................................................................................................. 66
Figure 6: Power and Grounding for Telecommunications Rooms with Distributed
UPS Equipment ................................................................................................................. 67
Figure 7: Power Distribution Architecture for TRs in ROBs with 1U Network
Switches ............................................................................................................................. 69
Figure 8: Power Distribution Architecture for TRs in ROBs with Chassis Network
Switches ............................................................................................................................. 70
Figure 8: Utility Service and Riser Backbone Cabling .......................................................... 75
Table 9: Fiber Optic Patch Cord Requirements ..................................................................... 79
Figure 9: One Patch Cord Pass-Through................................................................................ 83
Figure 10: Terminated Half Patch Cord ................................................................................... 84
Figure 11: Two Coupled Patch Cords ..................................................................................... 85
Figure 12: Horizontal Cable Pass-Through ............................................................................ 86
Figure 13: Outlet Locations on End Wall of Conference Room ............................................ 87
Figure 14: Terminated Half Patch Cord (Option 1a) ............................................................... 89
Figure 15: Terminated Half Patch Cord (Option 1b) .............................................................. 89
Figure 16: Terminated Half Patch Cord (Option 1c) ............................................................... 90
Figure 17: Two Coupled Patch Cords (Option 2a) ................................................................. 90
Figure 18: Two Coupled Patch Cords (Option 2b) ................................................................. 91
Figure 19: Two Coupled Patch Cords (Option 2c) ................................................................. 91
Table 20: Faceplates, Jacks and Blank Inserts ...................................................................... 96
Figure 21: Cable Support Elevations ...................................................................................... 98
Figure 22: Cable Support Elevations ...................................................................................... 99
Figure 23: Cable Support Elevations .................................................................................... 100
Figure 24: Angled Patch Panel Requirements ..................................................................... 107
Table 25: Copper Patch Cord Requirements ........................................................................ 111
Figure 26: Horizontal Cables and Copper Patch Cord Labeling Requirements ................ 112
Figure 27: Cable Labeling Diagram ....................................................................................... 116
Figure 28: Horizontal Cabling Options for Building Automation Systems and
Electronic Safety & Security Devices ............................................................................ 122
Figure 29: RIC Sizing and Arrangement ............................................................................... 126
Figure 30: RIC Cabinet Elevation Diagram ........................................................................... 129
Figure 31: RIC Rack Elevation Diagram ................................................................................ 131
Figure 32: RIC Cabling Diagram ............................................................................................ 133
Figure 33: Backup Power Decision Tree............................................................................... 136
Table 34: NEC-Defined Generator Classes ........................................................................... 138
Figure 35: RIC Power Distribution Architecture................................................................... 142
Figure 36: One-Rack Room .................................................................................................... 157
Figure 37: Two-Rack Room .................................................................................................... 158
Figure 38: Three-Rack Room ................................................................................................. 159
Figure 39: Wall-Mounted Cabinet Plan View ........................................................................ 160
Figure 40: Wall-Mounted Cabinet Elevation ......................................................................... 161
Figure 41: Sample Rack Elevation Detail .............................................................................. 163
Figure 42: Sample Wall ELevation Detail .............................................................................. 165
Figure 43: Sample Fiber Optic Link-Loss Budget ................................................................ 167
Figure 44: Cable Color Scheme ............................................................................................. 168
Figure 45: Standards Variance Request ............................................................................... 170
This page intentionally left blank.
1
Preface

A. The Telecommunications Distribution Design Guide (TDDG) is written to


communicate the requirements of U.S. General Services Administration (GSA)
for the design and installation of telecommunications distribution systems at GSA
facilities.
• The TDDG is written for the following audiences:
+ Architects, Engineers, and Designers who are responsible for the design of
new or remodeled facilities for GSA, where telecommunications
infrastructure currently exists or will be installed.
+ Telecommunications contractors (and other low voltage contractors)
installing telecommunications infrastructure at GSA facilities.
+ GSA personnel who are involved in the construction of projects with
technology infrastructure, regardless of the size or scope. This may
include personnel from GSA IT, GSA FAS, and GSA PBS, or their
representatives.
B. Telecommunications distribution systems designed for GSA are expected to
support and integrate telecommunications of voice, data, video, and other low
voltage systems with common media; for example, fiber optic and unshielded
twisted pair (UTP) copper cable.
C. Telecommunications distribution designers shall be responsible to apply the
guidelines, instructions, and requirements in this document while designing
telecommunications distribution infrastructure at GSA facilities.

9 Telecommunications Distribution Design Guide [ Version 8 ]


Preface 1
D. It is the responsibility of telecommunications distribution designers to coordinate
with the other designers on a project (architectural, electrical, mechanical, etc.) to
determine whether other systems are both compatible with and complementary
to the telecommunications cabling system. It is critical to coordinate between
disciplines during the design phase of a project, rather than making adjustments
in the field during construction.
E. Contractors and cabling installers involved in projects without a formal
engineering and design process shall be fluent with and adhere to the
requirements of this document in the course of their work at GSA facilities.
F. This document was prepared by GSA IT. It is updated periodically by GSA IT to
reflect changes in technology and policy. The revision history is as follows:

August 9, 2010 Originally published


September 30, 2010 Updated
July 27, 2011 Updated
April 16, 2014 Updated, Version 7 published
August 6, 2016 Updated, Version 8 published

G. For inquiries about this document, please email [email protected].

1.1 Low Voltage Systems


A. Wherever practical, telecommunications pathway and cabling systems designed
for GSA facilities are expected to support and integrate with the complete set of
building automation systems and other low voltage systems that convey
information and operate facilities. Telecommunications infrastructure shall be
designed in accordance with the requirements in ANSI/TIA/EIA 862-A – Building
Automation Systems Cabling Standard, and the requirements in this document,
to support the Ethernet telecommunications channels on low voltage devices.
Throughout this document, references to “low voltage systems” shall include
those referenced in ANSI/TIA/EIA 862-A, and shall be subject to specific
requirements in that standard and as discussed below.
B. Wherever possible, cabling supporting building automation systems and other
low voltage systems shall be either 24 AWG UTP copper cable (Category 5e-
rated or better) or 50/125 micron multimode fiber optic cable. Backbone cabling
is permitted to be shared among systems; however, horizontal cabling serving
these systems shall be dedicated to each system.
C. The common inside plant (ISP) telecommunications pathway is intended for
shared use by these systems.

Telecommunications Distribution Design Guide [ Version 8 ] 10


1 Preface

D. The following is a non-exclusive list of building automation systems and other low
voltage systems that use telecommunications infrastructure. Other similar
systems may also require the support of telecommunications infrastructure.
• Voice-Over-IP (VOIP) Telephone Systems • Video Systems (Digital)
• Data Networks (wired and wireless) • Fire Alarm Systems
• Building Automation Systems • Security Systems
• Video Surveillance Systems (IP-based) o Access Control Systems
• Energy Management Systems o Alarm Systems
• Environmental Control Systems • PLC Control Systems

E. Inside plant telecommunications infrastructure intended to support Ethernet


telecommunications (or other similar protocols for security and fire alarm
systems) shall be designed in accordance with the inside plant
telecommunications infrastructure requirements in this document. However, due
to the critical nature of these systems, inside plant pathway and cabling serving
these systems shall typically homerun to a Mechanical Room or other Low
Voltage Electronics Room rather than to a common shared telecommunications
room.
F. Where low voltage systems require different media (other than fiber optic cabling
and 24 AWG UTP), the systems shall be designed to comply with the pathway
and space requirements of this document wherever practical.
G. The Designer shall design pathways and cabling to serve these systems, in
cooperation with the other design disciplines on a project.

1.2 Outside Plant Infrastructure


A. The majority of GSA facilities are stand-alone buildings that are not networked
directly with other buildings in a campus-like environment. Interconnections
between buildings are typically accomplished using third-party service providers.
B. The installation of GSA-owned outside plant telecommunications infrastructure is
rare. In such cases the Designer shall design outside plant spaces, pathways
and cabling to meet the requirements of the project, under the direction of GSA
IT IT-Specialists.
C. Where outside plant telecommunications infrastructure is required for a project,
the services of an engineering firm specializing in OSP will be necessary to
design standards-compliant underground ductbanks, maintenance holes, aerial
pathways, and outdoor-rated cabling.

11 Telecommunications Distribution Design Guide [ Version 8 ]


Preface 1

1.3 Document Context


A. GSA has standardized on the ANSI/TIA/EIA – Commercial Building
Telecommunications Standards series and has adopted the following BICSI1
design guide documents as the basis for telecommunications distribution design
in GSA facilities:
• Telecommunications Distribution Methods Manual (TDMM), 13th Edition
• Information Transport Systems Installation Methods Manual (ITSIMM)
The GSA TDDG is the guide to the application of the ANSI/TIA/EIA Standards,
the BICSI TDMM, the BICSI OSP Design Reference Manual (OSPDRM), and the
BICSI ITSIMM to the unique circumstances present in GSA facilities and
projects. See Figure 1 below for further information.
B. The TDDG is intended to be used in conjunction with the TDMM to reinforce
selected TDMM content. It is also used to highlight any restrictions and/or
limitations on TDMM content to meet the specific requirements of GSA facilities.
The TDDG is not intended to detract from or replace the TDMM.
C. The TDDG is not intended to serve as a master specification nor for stand-alone
use on design-build projects. This document is a guide for making standards-
compliant design decisions that will in due course be reflected in a project
specification.
D. In addition to the telecommunications specifications for a project, plan drawings,
schematic diagrams, and details shall also be produced by the Designer, in
conformity with the guidelines contained in the TDDG.
E. The following diagram (Figure 1) depicts the relationships between the
ANSI/TIA/EIA Standards, the BICSI Design Guidelines, the GSA TDDG, and the
project-specific Construction Documents. Telecommunications distribution
infrastructure at GSA facilities shall be designed based on the BICSI design
guidelines (the TDMM, the OSPDRM, and the ITSIMM) and compliant with the
ANSI/TIA/EIA Standards as applied by and illustrated in the GSA TDDG.

1The BICSI TDMM is widely considered to be the industry reference text for the design of standards-compliant
telecommunications distribution systems (see http://www.bicsi.org/manuals.htm ). BICSI, 8610 Hidden River Pkwy,
Tampa, FL 33637-1000 USA; 1-800-242-7405; http://www.bicsi.org

Telecommunications Distribution Design Guide [ Version 8 ] 12


1 Preface

FIGURE 1: THE DESIGN PROCESS

F. The TDDG provides guidelines for telecommunications distribution system


design for use within a building for all telecommunications, low voltage, and
signal systems as related to:
• Telecommunications Spaces – Entrance facilities, equipment rooms, and
telecommunications rooms
• Intra-building Backbone Distribution – Pathway and raceway requirements,
telecommunications media requirements
• Horizontal Distribution – Pathway and raceway requirements,
telecommunications and low voltage media requirements, requirements for
special work areas
G. This document provides directions for making standards-compliant design
decisions that will ultimately be reflected in Construction Documents. The
Construction Documents for a project will be comprised of drawings and a
specification that properly incorporates telecommunications infrastructure within

13 Telecommunications Distribution Design Guide [ Version 8 ]


Preface 1
a project. The TDDG shall be used to guide the development of content in
project-specific Drawings Specifications.
H. Adherence to and compliance with the latest versions and addenda of the codes,
standards, and industry practices listed below, along with the GSA requirements
contained in this document, is mandatory. Please note that when new versions
of industry standards are released (independent of GSA’s actions), conflicts
between the TDDG and the new standards version may result. It will require
some time for GSA IT to review the new standards and update the TDDG.
Therefore, when conflicts are discovered, please seek guidance from the GSA IT
ITS.
• National Electrical Safety Code, American National Standards Institute C2
• National Electrical Code (NEC), National Fire Protection Association (NFPA
70)
• Manual of Practice, Firestop Contractors International Association (FCIA)
• ANSI/TIA/EIA 568-C series – Commercial Building Telecommunications
Standards
• ANSI/TIA/EIA 569-C series – Telecommunications Pathways and Spaces
• ANSI/TIA/EIA 606-B series – Administration Standard for
Telecommunications Infrastructure
• ANSI/TIA/EIA 607-B series – Generic Telecommunications Grounding
(Earthing) and Bonding Requirements for Customer Premises
• ANSI/TIA/EIA 758-B series – Customer-Owned Outside Plant
Telecommunications Infrastructure Standard
• ANSI/TIA/EIA 862-A – Building Automation Systems Cabling Standard
• NISTIR 6392 – GSA Guide to Specifying Interoperable Building Automation
and Control Systems Using ANSI/ASHRAE Standard 135-1995, BACnet
• ANSI/TIA/EIA 942-A – Telecommunications Infrastructure Standard For Data
Centers
• ANSI/BICSI 005-2013 – Electronic Safety and Security (ESS) System Design
and Implementation Best Practices
• TIA/EIA 455 (Series) – Standard Test Procedures for Fiber Optic Systems
• TIA/EIA 526 (Series) – Optical Fiber Systems Test Procedures
• IEEE 802.3 (Series) – Ethernet
• IEEE 802.11 (Series) – Wireless LANs
I. All references to the following manuals within the TDDG shall specifically
address only the editions specified below. Newer editions shall be used “for
reference only” until authorized by GSA in writing or through a revised edition of
the TDDG:
• BICSI Telecommunications Distribution Methods Manual (13th Edition)
• BICSI Outside Plant Design Reference Manual (5th Edition)
• BICSI Information Transport Systems Installation Methods Manual (6th
Edition)
J. Requests to deviate from the GSA requirements may be submitted on a case-by-
case basis. No deviation from the requirements of the National Electrical Code

Telecommunications Distribution Design Guide [ Version 8 ] 14


1 Preface

will be allowed. For further information regarding codes and standards, please
refer to Appendix A in the BICSI TDMM as well as the BICSI OSPDRM
Bibliography.
K. Where conflicts may arise between industry standards, Codes, GSA’s standards,
and the requirements of the local Authority Having Jurisdiction, the most stringent
requirements shall apply.
L. The requirements contained in the TDDG are considered to be in addition to the
requirements in the Facilities Standards for the Public Buildings Service (PBS
P100-2016). Where a specific requirement differs, the conflict shall be brought to
the attention of the GSA PBS Project Manager for resolution.
• While the entire P100-2016 document has important content, Sections 6.5.8
through 6.5.11 contain content specifically related to telecommunications.

1.4 Document Structure


The TDDG is organized in six sections:
1. Preface
2. GSA Telecommunications Policies
3. Project Procedures
4. Design Criteria
5. Construction Document Content
6. Appendices
A. The Preface (this section) describes this document, its intent, and its relationship
to industry standards, practices and the various audiences affected by the
document. It also describes how to use this document.
B. The GSA Telecommunications Policies section applies specifically to GSA
personnel. It describes internal GSA telecommunications policies, requirements,
standard practices, and processes for designing, installing, and operating
telecommunications infrastructure. GSA personnel should also be aware of the
instructions, requirements, and guidelines for Designers contained in the other
sections of this document, with respect to their application on both large-scale
telecommunications distribution projects and small-scale “moves/adds/changes”
(MAC) projects. In addition, these requirements apply to in-house operations
and maintenance of existing telecommunications distribution systems.
C. The Project Procedures section describes the required qualifications for
telecommunications Designers, as well as the procedures that Designers must
follow when working on telecommunications infrastructure projects at GSA
facilities. It includes activities that are required throughout the project as well as
phase-specific requirements.

15 Telecommunications Distribution Design Guide [ Version 8 ]


Preface 1
D. The Design Criteria section serves two purposes. The first is to describe the
general requirements for GSA telecommunications infrastructure, along with the
typical features required for different categories of building spaces and
construction types. The second purpose is to place limitations on the materials
and methods described in the BICSI TDMM. While the TDMM describes many
materials and methods that are generally accepted in the industry for providing
telecommunications infrastructure, GSA facilities have some unique
characteristics that impose limitations on some of the materials and methods that
otherwise might be acceptable. Some of the practices discussed in the TDMM
are expressly prohibited in GSA facilities.
Generally speaking, if the BICSI TDMM does not describe a particular material or
method for use with telecommunications distribution infrastructure, it will not be
allowed for GSA facilities unless specifically requested and pre-approved. In
addition, the GSA TDDG places further restrictions on the use of some materials
and methods that the BICSI design guidelines support.
E. The Construction Document Content section defines the minimum level of
detail that GSA requires to be present in the telecommunications portion of the
Construction Documents for a project. In this section, the required types of
details, as well as the content in the details, are both described. This section
also briefly describes the specifications that are required for a project.
F. The Appendices section provides example forms and diagrams that are required
for GSA telecommunications infrastructure designs.

1.5 Construction Type


For the purposes of this document, construction projects are categorized by the extent of
the construction work, as follows:
Construction Type Definition
New Construction A new building
Modernization An existing building undergoing extensive remodeling,
frequently including reallocation of internal spaces
Minor Remodel An existing building undergoing adjustments to
(workspace remodel) office/work spaces. The project typically does not
include changes to building systems (HVAC, electrical,
etc.).
Telecommunications-only Projects involving minor remodeling to create
telecommunications spaces and the installation of
telecommunications infrastructure
Moves, Adds, and Projects involving very limited adjustments to the
Changes telecommunications infrastructure
Historical Building Changes made to buildings that are designated as
Remodel historical properties.

Telecommunications Distribution Design Guide [ Version 8 ] 16


1 Preface

Unless otherwise stated, the guidelines defined in the TDDG apply to all five types of
construction and to areas that GSA occupies within GSA-owned and leased facilities.
Historical Building Remodel projects will qualify as multiple construction types, for
example:
• Historical Building Remodel + Modernization
• Historical Building Remodel + Minor Remodel
• Historical Building Remodel + Telecommunications-only
The Designer shall assume that adherence is required to BICSI guidelines, referenced
industry standards, and the TDDG (unless specifically indicated otherwise) for all facility
types and for all extents-of-construction. Where exceptions are permitted, this document
will specifically highlight the construction type where GSA’s requirements may differ from
generally applicable practices and standards.
Adherence to applicable code is always required.

1.6 Building Types


The requirements described in this document apply to all building types. Where
specifically noted for Warehousing/Stores facilities, some of the requirements may be
relaxed.

1.7 Tenant Specific Requirements


The requirements described in this document apply only to spaces and systems for
which the GSA IT has stewardship. Some departments within GSA may have their own
telecommunications standards. The Designer shall communicate with each GSA
department that will occupy space in the building to request and receive the
requirements for telecommunications infrastructure in spaces and for systems under
their stewardship.
Other non-GSA tenants may also occupy space in a building. The Designer shall inquire
whether a facility will serve non-GSA tenants, and if so, shall work with the GSA PBS
PM to obtain tenant-specific telecommunications infrastructure requirements for non-
GSA tenants.

17 Telecommunications Distribution Design Guide [ Version 8 ]


Preface 1

1.8 GSA Departments


The following is a partial list of the departments within the General Services
Administration (GSA) with which the Designer may be required to communicate and for
whom telecommunications infrastructure may need to be designed:
• Office of the Chief Information Officer (GSA IT)
• Federal Acquisition Services (FAS)
• Public Building Services (PBS)
• Inspector General (IG)
• Office of General Counsel (OGC)

1.9 GSA Personnel


The following is a list of the GSA personnel who have authority over or responsibility for
the telecommunications infrastructure in GSA facilities:
A. GSA PBS PM: Public Building Services Project Manager
• Responsible for the overall project, as it relates to the structure and
serviceability of the building as a whole.
• Authorized to make final decisions for project-related issues related to the
structure and serviceability of the building as a whole.
B. GSA PBS Building Manager:
• Responsible for the operation and maintenance of an existing building.
• The Designer may need to obtain as-built information from this individual
regarding an existing building that will be remodeled or will receive new
telecommunications infrastructure.
C. GSA IT ITS: GSA IT Information Technology Specialist
• Assigned on a project-by-project basis.
• Serves as the local IT specialist, having familiarity with the building, its
resources, history, and operations.
D. GSA IT Tech PM: GSA IT Technology Project Manager
• Serves as the Designer’s main point of contact within GSA for
telecommunications infrastructure guidance.
• Responsible for the telecommunications aspects of a project.
• Authorized to interpret the TDDG and to make decisions affecting the
telecommunications infrastructure on a project.
• Coordinates with the GSA IT ITS infrastructure-related communication on
capital projects.

Telecommunications Distribution Design Guide [ Version 8 ] 18


1 Preface

• Ensures that relevant GSA management and specialized technical staff are
kept informed and involved in all telecommunications-related aspects of a
project (design, construction, support, and maintenance).
• Ensures that the installed telecommunications infrastructure meets GSA
standards and that the requirements of the TDDG are enforced.
E. GSA IT TD: GSA IT Telecommunications Designer
• Designs smaller telecommunications projects without the involvement of a
consultant.
F. GSA Network Operations Branch Manager:
• Responsible to participate in the specification process (types, quantities,
styles, makes-and-models) for network electronics and wireless networking
required for internal GSA operations. This in turn will guide the decisions
affecting the telecommunications infrastructure that will be required for
specific application objectives. Quantity, type (pizza box, chassis switch),
WAPs, style, make/model, etc. Aids in the design process to help create a
cooperative infrastructure.
G. GSA Circuits Management Branch:
• Responsible to participate in the specification process (types, quantities,
bandwidths, protocols) for wide area network (WAN) circuits required for
internal GSA operations. This in turn will influence the network electronics
specifications and will guide the decisions affecting the telecommunications
infrastructure that will be required for specific application objectives.

1.10 Key Terms and Abbreviations


The TDDG uses many terms and abbreviations that are common in the
telecommunications industry. While a glossary is included in Appendix 6.8 at the end of
this document, please refer also to the Glossary in the BICSI TDMM for further
information.
A/E Architect/Engineering design team
FAR Federal Acquisition Regulation http://www.gsa.gov/far
POE Power over Ethernet
RCDD Registered Communications Distribution Designer http://www.bicsi.org
RITP Registered Information Technology Professional http://www.bicsi.org
SCS Structured Cabling System: telecommunications cabling, connectors,
patch panels, etc., which, when installed in a building, constitute its
structured cabling system.

19 Telecommunications Distribution Design Guide [ Version 8 ]


Preface 1

This page intentionally left blank

Telecommunications Distribution Design Guide [ Version 8 ] 20


2
GSA Telecommunications Policies

This section describes internal GSA telecommunications policies, requirements,


standard practices, and processes associated with designing, installing, maintaining, and
operating telecommunications infrastructure. It is directed toward an audience of GSA
personnel, including GSA IT personnel, PBS personnel, building maintenance
personnel, and any others that may be involved in these activities at a GSA facility.
A. GSA personnel designing telecommunications infrastructure for GSA facilities
shall follow the requirements in this document.
B. Input from the GSA IT Tech PM must be incorporated when developing the initial
and ongoing construction schedules. This input is especially important when an
early or phased turn-up of buildings is required, but is also vital for the initial
startup of a new facility. The telecommunications rooms, Regional Information
Centers, backbone pathways and cabling are all critical path items required for
bringing buildings online within schedule.
C. Management of GSA’s Enterprise Network is the responsibility of the GSA IT
Network Operations (NetOps) personnel, who cooperate in the specification
process (types, quantities, styles, makes-and-models) for network electronics
and wireless networking required for internal GSA operations at all GSA facilities.
NetOps works in conjunction with the Circuits Management Branch.
• At some GSA facilities, network documentation does not exist, is incomplete,
or has not yet been updated to reflect recent changes. While GSA IT is
currently working to improve the library of network documentation at each

21 Telecommunications Distribution Design Guide [ Version 8 ]


GSA Telecommunications Policies 2
facility, anyone relying upon this documentation for a project shall be
responsible to verify that it is sufficiently accurate for their purposes.
• When using GSA IT’s existing network documentation for a new project, there
is no guarantee that the documentation will (in its current condition) be
suitable for that project. Users of GSA IT network documentation shall be
responsible to investigate and update the documentation to meet their needs.
Project Managers shall include scope in their projects to prepare or update
the documentation to meet the needs of their projects.
D. GSA’s GSA IT Information Technology Specialists are responsible for the
installation and support of LAN hardware, data telecommunications, and VOIP
network systems, as well as certain enterprise network hardware and software.
E. The responsibility for provision and procurement of IT services, hardware,
software, and related products is project-dependent. The responsible
Department or Division will be accountable for ensuring that the procurements
meet GSA technology standards and that the procurement process is conducted
in compliance with federal procurement guidelines, GSA policy, delegated
authority, and statutory requirements. The Designer shall inquire on each project
to determine who has this responsibility.

2.1 GSA Personnel


2.1.1 GSA Personnel Installations
A. GSA personnel (or representatives) who install telecommunications pathway and
cabling infrastructure at GSA facilities must be familiar with the requirements of
this document. They should also have a current copy of, be familiar with, and
adhere to the guidelines in the BICSI TDMM and this document.
B. Telecommunications pathway work shall be done in accordance with the
requirements of the NEC. Prior to constructing telecommunications pathways, a
Registered Communications Distribution Designer (RCDD) shall be contracted to
prepare drawings and specifications for the project. The RCDD shall also be
contracted to periodically observe the work while in progress and upon
completion, providing written observation reports following each visit. The RCDD
shall also be contracted to produce as-built drawings bearing the RCDD’s stamp
and signature. (For more information, see Section 2.7.7 – Telecommunications
Administration, below.) GSA’s objective is that telecommunications infrastructure
be:
+ Properly installed
+ Properly tested
+ Properly documented
C. Cabling system manufacturers may provide training for GSA personnel who will
install or modify telecommunications infrastructure. In addition, GSA strongly
encourages GSA personnel to obtain training in telecommunications

Telecommunications Distribution Design Guide [ Version 8 ] 22


2 GSA Telecommunications Policies

fundamentals from BICSI prior to installing or modifying telecommunications


infrastructure. GSA personnel should inquire whether a given manufacturer
offers this training.
D. Any penetration created by a telecommunication pathway through fire walls, fire
barriers, fire partitions, smoke barriers, and smoke partitions shall meet the
requirements in the International Building Code (IBC) and any applicable
requirements in the PBS-100, which may exceed the IBC requirements.
E. At the commencement of each project, it is suggested as a good practice that
project managers coordinate with the PBS Building Manager responsible for that
building. The PBS Building Manager may be aware of other projects that are
underway, and might offer helpful logistical insights or identify other building
conditions that can affect choices and decisions.

2.2 Initiating New Projects – General


The following information is provided as guidance to any GSA department desiring
telecommunications or low voltage additions to facilities, or who will be involved in
projects requiring such infrastructure.

2.2.1 New Construction


New construction projects shall include telecommunications infrastructure designed and
installed in accordance with the requirements of this document.

2.2.2 Modernization of Existing Structures


GSA facilities undergoing modernization projects shall incorporate telecommunications
infrastructure in the project, designed and installed in accordance with the requirements
of this document. A GSA IT ITS shall be included in the initial development of the
project scope to determine the extent of any required telecommunications infrastructure
upgrades.

2.2.3 Minor Remodel (workspace remodel)


GSA facilities undergoing minor remodel projects (typically to make adjustments to
accommodate workspace/office arrangements) shall incorporate telecommunications
infrastructure in the project, designed and installed in accordance with the requirements
of this document. A GSA IT ITS shall be included in the initial development of the
project scope to determine the extent of any required telecommunications infrastructure
upgrades.

2.2.4 Upgrading Telecommunications Infrastructure to


Support New Technology
GSA will occasionally install new systems (voice, data, video, etc.) at a facility where the
existing telecommunications infrastructure may be inadequate for the new application.

23 Telecommunications Distribution Design Guide [ Version 8 ]


GSA Telecommunications Policies 2
GSA IT will verify whether the existing infrastructure is adequate to support the new
system(s) and will make recommendations for upgrading the infrastructure where
necessary. Any upgrades made to the telecommunications infrastructure shall meet the
requirements of the TDDG.

2.2.5 Upgrading Telecommunications Infrastructure to Meet


New Standards
There is not a requirement to upgrade existing telecommunications infrastructure at any
GSA facility simply to meet industry standards or the requirements of this document.
However, infrastructure upgrades may be required to correct code violations or to meet
system performance requirements.

2.2.6 Infrastructure to Support Other Tenants at GSA


Facilities
Most GSA facilities host tenants that are not GSA operations. The GSA TDDG does not
address telecommunications cabling infrastructure to support other tenants. It is
possible that other tenants may wish to adopt GSA’s TDDG (this document). Otherwise,
the tenants will need to provide guidance regarding the telecommunications
infrastructure required to meet their needs.

2.2.7 Damage to Existing Telecommunications


Infrastructure
A. Construction, maintenance, and other activities may result in damage to existing
telecommunications infrastructure, including cabling.
B. In the event of damage to telecommunications infrastructure, regardless of the
cause or party responsible, GSA personnel shall immediately contact GSA IT,
who will determine the repair or replacement strategy for the damaged
infrastructure.
C. The GSA IT ITS shall:
• Work with GSA staff to identify any potential methods of temporary/interim
repairs.
• Identify the steps necessary to assess whether the damaged infrastructure
can be repaired or whether it must be replaced.
D. The party responsible for the damage to the telecommunications infrastructure
shall be responsible for the total cost of all temporary/interim repairs and all
replacement costs.
All damaged infrastructure shall be restored so as to be within the scope of the original
design/installation parameters. This shall include (but not be limited to) all repair or
replacement work performed by certified contractors of GSA’s choosing, and all testing
and recertification of the infrastructure for full compliance with GSA’s
Telecommunications Standards and applicable SCS warranty.

Telecommunications Distribution Design Guide [ Version 8 ] 24


2 GSA Telecommunications Policies

2.3 Initiating New Projects – Specific


All telecommunications infrastructure activity, regardless of the size or scope of the
project or quantity of cable involved, must have either prior written approval from, or
include prior notification to, the GSA IT ITS to proceed with the design and/or
installation. The requirement to contact the GSA IT ITS applies even to small projects,
so that the documentation can be updated to reflect the work being done. This includes
the following types of projects:
• New construction.
• Renovation of existing structures.
• Upgrading telecommunications infrastructure to support new technology.
• Upgrading telecommunications infrastructure to meet new standards.
• Infrastructure to support other agencies or tenants at GSA facilities.
• All moves, adds, and changes (MACs) at GSA facilities, including MAC work
performed by GSA personnel.
• Low voltage cabling to support proprietary systems that will use the
telecommunications infrastructure (pathways and spaces) as identified in
Building Automation Systems Cabling Standard (ANSI/TIA/EIA-862-A).
It is required that the GSA IT ITS be consulted prior to any planned infrastructure moves,
adds, or changes to determine if existing infrastructure may be adequate, or if efforts can
be coordinated with other planned or proposed work. Please initiate contact by emailing
[email protected]. The following specific requirements apply:

2.3.1 Telecommunications Room Work


Any GSA department that is planning the installation of cabling or equipment in any
Telecommunications Room must coordinate the installation with the GSA IT ITS prior to
commencing work, regardless of the type of cabling or equipment to be installed. This
coordination is intended to assure efficient use of existing space, and to ensure that
resources/spaces planned for future projects are not inadvertently lost due to other
uncoordinated equipment.

2.3.1.1 Telecommunications Room Design Parameters


When considering the budgeting requirements for a new project, the following items shall
be included for each telecommunications room (TR):
• TRs should be located centrically within the areas they serve.
• Each rack in a TR will support a maximum of 384 cables. Typically, modular
furniture offices (cubicles) require an average of 1.25 cables each, and
hardwall offices require 4 cables (2 outlets with 2 cables each). TRs shall be
sized to hold the required rack space and provide appropriate accessibility.
See TDDG Section 4.5 – Horizontal Distribution Systems for further
information.
25 Telecommunications Distribution Design Guide [ Version 8 ]
GSA Telecommunications Policies 2

• TR doors shall swing out of the room.


• For some new construction projects, a TR often requires its own technical
power panel inside the telecommunications room. The technical power panel
should be fed from a centralized uninterruptible power supply.
• For remodel projects where work on the electrical power distribution system
may be limited, it may be sufficient to supply power to the TRs from dedicated
circuits out of panels that do not serve loads that are electrically noisy. The
electrical engineer shall evaluate the appropriate solution for this situation.
• TRs should be designed such that the environmental conditions are kept
within a temperature range of 64 to 81 degrees, in compliance with ANSI/TIA-
569-C. Achieving this requirement commonly requires air conditioning
systems, although in some cases an exhaust fan might be adequate. In
cooler climates, cooling with outside air is encouraged. Since this is a year-
round requirement, it may not be sufficient to rely upon building cooling
systems that operate only during the summer. Wherever heat loads are
relatively small, it is often sufficient to ventilate the room without providing
mechanical refrigeration.
+ RICs require humidity control. Humidity is not typically controlled in a TR.
+ The desirable range is between 45% and 55% relative humidity.

• Environmental monitoring and real-time reporting shall be incorporated in all


telecommunications rooms, in accordance with the Environmental Monitoring
for IT Spaces (EMITS).
• All telecommunication rooms and technical spaces defined in this document
shall be protected by a wet-pipe sprinkler system that is designed and
installed in accordance with the requirements in PBS P100-2016 Section 7.8,
including the use of sprinkler guards.
• Backbone cabling shall be 50-micron multimode fiber optic cabling and copper
backbone cabling.

Telecommunications Distribution Design Guide [ Version 8 ] 26


2 GSA Telecommunications Policies

Example telecommunications room floor plan sizing:

FIGURE 2: TELECOMMUNICATIONS ROOM


FLOOR PLAN SIZING

For more detailed examples of telecommunications room arrangements, please see


Appendix 6.2.

