0% found this document useful (0 votes)
145 views

Explosion and Fire at The Macondo Well

Volume 1 of the investigation report provides background on the 2010 Macondo incident in the Gulf of Mexico, which resulted in 11 fatalities, 17 injuries, and significant environmental damage. It describes the involved parties, including BP, Transocean, and Halliburton. It also discusses deepwater drilling operations and the temporary abandonment process that was underway at the Macondo well when the rig explosion occurred. The report aims to explain the relevant context around the incident and set the stage for subsequent volumes that will analyze causal factors.

Uploaded by

Kalou Boni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
145 views

Explosion and Fire at The Macondo Well

Volume 1 of the investigation report provides background on the 2010 Macondo incident in the Gulf of Mexico, which resulted in 11 fatalities, 17 injuries, and significant environmental damage. It describes the involved parties, including BP, Transocean, and Halliburton. It also discusses deepwater drilling operations and the temporary abandonment process that was underway at the Macondo well when the rig explosion occurred. The report aims to explain the relevant context around the incident and set the stage for subsequent volumes that will analyze causal factors.

Uploaded by

Kalou Boni
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 37

US C H E M I C A L S A F E T Y A N D H AZ A R D I N V E S T I G A T I O N B O A R D

INVESTIGATION REPORT
VOLUME 1
EXPLOSION AND FIRE AT THE MACONDO WELL
(11 Fatalities, 17 Injured, and Serious Environmental Damage)

DEEPWATER HORIZON RIG


MISSISSIPPI CANYON BLOCK #252, GULF OF MEXICO
APRIL 20, 2010
KEY ISSUES IN VOLUME 1
• MACONDO INCIDENT BACKGROUND AND GENERAL DESCRIPTION
• DEEPWATER DRILLING AND TEMPORARY ABANDONMENT OF THE MACONDO WELL

REPORT NO. 2010-10-I-OS


6/5/2014
Macondo Investigation Report Volume 1 June 5, 2014

[This page left intentionally blank.]

2
Macondo Investigation Report Volume 1 June 5, 2014

Volume 1
Macondo-specific incident
events: Relevant background
on deepwater drilling and
temporary abandonment

3
Macondo Investigation Report Volume 1 June 5, 2014

[This page left intentionally blank.]

4
Macondo Investigation Report Volume 1 June 5, 2014

Contents
VOLUME 1 .................................................................................................................................................. 3

ACRONYMS AND ABBREVIATIONS ..................................................................................................... 7

1.0 MACONDO BACKGROUND AND INCIDENT SUMMARY..................................................... 8


1.1 Involved Parties ............................................................................................................................... 8
1.2 The US Offshore Regulator ........................................................................................................... 10
1.3 The Well, the Rig, and the Crew.................................................................................................... 12
1.3.1 The Deepwater Horizon Rig ............................................................................................. 14
1.3.2 The Crew........................................................................................................................... 14
1.4 Planning the Well........................................................................................................................... 15
1.5 Incident Description ....................................................................................................................... 16

2.0 DEEPWATER DRILLING AND TEMPORARY ABANDONMENT OF THE MACONDO


WELL ............................................................................................................................................ 18
2.1 Controlling Pore Pressures with Drilling Fluids ............................................................................ 19
2.2 Controlling Pore Pressures with Casing and Cement .................................................................... 23
2.2.1 Cement Integrity Testing and Final Displacement ........................................................... 26
2.3 Controlling Pore Pressures with a Blowout Preventer ................................................................... 28
2.4 Consequences of Explosion and Fire ............................................................................................. 31

REFERENCES ........................................................................................................................................... 32

5
Macondo Investigation Report Volume 1 June 5, 2014

Figures and Tables

Figures
Figure 1-1. Relationship between key companies associated with the Deepwater Horizon accident........... 9
Figure 1-2. Location of the Macondo well. ................................................................................................ 12
Figure 1-3. Timeline from when BP acquired the Macondo well lease until the Deepwater Horizon took
over drilling the well. .............................................................................................................. 13
Figure 2-1. During drilling, mud travels down the drillpipe, through the drill bit, and then back up the
annulus (yellow), carrying crushed rock back to the rig. ........................................................ 20
Figure 2-2. A simplified drilling margin plot. The planned mud weight (red dashed line) is formulated to
remain less than the fracture gradient (green line) and greater than the pore pressure (black
line). New casing transitions (green diamonds) are installed when the fracture gradient is
approached............................................................................................................................... 22
Figure 2-3. Cementing casing in place involves filling the annulus with cement above any hydrocarbon
bearing zones if they are present as well as a small length (30ˈ-90ˈ) in the shoe track........... 24
Figure 2-4. The final Temporary Abandonment configuration intended to remove drilling mud down to
8,367 feet to install a cement plug in seawater. ....................................................................... 26
Figure 2-5. The Deepwater Horizon BOP .................................................................................................. 29

