Actm Volume-Ii Part-I November-2022
Actm Volume-Ii Part-I November-2022
jsy ea=ky;
(jsyos cksMZ)
Hkkjrh; jsy
, lh d’kZ.k fu;ekoyh
vuqj{k.k ,ao ifjpkyu
ftYn - 2 (Hkkx - 1)
fL/kj laL/kkiuk,a
uoacj] 2022
GOVERNMENT OF INDIA
MINISTRY OF RAILWAYS
RAILWAY BOARD
INDIAN RAILWAYS
MANUAL OF AC TRACTION
MAINTENANCE AND OPERATION
VOLUME II (PART I)
FIXED INSTALLATIONS
NOVEMBER, 2022
INDEX
i
20221 Protective Relays ...............................................................................................19
20222 Guidelines for Maintenance of Switching Stations ...........................................20
20223 Schedules of Inspection .....................................................................................20
20224 General ..............................................................................................................21
20225 General Inspection by a PSI Supervisor ............................................................21
20226 Battery ................................................................................................................22
20227 Bonding And Earthing .......................................................................................22
20228 Oil Level in Transformers, CTS ,PTs etc. ..........................................................22
20229 Insulators ............................................................................................................22
20230 Traction Transformers .......................................................................................22
20231 Operating Mechanism of Circuit Breakers and Interruptors..............................23
20232 Isolators ..............................................................................................................23
20233 Busbars, Clamps and Connectors ......................................................................23
20234 Control and Relay Panels. ..................................................................................23
20235 Batteries and Battery Chargers ..........................................................................24
20236 PTs and CTs .......................................................................................................24
20237 Booster Transformers- deleted ...........................................................................24
20238 Auxiliary Transformers ......................................................................................24
20239 General ...............................................................................................................24
20240 Traction Transformers ........................................................................................24
20241 Isolators ..............................................................................................................24
20242 Control and Relay Panels. ..................................................................................25
20243 General. ..............................................................................................................25
20244 Lightning Arrestors ............................................................................................25
20245 Bonding and Earthing ........................................................................................25
20246 Traction Transformers. .......................................................................................25
20247 Isolators ..............................................................................................................25
20248 Bus Bars and Connectors ...................................................................................26
20249 Control and Relay Panels ...................................................................................26
20250 Batteries and Battery Chargers ..........................................................................26
20251 PTs and CTs .......................................................................................................26
20252 Deleted (RDSO SPEC No. TI/SPC/PSI/HV CB /0121(MAY 2021) .............26
20253 Pre-Monsoon Check...........................................................................................26
20254 Overhaul Schedule for Equipment .....................................................................26
ii
Chapter-3 Overhead Equipment ............................................................................... 47
20300 Introduction ........................................................................................................ 47
20301 Duties of SSE (OHE) ......................................................................................... 47
20302 Duties of Field Supervisors................................................................................ 48
20303 Technician (Rly Bd. L.No. 2013/ELECT/148/1Dt.10.05.2019
Foot Patrolling by Technician) ........................................................................... 49
20304 Introduction....................................................................................................... 49
20305 Out of Plumb Masts ........................................................................................... 50
20306 Rail Level and Setting Distance......................................................................... 51
20307 Contact Wire Hard Spots and Wear.................................................................... 52
20308 Sparking During Current Collection .................................................................. 53
20309 Contact Wire Wear ............................................................................................. 53
20310 Splice Fittings .................................................................................................... 54
20311 Section Insulator Assembly ................................................................................ 55
20312 Short Neutral Sections Assembly ....................................................................... 58
20313 Jumper Connections ........................................................................................... 60
20314 Environmental Effect on OHE ........................................................................... 61
20315 Clearances in Tunnels and Other Overline Structures ....................................... 64
20316 Regulating Equipment ....................................................................................... 64
20317 OHE Inspection Car (Tower Wagon) ................................................................. 66
20318 Salient Features of OHE Inspection Cars .......................................................... 67
20319 Rules for Operation of OHE Inspection Car ...................................................... 69
20320 Schedule of Inspections ..................................................................................... 70
20321 General............................................................................................................... 71
20322 Foot-Patrolling of OHE...................................................................................... 71
20323 Footplate Inspection of OHE ............................................................................. 73
20324 Current Collection Tests .................................................................................... 73
20325 Special Checks ................................................................................................... 73
20326 Annual Maintenance and Checks by OHE Inspection Car .................................. 75
20327 Integrated Blocks .................................................................................................. 79
20328 Re-tensioning of Unregulated OHE ..................................................................... 80
20329 Periodical Overhaul .............................................................................................. 80
20330 Rehabilitation of OHE ....................................................................................... 82
20331 Transmission Lines ............................................................................................ 82
20332 General............................................................................................................... 84
20333 Documents to be kept with OHE Supervisors for Work on OHE ...................... 84
iii
20334 Permit to Work ................................................................................................... 84
........... 84
20336 Earthing before Commencement of Work ......................................................... 85
20337 Procedure for Providing Temporary Earths........................................................ 85
20338 Precautions in Regard to Discharge/Earthing Pole Assembly............................ 86
20339 Work on OHE or any Conductor having a Sectioning Point .............................. 86
20340 Protective Helmets ............................................................................................. 86
20341 Safety Belt.......................................................................................................... 86
20342 Rules for use of Ladders .................................................................................... 86
20343 Other Important Precautions to be taken while Carrying out Works on OHE ... 87
20344 Procedure for Effecting Shut-Down for Work on Auxiliary Transformers ......... 87
........................ 87
20346 Deleted ............................................................................................................... 87
20347 Isolators.............................................................................................................. 87
20348 Petroleum Sidings .............................................................................................. 88
20349 Records to be Maintained .................................................................................. 88
Chapter-4 Remote Control Equipment ................................................................... 105
20400 Introduction...................................................................................................... 105
20401 General............................................................................................................. 105
20402 Transmission Path ............................................................................................ 105
20403 Master Station Equipment................................................................................ 105
20404 Overall Screen Design &Real Time Display ................................................... 106
20405 Alarm Processing and displays: ...................................................................... 106
20406 SCADA Software ............................................................................................. 106
20407 Test Procedure& Diagnostics ........................................................................... 107
20408 Historical Data Storage .................................................................................... 107
20409 UPS and Batteries at RCC ............................................................................... 107
20410 Remote Terminal Unit (RTU) .......................................................................... 108
20411 RTU FUNCTIONAL DETAILS....................................................................... 108
20412 SCADA Equipment Capacity .......................................................................... 108
20413 Energy Management System (EMS): .............................................................. 109
20414 Special Features in SCADA Equipment........................................................... 109
20415 Duties of SSE(RC) ........................................................................................... 110
20416 Operation of RC Equipment ............................................................................ 110
20417 Investigation of Failures by SSE (RC)............................................................. 111
20418 Maintenance Schedule ..................................................................................... 111
iv
Chapter-5 Operation Of Traction Power Control ...................................................113
20500 Remote Control Centre .................................................................................... 113
20501 Manning of RCC.............................................................................................. 113
20502 Knowledge of Rules ........................................................................................ 113
20503 Entry into RCC ................................................................................................ 113
20504 Shift Duty......................................................................................................... 113
20505 Shift Duty Register .......................................................................................... 113
20506 Repair and Adjustment of RC Equipment........................................................ 114
20507 Switching Operations to be Deliberate ............................................................ 114
20508 Liaisons with Section Controller ..................................................................... 114
20509 Prompt Attention to Telephone Calls................................................................ 114
20510 Log Book ......................................................................................................... 114
20511 Movements of Maintenance Staff .................................................................... 114
20512 Checking of Time............................................................................................. 114
20513 deleted .............................................................................................................. 114
20514 Emergency Generator Set ................................................................................ 115
20515 Duties of Chief Traction Power Controller ...................................................... 115
20516 Duties of Traction Power Controller ................................................................ 115
20517 Failure of Traction Power Supply .................................................................... 116
20518 Failures of Grid Supply.................................................................................... 117
20519 Prolonged Power Supply Failures .................................................................... 117
20520 Faults on Railway Equipment and Lines ......................................................... 117
20521 Lowering Pantographs of Defective Locos...................................................... 118
20522 Isolation of Faulty Section ............................................................................... 118
20523 Faulty Section to be kept Isolated .................................................................... 118
20524 Advice to Section Controller ............................................................................ 119
20525 Information to Traction Staff ........................................................................... 119
20526 Action to Rectify OHE Fault............................................................................ 119
20527 Emergency Telephone Working ....................................................................... 120
20528 Breakdowns and Emergencies ......................................................................... 120
20529 Obstruction of Track - Protective Steps to be taken by TPC............................ 120
Chapter-6 Power Blocks And Permits-To-Work..................................................... 123
20600 Operation of Isolator Switches ........................................................................ 123
20601 Isolators in Yards and Sheds............................................................................. 123
20602 Maintenance Blocks......................................................................................... 123
20603 Power Blocks ................................................................................................... 124
v
20604 Emergency Power Block ................................................................................. 124
20605 Reporting Abnormalities in OHE ..................................................................... 124
20606 Request for Emergency Power Block .............................................................. 124
20607 Action to be taken by TPC ............................................................................... 125
20608 Precautions after Emergency Power Block is Imposed ................................... 125
...................... 125
20610 Telephone Messages......................................................................................... 125
.......... 126
20612 Pre-arranged Power Block ............................................................................... 127
20613 Restoration of Supply After a Permit-to-work is Returned ............................. 128
20614 Work by other than Authorized Persons ........................................................... 128
20615 Local Cancellation of Permit-to-Work When Telephones are Interrupted ....... 128
20616 Multiple Working Parties ................................................................................. 128
20617 Entries in the Log Book ................................................................................... 129
20618 Work Inside Loco Shed or Car Shed ................................................................ 129
20619 Local Block...................................................................................................... 129
20620 Protective Measures for Power Blocks ............................................................ 129
20621 Longitudinal Protection ................................................................................... 129
20622 Transverse or Cross Protection ........................................................................ 130
20623 Procedure for Arranging Longitudinal and Transverse Protection ................... 131
20624 Station Working Rules for Longitudinal and Transverse Protection ................ 131
20625 Protection of Dead Section .............................................................................. 131
20626 Shunting Movement Towards Dead Section .................................................... 132
20627 Movement of Other than Electric Trains ......................................................... 132
20628 Standard Forms for Power Block Messages .................................................... 133
Chapter-7 Signalling & Telecommnication And Permanent Way Installations
............................................................................. 147
20700 Introduction ...................................................................................................... 147
20701 Effects of 25 kV Traction on S&T Equipment ................................................. 147
20702 Types of Signals ............................................................................................... 148
20703 Locations of Signals ........................................................................................ 148
20704 Insulation of Wires and Point Rods.................................................................. 149
20705 Earthing of S&T Equipment ............................................................................ 149
20706 Signaling & Telecommunication Cables .......................................................... 149
20707 Block Instruments and Block Circuits ............................................................. 150
vi
20708 Track Circuits ................................................................................................... 150
20709 Bonding in Track Circuited Zones ................................................................... 150
20710 Signalling and Inter-locking Circuits ............................................................... 150
20711 Telecommunication Circuits ............................................................................. 151
20712 Principles of Tapping ....................................................................................... 151
20713 Power Supply Arrangement ............................................................................. 152
20714 Major Track Maintenance Works ..................................................................... 152
......................................................................... 153
Chapter-8 Breakdowns ............................................................................................. 155
20800 Knowledge of Rules ........................................................................................ 155
20801 Types of Breakdowns ....................................................................................... 155
20802 Breakdown Gangs............................................................................................ 155
20803 Emergency Stores and Breakdown Equipment................................................ 155
20804 Record of Staff Movements ............................................................................. 156
20805 Summoning of Emergency Staff ...................................................................... 156
20806 Traction Transformer Breakdowns ................................................................... 156
20807 Repair of Traction Transformer........................................................................ 156
20808 Mobile Power Van............................................................................................ 156
.................................................. 157
20810 Rail and Road Access....................................................................................... 157
20811 Procedure for Manning Sub-Stations And Switching Stations ......................... 157
20812 Restoration of Remote Control ........................................................................ 158
vii
20825 Safety Rules to be Observed ............................................................................ 160
.................................................. 161
20827 Clearance of Line for Steam/Diesel Traction................................................... 161
20828 Wiring Train ..................................................................................................... 161
20829 Interference with OHE During Restoration ..................................................... 161
20830 Temporary Diversions ...................................................................................... 161
20831 Funds Required for Dealing with Breakdowns ................................................ 163
20832 Log of Events and Reporting of Breakdowns.................................................. 164