2.3.2 Horizontal Cabling


Any GSA department requiring changes or additions to horizontal infrastructure shall
contact the GSA IT ITS. No horizontal infrastructure shall be installed in any GSA facility
without the GSA IT ITS approval. This includes the installation of any other low voltage
infrastructure using the telecommunications pathway/media.

2.3.3 Regional Information Center (RIC)


Regional office buildings shall be designed to include a “Regional Information Center”
(RIC) to support local operations and field offices in that region. A RIC is essentially an
upsized main telecommunications room (MDF) with support functions that wouldn’t exist
in a regular MDF. Power and cooling requirements are more demanding in RICs.
See Section 4.18 – Regional Information Centers and Data Centers for further
information.

27 Telecommunications Distribution Design Guide [ Version 8 ]


GSA Telecommunications Policies 2

2.4 Procurement and Installation Policy


A. The primary responsibility for the management and use of information systems,
telecommunications, and information technology equipment, software, and
services rests with each Department head. Equipment is defined as machines,
devices, and transmission facilities used in information processing, such as
computers, VOIP telephones, and cables. This section highlights certain
procurement policies applicable to the telecommunications infrastructure.
Readers shall consult the FAR for further information.
B. There are two general methods used for the procurement and installation of the
telecommunications infrastructure. In larger construction projects, the
telecommunications infrastructure installation might either be part of the general
construction contract or it could be a separate contract.
C. Use of a GSA IT Blanket Purchase Agreement (BPA) may apply to a given
project. Contact GSA IT for further information.
The following policies and procedures apply to the planning and management of
telecommunications infrastructure installation as a separate project (apart from other
remodeling or new construction work):

2.4.1 Procurement Policy for Information Technology


Infrastructure
2.4.1.1 GSA Information Technology Services Approval
GSA procurement and installation of telecommunications infrastructure must have the
prior approval of GSA IT to achieve consistent and competent technical design in
compliance with the TDDG and with federal procurement requirements. Requests for
approval shall be submitted to the GSA IT Department and will be forwarded to the
appropriate internal division for action. Requests for approval must include a description
of the procurement and installation procedures and must also identify the following:
• Source of funding.
• RCDD Designer for design services (if appropriate).
• RCDD for construction observation services (optional).
• Structured Cabling System (SCS) cable installer (typically known after bid
selection).
The procurement process itself is governed by the FAR.

2.4.1.2 Cabling Infrastructure Materials


Standardization on a cabling infrastructure product line permits GSA personnel to be
familiar with the installed infrastructure components at all facilities, and helps them to be
prepared to handle moves, adds, and changes to the infrastructure in an efficient
manner. Standardization also ensures that there will be performance compatibility with

Telecommunications Distribution Design Guide [ Version 8 ] 28


2 GSA Telecommunications Policies

the installed base when additions are made to the infrastructure, and that spare parts
and components from one facility can be used at other facilities as needed. Finally,
product standardization allows GSA to manage and benefit from consistent warranty
coverage at all GSA facilities.

2.4.1.2.1 Structured Cabling System


A. Where additions are made to existing facilities, the design shall specify the use
of cabling materials from the same manufacturer whose cabling exists in the
building, as long as the existing cabling was produced by an approvable
manufacturer.
B. The telecommunications infrastructure design for new facilities shall be based
upon the SCS products from an approvable manufacturer.

2.4.1.2.2 Approvable SCS Manufacturers


GSA only accepts cabling materials from manufacturers that are approved through the
GSA contracting process. The following criteria are key factors in designating
approvable manufacturers and materials:
A. The materials shall be UL Listed.
B. The materials shall comply with Industry Standards.
C. The materials shall be compliant with the Federal Acquisition Regulation (FAR).
D. The company shall manufacture its own products (cabling and connecting
hardware). Using cabling from one manufacturer and connectors or patch panels
from a different manufacturer is not approvable, unless the manufacturers have
established a publicly recognized cooperative alliance and offer a joint warranty.

2.4.1.2.3 Approvable SCS Materials


GSA only accepts cabling materials that meet the following criteria:
A. The materials shall be manufactured by an Approvable Manufacturer (see
above).
B. The materials shall be in new, original-manufacturer packaging.
C. The materials shall not be remanufactured, refurbished, recertified, or reused in
any way.
D. The materials shall not be “gray-market,” meaning that they shall be procured via
the manufacturer-intended distribution channels.

2.4.1.2.4 Manufacturer 20-Year Warranty


A. The structured cabling system manufacturer must provide a 20-year (minimum)
warranty and must require contractor certification under stringent requirements
that will ensure a high quality installation. The manufacturer must honor the
warranty regardless of the longevity of the installation contractor. In the event
that warranted cabling or terminations fail to perform as warranted, the

29 Telecommunications Distribution Design Guide [ Version 8 ]


GSA Telecommunications Policies 2
manufacturer must replace underperforming portions of the cabling system at no
charge to the Owner for either materials or labor.
B. Where multiple manufacturers have established a publicly recognized
cooperative alliance for the purpose of using cabling from one manufacturer and
termination materials from another manufacturer, the manufacturers shall
demonstrate that their materials cooperatively comply with Industry Standards.
The entire system shall be warranted by the manufacturers under a joint warranty
(as if the materials were provided by a single entity) subject to the requirements
discussed above.

2.4.1.2.5 Installation Contractor 1-Year Warranty


A. In addition to the twenty-year minimum warranty required of all involved
manufacturers, the installation contractor shall be required to provide a 1-year
warranty covering workmanship and craftsmanship, ensuring that the system is
installed in compliance with Industry Standards, manufacturer requirements, and
the requirements of the construction contract.

2.5 Telecommunications Projects


Depending on the size and scope of a project, the GSA IT Telecom Project Manager,
working with GSA PBS, will determine whether an engineering firm or contractor is
required to develop a telecommunications distribution design.

2.5.1 Externally Designed


Externally designed telecommunications infrastructure installation may be handled as
stand-alone projects to prepare for the installation of new technology. They may also be
accomplished as separate projects, running concurrently with another capital project.

2.5.1.1 Design Philosophy


A. An engineered telecommunications design is required for all new construction,
modernization, or minor remodeling, including technical specifications and
drawings to be used as the basis for competitive bidding for the construction
contract.
B. GSA requires the use of a Registered Communications Distribution Designer
(RCDD) to design the telecommunications distribution infrastructure for all new
construction, modernization, and major telecommunications upgrades at GSA
facilities. The RCDD designation is recognized worldwide as indicating a design
professional that has met specific professional design experience requirements
and has successfully completed an extensive examination on the subject of
telecommunications distribution design. RCDDs are employed by architectural
and engineering firms, and also by telecommunications infrastructure installation
Contractors.

Telecommunications Distribution Design Guide [ Version 8 ] 30


2 GSA Telecommunications Policies

C. Telecommunications infrastructure shall be designed and installed in accordance


with applicable codes and industry standards. Due to the unique physical
characteristics of many GSA facilities, some technical design solutions are better
suited than others. This document identifies which design solutions are
appropriate for, as well as approved for, common types of buildings and areas at
GSA facilities.
D. Telecommunications infrastructure design shall be incorporated during the
preliminary design phase of each project. This will provide GSA IT the
opportunity to influence the design from the start and address
telecommunications requirements at appropriate points in the design process. It
is imperative that the A/E firm and their RCDD work closely with the GSA IT ITS,
the GSA IT Technology Project Manager, and the GSA PBS Project Manager
from the start of each project.

2.5.2 Internally Designed Telecommunications Projects


A. For small projects, a GSA IT Telecommunications Designer may be selected to
prepare a design internally (without the use of outside engineering).
B. For small projects or installation of additional cabling, a manufacturer-certified
installation contractor may be hired for a limited-scope installation. The
contractor must be currently in good standing with the manufacturer, with the
ability to provide the required warranties.
The alternative to using a certified contractor (for copper cabling installation only)
is to use BICSI-trained GSA personnel. (See Section 2.7.3 – Manufacturer-
Certified Installation below for further information.) There shall be no exceptions
to this requirement.

31 Telecommunications Distribution Design Guide [ Version 8 ]


GSA Telecommunications Policies 2

2.6 Reviewing Telecommunications Designs


2.6.1 Standards Variance Requests (SVR)
A. Requests to deviate from industry standards or GSA design solutions will be
considered on a case-by-case basis. Any request to deviate from the
requirements of the National Electrical Code will not be accepted.
B. Requests to apply alternative design solutions shall be submitted to the GSA IT
Tech PM for consideration. The SVR will follow the review process as shown in
the flow chart in Appendix 6.7. Approval will only be granted in writing, and must
be authorized by the GSA IT Tech PM, or GSA IT ITS. Approval must also be
authorized by the GSA PBS Project Manager if capital funding is involved.
C. For more information, see Section 3.3.2 – Standards Variance Request (SVR) in
this document.

2.6.2 Design Review


A. Project milestones will be designated by GSA for each project and in some cases
may not follow conventional patterns. The GSA IT Design Review process will
mirror the milestones established for the project. For the purposes of describing
the Design Review Process, a common project structure is used in TDDG
Section 3.5 – Design Review Process. The process should be adapted to reflect
the milestones established by GSA for each specific project.
B. The following is a partial list of the people who should participate in the Design
Review Process:
• GSA IT Tech PM
• GSA IT ITS
• GSA-selected RCDD Review Consultant (optional)
• Architect/Engineer (Prime Consultant)
• Designer
• GSA PBS PM
• GSA PBS Fire Protection Engineer
• GSA PBS Building Manager
C. For more information, see TDDG Section 3.5 – Design Review Process.

Telecommunications Distribution Design Guide [ Version 8 ] 32


2 GSA Telecommunications Policies

2.7 Telecommunications Operation and Maintenance


2.7.1 GSA Telecommunications Infrastructure
Responsibilities
A. GSA IT is responsible for defining the requirements for a cable pathway between
the Entrance Facility and each telecommunications room in a building, as well as
the pathway, cabling and outlets served by those telecommunications rooms.
B. GSA IT is responsible for providing the network equipment and installing it in
racks in its telecommunications rooms.
C. The design of the Entrance Facility (EF) is not under the stewardship of GSA IT,
and therefore the TDDG does not contain guidelines concerning the EF. Contact
GSA PBS on a case-by-case basis to identify who will provide EF design
guidance.
D. It may also be necessary to provide telecommunications infrastructure to serve
other (non-GSA) tenants. The Designer shall contact each tenant and request
the requirements that will meet the telecommunications infrastructure needs of
each individual tenant.

2.7.2 Service Provider Responsibilities


The service provider is responsible for providing and installing the entrance cable up to
the demarcation point, as well as the termination hardware at the demarcation point. In
some cases, GSA contracts with the service provider to extend the demarcation point
from the EF to another location at the facility. In such cases, the service provider is also
responsible for maintenance and troubleshooting of the extended portion of the cabling
and termination hardware.

2.7.3 Manufacturer-Certified Installation


A. GSA telecommunications cabling systems are covered by a 20-year (minimum)
warranty from the cabling system manufacturer and a 1-year warranty from the
installation contractor. If any portion of the warranted cabling system fails to
perform at its original capacity, the manufacturer shall provide both labor and
materials to restore its performance.
B. To obtain this warranty coverage, the contractors who perform the installation
must be fully certified by the cabling system manufacturer. Contractors who are
manufacturer-certified will have met certain requirements established by the
manufacturer (including copper and fiber optic cabling installation) giving the
manufacturer confidence as it endorses the cabling installation work of the
contractor.

33 Telecommunications Distribution Design Guide [ Version 8 ]


GSA Telecommunications Policies 2

2.7.4 GSA Telecommunications Technicians


A. To preserve the 20-year (minimum) manufacturer warranty, GSA personnel who
may be modifying warranted telecommunications cabling systems shall also be
certified by the manufacturer, through training courses and working with a local
manufacturer’s representative.
In addition to cabling manufacturer training, GSA also strongly encourages GSA
personnel or their designated representatives who install, move, or make changes to
telecommunications cabling to receive ITS Installer 1 (IN101), ITS Installer 2 Copper
(IN225), and ITS Installer 2 Optical Fiber (IN250) training from BICSI 2. Cabling
installations performed by GSA personnel must be tested in accordance with
manufacturer requirements, and may also be inspected by an RCDD as discussed in
Section 3.4.5 – Construction Observation.

2.7.5 Moves, Adds, and Changes


A. Moves, adds, and changes (MACs) to the telecommunications infrastructure shall
be performed in accordance with the requirements of this document. This
includes (but is not limited to) all copper or fiber optic cables for the LAN, VOIP
telephones, workstation area outlets, patch panels, patch cords, etc. All MACs
must be coordinated with the GSA IT ITS.
B. Whenever moves, adds, or changes (MAC) are made, the new cabling shall
follow the routes of existing established (properly installed) telecommunications
cabling pathways. Where existing pathways are not properly installed, new
cabling shall be routed in a manner compliant with Industry Standards and GSA
Standards.

2.7.5.1 Splitting of Cable Pairs


A. In certain situations, it may be necessary to use one or two pairs of a four (4)-pair
cable to support one telephone device, and to use the remaining pairs to support
a different telephone device. In these situations, the splitting of the pairs shall be
accomplished with a line-splitting device installed on the outside of the Work
Area Outlet faceplate. In the telecommunications room, a similar line-splitting
device may be installed at the patch panel.
B. Under no circumstances will cable pairs be split or removed from the back of a
modular jack or patch panel. All four pairs of each horizontal distribution cable
must be terminated to a single eight-position, eight-conductor jack.
C. Under no circumstances will the splitting of data cable pairs be allowed. The
integrity of all four-pair cable (all eight wires) must be maintained end-to-end for
the LAN equipment.

2 As of the date of this writing, information about the ITS Installer 1 training course is available from BICSI’s website at:
https://www.bicsi.org/credential_programs.aspx This address is subject to change without notice.

Telecommunications Distribution Design Guide [ Version 8 ] 34


2 GSA Telecommunications Policies

2.7.6 Electrical Power in Telecommunications Rooms


A. Each telecommunications room (TR) shall be equipped with technical power
outlets that are dedicated for use by telecommunications equipment. Technical
power outlets shall be labeled and used exclusively for telecommunications
equipment and shall not be used for general-purpose or utility devices such as
electric drills, vacuum cleaners, coffee pots, etc.
B. Each TR will also be equipped with white, gray, or beige-colored convenience
power outlets that are available for use with non-telecommunications equipment
(one convenience power outlet per wall).

2.7.7 Telecommunications Administration


A. GSA’s telecommunications administration system is based on “records” and
“identifiers.” It documents cabling, termination hardware, patching and cross-
connection facilities, conduits, cable pathways, telecommunications rooms, and
other telecommunications spaces. ANSI/TIA/EIA-606-B – Administration
Standard for the Telecommunications Infrastructure is the industry standard for
administering and documenting the telecommunications infrastructure. The
purpose of this industry standard is to provide a uniform administration scheme
that is independent of applications, because applications may change several
times throughout the life of a building. The TDDG establishes guidelines for GSA
personnel, end users, manufacturers, installers, and facilities administrators
involved in the administration of the telecommunications infrastructure at GSA
facilities.
B. “Records” are a collection of information about each specific component of the
telecommunications infrastructure. Drawings, details, diagrams, specifications,
spreadsheets, and databases are all examples of telecommunications records.
C. Telecommunications records show unique “identifiers” for each component of the
telecommunications infrastructure. For more information about identifiers, see
TDDG Section 4.10 – Telecommunications Administration.
D. Records shall be maintained electronically in their native formats using AutoCAD
and/or MS Visio. Drawings shall be saved as AutoCAD 2015 and MS Visio 2010
version files, regardless of the version of the software that is used (newer
program versions are acceptable). Whenever AutoCAD or Visio files are
submitted, a parallel set of files printed to Portable Document Format (PDF) shall
also be submitted, as a snapshot record of the original state of those files.

“As-Built Drawings” (typically prepared by installers) and “Record Drawings”


(initially prepared by Designers based on the installer’s as-built drawings) are a
vital component of the telecommunications administration system, and must be
kept current as moves, adds, and changes take place.
See Section 5.3 – Record Drawings and Documentation for more information.
E. All GSA facilities shall maintain a system for documenting and administering the
telecommunications infrastructure. The administration system shall include cable

35 Telecommunications Distribution Design Guide [ Version 8 ]


GSA Telecommunications Policies 2
records, equipment records, as-built drawings, and record drawings (including
installation dates) for all information technology systems. The administration
system shall follow the ANSI/TIA/EIA-606-B standard.
• While the GSA IT is responsible to verify that the cable and equipment
records, record drawings, and as-built drawings are kept up to date, it is the
responsibility of the local GSA PBS representatives (using local facility
personnel) to maintain/update the telecommunications record drawings for
each facility after any construction project and to provide electronic copies to
GSA IT for storage, as well as hardcopy documents if they have been printed.
• Regional GSA IT personnel shall be responsible for storing the
telecommunications-related documentation.

Telecommunications Distribution Design Guide [ Version 8 ] 36


3
Project Procedures

A. The Project Procedures section contains guidelines for architects, engineers, and
telecommunications distribution designers regarding the procedures that GSA
requires for projects that include telecommunications distribution systems. This
applies both to projects that entail primarily telecommunications distribution work
(such as telecommunications infrastructure replacement projects) as well as to
architectural projects and other work (such as a new building or a
remodel/renovation) involving telecommunications design.
B. This section is not intended to supersede the requirements in the Facilities
Standards for the Public Buildings Service document (PBS P100-2016), but
rather to complement them, providing additional requirements that apply
specifically to telecommunications distribution design projects at GSA facilities.
C. It is intended that the requirements in this section be considered contractually
binding for design professional firms and design/installation contractors providing
telecommunications distribution design services.

3.1 Designer Qualifications


A. For the purposes of this document, the term “Designer” shall mean a Registered
Communications Distribution Designer (RCDD) who is currently in good standing
with BICSI. This means that the telecommunications design shall be produced
by the RCDD. GSA’s communications with the telecommunications consultant

37 Telecommunications Distribution Design Guide [ Version 8 ]


Project Procedures 3
shall be mainly through the RCDD. On projects where the RCDD is not the
prime consultant, the RCDD shall keep the prime consultant, the
Architect/Engineer (A/E), informed of all direct communications with GSA.
• The Registered Information Technology Professional (RITP) certification from
BICSI is not an acceptable substitute for the RCDD.
B. In addition to the RCDD certification, it is desirable that the RCDD have one or
more of the following qualifications:
• Professional Engineer (P.E.) in the electrical engineering field
• CCNA certification from Cisco
• CCNA Wireless certification from Cisco
• CTS certification from InfoComm
C. In addition, the RCDD shall have the following qualifications:
• The RCDD shall demonstrate a minimum of 5 years of experience in the
design of inside plant telecommunications distribution systems. Experience
designing telecommunications infrastructure on Federal Government projects
is desirable but not required.
• Experience not directly related to the design of inside plant
telecommunications distribution systems, such as sales and/or marketing,
project management, or installation experience, is not acceptable.
• The RCDD shall demonstrate that he/she has:
+ personally designed, or
+ personally overseen the design of a minimum of five projects similar in size
and construction cost to the current GSA project.
• The RCDD shall be independent from and unaffiliated with any manufacturer
associated with the telecommunications distribution system industry.
Manufacturers’ representatives are not considered independent or
unaffiliated.
• The RCDD shall be completely familiar and conversant with industry and
GSA telecommunications standards (this document).
D. The RCDD shall affix his/her RCDD logo stamp (showing the registration number
and expiration date) and signature to the final Construction Documents (drawings
and specifications) pertaining to the telecommunications distribution design.
E. The services of a professional engineer shall be required to design the following
aspects of a complete telecommunications infrastructure:
• Grounding and bonding
• Firestopping
• Electrical power distribution in telecommunications spaces
• Telecommunications room cooling systems
F. Under the direction of PBS, the services of a licensed fire protection engineer
shall be required to design the fire protection and life safety systems in
telecommunications rooms and technical spaces (e.g., fire suppression, fire
alarm system, etc.).

Telecommunications Distribution Design Guide [ Version 8 ] 38


3 Project Procedures

3.2 Architect/Engineer Teams


It is imperative that the telecommunications design be incorporated during the
preliminary architectural design phase. To accomplish this, the architects and engineers
on the design team shall work closely with the designated project RCDD, the GSA ITS
Telecom Project Manager, and the GSA PBS Project Manager, beginning with the
Schematic Design phase of the project.

3.2.1 Cross-Discipline Coordination


Successful telecommunications projects require frequent and thorough design
coordination between the disciplines involved in the project. The Designer shall be
primarily responsible to coordinate the telecommunications requirements and design
features with the designs produced by the other Designers on the project.
At a minimum, the following aspects of the design shall be coordinated:
• HVAC requirements for telecommunications rooms (TR).
• HVAC ductwork routing (avoiding TR ceiling spaces).
• Plumbing routing (avoiding TR spaces).
• Lighting requirements for TRs.
• Power requirements for TRs.
• Power requirements for work areas (receptacle locations near
telecommunications outlet locations).
• Proximity of cabling to sources of EMI.
• Routing of telecommunications conduits through and location of
telecommunications pullboxes in congested areas (HVAC ductwork, plumbing,
electrical, etc.).
• Floor treatments in TRs.
More information regarding the above requirements is available in Section 4 – Design
Criteria in this document.

3.3 General Procedures


3.3.1 CAD Files
The Designer shall coordinate with the A/E team to determine that the electronic CAD
files used as backgrounds for the telecommunications design are consistent with the
CAD file backgrounds used by the other disciplines on the project.
GSA has adopted the National CAD Standards. Therefore, all drawings shall be
numbered according to the National CAD Standards numbering scheme and all symbols

39 Telecommunications Distribution Design Guide [ Version 8 ]


Project Procedures 3
shall be National CAD Standards-compliant.
The Designer may wish to request copies of existing network documentation for use on
a project. At some GSA facilities, network documentation does not exist, is incomplete,
or has not yet been updated to reflect recent changes. If the documentation is available,
GSA may provide it to the Designer as a courtesy; however, GSA is not obligated to do
so. While GSA IT is currently working to improve the library of network documentation at
each facility, anyone relying upon this documentation for a project shall be responsible to
verify that it is sufficiently accurate for his or her purposes.
• When using GSA IT’s existing network documentation for a new project, there
is no guarantee that the documentation will be suitable for that project in its
current condition. Users of GSA IT network documentation shall be
responsible to investigate and update the documentation to meet their needs.
Project Managers and Designers shall include scope in their projects to
prepare or update the documentation to meet the needs of those projects.

3.3.2 Standards Variance Request (SVR)


A. It is not the intent of GSA to rigidly impose standards on every aspect of a
telecommunications system design. Each design is unique, and special
requirements may lead to situations in which deviations from the standards are
warranted.
B. This document identifies specific design solutions that are intended to meet the
technical requirements of GSA telecommunications and information technology
systems at most GSA facilities. Design issues that are not consistent with the
requirements in this document shall require prior approval through the GSA
Standards Variance Requests (SVR) process. Requests to deviate from industry
standards or GSA design solutions will be considered on a case-by-case basis.
Any request to deviate from applicable Code requirements or to deviate from
manufacturer’s warranty requirements will not be approved.
C. If the Designer feels that deviation from a given standard is warranted, the
Designer shall submit a written standards variance request to GSA. The
Designer may, upon written approval from GSA, incorporate the design deviation
into the overall design. GSA approval is required on a project-by-project basis –
the Designer shall not assume that a deviation approval for one project means
that the deviation will necessarily be approved for a subsequent project.
SVR requests shall include a complete description of the proposed alternative
design identifying:
+ The type of facility
+ The conditions at the facility
+ The approved design solution as described in this document, or as
described in the standards referenced in this document
+ The proposed alternative design
+ A list of the guidelines and standards referenced in this document with
which the alternative design will not be in compliance, and the effect of
non-compliance, both short and long term

Telecommunications Distribution Design Guide [ Version 8 ] 40


3 Project Procedures

+ The reason for requesting the alternative design


+ The Contractor or personnel performing the construction
The Designer shall provide written comments indicating that the proposed
alternative design will meet the applicable GSA system performance
requirements, and identifying any performance limitations, drawbacks and
benefits from using the alternative design.
D. The Designer shall be responsible to determine that the SVR process is properly
conducted. For projects where the Designer is not the prime consultant, the
prime consultant shall also be responsible to determine that the SVR process is
properly conducted, and shall participate in the process (review, acknowledge
and address issues) to determine that GSA’s requirements are met.
E. The SVR will follow the review process as shown in the flow chart in Appendix
6.7.

3.4 Procedures Related to Project Phases


Telecommunications projects are typically conducted in phases. In addition to the
requirements contained in the Facilities Standards for the Public Buildings Service
document (PBS P100-2016), Designers of telecommunications distribution systems for
GSA facilities have the following phase-related responsibilities:

3.4.1 Schematic Design and Fieldwork


A. Telecommunications projects at existing GSA facilities may require preliminary
fieldwork to document the existing cabling and infrastructure systems into which
the new cabling and infrastructure will integrate. GSA believes that this
information is vital to a successful project.
B. For projects that involve modifications to existing buildings, the Designer shall
visit the project site during the Schematic Design phase to perform preliminary
field investigation of the horizontal and intra-building backbone
telecommunications infrastructure. The Designer shall create the following types
of documentation based on information gathered while onsite:
• Take digital photographs of existing telecommunications rooms and work
areas that affect or are affected by the new project work.
• Verify existing or create a new riser diagram showing the existing intra-
building backbone cabling associated with the new project and the existing
cross-connection strategy.
• Investigate and document the routing of existing horizontal pathways and
cabling that are affected by the project.
• Verify existing or create new elevation diagrams of each telecommunications
rack and each wall within each TR affected by or affecting the new project
work.
• Meet with local GSA IT staff to review and validate field investigation findings
and also to gather undocumented legacy information from the experiential

41 Telecommunications Distribution Design Guide [ Version 8 ]


Project Procedures 3
knowledge of the local staff. This is not a substitute for a complete field
investigation, but rather is intended to augment the field investigation effort.
C. The Designer shall also conduct a needs analysis (involving GSA personnel) to
identify and describe the required features and functionality of the new
telecommunications infrastructure.
D. The information gathered during the fieldwork, combined with the results of the
needs analysis, shall be the starting point for Schematic Design of the proposed
new work.
E. Schematic Design documents shall show the following information:
• Building and local distribution
• Telecommunications Room sizes and locations
• Major distribution pathways
• Telecommunications Room Backboard locations
F. Upon completion of the Schematic Design documents, the standard Design
Review Process shall be conducted prior to progressing to the Design
Development phase.

3.4.2 Design Development


A. The Designer shall modify the design documents to address the review
comments received during the Schematic Design Phase.
B. During the Design Development phase, the Designer shall obtain the assistance
of manufacturer product representatives to review the project specifications to
determine that the correct part numbers have been included for each product in
the specification.
C. In addition to the content shown on the Schematic Design documents, the
Design Development documents shall show the following information:
• Schematic diagrams
• Data outlet locations and port counts for each outlet
• Power outlet types, quantities and locations
D. Upon completion of the Design Development documents, the standard Design
Review Process shall be conducted prior to progressing to the Construction
Document phase.

3.4.3 Construction Documents


A. The Designer shall modify the design documents to reflect the accepted review
comments received during the Design Development Phase.

Telecommunications Distribution Design Guide [ Version 8 ] 42


3 Project Procedures

B. In addition to the content shown on the Schematic Design and Design


Development documents, the Construction Documents shall show the following
information:
• Raceway routing plans
• Telecommunications room wall elevation details
• Rack elevation details
The Construction Documents are also expected to contain the items discussed in
Section 5 – Construction Document Content in this document.
C. It is expected that the Designer will expend considerable effort coordinating
details between different disciplines during the design process. Non-coordinated
pathway/raceway is not acceptable to GSA.
D. Upon completion of the Construction Documents, the standard Design Review
Process shall be conducted. The Designer shall then modify the documents to
reflect the accepted review comments associated with the Construction
Documents prior to the Bidding Phase.
E. Upon completion of the Final Construction Documents, the standard Design
Review Process shall be again conducted as described above. The Designer
shall modify the documents to address the review comments associated with the
Final Bid Documents prior to the bidding phase rather than “by addendum.”

3.4.4 Bidding
A. On projects where a pre-bid walkthrough is held, the Designer shall attend the
walkthrough and shall provide the bidders with a written list of materials and
practice requirements that the bidders might find peculiar and that might affect
the bids if such requirements are overlooked. Noteworthy items would typically
be requirements that are more restrictive than practices considered acceptable
for other commercial projects. The Designer shall consider the following items
for inclusion on such a list, as well as any other items applicable to the project:
• The use of flex-conduit is prohibited.
• In slab-on-grade situations, the installation of conduit under-slab or in-slab is
prohibited, unless specifically noted.
• The requirement for no more than two 90-degree bends in any conduit run.
• The fact that telecommunications standards are more stringent than electrical
installation requirements.
B. On projects where a cabling contractor will design the work, the Contractor shall
submit the following documentation with the bid, depicting what will be installed
by the Contractor:
• Material cut-sheets.
• Plan drawings of new outlets and cable routing.
• Drawings of the grounding/bonding plan (as appropriate, when required).

43 Telecommunications Distribution Design Guide [ Version 8 ]


Project Procedures 3
All drawings shall be prepared using professional design software. Drawings that
are hand-drawn sketches or produced using bitmap graphics editors shall not be
accepted.
C. During the bid evaluation process, GSA will consider the value and quality of the
materials proposed. The selection will be based in part on the following criteria:
• Price.
• Whether the proposed SCS manufacturer is the manufacturer of existing
cabling to remain in service.
• Terms and benefits of the manufacturer’s 20-year (minimum) warranty.
• Manufacturer-guaranteed performance parameters that exceed Industry
Standards.
• The perception of the SCS manufacturer’s stability and longevity.

3.4.5 Construction Observation


A. The Designer shall review the Contractor’s submittals that are required by the
Construction Documents. When the Contractor’s submittals include materials or
methods that deviate from GSA standards, the Designer shall either:
• Reject the specific materials and methods that do not comply, when the
Designer believes that they constitute undesirable solutions, or
• Pursue the Standards Variation Request process to seek separate approval
for each specific material or method that the Designer believes would
constitute a better solution, within the limitations described in the TDDG.
B. The Designer (RCDD) shall visit the construction site frequently to observe the
construction quality and progress. The Designer shall confer with the GSA PBS
Project Manager and the GSA IT PM prior to proposing services for the project to
determine an appropriate site visit frequency for the project. On average, one
site visit per week will typically be required. The site visit frequency will likely
change during the construction as the telecommunications-related activity
increases and decreases.
C. Accurate record drawings are considered critical for the efficient operation of
GSA facilities. During these site visits, the Designer shall observe and report on
the Contractor’s progress toward keeping a set of As-Built drawings current with
appropriate notations.
D. During the site visits, the Designer shall take digital photographs of existing and
new telecommunications pathways, spaces, and cabling that are related to the
project. In particular, the Designer shall photograph infrastructure that will later
be concealed during the course of construction.
E. The Designer and GSA IT representatives shall use the Construction
Observation Checklist as an aid during construction observation visits. (See
Appendix 6.1.3.).
F. After each site visit, the Designer shall submit a written report describing the
observed construction progress. Observations shall be documented in the report
with annotated digital photographs and a written description of any problems, a

Telecommunications Distribution Design Guide [ Version 8 ] 44


3 Project Procedures

description of the requirements in the Construction Documents and the resolution


to the issues. For each item requiring corrective attention, the report shall
describe the following:
• A description of the issue
• Applicable requirements in the Construction Documents
• Applicable GSA standards, industry standards, and codes
• Corrective options available to GSA
• Designer’s recommendation
G. The Designer shall submit the construction observation reports via email to the
GSA PBS PM and the GSA IT Tech PM and to [email protected] as soon
as possible following each site visit. The reports shall also be reviewed at the
next construction meeting. A timely report submission will aid the Designer and
GSA in identifying potential problems early in the construction process.
H. Cable testing shall be performed after electrical systems have been powered on
and after building operational conditions become similar to normal operations.
Also, any dust-producing construction activities shall be completed prior to any
cable testing. The intent is that testing not be done until normal operating
conditions exist (and the associated electromagnetic interference is being
generated by electrical systems in the building).
I. The Designer shall review the cable test reports produced by the Contractor for
each cable installed during the project. The Designer shall verify that the test
reports are complete and indicate passing results, as defined in TDDG Section
4.12 – Field Testing.
J. The Designer shall require that the Contractor submit weekly project progress
status reports.
K. The Designer shall require that the Contractor submit formal requests for
information (RFI) in written, electronic format.
L. The Designer shall require that the Installation Contractor’s supervisor be
certified as a BICSI ITS Installer Level 2 Copper/Fiber and also be fully certified
by the SCS manufacturer. The supervisor shall be on site full time during
construction to supervise contractor activities.

3.4.5.1 Construction Observation Checklist


A. During the Construction process, the Designer and GSA IT representatives
should visit the construction site periodically to review the quality and
completeness of the work.
B. The Designer shall use the Construction Observation Checklist during each site
visit.
C. The GSA IT Tech PM and the GSA IT ITS shall use the Construction
Observation Checklist during each site visit.
D. See Appendix 6.1.3.