Tables
Table 1-1. Total number of employees and revenue as reported by companies associated with the
Deepwater Horizon ................................................................................................................... 10
Table 1-2. Personnel On Board on April 20 by Company [NEED UPDATED TABLE] .......................... 14
Table 1-3. Well Control Personnel On Board the Rig on April 20, 2010 ................................................... 15

6
Macondo Investigation Report Volume 1 June 5, 2014

Acronyms and Abbreviations

APD Application for Permit to Drill


BOEM Bureau of Ocean Energy Management (United States)
BOEMRE Bureau of Ocean Energy Management, Regulation, and Enforcement (United
States); the US offshore safety regulator between June 18 and October 1, 2011 a
BOP Blowout Preventer
BSEE Bureau of Safety and Environmental Enforcement (United States); US offshore
safety regulator since October 1, 2011 b
CSB United States Chemical Safety & Hazard Investigation Board
DWH Deepwater Horizon
EDS Emergency Disconnect System
IADC International Association of Drill Contractors
MMS Minerals Management Service (United States); US offshore safety regulator at
the time of the Macondo accident until June 18, 2011 c
MODU Mobile Offshore Drilling Unit
OCS Outer Continental Shelf
ONRR Office of Natural Resources Revenue (United States)
ppg pounds per gallon
SEMS Safety and Environmental Management System
UK United Kingdom

a
Department of Interior, Order No. 3302, Change of the Name of the Minerals Management Service to the Bureau
of Ocean Energy Management, Regulation, and Enforcement (June 18. 2011),
http://www.doi.gov/deepwaterhorizon/loader.cfm?csModule=security/getfile&PageID=35872. Accessed
February 19, 2014.
b
The Reorganization of the Former MMS, http://www.bsee.gov/About-BSEE/BSEE-
History/Reorganization/Reorganization/..Accessed February 19, 2014.
c
Department of Interior, Order No. 3302, Change of the Name of the Minerals Management Service to the Bureau
of Ocean Energy Management, Regulation, and Enforcement (June 18, 2011),
http://www.doi.gov/deepwaterhorizon/loader.cfm?csModule=security/getfile&PageID=35872. Accessed February
19, 2014.

7
Macondo Investigation Report Volume 1 June 5, 2014

1.0 Macondo Background and Incident Summary


At the time of the accident, the Deepwater Horizon (DWH) crew had finished drilling and was
completing temporary abandonment of the well so that a production facility could return later to extract
oil and gas from the well.
Chapter 1.0 Overview
The Macondo well was exploratory in nature, meaning
significant uncertainty remained about the geology, the This chapter provides general
petroleum resources, and the formation characteristics that background as an introduction to the
make the well easy or difficult to drill. Managing such CSB’s investigation of Macondo. It is
uncertainties ultimately determines a company’s success. not meant to be all-encompassing.
Additional relevant information
On the day of the April 20 tragedy, no effective safeguards
including key findings appears in
were in place to eliminate or minimize the consequences of
subsequent volumes.
a process safety incident. a The safeguards (or barriers)
intended to prevent such a disaster were not properly This chapter summarizes information
constructed, tested, or maintained, or they had been on the companies and entities
removed. The management systems intended to ensure the involved in the drilling and temporary
required functionality, availability, and reliability of these abandonment of the Macondo well,
safety critical barriers were inadequate. Ultimately, the the well itself, the Deepwater Horizon
barriers meant to prevent, mitigate, or control a blowout rig, and the drilling crew aboard the
failed on the day of the accident. rig on the day of the incident. It
concludes with an incident
1.1 Involved Parties description summary that identifies
the failures in the hours leading up to
BP Exploration & Production Inc. (BP) b was and is the main the explosions and fires aboard the
lease holder/operator of the block of land c that includes the DWH.
Macondo well site. d BP identifies itself as the largest
leaseholder in US Gulf of Mexico deepwater, owning more
than 650 different blocks of land in water depths of 1,200 feet or greater. 1
Offshore lease holder/operators such as BP largely conduct deepwater well drilling and completion
activities through a number of contractors. Effective selection, oversight, and coordination among the
operator and various contractors are vital to safe offshore exploration. To drill the well at Macondo, BP

a
A process safety incident is the unexpected releases of toxic, reactive, or flammable liquids and gases in processes
involving highly hazardous chemicals—Process Safety Management, OSHA 3132, 2000 (reprinted).
b
BP p.l.c. is the parent company of many BP group companies, including BP Exploration & Production Inc.
(BPXP). When referring to “BP,” BPXP is intended unless otherwise stated.
c
The Outer Continental Shelf has been divided into geographical areas referred to as blocks for identification
purposes on maps and in databases, http://www.data.bsee.gov/homepg/pubinfo/freeasci/leasing/leaselistdfn.asp.
d
As of February 23, 2010, U.S. Department of Interior documents indicate Anadarko E&P Company LP (22.5%),
Anadarko Petroleum Corporation (2.5%), MOEX Offshore 2007 LLC (10%), and BP Exploration & Production
Inc. (65%), shared leasing title interests, but as of December 5, 2011, BP retained 100%,
http://www.data.bsee.gov/PI/PDFImages/ACTIVE-LEASE/130/133905.pdf. Retrieved November 12, 2013.