20833 Protection of Staff ............................................................................................ 164
20834 Use of Cranes................................................................................................... 164
20835 Use of Road Vehicles during Emergencies....................................................... 164
20836 Driver’s Duties ................................................................................................. 164
20837 Operation of Road Vehicles ............................................................................. 165
20838 Precautions when Transporting Heavy Materials............................................. 166
20839 Transportation of Personnel ............................................................................. 166
20840 Parking ............................................................................................................. 166
20841 Maintenance of Road Vehicles......................................................................... 167
......................................................................... 167
Chapter-9 Preparation For Commssioning ............................................................ 171
20900 Introduction ...................................................................................................... 171
20901 Reference to Rules and Statutory Rules........................................................... 171
20902 Pre-Commissioning Inspections ...................................................................... 172
............................................................................. 172
20904 Planning of Power Supply ............................................................................... 172
20905 Commissioning of Traction Transformers ....................................................... 173
20906 Precautions During Commissioning of Traction Transformer ......................... 173
20907 Tests on Transformer Windings ........................................................................ 174
20908 Circuit Breakers and Interruptors .................................................................... 174
20909 Isolators............................................................................................................ 175
20910 Current and Potential Transformers ................................................................. 175
20911 Lightning Arrestors .......................................................................................... 175
20912 Shielding and Earthing..................................................................................... 175
20913 Busbars and Insulators ..................................................................................... 176
20914 Clearances ........................................................................................................ 176
20915 Auxiliary Power Supply for Traction Substations & Control Room ................ 176
viii
20916 Batteries & Battery Charger ............................................................................ 176
20917 General............................................................................................................. 177
20918 General Inspection of Substations and Commissioning .................................. 177
20919 Detailed Inspection of Transmission Lines ...................................................... 177
20920 Compliance with Rules and Approved ............................................................ 178
20921 Visual Inspection .............................................................................................. 178
20922 Clearances and Sag .......................................................................................... 178
20923 Earthing............................................................................................................ 179
20924 Insulators and Insulation Resistance ................................................................ 179
20925 Continuity Test ................................................................................................. 179
20926 Accessories ....................................................................................................... 179
20927 General inspection and Energization ............................................................... 180
20928 25 kV Feeders .................................................................................................. 180
20929 Testing of Protective Relays ............................................................................. 180
20930 Inspection of Setting of Relays and Calibration of Meters.............................. 180
20931 Protective Devices at Sub-stations ................................................................... 181
20932 Control Circuits and Wiring............................................................................. 182
20933 Fuses ................................................................................................................ 182
20934 Insulation and Lead Burden Measurement ...................................................... 183
20935 Current Transformer Ratio and Polarity Test ................................................... 183
20936 Primary Injection Test ...................................................................................... 184
20937 Voltage Transformer Ratio and Polarity Check ................................................ 184
20938 Electrical Operation of Indicators and Associated Devices ............................. 184
20939 Secondary Injection Test .................................................................................. 184
20940 Alarm and Trip Check ...................................................................................... 184
20941 Load Test.......................................................................................................... 185
................................................... 185
20943 Power Supply ................................................................................................... 186
20944 Installation of Equipment ................................................................................ 186
20945 Clearances ........................................................................................................ 186
20946 Auxiliary Transformers .................................................................................... 187
20947 General............................................................................................................. 187
20948 Interlocking ...................................................................................................... 187
20949 Feeding Posts ................................................................................................... 187
20950 Number Plates and Boards ............................................................................... 188
20951 Earthing and Bonding ...................................................................................... 188
ix
20952 Importance of Remote Control ........................................................................ 188
20953 Manning of Substations and switching posts ................................................... 189
20954 Level Measurements ........................................................................................ 189
20955 Detailed Inspection of RC Equipment ............................................................. 189
20956 Interlocking of the Bridging Interruptor .......................................................... 190
....................................................... 190
20958 Detailed Joint Inspection of OHE .................................................................... 191
20959 Compliance with Latest ................................................................................... 191
20960 Infringements ................................................................................................... 191
20961 Important Point to be Checked ........................................................................ 191
20962 Notices to be Displayed – Caution Boards and Number Plates ....................... 193
.......................................................... 193
................................... 193
20965 Lapping and Polishing of OHE........................................................................ 194
20966 Procedure for Final Test of OHE...................................................................... 194
20967 Insulation Tests ................................................................................................ 195
20968 Continuity Tests ............................................................................................... 197
................................................................ 197
................................................. 197
20971 Preparation by the Engineering Department .................................................... 199
20972 Preparation by the S&T Department ................................................................ 199
Chapter-10 Commissioning Of Electric Traction ................................................... 201
21000 General............................................................................................................. 201
21001 Preparation by Open Line ................................................................................ 201
21002 Organization for Inspection and Taking Over .................................................. 201
21003 Duties of Senior Divisional Electrical Engineer (TrD) .................................... 202
21004 Duties for Senior Divisional Electrical Engineer (RS) .................................... 203
21005 Responsibility of Construction Organization................................................... 203
21006 Commissioning of Traction Substations .......................................................... 204
......................... 205
21008 Sanction of Electrical Inspector to the Railway (EIG sanction)
& OHE energisation......................................................................................... 205
21009 Introduction of services on Electric Traction:.................................................. 207
21010 Inspection by CRS for the Introduction of Passenger Services
on Electric Traction:......................................................................................... 208
x
21011 Sanction of CRS for introduction of passenger services
on Electric Traction:......................................................................................... 208
21012 Anti-theft Energization ..................................................................................... 208
......... 208
21014 Contractor’s Responsibility During Guarantee Period .................................... 209
21015 Failure of Equipment After Commissioning and During
the Guarantee Period........................................................................................ 209
21016 History Sheet ................................................................................................... 210
............................................................................ 210
21018 Standard Forms ................................................................................................ 210
Chapter-11 Recent Developments ............................................................................ 229
21100 2x25 kV Auto-Transformer Feed System ......................................................... 229
21101 OHE Recording-cum-Test Car ......................................................................... 236
21102 Rail-cum-Road Vehicle .................................................................................... 237
21103 Transportable Self Propelled Trolley ................................................................ 237
21104 Microprocessor Based Numerical Integrated Feeder Protection Module ........ 237
21105 Composite Insulators........................................................................................ 238
21106 Automatic Phase Switching Section (in place of Neutral Section)
and Numerical Control Logic Relay: Deleted .................................................. 238
21107 HIGH RISE OHE ............................................................................................. 240
21109 Spring type ATD ............................................................................................... 247
21110 Open Access- Optimization of Traction Power Procurement Cost ................... 248
............................................... 251
21200 Introduction ...................................................................................................... 251
21201 Planning of Training in Advance...................................................................... 251
21202 Categories to be trained ................................................................................... 251
21203 Initial Training ................................................................................................. 251
21204 Promotional Courses ........................................................................................ 252
21205 Refresher Courses ............................................................................................ 252
21206 Facilities for Training....................................................................................... 253
21207 Training in General and Subsidiary Rules ....................................................... 254
...................................................... 254
21209 Examination at the End of Training ................................................................. 254
21210 Specialized Training......................................................................................... 254
xi
21211 Syllabi .............................................................................................................. 254
21212 Authorized Person ............................................................................................ 255
.................................................................................... 255
21214 Period of Training ............................................................................................ 256
21215 OHE Inspection Car Driver ............................................................................. 256
21216 Knowledge of Rules ........................................................................................ 256
..................................................................................... 256
21218 Service Record ................................................................................................. 257
21219 Inspections ....................................................................................................... 257
xii
CHAPTER-1
POWER SUPPLY FOR TRACTION
lines be taken:
1. A system of periodic meetings at different levels at mutually agreed intervals needs to be evolved.
2. Reliability of supply involves also the maintenance of traction voltage between 25 kV and 27.5
kV at the feeding posts and frequency between 48.5 Hz and 51.5 Hz. The serious repercussions
Supply Authorities.
3. The traction load should be treated as essential load and should not be disconnected or reduced to
meet supply system exigencies. This principle has been accepted by most Supply Authorities and
where this has not been done, constant efforts should be made at the high level periodic meetings
to get this principle accepted.
4. Since the cumulative effect of frequent power supply interruptions, even though of short duration at
a time, can be very serious to Railway working, a periodical review of all such interruptions should
be made at the Divisional level and the cause of each interruption ascertained as far as possible.
The results of the review should be furnished to PCEE to keep him fully informed of the power
supply position. This subject should also form an important item for discussion at the periodic
meetings with the Supply Authorities.
Railway with the concerned Supply Authority before the supply is actually taken. Where this has
6. When grid supply to any traction sub-station fails and consequently emergency working has to be
resorted to by extending the feed from adjacent sub-stations, the maximum demand at these sub-
stations may go up. Most Supply Authorities have agreed to ignore such temporary increase in
maximum demand for billing purposes. Where this has not yet been agreed to, efforts should be
continued to persuade the Supply Authorities to accept this principle.
1
Indian Railways - AC Traction Manual - Volume-II Part-I
7. The present methodology of measuring maximum demand at each individual sub-stations for the
purpose of billing has been reviewed by the Central Electricity Authority. It has been agreed that
Railways should be charged for traction power on the basis of simultaneous maximum demand
parameters. The implications of the various parameters should be studied carefully to keep the
energy cost to the minimum possible level.
2. Contract demand for each sub-station should be stipulated in relation to the expected actual
Maximum Demand in such a manner that in fructuous payments by way of minimum guarantee
on the one hand and penal charges for exceeding the contract demand on the other, are avoided.
Notice period for altering Contract Demand should also be kept as low as possible in the agreement,
preferably 4 to 6 weeks.
2
Chapter-1 Power Supply For Traction
3. In the tariff charged for electric traction, following are some of the parameters that should be given
careful consideration with a view to keeping down the energy bill to the minimum.
load. If two sets of trivector meters are provided, the higher of the two should be the MD to be
charged. Caution may be exercised to ensure that addition of both is not taken as MD in billing.
b. Energy charge Paise/kwh
d. Penalty for low power factor: The penal charge is prescribed as an extra amount leviable in Rs/
on consumer providing PF correcting equipment and do not permit power factor lower than a
prescribed value.
is higher.
f. Excess over Contract Demand and corresponding units of energy are usually charged at higher
tariff (excluding FAC). Even if the excess MD is for a short period of just 15 min., proportionate
MD = Maximum Demand
CD = Contract Demand
The Contract demand therefore, has to be carefully determined and reviewed periodically and
g. Minimum Guarantee
by the pattern of energy consumption in traction. However, minimum guarantee in some cases
if contract demand is too low, exceeding it and attracting penal changes becomes a possibility.
3
Indian Railways - AC Traction Manual - Volume-II Part-I
Authorities has been installed to meter the traction load. In later installations, a second set of
meters is being provided on the sub-station switchboard at Railways cost. Where only one set of
meters belonging to the supply authority is installed yearly testing of the meter should be carried
out. If its accuracy is in doubt at any point of time, the Railway is entitled to ask for testing and
these aspects should be embodied in the Agreement with the Supply Authorities.
2. The monthly meter readings should be taken on an agreed date each month jointly by representatives
of the Supply Authority and the Railway. The meter card as well as the printomaxigraph chart
reading showing the maximum demand for the month should be initialed by representatives of both
will also obtain additional information such as daily maximum demand for traction, power factor,
load factor, variation of voltage, changes in the system of interconnection, which have a bearing
on power supply for traction. Suggestions for suitable changes in the Supply Authority’s network
may be made at appropriate level and if necessary concrete proposals initiated for making power
to the Agreement and the tariff. A time schedule should be laid down jointly with the Accounts
Department for scrutiny and passing of the bill so as to take advantage of the rebate admissible, if
any, for prompt payment. Panel charges levied, if any, should be carefully scrutinized and appropriate
remedial measures taken to prevent recurrence. If the minimum charge payable is in excess of the
amount warranted by the actual energy consumption, this fact should be promptly brought to the
notice of PCEE as well as the operating Department to take special steps to arrange for movement of
2. Detailed instructions should be issued locally, jointly with the Accounts Department, listing the
items to be checked prior to passing the bills from the Supply Authorities. An illustrative list is
given below:
a. Arithmetical accuracy
b. Meter readings shown on the bill tally with those received earlier from the subordinates.
c. The tariff applied is in terms of the agreement.
d. The method of computation of the maximum demand for billing purpose is in accordance with
the agreement and that temporary increase in maximum demand on account of emergency
feeding has not been taken into account where this principle has been accepted.
4
Chapter-1 Power Supply For Traction
h. Each new bill should be analyzed and compared with earlier bill and the reasons for any
which may have to re-schedule trains and take other measures as necessary.
2. A double circuit set of transmission lines from the Grid sub-station are run to give supply to traction
sub-station. Therefore, maintenance of the transmission line does not necessitates total shut-down
of the systems. However, all such shut-downs should be planned well in advance giving the reasons
for the shut-down and anticipated duration.
contacted in an emergency.
5
Indian Railways - AC Traction Manual - Volume-II Part-I
6. Mutual assistance to be rendered for transmission of important messages in the event of telephone
failures at the grid sub-stations or RCC.
*****
6
CHAPTER-2
SUB-STATIONS AND SWITCHING STATIONS
20200 Introduction
1. This chapter is divided into 4 sections as under –
Section I Organization: A broad set up of the organisation and duties of SSE (Power Supply
Installations) are covered.
Section II Operation of Sub-Stations: The important points relating to operation of transformers
and protective devices are covered.
Section III Guiding Notes on Maintenance: The important points to be borne in mind in the
maintenance of power supply equipments are covered.
Section IV A recommended schedule of maintenance for power supply equipments is given.
I ORGANISATION
envisages separate Sr. Subordinate to be incharge of each activity viz. sub-station, OHE, workshop,
function. For territorial set up, the SSE incharge will perform his duties keeping all functions in view,
Remote Control system or protective relay testing being a specialized activity, SSE (RC) and SSE/Test
Room usually have a functional jurisdiction over the entire division, with Head Quarters at the Remote
Control Centre and Divisional Repair Shop respectively. The SSEs in territorial charge, should keep a
constant liaison between themselves since these aspects will have an element of dual control.
