Siphonitech Users Guide
Siphonitech Users Guide
SiphoniTec
A Siphonic Roof Drainage
Design Utility
User’s Guide
Release 2.0
Table of Contents
Introduction......................................................................................................................... 3
Who Is This Guide For?.................................................................................................. 3
System Requirements...................................................................................................... 3
Updates ........................................................................................................................... 4
Questions and Comments ............................................................................................... 4
Working with the Software................................................................................................. 5
Overview......................................................................................................................... 5
Determining the Version................................................................................................. 6
Getting Help.................................................................................................................... 6
RMS Website .............................................................................................................. 6
Users Guide................................................................................................................. 7
Get Latest Components............................................................................................... 7
Projects............................................................................................................................ 7
Starting a New Project ............................................................................................ 7
Removing a Project................................................................................................. 9
Renaming a Project ................................................................................................. 9
Loading a Project .................................................................................................... 9
Saving a Project .................................................................................................... 10
Clearing Messages ................................................................................................ 10
Building a System ..................................................................................................... 10
Adding Elements................................................................................................... 10
Checking the Design ................................................................................................. 18
Running Calculations............................................................................................ 18
Viewing Calculations............................................................................................ 18
Checking Errors .................................................................................................... 19
Checking Residual Head and Imbalance .............................................................. 19
Generating a Formal Report...................................................................................... 20
The Library ................................................................................................................... 20
Drainage Elements .................................................................................................... 20
Viewing Elements................................................................................................. 21
Modifying Elements.............................................................................................. 21
Adding Elements................................................................................................... 21
Saving the Library................................................................................................. 21
Configuration Elements ............................................................................................ 21
Introduction
Why use a software product to design siphonic roof drainage systems? The answer is
simple enough. The design of a system involves mathematics, precision and repetitive use
of hydraulic formulas; which is what computer software is best suited for. The software
manages the serious number crunching and leaves the designer free to manage simpler
physical parameters to arrive at a properly dimensioned system.
Currently, the software takes about 41 megabytes of storage space, including all Library
Elements to build a siphonic drainage system. It can load and remove Projects and have
multiple Projects loaded at the same time. Projects are saved to simple XML files and can
be handled individually.
The Windows Graphic User Interface (GUI) makes system design easy. A GUI Design
View tree display of the system shows (and allows selection of) every component. A
tabbed display shows Configuration, Calculation, and system Imbalance.
The Library of components is used in building a system. The software can add new
Elements to the existing Library and use them in Projects. This gives flexibility to
designs and lets an engineer design what is needed.
The Microsoft Excel Report summarizes a system with a hard-copy Report. The Report is
produced on request. It is a formal Report intended to be delivered to a client or building
official and has an area reserved for your Engineering Seal. The report can be altered to
suit varying tastes including your company information and logo. This feature saves
engineering time and effort gathering and confirming information.
System Requirements
While this software may run with other hardware and software, performance is not
guaranteed. You’ll need the following hardware and software to run this program:
Video (800 x 600 or higher resolution) monitor with at least 256 colors (1024 x
768 High Color 16-bit recommended)
Microsoft Mouse or compatible pointing device
Updates
As the software and technology related to this product are updated, links to information
will be added to the Rainwater Management Solutions website. Visit the website
periodically at www.rainwatermanagement.com for the latest information.
Overview
The main interface gives you access to all the features of the SiphoniTec®. Just below
the title bar are the drop-down menus, action buttons and status display. The drop-down
menu gives access to Help features, the About information for this release, and the load
and save commands for Projects as well as the Library. The action buttons give access to
the check, calculate and report generation functions. The status display shows the status
of the selected Element.
The area between the Project, Detail and Message windows is adjustable by placing the
Windows cursor over the dividing bar and dragging left or right.
The best way to use the SiphoniTec® is start by opening or creating a Project. Then build
a system by selecting Elements from the Library to put a roof drainage system in place
from discharge to roof drain. When the basic system is in place, review the design by
checking the details of the configuration, calculations and imbalance. Adjust the values
and check again. When you are satisfied with the results, generate a report.
Getting Help
SiphoniTec® offers three different types of help. All three are accessed by right clicking
on Help in the drop-down menu. From the drop-down menu you can select RMS
Website, Users Guide, or Get Latest Components.
RMS Website
Right clicking on RMS Website will open your web browser and take you to the RMS
website. From there you can find out the latest news about rainwater harvesting and
SiphoniTec®.
Users Guide
Right clicking on Users Guide will bring up this document in a new window. You can
browse this document for the section you need without having to locate this document on
your computer.
Projects
Managing Projects
Proceed to build the Project by adding Elements, starting with the Discharge and working
back into the building to the roof drains.
Removing a Project
To delete a Project from the Project Window, first select a Project. Right click on the
selected Project. In the popup window that appears, click on Delete.