45 Telecommunications Distribution Design Guide [ Version 8 ]


Project Procedures 3

3.4.6 Post-Construction
A. The Designer shall review the Operation and Maintenance information provided
by the Contractor for the telecommunications distribution system. The Designer
shall verify that information is included for each component in the
telecommunications distribution system. Upon approval of the content in the
Operation and Maintenance information, the Designer shall submit the
information to local GSA ITS Staff with written documentation indicating that the
Designer has reviewed the information and that it appears to meet the
requirements in the Construction Documents.
B. The Designer shall provide complete, accurate record drawings and record
documentation to GSA (based on as-built documents that have been “red-
lined”/marked-up by the Contractor). Record documents shall be provided in
electronic CAD format where applicable, in addition to requirements put forth by
the Designer’s contract with GSA.
• GSA IT Tech PM will review the record documents submitted by the
Designer. Any inaccuracies or incompletions discovered by GSA shall be
addressed by the Designer within 30 days of receiving review comments from
GSA.
C. The Designer shall inquire with the GSA IT Tech PM whether it would be
desirable to have a laminated set of record drawings to be stored in each TR.
Where the GSA IT Tech PM feels it would be desirable, the Designer shall
provide the laminated set of drawings as described in TDDG Section 5.3 –
Record Drawings and Documentation.
D. The Designer shall require that the cabling contractor provide cable test reports
immediately upon completion of the testing. The Designer shall review each
individual report to verify that each test was correctly performed and that each
cable passes. After the Designer reviews the reports, the Designer shall submit
the cable test reports to GSA.
E. The Designer shall verify that the cabling contractor provides the appropriate
manufacturer-backed, 20-year (minimum) warranty certification documentation to
GSA within 30 days of completing the cable testing.
F. See TDDG Section 5.3 – Record Drawings and Documentation for further
requirements.

Telecommunications Distribution Design Guide [ Version 8 ] 46


3 Project Procedures

3.5 Design Review Process


As noted in TDDG Section 3.4 – Procedures Related to Project Phases, the project
documents will pass through the design review process at the end of each design phase
plus follow-up reviews when necessary. These requirements are in addition to those
contained in the Facilities Standards for the Public Buildings Service document (PBS
P100-2016).
The design review process involves two main objectives:
• Finding undesirable conditions that are visible among the content.
• Noticing content or features that should be included, but are lacking.
To help improve the quality and thoroughness of design review, a Design Review
Checklist has been prepared (see Appendix 6.1.2). The checklist is not intended to be
all-inclusive, comprehensive, or static. The reviewer using the Design Review Checklist
is expected to draw upon his or her professional experience to completely review the
document set considering any noteworthy applicable parameters, even if those
parameters do not appear on the Design Review Checklist.
On some projects, GSA may hire an RCDD Review Consultant to act in the capacity of
an independent reviewer and consultant to GSA. The RCDD Review Consultant will be
responsible to review the overall design, paying particular attention to areas of the
design that are related to the current or future operation and maintenance of the
telecommunications system, and sometimes low voltage systems other than voice and
data. The RCDD Review Consultant will identify issues that do not appear to be
compliant with the requirements in the TDDG or other GSA Standards, appear to depart
from industry best practices, or which conflict internally within the construction document
set.
To avoid a conflict of interest in situations where GSA does not own the building, a
Review Consultant cannot work for a building owner who leases to GSA. Instead, GSA
shall contract directly with the Review Consultant so that the Review Consultant is
independent of and not influenced by the building owner.
The following steps correspond to the numbered activities shown on the Design Review
Process diagram below:
c Each time a review is required, the A/E shall provide copies of the complete
project documents set (drawings and specifications for all disciplines involved in
the project) for the following people:
• GSA PBS Project Manager (PM) (three sets)
+ GSA PBS Property Manager
+ GSA PBS Fire Protection Engineer
• GSA IT ITS (one set)
• RCDD Review Consultant (two sets)
A B
The RCDD Review Consultant will have 3, 5, or 10 days (depending on the
project phase) to review the design documents and provide written RCDD
Review Comments to the GSA PBS PM and the GSA ITS Telecom Project
Manager.

47 Telecommunications Distribution Design Guide [ Version 8 ]


Project Procedures 3
def The GSA PBS PM and the GSA IT ITS will have 5, 8, or 10 days
(depending on the project phase) to review the design documents and the RCDD
Review Consultant’s comments. The GSA IT ITS will create the GSA ITS
Review Report, and incorporate the RCDD Review Comments into the report.
Following their review, they will distribute the complete set of comments to the
RCDD Review Consultant (if present on the project) and hold brief discussions
about the comments. If there is no RCDD Review Consultant assigned to the
project:
• The GSA IT ITS will create the GSA ITS Review Report without RCDD
Review Comments.
• The GSA ITS Review Report will then be sent to the GSA PBS PM for review.
gh The GSA PBS PM will submit the RCDD Review Report to the Designer.
The Designer will then be given five days to review the comments and respond to
them in writing. Negative responses to any comment shall include a discussion
of the reasons for non-compliance.
ij Finally, a meeting or teleconference will be held with the GSA PBS PM, the
GSA IT ITS, the RCDD Review Consultant, and the Designer to discuss the
review comments and the Designer’s responses. Following the meeting, the
Designer shall revise the design in accordance with the GSA’s resolution for
each comment.
The following diagram depicts a typical telecommunications design review
process when an RCDD Review Consultant is not involved in the review process.
The number of days listed for #3 and #6 may need to be adjusted based on the
scope or depth of the telecommunications infrastructure on a project.

Telecommunications Distribution Design Guide [ Version 8 ] 48


3 Project Procedures

FIGURE 3: DESIGN REVIEW PROCESS

49 Telecommunications Distribution Design Guide [ Version 8 ]


Project Procedures 3
The following diagram depicts a typical telecommunications design review process,
including the RCDD Review Consultant’s role in the review process. The number of
days listed for #A, #3 and #6 may need to be adjusted based on the scope or depth of
the telecommunications infrastructure on a project.

Telecommunications Distribution Design Guide [ Version 8 ] 50


3 Project Procedures

FIGURE 4: DESIGN REVIEW PROCESS WITH CONSULTANT

51 Telecommunications Distribution Design Guide [ Version 8 ]


Project Procedures 3
G. The Designer shall not proceed with the next phase of telecommunications
design without receipt of written comments from the GSA IT Information
Technology Specialist.
H. The Prime Consultant shall be responsible to determine that the review process
is conducted in accordance with GSA’s requirements, and shall participate in the
review process to determine that the review comments are satisfactorily
addressed.

3.5.1 RCDD Review Consultant


For projects where GSA hires an RCDD Review Consultant, the prime consultant
(Designer or A/E) shall provide two sets of the drawings and specifications (from all
disciplines involved in the project) for the RCDD Review Consultant. The RCDD Review
Consultant will not perform any design services. The RCDD Review Consultant could
be asked to do the following:

3.5.1.1 Typical Document Review Scope


A. Review telecommunications distribution system design:
• For compliance with the GSA TDDG and Industry standards.
• To identify apparent conflicts (routing, electromagnetic interference, etc.) with
designs from other disciplines.
• To identify points of coordination between GSA and telephone service
providers or Internet service providers.
• For general document clarity.
B. Review the completed needs analysis report.
C. Review the cutover plans.
D. Prepare a report consistent with the format shown in Appendix 6.1.1 of the TDDG
that addresses at a minimum the items in the Design Review Checklist in
Appendix 6.1.2.

3.5.1.2 Other Services (upon specific GSA request)


A. On some projects, GSA may also use an RCDD Review Consultant to provide
services during the construction phase. These services may include submittal
review and “big-picture” construction observation services. In these situations
however, the Designer always remains responsible for submittal review,
construction observation, punchlist management, and other standard services as
indicated in the Facilities Standards for the Public Buildings Service document
(PBS P100-2016).
B. In these situations, the RCDD Review Consultant shall provide written comments
to GSA and to the Designer. In turn, GSA will decide how to act on the written
comments, and then direct the A/E, Designer, or Contractor accordingly. The
RCDD Review Consultant shall not, under any circumstances, give direction to
the A/E, Designer, or Contractor.

Telecommunications Distribution Design Guide [ Version 8 ] 52


3 Project Procedures

3.5.2 Design Review Checklist


A. The Designer shall use the Design Review Checklist prior to submitting drawings
and specifications at each project milestone.
B. The GSA IT Tech PM, the GSA IT ITS, and the RCDD Review Consultant shall
use the Design Review Checklist during the review process.
C. See Appendix 6.1.2.

3.6 Field Investigation Activities


Some projects may involve existing buildings where existing conduit pathways may be
considered for reuse with new cabling.
Early in the design process, the Designer shall fully investigate the existing pathways,
documenting the entire pathway, all changes in direction, all junction boxes, and pull
points. This is an important task, because existing pathways in old buildings are
commonly constructed without consideration of modern telecommunications standards.
Without a complete investigation, the design may attempt to reuse conduits that have
too many bends, have been constricted (flattened by bending) or have improperly
installed junction boxes, all of which may damage new high-performance cabling which
the conduits were not originally designed to support.
Conduits that are determined not to be compliant with GSA’s standards shall be either
de-rated (reduced cable carrying capacity or distance), modified (pull points added, bend
radii increased) or not used.

3.7 Designing for Demolition


Some projects may involve existing buildings that require the demolition of existing
telecommunications cabling and components.

3.7.1 Site Specific Code Requirements


The Designer shall clearly understand the site-specific, Code-based requirements for
demolishing cabling and components that are no longer in use, and shall communicate
these requirements to GSA.

3.7.2 Salvage Objectives


The Designer shall inquire with GSA on a project-by-project basis about equipment and
materials that should be removed and salvaged to the Owner. The Designer shall also
inquire how and where the salvaged materials will be delivered to the Owner, in
compliance with any applicable “green” requirements.

53 Telecommunications Distribution Design Guide [ Version 8 ]


Project Procedures 3

3.7.3 Preservation Objectives


GSA may wish to preserve in operational condition some existing cables. Such existing
cables may not be used immediately following the completion of the work, but GSA may
have plans for future use of those cables. It may be required by Code that such cables
be physically tagged for future use, or otherwise be subject to demolition.

Telecommunications Distribution Design Guide [ Version 8 ] 54


4
Design Criteria

4.1 Principles of Transmission


Please refer to Chapter 1 – Principles of Transmission in the BICSI TDMM for general
information regarding the design of telecommunications distribution infrastructure.

4.2 Electromagnetic Compatibility


Please refer to Chapter 2 – Electromagnetic Compatibility in the BICSI TDMM for
general information regarding the electromagnetic interference with and clearance
requirements for telecommunications infrastructure. The following requirements take
precedence over the BICSI TDMM guidelines for telecommunications infrastructure at
GSA facilities:
A. The BICSI TDMM includes tables listing minimum separation distances from
sources of electromagnetic interference (EMI). Telecommunications
infrastructure shall not be installed closer than the minimum separation distances
listed in the BICSI TDMM. Where the NEC or local codes require greater
separation distances than those listed in the BICSI TDMM, the largest separation
distance shall be maintained.

55 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
B. Separation distances apply equally to both copper cabling and fiber optic cabling.
Even though fiber optic cabling is impervious to EMI, once a pathway is
established for fiber it could later be used for copper cabling.
C. OSP telecommunications infrastructure designs shall adhere to the governing
clearance requirements of the NEC and NESC.

4.3 Telecommunications Spaces


Please refer to Chapter 3 – Telecommunications Spaces in the BICSI TDMM for general
information regarding the design of telecommunications rooms. The following
requirements take precedence over the BICSI TDMM guidelines for telecommunications
infrastructure at GSA facilities:
A. In GSA facilities, the TRs in a building may also serve as low voltage systems
equipment rooms, typically containing electronic equipment intended to serve the
building or a portion of the building. The TR shall not be shared with electrical
installations other than those necessary for telecommunications.

4.3.1 Telecommunications Room Location


A. The Designer shall be responsible to inform the Architect of the sizing and
location requirements for Telecommunications Rooms during the Schematic
Design phase of the project.
B. The most desirable location for telecommunications rooms is to be located as
centrally as possible and as near as possible to the area being served. In
addition, for multi-story buildings, telecommunications spaces shall be vertically
aligned wherever possible. This allows for clean, vertical pathway to be easily
provided to each space. It also reduces the number of bends and offsets that the
intra-building backbone pathway must undergo as it connects each of the
telecommunications rooms. Please see the discussion in TDDG Section 4.4.1 –
Intra-building Backbone Pathways for further information.
• In minor remodel projects, this requirement may be waived due to budget or
space availability limitations.
C. There shall be a minimum of one TR per building. Additional TRs shall be added
when the area to be served exceeds 10,000 square feet or where the cable
lengths will exceed 295 feet between a TR and the work area
telecommunications outlet, including allowance for cable slack loops. Generally,
each floor of a building shall be served by a TR located on that floor.
• When specifically approved by the GSA IT ITS, a TR may be designed to
serve multiple floors of a building.
D. Field offices are generally smaller and can be supported with less infrastructure
than what is required for regional office buildings. Some options that might be
considered include:

Telecommunications Distribution Design Guide [ Version 8 ] 56


4 Design Criteria

• A one-rack solution for the headend equipment and remote wall-mounted


cabinets serving other areas of the building may be sufficient for smaller Field
Offices. The Designer shall work with GSA IT to obtain direction whether this
solution or something similar would be appropriate for the application.
E. Telecommunications Rooms shall not be co-located with any type of electrical
room or mechanical room. The TR location shall maintain the separation
distances identified in the Electromagnetic Compatibility subsection of this
document.
F. The telecommunications room shall not be constructed in any of the locations
listed below:
• Areas subject to water or steam infiltration, particularly basements. Floor
drains (with trap primers) are required if there is any risk of water entry.
• Adjacent to wet rooms (restrooms, janitorial, etc.).
• Areas exposed to excessive heat or direct sunlight.
• Areas exposed to corrosive atmospheric or environmental conditions.
• Near or adjacent to potential sources of electromagnetic interference (EMI) or
radio frequency interference (RFI) such as large electric motors, power
transformers, arc welding equipment, or high-power radio transmitting
antennas.
• In a shared space with electrical equipment other than equipment serving the
telecommunications system.

4.3.2 Telecommunications Room Sizing


A. Telecommunications rooms shall typically be one of the following three sizes
(and larger where required):
• 8’ x 6’ for a one-rack application
• 10’ x 10’ for a two-rack application
• 13’ x 10’ for a three-rack application
See the sample telecommunications room plan drawings in Appendix 6.2 of the
TDDG for further information.
B. If project circumstances prevent the establishment of adequately-sized
telecommunications spaces, the following options may be considered on a case-
by-case basis, subject to the approval of GSA:
• Reach-in closets and small room designs for minor remodel construction
projects may be considered through the SVR process.

• Wall-mounted swing cabinets are appropriate for some remodel applications


serving small numbers of people and where floor space for a full
telecommunications room would be unavailable or impractical. See the
sample wall-mounted cabinet plan and elevation drawings in Appendix 6.2 of
the TDDG for further information.

57 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

• The Designer shall pay close attention to the requirements of the equipment
that will reside in the cabinet and the space that will host the cabinet.
+ Don’t undersize the cabinet. Use cabinets that are 36” to 48” high.
+ Some applications require cabinets that are 30” deep, and other
applications will not permit cabinets that are more than 12” deep (with
vertically mounted electronics).

• The cabinet shall be on a painted, ¾” plywood backboard unless it can be


determined that studs and backing in the wall are suitable to carry the rated
weight of a fully-loaded cabinet (not just the day-1 weight).

• Provide a power outlet inside cabinet so that power cords remain inside the
secure, locked cabinet and to prevent convenience use of the power outlet.

• Route cabling into the top of the cabinet using one or more conduits, sized as
required to handle the required cabling.
C. Telecommunications room sizing shall be increased if other low voltage systems
equipment is intended to be hosted in the TR; for example, fire alarm panels,
security system equipment, etc. The Designer shall seek input from the GSA IT
ITS regarding room sizing.
D. Telecommunications rooms in new construction and modernization projects shall
be sized such that adequate space for equipment maintenance is available after
racks and equipment have been installed.

4.3.3 Architectural Provisioning


A. The Designer shall be responsible to inform the Architect of the architectural
provisioning requirements for Telecommunications Rooms, and to do this early in
the Design Development phase of the project.
B. The Designer shall be responsible to review project documents and determine
that the architectural requirements for the telecommunications spaces are met as
described in this document. For projects where an architect is involved, the
Designer shall coordinate directly with the architect, and verify that the architect’s
design documentation meets these requirements. For projects without an
architect, the Designer shall alert GSA where additional architectural adjustments
are needed to meet the requirements.
C. Doors shall open out (180-degree swing) from telecommunications spaces, and
shall be a minimum of 36” wide and 80” high, fitted with a lock. Coordinate lock
and key requirements with GSA. Doors shall be located in hallways or other
common areas. Telecommunications room doors shall never be located in
another building occupant’s designated space.
• Access control hardware is required for telecommunications rooms and RICs
in regional office buildings (ROBs). Access control hardware shall have the
capability to require two-factor authentication in compliance with the
requirements of NIST SP 800-116. Typically, a card reader with a keypad is

Telecommunications Distribution Design Guide [ Version 8 ] 58


4 Design Criteria

an appropriate solution. See Building Technologies Technical Reference


Guide for further information.
• For field offices, the Designer shall inquire whether access control electronics
are required for a given telecommunications room.
D. Minimum clearance height within a telecommunications space shall be 8 feet
without obstructions (light fixtures, ducting, etc.). False ceilings (t-bar ceilings,
ceiling grids, etc.) shall not be installed in telecommunications spaces. Walls and
plywood backboards shall be painted with a light-color (white) paint. To enhance
visibility in the room and reduce dust, GSA IT prefers that ceilings be painted with
a light-color paint.
E. Finishes shall be light in color (white) to enhance room lighting. Flooring
materials shall be light-colored and slip-resistant; carpet is not acceptable for
telecommunications rooms. Interior floor finish and floor covering materials shall
also meet the requirements in the International Building Code.
F. The walls in telecommunications rooms shall be covered with either fire
retardant-treated ¾” plywood (that has been treated with fire-retardant chemicals
by a pressure impregnation process), or plywood that has been painted with a UL
listed, non-toxic fire-retardant intumescent coating having a Class A surface
flame spread rating, and that has been approved by the GSA PBS fire protection
engineer. The plywood shall be painted with primer and two coats of white paint.
• If treated plywood is used, mask the stamp on each sheet prior to priming
and painting. Leave the stamps exposed and visible for long-term
maintenance awareness.
• If an approved fire-retardant intumescent coating is used, a small plaque shall
be attached to the backboard near the door listing the fire spread rating of the
backboard, the name of the manufacturer, and the product number of the fire-
retardant intumescent coating. This information may be helpful for future
maintenance activities.
Plywood backboards shall extend from 6” above the floor up to a height of 8’6”
above the finished floor.

4.3.4 Environmental Provisioning


A. The Designer shall be responsible to inform the Mechanical Engineer of the
environmental provisioning requirements for Telecommunications Rooms, and to
do this early in the Design Development phase of the project.
B. The Designer shall be responsible to determine that the mechanical HVAC
requirements for the telecommunications spaces are met as described in this
document. For projects where a Mechanical Engineer is involved, the Designer
shall coordinate directly with the engineer, and verify that the engineer’s design
documentation meets these requirements. For projects without the involvement
of a Mechanical Engineer, the Designer shall alert GSA where adjustments to the
mechanical infrastructure are needed to meet the requirements.

59 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
C. The Designer shall coordinate with the Mechanical Engineer to ensure that the
HVAC requirements for the telecommunications spaces are met and also that
HVAC ductwork and motors do not conflict with cable tray or conduit routing.
D. In addition to the requirements in the BICSI TDMM, telecommunications rooms
shall be environmentally provisioned as follows:
• A fundamental design assumption is that all TRs will at some time contain
active electronic equipment (routers, switches, etc.) even if the current design
does not call for such devices.

In some telecommunications rooms, the quantity of network electronics


devices will produce a heat load that requires mechanical cooling. If the
building system cannot assure continuous cooling operation (year round), a
stand-alone unit shall be provided for the TR.

In other telecommunications rooms with less active equipment and


correspondingly limited heat loads, it may be possible to adequately cool the
rooms through the use of an air supply fan to exchange air in the room with
ambient air from the corridor.

The Designer shall evaluate the expected heat load and recommend an
economical solution that is adequate for the load.

In addition, a positive pressure differential with respect to surrounding areas


is required to help keep dust and other particles out of the room.
+ In cooler climates and seasons, the use of outside air for cooling is
encouraged. Dehumidification and filtration may be required for systems
using outdoor air.
+ Environmental management and monitoring systems shall be designed for
TRs. The Designer shall inquire with GSA to determine the required
features of the monitoring solution for a given application.
+ Split systems are permissible for remodel projects, with the equipment
located outside the TRs wherever possible. The temperature controls shall
be located inside the TR.
+ The PBS P100-2016 in Section 6.5.9 states that air conditioning systems
for technology/server and UPS rooms shall be supported by emergency
power systems.
+ Air conditioning units serving TRs shall be procured with the network
management option, providing a network jack to connect to an Ethernet
switch.
• GSA typically provides network electronics that provide Power-over-Ethernet
(POE). The Designer shall request power consumption data for the
equipment that GSA will use, and work with the mechanical systems designer
to ensure that the cooling capacity is sufficient to support the POE heat load.

• Humidity is not typically controlled in a TR. However, the desirable range is


between 45% and 55% relative humidity.

Telecommunications Distribution Design Guide [ Version 8 ] 60


4 Design Criteria

4.3.5 Fire Suppression


A. All telecommunication rooms shall be protected by a wet-pipe sprinkler system
that is designed and installed in accordance with the requirements in PBS P100-
2016, Section 7.8. In addition, listed sprinkler guards shall be provided.

4.3.6 Equipment Racks and Cabinets


A. Each telecommunications room shall be provisioned with a minimum of one floor-
standing 7’ high x 19” wide x 3” deep ANSI/TIA/EIA standard open-frame
equipment rack, regardless of whether or not equipment is required at the time of
construction.
• For minor remodel construction, this requirement may be waived given
budget, project size, or other limiting factors. The use of a wall-mounted
swing rack or a wall-mounted hinged bracket may be acceptable, subject to
GSA approval via the SVR process.
B. 36” clearances are required surrounding racks, cabinets, and any equipment that
may be mounted in the racks, as required by code. See the sample
telecommunications room plan drawings in Appendix 6.2 of the TDDG for further
information.
C. Racks shall be sized to accommodate, at a minimum, all existing and new
equipment that is to be installed in the rack plus an additional 50% unused space
for additional equipment that may be added in the future. If a rack is more than
50% full at design time, a spare rack shall be specified.
D. It can be difficult to read labeling and see cables and connectors inside cabinets
during maintenance activities. The Designer shall seek guidance from the GSA
IT Tech PM about whether to specify LED lighting inside cabinets (in the front,
rear and sides).

4.3.6.1 Floor-standing Equipment Racks


A. See the sample floor plan details in Appendix 6.2 of the TDDG for rack
arrangement guidance.
B. Floor-standing racks shall be securely bolted to the floor, and shall be braced to
the wall with cable ladder racking. Multiple racks in the same TR shall be
interconnected with cable ladder racks.
C. To provide the required clearances, rack locations shall be designed to have 72”
of clear space between the front of the rack and the wall behind the rack. Also, a
workspace access clearance of 36” is required on one side of an aisle of racks.
The Designer shall discuss with GSA the potential for future requirements for
additional racks, and identify spaces on the plan drawings for future racks. See
the sample telecommunications room plan drawings in Appendix 6.2 of the
TDDG for further information.
D. Racks shall be mounted such that the rack post shall be no closer than 14” to the
nearest wall, allowing space for an 8”, 10”, or 12” vertical cable manager to be

61 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
used near the wall, including space for the vertical cable manager door to swing
open.
E. Racks shall be equipped with horizontal and vertical cable management modules
both front and rear, with strain relief brackets to support proper patch cord bend
radius and to maintain strain relief for patch cords. Vertical cable management
(VCM) modules shall include spools/posts to manage cable slack. VCM modules
shall be used to manage patch cords. Do not store horizontal cable slack in
VCM modules. Typically slack shall be stored in the overhead ladder rack in the
telecommunications room, or using some other solution intentionally designed for
this purpose.
• VCM modules shall be engineered to function with the racks as a system.
• VCM covers (doors) shall be metal, and shall be easily removable.
• VCM doors shall have at least two metal, cam-style hinges, being capable of
opening to the right or left to accommodate workspace requirements of a
technician’s task. Doors shall latch closed or open with a single knob. Snap-
on covers are not acceptable.
• VCM modules shall have openings in the back wall to allow cabling to pass
between the front and rear of the rack.
• The VCMs shall have adjustable cable management panels, cable spools,
and other accessories that can be adapted to accommodate the volume of
cables that they contain, and to meet special requirements.
• The Designer shall evaluate the patch cord quantities expected to be
managed in the vertical cable management and shall specify appropriately
sized VCM hardware for each telecommunications room.
• Vertical cable management between racks typically ranges between 10” and
15” wide.
• Vertical cable management on the ends of rack rows shall typically be 10”
wide. Some applications, however, may require 12” or 15” wide vertical cable
management for the sides of racks. The Designer shall consider whether
additional space might be required between the VCM and the wall to allow
the door to pivot on its hinge as it swings open.
F. Horizontal cable management products shall belong to the same product family
(and same manufacturer) as the VCM products. Horizontal cable management
products shall be engineered to function together with the VCM, such that patch
cords can transition smoothly between horizontal and vertical cable management
modules.
G. Sometimes an equipment cabinet is required for larger IT equipment (servers,
large UPSs, etc.) with both front and rear mounting rails. The Designer shall
discuss with GSA the network electronics that will be hosted in each TR and shall
design appropriate racks and cabinets to support the equipment. Racks and
cabinets shall be shown on the rack elevation details in the plan drawings.
H. Ladder racking shall be provided at 7’ and 8’ above finished floor circling the
room and crossing the room over the tops of the equipment racks. Backbone
cables and patch cords shall be routed via the 7’-level ladder racking. Horizontal
cables and their service loops shall be stored in the 8’-level ladder racking.

Telecommunications Distribution Design Guide [ Version 8 ] 62


4 Design Criteria

I. Horizontal cables and patch cords shall be secured to cable supports (such as
ladder rack and VCM) using hook-and-loop straps. The Contractor is welcome to
use its choice of white, black, or grey straps, as long as that single color choice is
used consistently throughout the telecom room.
• Tie-wraps (zip-ties) shall not be used to secure any cables, at any time (even
temporarily during installation).

4.3.6.2 Telecommunications Cabinets


A. When planning the size and location of TRs in existing buildings, the Designer
shall make every reasonable effort to meet the requirements for
telecommunications rooms. In certain instances, the only viable alternative may
be the use of one or several telecommunications cabinets in lieu of TRs.
B. In minor remodel projects, some buildings may not justify a separate room as the
telecommunications room. In some circumstances, sufficient space may not be
available for a telecommunications room. In these instances, a wall-mounted or
floor-standing telecommunications cabinet may be used.
C. Cabinets shall be sized to allocate space for cabling termination infrastructure,
network electronics and UPS equipment, and shall also include space allocated
for future growth.
D. Cabinets shall be equipped with horizontal wire management modules with strain
relief brackets to support proper cable bend radius and to maintain strain relief
for the cabling.
E. All telecommunications cabinets require lockable doors, and most applications
need more security than can be provided with the manufacturer’s standard door
lock. The Designer shall inquire for each application whether GSA would prefer
to have uniquely keyed locks installed on each cabinet door, and whether GSA
would prefer to have electronic locks with card readers in lieu of keyed locks.
F. Power and telecommunications cables for equipment housed within the cabinet
are to be contained within the cabinet. Exposed wiring or cables are not
permitted. Power and telecommunications cables routed to or from the cabinet
shall be contained in conduit, surface-mounted raceway, or concealed within the
adjacent wall.
G. Each cabinet shall have a telecommunications grounding busbar (TGB) installed
inside, in accordance with the grounding requirements discussed in the BICSI
TDMM Chapter 9 – Bonding and Grounding (Earthing).
H. The cabinet shall not be located in or adjacent to areas containing sources of
electromagnetic interference (EMI). See TDDG Section 4.2 – Electromagnetic
Compatibility (above) for further information.

4.3.6.2.1 Floor Standing Cabinets


A. Each cabinet that hosts equipment that produces a significant heat load shall
have front and rear screen doors, allowing airflow through the equipment.
Cooling fans are typically not required.

63 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

• The Designer shall inquire with GSA regarding the network equipment that
GSA will install in each cabinet. Some equipment (such as the Cisco 6500
series) has side-to-side airflow, while other equipment has front-to-back
airflow. Based on this information from GSA, the Designer shall specify the
appropriate air baffles that will be suitable for the airflow pattern needed.

4.3.6.2.2 Wall-Mounted Cabinets


A. Wall-mounted cabinets shall be double-hinged to permit access to both the front
and rear of the equipment. Telecommunications cabinets shall be constructed of
heavy gauge steel and be lockable. Care shall be taken to specify cabinets with
strong hinges that do not begin to sag over time due to the weight of the
cabinet’s contents. Cabinets shall have a clear Plexiglas window in the front
door to allow non-technical people to view equipment status without accessing
the locked door. See the sample wall-mounted cabinet plan and elevation
drawings in Appendix 6.2 of the TDDG for further information.
B. Wall space shall be allocated to permit cabinets to fully swing open.
C. Technical power outlets serving wall-mounted cabinets shall be mounted inside
the cabinet. Wall-mounted cabinets typically require a single 5-20 receptacle.

4.3.7 Power Requirements


A. The Designer shall be responsible to determine that the power requirements for
the telecommunications spaces are met as described in this document. For
projects where an electrical engineer is involved, the Designer shall coordinate
directly with the engineer, and verify that the engineer’s design documentation
meets these requirements. For projects without the involvement of an electrical
engineer, the Designer shall alert GSA where additional power infrastructure is
needed to meet the requirements.
B. GSA typically provides network electronics that provide Power-over-Ethernet.
The Designer shall request power consumption data for the equipment that GSA
will use, and work with the electrical power distribution designer to ensure that
the cooling capacity is sufficient to support the POE heat load.

4.3.7.1 Uninterruptible Power Supplies


A. For Regional Information Centers (RIC), GSA generally prefers centralized
uninterruptible power supply (UPS) equipment, which shall also serve the
telecommunications rooms in the building. However, for non-regional office
buildings, rack-mounted UPS equipment in each telecommunications room will
likely suffice. The Designer shall discuss with GSA on a project-by-project basis
which UPS would be best for that project. See Section 4.18.3.9.2 – Backup
Power for further information.
B. The Designer shall design appropriate power receptacles that will be suitable to
serve the UPS equipment that will be used on the project.
C. The Designer shall inquire whether a rack-mounted auto-transfer switch would be
desirable for applications where distributed UPSs are used. Rack-mounted auto

Telecommunications Distribution Design Guide [ Version 8 ] 64


4 Design Criteria

transfer switches can be helpful to supply redundant power to single-corded


equipment or to switch power to bypass a failed UPS during normal power
conditions.
D. UPS equipment shall be procured with the network management option,
providing a network jack to connect to an Ethernet switch.

4.3.7.2 Technical Power Panels


A. The technical power circuits in each telecommunications room shall originate
from a technical power panel, dedicated to serving the TR. In the absence of
other influencing circumstances, the panel shall be sized for 100 amp service.
The technical power panel shall not be used to supply power to sources of
electromagnetic interference such as large electric motors, arc welding, or
industrial equipment. The power panel shall be located in the TR or in close
proximity to the TR. The technical power panel shall be labeled
“Telecommunications Equipment Only.”
• If an Optional Standby Generator (NEC 702.2) is available to the facility, the
TR technical power panel shall be served by the generator.
• Some circumstances might not justify a dedicated technical power panel. In
these cases, an available general-purpose electrical panel may be used. The
Designer shall seek direction from GSA regarding a decision not to design a
dedicated technical power panel.
B. The panel schedule affixed inside each technical power panel shall indicate the
rack number or cabinet number and outlet type served by each circuit. The
practice of describing circuit with vague references such as “IT Load” or
something similar is not permitted.
C. The following two diagrams depict strategies for distributing technical power to
telecommunications rooms where a centralized UPS is used and where UPS
equipment is distributed to each telecommunications room:

65 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

FIGURE 5: POWER AND GROUNDING FOR


TELECOMMUNICATIONS ROOMS
WITH CENTRALIZED UPS EQUIPMENT

Telecommunications Distribution Design Guide [ Version 8 ] 66


4 Design Criteria

FIGURE 6: POWER AND GROUNDING FOR


TELECOMMUNICATIONS ROOMS
WITH DISTRIBUTED UPS EQUIPMENT

67 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
D. Where wall-mounted telecommunications cabinets are used in lieu of a TR, an
available general-purpose power panel may be used to support the
telecommunications cabinet power outlet. However, the power panel shall not be
used to supply power to sources of electromagnetic interference such as large
electric motors, arc welding, or industrial equipment. The power panel shall be
located in close proximity to the cabinet.
E. Technical power panels shall be provided with a Transient Voltage Surge
Suppressor (TVSS) to protect equipment served by the panel from destructive
voltage spikes.
F. Convenience power panels serving workstation computers and printers would
also benefit from having a Transient Voltage Surge Suppressor (TVSS) to protect
the equipment served by the panel.