8
Macondo Investigation Report Volume 1 June 5, 2014

contracted Transocean, the drilling contractor, and other well service providers, including Halliburton and
Sperry-Sun Drilling Services, a subsidiary of Halliburton (Figure 1-1).
As of November 2013, Transocean operated a worldwide fleet comprising 80 different drilling rigs. 2 In
the US Gulf of Mexico, the fleet included 13 ultra-deepwater drilling rigs, which have the same water
depth capability as the Deepwater Horizon’s, 7,500 feet and greater. Transocean has stated that BP was
one of its most significant customers in 2012, accounting for approximately 11 percent of operating
revenues. 3
As indicated in Figure 1-1, Cameron was not directly contracted to BP, but the original contract between
Transocean and BP specified the configuration of the blowout preventer and made specific references to
“Cameron or equivalent” components throughout the contract. 4 Cameron provided updated parts, testing,
technical assistance, and repair services for the Deepwater Horizon BOP throughout its service period. a

Figure 1-1. Relationship between key companies associated with the Deepwater Horizon accident.

Transocean owned and operated both the Marianas and the DWH drilling rigs that were used at Macondo.
It also employed most of the onboard crew of both rigs. As the contracted driller, Transocean was in
charge of furnishing and maintaining materials, supplies, equipment, and services required for the drilling
and completion activities that occurred at Macondo. 5 These services included maintaining well control
equipment, which the contract between BP and Transocean stipulated would be done according to good
oilfield practices and by “all reasonable means to prevent fire and blowouts.” 6 BP retained control of how
various aspects of the drilling program would progress by specifying the completion activities (Section
1.5), the mud program (Section 2.1), and the casing program (Section 2.2). 7
Halliburton Energy Services (Halliburton) and its subsidiary Sperry-Sun Drilling Services provided
cementing and well monitoring services to BP during drilling, completion, and temporary abandonment
activities at Macondo. 8
BP, its contractors, and the BOP manufacturer operate worldwide and earn between $8 and $375 billion
dollars annually (Table 1-1).

a
Cameron provided the CSB with numerous engineering report sheets, signed factory acceptance tests, repair sales
orders, and purchase orders.

9
Macondo Investigation Report Volume 1 June 5, 2014

Table 1-1. Total number of employees and revenue as reported by companies associated with the
Deepwater Horizon 9

1.2 The US Offshore Regulator


At the time of the Macondo incident, Minerals Management Service (MMS), a division within the
Department of the Interior, was the primary offshore regulator responsible for overseeing offshore energy
operations to ensure compliance with relevant laws and regulations, predominantly the Outer Continental
Shelf Lands Act and 30 CFR Part 250. a MMS managed the nation’s natural gas, oil, and other mineral
resources on the Outer Continental Shelf (OCS). Its jurisdiction incorporated developing and
implementing plans for leasing conventional and renewable energy resources, safety and environmental
protection in all offshore energy activities, and revenue management. MMS minerals revenue amounted
to approximately $13 billion annually, approximately 95% of the total revenue collected by the
Department of the Interior. b,10
On May 19, 2010, four weeks following the Deepwater Horizon incident, then-Secretary of the Interior
Ken Salazar signed a Secretarial Order to separate and reassign the responsibilities of the Minerals
Management Service 11 into three independent entities:

a
In addition to the Department of the Interior, several other federal agencies regulate safety and environmental
activities on the OCS. For instance, the US Coast Guard regulates marine safety, particularly the “safety of life
and property on Outer Continental Shelf (OCS) facilities, vessels, and other units engaged in OCS activities.” 33
C.F.R §140.1. The Environmental Protection Agency regulates air pollution from OCS sources (40 C.F.R. § 55.1)
and manages oil spill response in inland waters (40 C.F.R. Pt. 110 and 112). The Outer Continental Shelf Lands
Act grants the Occupational Safety and Health Administration the authority to enforce its regulations on the OCS.
However, if the working conditions are already regulated by another agency, the Department of the Interior and
the US Coast Guard, 4(b)(1) of the Occupational Safety and Health Act and 21(d) of OCSLA prevent OSHA from
duplicating their efforts.
b
The Department also manages other natural and cultural resources, including Bureau of Indian Affairs, Bureau of
Land Management, Bureau of Reclamation, National Park Service, Office of Surface Mining, Reclamation and
Enforcement, U.S. Fish and Wildlife Service, and U.S. Geological Survey,
http://interior.gov/whoweare/index.cfm. Retrieved October 28, 2013.