7
Indian Railways - AC Traction Manual - Volume-II Part-I
sub-stations (when owned by the railway), switching stations, booster transformer and auxiliary
transformers in his jurisdiction. He shall be thoroughly conversant with all technical details of the
equipment under his charge including their rating, trend of power demand as also correct methods of
their operation and maintenance, in particular, he shall
1. supervise the maintenance of installations under his charge in accordance with the prescribed
schedules to keep them fully serviceable at all times and in a state of good repair;
2. maintain proper co-ordination with the Traction Power Controller, SSE(OHE), Supply Authorities
and render assistance when required to ensure reliability of power supply;
3. keep his organization in constant readiness to deal promptly with any breakdowns and failures of
equipment;
4. ensure that the programme of testing and maintenance of protective relays is adhered to and ensure
that other safety equipment including bonding and earthing are functioning effectively;
5. instruct, train and supervise staff under his control and ensure that they do operate and maintain
the equipment properly and in particular do actually observe all rules and regulations and safety
precautions laid down;
their working;
7. Ensure that special instruments and tools provided for maintenance operation and testing of all
installations are properly cared for;
8. keep a close watch on availability of spare parts and other stores required for maintenance and
operation of the installations and initiate timely action to recoup stocks;
10. Depute staff when required to man sub-stations and switching stations in the event of failure of
remote control equipment;
11. Inspect all installations under his charge at least once a month, with particular attention to safety
aspects;
12. Submit prescribed periodical returns after careful scrutiny to ADEE/TRD and Sr. DEE/DEE(TRD);
when required;
II OPERATION OF SUB-STATIONS
20203 Introduction
Since the electric traction system depends upon continuous availability of power supply, sub-stations
and switching stations have to be kept in proper working condition at all the time. To ensure this, the
transmission lines, the 25 KV feeder lines and traction transformers with associated switch gear and
control and relay panels are duplicated so that if one unit fails, the standby unit can be brought into
service to continue power supply. All switching operations are also centralized and controlled by
remote operation by a single authority, namely Traction Power Controller.
8
Chapter-2 Sub-Stations and Switching Stations
a log book should also be maintained to keep a record of the traction transformer oil temperature,
every morning. If there is any thing abnormal unusual, SSE/PSI will investigate the cause thoroughly
and take necessary remedial action.
connected at the traction sub-station to the secondary side of a potential transformer to ascertain the
pattern of voltage variation throughout the 24 hours for at least 3 typical days. Based on the readings
sub-station lie just below 27.5 KV but does not touch 27.5 KV. This will ensure that the OHE voltage
is well above the minimum of 19 KV at the farthest point on the system even when heavily loaded.
Once a year a 24 hours record of voltages available on the two sides of every neutral section should be
taken to make sure that the voltage does not fall below 19 KV at any time.
Since any change in the inter-connections of the grid system would have repercussions on the voltage
at the traction sub-station, the SSE/PSI should keep in touch with the supply authorities in regard to
system changes so that he may arrange to take another set of 24 hour voltage readings if any change
has taken place and to change the tap setting if required.
9
Indian Railways - AC Traction Manual - Volume-II Part-I
2. IS- 1866 Code of practice for maintenance and supervision of insulating oil in service.
A summary of tests for various characteristics, the requirements to be complied with and methods of
should be done once a year. However, some of the tests like Breakdown voltage (BDV) test, acidity
tests, crackle test for moisture, may be carried out in PSI depots or sub-stations once in six months
when samples are drawn for condition monitoring as per para 20216 Procedures for these test are
indicated in IS 1866.
dissolved moisture and gases. The most important quality to be preserved is the di-electric strength,
which is affected by the presence of moisture.
The insulating materials used in the winding are hydroscopic by nature and therefore moisture is
absorbed through defective breathers, gaskets and addition of untreated make up oil. It is essential to
remove these impurities by purifying the oil when the di-electric strength goes below the permissible
limits.
may be used. These are normally operated from 240 V single phase supply taken from the 100 kVA
transformers should make themselves familiar with the supplier’s instructions in regard to the operation
and maintenance of the oil purifying equipment.
10
Chapter-2 Sub-Stations and Switching Stations
11
Indian Railways - AC Traction Manual - Volume-II Part-I
down, the second standby transformer may have to be pressed into service for the duration of the
peak load. Such parallel operation of traction transformers may sometimes also incidentally result in
reduction of the total losses thereby effecting economy. Secondly, it will also result in higher OHE
voltage, since traction transformer impedance is now halved as the transformers are identical.
If a sub-station is persistently overloaded and an adjacent sub-station is appreciably underloaded, the
possibility of shifting the neutral section may be considered.
operate causing the relay to trip. Analysis of the composition of gas collected will indicate the nature
of fault. If it is mere air bubbles the transformer is sound. For details of tests manufacturers write up
may be referred to. It is always a wise policy to get the di-electric strength of the oil tests, measure the
insulation resistance and carry out ratio test.
20215 Introduction
1. For better utilization of traction assets, outage of any traction equipment from service should be
minimum without compromising on safety of the equipment and personnel. Monitoring of condition
of the equipment by reliable means is essential for following system of need based maintenance
i.e. directed maintenance. However, till such time reliable condition monitoring techniques are
introduced, the present system of preventive maintenance has to continue.
2. Recommendations of Original Equipment Manufacturer (OEM) and guidelines issued by RDSO,
3. The tightening torque for fasteners of various sizes is given in Annexure 2.08.
20216 Transformers
1. Condition Monitoring
thermo-chemical reaction with participation of heat, moisture and oxygen. This results in formation
of soluble and insoluble products which accumulate and deteriorate the properties of oil and cellulosic
insulation. Whereas the oil can be reconditioned to restore functional properties, no such treatment
is possible for the cellulosic insulation, which suffers from reduction of mechanical and di-electric
strength. The condition of the insulation, therefore, needs to be checked by suitable methods.
The thermal and electrical stresses caused during short circuits, overloads and over voltages in the
system result is gas formation in appreciable amount and deterioration of di-electric properties and
12
Chapter-2 Sub-Stations and Switching Stations
extreme cases.
In the case of incipient faults, the gases being soluble, are absorbed in oil. The Buchholz relay
cannot respond during early stages of trouble and by the time these devices operate the damage is
done. Dissolved gas analysis (DGA) provides an important means in the art of condition monitoring
detection of incipient faults and for monitoring of growing faults which are not always revealed by
established routine tests etc. In order to timely detect the deterioration of insulation, oil sample shall
be drawn annually and subjected to gas chromatography.
Guidelines for condition monitoring of traction transformers by Dissolved Gas Analysis technique are
appended at Annexure 2.04.
2. Overhaul of Transformers
a. Overhauling of Traction Power Transformer can be undertaken either at site (Traction Sub-
TI/MI/0039 Rev.02 (or latest). In addition to this, if transformer overhauling is required at OEM
/Approved manufacturer premises, same to be decided by Sr. DEE/TRD.Before commencing
the work ensure that spare gaskets of proper quality are available. Drain out the oil, disconnect
all leads, remove manhole covers where required. The EHV and 25 KV bushings are then
carefully removed out and stored well protected in a safe place. Then remove the core by
to the windings. Traces of the sludge left over in inaccessible places are best removed by
the old surface contamination should be brushed and washed down, until the clear surface of
the winding is exposed.
e. Care should be taken to protect the windings against ingress of moisture particularly during
inclement weather. Care should also be taken by wiping off body sweat with a towel. The
13
Indian Railways - AC Traction Manual - Volume-II Part-I
windings should also be kept warm by surrounding the open windings by a number of infra-red
lamps or by other means.
f. Fully push home the wedges between the coils and take up the slackness of end-plates by
tightening up the bolts and locking them. These are provided on traction transformers to hold
the windings tightly together to withstand the high mechanical forces generated at the time of
commissioning of a transformer. The coils are also liable to suffer displacement due to short
circuit forces. If the coils are not held tightly in position, it will lead to repeated movement of
the coils as well as layers and turns which will in turn cause abrasion and wear of insulation and
should be taken to have the wedges fully home and tighten up the pressure screws where they
are provided.
g. Finally put back the core assembly inside the tank, assembly the bushing check tightness of
para 20208 to 20210. Experience has shown that tools like spanners and foreign objects like
washers, pieces of cloth, etc. are sometimes inadvertently left behind in the transformers, which
present hazard of short circuits. It is, therefore, important that al tools, etc. used in the overhaul
work should be listed out at the beginning and accounted for at the end of the work.
When overhauled transformers are to commissioned the same procedure as detailed in Chapter IX for
new transformers should be followed.
Each railway should plan, taking into consideration the resources available with them to carry out the
POH and repairs of the transformer and decide the agency to execute the work.
be healthy.
b. Sustained overloads – The windings in one or all phases would show signs of overheating and
charring; the insulation would be very brittle and would have lost all its elasticity.
c. Inter-turn short, inter-layer short, or inter-coils short - The same signs as for indicated for
sustained over load would be noticed, but only on affected coils, the rest of the coils being
intact. This is likely if the differential relay or the Buchholz relay has operated.
of the coils. The coils may be loose on the core, some turns on the outermost layer may have
burst outwards and broken as if under tension. If, in addition to these signs, the windings are
also completely charred, it is conclusive evidence that the short circuit has continued for an
appreciable period, not having been cleared quickly by the protective relays.
e. If the upper chamber of the Buchholz relay alone has tripped, check the insulation of core bolts,
by applying a voltage of 230 V to 1000 V between the core and each bolt. If it fails, renew the
insulating bush. Observe also all the joints, and tap-changer contacts, for over heating and arcing.
14
Chapter-2 Sub-Stations and Switching Stations
f. If the oil shows a low BDV, it does not necessarily mean that it has caused the breakdown.
between the live parts and earth, which will leave corresponding tell-tale marks.
maintenance of circuit breakers and interrupters, in general, are given in the succeeding paragraphs.
conditions as existing in the breaker. A good quality absorbent is used in the apparatus to
remove decomposed gaseous by-product. During the maintenance, record gas pressure and
temperature. Supply the gas if pressure is less than the prescribed value. Check setting of gas
pressure switches.
15
Indian Railways - AC Traction Manual - Volume-II Part-I
b. Interrupting Unit
Clean the surface of the porcelain and other parts. Contacts should be inspected and replaced
if necessary.
Renew the absorbent taking care that exposure of the absorbent to the atmosphere is minimal.
The breaker should be evacuated as soon as possible.
c. Operating Mechanism
Check stroke from closed position to completely opened position and over stroke from
completely opened position to stopped position. Check prescribed clearances. Relubricate
moving parts. Check that pressure gauge is working correctly. Check pneumatic system for
tightness.
The housing should be checked for water penetration and rust. Ensure that fasteners are not
loosened. Check connections of control circuit wires for tightness.
3. Vacuum Circuit Breakers
Maintenance is to be conducted as per the maintenance instruction no. TI/MI/0054 or latest. (RDSO
Letter No. TI/PSI/CVINT/POLICY/Dt.13.09.2017)
1. Traction Sub-Stations –
110 V 200 Ah. Lead acid cells for control, protection and indication circuits.
2. Switching Stations –
110 V or 72 V, 40 Ah. Lead acid batteries for operation of circuit breakers and interruptors and motor
operated isolators.
3. Remote Control Equipment
Batteries of suitable voltage and capacity at remote control centre, traction sub-station and switching
stations.
To reduce number of batteries at TSS/SS the remote control equipment is now being connected to the
battery of TSS/SS.
In all cases, mains operated battery chargers are provided with facilities for either trickle charge or
boost charging. The rating of the battery charger should related to the capacity of the battery.
16
Chapter-2 Sub-Stations and Switching Stations
c. Charging current
d. Cell voltage
e. Condition of the plates and extent of deposits
f. Inter-cell connectors and main battery terminals
A detailed history of every battery should be separately maintained in which all relevant information is
forms.
fuse protection for short circuit in the wiring between the battery and distribution switch board should
be provided.
it drops to 1.150 the cell may be considered discharged. These values vary with the type of battery,
temperature, age and working conditions.
a. For each 1 degree C above 27 degree C add 0.0007 to the observed reading and
b. For 1 degree C below 27 degree C deduct 0.0007 from the observed reading.
unequal rate of evaporation. This should be corrected by adding distilled water. In no circumstances
should concentrated or diluted sulphuric acid be added to any cell except when acid is known to have
spilled out. Distilled water alone should be used for topping up the level.
therefore be taken after allowing all bubbles to subside. Hydrometer of reputed make should only be
used. Hydrometers of 300 mm length are necessary to give required accuracy. Two hydrometer should
always be maintained in a station and they should be periodically checked to see that they read alike.
3. Pilot Cells
One of the cells in each row of the battery set should be selected and kept as the pilot cell. Readings
and serve as a guide to the condition of the other cells. The pilot cell when once selected should not be
changed unless the cell has to undergo special treatment or repairs in which case a note should be made
immediately on record sheets. The height of the electrolyte in the pilot cell should invariably be kept at
4. Trickle Charging
Lead acid batteries are very sensitive to overcharging as well as cover discharging. If over charged,
the positive plates will shed their active material quickly. If kept in discharged condition for long, the
plates will suffer ‘sulphation’ evidenced by appearance of whitish deposits on the plates. Prolonged
17
Indian Railways - AC Traction Manual - Volume-II Part-I
sometimes useful if the sulphation is very light. However, there should be no occasion at all for any
battery set used in stationery traction installations to be sulphated, as they are continuously on trickle
intermittent rates of discharge over a period of 24 hours, so that the battery is always kept in fully
charged condition and never overcharged or over-discharged.
rise slowly from the plate to the surface of the electrolyte in batteries, that are being overcharged the
bubbles are much larger and reach the surface at a higher rate.
5. Cell Voltage
at the end of a full charge will be about 2.5 to 2.75 V when it is receiving charge at the 10 hour rate.
This gradually decreases as the age of the battery increases until it comes down to 2.4 V with normal
temperature and charging rate.
No cell should ever be discharged below the point where the cell voltage reaches 1.85 V as measured
when the cell is discharging at the normal 10 hour rate.
It should be noted that the voltage of a cell gives an approximate indication of its state of charge (or discharge)
only when it is being discharged, say at the 10 hour rate, and not when the cell is an open circuit.