4.3.7.3 Technical Power Outlets


A. Every site will have different requirements depending on the applications that it
supports. The Designer shall obtain electrical power connection/load
requirements from GSA for each piece of equipment, and tabulate the
information for review and confirmation by GSA. This equipment may include
network electronics, UPS equipment, computers/servers, phone system
equipment, voice mail systems, video equipment, and service provider
equipment. The Designer shall be attentive to equipment that uses dual-
redundant power supplies. The Designer shall be responsible to verify, validate,
and account for device quantities and associated power loads to ensure that
proper capacity and outlet types are designed for the project.
B. The Designer shall specifically investigate the potential need for voltage or
ampere requirements other than 110VAC/20 Ampere power. Some UPS and
network switch equipment requires specialized plugs or electrical service. The
Designer shall inquire with the GSA ITS to determine whether any dedicated or
specialized circuit requirements exist.
C. Preferably, technical power outlets would be supplied by a panel that is
dedicated for technical purposes only, to reduce the possibility of electrical noise
from motors and other sources of disruptive interference.
D. At a minimum, each rack (or cabinet) in a telecommunications room or RIC will
require the following set of power outlets (each with dedicated circuits) for
exclusive use by telecommunications-related electronic equipment:
• L6-30 (single phase, 208V, 30A) – quantity of 2
• L5-20 (single phase, 120V, 20A) – quantity of 2
• 5-20 (single phase, 120V, 20A) – quantity of 2
• Each pair of outlet types shall be fed from separate power phases.

Telecommunications Distribution Design Guide [ Version 8 ] 68


4 Design Criteria

FIGURE 7: POWER DISTRIBUTION ARCHITECTURE FOR TRS IN


ROBS WITH 1U NETWORK SWITCHES

69 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

FIGURE 8: POWER DISTRIBUTION ARCHITECTURE FOR TRS IN


ROBS WITH CHASSIS NETWORK SWITCHES

Telecommunications Distribution Design Guide [ Version 8 ] 70


4 Design Criteria

E. Each wall-mounted telecommunications cabinet (typically located in non-


telecommunications room spaces) shall be equipped with a minimum of one
quad 120V technical power outlet, installed inside, near the bottom of the
cabinet. See the sample wall-mounted cabinet plan and elevation drawings in
Appendix 6.2 of the TDDG for further information.
F. Other requirements:
• Outlets shall be labeled as “Technical Power” and shall show the panel and
circuit numbers.
• Where 110VAC Technical power outlets are required, outlets shall be
equipped for “straight-blade plugs” (NEMA 5-20R), rather than twist-lock style
receptacles. In addition, receptacles shall have a T-shaped universal blade
slot to support both plugs with vertically oriented blades as well as 20A plugs
with one blade rotated 90 degrees.
• Where 208VAC Technical power outlets are required, the Designer shall
inquire with GSA to determine the plug requirements for the equipment to be
served.
• Each outlet shall be equipped with a dedicated insulated solid copper
equipment-grounding conductor.
• Ground conductors serving technical power outlets shall not be isolated
ground conductors.
• See the telecommunications room plan details in Appendix 6.2 of the TDDG
for technical power outlet locations.

4.3.7.3.1 For New Construction and Modernization Projects


A. Faceplates for convenience power receptacles and light switches in the TR shall
be mounted at the surface of the plywood backboard (as opposed to being
recessed into a cutout in the plywood backboard). In other words, the device
boxes shall be recessed into the wall rather than surface-mounted.
B. Power receptacles shall be attached to the overhead ladder racking at the rear of
the rack or cabinet. Each set of receptacles serving a rack or cabinet shall be
centered within the width and above the rack or cabinet they serve. See outlet
types, quantities, and locations in Figure 7: Power Distribution Architecture for
TRs in ROBs with 1U Network Switches, and in Figure 8: Power Distribution
Architecture for TRs in ROBs with Chassis Network Switches.
C. The rack nearest the wall is expected to host a rack-mounted UPS at the base of
the rack as well as a horizontal (19”) rack-mounted power strip or Power
Distribution Unit (PDU). The UPS will plug into the power outlet, and the power
strip or PDU will plug into the UPS.
• GSA prefers to use horizontal PDUs that provide both rear and front facing
receptacles in a single unit.
• The Designer shall specify appropriate plug types for each application and
cord lengths that are sized without unnecessary slack.

71 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
D. Typically, the contractor is required to furnish and install the horizontally-mounted
PDU equipment.

4.3.7.3.2 For Minor Remodel Projects


A. Wherever possible, the design shall include technical power outlets according to
the “new construction” requirements. However, for some projects it may not be
practical to meet those requirements. The following two paragraphs describe an
alternative arrangement of technical power outlets that may be approved on a
project-by-project basis via the SVR process:
• If it is not practical to install a new power outlet at the top of each equipment
rack, it may be acceptable to serve the rack’s power needs from a wall-
mounted outlet.
• If power outlets are not installed at the top of each rack, the number of wall-
mounted technical power outlets shall be increased to an interval of one
outlet every 4 feet. Power outlets in this arrangement shall be located such
that they are conveniently aligned with the equipment racks to avoid
inadvertent disconnection of the power cords.
B. Where telecommunications backboards are applied to existing walls with existing
power outlets and light switches, the design shall require backboards to be
provided with cutouts permitting access to the existing electrical devices.

4.3.7.4 Additional Convenience Power Outlets


A. In addition to the technical power outlets described above, the design shall
require the Contractor to provide other duplex convenience outlets (120VAC, 15
Ampere) that would be available for use with power tools and testing equipment.
Each outlet shall be gray or white colored, and be labeled with its panel
identification and circuit number.
B. Where telecommunications cabinets are used in lieu of a TR, there shall be at
least one general-purpose convenience power outlet (120VAC, 15 Ampere)
located within six feet of each telecommunications cabinet. This outlet shall be
colored consistently with other convenience outlets in the building. The general-
purpose outlet shall not be used to power telecommunications equipment
associated with the cabinet.
• For minor remodel projects, the number of convenience outlets in a TR can
be reduced.
C. Convenience power outlets can be circuited to the technical power panel.

4.3.8 Lighting
A. Light levels in telecommunications spaces shall be 50 foot-candles at 3 feet
above finished floor.
B. Light fixtures shall be mounted at approximately 8 or 9 feet above finished floor.
Fixtures shall not be located directly above racks or ladder racking, but rather to
the side of racking. The intent is that overhead light fixtures illuminate the front

Telecommunications Distribution Design Guide [ Version 8 ] 72


4 Design Criteria

and rear of racks and cabinets. See Appendix 6.2 for recommended light fixture
locations.
C. Light fixtures in telecommunications rooms shall be industrial style fixtures, as
opposed to artistic or architectural grade fixtures that are typically more costly.
Fixtures shall be specified to be appropriately sized for the application (not too
large or too small). Fixtures shall be secured with a diagonal member to prevent
the fixture from swinging due to airflow in the telecommunications room.

4.3.9 Grounding, Bonding, and Electrical Protection


All equipment racks, metallic conduits, and exposed non-current carrying metal parts of
telecommunications and information technology equipment in the TR shall be bonded to
the TMGB. Refer to Chapter 9 – Bonding and Grounding in the BICSI TDMM and TDDG
Section 4.8, Bonding and Grounding (Earthing) for more information regarding the
design of grounding, bonding, and electrical protection systems.
A. Grounding and bonding conductors shall be sized according to the requirements
in ANSI/TIA/EIA J-STD-607-B.
B. See PBS P100-2016, Section 6.5 for additional requirements.

4.3.10 Cables Entering Telecommunications Rooms


A. All cables shall be fully supported and properly transitioned throughout their
lengths, including proper bend radius fittings at pathway transitions. Where
cabling is routed vertically, it shall be appropriately secured such that the weight
of the cabling does not subject the cabling to stresses that could potentially
reduce the performance of the cabling.
B. Cabling shall be bundled in quantities not exceeding 24 cables per bundle.

4.3.11 Entrance Facilities


The stewardship over entrance facilities falls largely under GSA PBS. Therefore, only a
few design guidelines from GSA IT are contained in the TDDG:
A. GSA IT requires a minimum of one 4’ x 8’ backboard space within the entrance
facility for GSA IT-specific service demarc equipment. The Designer shall inquire
whether a given project requires more space than this.
B. The Designer shall inquire with GSA PBS about backup power for utility-provided
circuits:
• How will operations in the building be affected if telephone or data circuits
shut off due to power outage?
• Does the project require backup power for the utility-provided circuits?
• What are the backup power runtime requirements?
C. The Designer shall provide GSA IT-dedicated pathway from the GSA IT
backboard to the main telecommunications room (MDF) in the building. Conduits
shall be provided, with the following quantities and designated purposes:

73 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

• Three 4” conduits shall be provided. In some cases, a minimum of two 4”


conduits might be sufficient. Where circumstances do not allow the
installation of 4” conduit, the equivalent carrying capacity (cross-sectional
conduit area) using a larger quantity of 2” conduit might be sufficient. The
Designer shall inquire with the GSA IT Tech PM before designing pathway
other than three 4” conduits.
• One conduit to carry a 50PR (minimum) copper backbone cable from the
utility demarc in the entrance facility to the MDF/RIC for analog phone
circuits.
• One conduit for utility-provided cables for use with extended demarc circuits
terminated in the MDF/RIC.
• One spare conduit.
See Section 4.4 – Backbone Distribution Systems.
D. One or more wall-mounted grounding busbars shall be provided for use with
utility demarc equipment. Utility circuits are normally extended to the RIC where
GSA IT requires grounding and bonding infrastructure. Grounding and bonding
infrastructure is also typically required in the Entrance Facility. The Entrance
Facility is normally under the stewardship of the building owner. Therefore, the
building owner shall work with the utility service provider to provide appropriate
grounding and bonding for the Entrance Facility.

4.4 Backbone Distribution Systems


Please refer to Chapter 4 – Backbone Distribution Systems in the BICSI TDMM, Chapter
3 – Cabling Topologies and Chapter 4 – Pathways and Spaces in the BICSI OSPDRM,
and Chapter 3 – Cabling, Pathways and Spaces in the BICSI ITSIMM for general
information regarding the design of backbone distribution pathway and cabling. The
following requirements take precedence over the guidelines in those documents for
telecommunications infrastructure at GSA facilities.
The following diagram applies to all intra-building backbone pathways and cabling:

Telecommunications Distribution Design Guide [ Version 8 ] 74


4 Design Criteria

FIGURE 8: UTILITY SERVICE AND


RISER BACKBONE CABLING

4.4.1 Intra-building Backbone Pathways


A. Intra-building backbone pathway shall utilize a physical star topology. However,
the Designer shall inquire whether another pathway topology would be
appropriate for a given application. Backbone raceway shall consist of conduit,
chases or shafts, sleeves, and/or vertically-mounted ladder racking.
B. All cables shall be fully supported and properly transitioned throughout their
lengths, including proper bend radius fittings at pathway transitions. Where
cabling is routed vertically, it shall be appropriately secured such that the weight
of the cabling does not subject the cabling to stresses that could potentially
reduce the performance of the cabling.

75 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
C. In new construction and modernization projects:
1. The main telecommunications room in the building shall have a direct
pathway connection to the entrance facility.
2. All intermediate telecommunications rooms (IDFs) shall have pathway
connections to the main telecommunications room in the building (RIC).
3. Backbone pathways are generally not required between two intermediate
telecommunications rooms on the same floor, as long as both
telecommunications rooms have pathways to the main telecommunications
room.
D. It may be prudent (due to budgetary or other project limitations) to design the
intra-building backbone pathway in an arrangement that sub-feeds an
intermediate telecommunications room from a second intermediate
telecommunications room on the same floor.
• Even though pathway from one telecommunications room may route through
another telecommunications room before connecting to the main
telecommunications room, backbone cabling shall not cross-connect in the
interposing telecommunications room. Intra-building backbone cabling shall
be continuous (non-spliced) between the main telecommunications room and
each intermediate telecommunications room.

4.4.1.1 Backbone Raceway Size and Quantity Requirements


A. Future growth requirements shall be considered when sizing intra-building
backbone pathways. The cost to install additional spare pathways during initial
construction is significantly less than the cost of retrofitting additional pathways in
the future.
B. In general, for new construction and modernization projects, GSA will need one
or more 4” EMT conduits or sleeves (whatever is sufficient to handle the volume
of riser/backbone cabling being designed) between the main telecommunications
room (MDF) and each intermediate telecommunications room. In addition to the
above backbone conduits, GSA requires two more 4” conduits (or sleeves) that
are vacant, for future cabling needs.

4.4.1.1.1 Single-Story Buildings


C. For single-story buildings with multiple telecommunications rooms, 4” conduit
pathways shall be routed through the ceiling, not in or under the floor slab. The
Designer shall determine the number of 4” conduits required to serve initial and
future backbone cabling requirements.
• In cases where it is not possible to route 4” conduits to each of the
telecommunications rooms, three 2” conduits may be substituted for each
required 4” conduit.

4.4.1.1.2 Multi-Story Buildings


A. In new construction and modernization projects, telecommunications rooms shall
be stacked wherever possible. Sleeves may be used in lieu of conduit if the

Telecommunications Distribution Design Guide [ Version 8 ] 76


4 Design Criteria

telecommunications rooms are stacked. Sleeved vertical pathways shall be


extended to the roof (or to an attic space with access to the roof) to facilitate
access for future roof-mounted or side-of-building-mounted telecommunications
equipment.
B. Ladder racking shall be vertically mounted on the walls in stacked
telecommunications rooms to route and support backbone cables passing
between telecommunications rooms through the vertical riser pathway. Cabling
shall be supported at maximum intervals of 24”, attached to the ladder rungs
using hook-and-loop style straps (for example, Velcro). The use of zip ties is
prohibited, even as a temporary convenience during construction.
C. If design constraints prevent vertical stacking of telecommunications rooms, a
centrally located vertical pathway (chase) shall be provided and shall be
dedicated to the telecommunications distribution system. This pathway shall
have a minimum cross-sectional area of 2 ft2 (two square feet), shall be
accessible at a maximum interval length of 3 feet, and shall extend to the roof or
attic space.
• 4” conduits shall be routed between the vertical chase and the
telecommunications rooms on each floor. The Designer shall determine the
number of 4” conduits required to serve initial and future backbone cabling
requirements.
• In cases where it is not possible to route 4” conduits to each of the
telecommunications rooms from the vertical chase, three 2” conduits may be
substituted for each required 4” conduit.

4.4.2 Intra-building Backbone Cabling


GSA requires both copper backbone cabling and fiber optic backbone cabling
between the main telecommunications room (typically the RIC) and the secondary
telecommunications rooms (IDFs) in the building. The following sections describe
the requirements for intra-building backbone cabling.

4.4.2.1 Intra-building Backbone Cable Types


A. GSA uses three types of telecommunications cabling for intra-building backbone
systems, terminated on rack-mounted patch panels:
• For distances less than 300 meters: 50/125µm OM3 Multimode fiber optic
cabling (aqua color).
• For distances between 300 meters and 550 meters: 50/125µm OM4
Multimode fiber optic cabling (aqua color).
• Multipair copper backbone cable: minimum 25PR, Category 5e rated or
higher.
B. GSA rarely uses singlemode or 62.5/125µm multimode fiber optic cabling, except
for providing new patch cords for existing applications.

77 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
C. In the past, GSA typically required the use of armored construction for all fiber
optic cabling. GSA is now switching to lower-cost, all-dielectric cable wherever
applicable.
• Some situations may not offer a necessary level of protection against
physical damage during the life of the cable. In such cases, armored
construction may be advantageous.
• Armored cable would also be desirable when fiber optic cabling passes
through a multitenant-accessible shared space en route to serving a GSA IT
application.
• All-dielectric (plastic) armored cable provides the physical protection benefit,
while being resilient to external impact and not requiring grounding.
D. Splices are prohibited for backbone cabling.

4.4.2.2 Strand and Pair Counts


A. Each telecommunications room shall be served with multimode fiber. The
Designer shall inquire on a project-by-project basis whether a CAT6A backbone
cable is also required.
B. Backbone cable sizing (# of strands) shall be considered with respect to possible
future requirements. The cost to add additional backbone pairs and strands
during the initial installation is significantly less than the cost of adding another
cable in the future.

The Designer shall inquire whether 40GB or 100GB backbone bandwidths are
required. These bandwidths require multiple strands for each circuit.
C. The minimum number of multimode fiber optic strands to be provided shall be
equal to four strands per piece of equipment being hosted in the
telecommunications room plus 100% expansion capability. The Designer shall
discuss with GSA whether additional equipment (apart from network electronics)
will also require fiber optic cabling. At a minimum, require the Contractor to
provide each telecommunications room with a 12-strand multimode fiber optic
cable to support only network electronics.
• GSA does not typically attribute value or advantage to the use of redundant
pathways or backbone cables between telecommunications rooms within a
building. However, if the Designer identifies a situation where redundancy
would have merit, the topic should be brought to the attention of GSA IT.
D. Between the Entrance Facility and the MDF or RIC, require the Contractor to
provide a copper backbone cable with a minimum of 48 pairs to distribute
analog/POTS dial tone throughout the building. The RIC/MDF end of this cable
shall be terminated on angled copper patch panels (Category 5e or better).
E. Each telecommunications room shall be served with a minimum of a 25-pair
copper backbone cable terminated on a flat (not angled) copper patch panel
(Category 5e or better). For projects where VOIP telephone systems are not
being deployed, the copper backbone cabling pair-count may need to be
increased to support the number of non-VOIP telephones to be used in the

Telecommunications Distribution Design Guide [ Version 8 ] 78


4 Design Criteria

building. Consequently, this will also change the number of horizontal cables to
the desktop. See Section 4.6.3.6 – Horizontal Cable to Support Voice
Applications.
F. Backbone fiber optic cabling shall each be installed as a single cable containing
all specified strands or pairs. For example,
Where 24 strands of fiber are specified, a single fiber optic cable containing 24
strands shall be provided. It is not acceptable to provide two cables containing
12 strands each.
G. Category 5e copper backbone copper cabling is typically manufactured in cables
with 25 pairs of copper wire per cable. Therefore, copper backbone cabling shall
be installed in multiples of 25-pair cables in quantities sufficient to provide the
total number of pairs required for the application. For example,
Where a 50-pair copper cable is specified, it is acceptable to provide two
Category 5e cables with 25 pairs each.

4.4.2.3 Fiber Optic Patch Cords


TABLE 9: FIBER OPTIC PATCH CORD REQUIREMENTS

Applications Patch Cord Requirements Length


Telecom Room Typically require that patch cords matching 2 to 3 meter length is typically
the rating of the cable shall be furnished but appropriate. The Designer shall work
(Patch panel not installed by the Contractor. A minimum with GSA IT ITS to evaluate the
and equipment quantity of 6 fiber optic patch cords is equipment that GSA will provide and
connections) typically required for each determine whether the patch cord length
telecommunications room. Typically, should be increased. Patch cords shall
cables shall be terminated with LC-duplex be long enough to permit future
connectors. These details shall be repatching without excessive slack.
confirmed with the GSA IT ITS on a case-
by-case basis.

A. Fiber optic patch cords shall be stored in the manufacturer-sealed bag until use.
B. Prior to using a fiber optic patch cord, clean the cord and test it. Clean the fiber
optic connector on the network electronics also prior to use.
C. Properly cap all fiber optic connectors and terminations when not in use.
D. As a best practice, do not reuse existing fiber optic patch cords that are salvaged
from other applications.

4.4.2.4 Cable Segregation


In no case shall copper or fiber optic backbone cabling be run in the same raceways as
those used by electrical power conductors. However, copper and fiber optic cables are
permitted to run together in shared raceways.

79 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

4.4.2.5 Innerduct
GSA IT does not require innerduct for inside plant fiber optic cabling, unless it is
otherwise required by the local authority having jurisdiction, local building policy, or other
applicable guidelines.

4.4.3 Inter-building (Campus) Backbone Pathways


Projects for GSA facilities rarely involve underground outside plant pathways. When
they are required, the Designer shall follow the guidelines in the BICSI TDMM and the
BICSI OSPDRM.
The design of the entrance facility is under the direction of the GSA PBS PM. Entrance
facilities shall always be separate from equipment rooms.

4.4.3.1 Wireless and Radio System Distribution


GSA facilities frequently use rooftop satellite, wireless, or radio systems. These systems
typically use one or more radio antennas connected by cabling to radio transceiver
equipment. Pathways shall be designed from rooftop locations down to
telecommunications rooms to serve these applications.

4.4.4 Inter-building (Campus) Backbone Cabling


Projects for GSA facilities rarely involve underground outside plant cabling. When OSP
cabling is required, the Designer shall follow the guidelines in the BICSI TDMM and the
BICSI OSPDRM.

4.4.4.1 Utility Services


At GSA, telephone services, cable television services, and Internet services are typically
provided by third-party utility service providers. The Designer shall request from the
GSA IT Tech PM information about any needed telecommunications infrastructure to
support the required services. The Designer shall also request similar information from
the GSA PBS PM for requirements to support other departments and tenants of the
building.

4.4.4.2 Wireless and Radio System Distribution


A. Outdoor-rated backbone cabling shall be designed to serve rooftop satellite,
wireless, or other radio system applications. Lightning protection equipment shall
also be designed as appropriate.
B. Radio antenna transmission cables that connect the antenna to the radio
transceiver emit radio frequency (RF) radiation. These cables may be routed in a
separate conduit from other telecommunications cables. Cables containing RF
radiation shall be shielded cables.

Telecommunications Distribution Design Guide [ Version 8 ] 80


4 Design Criteria

4.5 Horizontal Distribution Systems


Please refer to Chapter 5 – Horizontal Distribution Systems in the BICSI TDMM for
general information regarding the design of horizontal distribution pathway and cabling.
The following requirements take precedence over the BICSI TDMM guidelines for
telecommunications infrastructure at GSA facilities:

4.5.1 Work Areas


4.5.1.1 Permanent Office Spaces
A. The standard treatment for each permanent office
space (walls, door, etc.) is two outlets on opposite sides
of the room with two angled ports (two copper cables)
per outlet. The outlets shall be arranged as shown in
the floor plan at right, intended to complement the
possible furniture orientations.
B. For larger offices, a third outlet (two ports) shall be
provided.
C. Outlets shall not be placed on the wall with the door.

4.5.1.2 Open Office/Modular Furniture


A. GSA prefers to serve open office areas by routing cable trays in a zone-like
fashion throughout the ceiling spaces above the open office areas, and then
establish J-hook pathways (where necessary) to reach each building column.
Preferably, the cable trays would route along the column lines so that J-hooks
would not be needed. The cables would then be routed down the columns to the
modular furniture.
• Columns that are wrapped or furred are preferable because conduits and
device boxes can be concealed inside.
• Surface-mounted raceway may be designed for columns that are not able to
conceal raceway.
• Where columns do not exist, utility poles shall be designed as a last resort.
• Raceways shall route cabling down from ceiling space to two outlets on
opposite sides of each column, allowing furniture to sit against the columns
on the sides lacking outlets.
• Outlets on columns shall have up to 6 ports per outlet, using angled
connectors.
• Outlets that are mounted near the floor can be difficult to use with angled
jacks. The Designer shall design a solution that allows patch cords to be
inserted and removed without bend radius conflict.
B. In applications where outlets are installed at desk height or bench height, the
Designer shall specify that that the angled jacks are facing down as opposed to
side-facing. The Designer shall specify the appropriate faceplate and jack parts

81 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
to make the cable terminations and furniture well-coordinated.

C. In some applications, GSA may wish to outfit each workstation with a monitor
arm, integrated cable raceway to manage cabling, power bricks for a docking
station mounted under the desk, power strips, power cords, and power splitters.
The Designer shall consult with the GSA IT Tech PM to determine whether a
given project will require these features.
D. Raceways integrated into modular furniture shall have separate channels for
power and data. The channels shall be designed with abrasion protection
features. Abrasion protection shall be installed prior to installation of cabling.
• The Designer shall be attentive to this requirement and make it a condition of
the Construction Contract.
E. For workspace applications with more than four workstations in an area, the
standard treatment is 1.25 ports per workstation.
• Provide one port and one cable per workstation. For every fourth
workstation, provide a second cable in a pattern distributed evenly throughout
the workspace.
• In addition to the workstations, provide cabling for each printer pod location.
For each designated printer pod (modular furniture stations used to host
printers and multifunction copiers), provide two cables per printer but no less
than four cables per printer pod.
• For workstations intended for use by GSA IT personnel, provide four cables
per desk.
F. For cubicle sets of four or fewer modular furniture workstations, the standard
treatment is on average 1.25 ports per cubicle for a total of five ports (with five
copper cables) per cluster of four cubicles.
• Where the design would result with a fractional cable under this formula,
round up. For example, a cluster of two cubicles should be provided with
three ports and three cables (one cubicle would have an outlet with one port
and the other cubicle would have an outlet with two ports).
G. The Designer shall be attentive to cases where a higher cable count would be
beneficial, and shall seek input from the GSA IT ITS on this topic.
H. There are four approved methods of routing cabling to modular furniture, each
with strengths and weaknesses:
1. One Patch Cord Pass-Through
2. Terminated Half Patch Cord
3. Two Coupled Patch Cords
4. Horizontal Cable Pass-Through
The Designer shall discuss with GSA which option(s) is/are to be used for a
particular project. The diagrams below depict the approved options:

Telecommunications Distribution Design Guide [ Version 8 ] 82


4 Design Criteria

FIGURE 9: ONE PATCH CORD PASS-THROUGH

83 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

FIGURE 10: TERMINATED HALF PATCH CORD

Telecommunications Distribution Design Guide [ Version 8 ] 84


4 Design Criteria

FIGURE 11: TWO COUPLED PATCH CORDS

85 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

FIGURE 12: HORIZONTAL CABLE PASS-THROUGH

Horizontal cable
from Telecom
Room
Furred: conduit concealed behind sheetrock

A. Horizontal cable from Telecom


Room, passing through open-face
Unfurred: surface raceway

outlet #1, and terminated in outlet #2.


Building Column

B. Patch Cord from outlet #2 to


Telephone or Computer.
A
Modular Furniture
1. Outlet with open faceplate.
Panel with
Horizontal Cable A passes through
integrated raceways
without terminating.
1
2. Outlet with angled-port faceplate.
2 Terminates Horizontal Cable A and
connects Patch Cord B.
To Telephone
B or Computer

I. For office areas lacking columns and where workstations are located away from
the wall-mounted outlets:
• The design shall include beveled rubber or vinyl cable protection to route
cabling across the floor while protecting it from foot traffic.
• Some situations may require flexible, protective cable whips or wraps.
• Utility poles shall be designed as a last resort.

4.5.1.3 Small Conference Rooms


A. Small conference rooms may also be called “teaming rooms,” “gathering rooms,”
or “mini conference rooms.” The rooms are typically sized for 4 occupants (6
maximum) and usually do not have a conference-style table.
B. Two outlets shall be provided in Small Conference Rooms. The outlets shall be
located on opposite walls (not on a wall with a door) and each shall be provided
with two ports (jacks).

Telecommunications Distribution Design Guide [ Version 8 ] 86


4 Design Criteria

4.5.1.4 Conference Rooms


A. On the end wall of the conference room, provide two power outlets, two telecom
outlets, and two A/V outlets located (concealed) behind a flat panel television and
concealed behind the Equipment Credenza. (See wall elevation below.)
Each application shall be provided with a telecommunications outlet with no
fewer than 4 data ports. The Designer shall inquire with GSA about the A/V
equipment requirements for each application and provide sufficient cabling to
support the equipment.
Each A/V outlet shall be provided with the following features:
• 1 coax TV port.
• 1 HDMI port.
• The Designer shall inquire whether a VGA port is also desired.
In cases where a television panel will not be installed initially, the A/V cabling
may be eliminated from this requirement. However, the conduits and A/V outlet
boxes shall be provided with blank faceplates, along with two power outlets and
two telecom outlets.

FIGURE 13: OUTLET LOCATIONS ON


END WALL OF CONFERENCE ROOM

87 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
B. Conference tables shall either have floor boxes installed beneath them or wall-
mounted boxes installed adjacent to the tables, with patch cords routed up to a
pop-up console providing access to power, HDMI, and data outlets.
• Provide a minimum of two ports per table.
• Provide four power receptacles per table.
• Provide one HDMI port, with the cable routed to a flat panel television on the
end wall of the conference room.
C. Provide one data outlet with two ports in the ceiling in or near each conference
room to host a wireless access point.
D. In addition to a power outlet for a projector, provide one data outlet with two ports
to host a projector in the ceiling of each conference room.
E. If the conference room is intended for shared use by multiple tenants, provide
keyed/secure jacks and matching patch cords for the data outlets. Coordinate
with the GSA IT ITS and GSA PBS PM for the requirements specific to each
conference room.

4.5.1.5 Conference Tables


A. GSA prefers to serve conference tables via a wall-mounted outlet or a floor box
and a tabletop pop-up device to provide access to the ports. Since tables can be
located against a wall or away from a wall, the following six combinations can
occur:
1a. Terminated Half Patch Cord – Table against Wall, Wall Outlet
1b. Terminated Half Patch Cord – Table away from Wall, Wall Outlet
1c. Terminated Half Patch Cord – Table away from Wall, Floor Box
2a. Two Coupled Patch Cords – Table against Wall, Wall Outlet
2b. Two Coupled Patch Cords – Table away from Wall, Wall Outlet
2c. Two Coupled Patch Cords – Table away from Wall, Floor Box
The Designer shall discuss with GSA which option(s) is/are to be used for a
particular project. The diagrams below depict the approved options:

Telecommunications Distribution Design Guide [ Version 8 ] 88


4 Design Criteria

FIGURE 14: TERMINATED HALF PATCH CORD (OPTION 1A)


Concealed: cabling in conduit or interstitial wall

Surface- mounted: cabling in surface raceway


Wall
space (behind sheetrock)

FIGURE 15: TERMINATED HALF PATCH CORD (OPTION 1B)

89 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

FIGURE 16: TERMINATED HALF PATCH CORD (OPTION 1C)

FIGURE 17: TWO COUPLED PATCH CORDS (OPTION 2A)

Telecommunications Distribution Design Guide [ Version 8 ] 90


4 Design Criteria

FIGURE 18: TWO COUPLED PATCH CORDS (OPTION 2B)

Horizontal cable
from Telecom A. Horizontal Cable A from Telecom
Room Two Coupled Room, terminated in outlet #1.
Patch Cords
B. Patch Cord patched in outlet #1 to
double coupler in outlet #2. Patch cord
Concealed: cabling in conduit or interstitial wall

routed through protective cable


Surface- mounted: cabling in surface raceway

management across floor to table leg.


Patch cord may route concealed inside
table leg or attached to the exterior of the
leg.

A To Telephone C. Patch Cord coupled in outlet #2 to


C or Computer Telephone or Computer.
Wall
space (behind sheetrock)

1. Outlet with angled-port faceplate.


2 Terminates Horizontal Cable A and
B connects Patch Cord B.

1 2. Outlet in table-top pop-up device with


double coupler. Couples two Patch
Table Away Cords B and C.
Cable
Management from Wall

FIGURE 19: TWO COUPLED PATCH CORDS (OPTION 2C)

Horizontal cable
from Telecom
Room Two Coupled
Patch Cords
A. Horizontal Cable A from Telecom
Concealed: cabling in conduit (behind sheetrock)

Room, terminated in floor box outlet #1.

B. Patch Cord patched in floor box outlet


#1 to double coupler in outlet #2. Patch
cord may route concealed inside table
leg or attached to the exterior of the leg.
A To Telephone
C or Computer C. Patch Cord coupled in outlet #2 to
Wall

Telephone or Computer.
2
B 1. Floor box outlet with angled-port
faceplate. Terminates Horizontal Cable
A and connects Patch Cord B.

Table Away from 2. Outlet in table-top pop-up device with


double coupler. Couples two Patch
Wall Cords B and C.

Floor
1 Box

91 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

4.5.1.6 Combination IT Storage Room and Staging Workbench


A. Some buildings will require a space for GSA IT storage combined with a
workbench for GSA IT personnel to use while configuring and commissioning
new computers and other IT equipment.
B. The Designer shall inquire with the GSA IT Tech PM about specific design
features needed for this space. As a starting point for this discussion, the
Designer shall anticipate providing a higher concentration of jacks in the vicinity
of the workbench. Outlets shall be mounted approximately 4” above the height of
the workbench surface (without conflicting with a bench-top hutch), and could
conceivably have a dozen or more jacks spread along the length of the
workbench. A corresponding number of duplex power outlets shall also be
provided in a ratio of one duplex receptacle per jack in order to power a computer
and monitor per computer.

4.5.1.7 Special Indoor Applications


A. Outlets serving wireless access points (WAP) shall have two ports each and
shall be mounted near the desired WAP location.
B. Outlets serving IP dome security cameras (some TRs, Data Centers, etc.) shall
have one port each and shall be mounted near the desired camera location.
C. Outlets serving VOIP telephones in waiting areas shall have two ports.
D. Outlets may be designed in mechanical and electrical spaces to provide network
services to mechanical control equipment, electrical power monitoring equipment
and lighting control panels.
E. Outlets serving digital signage shall be provided with one port and appropriate
baluns.
F. Outlets serving televisions shall be provided with one data port and one coax
port.
• The Designer shall be aware of modern audio/visual technologies such as
HDBaseT, which performs most reliably with Shielded CAT6A cabling.
• Equipment (such as television panels) shall be HDBaseT-certified if Power-
over-HDBaseT (POH) is intended for use.
G. Outlets shall be provided in technical spaces to support power monitoring
equipment and other technical equipment.
H. Outlets serving fire alarm panels, elevators, security systems, access control
systems, security systems, security scanning stations, point-of-sale equipment,
etc. shall be provided under the direction of the GSA PBS PM, with input from the
GSA IT ITS and other departments and tenants.
I. During the past decade, many non-computer applications (such as IP Security
Cameras) have converged into the IP network environment. While GSA IT does
not administer these applications, GSA IT does support the cabling and pathway
for them.