10
Macondo Investigation Report Volume 1 June 5, 2014

• The Office of Natural Resources Revenue (ONRR), responsible for the royalty and revenue
management function, including the collection and distribution of revenue, auditing and
compliance, and asset management. On October 1, 2010, the office began its duties. 12
• The Bureau of Ocean Energy Management (BOEM), responsible for the sustainable
development of the Outer Continental Shelf’s conventional and renewable energy resources,
including resource evaluation, planning, and leasing-related activities.
• The Bureau of Safety and Environmental Enforcement (BSEE), responsible for the
comprehensive oversight, safety, and environmental protection of all offshore energy
activities.
The changes could not immediately take effect, so in the interim Salazar renamed MMS to Bureau of
Ocean Energy Management, Regulation and Enforcement (BOEMRE), to identify the agency’s role more
accurately. 13 On October 1, 2011, BOEMRE ceased to exist after transferring its remaining
responsibilities to BOEM and BSEE. 14
In the aftermath of the incident, BOEMRE and then BSEE took significant proactive steps to promulgate
new safety regulations, including the Interim 15,a and Final [Drilling] Rules, 16,b the Safety and
Environmental Management Systems (SEMS) Rule [30 CFR Part 250 Subpart S], 17 and subsequent
amendments (SEMS II). 18
While these are the principal entities of the Macondo case, additional companies, government agencies,
and stakeholder organizations are associated with the incident aftermath and general offshore operations.
Background information on relevant entities appears throughout the CSB Macondo Investigation Report
volumes.

a
Requirements included a one-time recertification of BOPs, ROV capabilities and testing, autoshear and deadman
on dynamically positioned rigs, stump test of autoshear and deadman, deadman initial seafloor test,
documentation of BOP inspections and maintenance according to API RP 53, and, if shear rams activated on pipe
during well control, retrival and inspection of the BOP.
b
Requirements included third-party verification of subsea BOP “compatibility” and up-to-date engineering, subsea
secondary BOP intervention capability and testing, BOP drillpipe shearing capacity at the maximum anticipated
surface pressure (MASP), third-party verification of shear calculations, and a BOP surface test between each well.

11
Macondo Investigation Report Volume 1 June 5, 2014

1.3 The Well, the Rig, and the Crew


The Macondo well is in the Central Gulf of Mexico, in Mississippi Canyon Block #252, approximately 50
miles from Louisiana, the nearest shoreline (Figure 1-2).

Figure 1-2. Location of the Macondo well.

BP acquired the lease for the Macondo well in March 2008 19 and began drilling there in October 2009 20
after the offshore regulator approved BP’s exploration plan and issued BP a permit to drill. 21 Two rigs,
first the Marianas and then the DWH, were used to drill the Macondo well (Figure 1-3). The Marianas
drilled the Macondo well from October 6 to October 29, 22 but the Marianas had to be moved to a shipyard
for repairs after being significantly damaged by a hurricane; 23 the Deepwater Horizon replaced it, arriving
on site with a crew on January 31, 2010, 24 and began setup and testing. Drilling resumed in February. 25

12
Macondo Investigation Report Volume 1 June 5, 2014

Figure 1-3. Timeline from when BP acquired the Macondo well lease until the Deepwater Horizon took
over drilling the well.

BP planned to drill two exploration wells—Macondo being the first—and follow with a production
facility if the oil and gas-bearing region revealed commercial potential. 26 The plan was to drill beyond the
primary target of approximately 18,400 feet to a total depth 20,200 feet to also assess the sections below
the target. 27 The water depth of the Gulf at the location was just short of 5,000 feet.
BP designed Macondo for use as a producing well if successful, but the well was, in fact, exploratory
because of the uncertainty about both the type and quantity of the oil and gas (hydrocarbons) present at
the site and the effort necessary to actually extract the oil and gas. If the well proved commercially viable,
data concerning the well’s geology and hydrocarbon properties would be collected and used to create a
production plan; alternatively, if the well was not viable, the data would be gathered to determine why the
commercial predictions failed. 28
Ultimately, as BP hoped, the Macondo well was appropriate for conversion to a producing well.

13
Macondo Investigation Report Volume 1 June 5, 2014

1.3.1 The Deepwater Horizon Rig


The DWH was a mobile offshore drilling unit (MODU) measuring 396 by 256 feet 29,a with housing
capacity for 146 people. 30 The DWH was a dynamically positioned rig that used global satellite
technology and thrusters to maintain position over the well rather than cables and anchors to hold it in
place. 31 By their very nature, offshore rigs like the Deepwater Horizon MODU face unique hazards
compared to their onshore counterparts. For example, on a rig a substantial number of workers occupy a
small living and working area, where escape and rescue from a catastrophic event, such as a hazardous
chemical release, fire, or explosion, are inherently more difficult due to the offshore location.

1.3.2 The Crew


At the time of the blowout, 126 people employed by 13 different companies were onboard the DWH
(Table 1-2).