Renaming a Project
To rename a Project, first select the Project in the Project Window. Right click on the
Project. In the popup window that appears, click on Rename. In the highlighted box, enter
the new name for the Project.
Loading a Project
To load a Project file previously created and saved, go to the pull down the menu at the
top of the screen and click on File. Click on Load Project and select the file from the
Open window that appears. Navigate to the directory and file the Project was saved to.
Finally, click on the Open button. Alternately, click on the Load Recent selection in
the File menu to load a recent Project.
Saving a Project
To save a Project file, in the pull-down menu at the top of the screen, click on File. Click
on Save Project and enter a filename in the Save As window that appears. Click on
the Save button.
Clearing Messages
To clear all messages, select a message and right click on the message. In the popup
menu that appears, click on Delete to remove the selected message or click on Clear All
to remove all the messages from the Message Window.
Building a System
Adding Elements
Once the Project has been created and the Project information has been entered, begin
“building” the Pipe system by adding Elements. Start with a Discharge Element.
Discharges
Select the Discharges heading in the GUI under Project and right click on it. Click on
New in the popup menu that appears. Select the New Discharge Element that appears.
In the Detail Window, click on the [Configuration] tab. The information displayed is the
configuration data for the selected Discharge. Enter a Diameter, Inner Diameter, Static
Head, Name and Height for the Discharge.
Tip: In this version of the software, the designer must make a first guess at the Pipe
and fitting sizes when entering the Elements. A good “rule of thumb” that works well
is to determine the total square footage served by the Pipe and look up the specified
size in the plumbing code for horizontal piping at 1/8” per foot slope and at the
design rainfall intensity. Take that Pipe size and divide it in half. This will be the
approximate size of the siphonic Pipe. For example, if the code says that a
traditionally sized Pipe should be 10 inches, the resulting siphonic size is 5 inches (or
6 inches depending on availability). When in doubt, round up.
Once there is a Discharge, Elbows, Pipes, Junctions and Reducers can be added. Right
click on the Empty placeholder in the GUI Design View and select Replace in the pop
up menu. Select the new Element from the pop-up menu to the right (Pipe, Reducer, Roof
Drain, Junction or Elbow).
When all required information is entered, the entry fields will be white (i.e. not red) and
the Pipe icon appearing in the GUI Design View tree will be yellow.
Note: The software’s error checking engine will sometimes catch the lack of a
flow, pressure, or velocity as an error even though the calculation process has not
yet been executed. If the Element is re ation has
been entered, check the nature of the error by clicking on the ellipsis button to the
right of the top status bar. A pop-up window will appear describing the error.
Most likely it will indicate calculated parameters are missing. If this is the case,
ignore the error until after calculations have been executed.
Changing Orientation: If you select the wrong Pipe orientation or if you wish to change
the orientation for any reason, right-click on the Pipe icon and select Pipe Orientation
from the pop up menu and then the desired orientation. Check the Pipe elevations in the
Configuration tab.
When all required information is entered, the entry fields will be white (i.e. not red) and
the Elbow icon appearing in the GUI Design View tree will be yellow.
Note: The software’s error checking engine will sometimes catch the lack of a
flow, pressure, or velocity as an error even though the calculation process has not
yet been executed. If the Element is red even though the physical information has
been entered, check the nature of the error by clicking on the ellipsis button to the
right of the top status bar. A pop-up window will appear describing the error.
Most likely it will indicate calculated parameters are missing. If this is the case,
ignore the error until after calculations have been executed.
Reducers
When a change in Pipe size occurs, a Reducer (Increaser) must be inserted. Two
Elements of different diameters must have a Reducer (Increaser) inserted between them
to account for the minor energy loss that occurs due to the gradual or sudden expansion
or contraction of the water flow. The Reducer/Increaser Library provides the appropriate
resistance coefficient for the calculations.
To insert a Reducer/Increaser, right-click on the Empty placeholder and select Replace
> Reducer from the pop-up flag menus. The Element inherits the elevation of the
previous Element (the Parent). By convention, the Reducer Element has an A x B
designation. The A value corresponds to the downstream (Parent) Element Nominal
Diameter and the B value corresponds to the next upstream (Child) Element Nominal
Diameter.
that appears, select Replace > Roof Drain. In the Detail Window, click on the
[Configuration] tab and select the desired drain from the Element pull-down list.
Note: The outlet inner diameter of a selected roof drain may not be exactly equal
to the Pipe it connects to. When this condition occurs, a Reducer must be inserted
between the drain and the connecting Pipe to account for the difference. Several
“Adaptors” are listed in the Library for use.
Editing a System
General
In every design effort, both major and minor changes will be needed to achieve a
properly dimensioned system. The cues to make changes are provided by the
calculations. The calculations provide Residual Heads for each roof drain, the Imbalance
between drains, Pipe velocities, and static pressures. Based on the results, Pipes and
fittings may need to be resized or a new configuration may be required.