Telecommunications Distribution Design Guide [ Version 8 ] 92


4 Design Criteria

• During the design process, consideration shall be given to providing IP


Security Cameras in the following locations:
+ The corridor near a RIC and TR
+ Inside a RIC
+ Storage Rooms
J. Outlets serving Room Wizard applications shall typically be located above the
ceiling. Category 5E cabling shall be used for Room Wizard applications. At the
device end of the cable, provide a field-installed RJ45 connector (not a jack).
Protect cabling as it routes through metallic mullions and drilled holes by using
braided mesh sleeving that is appropriately sized for the cable volume that it
contains. Cabling terminated in an outlet above the ceiling is also acceptable.

4.5.1.8 Special Outdoor Applications


A. Outdoor-rated data outlets may be required to serve outdoor wireless access
points.
B. Outlets serving security cameras, pay phones, power monitoring equipment,
security systems, guard shacks, gate houses, irrigation controllers, etc. shall be
provided under the direction of the GSA PBS PM, with input from the GSA IT ITS
and other departments and tenants.

4.5.1.9 Other Considerations


A. While GSA would prefer to avoid using consolidation points, it is recognized that
there are circumstances that can justify their use.
B. GSA considers undercarpet telecommunications cabling (UTC) solutions to be
undesirable in most cases. The Designer shall discuss any apparent
justifications for undercarpet cabling with the GSA IT ITS prior to its inclusion in a
design and shall also discuss the next best alternative to using undercarpet
cabling.

4.5.1.10 Workstation Power Outlets


A. There shall be at least one general-purpose convenience power outlet (120VAC,
15 Ampere minimum) located within three feet of every telecommunications
outlet. The Designer shall discuss any application-specific needs with GSA IT
staff and adjust the power outlet locations and amperage accordingly.
• In the case of new construction and modernization projects, the power outlet
associated with each telecommunications outlet shall be a 4” x 4” device box
(dual gang) with four power receptacles. It is the Designer’s responsibility to
coordinate with the electrical engineer to ensure that power outlets are
located near telecommunications device boxes.
• In the case of minor remodel, historical building remodel, and
telecommunications-only projects, it may be difficult to meet this requirement.
Therefore, where existing power outlets are not located within six feet of each

93 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
telecommunications outlet, the Designer shall alert GSA IT staff and request
their consideration of the situation on a case-by-case basis.

4.5.1.11 Special Design Considerations


The Designer shall inquire about the requirements for any special design considerations
and how the Architectural Barriers Act Accessibility Standard (ABAAS) requirements will
affect these features, including:
• Coin-operated and other public-use telephones within GSA facilities
• Spaces within GSA facilities which must include ABAAS features
• Point-of-Sale applications
• ATM Machines
• Reception Areas
• Digital Signage

4.5.1.12 Device Box Considerations


A. Device boxes intended for use with low voltage cabling (telecommunications,
CATV, etc.) shall not host electrical power receptacles or power wiring. “Combo
boxes” (divided, multi-gang device boxes for power and data behind a single
faceplate) are not permitted.
B. Device boxes shall not be mounted in the floor (i.e. “floor boxes”) except where
no suitable alternative exists. If device boxes must be mounted in the floor, each
device box shall be served with its own individual conduit – floor boxes shall not
be “daisy-chained” together.
C. Power outlets may be combined with CATV and telecommunications cabling in
floor boxes if the power wiring is routed to the floor boxes separately from the
other cable media and if the floor box provides for metallic barrier segregation of
the power and telecommunications cabling within the box.
D. Providing spare ports for an outlet in a work area and providing spare outlets in a
room are encouraged, within the limitations of the project budget, to meet
projected future needs.
E. Both telecommunications cabling and CATV coaxial cabling are permitted to be
terminated in a shared device box.
F. Device boxes for telecommunications outlets shall be mounted at the same
height as the electrical power receptacles.
G. For projects using Category 6A (Augmented) cabling, the commonly-used 4” x 4”
device boxes may be too small to provide sufficient cable bend radius, for
example when there are five or more cables terminating in the box. Therefore,
where device boxes are used with CAT6A cabling, 5” x 5” device boxes might be
needed, with reducing extension rings and faceplates with angled jacks. The
Designer shall verify cable dimensions and bend radius limitations with the cable
manufacturer to determine whether larger boxes are required.

Telecommunications Distribution Design Guide [ Version 8 ] 94


4 Design Criteria

• As of the date of this writing, there are three sources of 5” x 5” device boxes:
+ RANDL Industries, Inc. (www.randl-inc.com)
+ Thomas & Betts (www.tnb.com)
+ Siemon (www.siemon.com)

4.5.1.12.1 For New Construction and Modernization


A. A device box shall be provided for each telecommunications outlet. Device
boxes shall be 4” x 4” x 3½” (where 2¼” is the depth of the box and 1¼” is the
depth of the extension ring, with an overall depth of 3½”). Device boxes shall be
recess-mounted.
• If Category 6A cabling will be used, the Designer shall require 5” x 5” device
boxes regardless of the cable count.
B. Surface-mounted device boxes are not acceptable. However, for concrete
masonry unit (CMU) walls or other wall types that may obstruct cable or conduit
installation, the Designer shall request direction from the GSA IT ITS on a case-
by-case basis.

4.5.1.12.2 For Minor Remodel, Historical Building and


Telecommunications-Only Projects
A. Existing device boxes and conduits shall be reused where existing boxes are
standards-compliant, or where it can be verified that the existing conduits and
boxes will permit telecommunications cabling to be installed without negatively
affecting the performance of the cabling. The bend radius of the cabling inside
each box shall be considered carefully in evaluating existing boxes. For
concealed conduits that cannot be verified, the GSA IT ITS will decide on a case-
by-case basis whether they are suitable for reuse.
B. A device box shall be provided for each telecommunications outlet. Device
boxes shall be recess-mounted wherever possible, and shall be 4” x 4” and at
least 2½” deep (a 3½” depth is preferable). Surface-mounted device boxes (if
required) may be standard single gang (2” x 4”) and at least 2½” deep.
C. Where cabling can be fished through interstitial wall spaces, it is typically
permissible to use faceplate mounting brackets in lieu of device boxes.

4.5.1.13 Faceplate Considerations


A. GSA prefers to not use 6-pack or 3-pack faceplates for the following reasons:
• Six labels are difficult to fit in the spaces at the top and bottom of the
faceplates.
• There is ambiguity about the labels corresponding to the middle row jacks.
• Utility poles might be the only approvable exception to this requirement due
to potential lack of space for another faceplate.
B. The following table depicts the faceplate, jack, and blank insert combinations that
shall be used:

95 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

TABLE 20: FACEPLATES, JACKS AND BLANK INSERTS

4.5.1.14 Horizontal Pathway Systems


The process of selecting the type of pathway that would be appropriate for a particular
project shall be a cooperative effort involving the Designer and the GSA IT ITS.

Telecommunications Distribution Design Guide [ Version 8 ] 96


4 Design Criteria

4.5.1.14.1 General Pathway Design Considerations


A. All cables shall be fully supported and properly transitioned throughout the length
of the cables, including proper bend radius fittings at pathway transitions. Where
cabling is routed vertically, it shall be appropriately secured such that the weight
of the cabling does not subject the cabling to stresses that could potentially
reduce the performance of the cabling.
• Cable supports shall be installed prior to the installation of cabling. It is not
acceptable to install cabling first, allowing it to hang unsupported, until
supports are later installed.
B. Cabling shall be properly supported whenever it changes elevation (routes higher
or lower). Whenever cabling changes elevation via a free-air gap from one
raceway to another, a radius drop or waterfall fitting is required on the upper
raceway. Whenever the elevation change exceeds 24”, a vertical supporting
raceway is required (such as a wall-mounted ladder rack, or a sloping cable tray).
The following are some examples of solutions that shall be used to prevent
damage to cabling during vertical elevation changes:

97 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

FIGURE 21: CABLE SUPPORT ELEVATIONS

Telecommunications Distribution Design Guide [ Version 8 ] 98


4 Design Criteria

FIGURE 22: CABLE SUPPORT ELEVATIONS

99 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

FIGURE 23: CABLE SUPPORT ELEVATIONS

C. During the Schematic Design phase, the Designer shall discuss pathway type
and size with the GSA IT ITS.
• The Designer shall discuss the relative merits of the pathway options
available and shall assist the GSA ITS staff and the project design team to
select the most appropriate pathway solution for the project.

Telecommunications Distribution Design Guide [ Version 8 ] 100


4 Design Criteria

• The future growth anticipated for the facilities affected by the project shall be
discussed. Horizontal feeder pathways (cable trays, conduits from TRs to
distribution junction boxes) shall be sized to support the initial cabling
installation plus a minimum of 50% growth. In other words, the pathway shall
not exceed 66% of rated capacity after installation is completed.
• J-hook pathways shall be sized to support 100% additional cables after the
original cabling installation. In other words, the pathway shall be no more
than 50% full after installation is completed.
D. Spare pathway shall be designed to terminate at building perimeters where future
expansion of the building is anticipated.
E. When considering the design of a ceiling-located cable tray or J-hook pathway,
the Designer shall verify that the pathway locations will comply with accessibility
and clearance requirements. Cable tray and J-hook pathways routed through
ceiling spaces shall be designed such that all installed cable is conveniently
accessible after construction, both for cable maintenance and to install
subsequent cable additions. J-hooks shall be installed at approximate intervals
of 4 to 5 feet. Conduit shall be used to span inaccessible areas where the
pathway will cross “hard-lid” ceilings, where ceiling tiles are not readily
removable, or where accessibility is impeded.
F. Pathway routing shall remain on the same floor as the telecommunications room
and telecommunications outlets served by the pathways. Where project-specific
conditions exist that justify other routing, the Designer shall request GSA
approval through the SVR process.
G. “Poke-thru” penetrations to the ceiling space of the floor below are normally not
permitted. For minor remodel construction, poke-thru penetrations may be
allowed given budgetary, project size, or other limiting factors. Permission to use
poke-thru pathways in any circumstance requires an SVR on a project-by-project
basis, and always requires the services of a structural engineer to avoid
irreparable structural damage.
H. All wall and floor penetrations for cabling shall be fully sleeved with bushings,
and protected in accordance with the requirements in the International Building
Code.

4.5.1.14.2 Pathways for New Construction and Modernization Projects


A. Where ceiling spaces will be inaccessible after construction, the only permitted
pathway option is conduit. J-hook pathways, cable tray, and wire basket are not
permitted if ceiling spaces will be difficult to access after construction.
B. Surface raceways and surface-mounted device boxes are not permitted.

4.5.1.14.3 Pathways for Minor Remodel and


Telecommunications-Only Projects
A. For minor remodel construction, there may not be an existing (or suitable space
for a new) telecommunications room available on the same floor as an outlet.
While pathways shall generally be designed from the device box serving the

101 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
telecommunications outlet to the nearest telecommunications room on the same
floor as the outlet, this requirement may be waived by the GSA IT ITS.
B. Existing pathways shall be reused where existing raceway is standards-
compliant, or where it can be verified that the existing pathway will permit
telecommunications cabling to be installed without negatively affecting the
performance of the cabling. Where a pathway is concealed or cannot otherwise
be verified, the Designer shall request direction from the GSA IT ITS on a case-
by-case basis.
C. Where existing pathways cannot be reused, or where additional pathways are
required:
• Where less than 40 cables are to be added, J-hook pathway may be used.
D-ring and bridal-ring pathways are not permitted. J-hook pathways shall be
established through concealed, accessible spaces. J-hook pathways shall be
sized for a minimum of 100% expansion. In other words, the pathway shall
be at no more than 50% of rated capacity after installation is completed.
• When 40 or more cables are designed to be routed through an area, the use
of cable tray or conduit shall be considered in lieu of J-hooks.
D. It may be permissible to use faceplate mounting brackets in lieu of device boxes.
In these cases, cabling is routed to the outlet location through interstitial wall
spaces. Permission from GSA IT is required for this method on a project-by-
project basis.

4.5.1.14.4 Cable Tray Pathway Systems


A. In general, cable tray systems shall be located in corridor or office throughway
spaces, and shall not be installed above office or conference room space.
Distances from EMI/RFI sources shall be maintained according to Section 4.2 –
Electromagnetic Compatibility (above), regardless of whether the raceway is
routing copper- or fiber optic-based media.
B. Projects designed using cable tray may use welded-wire type trays in locations
concealed in the ceiling. Where it is not possible to conceal cable trays, the
design shall specify aesthetically finished aluminum or steel cable trays.
C. The Designer shall coordinate the selection of the cable tray materials with the
design intent of the Architect or interior designer.
D. Cable trays shall not be shared with power cables.
E. Conduit used to route cabling from the cable tray to the work area outlet shall be
a minimum of 1” trade-size conduit.
F. Ladder racking shall be used only in the telecommunications rooms. It shall not
be used anywhere else.
G. Spine-style tray is not acceptable.

Telecommunications Distribution Design Guide [ Version 8 ] 102


4 Design Criteria

4.5.1.14.5 Conduit and Junction Box Pathway Systems


A. Ceiling-routed home-run conduit is not a primary preference of GSA. While
certain design circumstances will require this type of pathway, it is expected that
these situations will be rare.
B. In “slab-on-grade” constructed buildings, conduits both in and under the ground
floor slab are considered “wet locations” where indoor-rated cabling is not
permitted. Therefore, conduit serving the main floors of such buildings shall be
routed in walls and ceilings – not in or under the slab. Intra-building and
horizontal pathways shall only be installed in “dry” locations where indoor cabling
can be protected from humidity levels and condensation that are beyond the
intended range of indoor-only rated cable.
C. Where conduit runs terminate at cable trays, the conduits shall be arranged in an
organized, uniform manner to facilitate an orderly cable transition from conduit to
cable tray. Conduits shall terminate within 18” of the cable tray.
D. Where conduit runs terminate in telecommunications rooms, the conduits shall
be arranged in an organized, uniform manner to facilitate an orderly cable
transition from conduit to backboard.
E. Non-metallic conduit and flex conduit shall not be used for horizontal pathways.
• GSA recognizes that in rare cases an application may not be possible without
the use of flex conduit. In such instances, the Designer shall request a
Standards Variance. The Contractor shall consult with GSA prior to using
flex conduit.
F. Conduits shall not be filled beyond 40%. The Designer shall verify the outer
diameter of the cabling for a project at the time of the design, to determine the
maximum number of cables that can be placed inside a conduit without
exceeding the 40% fill limitation.

The Designer shall review the Contractor’s submittals to verify that the cabling
provided is sized such that it is compatible with BICSI’s conduit fill/sizing tables
and that it will not exceed conduit fill limits.
G. In new construction, all work area outlets shall have a minimum 1” conduit
routing from the device box to an accessible cable pulling location. The conduit
size shall be increased as necessary for the quantity of cables to be installed.
• Where new conduit is installed in existing buildings, the Designer shall notify
GSA when existing conditions prevent the use of 1” trade size conduit as a
minimum conduit size. This is not an option left to the Contractor’s
prerogative. In such instances, the Designer shall request a Standards
Variance.
H. Device boxes shall not be “daisy-chained.” Each device box shall be complete
with its own dedicated conduit to the nearest distribution point/pathway.

103 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
I. Junction boxes and pull boxes shall be oriented so that access doors can open
from the area where the cable installer will normally work. For ceiling-mounted
boxes, this is typically from the bottom (floor) side of the box.
J. Ceiling access to junction boxes and pull boxes shall be designed to allow full
access to the door and adequate working room for the installation personnel.
Access shall also be designed to provide space for proper pulling and looping of
the cable during installation.
K. Junction boxes and pull boxes shall be located in spaces that are easily
accessible during normal working hours, such as hallways and common areas.
Junction boxes and pull boxes shall not be located in conference rooms or offices
unless there is an overriding design reason for doing so, dependent upon
approval from GSA.

4.5.1.14.6 Surface Raceway


A. Surface raceway may be permissible in areas where no suitable alternatives
exist. Surface raceway shall conform to bend radius requirements for the cable
type being installed.
B. Surface raceway may be either plastic or metal.

4.5.1.14.7 Underfloor Duct Systems


A. The design of new underfloor duct systems is discouraged. Some existing
buildings have existing underfloor duct systems, and as long as the existing
ducts are suitable for use with new cabling, using the existing ducts is permitted.
B. Walkerduct is permitted where required.

4.5.1.14.8 Access Floors


A. See Section 4.18.3 – Regional Information Center (RIC) for additional details.

4.6 ITS Cables and Connecting Hardware


Please refer to Chapter 6 – ITS Cables and Connecting Hardware in the BICSI TDMM
for information regarding the design of telecommunications cables and connecting
hardware. The following requirements take precedence over the BICSI TDMM
guidelines for telecommunications infrastructure at GSA facilities:

4.6.1 Copper Cabling


A. Where termination blocks are required in the design of new telecommunications
infrastructure at GSA facilities, patch panels and connectors shall be used for
voice and/or data.
B. Utility demarcation points (demarcs) for copper cabling shall use 110-style
blocks. This is the only acceptable use of 110 blocks for GSA IT facilities.

Telecommunications Distribution Design Guide [ Version 8 ] 104


4 Design Criteria

C. The design of new telecommunications infrastructure at GSA facilities shall not


include the use of the following termination blocks or connectors. This prohibition
applies to both voice and data circuits.
• 66-style blocks or connectors
• BIX-style blocks or connectors
• LSA-style blocks or connectors
• 50-position miniature ribbon connectors

4.6.2 Fiber Optic Cabling


A. Fiber optic cabling shall be terminated at both patch panels and outlets using LC-
style connectors.
B. Where an application requires connectors with more than two strands of fiber
(40GB/100GB high bandwidth applications, pre-terminated cables, etc.), MTP or
MPO connectors shall be used in accordance with manufacturer
recommendations. Other connector types may be approved by GSA IT ITS on a
case-by-case basis.
C. All other connector styles (including SC, ST, and MTRJ) are prohibited for new
fiber optic cabling at GSA facilities. Where equipment does not support LC-style
connectors, the Designer shall specify hybrid patch cords with LC connectors on
one end, with the other end matching the requirements of the equipment.

4.6.3 Splicing
Except for the purpose of connectorizing fiber optic cabling at the termination points
(typically in telecommunication rooms), splicing or coupling copper or fiber optic cable is
prohibited for inside plant infrastructure.
• Spliced or coupled copper cabling will not pass the industry-standard testing
procedures.
• Spliced fiber optic cabling will exhibit a reduced link-loss budget compared
with unspliced fiber optic cabling. Some systems (such as Distributed
Antenna Systems) are very sensitive to reductions in headroom.
Inside plant fiber optic and copper cabling shall not be installed new in a spliced or
coupled manner. Inadvertent damage to existing inside plant fiber optic and copper
cabling shall be repaired by completely replacing the damaged cable from end to end.
Repairs shall not be achieved through splicing or coupling cables.

4.6.3.1 General
A. The Designer shall work with the GSA PBS PM and the GSA IT ITS to identify
and understand the needs and requirements for the facility on a project-by-
project basis. This includes understanding the expected future uses of the
facility. The Designer shall design the horizontal cabling accordingly.

105 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
B. Telecommunications infrastructure designs and specifications shall be based
upon products from approvable manufacturers, as defined in TDDG Section
2.4.1.2.2 – Approvable SCS Manufacturers, above.
C. GSA has standardized on the use of plenum-rated cabling, regardless of the
application and regardless of whether the building contains plenum-rated
pathways.
D. The modular jacks on both the workstation outlet and patch panel shall use the
T568A eight-position pin/pair assignment for new cabling in new construction, as
required by FIPS 174.
E. Splitting of wire pairs degrades the performance of the cable pairs and voids the
manufacturer’s warranty.
• Under no circumstances shall cable pairs be split or removed from the back
of a modular jack or patch panel. All four (4) pairs of each horizontal
distribution cable must be terminated to a single eight (8)-position, eight (8)-
conductor jack.
• To support an additional analog telephone at a work area on existing cable,
install an external line-splitting device on the outside of the faceplate and
connect the additional cross-connect wires to the appropriate pins on the
connecting blocks in the TR.
F. Whenever moves, adds, or changes (MAC) are made to existing systems, the
new cabling shall follow the routes of existing established telecommunications
cabling pathways.
G. Recently, some manufacturers have developed “small-diameter” Category 6A
cable products. These products can provide desirable benefits (compared with
standard Category 6A products). The Designer shall suggest this option for
GSA’s consideration where appropriate in horizontal applications and for patch
cords.

4.6.3.2 Topology
A. GSA has standardized on the star topology for all horizontal cabling, with some
exceptions for certain building automation systems that require (or benefit greatly
from) ring or other topologies.
• Horizontal cables must terminate in a patch panel. Do not “connectorize”
horizontal cables, bypassing the patch panel to plug directly into a network
switch.
B. GSA IT accepts the ANSI/BICSI 005 standard practice of field-connectorizing the
outlet end of a horizontal cable (as opposed to terminating the cable in a jack) for
permanent building feature applications that are installed by technicians. This
solution allows the horizontal cable to plug directly into a video surveillance
camera or other device without requiring a jack, faceplate, or patch cord. The
telecommunications room end of the cable must still terminate on a patch panel.
Horizontal cables terminated in this fashion shall be tested using the appropriate
test methodology for a connectorized horizontal cable.

Telecommunications Distribution Design Guide [ Version 8 ] 106


4 Design Criteria

C. The centralized fiber optic cabling alternative topology is rarely useful for GSA
facilities.

4.6.3.3 Horizontal Cross-Connect (HC)


A. GSA has standardized on angled patch panels with black ports/jacks for
terminating all copper horizontal telecommunications media, regardless of the
intended use of the horizontal cabling, including cabling that will be used for
voice, data, or IP video.
• The two primary benefits of angled patch panels are to:
+ Provide additional finger space for patch cord insertion.
+ Dress patch cords without the use of adjacent horizontal cable
management panels.
• In order to achieve these two benefits, the angle of the patch panel must be
less than 130 degrees, but at least 90 degrees. In other words, the peak of
the patch panel must extend at least four inches away from the face of the
rack, as shown in the figure below. The purposes of these requirements are
to:
+ Increase the amount of space available for labeling.
+ Improve the patch cord management.
+ Increase the amount of finger space to insert and remove patch cords.

FIGURE 24: ANGLED PATCH PANEL REQUIREMENTS

• Patch panels shall allow for jack modules to snap into the patch panel frame
from the rear of the patch panel, so that cables can be rearranged within the
patch panel without requiring the cable to be cut from the jack and re-
terminated.
B. The following applications require dedicated patch panels:
• All horizontal cabling that supports devices mounted in the ceiling (wireless
access points, security cameras, etc.) shall terminate on a patch panel that is
separately dedicated for above-ceiling applications.

107 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

• All horizontal cabling that supports access control and security devices (door
card readers, access code keypads, sensors, etc.) shall terminate on a patch
panel that is separately dedicated for access control and security
applications.
C. See Appendix 6.6 for a diagram that depicts GSA’s standard patch cord colors.
Patch cords in the telecommunications rooms shall be colored as follows:
• Workstation applications (computer, phone, etc.) – Yellow
• Network printers – Green
• Servers and managed devices (SANs, Tape Backup, UPSes, etc.) – Black
• Wireless access points – Blue
• Circuits – Red
• Analog connections – Gray
• Audio/visual (Room Wizard) – Orange
• Building automation systems – Purple/Violet
• Security – White

4.6.3.4 Horizontal Cable to Support Data Applications


A. At GSA facilities, horizontal distribution copper cable and components for data
applications shall be rated for and installed to support the IEEE 802.3ab
1000Base-T Gigabit Ethernet standard.
B. In new installations, horizontal cable supporting data applications (and all other
low voltage systems that are capable of operating with 24 AWG UTP copper
cabling) shall be 4-pair 100-ohm Category 5e or better cable. The Designer shall
inquire which cabling should be used for a given project.
• Horizontal cables shall be terminated at the work area end and patch panel
end with modular jacks.
• The Designer shall coordinate the modular jack and faceplate color (at the
outlet) with GSA or the interior designer for a project.
• GSA has standardized on white as the horizontal cable color. The Designer
shall inquire with GSA whether cable color should be different for a given
project.
+ Some cable manufacturers have developed standards-compliant
telecommunications cabling using UTP cabling with conductors that are
smaller than 24 AWG. GSA IT is willing to accept such materials so long
as they meet all industry-standard performance requirements and also the
requirements of the TDDG.
+ The equipment used in RICs operates at 10GB speeds, which require the
use of Category 6A cabling. Do not install Category 5e or Category 6
cabling between RIC cabinets. See Section 4.18.3 – Regional Information
Center (RIC) for additional details.
C. In existing buildings, where additions are made to an existing Category 5 or 5e
installation, the Designer shall seek direction from GSA regarding whether to
install Category 5e or Category 6 cabling. If the number of additional cables to
be installed is small compared to the installed base, GSA will likely wish to add

Telecommunications Distribution Design Guide [ Version 8 ] 108


4 Design Criteria

new Category 5e cabling. If the number of new cables to be installed is relatively


large, GSA may choose to use Category 6 cable and matching components.
• Category 5 cable and components shall not be purchased or installed.
• Category 5e or 6 cables shall be terminated at the work area end with a
modular jack matching the category of the cabling.
• Modular jack color (at the outlet) shall be coordinated with GSA by the
Designer.
D. See Appendix 6.6 for a diagram that depicts GSA’s standard horizontal cable
colors.

4.6.3.5 Horizontal Cable to Support Above-Ceiling Data Applications


A. All horizontal cabling that supports devices mounted in the ceiling (wireless
access points, security cameras, etc.) shall use Category 6A-rated cabling. See
TDDG Section 4.16 – Wireless for additional information.
B. Provide two cables to each above-ceiling outlet.
C. Plenum-rated patch cords are required for above-ceiling applications.

4.6.3.6 Horizontal Cable to Support Voice Applications


A. GSA uses VOIP for all new voice applications, and networks the workstation
computer through the VOIP telephone. Therefore, only one Category 5e or
better horizontal cable is required. This cabling shall meet the same
performance and test requirements as cabling intended for data applications.
B. In existing buildings where Category 3 cabling currently serves voice applications
for non-VOIP telephone systems, Category 5e or better cable shall be used when
new voice cabling is installed. GSA is in the process of converting all of its
telephone systems to VOIP. Therefore, it would be prudent to install Category 5e
or better cabling even if analog telephones are being used. Each workstation will
require two cables under this scenario, because the computer and telephone will
be separately connected.

4.6.3.7 Horizontal Cable to Support Low Voltage and


Building Automation Systems
A. During planning for intra-building telecommunications cabling installations, the
Designer shall identify options for supporting power-limited (low voltage) and
building automation systems with the common structured cabling system, and
present the options to GSA for consideration. These options shall comply with
ANSI/TIA/EIA 862-A – Building Automation Systems Cabling Standard.
B. By providing a common cabling distribution system for the various building
automation systems, it may be possible to reduce construction costs and
operational costs while creating an intelligent building that can contribute many
other benefits (see TDMM Chapter 16 – Building Automation Systems for further
information). Low voltage systems that are capable of using a common
structured cabling system (either backbone or horizontal cabling) shall be

109 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
designed to use telecommunications cable and termination hardware wherever
possible.
C. The Designer shall request from GSA a list of systems that will require
telecommunications outlets for operations. The Designer shall then include
outlets in the design as necessary to meet the listed requirements.

4.6.3.8 Patch Cords


A. Patch cords shall be factory-manufactured and shall be certified by the
manufacturer to match the cable type used in the horizontal distribution.
• Category 5e patch cords are only permitted for use with Category 5e
horizontal cabling applications.
• Category 6 patch cords are permitted for use with both Category 5e and
Category 6 horizontal cabling applications.
• For Category 6A applications, Category 6A patch cords shall be used.
• Patch cords shall be factory-assembled by the SCS manufacturer. Field-
connectorized patch cords are not acceptable. Any existing field-
connectorized patch cords used in areas affected by a project shall be
replaced under the project with factory-assembled patch cords.
• Analog patch cords shall be Category 5e or better.
• Patch cord colors shall be as depicted in Appendix 6.6.
B. Patch cords for devices mounted in the ceiling (wireless access points, security
cameras, etc.) shall be plenum-rated, Category 6A-rated, and white-colored.
Patch cords would not be required for applications that are terminated with
connectors per ANSI/BICSI 005. See Section 4.6.3.2 – Topology for further
information.
C. The Designer shall quantify and specify the required patch cords in the Contract
Documents to be provided by the Contractor for each particular project, as shown
in the table, below:

Telecommunications Distribution Design Guide [ Version 8 ] 110


4 Design Criteria

TABLE 25: COPPER PATCH CORD REQUIREMENTS

Applications Copper Patch Cord Requirements Length


Work Area Typically require that patch cords matching For each application that is known,
the rating of the horizontal cable shall be provide a length that will reach the
(Outlet end) furnished and possibly installed by the equipment plus 6 ft to 10 ft additional
Contractor. A quantity of one patch cord for length. Otherwise, provide a 10 ft patch
each port installed, plus 10% spare. This cord.
shall be confirmed with the GSA IT ITS on
a case-by-case basis.
Telecom Room Typically require that patch cords matching Provide patch cords in lengths sufficient
the rating of the horizontal cable shall be to reach between patch panels and
(Patch Panel furnished and possibly installed by the network switches. Patch cords shall
end) Contractor. A quantity of one patch cord for also be long enough to permit future
each port installed, plus 10% spare. This repatching without excessive slack. The
shall be confirmed with the GSA IT ITS on majority of the patch cords will need to
a case-by-case basis. fall within a 5 ft to 7 ft range. A small
percentage of short (3 ft) patch cords
and long (10 ft) patch cords will typically
also be needed.

D. The Designer shall inquire with GSA IT whether the patch cords for a project
should be installed by the Contractor or GSA IT, both in the telecommunications
rooms and at the workstation end. For projects where the patch cords are to be
installed by the Contractor, the Designer shall include requirements in the
Construction Documents to achieve the following:
• In the telecommunications rooms, the patch cords do not require labels.

• At the workstation end, the patch cord shall be labeled at the location
indicated in the diagram below, with a label matching the label for the
faceplate jack to which the patch cord is connected.

• See the diagram below depicting these requirements.

• Horizontal cable testing shall be a Link Test, even for applications where the
workstation patch cord is to be installed by the Contractor. Do not perform a
Channel Test.

111 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

FIGURE 26: HORIZONTAL CABLES AND COPPER PATCH CORD


LABELING REQUIREMENTS

4.7 Firestop Systems


Please refer to Chapter 7 – Firestop Systems in the BICSI TDMM for general information
regarding the design of firestopping for telecommunications infrastructure. The following
requirements take precedence over the BICSI TDMM guidelines for telecommunications
infrastructure at GSA facilities:
A. The Designer shall pay careful attention to the fire ratings of existing and new
walls. Wherever penetrations are made through fire-rated walls, the Drawings
shall identify the firestopping requirements.
B. Penetrations through fire-rated walls and floors shall be firestopped in
accordance with the requirements of the manufacturer of the firestopping
materials and shall also satisfy local code officials.
C. The Designer shall avoid design solutions calling for penetration of fire walls, fire
barriers, fire partitions, smoke barriers, and smoke partitions when other
reasonable cable-routing options exist.
D. The predominant color of fire-rated pathway devices shall be red.
E. The use of manufactured closeable fire-rated penetration devices is encouraged
and accepted.

Telecommunications Distribution Design Guide [ Version 8 ] 112


4 Design Criteria

4.8 Bonding and Grounding (Earthing)


Please refer to Chapter 8 – Bonding and Grounding (Earthing) in the BICSI TDMM for
general information regarding the design of grounding, bonding, and electrical protection
systems. The following requirements take precedence over the BICSI TDMM guidelines
for telecommunications infrastructure at GSA facilities:
• Grounding and bonding conductors shall be sized according to the
requirements in ANSI/TIA/EIA J-STD-607-B.
A. See PBS P100-2016, Section 6.5 for additional requirements.
B. The Telecommunications Grounding Busbar shall be sized to allow for at least
25% available (unused) terminal spaces for future use after the project is
completed.
C. Bonding conductors shall be run between each piece of non-current-carrying,
metallic equipment in each telecommunications room and the
Telecommunications Grounding Busbar in that room.
D. Bonding conductors shall run unspliced between termination points. Riser
bonding conductors that route from the MDF up to upper floor IDFs shall be
continuous conductors (unspliced, uncut) but exothermically welded at each
Telecommunications Grounding Busbar en route to the upper floor.
E. Power outlets circuited to technical power panels shall be properly grounded and
bonded. Where power outlets are attached to unistrut mounting hardware, the
unistrut shall be bonded. Power outlet bonding shall be checked periodically and
tightened when impedance values are approaching maximum limits.
F. Avoid unnecessary loops, unnecessary length, and sharp bends in the bonding
conductors. Conductors should run as directly as possible.
G. Bonding conductors shall be terminated at each end using UL-listed termination
methods. Verify that conductors are inserted completely into the terminal lugs
(visible in the inspection window of the lug), and that crimped connections
accomplish a solid mechanical compression. Verify that bonding hardware
breaks through paint and powder coatings to make solid, reliable contact with the
metal substrate.
• Terminations at grounding busbars shall be made with dual-hole, dual-crimp
lugs with two hex-head bolts, properly crimped (using a crimping/swaging tool)
and tightened to meet the manufacturer’s torque specifications. Phillips-head
screws are not acceptable.
H. A #6 AWG bonding conductor shall be run from the grounding busbar in the
technical power panel and the Telecommunications Grounding Busbar.
I. All bonding conductors shall be labeled to identify the termination point of the
opposite end of the conductor.
J. Contractors who design/bid projects for GSA shall include the bonding and
grounding design in their bid submittal, as described in TDDG Section 3.4.4 –
Bidding, above.
113 Telecommunications Distribution Design Guide [ Version 8 ]
Design Criteria 4
K. In GSA facilities, the TRs in a building may also serve as low voltage systems
equipment rooms, typically containing electronic equipment intended to serve the
building or a portion of the building. The TR shall not be shared with electrical
installations other than those necessary for telecommunications.