Sulphated plates, lug corrosion, partial short circuit due to cracked separators and other defects of a
voltmeters in use should be periodically checked and recalibrated, if necessary. When not in use they
should be kept in a safe place.
6. Condition of Plates and Deposits
The active material in the positive plates in healthy cells in use for more than 12 months (when fully
charged) should be chocolate in color and negative plates light or bluish grey according to age. The
chief indications of weak cells are badly coloured plates, irregularity in gassing or entire failure to gas
This formation of scale is normal. Until all this scale is dispersed, the plate cannot be considered as
stabilized. Sometimes pieces of this scale may lodge across adjacent negative plates and cause a partial
fall to the bottom of the cell. This scaling occurs only on the edges of the plates. The removal of the
scales should be done very carefully so that the plates are not damaged.
Examine carefully the physical condition of the plates such as cracks, distortions, accumulation of
whitish deposits, etc.
The color of the deposits gives a good indication of the state of health of the cells. Whitish deposit
indicates undercharging leading to discharged condition. In healthy cells, the deposit is brown in
18
Chapter-2 Sub-Stations and Switching Stations
colour but excessive shedding of active material for the positive plates indicates overcharging of the
battery. If this is noticed, reduce the rate of charge immediately. If all the cells in a battery show
whitish deposits immediate action should be taken to give a boost charge at an appropriate rate and
time. Weak cells should be immediately examined for any possible short circuit or metallic contact
between positive and negative plates. The short circuit should be removed and the cell should then be
given special additional charging by cutting it out and putting it back again when a healthy condition
is regained, after it is attended to.
7. Inter-Cell Connectors
The inter-cell connectors of the battery should be examined to ensure that they are clean and tight,
making perfect contact with cell lugs and that no corrosion is taking place. Light viseline should be
applied to prevent corrosion.
Inspection of copper inter-row connectors should also be made for any signs of copper sulphate
corrosion which should be cleaned up. Acid-proof paint or enamel should be applied to all exposed
the maintenance overhauling, testing adjustment and calibration of protective relays as well as
indicating, integrating and recording instruments. Such specialist staff shall hold competency
2. The Central Repair Shop should be fully equipped with necessary apparatus, instruments, tools and
equipment for overhauling, testing and calibration of relays.
3. Each Supervisor responsible for maintenance and testing of protective relays should maintain a
register in which full details regarding each relay should be entered. The details to be recorded are
the type and serial number, PT & CT ratios, range of settings available, characteristic curves (where
applicable), location where installed, schematic diagram of connections, normal settings and details
of Sr. DEE/TRD.
4. No alterations in the settings of protective relays should be carried out without the written
authorization of Sr. DEE/TRD, who will submit proposals including detailed calculations for
changes required, if any, for prior approval of PCEE. Guidelines for setting of relays are given in
the Appendix V.
5. The procedure for commissioning of protective relays has been given in Chapter IX.
6. The normal maintenance attention required for relays in service is generally as under:
These tests should be carried out by atleast at the level of ADEE once in a year for all relays.
Simultaneously visual checks on relay connections, condition of the trip battery, trip and alarm
circuits, and also the dust-tightness of protective covers should be made. The relay cover
should then be sealed. A record should be maintained showing the date and time this is done.
On each occasion when the seal is broken subsequently the reasons should be recorded in the
log book.
19
Indian Railways - AC Traction Manual - Volume-II Part-I
c. Distance protection relay may be tested for calibration once in a year with primary injection set.
d. Secondary injection test - These should be done annually preferably before onset of busy
season, making use of portable testing equipment and at the settings approved by the competent
authority. Apart from testing the operation at the normal setting tests should also be carried out
at other settings to make sure that the relay has the required characteristic.
e. Overhaul bench tests and calibration: These are necessary once in ten years of when a relay is
not found functioning correctly. This work should invariably be carried out only in the Central
Repair Shop by highly skilled technicians fully conversant with all details of construction and
adjustment.
if any and measurement of coil resistance and other datain case of electro mechanical relays.
Transport of the relays to and from the Central Repair Shop also requires utmost care including
locking of the moving parts and careful packing and handling. When laboratory tests are fully
satisfactory, the relays should be sealed and date of overhaul painted on the outer cover of the
relay.
However, if numerical relays are provided, periodic calibrations should be done with the help of
suitable Relay Test Kit. It shall also be ensured the healthiness of the cable/wiring and tightness
of the connection of wires terminal with the TBs after testing.
Note : Existing relays are numerical relays and has no moving part if numerical relays are used
then measurement of coli resistance and other data in relay shall not be required.
of these from the electrical point of view to the SSE(P. Way) so that they in turn may warn their
their periodical inspection, make it a point to inspect the return feeder rail connections and ensure that
they are in excellent condition.
IV MAINTENANCE SCHEDULES
should be independent of other tasks. They will not be of routine nature but shall be carried out in
depth to identify:
20
Chapter-2 Sub-Stations and Switching Stations
installations in their jurisdiction within the stipulated periods and stagger the inspections among
themselves to avoid over inspections of the some installations repeatedly in a very short time and
neglect of other installations. A check list in brief for various inspections is given in the Annexure
2.02.
3. The items of attention listed hereunder at any particular periodicity are over and above those
mentioned in the previous schedule. This should be kept in view while carrying out maintenance
work.
20224 General
1. No work of any kind shall be commenced on or in the vicinity of live equipment unless power
supply to the particular part has been switched off and all other prescribed safety measures taken.
2. To guard against the possibility of unauthorised interference and pilferage from unattended sub-
stations and switching station, all electrical department staff shall be vigilant and watch for any
such activity when they are in the vicinity. Surprise checks coupled with periodical inspections
will also act as deterrents.
3. The TPC shall once a day check up communication to each of the grid sub-stations and obtain the
register. Whenever inspecting staff visit the sub-station or switching stations, they shall contact the
TPC on the telephone.
FORTNIGHTLY MAINTENANCE
20225 General Inspection by a PSI Supervisor
1. Go round the whole area of the sub-station ; inspect for general cleanliness, proper drainage, road
outer periphery; cut any tree branches likely to come in the vicinity of live lines.
serviceable.
4. Inspect structure and plant foundations for any sinking or cracking. Go round the structural work
for checking tightness of various bolts and nuts.
21
Indian Railways - AC Traction Manual - Volume-II Part-I
20226 Battery
1. Check all cells generally in accordance with para 20220.
top up with distilled water exactly to the correct level for every cell.
3. Check operation of battery charger and note charging rate in register.
MONTHLY MAINTENANCE
20227 Bonding And Earthing
Visually inspect all earth connections and see that they are in order and that every equipment has
duplicate earths. Tighten connecting bolts and nuts as necessary. Where the sub-station and feeding
post are close by ensure that sub-station structures are properly bonded with the feeding post and the
track by two independent connections.
20229 Insulators
which are badly chipped should be replaced. Minor chippings can be rendered impervious to moisture
by a light coating of Araldite or similar epoxy resin.
moisture. If changing color due to moisture, replace it with dry gel and recondition the old silica
gel. If the (silica-gel is too wet, check di-electric strength of transformer oil. (RDSO SPEC No.
ETI/SI/118(10/93) A&C Slip No. 10 August 2012
5. Check for gas collection, if any, in Buchholz relay.
6. Check for oil leakage on transformer body, conservator tank, oil drain valve and foundations. If
leaking, take corrective action by tightening the bolts; replace gaskets, if necessary.
7. Check if heater in the marshalling box is functioning properly, and if all terminal connections are
in order.
22
Chapter-2 Sub-Stations and Switching Stations
repaint the rusted parts. Check in particular if the weather-proof gaskets are in good condition;
if not, replace them to make the control box water-tight and dust-tight. Examine if the leading in
pipe connections are properly bushed, sealed and water-tight. Check if all pins and checknuts are
in place. Check also tie-rod nuts for tightness.
2. Operate the mechanism at least twice manually. Have it operated on remote control from RCC; keeping
the control door open, observe whether the mechanism functions smoothly without any rubbing or
obstruction, and also if the shock absorber functions properly when circuit breaker is tripped.
3. Examine the commutator of the motor and clean with muslin cloth. Examine carbon brushes and
replace if necessary.
4. Check breather and breather holes for clogging.
5. Check gear-oil level in the mechanism and replenish it, if required.
6. Check if heater is functioning properly.
7. Check interlocks of the equipment and associated isolators.
8. Check local position indicator and remote semaphore indicator for operation. Observe for the
correct operation of recording counter.
After complete checking, close the cover and test the breaker for operation under remote, local and
manual control. In addition to this, for 25kV Vacuum Circuit Breaker and Interrupter, Maintenance
is to be conducted as per the maintenance instruction no. TI/MI/0054 or latest.
(RDSO Policy Letter No. TI/PSI/CV INT/POLICY/17 Dt. 13.09.2017)
20232 Isolators
1. Manually operate isolator several times and observe if it operates smoothly and correctly. Check
interlocks and integral lock, lubricate moving parts as necessary with appropriate lubricant.
2. If isolator is motor-operated, check commutator of motor and clean with dry mull cloth, and check
carbon brushes for proper bedding and wear. Check if motor is working smoothly, clean limit-
switch and auxiliary switch contacts and check tightness of wiring connections. Examine contactor
box and signal box; clean thoroughly and lubricate all gears, shafts, bearings contact etc.
2. Check if all indicating and recording instruments are working normally and the pointers are not
sticky.
3. Note and record in the Register the ranges of voltage and current variations during a 15 minute
period at the time of the day when inspection was carried out. Abnormal voltage or current should
be noted for corrective action.
4. Clean the panels externally.
23
Indian Railways - AC Traction Manual - Volume-II Part-I
QUARTERLY MAINTENANCE
2. If the battery is not in a fully charged condition, boost charger should be given as required and
trickle charging rate increased to the extent required. This should only be done by a supervisory
3. Make a general examination of battery charger. Check earth connection to the body.
20239 General
network has occurred during the past six months or are expected shortly.
20241 Isolators
1. Observe for any signs of overheating and check the wipe of contact blades. Clean blade tips and
blades are fully horn between the contacts when handle is in closed position.
24
Chapter-2 Sub-Stations and Switching Stations
YEARLY MAINTENANCE
20243 General.
1. Inspect the fence all-round the sub-station and bonding between metal fencing panels and to earth.
Put a drop of oil in the hinges of all doors. Repaint any of the structural parts as necessary.
2. Open all the trench cover and clean them completely. Clean all culverts and remove cobwebs;
check possibility of lizards or other insects gaining entry into enclosed control equipment, and
make them insect-proof.
3. Arrange for painting of walls and metal-works as necessary.
4. Check all explosion vent diaphragms for any damage.
5. Check rod gap setting.
20247 Isolators
Vaseline.
25
Indian Railways - AC Traction Manual - Volume-II Part-I
2. Measure clearance of blade in open position and record and adjust crank mechanism, if found
necessary.
3. Check the adjustable stop set-screws for proper condition and correct positioning.
4. If the isolator is motor-operated, measure and record insulation resistance of motor windings and
contactor coils using a 500 V megger.
26
Chapter-2 Sub-Stations and Switching Stations
Annexure 2.01
(Para 20202, 20223)
Notes:
1. These inspections are the minimum quantum per month
2. * In respect of Supervisory staff, the inspections pertain to their respective jurisdiction
3. Check lists of items to be broadly covered are indicated at Annexure 2.02. The maintenance
schedules prescribed should also be kept in view.
27
Indian Railways - AC Traction Manual - Volume-II Part-I
Annexure 2.02
(Para 20223)
a. OHE/PSI Depots
Check
i. Staff grievance register
ii. Quarter Register.
iii. Attendance register
iv. Cleanliness of depot
v. Upkeep of stores.
vi. Stock position in Stores
vii. Compliance of audit & account inspection notes.
viii. Test & Trial report
Check
i. Attendance register.
ii. Compliance of audit & account inspection notes.
2. Check up if there is any equipment under breakdown which is likely to increase risk of interruption
in power supply to traction.
3. Note down meter readings and scrutinize and record important data regarding power supply
parameters including daily MD, variation in voltage, frequency and power factor.
28
Chapter-2 Sub-Stations and Switching Stations
29
Indian Railways - AC Traction Manual - Volume-II Part-I
30
Chapter-2 Sub-Stations and Switching Stations
f. Earthing
Check
i. Soundness of earth connection to each electrical equipment & structures.
ii. Last recorded earth resistance readings.
g General
Check
31
Indian Railways - AC Traction Manual - Volume-II Part-I
Annexure 2.03 A
(Para 20207)
32
Chapter-2 Sub-Stations and Switching Stations
Annexure 2.03 B
(Para 20207)
33
Indian Railways - AC Traction Manual - Volume-II Part-I
Annexure 2.04
(Para 20216)
1.0 Introduction
1.1 Dissolved gas analysis (DGA) is a powerful diagnostic technique for monitoring the internal
condition of transformer as it is capable of detecting faults in the incipient stage, before they develop
into major faults and results in the outage of the transformer. The conventional Buchholz Relay is
universally used in transformers to protect against severe damages. However, its limitation is that
gas surge to operate this relay. Moreover, Buchholz Relay is never meant to be a diagnostic device
for preventive maintenance of transformers.