32
Table 1-2. Personnel On Board on April 20 by Company

Eighteen of these individuals are typically identified as the crew intimately involved in the drilling and
temporary abandonment activities or having direct oversight responsibilities for those activities. (Table

a
For comparison purposes, the dimensions of a National Football League football field are 360 by 160 feet.

14
Macondo Investigation Report Volume 1 June 5, 2014

1-3 provides additional details relevant in subsequent volumes of the CSB Macondo Investigation
Report.)

33
Table 1-3. Well Control Personnel On Board the Rig on April 20, 2010

1.4 Planning the Well


The goal of drilling a deepwater well is to create a pathway between oil and gas reservoirs trapped
beneath the seafloor and the surface. a To reach the reservoirs, a hole (the wellbore) is drilled through

a
The general references describing drilling used in this chapter include Van Dyke, K. Fundamentals of Petroleum,
4th ed. Austin: University of Texas, 1997; Offshore Well Construction, 1st ed. Austin: University of Texas, 2005;
and A Primer of Oilwell Drilling, 7th ed. Austin: University of Texas, 2008. Readers may also review the Chief
Counsel’s report by the National Commission, which offers more detail than this report, but still at an introductory
level. See the National Commission on the BP Deepwater Horizon Oil Spill and Offshore Drilling, Chief
Counsel’s Report: The Gulf Oil Disaster,
http://www.oilspillcommission.gov/sites/default/files/documents/C21462-408_CCR_for_web_0.pdf (February
14, 2011). Accessed August 14, 2013.

15
Macondo Investigation Report Volume 1 June 5, 2014

various layers (formations) of rocks and/or unconsolidated sediments such as sand, shale, a gravel or silt. b
The formations, such as the target reservoir, are porous c and permeable, and they contain water, oil,
and/or gas which are under pressure. An unplanned flow of these fluids into the wellbore is called a
“kick,” which, if not managed, can progress to a “blowout,” the uncontrolled release of oil and gas
(hydrocarbons) from the well. This is most dangerous for people and property when the hydrocarbons
release onto the drilling facility, where ignition sources are present.
Thus, the flammable and potential explosive nature of oil and gas contained in the reservoir(s) of a
potential well is one of the most significant major hazards that must be managed throughout the lifecycle
of a drilling and production operation, beginning with the planning stages of the well. Part of the planning
process is a well-specific hazard analysis of the operation to determine the appropriate safeguards for
mitigating the hazard and control of the risks. (Volume 2, Chapters 4 and 5, of the CSB Macondo Incident
Investigation Report addresses the hazard analysis issue further).

1.5 Incident Description


On April 20, 2010, the drilling activities were completed after several productive oil and gas zones had
been discovered at Macondo, and the crew was performing a series of steps to temporarily abandon the
well. Abandonment activities would essentially plug the well so that the rig could move on to a new
drilling site and a production installation could return to the Macondo site at a later date to extract the
hydrocarbons.
BP’s temporary abandonment plan d called for removal of most of drilling fluid column in the well before
installation of a surface cement plug. e Earlier, a critical cement barrier intended to keep the hydrocarbons
below the seafloor had not been effectively installed at the bottom of the well, and the cement integrity
was not not conducted in a way that provided a clear “pass” or “fail” result to the workers. Both BP and
Transocean personnel on the DWH rig misinterpreted the test results concerning the cement integrity,
leading them to erroneously believe that the hydrocarbon bearing zone at the bottom of the well had been
sealed when in fact it was not. When the drilling fluid column was removed, pressure gradually reduced
above the hydrocarbon reservoir at the bottom of the well. Eventually, this action allowed hydrocarbons
to flow past the failed cement barrier and up toward the DWH. Meanwhile, because of a failure to
recognize the increase in fluids from the well, the crew continued to remove more of the drilling fluid
column, causing both the hydrocarbon influx rate into the well and movement of hydrocarbons toward the
rig to increase. The hydrocarbons continued to flow from the reservoir for almost an hour without human
intervention or the activation of automated controls.

a
Shale is a common deepwater rock.
b
Silt is loose sedimentary material of a size between sand and clay.
c
Porous formations constitute rock or other material that contains small spaces or holes that can hold liquids.
d
A well may be temporarily sealed with cement or mechanical plugs to allow removal of the blowout preventer and
departure of the drilling rig.
e
Cement plugs are portions of cement put into a wellbore to seal it. “Surface” is typically used to refer to the most
shallow cement plug used in a well.