4.9 Power Distribution


Please refer to Chapter 10 – Power Distribution in the BICSI TDMM for general
information regarding the design of power distribution for telecommunications
infrastructure. The following requirements take precedence over the BICSI TDMM
guidelines for telecommunications infrastructure at GSA facilities:
A. The Designer shall be responsible to determine that the electrical power
distribution requirements supporting the telecommunications infrastructure are
met as described in this document.
B. For projects where an electrical engineer is involved, the Designer shall
coordinate directly with the engineer, and verify that the engineer’s design
documentation meets these requirements. For projects without the involvement
of an electrical engineer, the Designer shall alert GSA where additional power
infrastructure is needed to meet the requirements.
• Please refer to Chapter 5.1 – Work Areas in the BICSI TDMM and also in
TDDG Section 4.5.1 – Work Areas for information on the power outlet
requirements for work areas.
• Please refer to Chapter 3 – Telecommunications Spaces in the BICSI TDMM
and also in TDDG Section 4.3 – Telecommunications Spaces for information
on the power outlet requirements for TRs.
+ GSA typically provides network electronics that provide Power-over-
Ethernet.
+ The Designer shall request power consumption data for the equipment that
GSA will use, and will size the power distribution infrastructure sufficient to
support this equipment.
• Please refer to Chapter 21 – Data Centers in the BICSI TDMM and also in
TDDG Section 4.18 – Regional Information Centers and Data Centers for
information on the power outlet requirements for RICs and Data Centers.
C. The Designer shall inquire about and evaluate which type of power
conditioning/power protection equipment should be designed for each project.
The most common solutions for technology projects include:
+ Rack-mounted chemical-battery UPS equipment
+ Centralized UPS equipment (either flywheel or chemical-battery UPS
equipment)

Telecommunications Distribution Design Guide [ Version 8 ] 114


4 Design Criteria

4.10 Telecommunications Administration


Please refer to Chapter 10 – Telecommunications Administration in the BICSI TDMM for
general information regarding the documentation and labeling of telecommunications
infrastructure. The following requirements take precedence over the BICSI TDMM
guidelines for telecommunications infrastructure at GSA facilities:

4.10.1 Identification Strategy


A. The “identifier” is the unique name or description assigned to a given
telecommunications infrastructure component. The Designer shall assign
identifiers to the telecommunications infrastructure components listed below and
clearly show the identifier assignments on the Construction Documents.
B. While it is the Contractor’s responsibility to provide marked-up drawings to the
Designer indicating any construction-related changes to the identifiers, the
Designer shall verify that the identifiers are clearly and accurately shown on the
record drawings.
C. Telecommunications components shall not be labeled with an application-
specific identifier. Ports shall not be labeled with the name or function of the
device that is served by the port (server names, computer types. Also, the use of
“V-#” and “D-#” are inconsistent with the industry-standard-based philosophy of
designing cabling systems that are independent of the application, and are
therefore not permitted.
D. The Designer shall prepare construction specifications that shall contain a
comprehensive listing of the identification strategy requirements.
E. Due to widely varying conditions among the many buildings that GSA manages,
some building circumstances may require adjustments to the identification
scheme. The Designer shall obtain approval from the GSA IT ITS before
committing to a scheme. The Designer and installation contractor are advised to
confirm with the GSA IT ITS that their intended identification and labeling scheme
will be satisfactory to GSA prior to installing labels, to avoid the risk of removing
and reapplying labels to make corrections.

4.10.1.1 Labeling Materials


A. Labeling for permanent hardware shall be engraved, phenolic nameplates.
B. Acceptable cable labeling stock must support laser printing and have a clear
overwrap. Labeling practices shall be consistent throughout a project. P-Touch
labeling and similar labeling equipment is not acceptable. The figure below
depicts acceptable labeling materials and practices:

115 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

FIGURE 27: CABLE LABELING DIAGRAM

4.10.1.2 New Telecommunications Distribution Systems


The items listed below shall be shown on the Construction Documents. The Designer
shall assign the identifiers to the telecommunications components based on the
following suggested identification strategy. The circumstances of each project may
require adjustments. The Designer shall discuss with GSA any recommendations for
customization, and cooperatively develop an identification strategy prior to adopting any
customizations.
A. Telecommunications Rooms, Equipment Rooms, and Data Centers shall be
identified by their room number. If a telecommunications room does not have an
assigned room number, then the room shall be identified as “TR#@”, where “#” is
the floor number on which the telecommunications room resides and “@”
represents the building quadrant as shown in the diagram below.
+ For example: a telecommunications room located in Room #1242 in a
building would be identified as “1242”.
+ For example: an un-numbered telecommunications room on the third floor
located in the Northeast quadrant would be labeled “TR3B”.

Telecommunications Distribution Design Guide [ Version 8 ] 116


4 Design Criteria

North Side
Northwest Northeast
Quadrant Quadrant
3rd Floor of
A B the Building
Telecom Building
Room Quadrant

D C
Southwest Southeast
Quadrant Quadrant
South Side

B. Racks in telecommunications rooms shall have identifiers of the form “@” where
“@” is a sequentially lettered rack (A, B, C, D, etc.) from left to right as viewed
from the front of the rack.
+ For example: Two general-purpose racks in a given telecommunications
room would have the labels “A” and “B”.
C. Fiber Optic Patch Panels shall have identifiers sequentially
numbered in the form of “F#” where “F” stands for “Fiber” and Fiber 1st Fiber
Patch Patch Panel
“#” is the sequential fiber optic patch panel number terminated Panel in the Rack
within a given telecommunications room. The numbering
sequence does not restart for each rack.
F1
+ For example: the first fiber optic patch panel would be
labeled “F1”. The second fiber optic patch panel would be labeled “F2”.
D. Ports on Patch Panels for fiber optic cabling are
typically pre-labeled by the manufacturer with
sequential numbers (i.e. 1 to 12). For ports First Connector in
which are not pre-labeled, label each port in the Mounting Space
form “@##” where “@” is the alphabetical letter 2nd Mounting
Space in Fiber 2nd TR on
for the mounting space and “##” is the Patch Panel the 3rd Floor
sequential port number within the mounting
space. The ports in each mounting space shall
start at number “01”. Note: the ports are B01 TR3B
labeled, not the strands.
• In addition to the pre-labeling, each port shall also be labeled with the far-end
termination point of the cable terminated at that port.
+ For example: the ports on a patch panel terminating fiber optic cabling in
duplex LC ports in the second mounting space in the patch panel would be
labeled starting with “B01” for the first duplex port (one label per pair of
117 Telecommunications Distribution Design Guide [ Version 8 ]
Design Criteria 4
fiber strands) and continue sequentially through the remainder of the
duplex ports. Also, the port labeling shall also indicate the room number
where the fiber optic cable terminates.
E. Copper Patch Panels shall have identifiers sequentially numbered in the form of
“@#” where “@” is the rack designation and “#” is the
sequential copper patch panel number terminated
within a given telecommunications rack. The
numbering sequence restarts for each rack. Patch
panels may also be lettered “W” to designate a rack
dedicated to Wireless applications
+ For example: the second copper patch panel in Rack A would be labeled
“A2”. The second copper patch panel in Rack B would be labeled “B2”.

F. Ports on Patch Panels for copper cabling are typically pre- The room
labeled by the manufacturer with sequential numbers (i.e. 1 8th Port in where the
to 48). For ports which are not pre-labeled, label each port Patch Panel cable ends

in the form “##” where “##” is the sequential port number


within the panel. The ports in each patch panel shall start at 08 2453
number “01”.
• In addition to the pre-labeling, each port shall also be labeled with the far-end
termination point of the cable terminated at that port.
+ For example: the ports on a patch panel terminating horizontal copper
cabling serving an outlet would be labeled starting with “01” for the first port
and continue sequentially through the remainder of the ports. Also, the
port labeling shall also indicate the room number where the copper cable
terminates.

G. Work Area Connectors (jacks in outlets) shall have identifiers in the form of
“####-@#-##” designating the
telecommunications room where the cable
terminates on the far end. The label is
constructed with “####” as the room number
of the telecommunications room, “@#” as the
rack and patch panel identifier and “##” as
the port number on the patch panel where
the horizontal cable terminates.
+ For example: if an outlet is used to terminate two cables from telecom room
number “TR3B”, rack 2, and patch panel 3 in that rack, on ports 12 and 13,
then the connectors (jacks) would have the labels “TR3B-B3-12” and
“TR3B-B3-13”, respectively.

For outlets that are located above a T-bar ceiling, a duplicate set of white labels
shall be applied to the ceiling grid (in addition to the faceplate labeling) so that
the jack numbering can be seen without lifting the ceiling tiles. These labels are

Telecommunications Distribution Design Guide [ Version 8 ] 118


4 Design Criteria

intended to be inconspicuous to the casual viewer while allowing a technician to


easily find an outlet.

H. Backbone Cables (both fiber optic and copper) shall be labeled every 6 feet
throughout the length of the cables. The labels shall designate the origin,
destination, and owner of the cable.

4.10.1.3 Moves, Adds, and Changes (MAC)


The only exception to the above identification scheme is for small projects relating to
moves or changes to existing cabling, or the addition of new outlets terminated among
other existing cables in existing TRs. In such cases (where the amount of new work is
small compared to the overall system) the cable identification scheme for the new cables
shall be consistent with the existing identification scheme.
For projects where the amount of change is larger, the Designer shall inquire with GSA
whether it is desirable to re-label the existing cables when new cabling is being installed.

4.11 Field Testing of Structured Cabling


Please refer to Chapter 11 – Field Testing of Structured Cabling in the BICSI TDMM for
general information regarding the field testing of telecommunications cabling. The
following requirements take precedence over the BICSI TDMM guidelines for field
testing at GSA facilities:
A. The Designer shall require the Contractor to test 100% of field-terminated cabling
and at least 10% of all pre-terminated cables.
• GSA reserves the right to require the Contractor to test more than 10% of all
pre-terminated cables if the 10% test results are unsatisfactory.
• Copper cables shall be Link-tested (not Channel-tested).
B. Cable tester equipment shall be manufactured by Fluke.
C. The Designer shall review the cable test results submitted by the Contractor.
The test results shall be the actual native machine test results downloaded from
the test equipment. In particular, the Designer shall check for the following items
on the cable test reports:
• The cable test report shall be automatically produced by the test equipment.
• The report shall indicate that the cable passed the test. It shall also indicate
the date of calibration, the software version, and the name of the technician
who conducted the test. The reports shall also include graphical results of
the performance curves obtained during the testing.
• Indications that the cabling meets distance limitation requirements.
• Indications that the wire map of the cable is correct.
• Indications that the cable test equipment was properly configured. For
copper cabling, the test equipment’s configuration parameter for Nominal

119 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
Velocity of Propagation (NVP) shall match the value stated by the cabling
manufacturer for the type of cable installed.
• For Fiber Optic Cabling: the cable test report shall indicate a headroom dB
value that is equal to or better than the value calculated in the link-loss
budget.
• Marginal test results (typically indicated with an asterisk “*”) are only
acceptable when the condition is “over length” and when the over-length
situation was intentional during design. For example, a low-bandwidth device
might be served by a cable that would otherwise be too long to support a
high-bandwidth device. Over-length issues due to choice of routing or extra
service loops are not acceptable.
D. The cabling performance characteristics shall meet or exceed the performance
guaranteed by the manufacturer, which may exceed standard industry
requirements. In other words, even though a particular cable might pass its
tests, the cable might still be rejected (requiring re-termination or replacement) if
it does not meet the higher standard of performance that the manufacturer may
list for its products.
E. GSA may choose to spot-test cabling to back-check the Contractor’s test results.
F. GSA may choose to hire a third-party cable test company to conduct an
independent cabling test.
G. The final test results shall have been verified by the Designer to be acceptable
before submission to GSA. Test results shall be submitted to GSA in electronic
form, both in PDF form and also the original test result data files.
H. Contractors shall be required to retain a copy of the test reports for a period of at
least 5 years after installation.

4.12 Outside Plant


Please refer to Chapter 12 – Outside Plant in the BICSI TDMM and the BICSI Outside
Plant Design Reference Manual (OSPDRM) for information regarding the design of
outside plant telecommunications infrastructure.
Most of GSA’s facilities are stand-alone buildings. Telecommunications services
delivered to the building are provided by commercial service providers. As a result, it is
unlikely that a project will include requirements for outside plant telecommunications
infrastructure.
The Designer shall inquire about the pathway requirements for telecommunications
service providers, and shall design the pathway to meet the requirements of the service
providers.

Telecommunications Distribution Design Guide [ Version 8 ] 120


4 Design Criteria

4.13 Audio/Visual Systems


Please refer to Chapter 13 – Audiovisual Systems in the BICSI TDMM for information
regarding the design of telecommunications infrastructure to support private CATV
distribution systems at GSA facilities.

4.13.1 Private CATV Distribution Systems


The Designer shall inquire with GSA to determine where cable television outlets are
required for a given project. The Designer shall also inquire whether inside plant coaxial
cabling or CAT5e cabling with skew-adjustable baluns will be required for cable
television distribution inside the building.

4.13.2 Distributed Paging Systems


The Designer shall inquire with GSA to determine whether emergency response paging
systems are required for a given project.

4.14 Building Automation Systems


Please refer to Chapter 14 – Building Automation Systems in the BICSI TDMM for
information regarding the design of telecommunications infrastructure to support building
automation systems at GSA facilities.
A. GSA will have a new document titled “Building Technologies Technical
Reference Guide” to be published soon with guidelines about Building
Automation Systems. The Designer shall inquire about the availability of this
document during the course of design.
• Where conflicts may arise between the Building Technologies Technical
Reference Guide and the TDDG, seek guidance from the project manager or
contracting officer.
• For projects that primarily involve building automation systems, the Building
Technologies Technical Reference Guide will govern.
B. ANSI/TIA/EIA-862-A applies to telecommunications infrastructure serving
building automation systems (BAS). The Designer shall pay particular attention
to the following BAS issues:
• Verify that the voltage and current requirements of each BAS application are
satisfied by the cabling materials to be installed.
• Verify that a suitable horizontal connection point (HCP) is installed for each
BAS application.
C. BAS devices are increasingly converging onto structured cabling systems. While
the design of these systems is typically outside the scope of work of the
telecommunications infrastructure designer, the Designer shall design the
telecommunications cabling required to support these systems.

121 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
D. Typically, BAS systems require telecommunications cabling routed from the
devices to a patch panel termination point in a designated mechanical room or
other location managed by building maintenance personnel. In addition to the
device-specific cables, other cables shall be designed from the
telecommunications rooms to the BAS patch panels, to permit these systems to
gain access to the data networks.
E. Horizontal connection points are only required for BAS applications. Do not use
an HCP for typical voice/data/video applications.
F. The following diagram depicts two approved horizontal cabling strategies for
supporting BAS devices and systems. This diagram also applies to Electronic
Safety and Security (ESS) devices, as described in TDDG Section 4.17 –
Electronic Safety and Security, below.

FIGURE 28: HORIZONTAL CABLING OPTIONS FOR


BUILDING AUTOMATION SYSTEMS AND
ELECTRONIC SAFETY & SECURITY DEVICES

Telecommunications Distribution Design Guide [ Version 8 ] 122


4 Design Criteria

4.15 Data Network Design


Please refer to Chapter 15 – Data Network Design in the BICSI TDMM for general
information regarding the design of telecommunications infrastructure for serving local
area networks. The following requirements take precedence over the BICSI TDMM
guidelines for telecommunications infrastructure at GSA facilities:
A. All GSA facilities use the Ethernet LAN protocol. Telecommunications
infrastructure for all GSA facilities shall be designed, installed, and tested to
support the Institute of Electrical and Electronic Engineers (IEEE) Ethernet 802.3
standards. GSA networks use the 1000Base-X Gigabit Ethernet protocol based
on the IEEE 802.3z standard. All newly installed cabling shall support this
protocol. The Designer shall give careful consideration to the multimode fiber
optic distance limitations and signal loss limitations (less than 2.5 dB end-to-end)
necessary to support the IEEE 802.3z protocol. GSA networks are typically
based on Cisco switches (Power-over Ethernet), with 1GB or 10GB backbones
and 100MB or 1GB service to the work area.
B. The design of the network electronics is the responsibility of GSA IT and is
outside the scope of work of the telecommunications designer.
C. The Designer shall coordinate with the GSA IT Internetworking & Security Branch
to determine the requirements for supporting the network electronics in each
space. The design shall provide rack space to host GSA’s network equipment.

4.16 Wireless
Please refer to Chapter 16 – Wireless in the BICSI TDMM for information regarding the
design of telecommunications infrastructure to support wireless and microwave
telecommunications systems at GSA facilities.
A. GSA currently uses Cisco’s Aeronet wireless access point equipment in its
buildings. Model numbers may change without notice. The Designer shall
inquire with GSA to determine which model numbers are currently being used.
The manufacturer’s requirements shall be met when designing wireless network
infrastructure. This equipment operates with Power-over-Ethernet. The
Designer shall accommodate POE equipment in the design, including the power
and cooling requirements.
• Regional Office Buildings typically use the 3500 series.
• Field offices typically use the 1100 series.
B. GSA currently uses Oberon’s 1064 and 1064-T enclosures for wireless access
point equipment in its buildings. Model numbers may change without notice.
The Designer shall verify that model numbers included in the design are current
and appropriate for each project.
C. The Designer shall work cooperatively with GSA IT ITS staff to design
telecommunications infrastructure to appropriately support wireless technologies.

123 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
Typically, GSA will identify the locations where wireless access points (WAP) are
desired. On occasion, however, GSA may request services to identify
appropriate WAP locations and prepare associated coverage and signal strength
maps.
D. Wireless access points will be “Owner-furnished, Contractor installed” (OFCI).
GSA will supply new, packaged wireless access point equipment to the
Contractor, who will be required to mount the equipment and provide patch cords
at the device end and network switch end to cause the equipment to power on
via Power-over-Ethernet. GSA IT will then provide services to configure the
wireless access points. The Designer shall indicate these requirements in the
Construction Documents.
E. The Industry is trending toward improvements in speed and capacity. Currently,
GSA requires at least two CAT6A cables for each WAP outlet location. However,
depending on the size of the project and budget, the Designer shall inquire with
GSA to determine whether only 1 cable should be provided.

4.17 Electronic Safety and Security


Please refer to Chapter 17 – Electronic Safety and Security in the BICSI TDMM for
general information regarding the design of telecommunications infrastructure for serving
electronic safety and security systems.
A. Electronic safety and security (ESS) devices are increasingly converging onto
structured cabling systems. While the design of these systems is typically
outside the scope of work of the telecommunications infrastructure designer, the
Designer shall design the telecommunications cabling required to support these
systems.
B. Occasionally ESS systems require telecommunications cabling routed from the
devices to a patch panel termination point in a designated low voltage electronics
room, or other location managed by building security personnel. In addition to
the device-specific cables, additional cables shall be designed from the
telecommunications rooms to the ESS patch panels, to permit these systems to
gain access to the data networks.
C. Other times, ESS systems can be cabled directly to patch panels in the
telecommunications rooms just like any other computer or telephone device.
D. TDDG Section 4.15 – Data Network Design (above) depicts the differences
between these two solutions. The Designer shall inquire on a project-by-project
basis which solution to apply to a given project. It is common that non-technical
issues will affect which solution is used.

Telecommunications Distribution Design Guide [ Version 8 ] 124


4 Design Criteria

4.18 Regional Information Centers and Data Centers


Please refer to Chapter 18 – Data Centers in the BICSI TDMM for general information
regarding the design of telecommunications infrastructure for serving data centers.
Generally speaking, GSA follows the TIA-942-A, Telecommunications Infrastructure
Standard For Data Centers standard in the design of data centers and larger equipment
rooms. The requirements below take precedence over the BICSI TDMM guidelines.
The Designer shall inquire with GSA whether a main telecommunications room
(sometimes called the “MDF”) in a given project is intended to be designed with
telecommunications room features, Data Center features, or Regional Information
Center features.

4.18.1 Small Scale Equipment Rooms


The requirements for small-scale equipment rooms are the same as for
telecommunications rooms. See TDDG Section 4.3 – Telecommunications Spaces.

4.18.2 Data Centers


For projects involving a Data Center, adhere to all data center-related guidelines from
the Office of Management and Budget (OMB).

4.18.3 Regional Information Center (RIC)


Regional office buildings shall be designed with a “Regional Information Center” (RIC) to
support local operations and field offices in that region.
The requirements for telecommunications rooms (TDDG 4.3) apply to RICs except as
described below.
The requirements below are considered to be a minimum set of features and are
provided as a starting point for the design process. The Designer shall inquire of the
GSA IT ITS to understand the unique requirements of a specific location and shall
design the RIC suitably.

4.18.3.1 Location and Sizing Considerations


A. RICs shall be located above ground.
B. RICs shall be designed in place of the main telecommunications room
(sometimes called the “MDF”). RICs shall perform all of the functions of the
MDF, in addition to hosting the enterprise network headend equipment.
C. A starting point for RIC sizing and arrangement is as follows and as depicted in
the diagram below:
• RIC spaces shall include a minimum of 4 server cabinets and 5 two-post
racks, including the two-post racks required for MDF functions.
• Either Computer Room Air Conditioning (CRAC) units or in-row cooling is
required for the server cabinets.

125 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

• RIC spaces shall be large enough to maneuver equipment and cabinets as


well as support 25% growth. A starting point for sizing considerations shall
be 20’ x 25’ (internal dimensions).
• The Designer shall consult with the GSA IT ITS on a project-by-project basis
to determine any additional factors that would contribute to a change in RIC
sizing requirements.

FIGURE 29: RIC SIZING AND ARRANGEMENT

Telecommunications Distribution Design Guide [ Version 8 ] 126


4 Design Criteria

D. Every project will encounter unique building circumstances and operational


considerations. Some situations will require larger RIC spaces, and in other
cases smaller rooms will be appropriate. The Designer shall work with GSA IT to
determine the most appropriate solution for the specific needs of that location.
E. The power consumption profile of equipment to be hosted in the data center and
its associated heat-load profile are the two key parameters for sizing a data
center. The Designer shall work with GSA IT to identify the power consumption
per cabinet footprint, which will have a direct correlation to the cooling
requirements of the space. The quantity of equipment cabinets that can be
powered and cooled in the space drives the sizing plan.
• During the life of the data center, advances in technology may shrink the
space requirements for each server, making more physical space available
for additional servers. However, if there is not sufficient power to serve
another server or sufficient cooling capacity to remove the heat produced by
another server, then the additional space is unusable.
F. The GSA IT ITS shall approve the final space requirements and design layout for
the equipment and racks.

4.18.3.2 Architectural Considerations


A. Raised (accessible) flooring in RICs is not desirable. Static Dissipative Tile
(SDT) flooring is required in RICs and associated telecommunications rooms in
ROBs.
Electrical rooms supporting RICs do not require accessible flooring.
B. The RIC shall be separated from other occupancies within the building by fire-
resistant-rated construction of not less than 1 hour.
C. Do not provide gypboard (hard-lid) or T-bar ceilings in RICs. The ceiling spaces
in RICs shall be exposed to structure.

4.18.3.3 Cable Pathways


A. Within the RIC, GSA prefers two layers of ladder racking or ladder tray,
suspended from above at 7’ and 8’ above finished floor, independent of the
cabinet hardware. Ladder racking shall circle the room and cross the room over
the tops of the equipment cabinets and racks.
• Backbone cables and patch cords shall be routed via the 7’-level ladder
racking.
• Horizontal cables and their service loops shall be stored in the 8’-level ladder
racking.
B. Size the ladder racking or ladder tray to support the cable quantity intended for
the RIC. It is likely that 12” wide and 18” wide ladder racking will be necessary.
C. The Designer shall create a solution that has the capacity to handle the cable
slack in the room.

127 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

4.18.3.4 Cabinets in RIC


A. Each cabinet shall have front and rear screen doors, allowing airflow through the
equipment. Cooling fans are typically not required.
B. Each cabinet will also have Owner-provided rack-mounted power management
equipment (currently from WTI).
C. Server cabinets in RICs shall have the following features:
• Sized 30” wide and 48” deep (minimum). All cabinets shall be uniformly
sized.
• The Designer shall inquire about whether cabinets shall be 42U high or 48U
high, depending on the circumstances applicable to the facility.
• Perforated front and rear door panels.
• Tool-less removal of door and side panels.
• Preference for square punch with cage nuts – the Designer shall discuss this
with GSA IT to coordinate with the Owner-provided equipment.
• Adjustable rails.
• Internal cable management with cable grooming features (either integrated or
manufacturer-designed accessory), to manage patch cords in rear of cabinet
and route between front and back.
• Leveling feet with glide pads and floor bolts (no casters).
• Seismic bracing may be needed where Code-specific requirements exist in
geographic areas that are susceptible to earthquakes.
• Two power distribution units (PDU), left and right sides, full height, with
receptacles distributed evenly along the full height of the cabinet. PDUs shall
be designed for and factory-manufactured to fit the specified cabinets. PDUs
shall be managed devices (Ethernet port) and shall meter the power
consumption of the cabinet.
• Power cords shall be right-sized (avoid excessive length). The Designer shall
work with GSA IT to determine whether the power cords will be provided by
the Contractor or whether GSA will provide them along with the network
equipment.
• Power cord management inside the rear of the cabinets to route the power
cords to the left and right sides of the cabinets.
• White-painted cabinets are desirable (but not required) to enhance visibility.
GSA may find this useful for a given project. The Designer shall inquire with
GSA whether white, black, or another color should be used for cabinets and
associated vertical cable management.
D. Acceptable cabinet manufacturers include APC, CPI, and other manufacturers of
equal quality and feature set.
E. The Designer shall also discuss with GSA the potential for future additional
cabinets, and identify spaces for the future cabinets on the plan drawings.
F. The following cabinet elevation diagram shall be used as a starting point in the
design of the cabinets for a RIC:

Telecommunications Distribution Design Guide [ Version 8 ] 128


4 Design Criteria

FIGURE 30: RIC CABINET ELEVATION DIAGRAM

129 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

4.18.3.5 Racks in RIC


A. One two-post rack (7’ high, 19” wide, 3” deep) shall host equipment and
terminations for incoming circuits (from utility service providers).
B. A separate two-post rack shall host equipment and terminations for outgoing
circuits (to regional field offices).
C. All analog backbone cabling serving other telecommunications rooms in the
building shall terminate on rack-mounted angled patch panels, as shown in the
diagram below.
D. The Designer shall also discuss with GSA the potential for future additional
racks, and identify spaces for the future racks on the plan drawings.
E. All racks shall be from the same manufacturer and from the same product series
from that manufacturer. Racks and their associated cable management
components shall be factory-engineered to connect and function together as a
system.
F. Racks shall support side-to-side airflow.
G. Current RIC network design includes two Cisco 6500-class switches (Owner-
provided), mounted in two separate racks. The Designer shall also inquire with
GSA about any other rack-mounted equipment that requires a different air-flow
pattern, and shall specify appropriate provisions for that equipment.
H. The following rack elevation diagram shall be used as a starting point in the
design of the racks for a RIC:

Telecommunications Distribution Design Guide [ Version 8 ] 130


4 Design Criteria

FIGURE 31: RIC RACK ELEVATION DIAGRAM

131 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

4.18.3.6 RIC Cabling


A. Copper backbone (riser) cabling between the RIC and the other
telecommunications rooms in the building shall be terminated on angled patch
panels mounted in Rack D. See the RIC Cabling diagram in the figure below.
B. In addition to managing the cabling entering the RIC from outside the room (the
MDF functions of this space), the following cable requirements exist to support
the RIC functions of this space:
• Between Cabinet 1 and Rack B (the headend):
+ 24 Cat6A copper cables (small diameter, terminated in a rear-facing, top-
of-cabinet, flat (not angled) patch panel with a shallow-style cable
manager)
+ 24-strand 50-micron multimode fiber optic cables
• Between Cabinet 2 and Rack B (the headend):
+ 24 Cat6A copper cables (small diameter, terminated in a rear-facing, top-
of-cabinet patch panel with a shallow-style cable manager)
+ 24-strand 50-micron multimode fiber optic cables
C. Terminate CAT6A copper cabling at the top of Rack E on angled patch panels
and in cabinets on either:
• Zero-U patch panels
• Faceplates mounted in the Zero-U side cable management
D. Provide two small-diameter CAT6A copper patch cords for each CAT6A cable
serving RIC cabinets.
E. Some connections for devices located inside the RIC can be accomplished using
a patch cord, in lieu of a horizontal cable terminated in an outlet.
• Patch cords may be used to connect devices that are mounted within a rack
or cabinet, or attached to the ladder rack or cable tray inside the RIC.
• Wall-mounted or floor-mounted devices that are not directly attached to patch
cord-friendly raceway require a horizontal cable, properly terminated in patch
panels and outlet boxes with a faceplate and jack.
F. The following schematic diagram depicts the minimum required cabling between
racks and cabinets in each RIC. The Designer shall adjust this design to serve
the unique requirements of each RIC, under the guidance of the GSA IT ITS.

Telecommunications Distribution Design Guide [ Version 8 ] 132


4 Design Criteria

FIGURE 32: RIC CABLING DIAGRAM

4.18.3.7 Environmental Provisioning


A. Environmental management and monitoring systems shall be designed for RICs.
B. The PBS P100-2016, Section 6.5.10.1 states that air conditioning systems for
technology/server and UPS rooms shall be supported by emergency power
systems. Typically, an Optional Standby Generator (NEC 702.2) performs this
function.

133 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
C. Consideration shall be given to both cooled cabinets and whole-room cooled air
solutions, in particular:
• Computer Room Air Conditioning (CRAC) units may the best fit for a RIC
space, because the substantial amount of equipment mounted in two-post
racks will require ambient cooling. CRAC units shall be designed in
redundant pairs, such that either unit could carry the room’s whole load
should one fail.
• CRAC units shall have variable-speed fans.
• However, the equipment housed in cabinets may be dense enough that it
produces a significant amount of concentrated heat, and could therefore
benefit from in-row cooling.
• Another consideration that could affect the choice of cooling system is
whether the space will have an accessible floor to route piping and supply air.
• The Designer shall work with the Mechanical Engineer and the GSA IT ITS to
select the best solution for each application.
D. Cooling capacity shall be designed to appropriately (but not excessively) support
the full load capacity of the power distribution system. The Designer shall
discuss with GSA whether the full cooling capacity shall be installed on Day 1, or
whether provisions shall be made to install a portion of the system first, followed
by additions to the system when future loads are added. The Designer shall
work with the mechanical designer to calculate the expected heat load for the
equipment in a RIC. The mechanical designer shall design CRAC equipment
that is appropriate for the heat load, temperature, and humidity circumstances of
each project. Below is a list of parameters that the mechanical designer can use
as a starting point for the design of appropriately sized CRAC units for a RIC:
• The Designer shall consider the following starting points for CRAC unit
capacity design:
+ 1kw per rack
+ 5kw per cabinet
+ two 7 ton CRAC units (n+1=2)
• The nominal environmental target conditions in the RIC are:
+ 72 degrees ambient temperature
+ 45%-55% relative humidity
E. CRAC units shall be procured with the network management option, providing a
network jack to connect to an Ethernet switch.

4.18.3.8 Fire Detection and Suppression


All RICs shall be protected by a wet-pipe sprinkler system that is designed and installed
in accordance with the requirements in PBS P100-2016, Section 7.11.2. RICs shall also
meet the additional requirements in PBS P100-2016 for Information Technology
Equipment Rooms.

Telecommunications Distribution Design Guide [ Version 8 ] 134


4 Design Criteria

4.18.3.9 Power Requirements


4.18.3.9.1 Technical Power Panels
A. See PBS P100-2016, Sections 6.5.5.3 and 6.5.7.3 for additional requirements.
B. A separate supply circuit serving the room shall be provided and terminated in its
own electrical panel located in the RIC. This power panel shall be designated as
“Regional Information Center Technical Power.” The Regional Information
Center technical power panel shall be used exclusively for supplying power to
electronics equipment in the equipment room. Sizing of electrical power supply
is dependent upon the equipment types and equipment load, and shall be
calculated on a case-by-case basis, including sufficient spare capacity for future
growth.
C. The technical power circuits in each RIC shall originate from a technical power
panel with a Transient Voltage Surge Suppressor (TVSS), dedicated to serving
the RIC. The technical power panel shall not be used to supply power to sources
of electromagnetic interference such as large electric motors, arc welding, or
industrial equipment.
D. As a starting point for design considerations, the Designer shall include
provisions for 10 kW per cabinet and 5 kW per rack, and adjust those values
after consultation with GSA IT ITS.
E. GSA typically uses network electronics that provide Power-over-Ethernet (POE).
The Designer shall request power consumption data for the equipment that GSA
will use, and will size the power distribution infrastructure sufficient to support this
equipment.
F. GSA uses (Owner-provided) rack-mounted equipment (currently from WTI,
www.wti.com) to allow devices to be rebooted and controlled remotely. The
Designer shall inquire with GSA where this equipment will be used, and shall
allocate rack space to host the WTI equipment.