1.2 The DGA technique is very sensitive as it detect gas in parts per million (ppm) of the oil by use
of the GAS Chromatograph. It is possible to check whether a transformer under service is being
subjected to a normal aging and heating or whether there are incipient defects such as Hot Spots,
Arcing, Overheating or Partial discharges. Such incipient faults otherwise remain undetected until
they develop into a major failure.
of the thermal and electrical stresses to produce hydro-carbon gases, hydrogen and carbon oxides.
to a greater extent as a result of faults. The accumulation of gases in transformer oil may be sudden
due to a severe arcing fault or more gradual as in the case of slow deterioration of insulation. The
34
Chapter-2 Sub-Stations and Switching Stations
paper. Oil degradation produces a number of hydro carbon gases such as methane, ethane, ethylene,
and acetylene. Methane and ethane are decomposition products that appear above 120 degree C
ethylene appears above 150 degree C while acetylene is a high temperature product, appearing at
several hundred degrees centigrade. Some hydrogen is also produced along with the hydro carbons
gases. The proportion of the various hydrocarbons varies with temperature. This is the basis of the
well known Ratio code introduced several years ago by Dorenberg and R.R. Rogers.
3.2 Partial Discharge
The second type of fault condition is partial discharge which occurs due to ionization of oil in highly
The main product during particle discharge is hydrogen, though small amounts of methane and
other gases would also be present depending upon thermal degradation. The disintegration of oil
and cellulose due to particle discharge is characterized by the removal of the outer hydrogen atoms
to form hydrogen gas. The remaining molecular framework polymerizes and long chain products
such as waxes are formed. Thermal degradation is a more predictable phenomenon which involves
the break up of chemical bonds. Cellulose decomposes ultimately to CO, CO2 and water; oil break
up into lower molecular hydro-carbons.
3.3 Arcing
The third type of fault condition is arcing. Arcing can occur between leads, between lead and coil
and between other highly stressed regions weakened by fault conditions. The high temperature
caused by arcing results in the production of acetylene and hydrogen.
3.4 Pattern of generation of gases in transformer is summarized below:
FAULT/PATTERN KEY GAS
Conductor Overheating CO/CO2 (carbon oxides)
Oil overheating C2 H4 (Ethylene)
Particle discharge H2(Hydrogen)
Arcing C2H2 (Acetylene)
35
Indian Railways - AC Traction Manual - Volume-II Part-I
oils helps in interpretation of gas analysis. The permissible concentration of dissolved gases in the
oil of healthy transformer is shown in table II. The combinations of Gas levels for different types
of faults are shown in Table III while table IV shows the gas composition by volume under arcing
fault with participation of various components of solid dielectrics in a transformer.
5.3 While the absolute concentration of fault gases gives an indication of status of insulation of
transformer, whereas the relative concentration of these gases provides a clue to the type of fault.
For fault diagnosis the method based on Roger’s Analysis is adopted.
5.4 Rodger’s method:
This method hold good for hydro carbon gasses by evaluating the gas ratios, the type of fault
is detected. Four ratios are used viz. Methane/Hydrogen, Ethane/Methane, Ethylene/Ethane and
Acetylene/Ethylene. The value of ratios can be greater or smaller than unity. The ratio and type of
fault represented by that ratio are given in Table V.
36
Chapter-2 Sub-Stations and Switching Stations
TABLE I
SOLUBILITY OF DIFFERENT GASES IN TRANSFORMER OIL AT 25 DEGREE C 1 atm
Gas Volume %
With reference to volume of oil
Hydrogen 7
Oxygen 16
Nitrogen 8.6
Argon 15
Carbon Monoxide 9
Carbon dioxide 120
Methane 30
Ethane 280
Ethylene 280
Acetylene 400
Propylene 400
Propane 1900
Butane 4000
TABLE II
RANGE OF GAS LEVELS
(All concentrations are in PPM)
Gas 0-4 years 4-10 years 10 years.
Methane 10-30 30-80 30-130
Ethane 10-30 30-50 30-110
Ethylene 10-30 30-50 50-150
Acetylene 10-16 10-30 10-40
Hydrogen 20-150 150-300 200-500
Carbon Monoxide 200-300 300-500 500-700
Carbon Dioxide 3000-4000 4000-5000 4000-10,000
Table III
Gas levels for different fault conditions
(All concentrations are in ppm)
Fault gases Hydrogen Methane Ethane Ethylene Acetylene Carbon Dioxide
H2 CH4 C2H6 C2 H4 C2H2 CO2
Arcing 500-1000 20-130 10-30 10-30 40-100 3000-4000
Partial discharge 500-1000 20-130 10-30 10-30 10-15 3000-4000
Hot spot 20-150 10-30 10-30 150-200 10-15 3000-4000
Gradual 20-150 10-30 150-200 10-30 10-30 3000-4000
Overheating
37
Indian Railways - AC Traction Manual - Volume-II Part-I
Table- IV
Gas composition by volume (%) with reference to volume of oil due to arcing faults
Oil only 60 0.1 0.1 3.3 0.05 2.1 2.1 2.4 6.3
Oil/Kraft paper 52 14 0.2 3.8 0.05 8 12 3 6.7
Oil/ Press board 48 27 0.4 5 - 5 6 2 6.2
laminate
Oil, Alkyl paint 55 20 0.2 4 - 5 8 2.4 7
Oil/ Polyure 60 1 0.1 9 - 11 10 2 6
thane enamel
Oil/ PVA 61 5 0.1 6.0 - 14 5 2.5 6.5
enamel
Oil/ Epoxy 57 2 0.1 14 - 10 8 2.5 6.5
glass clothes
Oil/ 55 11 4 8 - 8 5 - -
Isophthalate
cotton tape
Table V
Roger’s method of diagnosis by Hydro-carbon gas ratios
CH4 - Methane
C2H6 - Ethane
C2H4 - Ethylene
C2H2 - Acetylene
H2 - Hydrogen
38
Chapter-2 Sub-Stations and Switching Stations
ANNEXURE 2.05
(Para 20218)
kgf/cm2 gm/lit.
At 0 : 6.25
At 1 : 12.3
At 5 : 38.2
At 10 : 75.6
At 15 : 119.0
39
Indian Railways - AC Traction Manual - Volume-II Part-I
Annexure 2.06
(Para 20223)
1.1 Schedules
The maintenance and check execution standard depends upon the working conditions of the CB. The
checks to be carried out, their frequency and scope are broadly as under:
Type of check Frequency Scope
Patrol Inspection Every Week The patrol inspection is an external check of the
Circuit breaker in live condition for irregularities.
Ordinary Inspection After every 1000 The ordinary inspection is inspection performed
operation by turning off the circuit breaker for a relatively short
time for simple inspection and servicing with emphasis
on functional checks e.g. visual check of irregularities and
cleaning of dust and dirt.
Detailed Inspection After every The detailed inspection is an inspection performed by turning
3000operation off the circuit breaker for a relatively long time to dismantle
and inspect the mechanism for irregularities for the purpose of
continuously maintaining the performance
Incidental Inspection - - The incidental inspection is performed when inspection and
repair are necessary due to the detection of an irregularity
during patrol inspection or during operation.
1.2 General
Attention should be paid to the following points during ordinary and detailed inspection.
a. Switch off control/compressor motor supply. Discharge all the air in the air receiver through the
drain valve.
instructions. At the open position of the breaker the safety pins for preventing closing and opening
must be inserted. On completion of the inspection, the safety pins must be removed.
c. Good quality grease should be used adequately.
d. Circlips and split pins which are removed must be replaced with new ones.
e. Remove”O” rings must be replaced with new ones. While handling and placing “O” rings in their
grooves care should be taken to avoid dust falling on them.
40
Chapter-2 Sub-Stations and Switching Stations
9. Renewal of absorbent x
10. Measurement of resistance of interrupting x
units
Gas system 11. Record of gas pressure and temperature x x x
12. Check the valve B is open and valve A is x x
closed
13. Supply the gas, if the pressure less than x x x
prescribed value
14. Check the setting of gas pressure switch x x
41
Indian Railways - AC Traction Manual - Volume-II Part-I
42
Chapter-2 Sub-Stations and Switching Stations
Annexure 2.07
(Para 20223)
1.0 General
The maintenance and check execution standard depends upon the working conditions of VCB, such
as the environmental condition, current switching frequency and others. Preventive maintenance is to
be conducted as per the maintenance instruction no. TI/MI/0054 or latest.The checks to be carried out,
their frequency and scope are broadly as under:
Type of check Frequency Scope
Patrol check Daily Check VCB under daily operating
condition.
Ordinary check Once every 3 years or once every 1000 Check VCB after disconnection main
switching times supply and local Remote switch in
LOCAL position.
Detailed check Every 6 years “
Provisional check When a trouble occurs “
For the minimum number of operation without replacement of vacuum bottle para 1.5 below may be
referred.
2. Temperature Main circuit terminals and electrode pole Check if the operating voltage and
assembly control voltage are kept at the respective
43
Indian Railways - AC Traction Manual - Volume-II Part-I
44
Chapter-2 Sub-Stations and Switching Stations
*****
45
CHAPTER-3
OVERHEAD EQUIPMENT
20300 Introduction
Section I
Section II
Section III
Section IV
Section V
I ORGANISATION
47
Indian Railways - AC Traction Manual - Volume-II Part-I
proper condition.
48
Chapter-3 Overhead Equipment
condition
Assistant
20304 Introduction
49
Indian Railways - AC Traction Manual - Volume-II Part-I
provided.
Indian Railways - AC Traction Manual - Volume-II Part-I
train operation.
Indian Railways - AC Traction Manual - Volume-II Part-I
61
Indian Railways - AC Traction Manual - Volume-II Part-I
is restored.
62
Chapter-3 Overhead Equipment
Indian Railways - AC Traction Manual - Volume-II Part-I
64
Chapter-3 Overhead Equipment
hex pipe
X-Y dimensions
66
Chapter-3 Overhead Equipment
67
Indian Railways - AC Traction Manual - Volume-II Part-I
68
Chapter-3 Overhead Equipment
69
Indian Railways - AC Traction Manual - Volume-II Part-I
position.
20321 General
71
Indian Railways - AC Traction Manual - Volume-II Part-I
72
Chapter-3 Overhead Equipment
74
Chapter-3 Overhead Equipment
noticed.
4. Droppers:
5. Turn outs
76
Chapter-3 Overhead Equipment
7. Isolators:
a. Overlaps:
77
Indian Railways - AC Traction Manual - Volume-II Part-I
attended to.
15. Masts:
78
Chapter-3 Overhead Equipment
18. PG clamps:
1.
2.
4.
79
Indian Railways - AC Traction Manual - Volume-II Part-I
81
Indian Railways - AC Traction Manual - Volume-II Part-I
82
Chapter-3 Overhead Equipment
Indian Railways - AC Traction Manual - Volume-II Part-I
in each depot.
84
Chapter-3 Overhead Equipment
86
Chapter-3 Overhead Equipment
20343 Other Important Precautions to be taken while Carrying out Works on OHE
20346 Deleted
20347 Isolators
87
Indian Railways - AC Traction Manual - Volume-II Part-I
Precautions
88
Chapter-3 Overhead Equipment
89
Indian Railways - AC Traction Manual - Volume-II Part-I
Annexure 3.01
1. 1 1 2 2 2 2
2. 1 2 4 4 6
Car
section in section in
4. 1 2 4 4
1 1 2 4 4 4
6. 1 1 2 2 2
7. 1 1 1 1
Chapter-3 Overhead Equipment
Annexure 3.02
2.0 Station
91
Indian Railways - AC Traction Manual - Volume-II Part-I
92
Chapter-3 Overhead Equipment
Indian Railways - AC Traction Manual - Volume-II Part-I
Annexure 3.03
1.
2.
4.
1.
2.
4.
6.
1.
2.
1.
2.
4.
94
Chapter-3 Overhead Equipment
1.
2.
1.
2.
4.
1.
2.
1.
2.
4.
1.
2.
1.
2.
Indian Railways - AC Traction Manual - Volume-II Part-I
1.
2.
4.
6.
7.
8.
9.
11.
12.
96
Chapter-3 Overhead Equipment
Annexure 3.04
PROFORMA 03-1
6.4
97
Indian Railways - AC Traction Manual - Volume-II Part-I
PROFORMA 03-2
Section______________________
attended
proposed
PROFORMA 03-3
Con
ca ance dition
9T
tion can per
done
tion visor
vers
98
Chapter-3 Overhead Equipment
PROFORMA 03-4
no. provision
strands
hard spot
PROFORMA 03-5
Contact
no..
at ends
and
99
Indian Railways - AC Traction Manual - Volume-II Part-I
PROFORMA 03-6
PROFORMA 03-7
Corrective
action corrective
action
Chapter-3 Overhead Equipment
PROFORMA 03-8
no. distance
To To
per
PROFORMA 03-9
PROFORMA 03-10
Regulating Equipment
Tension
oC
oC done
Contact
one
1 2 4 6 7 8 9 11 12 14 16 17 18 19
PROFORMA 03-11
Isolator Switches
Condition
section
connected
1 2 4 6 7 8
Chapter-3 Overhead Equipment
Performa 03-12
1
crossover(Givethe
7
8
11
12
14
Indian Railways - AC Traction Manual - Volume-II Part-I
16
17
18
19
21
22
24
(Proforma 03-14)
Condition
Contact
road
1 2 4 6 7 8 9
*****
CHAPTER-4
REMOTE CONTROL EQUIPMENT
I. GENERAL
20400 Introduction
20401 General
105
Indian Railways - AC Traction Manual - Volume-II Part-I
106
Chapter-4 Remote Control Equipment
RTU Diagnostics
RCC Diagnostics
Input:
Indian Railways - AC Traction Manual - Volume-II Part-I
Output:
Battery:
110
Chapter-4 Remote Control Equipment
111
CHAPTER-5
OPERATION OF TRACTION POWER CONTROL
113
Indian Railways - AC Traction Manual - Volume-II Part-I
20513……………..deleted
Chapter-5 Operation Of Traction Power Control
115
Indian Railways - AC Traction Manual - Volume-II Part-I
117
Indian Railways - AC Traction Manual - Volume-II Part-I
118
Chapter-5 Operation Of Traction Power Control
119
Indian Railways - AC Traction Manual - Volume-II Part-I
*****
CHAPTER-6
POWER BLOCKS AND PERMITS-TO-WORK
asked to do so by TPC by a clear message supported by a private number or after receipt of a separate
permit-to-work for the section which includes the elementary sections on either the isolator switch.