16
Macondo Investigation Report Volume 1 June 5, 2014

The force of the hydrocarbons accelerating up the mile-long drilling riser a resulted in well fluids gushing
onto the drilling rig floor—a blowout. At this point, the crew took action to activate the blowout preventer
(BOP). This safety critical element, b located at the sea floor, temporarily sealed the well but could not
stop the hydrocarbons that had already traveled above the BOP from releasing onto the rig.
Once oil and gas had risen above the BOP, the only action the crew could take was to divert it to a safer
location than onto the rig floor. However, the flow from the diverter had been preset to route well fluids
to the mud-gas separator rather than over the side of the Deepwater Horizon. The mud-gas separator was
rapidly overwhelmed, as it was not designed to safely handle a flow of the magnitude of the Macondo
blowout. As a result, drilling mud and hydrocarbons rained down onto the rig floor. The hydrocarbons
found an ignition source, and explosions and fire ensued.
As discussed in detail in Volume 2, both manual and automated emergency systems within the blowout
preventer were activated in an attempt to shear the drillpipe and seal the well. However, pressures in the
well had caused the drillpipe to buckle, which inhibited the BOP from sealing the well.
The explosion and fire resulted in 11 crew members suffering fatal injuries and 17 others being critically
injured. 34 The Deepwater Horizon rig sank on April 22, 2010, about 36 hours after the initial explosions. 35
Approximately 5 million barrels of oil spilled into the Gulf of Mexico. c
Ultimately, in the hours leading up to the incident, no effective barriers were in place to prevent or
mitigate a blowout. The physical barriers intended to prevent such a disaster were not properly designed
for the well conditions, constructed, tested, or maintained, or they had been removed. The management
systems intended to ensure the required functionality, availability, and reliability of these barriers were
inadequate. An examination of the treatment of safety critical equipment and tasks at Macondo, such as
the BOP and cement barrier testing, reveals opportunities for further improvements in effective barrier
safety management. Furthermore, a comparison of the US regulatory requirements for these safety critical
elements to other international offshore regimes illustrates gaps in the US model and offers support for
further post-Macondo changes to the US offshore safety regulations.

a
A drilling riser is a large diameter pipe that connects a drilling rig to the BOP attached to the wellhead.
b
As defined by the UK Health and Safety Executive, safety critical elements are controls (hardware, people
systems, or software) or tasks whose failure could cause or contribute to a major accident or which the purpose is
to prevent or limit the effects of a major accident; UK Offshore Installations (Safety Case) Regulations 2005, 2
Interpretation , http://www.legislation.gov.uk/uksi/2005/3117/pdfs/uksi_20053117_en.pdf.
c
The total volume of oil spilled has yet to be determined by the U.S. District Court in the multidistrict litigation, but
estimates range from approximately 3.2 million to 5 million barrels. In Re: Oil Spill by the Oil Rig “Deepwater
Horizon” in the Gulf of Mexico, on April 20, 2010, U.S. Br. 1, January 27, 2014, ECF No. 12237; BP Br. 29,
January 24, 2014, ECF. No. 12227.

17
Macondo Investigation Report Volume 1 June 5, 2014

2.0 Deepwater Drilling and Temporary Abandonment of the


Macondo Well a
Drilling a well requires controlling the pressure exerted by
oil and gas trapped within the reservoirs that drillers are Chapter 2.0 Overview
trying to reach. The pressure, known as pore pressure or
formation pressure, is created in part by the weight of the This chapter focuses on the issue of
water and rock pushing down from above. controlling formation pressures of the
well during the deepwater drilling
Pore pressure needs to be controlled throughout the subsea
and temporary abandonment
drilling and well completion operations to minimize the
operations at Macondo. Basic drilling
occurrence of well kicks—Macondo was a particularly
and completion activities are
challenging well in this regard. Well control actions must be
described, integrated with facts
initiated before a kick develops into an uncontrolled
pertaining to the events of April 20,
hydrocarbon release into the environment—a blowout—
2010. This information provides the
because gas that travels up the riser and is released onto the
foundation for the CSB’s technical,
rig where ignition sources are present, is a serious threat to
systemic, organizational, and
people.
regulatory analyses in subsequent
To control pore pressures and prevent kicks during drilling report volumes.
and completion activities, drillers commonly use a variety of
physical barriers, including:
• the weight of a column of fluid that fills the hole being drilled (wellbore) and the riser
• steel casing and the cement used to secure it for protecting the sides of the wellbore and
preventing hydrocarbons from entering
• cement placed at the bottom of a well to seal the hydrocarbon bearing zone
• a “surface” cement plug—cement placed in a shallow location in the well close to the surface at
the seafloor—to seal the wellbore
• drilling equipment known as a blowout preventer (BOP).
Each of these barriers is discussed briefly throughout this chapter, but the BOP receives additional in-
depth discussion in Volume 2 of the CSB Macondo Investigation Report. An introductory discussion of
these barriers is necessary for a broader examination of the systemic, human, organizational, and
regulatory issues that contributed to the incident. This chapter provides a basic description of some

a
This section focuses on deepwater drilling and temporary abandonment operations from a floating vessel, such as
the Deepwater Horizon rig. General references describing drilling include Van Dyke, K. Fundamentals of
Petroleum, 4th ed. Austin: University of Texas, 1997; Offshore Well Construction, 1st ed. Austin: University of
Texas, 2005; and A Primer of Oilwell Drilling, 7th ed. Austin: University of Texas, 2008. The Chief Counsel’s
report by the National Commission offers more detail than this report, but still at an introductory level. See the
National Commission on the BP Deepwater Horizon Oil Spill and Offshore Drilling Chief Counsel’s Report: The
Gulf Oil Disaster, http://www.oilspillcommission.gov/sites/default/files/documents/C21462-
408_CCR_for_web_0.pdf (February 14, 2011). Accessed August 14, 2013.