4.18.3.9.2 Backup Power


A. Power for critical network components such as servers, routers, switches, and
telephone systems shall always be provided through at least one uninterruptible
power supply (UPS).
B. GSA IT requires that every RIC facility be provided with a solution to supply
electrical power for two hours during a utility power outage. The Designer,
electrical engineer, and mechanical engineer shall review the options and
present recommendations to GSA regarding the backup power solution that will
be the best value for GSA.
C. The Designer shall refer to the PBS P100-2016, especially Section 6, for
guidance on backup power generators.
D. RICs host enterprise-critical systems and support field offices in a Region. RICs
therefore will likely need “Optional Standby Generators” and reliable

135 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
uninterruptible power supplies (UPS) to provide electrical power when utility
power outages occur.
E. The following diagram depicts a possible decision tree that may be of guidance in
the process of selecting an appropriate solution for each project:

FIGURE 33: BACKUP POWER DECISION TREE

• Where a generator is provided, the UPS system should be capable of


keeping the equipment operating until the generator is carrying the load.
• When a generator is provided, GSA IT prefers to use flywheel-based UPS
equipment rather than conventional battery UPS equipment. The Designer
shall evaluate the relative merits of these two system types for the specific
application, considering the life-cycle economics, periodic battery
replacement, equipment maintenance, and additional cooling requirements.
• GSA prefers that the flywheel and UPS equipment be an integrated package
from a single manufacturer.

Telecommunications Distribution Design Guide [ Version 8 ] 136


4 Design Criteria

• Flywheel equipment shall be manufactured in the US. As of the date of this


writing, the following US manufacturers are known:
o Vycon (www.vyconenergy.com)
o ActivePower (www.activepower.com)
F. UPS equipment shall be procured with the network management option,
providing a network jack to connect to an Ethernet switch.
G. Please note that the term “Optional” is an NEC Code-defined term (NEC 702.2)
contrasting it with “Legally Required” (NEC 701.2) and “Emergency” (NEC 700.1)
generators that the NEC also defines. Consistent with the PBS P100-2016, GSA
IT supports and encourages the use of appropriately classified generators
wherever it makes sense to do so. The following table contains excerpts from
the three NEC sections referenced above, and explains the three generator
classes, providing examples of the types of facilities in each class:

137 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

TABLE 34: NEC-DEFINED GENERATOR CLASSES

Emergency Systems Legally Required Standby Optional Standby


(NEC 700.1) Systems (NEC 701.2) Systems (NEC 702.2)
Those systems legally required Those systems required and Those systems intended
and classed as emergency by so classed as legally to supply power to
municipal, state, federal, or required standby by public or private
other codes, or by any municipal, state, federal, or facilities or property
governmental agency having other codes or by any where life safety does
jurisdiction. These systems governmental agency not depend on the
are intended to automatically having jurisdiction. These performance of the
supply illumination, power, or systems are intended to system. These systems
both, to designated areas and automatically supply power are intended to supply
equipment in the event of to selected loads (other than on-site generated power
failure of the normal supply or those classed as emergency to selected loads either
in the event of accident to systems) in the event of automatically or
elements of a system intended failure of the normal source. manually.
to supply, distribute, and
control power and illumination
essential for safety to human
life.
Informational Note: Informational Note: Informational Note:
Emergency systems are Legally required standby Optional standby
generally installed in places of systems are typically systems are typically
assembly where artificial installed to serve loads, such installed to provide an
illumination is required for safe as heating and refrigeration alternate source of
exiting and for panic control in systems, communications electric power for such
buildings subject to occupancy systems, ventilation and facilities as industrial
by large numbers of persons, smoke removal systems, and commercial
such as hotels, theaters, sports sewage disposal, lighting buildings, farms, and
arenas, health care facilities, systems, and industrial residences and to serve
and similar institutions. processes, that, when loads such as heating
Emergency systems may also stopped during any and refrigeration
provide power for such interruption of the normal systems, data
functions as ventilation where electrical supply, could processing and
essential to maintain life, fire create hazards or hamper communications
detection and alarm rescue or fire-fighting systems, and industrial
systems, elevators, fire operations. processes that, when
pumps, public safety stopped during any
communications systems, power outage, could
industrial processes where cause discomfort,
current interruption would serious interruption of
produce serious life safety the process, damage
or health hazards, and similar to the product or
functions. process, or the like.

Telecommunications Distribution Design Guide [ Version 8 ] 138


4 Design Criteria

H. If an Optional Standby Generator is available to the facility, the RIC technical


power panel shall be linked to the generator power supply.
• Generators shall be designed with fuel tanks sized large enough to run the
generator continuously for 48 or 72 hours, as described in PBS P100-2016,
Section 5.3.6.9. Fuel tanks shall be sited to allow fuel delivery trucks to
conveniently fill the tank.
• GSA prefers generators designed to run on diesel fuel. Natural gas shall not
be used as a fuel for generators.
I. GSA will consider the use of centralized UPS equipment as applications warrant,
such as for RICs. However, if GSA wishes to use a centralized UPS, the
following requirements shall be met:
• Some centralized UPS equipment may vent noxious battery gases. The UPS
may therefore need to be housed in a room that is equipped to properly vent
the gases. Rooms housing centralized UPS systems shall have the same
environmental provisioning features as the RIC.
• Some battery manufacturers claim that valve-regulated lead-acid batteries do
not emit gases and therefore might not require mechanical systems for
venting battery gases. The Designer shall evaluate such claims for
applicability on each project.
• Centralized UPS equipment shall be provided with a network interface card
so that the UPS can communicate via the network with servers and other
equipment to orchestrate a coordinated safe-shutdown of the equipment in
the event of an extended power outage. The telecommunications cabling
design shall require a telecommunications outlet located in the centralized
UPS room near each UPS to support the UPS’s network connection.
J. Where a generator is not provided, the UPS’s battery bank shall be sized to
provide a minimum of two hours of run time for the supported low voltage
systems hardware. The Designer shall request direction from the GSA IT ITS
regarding project specific needs for increased run time.
K. Upon installation, a qualified electrician shall test new centralized UPS units for
correct output voltage prior to connecting electronic equipment.
L. A separate electrical room will be required to host the RIC’s electrical panels,
generator control panels and UPS equipment. If flywheel UPS equipment is
provided for an application, this equipment shall also be located in the electrical
room.
• Ideally, the RIC’s electrical room shall be located adjacent to the RIC to
minimize the effects of (and cost to mitigate) voltage drop.
• RIC electrical rooms shall be sized to allow for maintenance of equipment
and battery replacement, including delivery of crated equipment.
M. The following table summarizes the set of appropriate backup power options for
the types of telecommunications rooms and equipment rooms under each
scenario:

139 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4
TRs in TRs in
RIC in ROB ROBs with RIC Field Offices
Generator Yes, if operation Desirable if the RIC has Neutral position.
requires continuous a generator with
operation. capacity to support the
TRs. Otherwise, no.
Flywheel Preferred if Desirable if the RIC has Unlikely
UPS with economic analysis a flywheel with capacity circumstance.
Generator shows this to be a to support the TRs.
best value solution. Otherwise, no.
Battery Desirable. Desirable if operations Unlikely
UPS with must continue during a circumstance.
Generator power outage.
Centralized Usually preferable Usually preferable over Unlikely
Battery over Distributed Distributed UPS. circumstance.
UPS UPS.
Distributed Acceptable. Acceptable. Local Acceptable.
Battery decision, but budget for Local decision,
UPS battery replacement. but budget for
battery
replacement.
Surge Achieved through Achieved through the Achieved through
Protection the use of a use of a TVSS. the use of a
transient voltage Power Strip with
surge suppressor surge
(TVSS). suppression.
Acceptable if
uptime is not
required during a
power outage
event.

4.18.3.9.3 Emergency Power Off (EPO) Button


A. Where required by Code (NEC 645.A), an Emergency Power Off (EPO) push-
button shall be provided near the exit of both the Data Center room and the
electrical room serving the RIC. The button shall be located per Code
requirements, preferably near the door at eye level but in a location that will not
be subject to inadvertent contact. The button shall be provided with a shield to
prevent accidental actuation from inadvertent contact.
• Note: the 2011 edition of the NEC has some conditions where an EPO is not
required. The Designer shall evaluate these conditions and advise GSA
whether this exception would apply to the project.

Telecommunications Distribution Design Guide [ Version 8 ] 140


4 Design Criteria

B. When the EPO button is pressed, the power to the room shall be shut off
immediately, per Code requirements. UPS equipment shall also shut off power
to equipment when the EPO button is pressed.
C. Provide a permanent, wall-mounted plaque near the EPO with instructions for
restarting the power following an EPO event. It is recommended that the plaque
be fabricated from engraved plastic or a similar indelible material. The text on
each plaque shall be specifically written for the facility. The following is an
approximate example to be modified by the Electrical Engineer to reflect actual
conditions at the facility:
• Before resetting any EPO pushbutton, verify that:
+ The condition for which EPO activation occurred has been corrected.
+ Fire suppression systems have been reset to clear alarms.
• Reset the activated EPO Station.
• Verify that all loads are fully energized and reset. Shunt any tripped
breakers.
• If AHU unit is not working, consult manufacturer’s startup procedures.
D. The Electrical Engineer shall prepare written guidelines describing examples of
events that would warrant pressing the EPO button. The guidelines are not
expected to be a comprehensive list.

4.18.3.9.4 Technical Power Outlets


A. Generally, the power outlet requirements that are applicable to
telecommunications rooms are also applicable to RICs. See TDDG Section 4.3.7
– Power Requirements (above).
B. The Designer shall obtain connection/load requirements from GSA for each piece
of equipment, and tabulate the information for review and confirmation by GSA.
This equipment may include network electronics, UPS equipment,
computers/servers, phone system equipment, voice mail systems, video
equipment, and service provider equipment.
C. Some telephone PBX equipment, UPS equipment, and network switch
equipment require specialized plugs or electrical service. The Designer shall
specifically investigate the potential need for voltage or current requirements
other than the typical 120VAC/20 Ampere power outlet, and shall coordinate with
the design team to design the electrical power infrastructure sufficient to serve
the needs of the equipment.
D. Technical power outlets shall be mounted at the top of each rack and cabinet in
the RIC, attached to the overhead ladder rack (see the diagram below). In
addition to a label indicating the panel and circuit number, the outlets shall also
be labeled “A” or “B” corresponding to the dual power supplies for network
switches and servers.
• For applications where an Optional Standby Generator (NEC 702.2) is
available for backup power to the RIC, one outlet of each pair shall be
supported by the generator, as depicted in the diagram below.

141 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

FIGURE 35: RIC POWER DISTRIBUTION ARCHITECTURE

Telecommunications Distribution Design Guide [ Version 8 ] 142


4 Design Criteria

4.18.3.9.5 Power Cords for Network Switches and Servers


A. For network switches and servers, do not use the 6’ long power cords that are
typically supplied with this equipment because the excess slack obstructs airflow
in the cabinet and causes congestion, making technical support activities difficult.
Instead, provide custom-length power cords that are sufficient to reach the
horizontal power strip or PDU without excessive slack.
B. Power cords shall be labeled “A” or “B” corresponding to the dual power supplies
for network switches and servers, and matching the power outlets that supply the
PDU or power strip.

4.18.3.9.6 Convenience Power Outlets


Convenience power outlets shall be provided as described (above) in TDDG Section
4.3.7 – Power Requirements (above).

4.18.3.10 Grounding, Bonding, and Electrical Protection


All equipment racks, metallic conduits, and exposed non-current carrying metal parts of
telecommunications and information technology equipment in the RIC shall be bonded to
the TGB. Please refer to Chapter 9 – Bonding and Grounding (Earthing) in the BICSI
TDMM and TDDG Section 4.8 – Bonding and Grounding (Earthing) for more information
regarding the design of grounding, bonding, and electrical protection systems.
• The RIC requires a non-isolated ground wire routed inside a metallic conduit
directly from the main electrical service-grounding electrode for PBX
equipment. This ground wire is in addition to and separate from the
telecommunications grounding system.
• Grounding and bonding conductors shall be sized according to the
requirements in ANSI/TIA/EIA J-STD-607-B.
• See PBS P100-2016, Section 6.5 for additional requirements.

4.18.3.11 Lighting
Light fixtures shall be mounted at approximately 8 or 9 feet above finished floor.
Fixtures shall not be located directly above racks or ladder racking, but rather to the side
of them. The intent is that overhead light fixtures illuminate the front and rear of racks
and cabinets. See the RIC Floor Plan figure above depicting recommended light fixture
locations.

4.19 Health Care


Please refer to Chapter 19 – Health Care in the BICSI TDMM for general information
regarding the design of telecommunications infrastructure for serving health care
facilities.
GSA owns very few health care-related facilities. The likelihood of encountering a
project of this type is low.

143 Telecommunications Distribution Design Guide [ Version 8 ]


Design Criteria 4

4.20 Residential Cabling


Please refer to Chapter 20 – Residential Cabling in the BICSI TDMM for information
regarding the design of telecommunications infrastructure to support residential facilities
within GSA facilities.
GSA owns very few residential-type facilities. The likelihood of encountering a project of
this type is low.
Generally speaking, GSA-owned residential facilities shall be provided with the same
telecommunications infrastructure materials and methods as are used for all other GSA
facilities, except where specifically noted in this document.
The Designer shall inquire about whether a “residential cabling” solution is required for a
particular project.

4.21 Business Development and Project Management


Please refer to Chapter 21 – Design, Construction and Project Management in the BICSI
TDMM for general information regarding design, construction and project management
of telecommunications infrastructure.
Please refer to TDDG Section 3 – Project Procedures for GSA-specific
telecommunications project procedure requirements.

4.22 Codes, Standards, Regulations, and Organizations


Please refer to Appendix A: Codes, Standards, Regulations and Organizations in the
BICSI TDMM for general information regarding the codes, standards, regulations,
and organizations that apply to telecommunications infrastructure.

Telecommunications Distribution Design Guide [ Version 8 ] 144


5
Construction Document Content

A. This section of the TDDG describes the content requirements that the Designer
shall include when creating the Construction Documents. This content is in
addition to the content found in some generally accepted document sets.
B. The documents produced by the Designer and the services provided by the
Designer shall comply with the requirements in the Facilities Standards for the
Public Buildings Service document (PBS P100-2016). In addition to these
requirements, the Designer shall also meet the requirements in the TDDG,
including the Construction Document content requirements in this section.
C. Construction Documents shall communicate a fully detailed and coordinated
design (rather than making adjustments in the field during construction) and are
expected to result in reduced construction costs and fewer change orders. The
level of detail required to meet this objective may be substantially greater than
some telecommunications designers may be accustomed to providing.
D. The sections below describe the Construction Document content to be included
by the Designer.

145 Telecommunications Distribution Design Guide [ Version 8 ]


Construction Document Content 5

5.1 Plans and Diagrams


5.1.1 General
A. GSA has adopted the National CAD Standards. Therefore, all drawings shall be
numbered according to the National CAD Standards numbering scheme, and all
symbols shall be National CAD Standards-compliant.
B. The drawing set shall include the following:
• Cover Sheet
• Sheet List
• Site Map
• Symbol Schedule – See National CAD Standards and BICSI TDMM Glossary
• List of Abbreviations
• Plan Sheets – Telecommunications
• Plan Sheets – Grounding/Bonding (when required)
• Elevation Diagrams – (telecom room walls, telecom/equipment racks, and
cabinets)
• Schematic Diagrams – (Riser/Backbone Cabling, Grounding/Bonding)
• Demolition (Plans, Elevations, Schematics)
C. Drawings shall be prepared using professional design software such as
AutoCAD, Microstation, or other similar caliber CAD software. Drawings that are
hand-drawn sketches, scanned images, or produced using bitmap graphics
editors shall not be accepted.
D. All plan sheets shall be scaled, shall indicate the scale, and shall show a north
arrow. All plan sheets shall show a key plan when the building floor or site is too
big to fit on a single sheet.
E. Telecommunications infrastructure identifiers shall be shown on the drawings
and diagrams.

5.1.2 Inside Plant Telecommunications Plan Drawings


A. Scaled plan drawings shall be provided for each building showing the horizontal
and intra-building backbone telecommunications infrastructure. These drawings
shall show the following:
• Routing of new pathway to be constructed during the project.
+ The content of the drawings shall be coordinated with other disciplines and
shall be representative of the complete pathway route that the Contractor
shall use, rather than a schematic depiction.
+ It is expected that the Designer will expend considerable coordination effort
during the design process. Non-coordinated pathway/raceway is not
acceptable to GSA.
• Approximate locations of junction boxes and conduit bends.
• The cable quantities and the raceway at any given point in the system.

Telecommunications Distribution Design Guide [ Version 8 ] 146


5 Construction Document Content

B. Where new cabling will be pulled into existing conduits, the Construction
Documents shall show the routes of each existing conduit. Where it is not
possible to determine the routing of existing conduits, the Designer shall inform
the GSA IT ITS and seek direction on whether to use the existing conduits or
design new conduits for use on the project. The Designer is required to identify
such conditions during field investigation activities.

5.1.3 Demolition
A. Any existing OSP and ISP cabling intended to be no longer in use following the
installation of new cabling shall be removed (demolished) as a part of the project.
B. Existing cabling to be demolished shall be shown on the plans and schematic
diagrams. Separate demolition plan sheets and schematic diagrams shall be
provided for projects with extensive cable demolition.
C. The Designer shall include requirements in the design that are clear and precise
such that the Contractor will meet Code requirements and achieve GSA’s
objectives. The instructions shall include, but not be limited to the following:
• Notations to indicate items to be salvaged to the Owner.
• Hatched over-marking on items to be demolished.
• Requirements to properly and legally dispose of demolished materials,
without additional cost to the Owner.
• Requirements that the Contractor properly tag existing cabling that is
intended to remain for future use, avoiding the potential determination by
Code officials that an untagged cable has been abandoned and would
therefore be subject to removal.

5.1.4 Telecommunications Room Plan Details


A. Construction documents for GSA projects shall show scaled plan drawing details
for the telecommunications spaces. The details shall show the footprint and
location of each of the major components in the room, including at least the
following:
• Backboards • Backbone Cable Routing • Space Reserved for Utility Demarc
• Ladder Racking • Entrance Conduits • Racks and Vertical Cable Mgmt
• Work Area • Space for Future Racks • Space for other low voltage systems
• UPS Equipment • Termination Blocks • Entrance Protection Equipment
• Grounding Busbar • PBX and Voice Mail Equipment

B. For modifications to existing telecommunications rooms, it may be necessary to


provide a demolition plan.
C. Sample telecommunications room plan drawings are included in Appendix 6.2 of
the TDDG.

147 Telecommunications Distribution Design Guide [ Version 8 ]


Construction Document Content 5

5.1.5 Elevation Diagrams


A. The Designer shall provide scaled wall elevation details for each TR and
ER/Data Center affected by the project. The Designer shall consider (on a
project-by-project basis) whether the plan drawings are better suited for depicting
the elevation diagrams, in lieu of the Project Manual.
B. For remodel projects, the Designer shall produce digital photographs of each wall
to depict the existing conditions where future TRs and ERs will be located.
These photos shall be provided with the wall elevation details in the Construction
Documents.
C. The wall elevation details shall show the components that are mounted on the
walls in the room including at least the following:
• Backboards • Backbone Cable Routing • Wall-Mounted Electronic Equipment
• Ladder Racking • Cable Management • Wall-Mounted Swing Racks and Contents
• Cable Slack Loops • Termination Blocks • Racks and Vertical Cable Mgmt
• Grounding Busbar • Power Receptacles • Entrance Protection Equipment
• Existing Devices • Entrance Conduits • Other low voltage systems
• Work Area • Space for Future Racks • Space for Future Equipment
• UPS • PBX and Voice Mail • Space Reserved for Utility Demarc
• Entrance Pit

D. Elevation details for each of the telecommunications racks in each TR and


ER/Data Center shall also be provided. Rack elevation details shall show the
racks and any components that are mounted on or near the racks. The details
shall depict the telecommunications materials that are listed in the specification,
including at least the following:
• Patch Panels • Shelves/Drawers • Space for Future Equipment
• UPS Equipment • Termination Blocks • Electronic Equipment
• Existing Devices • Power Receptacles • Cable Management

E. Where a project involves additions to existing racks, the elevation details shall
show the existing equipment in the racks and indicate which items are existing, in
addition to indicating which items are “new, to be provided under the Contract.”
F. Examples of rack and wall elevation details are included in Appendix 6.3 and
Appendix 6.4 of the TDDG.

Telecommunications Distribution Design Guide [ Version 8 ] 148


5 Construction Document Content

5.1.6 Intra-building Backbone Schematic Diagrams


A. Where there are multiple TRs in a given building, a schematic diagram of the
intra-building backbone riser is required. At a minimum, the diagram shall depict
the following information:
• Copper backbone cable (CAT6A, multipair, etc.)
• Copper termination hardware
• Fiber optic backbone cable for data
• Fiber termination hardware
• Backbone cables that are “existing-to-remain”
• Backbone cables that are “existing-to-be-demolished”
• Backbone connections to the entrance facility and service providers
B. On projects where existing intra-building backbone cabling is to be removed, it
may be useful to provide a separate schematic diagram depicting cabling to be
demolished.

5.2 Project Manual


A. The Facilities Standards for the Public Buildings Service document (PBS P100-
2016) lists requirements for the Project Manual and additional requirements for
the Designer.
B. The Project Manual shall contain a summary of the telecommunications work on
the project, a description of the demolition requirements (if applicable), and a
discussion of the utility coordination requirements.
C. In addition to these requirements, the Project Manual shall contain the following
items as described below:
• Elevation Diagrams
• Fiber Link-Loss Budget Analyses
• Cutover Plans

5.2.1 Specifications
A. The Designer shall create a set of specifications that are appropriate for a given
project.
B. Specifications shall be created in CSI 2014 format, and shall include some or all
of the following sections:
• 270500 – Common Work Results for Communications
• 270526 – Grounding and Bonding for Communications Systems
• 270528.29 – Hangers and Supports for Communications Systems
• 270528.33 – Conduits and Backboxes for Communications Systems
• 270528.36 – Cable Trays for Communications Systems
• 271100 – Communications Equipment Room Fittings

149 Telecommunications Distribution Design Guide [ Version 8 ]


Construction Document Content 5

• 271300 – Communications Backbone Cabling


• 271500 – Communications Horizontal Cabling
• 271600 – Communications Connecting Cords, Devices, and Adapters
• 273200 – Voice Communications Telephone Sets
C. Other specification sections may also need to be created to meet the needs of a
given project.

5.2.2 Cutover Plan


The Designer shall provide a detailed cutover plan that is coordinated with other
disciplines on the project as well as with GSA data and telephone equipment cutover
requirements. Verbiage describing the sequence of work tasks to accomplish the
cutover shall be provided in the Cutover Plan. Limitations on the permissible downtime
allowed and temporary service arrangements shall be discussed in the Cutover Plan.

5.2.3 Fiber Link-loss Budget Analysis


A. The Designer shall inquire with GSA on a project-by-project basis whether a link-
loss budget analysis is required. If so, the Designer shall include in the
Construction Documents a link-loss budget analysis for each fiber optic cable in
the project.
B. The link-loss budget analysis shall be formatted as shown in Appendix 6.5 of the
TDDG. Upon request, GSA will provide a spreadsheet to be used as a template.

5.3 Record Drawings and Documentation


A. The Designer shall prepare Record Drawings based on Contractor-produced as-
built drawings. See TDDG Section 3.4.5.1 – Construction Observation Checklist
for requirements for preparing accurate Record Drawings. The Record Drawings
shall incorporate the same content that the TDDG requires for Construction
Documents, including the identifiers for the telecommunications infrastructure
components as constructed.
B. The Designer shall provide two sets of CDROMs containing the following record
drawing and submittal items at the conclusion of the project. The CDROMs shall
have machine-printed labeling that identifies the project name, number, location,
date, contact information for the design firms, and contact information for the
Contractors. One set shall be delivered to GSA PBS and the other set to GSA
IT.
• Record drawings in two electronic formats: the drawings shall be provided
both as native AutoCAD 2015 files and also as printed or scanned full-sized
PDF documents.
• Digital photographs: photos taken by the Designer and Contractor during the
design (field investigation of existing conditions) and construction of the
project.

Telecommunications Distribution Design Guide [ Version 8 ] 150


5 Construction Document Content

C. In addition to the above record drawing submittals, the following drawings shall
be submitted:
+ Floor plans showing telecommunications outlets and the port/jack
identifiers for each outlet.
+ Separate floor plans showing the pathways serving each
telecommunications outlet (without outlet identifiers).
+ Backbone cable riser diagram.
+ All floor plan drawings shall include a key plan with a shaded portion
indicating the region of the building to which the drawing applies.
D. An additional set of the above drawings shall be submitted as follows:
+ Printed in reduced-size (not to scale) in 11” x 17” or 12” x 18” format.
+ Thermally laminated with 5-mil or thicker lamination (flat, with some rigidity
– not prone to scrolling).
+ Hole-punched in the upper left corner of each sheet, with a 1” split ring in
each sheet.
This laminated drawing set will be spread throughout the various
telecommunications rooms (applicable portions stored in each TR) by GSA.
Local GSA IT staff will use the laminated drawings as they administer the
system.

151 Telecommunications Distribution Design Guide [ Version 8 ]


Construction Document Content 5

This page intentionally left blank

Telecommunications Distribution Design Guide [ Version 8 ] 152


6
Appendix

6.1 Design Review and Construction Observation


6.1.1 Sample Review Comment Report
The table below depicts an example Review Comment Report form that will be used.
The Designer shall create a document formatted as shown below. The document shall
be used for any comments from the Designer’s review process, and the completed
document shall be submitted electronically to GSA. Upon request, GSA will provide an
electronic document for this form to be used as a template.

153 Telecommunications Distribution Design Guide [ Version 8 ]


Appendix 6
Project Number Project Name Date of Review
Drawing/Spec Comment Designer’s Final Resolution
Reference Response
Sheet number of Reviewer’s comment, citing the item Accept/Reject
drawing needing attention and any applicable code
or standard reference. Comment

Specification Reviewer’s comment, citing the item Accept/Reject


number and needing attention and any applicable code
paragraph or standard reference. Comment

6.1.2 Design Review Checklist


A Design Review Checklist for reviewers to use as a structured approach to reviewing
project documents can be obtained by emailing [email protected].
The Design Review Checklist has been prepared as an Adobe Acrobat PDF file that can
be hand-marked or edited using PDF editing tools. Reviewers can use a variety of PDF
editing tools to directly enter their comments into the checklist.
• Reviewers are welcome to print the checklist pages and hand-mark the checklist
during the review.
• Reviewers can request the latest version of the checklist by emailing
[email protected].
The first page of the Design Review Checklist provides instructions for using the
checklist.
The last pages of the Design Review Checklist provide space for review comments to be
written.

6.1.3 Construction Observation Checklist


A Construction Observation Checklist has been prepared for observers to use as a
structured approach as they walk through and check on the construction completion of
projects. The checklist can be obtained by emailing [email protected].

Telecommunications Distribution Design Guide [ Version 8 ] 154


6 Appendix

The Construction Observation Checklist has been prepared as an Adobe Acrobat PDF
file that can be hand-marked or edited using PDF editing tools. Observers can use a
variety of PDF editing tools to directly enter their comments into the checklist.
• Observers are welcome to print the checklist pages and hand-mark the checklist
during the review.
• Observers can request the latest version of the checklist by emailing
[email protected].
The first page of the Construction Observation Checklist provides instructions for using
the checklist.
The last pages of the Construction Observation Checklist provide space for observation
comments to be written.

6.1.4 What to Do with the Completed Checklists


A. After completing a checklist (either Design Review or Construction Observation),
please submit the list to [email protected] for storage with other project
files. This will allow the checklists to be available to others on GSA’s team when
they conduct a follow-up review or construction observation.

155 Telecommunications Distribution Design Guide [ Version 8 ]


Appendix 6

6.2 Sample Telecommunications Room Plan Details


Below are sample plan details for three sizes of telecommunications rooms. The
Designer shall provide similar information for each telecommunications room and
equipment room affected by the project. This information shall be provided either as a
portion of the Project Manual or on the drawings, and shall be considered part of the
Construction Documents.
The layouts of these sample plan details have been pre-approved for use at GSA. The
Designer shall use these layouts wherever appropriate and shall discuss project-specific
alternatives with the GSA IT ITS.

Telecommunications Distribution Design Guide [ Version 8 ] 156


6 Appendix

6.2.1 One-Rack Room


A one-rack room is intended only for applications where there is limited need (for
example, smaller field offices).
In other rare circumstances, space constraints may be insurmountable, and a one-rack
room may be the only possible solution. This situation is considered suboptimal, and is
expected to result in higher life-cycle costs since it will likely not have sufficient space to
support future requirements. The Designer shall not design a one-rack room for this
purpose without approval from the GSA IT ITS.
The Designer shall be attentive to the strong industry trends of devices and systems
converging onto Ethernet. It is conceivable that in the near future many systems could
present a need for space in telecommunications rooms. The Designer shall take these
future space requirements into consideration when designing a one-rack room.

FIGURE 36: ONE-RACK ROOM

157 Telecommunications Distribution Design Guide [ Version 8 ]


Appendix 6

6.2.2 Two-Rack Room


A two-rack room is intended only for applications with 384 x 2 = 768 horizontal cables or
fewer.

FIGURE 37: TWO-RACK ROOM

Telecommunications Distribution Design Guide [ Version 8 ] 158


6 Appendix

6.2.3 Three-Rack Room


A three-rack room is intended only for applications with 769 to 1,152 horizontal cables.
For applications with more than 1,152 horizontal cables, provide additional
telecommunications rooms (two or three racks).

FIGURE 38: THREE-RACK ROOM

159 Telecommunications Distribution Design Guide [ Version 8 ]


Appendix 6
6.2.4 Wall-Mounted Cabinet
A wall-mounted cabinet solution is intended only for small field office applications
requiring no more than 96 network switch connections (two 48-port switches).
Below are plan view and wall elevation drawings of this application.

FIGURE 39: WALL-MOUNTED CABINET PLAN VIEW

Telecommunications Distribution Design Guide [ Version 8 ] 160


FIGURE 40: WALL-MOUNTED CABINET ELEVATION

161 Telecommunications Distribution Design Guide [ Version 8 ]


Appendix 6

6.3 Sample Rack Elevation Detail


This page shows a sample scaled rack elevation detail. The Designer shall provide
similar information for each new or existing telecommunications rack, showing new and
existing equipment rooms affected by the project.
This information shall be provided either as a portion of the Project Manual or on the
drawings, and shall be considered part of the Construction Documents.

Telecommunications Distribution Design Guide [ Version 8 ] 162


FIGURE 41: SAMPLE RACK ELEVATION DETAIL

163 Telecommunications Distribution Design Guide [ Version 8 ]


Appendix 6

6.4 Sample Wall Elevation Detail


This page shows a sample scaled wall elevation detail. The Designer shall provide
similar information for each new or existing telecommunications room wall, showing new
and existing equipment room affected by the project.
This information shall be provided either as a portion of the Project Manual or on the
drawings, and shall be considered part of the Construction Documents.

Telecommunications Distribution Design Guide [ Version 8 ] 164


FIGURE 42: SAMPLE WALL ELEVATION DETAIL

165 Telecommunications Distribution Design Guide [ Version 8 ]


Appendix 6

6.5 Sample Fiber Optic Link-Loss Budget Analysis


The following is a sample Fiber Optic Link-Loss Budget Analysis that the Designer shall
use for each new fiber optic cable designed in the project. The Designer shall submit
the completed link-loss budget analyses to GSA in both electronic and paper forms.
Upon request, GSA will provide an electronic spreadsheet of this form to be used as a
template.