TPC shall ensure that the sub-sector is dead before he orders opening of an Isolator switch in it.
5. Isolator switches, however, can be closed by a duly authorised person even if the adjacent lnterruptors
are closed (i.e. on load) provided the closure is made swiftly in one motion. It is imperative that once
diesel locomotive hauled. This will be required whenever heavy repair have to be carried out. A
vehicles or EMUs only i.e., a section where 25 kV electric supply to the OHE is switched off and
the section made dead. Power block will be required whenever light repairs to or maintenance of
123
Indian Railways - AC Traction Manual - Volume-II Part-I
block is granted by TPC, movement of vehicles hauled by other than electric power, i.e., steam or
diesel may be permitted, provided a caution order is issued as per General and Subsidiary Rules
drawing the attention of the Driver to the fact that the OHE staff are working at the kilometerage
2. In all cases of power block TPC shall put red warning caps on control switches corresponding to
on all manually operated switches opened locally for isolating the section. This shall be done by
the operator who opens the switches. These red warning caps and warning boards can be removed
only when cancelling the power block. In case SCADA system is in operation instructions issued
for the operation of the system shall be followed.
supply is considered necessary by TPC or the Section Controller, in the interest of safety.
are mentioned in para 20604 or of tracks, masts/ structures or pantographs of locomotives as may
adversely affect safety of trains movements, to the TPC either directly or through any Station Master,
Section Controller or through the nearest available telephone. If the damage is heavy or the moving
dimensions are infringed he should take steps to protect the lines in accordance with General and
Subsidiary Rules.
essential information such as his name, designation, kilometerage where the abnormality has been
124
Chapter-6 Power Blocks And Permits-To-Work
noticed, its nature and place from where he is reporting. He should leave the place only with the
permission of the TPC.
correct method of identifying and describing any section of the OHE where shutdown is required.
section, showing all relevant particulars such as station names, position of all isolators, interruptors,
circuit breakers, “up” and “down” tracks, cross-over section insulators, sectors, sub-sectors and
elementary section numbers.
Sectors: These are described by referring to a section of OHE of a track which can be energized by
closing a feeder circuit breaker at the substation/ feeding post. It covers the section between sub-
station/feeding post and adjacent neutral sections.
Sub-sectors: These are described by the names of two limiting switching stations in the order in which
the train moves and adding the name of the track, e.g., Sub-sector Kendposi-Tabu Dn.
Elementary Sections:
in the direction of power supply i.e., from the feeding post/substation towards the neutral section or
digits represent the interrupter controlling feed to the section and the last two digits the serial number
of the elementary section. Up line elementary sections have progressively odd numbers and Down line
elementary section from the feeding post/sub-station on the down line, fed by interrupter 02.
125
Indian Railways - AC Traction Manual - Volume-II Part-I
permit-to- work form is an important document and should be carefully preserved for a period of
one year unless required for a longer period in connection with an inquiry or investigation.
the telephone.
it. Each message shall be recorded by the sender as well as by the receiver in message books
maintained for the purpose.
6. To avoid confusion, use words “Open” and “Close” shall be used instead of phonetically similar
(e.g.,1 (one) 4 (four) and not fourteen), B for Bombay, C for Calcutta and so on.
work in the danger zone of traction equipment, or who require OHE and or bonding staff to be present
from TPC.
to be attended in the traction sub-station, the permit to work should be obtained by the supervisor
incharge from the TPC and after completing the work, the permit to work should be returned by the
Supervisor incharge to the TPC. Similarly at the switching stations normally the alternative feed is
126
Chapter-6 Power Blocks And Permits-To-Work
available to the concerned sub-sector and therefore, does not necessitate the power block but only a
permit to work should be obtained from the TPC and after completion of the work, the same should
be rerturned to the TPC. In case of attending to the gantry of a switching station, complete block of
the switching station is required for which power block has to be taken from the TPC.
1. On the scheduled day about two hours before the block period, i.e., at about 8.00 hours, TPC will
10-00 hrs.
2. The TPC will pass on information to the JE of the maintenance gang that the power block, as
already arranged, will be available in time.
3. The maintenance gang should arrange to leave the depot in time with all materials and tools so as
to be ready at site at about 9.30 hrs. The OHE staff (in charge of the work) on arrival at site should
immediately contact the TPC and inform him of their arrival.
Any person detailed to open an isolator switch for switching off power supply shall also report to
TPC of his arrival at site at the required location.
The maintenance gang should carry at least two portable telephone sets and the necessary earthing
pole assembly along with them while proceeding to do maintenance work on the OHE.
4. The TPC should maintain continuous contact with the OHE staff at site.
Station Master on duty at all stations concerned to arrange for “longitudinal” and “cross” protection
7. The Section Controller on receipt of assurances from the concerned Station Masters will advise
TPC that the power block may be given.
8. If the power block message is given by TPC in the prescribed printed form the Section Controller
will sign the same and send it to the TPC; if it is given over the telephone, the Section Controller
9. On receipt of the above message TPC will open the interruptors concerned and issue messages
that the isolators have been opened, TPC will close the interruptors restoring power supply to
issue a permit-to-work message in the prescribed form to the authorized person in charge of the
maintenance gang.
the nominated staff to discharge and earth the OHE at two or more points.
11. The maintenance gang will start the work after taking necessary safety precautions to protect
Note: On sections with automatic signalling, the signals may be at danger due to earthing of OHE with the
rails during the period of the power block. The Station Master shall issue necessary authority as per rules for
steam, and diesel trains when these are permitted to be moved over the section under power block.
127
Indian Railways - AC Traction Manual - Volume-II Part-I
permit- to-work was issued, has been completed, the men and materials have been withdrawn from the
person.
work getting an acknowledgment on the other copy. A duplicate copy of every permit-to-work card
3. On completion of the work and when all men and materials have been withdrawn from the electric
equipment and its vicinity, the person in-charge of the working party shall cancel his permit-to-
if possible. Before this is done the authorized person should satisfy himself that no other party has been
given a permit-to-work for the same section.
elementary section, the permit -to-work shall be issued by the TPC only to one authorized person
permit-to-work. Other party or parties may work on the same portion of electrical equipment only
with the permission of this authorized person. The authorized person shall cancel the permit-to-
to work in the section covered by the permit-to-work have withdrawn their men and materials and
have removed the earths from the electrical equipment on which they had worked. In the event of
telephone communication being interrupted, the person responsible shall take action as provided in
para 20615 above for cancellation of the power block.
128
Chapter-6 Power Blocks And Permits-To-Work
period shall take the permit-to-work and then permit the other party to start his work by a message
permit-to-work of completion of work and removal of earths and withdrawal of men and material
permit-to-work must be received for cancellation from the person in-charge of the work by the SSE,
JE or JE (RS) before the switches are closed.
1. The Station Master, Cabin Assistant Station Master, and others responsible for the movement of
section, have a thorough understanding of the precautions to be taken to ensure safety of staff working
on the OHE under power blocks. The reasons for the precautions and the nature of the precautions are
therefore given at some length in the following para graphs.
The protective measures are -
1. Longitudinal Protection: To stop movement of electric rolling-stock running on the same track on
which a section has been made dead and power block has been granted.
2. Transverse or Cross Protection: To stop movement of electric rolling-stock running into a section,
which has been made dead, from another track or from a siding through cross-overs.
129
Indian Railways - AC Traction Manual - Volume-II Part-I
is normally in closed position, it connects the two OHE together and, therefore, they are both
energized at the same voltage
destructive arcing resulting in severe damage to the pantograph and the contact wire.
3. To avert such disastrous effects, under no circumstances should electric rolling-stock be admitted
into the insulated overlap separating the dead section on which a power block has been taken from
live sections.
130
Chapter-6 Power Blocks And Permits-To-Work
rolling- stock be passed below an insulated overlap span or a section insulator which separates a
dead section on which a power block has been granted, from the live section.
of power block. The Station Master, Yard Master and Cabin Assistant Station Master concerned
will continue to maintain protection till the power block is cancelled by the Section Controller.
2. The Section Controller will in turn permit removal of protection only after the power block is
cancelled by TPC.
It is the duty of every Station Master, Yard Master and Assistant Yard Master to be thoroughly
measures prescribed.
4. Every Station Master/Yard Master/Asstt. Station master shall be trained for the purpose and be
fully conversant with all the local switches/isolators/cross-overs and special instructions applicable
2. If the points and signals are locally operated, they should be locked and the keys controlling the
lever frames are controlled electrically by a Station Master or a Cabin Assistant Station Master, the
Station Master or Cabin Assistant on duty shall place the warning collars on the relevant slides of
131
Indian Railways - AC Traction Manual - Volume-II Part-I
This action must be taken by the Cabin Assistant may be, in respect of each and every movement
signals should have “red warning collars” placed on them to give protection to the dead section.
However, If It Is essential to carry out a shunting operation with an electric locomotive situated
3. Train or shunting movements by other than electric locomotives, I.e., by steam or diesel locos,
may be permitted to enter the dead section, provided that the Station Master ensures by personal
inspection that the Train formation does not include an electric locomotives or OHE Inspection Car
or EMU with pantograph raised. The 11 red warning collars” may be permitted to be removed to
allow such movements.
2. Steam or diesel engine or trains hauled by such engines shall be brought to a stand at the station
preceding the station/section at which power block is granted and the Station Master or this station
shall satisfy himself by personal inspection that there is no electric locomotive in the train in
question.
132
Chapter-6 Power Blocks And Permits-To-Work
3. He shall also give a Caution Order to the Driver of such engine or train warning him of the power
block ahead and instructing him to watch for hand signals and observe them.
of the preceding station that there is no electric locomotive or Inspection Car with pantograph
raised in the train.
and this para, it shall be replaced back on the signal control lever immediately after the movement
is completed.
For purposes of the above rule the term “Electric Rolling -Stock” does not include electric rolling-
locked down.
133
Indian Railways - AC Traction Manual - Volume-II Part-I
in adjacent rooms, the messages will be made out in duplicate and sent to the other party obtaining
Form ETR.3 This has 4 parts and is used when an authorized person who has taken a power block has
to issue a “permit-to-work”. Messages in this form will invariable be made out in duplicate and sent to
the other party obtaining acknowledgment on the carbon copy.
Form ETR. 4 This has 3 parts and is used when local blocks are to be arranged. Messages in this form
also should invariably be written out and sent to the other party obtaining acknowledgment on the
carbon copy.
Form ETR. 1
Part A.
RAILWAY
POWER BLOCK MESSAGE FOR BLOCKING OF LINES FOR ELECTRIC TRACTION
PURPOSES
Date .......................................
Time Hr ............. Mts ............
From, To,
Traction Power Controller Section controller
State below which line/s and between which limits (Sector, Sub-sector, Elementary Section, etc.) the
block is required.
..............................................................
..............................................................
The block is likely to last for ... Hr. Mts ...
Sent by .........................
Received by ..................
134
Chapter-6 Power Blocks And Permits-To-Work
Form ETR. 1
Part B
................... RAILWAY
Line/s Duration
Sent by ..............................
Received by ...........................
135
Indian Railways - AC Traction Manual - Volume-II Part-I
Form ETR-1
Part-C
........... RAILWAY
The following line/s have been made alive and the block imposed on these line/s may be cancelled:-
Sent by ..............................
Received by ...........................
136
Chapter-6 Power Blocks And Permits-To-Work
Form ETR-2
Part-A.
................... RAILWAY
SHUT DOWN NOTICE ON TRACTION OVERHEAD OR OTHER ELECTRICAL
EQUIPMENT
I hereby declare that the following electrical equipment/s has/ have been isolated. The equipment
shall be earthed according to standing instructions before commencing any work or prior to issue of
Permit-to-work :-
.............................................. ..............................................
................ ............................. ..............................................
.............................................. ..............................................
Sent by ........................................
Received by ..................................
137
Indian Railways - AC Traction Manual - Volume-II Part-I
Form ETR-2
Part-B.
................... RAILWAY
The following permit to work have been issued on the authority and I am responsible for the permit to
work:-
(1)....................................(2).............................................(3)......................................
Sent by .............................................
Received by ...........................................
138
Chapter-6 Power Blocks And Permits-To-Work
Form ETR-2
Part-C
................... RAILWAY
Time Hr................Mts..................
From, ............................. To,
......................................... Traction Power Controller
at ....................................... at....................................
I hereby declare that the work on or near electrical equipment/s which has/have been isolated has been
completed. All men and materials have been withdrawn and the men have been warned that it is no
longer safe to work on or adjacent to electrical equipments. All Permits-to-work issued by me have
been withdrawn and cancelled. All local earths have been removed, and the electrical equipment/s can
be made alive.
Sent by .............................
Received by .............................
139
Indian Railways - AC Traction Manual - Volume-II Part-I
Form ETR-3
Part-A.
.................. RAILWAY
I hereby declare that it safe to work on or near the following electrical equipment which is dead,
isolated from all live conductors and is connected to earth.
The equipment shall not be alive until this Permit-to-work is returned duly signed by the person in-
charge of the work.
Designation ..................
Date ............ Hr ............ Mts.......
140
Chapter-6 Power Blocks And Permits-To-Work
Fnorm ETR-3
Part-B.
.................. RAILWAY
Received the original foil of this Permit to work, I fully understand the portion of electrical equipment
which is dead, isolated and earthed and that all other parts are dangerous.