18
Macondo Investigation Report Volume 1 June 5, 2014

underlying premises to offshore drilling and completion operations and the essential concepts that support
the CSB’s investigative analysis in subsequent volumes.

2.1 Controlling Pore Pressures with Drilling Fluids


The primary barrier used to control pore pressures while drilling is a column of fluid that fills the
wellbore and the riser. Various drilling fluids, such as water or water-based and oil-based drilling muds, a
are circulated down from the rig through the pipe used to drill the wellbore (drillpipe) and the drill bit
used to cut through the formations to create the wellbore. Afterwards, the same fluids carry the crushed
rock back around the drill bit up through the annular space between the drillpipe and wellbore (also called
the annulus) to the surface via the riser, a large diameter pipe that connects a drilling rig to the BOP
attached to the wellhead (Figure 2-1). The column of drilling fluid exerts hydrostatic pressure b on the
walls of the wellbore. When the hydrostatic pressure in the wellbore is greater than the pore pressure, the
well is said to be overbalanced. In this instance, the fluid column acts as a barrier by pushing back against
the pore pressure, thus keeping the hydrocarbons from entering into the wellbore. Keeping a well in this
overbalanced state is typically the primary means for controlling pore pressures and the basis of well
control. If for some reason the hydrostatic pressure drops below the pore pressure, the well becomes
underbalanced and a kick can occur.
Alternatively, if the pressure exerted by the drilling fluids is too high, it can exceed the “fracture
gradient,” or the pressure at which the walls of the exposed wellbore break down and drilling mud is lost
into the formation. c These “lost returns” or “lost circulation” events are costly due to expenses related to
the lost drilling mud, and they are also dangerous due to the resulting drop in the height of the drilling
fluid column, which may result in an underbalanced state if a sufficient volume of the fluid column is lost
to the formation and not replaced at the surface fast enough. This, too, can potentially result in a kick or,
even worse, a blowout. d

a
Drilling muds are liquids and mixtures of liquids and solids circulated through the wellbore during drilling
operations.
b
Hydrostatic pressure is exerted by liquid at a given point as a result of the weight of the column of fluid above it.
c
The total pressure exerted by the drilling fluids will be a combination of the hydrostatic pressure and additional
pressure generated when the drilling fluids are circulated through the annulus. This can be expressed as
“equivalent circulating density” (ECD).
d
Closing the BOP on a combined lost circulation event and well kick can lead to an underground blowout. In some
cases, an underground blowout can cause pressures to exceed either casing failure pressures or the burst pressure
of pressure relief valves known as rupture disks, which are designed to fail before the casing. (See Section 2.2 for
casing description). An underground blowout was a serious concern at Macondo because if the installed rupture
disks had burst due to the high blowout or kill pressures, a well flow up the annulus ultimately could have resulted
in a surface blowout. See National Commission on the BP Deepwater Horizon Oil Spill and Offshore Drilling,
Chief Counsel’s Report: The Gulf Oil Disaster, Chapter 4.2,
http://www.oilspillcommission.gov/sites/default/files/documents/C21462-408_CCR_for_web_0.pdf (February
14, 2011), Accessed August 14, 2013.

19
Macondo Investigation Report Volume 1 June 5, 2014

Figure 2-1. During drilling, mud travels down the drillpipe, through the drill bit, and then back up the
annulus (yellow), carrying crushed rock back to the rig.

20
Macondo Investigation Report Volume 1 June 5, 2014

Drilling fluid is formulated as a barrier to keep the pressure at the bottom of the well within the drilling
window or margin, which the International Association of Drill Contractors (IADC) defines as “the
difference between the maximum pore pressure and the minimum effective fracture pressure.”36 In its
well control manual in effect at the time of the Macondo incident, Transocean stated well planning is
highly influenced by the drilling margin, as it dictates how drilling is conducted to achieve an efficient
and safe operation. 37
Applications to drill in the Gulf of Mexico must include the planned drilling margin, 38 which is usually
submitted in graphic form. Figure 2-2 represents a simplified drilling margin plot and demonstrates that
the fracture gradient and the pore pressure typically increase as well depth increases, but not necessarily
uniformly or constant relative to one another. The planned drilling margin is given in terms of equivalent
mud density, reported in pounds per gallon (ppg), so that pressure can easily be related to the density of
the drilling mud column. Mud weight is formulated to remain within the drilling margin to keep well
fluids contained and to avoid fracturing the walls of the wellbore, risking a lost circulation event and
potentially a subsequent kick. Offshore US drilling regulations state: “[w]hile drilling, you must maintain
the safe drilling margin identified in the approved APD [Application for Permit to Drill]. When you
cannot maintain this safe margin, you must suspend drilling operations and remedy the situation.” 39 The
regulations do not specify what the minimum drilling margin should be, but keeping the mud weight at
least 0.5 ppg under the fracture gradient is typically accepted practice. 40