Telecommunications Distribution Design Guide [ Version 8 ] 166


FIGURE 43: SAMPLE FIBER OPTIC LINK-LOSS BUDGET

Cable ID: Enter Cable ID Here # of MM Strands


From: Enter MDF/Building Name Here # of SM Strands
To: Enter IDF/Building Name Here

MM 850 MM 1300 SM 1310 SM 1550


Passive Cable System Attenuation
Fiber Loss at Operating Wavelength Cable Length (in kilometers) km
x Attenuation per km x 3.75 x 1.5 x 0.5 x 0.5 dB/km
= Total Fiber Loss 0.00 0.00 0.00 0.00 dB

Connector Loss Number of Connector Pairs 2 2 2 2 pairs


(Excluding Tx & Rx Connectors) x Individual Connector Pair Loss x 0.75 x 0.75 x 0.75 x 0.75 dB/pair
= Total Connector Loss 1.50 1.50 1.50 1.50 dB

Splice Loss Number of Splices splices


x Individual Splice Loss x 0.30 x 0.30 x 0.30 x 0.30 dB/splice
= Total Splice Loss 0.00 0.00 0.00 0.00 dB

Other Components Loss Total Components Loss dB

Total Passive Cable System Attenuation Total Fiber Loss 0.00 0.00 0.00 0.00 dB
+ Total Connector Loss + 1.50 + 1.50 + 1.50 + 1.50 dB
+ Total Splice Loss + 0.00 + 0.00 + 0.00 + 0.00 dB
+ Total Components Loss + 0.0 + 0.0 + 0.0 + 0.0 dB
= Total System Attenuation 1.50 1.50 1.50 1.50 dB

MM 850 MM 1300 SM 1310 SM 1550


Link Loss Budget
From Manufacturer's Specifications Average Transmitter Output -18.0 -18.0 -18.0 -18.0 dBm
Receiver Sensitivity (109 BER) -31.0 -31.0 -31.0 -31.0 dBm

System Gain Average Transmitter Power -18.0 -18.0 -18.0 -18.0 dBm
- Receiver Sensitivity - -31.0 - -31.0 - -31.0 - -31.0 dBm
= System Gain = 13.00 = 13.00 = 13.00 = 13.00 dB

Power Penalties Operating Margin 2.0 2.0 3.0 3.0 dB


# of Fusion Splices Loss per Splice + Receiver Power Penalties + 0.0 + 0.0 + 0.0 + 0.0 dB
2 X 0.3 = + Repair Margin + 0.6 + 0.6 + 0.6 + 0.6 dB
= Total Power Penalties = 2.60 = 2.60 = 3.60 = 3.60 dB

Link Loss Budget System Gain 13.00 13.00 13.00 13.00 dB


- Power Penalties - 2.60 - 2.60 - 3.60 - 3.60 dB
= Total Link Loss Budget = 10.40 = 10.40 = 9.40 = 9.40 dB

MM 850 MM 1300 SM 1310 SM 1550


Performance
System Performance Margin Link Loss Budget 10.40 10.40 9.40 9.40 dB
- Passive Cable System Attenuation - 1.50 - 1.50 - 1.50 - 1.50 dB
= System Performance Margin = 8.90 = 8.90 = 7.90 = 7.90 dB

Users of this spreadsheet shall verify prior to use that the parameters and calculations
are appropriate for the project, equipment, and materials that are used. GSA is not
responsible for errors or omissions resulting from the use of this spreadsheet.

167 Telecommunications Distribution Design Guide [ Version 8 ]


Appendix 6

6.6 Cable Color Scheme


The following graphic depicts the approved cable color scheme for GSA projects:

FIGURE 44: CABLE COLOR SCHEME

DATA-PATCH

DATA-PATCH

SWITCH MUST BE IN OFF "O" POSITION TO INSTALL POWER SWITCH MUST BE IN OFF "O" POSITION TO INSTA LL POWER
SUPPL Y, FA STENERS MUST BE FULL Y ENGA GED PRIOR TO SUPPLY, FASTENERS MUST BE FULLY ENGAGED PRIOR TO
OPERATING POWER SUPPLY . OPERA TING POWER SUPPLY.

IN USE IN US E
POWER ENABLED POWER ENABLED

INPUT OK INPUT OK

FA N OK FAN OK

OUTPUT FAIL OUTPUT FAIL

100 - 240V- 100 - 240V-


16 - 7A 16 - 7A
50/60 Hz 50/60 Hz
1400 ACV 1400 ACV

WS-X4515 S UPE RVIS OR ENGINE IV


10/100
CON SOLE MGT
U PLIN K 1 U PLIN K 2
FLA SH RE SE T
1
Catalyst U TILI ZA TI ON

E JE CT

4507R STA TUS


LINK AC TI VE LIN K A CTI VE ACT IV E 1% 100% LIN K

WS-X4515 S UPE RVIS OR ENGINE IV


10/100
CON SOLE MGT
U PLIN K 1 U PLIN K 2

FLA SH RE SE T
2
U TILI ZA TI ON

E JE CT

STA TUS
LINK AC TI VE LIN K A CTI VE ACT IV E 1% 100% LIN K

WS-X4412-2GB-TX

3
1000BA SE -TX GIGA BI T E TH ERN ET
SW I TCH IN G MOD ULE
STA TU S
1 2 3 4 5 6 7 8 9 10 11 12 17 18

WS-X4412-2GB-TX

4
1000BA SE -TX GIGA BI T E TH ERN ET
SW I TCH IN G MOD ULE
STA TU S
1 2 3 4 5 6 7 8 9 10 11 12 17 18

WS-X4412-2GB-TX

5
1000BA SE -TX GIGA BI T E TH ERN ET
SW I TCH IN G MOD ULE
STA TU S
1 2 3 4 5 6 7 8 9 10 11 12 17 18

W S-X4448-GB-RJ45
15

17

31

33

47
1

16

18

32

34

48
2

STAT US 10/100BA SE-T X MU LTI- SPEED


ETH ER N ET GIGABIT ETH ER N ET
0

12

13

15

26

27

30

SW T
I C H IN G MOD U LE
2

44

45

47

8
1

17

18

19

20

21

22

23

24

25

33

34

35

36

37

38

39

40

41
1

W S-X4448-GB-RJ45
15

17

31

33

47
1

16

18

32

34

48
2

FAN
STATUS 7

STAT US 10/100BA SE-T X MU LTI- SPEED


ETH ER N ET GIGABIT ETH ER N ET
SW T
I C H IN G MOD U LE
1

10

11

12

13

14

15

16

17

20

21

24

26

27

28

29

30

31

32

35

38

39

41

42

43

44

45

46

47

48
1

www.apc.com

Smart-UPS

RT X

6 0 0 0

I
O Test

ThinkVision

Telecommunications Distribution Design Guide [ Version 8 ] 168


6.7 Standards Variance Request Approval Process
The flow chart on the following page describes the approval process that will be followed
as GSA considers Standards Variance Requests:

169 Telecommunications Distribution Design Guide [ Version 8 ]


Appendix 6

FIGURE 45: STANDARDS VARIANCE REQUEST

Telecommunications Distribution Design Guide [ Version 8 ] 170


6.8 Glossary
Analog
Analog comes from the root word “analogous,” which means “similar to.” In telecommunications, analog is a
way of sending signals—voice, data, or video—in which the transmitted signal is analogous to the original
signal. In other words, if you spoke into a microphone and saw your voice on an oscilloscope and compared
it with the same voice as was transmitted on the phone line and viewed on an oscilloscope, the two signals
would look the same. See Digital.

AWG (American Wire Gauge)


The standard measuring gauge of the diameter of copper wires in telecommunications and electrical cables.

Backboard
A plywood sheet mounted to the wall where telecommunications distribution equipment is installed.

Backbone Cabling
A major service cable that is used to interconnect various buildings on a campus, connect equipment rooms
to telecommunications rooms within a building, or connect one telecommunications room to another within
the same building. Backbone cables are typically large-capacity (high pair-count) copper cables, or fiber
optic cables.

Bend Radius
The maximum radius that a cable can be bent to avoid physical or electrical damage or cause adverse
transmission performance.

Bonding
The permanent joining of metallic parts to form an electrically conductive path that will assure electrical
continuity and the capacity to conduct safely to ground any current likely to be imposed.

Bus
An electrical connection which allows two or more wires to be bonded together.

Busbar
A copper bar, drilled and tapped, to allow the bonding together of wires or cables.

Cable Pair
Each telecommunications circuit is made up of two copper wires, or a pair of wires. Traditional analog
telephone service uses one pair of wires. Some modern digital telephone systems and most computer
networks operate over two or four pairs of wires. The ANSI/TIA/EIA-568-C standard requires a four-pair
cable to each work area modular jack.

Cable Plant
A term which refers to the physical connection media such as optical fiber cable or copper cable. See
Telecommunications Infrastructure.

Cable Pull Tension


Stated by the manufacturer as the maximum limit at which the cable’s performance characteristics are

171 Telecommunications Distribution Design Guide [ Version 8 ]


Appendix 6
altered, experiencing electrical or mechanical degradation. Also known as maximum recommended
installation load (MRIL).

Cable Tensile Strength


The limit point where the cable is pulled apart.

Change Order (CO)


Change Orders document the modifications to an existing contract. The change order procedure can be
initiated by the Owner, Contractor, or the A/E. The A/E will generally start the process using the Change
Order/Change Order Proposal form.

CATV (Community Antenna Television)


Commonly referred to as “cable TV.” In the traditional sense, CATV is a master antenna that receives
television signals, and distributes the signal over cables to a limited geographical area, such as a campus,
or neighborhood (community). Most GSA facilities receive cable TV service from a local service provider for
a subscription fee.

CCTV (Closed Circuit Television)


CCTV is a system where one or more cameras send television signals to television monitors at another
location in the same building or campus.

Cross-connect (XC)
A cross-connect, or cross-connection, is a termination junction point where individual cable pairs from two
different cables are connected together with jumper wires. An XC is intended to be easily reconfigured, as
opposed to a cable splice which is permanent.

Data Services
Data service generally refers to the computer network. For future planning purposes, data shall be
considered to be any information that is transferred in digital form. Advances in technology are blending
together traditional voice, data, and video services. Eventually, a single telecommunications system may
process all forms of telecommunications (voice, data, and video) over a common infrastructure.

Demarc
The point of demarcation between the service provider and the customer. The demarc is a cable
termination block with an orange cover where the service provider’s cable terminates. The services are then
cross-connected to the customer’s cable for distribution throughout the facility. See Telecommunications
Service Entrance Facility.

Digital
In telecommunications or computing, digital communication is the use of a binary code to represent
information. In binary code, the information is represented by a series of “on” or “off” states (a signal, or an
absence of a signal). Analog signals—like a voice—are encoded digitally by sampling the voice analog
signal many times a second and assigning a number to each sample. During transmission, the signals will
lose strength and progressively pick up noise or distortion. In analog transmission, the signal (along with
any noise that is picked up) is simply amplified to maintain the proper signal strength at the distant end. In
digital transmission, the signal is regenerated, cleaning off any noise, and restoring the signal to its original
form. Then the signal is amplified and sent to the destination. At the destination, the digital signal is again
regenerated, and restored to its original form for processing. See Analog.

Telecommunications Distribution Design Guide [ Version 8 ] 172


Electromagnetic Interference (EMI)
Electromagnetic interference is a signal distortion directly related to a foreign signal being imposed through
coupling onto a transmission path to which the foreign signal is not physically connected.

Entrance Facility (EF)


See Telecommunications Service Entrance Facility (EF).

Facility Control and Monitoring


It is becoming increasingly common for heating, ventilation, air conditioning, power distribution, and water
distribution systems to be computer-controlled. These computer-controlled systems can be networked on
the same LAN, or on the same telecommunications infrastructure, as the traditional data services.

Ground
A conducting connection, whether intentional or accidental, between an electrical circuit or equipment and
the earth, or to some conducting body that serves in place of the earth.

Grounding, Bonding, and Electrical Protection


Proper grounding and bonding serves three very important purposes. First, to safeguard life, the ground
connection insures that voltages from a malfunctioning system are routed directly to ground to prevent an
electrocution hazard to people who may come in physical contact with the system. Secondly, from a
telecommunications standpoint, grounding and bonding of telecommunications equipment and systems is an
important measure for controlling electromagnetic interference (EMI). Ungrounded systems can pick up
energy radiated from another electrical source, such as a large electric motor, arc welder, or large copy
machine. If this energy is absorbed into the telecommunications system, it can result in annoying
interference on the signal, or at worst, corruption and loss of critical data. Thirdly, the telecommunications
ground may be used as a reference voltage for electronics equipment. The telecommunications ground
potential must be consistent to insure reliable system performance.

Grounding Electrode
The metallic component that is placed in the earth to form the electrical connection with the earth. A
grounding electrode is usually a metal rod at least eight feet long driven into the earth. Refer to NFPA 70,
Article 250, Part H for acceptable electrical service grounding electrodes.

Handhole
A small cast concrete box placed in an outside plant conduit run as an access point to facilitate pulling cable
into the conduit.

Headend
In a CATV system, the headend is a term that refers to the electronics equipment that receives the television
signals from the antennas, and distributes them over the copper and/or fiber optic cables.

Horizontal Distribution Cabling (HDC)


The cable that routes from the telecommunications room to the work area. Generally, these cables are
routed horizontally on the same floor of a building, as opposed to a backbone or “riser” cable that may route
vertically in a building. Occasionally, a telecommunications room will also serve the floor above and/or
below. In this case, the cables routing from the telecommunications room to a work area on the floor above
or below are still considered to be horizontal distribution cabling.

173 Telecommunications Distribution Design Guide [ Version 8 ]


Appendix 6
Identifier
A unique descriptive name or number that identifies a specific telecommunications infrastructure component.

Infrastructure
The ISP and OSP pathways, spaces, cable plant, and associated electronic devices comprising the low
voltage signaling systems including but not limited to voice, data, building controls, security etc.

Inside Plant (ISP)


That part of the telecommunications infrastructure that is contained within a building.

Intermediate Cross-connect (IC)


A point where a backbone cable originating from the Main Cross-connect (MC) is cross-connected to
another backbone cable routing to the final destination. The IC is usually located in a Telecommunications
Room. The IC was previously referred to as the Intermediate Distribution Frame (IDF).

Intermediate Distribution Frame (IDF)


An obsolete term referring to the Intermediate Cross-connect (IC).

Jack (or Outlet Jack)


A wiring device used to terminate horizontal distribution cable, normally housed in an outlet box. See
Modular Jack.

Jumper Cord
A short length of telecommunications cable with modular plugs on each end directly connecting two
electronics devices in the Telecommunications Room or Equipment Room.

Jumper Wire
A short length of wire used to route a circuit by linking two cross-connect points.

Local Area Network (LAN)


The network that interconnects all data services for a building or campus. There may be one or more LANs
in any given building or campus.

Local Exchange Carrier (LEC)


The local telephone company.

Maintenance Hole (MH)


A concrete box placed in an outside plant conduit run as an access point to facilitate pulling cable into the
conduit. Maintenance holes are large enough for a service technician to enter and work on the cabling.
OSHA regulates the safety aspects of working in maintenance holes. GSA has policies governing work in
maintenance holes. “Manhole” is an obsolete term. See Handhole.

Main Cross-connect (MC)


The point where all telecommunications services are cross-connected to the building or campus backbone
cables for distribution to other buildings, and ultimately, to the users’ work areas. The MC is usually located
in the Main Telecommunications Equipment Room (ER).

Telecommunications Distribution Design Guide [ Version 8 ] 174


Main Distribution Frame (MDF)
An obsolete term referring to the Main Cross-connect (MC).

Main Telecommunications Equipment Room (ER)


The Main Telecommunications Equipment Room is the central location on a campus or in a building where
the major telecommunications equipment is located. The ER typically contains the telephone switching
system and the data center with computer servers and network equipment.

Maximum Recommended Installation Load (MRIL)


Stated by the manufacturer as the cable strength or maximum cable pull tension. It is based on the
conductor strength within the cable sheath.

Modular Jack (or Port, or Outlet Jack, or Outlet Connector)


A “female” telecommunications connector that accepts a mated male modular plug, used to terminate
horizontal distribution cable at the work area, normally housed in an outlet device box. The jack will accept
the modular eight (8)-position, eight (8)-conductor plug that is normally installed on the end of a patch cord
or equipment cord.

Modular Plug
A “male” telecommunications connector that is inserted into a mated female modular jack.

MPOP
Minimum-Point-of-Presence. A policy statement, where it is generally the service provider’s policy to locate
the Point-of-Presence (POP) the minimum distance possible in from the street. The service provider usually
prefers the POP to be at the street. However, the customer usually prefers the POP to be in the Equipment
Room. See POP, Demarc, and Telecommunications Service Entrance Facility.

NEMA
National Electrical Manufacturers Association.

Outlet Box
An enclosure mounted in the wall, or surface-mounted on a wall, floor, or furniture, into which a modular jack
may be installed.

Outlet Connector
See Modular Jack.

Outside Plant (OSP)


The part of the telecommunications infrastructure that is outside a building. OSP usually refers to an
underground conduit system, direct buried cable, or aerial cable.

Patch Cord
A short length of telecommunications cable with modular plugs on each end used to connect between a
modular jack and a work area device such as a telephone or computer, or to connect between a patch panel
and an electronics device in the Telecommunications Room or Equipment Room. A similar cord directly
connecting two electronics devices is called a jumper cord.

175 Telecommunications Distribution Design Guide [ Version 8 ]


Appendix 6
Patch Panel
A panel mounted in an equipment rack in the Telecommunications Room or Equipment Room containing
modular jacks. The telecommunications room or ER end of the horizontal distribution data cable is
terminated at the patch panel. Patch cords are used to connect work area devices to network switches
located in the telecommunications room or ER.

Pathway (or Cable Pathway)


A raceway, conduit, sleeve, or reserved location for the placing and routing of telecommunications cable.

PBX
Private Branch eXchange. A large, full-featured telephone switching system that usually serves a large
building or campus.

POP
Point-of-Presence. The physical location where a service provider delivers telecommunications service.
See MPOP, Demarc, and Telecommunications Service Entrance Facility.

Port
See Modular Jack.

Primary Protector (or Protector Block, or Protector Panel)


A device interconnected to the telecommunications service provider’s access line, or to each end of an
outside plant campus distribution copper cable, to protect the connected equipment and personnel from
over-voltage and/or over-current conditions. Hazardous voltages and currents are shunted to ground
through the protector block.

Pullbox
A box, located in an inside plant cable pathway, intended to serve as an access point to facilitate pulling
cable through the conduit.

Registered Communications Distribution Designer (RCDD)


An internationally recognized professional designation presented by BICSI to its members that have proven
their ability through on-the-job experience and having passed a thorough exam.

Radio Frequency Interference (RFI)


A signal distortion directly related to a foreign radio signal being imposed through coupling onto a
transmission path to which the foreign radio signal is not physically connected.

Raceway
A metal or plastic channel used for loosely holding telecommunications or electrical cables. See Pathway.

Riser Cable
An obsolete term referring to backbone cable.

Router
A device that connects two networks and routes data traffic between them.

Telecommunications Distribution Design Guide [ Version 8 ] 176


Security Systems
Systems such as intrusion alarms, remote door locks, and magnetic strip identification cards which may be
computer-controlled and networked. Some new technology employs biometric systems that scan the retina
of the eye, or make an optical image of the fingerprint, and compare that image to a computer database as a
means of identification. Many of these systems have proprietary components, but many can be networked
on the common telecommunications infrastructure and shall be taken into consideration in any design.

Service Provider
The company or utility that provides telecommunications services to a customer.

Sneak Current
Unwanted but steady currents that seep into a communication circuit. These low-level currents are
insufficient to trigger electrical surge protectors and therefore are able to pass them undetected. They are
usually too weak to cause immediate damage, but if unchecked will create harmful heating effects. Sneak
currents may result from contact between telecommunications lines and AC power circuits or from power
induction, and may cause equipment damage due to overheating.

Splice
A permanent joining of conductors from separate cables.

Splice Box
A box, located in a pathway, intended to house a cable splice.

Splice Closure
A device used to enclose and protect a cable splice.

Star Topology (or Star Distribution)


A cabling topology where all telephones and computers in a given area are wired directly to a central service
location in the telecommunications room. Star topology is the standard wiring topology for the GSA.

Sweep
A conduit bend that meets ANSI/TIA/EIA-569-C bend-radius requirements forming a gentle arc rather than a
sharp bend.

Switch
An electronic device that interconnects networked data devices (computers) through port-to-port switching.

Telecommunications
Any transmission, emission, or reception of signs, signals, writings, images, and sounds, or information of
any nature by wire, radio, visual, or other electromagnetic systems.

Telecommunications Bonding Backbone (TBB)


The grounding conductor (cable) that interconnects the Telecommunications Main Grounding Busbar
(TMGB), Telecommunications Grounding Busbars (TGB), various telecommunications equipment,
equipment racks, and cable shields to the building’s electrical service grounding electrode.

177 Telecommunications Distribution Design Guide [ Version 8 ]


Appendix 6
Telecommunications Room (TR)
A location in each building, or each floor of a building, where backbone cables transition to horizontal
distribution cables. The TR may also contain certain items of network electronics equipment, such as hubs
or routers. A large building, with large floors, may have multiple TRs on a floor. Depending on the size of
the building, a TR may be a separate room, or it may be simply be a cabinet containing telecommunications
equipment.

Telecommunications Grounding Busbar (TGB)


In buildings with multiple Telecommunications Rooms, each telecommunications room is equipped with a
TGB. All of the TGBs in the building are bonded to the Telecommunications Main Grounding Busbar
(TMGB) by the Telecommunications Bonding Backbone (TBB).

Telecommunications Infrastructure
The pathways, spaces, and cabling necessary to support the signaling between telecommunications
devices. The infrastructure must be designed to support the known present, and reasonably certain future,
signaling requirements of the telecommunications systems. With the rapid advances in telecommunications
technology, the telecommunications cabling will likely require replacement or upgrade several times over the
life of a building, with an average life expectancy of 8 to 15 years. Therefore, the design of the pathways
and spaces has a major impact on the cost of future cabling upgrades.

Telecommunications Main Grounding Busbar (TMGB)


A busbar placed in a convenient and accessible location in the Entrance Facility (EF), Equipment Room
(ER), and all Telecommunications Rooms. All telecommunications equipment, equipment racks, protector
blocks, metallic cable shields, and exposed non-current-carrying metal parts of information technology
equipment are bonded to the TMGB, which is then bonded by means of the Telecommunications Bonding
Backbone (TBB) to the main electrical service grounding electrode.

Telecommunications Service Entrance Facility (EF)


The point where the telecommunications service enters the customer’s property. The EF may contain
electronics equipment and line protection equipment required by the service provider. The EF may be
combined with the Main Telecommunications Equipment Room, or the EF may be an outdoor pedestal or
cabinet near the street. See also Demarc, POP, and MPOP.

Termination Field
A space on the plywood telecommunications backboard where termination hardware is mounted. The
termination field is arranged into areas where different types of cables are terminated based on their
purposes and uses.

Termination Hardware
Any device used on the end of a cable to connect or cross-connect cables to other cables, or to
telecommunications equipment.

Uninterruptible Power Supply (UPS)


A device used to temporarily supply power during a utility power outage and to stabilize power to its load
when utility power experiences anomalies. UPSs include flywheel equipment as well as traditional battery-
backed equipment.

Voice Services
Communications supported by the telecommunications infrastructure, including telephone services, either
directly from the Local Exchange Carrier (LEC), or from a GSA-owned telephone system, voice mail

Telecommunications Distribution Design Guide [ Version 8 ] 178


services, intercom and paging services, and some radio systems. Fax services and individual computer
modems usually operate over the voice system.

Voice-Over-IP (VOIP)
Modern telephone equipment carries audible voice signals through the data network via Ethernet data
packets, compared with traditional analog and digital telephone systems that require circuit connections or
proprietary digital signaling.

Voice Switch
An electronic device that establishes or disestablishes circuits between telecommunications systems or
devices.

Wireless Access Point (WAP)


A device typically mounted at the ceiling to provide wireless networking services for use with portable
devices such as tablets, notebook computers, and smart phones.

Work area
The location where telecommunications service is provided for people to use. This is the area where a
computer, telephone, or other telecommunications device is located and where people will use these tools to
do work.

179 Telecommunications Distribution Design Guide [ Version 8 ]


Appendix 6

This page intentionally left blank

Telecommunications Distribution Design Guide [ Version 8 ] 180


7
Index

20-year (minimum) Application Assurance ANSI/TIA/EIA 942-A – Telecommunications


Warranty ................. 24, 29, 33, 34, 40, 46, 106 Infrastructure Standard For Data Centers ....14,
125
Access Control Systems ....................... 11, 59, 92
ANSI/TIA/EIA Commercial Building
Alarm Systems .................................................. 11 Telecommunications Standards . 12, 14, 17, 32,
American National Standards Institute (ANSI) .. 14 40, 43

ANSI/TIA/EIA 568-C series – Commercial Architects 9, 19, 31, 32, 37, 38, 39, 47, 52, 56, 58,
Building Telecommunications Standards ..... 14, 102, 172
171 Architectural Barriers Act Accessibility Standard
ANSI/TIA/EIA 569-C series – (ABAAS) ...................................................... 94
Telecommunications Pathways and Spaces 14, Backboards42, 59, 71, 72, 73, 103, 147, 148, 178
177
BICSI...........................................................12, 16
ANSI/TIA/EIA 606-B series – Administration
Standard for Telecommunications Information Transport Systems Installation Methods
Infrastructure .................................... 14, 35, 36 Manual (ITSIMM) .................................. 12, 14, 74

ANSI/TIA/EIA 607-B series – Generic Outside Plant Design Reference Manual (OSPDRM)
........................................................ 12, 14, 15, 74
Telecommunications Grounding (Earthing) and
Bonding Requirements for Customer Premises Telecommunications Cabling Installation Manual
................................................ 14, 73, 113, 143 (TCIM) ........................................................ 12, 17

ANSI/TIA/EIA 758-B series – Customer-Owned Telecommunications Distribution Methods Manual


Outside Plant Telecommunications (TDMM) . 12, 14, 15, 16, 55, 60, 63, 73, 105, 109,
114, 121, 143
Infrastructure Standard ................................. 14
ANSI/TIA/EIA 862-A – Building Automation Bidding ................................ 30, 43, 113, 122, 124
Systems Cabling Standard10, 14, 25, 109, 121 Building Automation Systems .... 11, 25, 106, 109,

181 Telecommunications Distribution Design Guide [ Version 8 ]


121 135, 139, 173, 177
Cabinets for Telecommunications Equipment .. 57, Electromagnetic Interference (EMI) 39, 52, 55, 56,
58, 61, 62, 63, 64, 68, 71, 72, 127, 128, 134, 57, 63, 65, 68, 135, 173
146
Elevation Diagrams 41, 43, 62, 87, 146, 148, 149,
Cable Length............................................. 56, 120 162, 164
Cable Test Reports ..................... 45, 46, 119, 120 Energy Management Systems ......................... 11
Cable Tray ........................ 60, 101, 102, 103, 149 Engineers ..........................................9, 37, 38, 39
Category 5 Cable ............................................ 109 Entrance Facilities .... 13, 33, 73, 76, 80, 147, 148,
149, 172, 173, 175, 176, 178
Category 5e Cable .......................................... 109
Environmental Control Systems .. 11, 59, 133, 139
Category 6 Cable .................................... 108, 109
Equipment Rooms 13, 56, 80, 114, 116, 125, 126,
Closed Circuit Television Systems .................... 11 135, 141, 143, 156, 162, 164, 174, 175, 176,
Conduit Bends ...................... 43, 62, 63, 146, 177 178

Conduit Fill ...................................................... 103 Facilities Standards for the Public Buildings
Service document (PBS P100) .................... 15
Construction Document Phase ......................... 42
Federal Acquisition Regulation (FAR) .........19, 28
Construction Documents .... 12, 13, 16, 38, 43, 44,
45, 46, 115, 145, 147, 148, 150, 156, 162, 164 Fiber Optic Cabling .. 9, 10, 11, 26, 34, 56, 77, 78,
79, 102, 105, 107, 117, 119, 120, 123, 149,
Construction Observation.......... 22, 28, 44, 45, 52 150, 166, 171, 173
Construction Type Fire Alarm Systems ...............................11, 58, 92
Historical Building Remodel ................. 16, 17, 93, 95 Fire Protection Engineer .............................38, 59
Minor Remodel 16, 23, 25, 30, 56, 57, 61, 63, 72, 93,
95, 101
Fire Suppression Systems ..................26, 61, 134

Modernization ................................ 16, 25, 30, 71, 76 Firestop Contractors International Association
(FCIA) .......................................................... 14
New Construction...... 16, 23, 25, 30, 71, 76, 93, 101,
103, 106 Firestopping ................................ 23, 38, 101, 112
Telecommunications-only ............ 16, 25, 93, 95, 101 Flex Conduit ..............................................43, 103
Contractors ...... 9, 30, 31, 33, 44, 45, 46, 52, 115, Floors ....................................................39, 57, 59
119, 146, 172
Grounding and Bonding ... 38, 43, 63, 71, 73, 113,
Convenience Power Outlet ........... 35, 72, 93, 143 143, 146, 147, 148, 149, 173, 177, 178
Coordination (Cross-discipline) 10, 39, 52, 58, 64, GSA
114, 123, 139, 145, 146, 149, 150
Federal Acquisition Services (FAS) ....................... 18
Cutover Plans ......................................... 149, 150 Inspector General (IG) ........................................... 18
Data Networks .................................................. 11 InterSec Branch Manager...................................... 19
Demarcation Point ............................ 33, 147, 172 Office of General Counsel (OGC).......................... 18
Design Development Phase............ 42, 43, 58, 59 Office of the Chief Information Officer (OCIO)....... 18
Design Review Process32, 42, 43, 47, 48, 50, 52, PBS Building Manager .......................................... 18
153
PBS Project Manager ............................................ 18
Designer Qualifications ......................... 15, 37, 38 Public Building Services (PBS)........................ 18, 30
Doors ........................ 26, 58, 63, 81, 86, 128, 177 Requirements & Operations Branch ...................... 19
D-Rings ........................................................... 102 GSA Personnel ...........................................21, 24
Electrical Engineers ...................... 38, 64, 93, 114 HVAC Systems ......................... 10, 16, 39, 59, 60
Electrical Power 57, 64, 65, 68, 71, 102, 109, 114, Identifiers .. 35, 115, 116, 117, 118, 146, 150, 174

Telecommunications Distribution Design Guide [ Version 8 ] 182


Innerduct ........................................................... 80 Poke-thru ........................................................101
International Building Code ................. 23, 59, 101 Power over Ethernet .......................................135
J-Hooks ................................................... 101, 102 Power over Ethernet (POE) .. 19, 60, 64, 114, 123
Junction Boxes.......................... 53, 101, 104, 146 Prime Consultant............................. 32, 38, 41, 52
Labeling ...................... 71, 72, 115, 116, 117, 118 Procurement and Provision .........................22, 28
Link-Loss Budget .................... 120, 149, 150, 166 Project Specification..... 12, 13, 16, 22, 30, 35, 38,
42, 47, 52, 106, 115, 148, 149, 150, 154
Local Area Network (LAN) ... 22, 34, 62, 123, 124,
173, 174, 177 Pullboxes ............................................39, 53, 104
Low Voltage Electronics Room ......................... 11 Racks ... 58, 61, 62, 63, 71, 72, 73, 117, 127, 130,
143, 146, 147, 148, 177, 178
Low Voltage Systems .. 10, 11, 13, 23, 25, 27, 56,
58, 94, 108, 109, 114, 124, 139, 147, 148 Record Drawings............. 35, 36, 44, 46, 115, 150
Mechanical Engineers ................................. 59, 60 Registered Communications Distribution
Designers..... 19, 22, 28, 30, 31, 32, 34, 37, 38,
Mechanical Room ....................................... 11, 57 39, 44, 47, 48, 50, 52
Moves/Adds/Changes (MAC)...................... 34, 35 Review Comment Report ................................153
National Electrical Code (NEC) 14, 17, 22, 32, 55, RF Radiation ...............................................57, 80
56
Schematic Design Phase .. 39, 41, 42, 43, 56, 100
National Electrical Safety Code................... 14, 56
Security Systems ............ 11, 58, 92, 93, 124, 177
National Fire Protection Association (NFPA) .... 14
Service Providers ........ 33, 52, 172, 175, 176, 178
Non-GSA tenants 1, 17, 24, 25, 33, 80, 88, 92, 93
Sizing of TRs .. 27, 42, 56, 57, 58, 63, 64, 71, 126,
OCIO 127
Information Technology Specialist 27, 31, 32, 34, 47,
48, 52, 126, 127, 139 Splicing ...........................................105, 172, 177

Information Technology Specialist ......................... 18 Splitting Pairs ............................................34, 106


Telecommunications Designer............................... 19 Standards Variance Request .......... 14, 32, 40, 41
Telecommunications Project Manager 18, 30, 31, 32, Steam ............................................................... 57
39, 47
Structured Cabling System (SCS) .................... 19
Operation and Maintenance Manuals ............... 46
Submittals .................................................44, 150
Outside Plant Telecommunications Infrastructure
........................ 11, 80, 120, 173, 174, 175, 176 Surface Raceway .................. 63, 81, 95, 101, 104

Paint (Fire-retardant) ....................................... 171 Technical Power Outlets ... 35, 64, 68, 71, 72, 141

Patch Cords ..... 34, 77, 79, 82, 88, 105, 110, 111, Technical Power Panels ..................................135
176 Telecommunications Construction Guide
Patch Panels 34, 77, 79, 105, 106, 107, 108, 111, Specification ................................................ 12
117, 118, 122, 124, 148, 175, 176 Telecommunications Rooms .... 13, 21, 25, 27, 35,
PBS 56, 63, 117, 118, 125, 147, 156, 164

Project Manager................. 31, 32, 39, 44, 45, 47, 48 Testing 22, 24, 34, 45, 46, 72, 109, 119, 120, 123,
139
PBX Telephone Equipment .... 141, 143, 147, 148,
176 TIA/EIA 455 Standard Test Procedures for Fiber
Optic Systems .............................................. 14
Photographs................................ 41, 44, 148, 150
TIA/EIA 526 – Optical Fiber Systems Test
PLC Control Systems ........................................ 11 Procedures .................................................. 14
Plumbing ........................................................... 39 Training .................................................22, 34, 45

183 Telecommunications Distribution Design Guide [ Version 8 ]


Under Slab or In Slab Conduit ............ 43, 76, 103 71, 133, 135, 139, 141, 147, 148
Undercarpet Telecommunications Cabling ....... 93 Voice-over-IP (VOIP) .............. 11, 28, 34, 92, 109
Underfloor Duct ............................................... 104 Wireless or Radio System Distribution .11, 80, 88,
92, 93, 123
Uninterruptible Power Supply... 60, 62, 63, 64, 68,

Telecommunications Distribution Design Guide [ Version 8 ] 184

You might also like