Signature ................
(of the authorized person)
Designation ..................
Date ............ Hr ............ Mts.......
141
Indian Railways - AC Traction Manual - Volume-II Part-I
Form ETR-3
Part-C
.................................. RAILWAY
From, To,
.............................................. ............................................
at........................................... at...............................................
all men and materials under my charge have been withdrawn the men have been warned that it is no
Signature ...............................
(of the authorized person)
Designation........................
Date...............Hr.............Mts.......
142
Chapter-6 Power Blocks And Permits-To-Work
Form ETR-3
Part-D
.................................. RAILWAY
From, To,
.............................................. ............................................
at........................................... at...............................................
Signature ...............................
(of the authorized person)
Designation........................
Date...............Hr.............Mts.......
143
Indian Railways - AC Traction Manual - Volume-II Part-I
Form ETR-4
Part A
................................. RAILWAY
LOCAL BLOCK
From, To,
Signature ..................................
Copy to:- (1) Traction Power Controller Section Controller
(c) Section Controller
144
Chapter-6 Power Blocks And Permits-To-Work
Form ETR-4
Part B
...........................................RAILWAY
LOCAL BLOCK
At......................................Hr.......................................Mts..........................................
................................................................
Signature of the station Master/Yard Master
Place....................................................
145
Indian Railways - AC Traction Manual - Volume-II Part-I
Form ETR-4
Part C
................................. RAILWAY
LOCAL BLOCK
.....................Hr...............Mts............
From,
Signature .................................................
*****
146
CHAPTER-7
SIGNALLING & TELECOMMNICATION AND PERMANENT
WAY INSTALLATIONS IN ELECTRIFIED SECTIONS
20700 Introduction
The important points concerning the signalling, telecommunication and permanent way installations in
147
Indian Railways - AC Traction Manual - Volume-II Part-I
height.
148
20704 Insulation of Wires and Point Rods
149
Indian Railways - AC Traction Manual - Volume-II Part-I
Volume
maintenance
I. GENERAL
155
Indian Railways - AC Traction Manual - Volume-II Part-I
156
Chapter-8 Breakdowns
157
Indian Railways - AC Traction Manual - Volume-II Part-I
158
Chapter-8 Breakdowns
159
Indian Railways - AC Traction Manual - Volume-II Part-I
160
Chapter-8 Breakdowns
161
Indian Railways - AC Traction Manual - Volume-II Part-I
162
Chapter-8 Breakdowns
163
Indian Railways - AC Traction Manual - Volume-II Part-I
V. ROAD VEHICLES
165
Indian Railways - AC Traction Manual - Volume-II Part-I
20840 Parking
166
Chapter-8 Breakdowns
167
Indian Railways - AC Traction Manual - Volume-II Part-I
Annexure 8.01
PANTO ENTANGLEMENTS : ITEMS TO BE CHECKED ON PANTOGRAPH
168
Chapter-8 Breakdowns
Annexure 8.02
PROFORMA FOR RECORDING MEASUREMENT/OBSERVATION IN RESPECT OF
OHE IN CASE OF PANTO ENTANGLEMENT.
*****
169
CHAPTER-9
PREPARATION FOR COMMSSIONING
20900 Introduction
171
Indian Railways - AC Traction Manual - Volume-II Part-I
I. TRACTION SUB-STATIONS
173
Indian Railways - AC Traction Manual - Volume-II Part-I
174
Chapter-9 Preparation For Commssioning
20909 Isolators
20914 Clearances
connection
20915 Auxiliary Power Supply for Traction Substations & Control Room
176
Chapter-9 Preparation For Commssioning
20917 General
177
Indian Railways - AC Traction Manual - Volume-II Part-I
178
Chapter-9 Preparation For Commssioning
20926 Accessories
Indian Railways - AC Traction Manual - Volume-II Part-I
20928 25 kV Feeders
181
Indian Railways - AC Traction Manual - Volume-II Part-I
20933 Fuses
Chapter-9 Preparation For Commssioning
183
Indian Railways - AC Traction Manual - Volume-II Part-I
184
Chapter-9 Preparation For Commssioning
Indian Railways - AC Traction Manual - Volume-II Part-I
20945 Clearances
186
Chapter-9 Preparation For Commssioning
20947 General
20948 Interlocking
187
Indian Railways - AC Traction Manual - Volume-II Part-I
188
Chapter-9 Preparation For Commssioning
20960 Infringements
Indian Railways - AC Traction Manual - Volume-II Part-I
Chapter-9 Preparation For Commssioning
*****
CHAPTER-10
COMMISSIONING OF ELECTRIC TRACTION
21000 General
201
Indian Railways - AC Traction Manual - Volume-II Part-I
202
Chapter-10 Commissioning Of Electric Tractiondowns
203
Indian Railways - AC Traction Manual - Volume-II Part-I
204
Chapter-10 Commissioning Of Electric Tractiondowns
energisation
Indian Railways - AC Traction Manual - Volume-II Part-I
206
Chapter-10 Commissioning Of Electric Tractiondowns
207
Indian Railways - AC Traction Manual - Volume-II Part-I
208
Chapter-10 Commissioning Of Electric Tractiondowns
21015 Failure of Equipment After Commissioning and During the Guarantee Period
Indian Railways - AC Traction Manual - Volume-II Part-I
SN Particulars Proforma
210
Chapter-10 Commissioning Of Electric Tractiondowns
SN Particulars Proforma
Proforma 10-1
INDIAN RAILWAYS
“PUBLIC NOTIFICATION”
211
Indian Railways - AC Traction Manual - Volume-II Part-I
Proforma 10-02
INDIAN RAILWAY
INTRODUCTION OF ac 25 kV TRACTION
“WARNING TO ROAD USERS”
212
Chapter-10 Commissioning Of Electric Tractiondowns
Proforma 10-03
CERTIFICATE REGARDING OHE
Proforma 10-04
CERTIFICATE REGARDING BONDINGAND EARTHING
Proforma 10-05
CERTIFICATE REGARDING SAFETY PROCEDURES AND PRECAUTIOINARY
MEASURES FOR STAFF
213
Indian Railways - AC Traction Manual - Volume-II Part-I
Proforma 10-07
214
Chapter-10 Commissioning Of Electric Tractiondowns
Proforma 10-8
Proforma- 10-09
COMPLETION CERTIFICATE
Indian Railways - AC Traction Manual - Volume-II Part-I
Proforma 10-10
CLEARANCE CERTIFICATE FOR ENERGIZATION ON 25 kV
1. 25 kV Feeder Lines
Proforma 10-11
CLEARANCE CERTIFICATE FOR ENERGIZATION ON 25 kV
2. Overhead Equipment
216
Chapter-10 Commissioning Of Electric Tractiondowns
Proforma 10-12
CLEARANCE CERTIFICATE FOR ENERGIZATION ON 25 kV
3. Switching Stations
217
Indian Railways - AC Traction Manual - Volume-II Part-I
Proforma 10-14
(Proforma deleted and its contents included in proforma (10-08) via ACS-3)
CLEARANCE CERTIFICATE FOR ENERGIZATION ON 25 kV
Proforma 10-15
218
Chapter-10 Commissioning Of Electric Tractiondowns
Proforma 10-16
Indian Railways - AC Traction Manual - Volume-II Part-I
Proforma 10-17
220
Chapter-10 Commissioning Of Electric Tractiondowns
Profarma 10-19
221
Indian Railways - AC Traction Manual - Volume-II Part-I
Proforma-10-20
Form XV-2
222
Chapter-10 Commissioning Of Electric Tractiondowns
Proforma-10-21
-------------- RAILWAY
JOINT SAFETY CERTIFICATE NO.SLC/BG/01/2004
restriction
speed of speed speed restriction
the section
1 2 3 4 6 7 8 10 11 12
223
Indian Railways - AC Traction Manual - Volume-II Part-I
Proforma-10-22
224
Chapter-10 Commissioning Of Electric Tractiondowns
Proforma-10-23
1 2 3 4
1
stations
2
station
3
stations
4
6
Indian Railways - AC Traction Manual - Volume-II Part-I
Proforma-10-24
1 2 3 4
Proforma-10-25
Whether
contact static
line anchored
structure
1 2 3 4 6 7 8
226
Chapter-10 Commissioning Of Electric Tractiondowns
earthed part
earth
1 2 3 4
Proforma-10-26
Whether
clearance as
1 2 3 4 6 7
*****
227
CHAPTER-11
RECENT DEVELOPMENTS
229
Indian Railways - AC Traction Manual - Volume-II Part-I
2. Power is generally obtained from 220 kV or 132 kV three phase networks from the power utility to
reduce voltage unbalance on the transmission network. In the 2X25kV TSS, the three phase supply
is utilized at the Traction Sub-station.
3. The 2X25 kV Auto Transformer (AT) system is having feeding voltage of 50 kV from the substation
which is dropped to 25 kV by the AT installed at about 10 to 18 Km spacing along the track for
supply to overhead equipment and rolling stocks. A pilot project for this system was provided in
Bina-Katni Section. The design of the system was done with the help of Japanese Consultants.
4. Better voltage regulation even at higher load currents.
5. Minimized rail currents resulting in reduction in rail potential rise. Return current through ground
also reduces considerably.
in the feeder wire is opposite to the direction of current in the catenary wire, it minimizes the effect
of the electromagnetic Interference in the proximity of the traction line.
7. Preferred solution across the globe to meet higher power requirement for Traction Purpose.
230
Chapter-8 Breakdowns
231
Indian Railways - AC Traction Manual - Volume-II Part-I
3. Auto Transformers:
Auto- transformers are used at TSS, SP and SSP. The transformer winding of 50kV with Centre tapped
neutral with both the terminals of the Autotransformer winding connected to feeder and contact /
Catenary wire. The neutral terminal of the ATs is connected to rail.
Two adjacent ATs feeding on the network share train loads on the section between them and transfer
the load current on 25 kV circuit to 50 kV circuit, consisting of contact wire and AT feeder. This
reduces the voltage drop on feeding network remarkably. Furthermore, it minimizes the return current
on the rail, which results in reducing induced voltage on nearby telecommunication lines.
In the Scott connected arrangement for 2 Line section, 12.3 MVA Auto transformers are to be installed
at the TSS and 8MVA Auto transformers to be used at the SP & SSP, as adopted by DFCCIL in Western
Corridor. Further, the Scott connected arrangement for 3 Line and 4 line sections have been provided
with 12.3 MVA auto transformers at TSS and 16.5 MVA auto transformers at SP/SSP. Moreover, no
independent AT post has been proposed in any scheme.
remains as standby and third transformer feeds the OHE on the other side of the TSS. The power
supply on either side of TSS is at a phase difference of 120 degree and therefore separated by a neutral
section provided near TSS.
5. V- Connected Transformer:
In the above arrangement, three 38/53/63 MVA (ONAN/ONAF/OFAF) Transformers are provided at
TSS along with associated switchgear for Control and Protection. Each single phase transformer has
a voltage input of 220kV or 132kV, 50 Hz and two independent secondary windings, to be connected
externally in such a manner (two inner terminals of these secondary windings are connected with each
other and also connected to earth/Rail) so as to give an output voltage of 2X25kV. The outer terminals
of the windings are connected to Feeder wire and overhead contact/catenary wire respectively. Two
transformers shall be in operation at a time and one shall be on standby. In the V connected Scheme,
each transformer in ONAN mode shall feed the 38MVA Power in either side of the TSS.
6. Auto Transformers:
i. Auto- transformers are used at SP and SSP. The transformer winding is 50 kV with Centre
tapped neutral with both the terminals of the winding connected to AT feeder and the contact
wire. The neutral terminals of the ATs are connected to rail.
ii. Two adjacent ATs feeding on the network share train loads on the section between them and
transfer the load current on 25 kV circuit to 50 kV circuit, consisting of contact & catenary wire
and AT feeder. This reduces the voltage drop on the feeding network remarkably. Furthermore,
it minimizes the return current on the rail, which results in reducing the induced voltage on
nearby telecommunication lines.
iii. Auto transformers are not used at the TSS. However, these have been provided at SP/SSP of
16.5 MVA capacities. Moreover, no independent AT post has been proposed.
232
Chapter-8 Breakdowns
8. Utilisation of Scheme:
Considering the complexities involved of the unbalancing (as deliberated under Para 4.3 above), space
constraints and other site problems, the Scott connected or V connected arrangement may be chosen by
the Zonal Railways after coordinating with the power utilities and with the approval of PCEEs.
233
Indian Railways - AC Traction Manual - Volume-II Part-I
spacing of the TSS in V connected scheme for 4 Line system has been kept same as in Scott connected
scheme i.e. 40-50 KM with a power requirement of around 0.5 MVA/TKM in ONAN mode.
The sectioning and paralleling post (SP) is to be constructed at approx. midway between consecutive
TSS and SSP may be constructed at approx. midway between TSS & SP.
The transformer is provided with ONAF/OFAF mode to meet the power requirement under feed
extension condition and to account for the margin of 10 KM given in the spacing.
Wherever the Traction Sub Station feeds a mix of 2 line- 3 line sections, 3 line-4 line sections etc., the
spacing and location selection of the Traction Sub Station may be decided by considering the above
power requirement in ONAN mode on TKM basis as per the scheme adopted. In such cases, the power
requirement on each side of Traction Sub Station may be done separately and accordingly the TSS and
SP to be located in terms of spacing. The SSP may be provided at approximately mid of TSS and SP.
11. Interlocking
a. Scott Connected TSS
i. The Closing of the LVCB on the secondary side of Traction Transformer (i.e. 50kV, SF6CB)
shall be possible only when any one of the Circuit Breaker of associated Autotransformer at
TSS is in closed condition.
ii. The automatic opening of the LVCB on the secondary side of Traction Transformer (i.e. 50kV,
SF6CB) shall happen as soon as all the Circuit Breakers of the associated Autotransformers
at the Traction Sub Station are opened.