Replace an Element
With the exception of Discharge and Roof Drain Elements, any Element in the system
can be replaced with another. To do this, right-click on the Element icon and select
Replace and then select the Element type you wish to change to. Go the [Configuration]
view to update the physical parameters. The only Element types that can not be made to
appear in a system are Roof Drains and Discharge Elements because these Elements can
appear only at the ends of a system.
Change Library Element
Any Element can be changed with a like Element from the Library. This feature is used
mainly to re-size Pipe, Elbows, Junctions, Reducers and Roof Drains. To change the
Element, go to the [Configuration] tab and pull down the Library Element list-box. Select
the desired Element from the list. If there is a diameter change, appropriate Reducers
must be inserted ahead of and/or behind the changed Element to account for transitions in
Pipe size. In this version of the software, only one Element can be changed at a time. So
if an entire series of Elements need to be changed in diameter, each one must be changed
individually.
Insert an Element
Inserting an Element in the GUI Design View tree is very easy. Upon identifying the spot
where you need to insert a new Element between two existing Elements, right-click on
the Child Element, that is, the Element that is to become “upstream” of the new Element
referenced to the direction of water flow. In the GUI Design View tree, it is always the
Element below on the tree. From the pop-up menu, select Insert Before and then select
the desired Element type. Go to the Configuration tab to update the physical parameters.
the Project Window. Click on the action button with the green arrow icon near the
top right of the screen. The colors of each Element will change to red, yellow or green.
Red Elements indicate an error. Yellow Elements indicate a warning that may require
system adjustment. Green Elements are fine as they are.
Viewing Calculations
The calculation results for any Element in the system can be viewed by clicking on the
Element and then going to the [Calculation] tab in the Detail Window. If there were any
errors or warnings, the specific parameter will appear in either red or yellow. View the
calculations to check minimum velocities, static pressures, etc. in order to understand the
operating conditions of the system.
Checking Errors
Review the calculated values of the Elements of the Project in the [Calculation] tab as
well as the Error Messages in the Message Window by clicking on the ellipsis to the right
of the status bar. Change the physical parameters of Elements in the Project to remove
any errors. When satisfied, run the calculations again.
1. Select a template
2. Select an output file
3. Determine if you want to see the changes as they occur
4. Click on Export Now
5. Close the window when done
The Report will be produced at the location with the name selected. It is based on the
format of the template selected. Users can create their own templates based on the
template provided by Rainwater Management Solutions.
The Library
The Library contains information on pipes and fittings used for designing your drainage
system. There are two types of Elements in the Library: Drainage Elements and
Configuration Elements. To view all of the available types, select the Library tab in the
Project Window.
Note that while the Library tab is selected in the Project Window, the Calculation and
Imbalance tabs in the Detail Window have no purpose. When you are planning on
viewing information on Library items, we suggest you select the Configuration tab in the
Detail Window first. This will save you time as you browse items.
Drainage Elements
There are several types of drainage Elements included in the Library. They are Elbows,
Junctions, Pipes, Reducers and Roof Drains.
Viewing Elements
To view all the available items under a Drainage Element type, click on the + symbol
beside the Name of the item type in the Project Window. This will expand a list showing
each item. If you want to view the detailed information for an item, click on the name of
the specific item. Then, make sure the Configuration tab is selected in the Detail
Window. This will display all of the detailed information about the selected item.
Modifying Elements
To modify an item, start off by viewing it, as described above. Then you can alter the
information in the Detail Window. Simply use your mouse to select a value and change
it. You may notice that you can’t just type in every field to replace a value. Some fields
restrict what values you can enter. If there is a box with a down-arrow at the far right of
the field, you can only pick from a select list of values. Click on the down-arrow and a
pull-down list will appear. Click on a displayed value and it will be entered for you.
Some fields have a gray background. The values in these fields can not be modified.
Adding Elements
To add a new item to the list of an Element type, right-click on the name of the Element
type in the Project Window. A menu will appear. Select New from the menu, and a new
item will be added to the list of items. To give the item specific values for the various
fields, just select the item then modify them as described above.
Configuration Elements
There are many types of configuration Elements included in the Library. They are
Materials, Nominal Angles, Nominal Sizes, States & Provinces, Unit Culture, Water
Density, Water Viscosity and Zip Codes. Many of these are reserved for future use, and
not currently active for users.
You may view all of the items of these Elements. Most items and Elements can not be
modified, and will not let you add new items. However a few will let you add and
modify. We recommend that you leave these Element lists as they are. Changing them
can have a severe effect on the calculations, and give erroneous results.
If you are interested in the values in this area, we suggest formal training in the area of
siphonic drainage. Please contact Rainwater Management Solutions to find out the latest
schedule and fees for advanced siphonic training.