234
Chapter-8 Breakdowns
iii. The closing of coupling motorised isolator between Main Bus and Teaser Bus should be
possible only when all the LVCBs of the Transformer are open. This coupling isolator has
been provided for the feed extension in case of failure of TSS.
iv. To ensure above, necessary interlock shall be provided.
b. V Connected TSS
In this scheme the middle Traction transformer is to be used in either direction in case of failure
of any one of the outer transformer. Therefore necessary interlock is to be provided between
Motorised Coupling Isolator and LV Circuit Breaker in order to avoid wrong phase coupling as
well as to ensure off load operation of the Motorised isolator.
There is off load circuit tap changer on primary side of the transformer with 6 tap positions
(including principal tap) for voltage adjustment. Therefore, the tap changer should be operated
only when both the primary and secondary circuit breakers are in open condition.
Level, The transformation capacity of any single sub-station for meeting loads shall not normally
exceed 75MVA. In view of this limitation, if 66kV incoming supply is there, only ONAN Mode
Transformer i.e. 60MVA Scott Connected or 38X2= 76MVA, V connected can be used. To address the
huge power requirement for future load, it is suggested to not to take feed from the utility at 66 kV.
Therefore, it is suggested to use 220kV or 132kV incoming Voltage only.
Interface of 25kV system with 2X25kV system and extension of feed from 25kV system to 2X25kV
System and vice versa:
The SP may be proposed as an interface between subject two systems as the SP have been provided with
adequate AT capacity to cater the feed extension. However, the overloading of the Autotransformer/
Autotransformers installed at SP shall determine the extent of feed extension.
235
Indian Railways - AC Traction Manual - Volume-II Part-I
In this case, AT-1 at boundary of both systems is burdened with all the train loads which are located
at right side of AT -2 and nearly half of the train loads between AT-1 and AT-2 Therefore, overload of
AT-1 shall be observed.
being increased gradually. Heavier freight trains hauled by one or two consists of locomotives will
draw heavy currents from the substation. For meeting the requirement of increasing passenger
to ascertain potential of the existing OHE and pantograph contact system for effecting requisite
improvement and developing newer designs to achieve satisfactory current collection at higher
speeds and heavier loads.
3. For achieving these objectives, efforts are on to develop an Overhead Equipment Recording cum
Test Car. This car will be used to measure and record various parameters of OHE and pantograph
both under static and dynamic conditions. The proposed car will be of trailer type, suitable for
running at speeds of 160 km/h with potential to run up to 200 km/h. The car shall be hauled
by locomotive or attached to a train. The car will be provided with on-board computer based
data acquisition and processing system. The facility for video recording of arcs generated due to
interruption in current drawn by locomotive as a result of loss of contact between pantograph and
the OHE is also proposed to be provided.
4. The various parameters proposed to be monitored are:
Measurements on pantograph:
a. acrodynamic upward force of the pantograph;
b. contact force between pantograph and contact wire;
c. vertical and horizontal movement of pantograph;
d. quality of current collection- loss of contact;
236
Chapter-8 Breakdowns
Measurements on OHE:
a. height of contact wire ;
b. stagger of the contact wire;
c. gradient of the contact wire;
d. detection of hard spots;
e. checking of crossovers and turn-outs;
f. body vertical acceleration;
g. body lateral acceleration;
h. quality of current collection - loss of contact.
capacity at TSS.
2. To overcome the above problem, the integrated microprocessor based numerical 25 kV feeder
protection module comprising of Polygonal characteristic distance protection, Wrong Phase
(OCR) , Potential Transformer Fuse Failure (PTFF) Alarm and Trip, Auto Reclosure Relay, CB
Trip Circuit Supervision Relay, Breaker backup (LBB) has been developed for Railway traction
application. For its full utilization in controlling / monitoring of protection system, the module is
capable of communicating with the RTU based on standard IEC 60870-5-103 protocol for transfer
of information stored in relays to the RTU.
3. Concept of Numerical Relay: The numerical relay comprises of the following components.
a Central Processing Unit
b. Memory (RAM & ROM)
c. ADC (Analog to Digital Converter)
d. IO modules (Input/output Modules)
e. Communication module (RS 232/485/Ethernet)
The numerical relay measures electric parameters (V, I) and convert them into digital data with the
help of ADC which undergoes mathematical and logical analysis based on the program stored in the
memory and to take action on tripping if fault occurs in the power system.
As the numerical relay is communicable the fault data stored in the relay can be transferred to RCC
through SCADA and the analysis of retrieved data is possible.
237
Indian Railways - AC Traction Manual - Volume-II Part-I
Failure (PTFF) Alarm and Trip, Auto Reclosure Relay, CB Trip Circuit Supervision Relay, Breaker
backup (LBB) has been developed for Railway traction application. For its full utilization in
controlling / monitoring of protection system, the module is capable of communicating with the
RTU based on standard IEC 60870-5-103 protocol for transfer of information stored in relays to
the RTU. To avoid malfunction of relay due to load encroachment, the load impedance area of
the polygonal shall be settable for non-tripping in case the impedance falls in this area. For other
referred.
(FRP) rod’ and injection moulded sheds of High Temperature Vulcanising (HTV) Silicone rubber.
ingress of moisture and direct tracking along the length of the core. Such insulators have excellent
impact withstand capability and excellent Hydrophobic & anti- tracking properties”.
21106 Automatic Phase Switching Section (in place of Neutral Section) and
Numerical Control Logic Relay: DELETED
Automatic Phase Switching Section (APSS) has been developed for 25 kV Single Phase 50 Hz AC
Traction Power Supply System of Indian Railway to facilitate automatic changeover of supply coming
238
Chapter-8 Breakdowns
from different phases as soon as the Electric Loco/EMU negotiates the IOLs meant for phase separation
without affecting the status of loco/EMU circuit breaker (DJ). No neutral section is required in APSS
for separation of different phase supply at SP and hence, Loco Pilot can run the train at desired speed
without any hassle and stress and worrying about DJ ON/OFF Boards giving instructions for opening
and closing of electric loco/circuit breaker (DJ) which were required in case of neutral section. Three
insulated overlaps along with CBs, CTs & PTs at SP (or any desired location) associated with Automatic
Phase Switching Section (APSS) has to be provided. Circuit Breaker rated for APSS operation will be
the manufacturer of the Numerical Control Logic Relay (NCLR) may be referred.
239
Indian Railways - AC Traction Manual - Volume-II Part-I
240
Chapter-8 Breakdowns
241
Indian Railways - AC Traction Manual - Volume-II Part-I
2. Heavy Overhead Structures, such as Road Over Bridges and Flyovers: 8050mm
3. Heavy Overhead Structures, Such as Road Over Bridges and Flyovers, if any turnout or crossover
is located under that heavy overhead structure or within 40meters from its nearest face: 8430mm
Note:
1. Necessary provision shall be made in overhead structure and overhead equipment to permit an
extra allowance for raising of track in future to cater for modern track structure in the form of
increased ballast cushion of 350mm, larger sleeper depth of 230mm and heavier rail section of
200mm including 10m thick rubber pad by using longer traction overhead mast, if necessary.
2. In case of restricted height of existing overhead structures, minimum height of overhead structure
for a distance of 1600mm on either side of centre of track for provision of high rise OHE as per
note (iii) below, to permit operation of double stack container having height as 6809mm shall be as
under:
a. Light Overhead Structure such as Foot Over Bridges: 7568 mm
b. Heavy Overhead Structures, such as Road Over Bridges and Flyovers: 7468mm
c. Heavy Overhead Structures, Such as Road Over Bridges and Flyovers, if any turnout or
crossover is located under that heavy overhead structure or within 40meters from its nearest
face: 7568mm
For these minimum restricted heights, catenary wire shall be terminated outside overhead
structure (Road Over Bridges & Flyovers/Foot Over Bridges)
3. In case of restricted height of existing overhead structures, bridges and tunnels the minimum height
of underside of the contact wire from rail level can be reduced to 7166mm. In such cases a special
study shall be made before 25kV AC traction is introduced as explained below:
(a) Height of Rolling stock 6809mm
(b) Short duration electrical clearance 200mm
(c) Additional electrical clearance for oscillation of contact wire (For OHE 50mm
span length of 49.5m or below)
(d) Allowance for track upgradation/maintenance 50mm
(e) Rise in rolling stock height under dynamic condition 57mm
Minimum Height of contact wire 7166mm
242
Chapter-8 Breakdowns
5. Clearances for Power Line Crossings including Telephone Line Crossings of Railway Tracks:
SN Overhead crossing Minimum clearance from Rail Level Minimum clearance
voltage Existing power New power line between highest traction
line crossing for crossing or conductor and lowest
existing Non- crossing planned transmission line crossing
for alteration conductor
Note:
existing crossings can continue, if dimensions are as per Column (5) above, even if dimensions
243
Indian Railways - AC Traction Manual - Volume-II Part-I
244
Chapter-8 Breakdowns
245
Indian Railways - AC Traction Manual - Volume-II Part-I
246
Chapter-8 Breakdowns
CHEMICAL COMPOSITION
Element %ppm
Cu+Ag Remaining
Mg 0.1% - 0.7%
Bi < 10 ppm
Pb <5 ppm
P <50 ppm
Oxygen <20 ppm
Spring ATD can be used for higher tension and high speed.
247
Indian Railways - AC Traction Manual - Volume-II Part-I
for its traction applications during 2018-19 which is about 1.3% of total electrical energy generated in
have been very conscious about saving energy and accordingly consistently been working towards
controlling its energy bill on traction side by adopting multi-pronged strategies including procuring
energy from open market.
Earlier IR has been procuring electricity as an ordinary consumer for its traction applications despite
being the single largest user of energy in the country. Accordingly, it has been paying higher tariffs
for energy duly taking the burden of distribution losses, cross subsidy and other surcharges of Power
Distribution Companies (DISCOMs). The Electricity Act 2003 conferred Deemed Licensee status on
IR being Central Government department due to its involvement in transmission &distribution of
energy from the time electricity came to India. Accordingly, IR had been working to get this provision
of Electricity Act operational; however it didn’t come through for quite some time due to various
factors.
Ministry of Railways took up this task with fresh impetus and subsequently a strategy was drawn.
In line with this, Indian Railway approached Central Electricity Regulatory Commission (CERC)
for issue of necessary guidelines to all State Transmission Utilities (STUs) and State Load Dispatch
Centers (SLDCs) to facilitate Open Access to Indian Railways on existing transmission network as
Deemed Licensee. This was made to enable Indian Railways to procure energy from any generating
unit, including captive generating plants, traders, or through power exchange up to the interconnection
In its historic judgment on 5th Nov.’15, CERC in Petition No. 197/MP/2015 ordered that:
“Indian Railways is an authorized entity under the Railways Act to undertake transmission and
distribution activities in connection with the working of the railways, independent of its status under
the Electricity Act. Indian Railways is a deemed Licensee under third proviso to Section 14 of the
Electricity Act and no separate declaration to that effect is required from the Appropriate Commission.
All concerned RLDCs, State Transmission Utilities and SLDCs are directed to facilitate long term
access and medium term access in terms of Connectivity Regulations from the generating stations or
other sources to the facilities and network of Indian Railways.”
Finally, IR’s vision of drawing electrical energy as deemed licensee was realized on 26th Nov.’15
when it started drawing about 200 MW power on Central Railway from Ratnagiri Gas Power Pvt. Ltd.
under open access as a distribution licensee using state distribution network. IR contracted about
540 MW from RGPPL for consumption in the states of Maharashtra, Gujarat, M.P., and Jharkhand
completed by 22nd Jan.’16. Further, IR also contracted 50 MW through open tender for taking on its
The salient features of CERC/SERC regulations regarding open access are as under.
Eligibility for Open access:
1. Application for open access should be made in prescribed format.
248
Chapter-8 Breakdowns
Completion of Works
1. Where the grant of Open Access is agreed to but requires the completion of works relating to
extension or augmentation of lines, transformers, metering arrangements, etc., or the commissioning
of new Sub-Stations, the Distribution Licensee shall complete such works within the time limits
Meter Reading
Settlement of Dues
1. A Consumer applying for Open Access to the Distribution System shall settle all dues of the
Distribution Licensee prior to applying for Open Access:
249
Indian Railways - AC Traction Manual - Volume-II Part-I
APPLICABLE CHARGES:
1. The bill will be raised on the Open Access Generator / Open Access consumer The bill will include
the following charges:
a. Wheeling Charges / Transmission Charges, as may be applicable;
b. Cross Subsidy Surcharge, as may be applicable;
c. Additional Surcharge on the Charges of Wheeling;
d. Standby Charges;
e.Voltage Surcharge, as may be applicable;
f. System Operating Charges& Market operating charges
g. Charges in case of over or under drawl with reference to the scheduled power. from the grid.
h. Any other charge or other sum recoverable.
*****
250
CHAPTER-12
TRAINING AND COMPETENCY CERTIFICATES
I. TRAINING
21200 Introduction
251
Indian Railways - AC Traction Manual - Volume-II Part-I
252
21206 Facilities for Training
253
Indian Railways - AC Traction Manual - Volume-II Part-I
21211 Syllabi
254
II. COMPETENCY CERTIFICATES
255
Indian Railways - AC Traction Manual - Volume-II Part-I
21219 Inspections
Indian Railways - AC Traction Manual - Volume-II Part-I
Annexure 12.01
ASSURANCE
Indian Railways - AC Traction Manual - Volume-II Part-I
*****