21
Macondo Investigation Report Volume 1 June 5, 2014

Figure 2-2. A simplified drilling margin plot. The planned mud weight (red dashed line) is formulated to
remain less than the fracture gradient (green line) and greater than the pore pressure (black line). New
casing transitions (green diamonds) are installed when the fracture gradient is approached.

22
Macondo Investigation Report Volume 1 June 5, 2014

2.2 Controlling Pore Pressures with Casing and Cement


To avoid exceeding the fracture gradient, the crew drills a well until the total pressure exerted by the
drilling fluids approaches the fracture gradient, at which point steel casing lines the wellbore to cover the
weaker formations. a Among other purposes, 41 casing serves to strengthen the wellbore so that it does not
fracture or collapse during drilling. Casing is secured in a well by pumping cement into the annular space
between the casing and the formation, where it sets and hardens (Figure 2-3). The cement in the annulus
and at the bottom of the casing, referred to as the shoe track, should keep drilling fluids from flowing up
around the outside of the casing, thus protecting the wellbore, and it should prevent any hydrocarbons in
the surrounding formation from flowing into the well. Cement is a crucial physical barrier to secure the
integrity of the well, preventing ingress of hydrocarbons into the well and loss of well control. Yet, an
MMS study of offshore blowouts published in 2007 noted the most common contributing factor for
blowouts between 1992 and 2006 was cementing operations. 42 Accordingly, cementing operations need to
be designed and managed in a manner that does not assume a successful cement job.

a
“Casing” is a generic term for steel pipe. Formally, casing also refers to pipe if it extends up to the wellhead. A
section of pipe also can be hung from the bottom of a previous casing. In this case, it is called a “liner.” Liners can
hang from casing or from another liner. The intended effect on control of drilling margin is the same.

23
Macondo Investigation Report Volume 1 June 5, 2014

Figure 2-3. Cementing casing in place involves filling the annulus with cement above any hydrocarbon
bearing zones if they are present as well as a small length (30ˈ-90ˈ) in the shoe track.

After casing has been installed, heavier mud can then be introduced into the wellbore, and operations
continue by drilling past the cement at the bottom of casing. The steps observed in the red line of Figure
2-2 are points in the well where the intention is to install casing to protect the weaker formations higher
up in the well. Installing new casing can be exercised only a limited number of times because each new
installation has to fit down through the casings installed immediately before, so the new casing must be
smaller in diameter than the last. Few transitions can be made before the wellbore simply gets too narrow
for additional drilling. Current drilling mechanics and the size of well logging instrumentation limit the
minimum practical hole size to be a 6-inch diameter except in extraordinary circumstances.43
During the planning of the Macondo well, BP calculated how many times and at what depth to install a
casing or liner transitions. 44 When drilling the Macondo well, the crew encountered differences in the

24
Macondo Investigation Report Volume 1 June 5, 2014

predicted geology, which resulted in shallower-than-anticipated transitions and ultimately a shallower-


than-planned final depth. BP has acknowledged that the final section of the well was difficult to drill due
to a narrowing of the drilling margin as a result of an unusual reduction in the fracture gradient at the
bottom of the wellbore, 45 but the already small diameter casing prohibited installation of additional casing
large enough to drill further.
Thus, drilling stopped on April 9, 2010, at 18,360 feet below sea level, short of the original well planned
depth of 19,650. Despite this change, the well had already encountered a good productive hydrocarbon
region for later production. Once the hydrocarbon zone was reached, BP decided to plug and abandon the
well for later hydrocarbon extraction.
The process of preparing the well so that the drilling rig can depart until another rig or production facility
returns is called temporary abandonment. For temporary abandonment to occur, the well needs to be
sealed; until it is, the hazards of a well kick and blowout are still very real. US regulations require cement
to be placed at the bottom of the well and the installation of a surface “retrievable or a permanent-type
bridge plug or a cement plug at least 100 feet long in the inner-most casing” with the top of the plug
required to be “no more than 1,000 feet below the mud line [sea floor]” 46 unless the company seeks
approval for an alternative plan from the regulator. 47 At Macondo, BP gained approval to set a surface
plug at approximately 3,000 feet below the seafloor. a,48 In its request, BP acknowledged this was a deep
surface plug and stated it planned to extend the surface plug length to 300 feet rather than the minimum
requirement of 100 feet “to compensate for the added setting depth.” 49 In addition to choosing the deep
placement of the surface plug, BP also decided to set the surface plug in seawater rather than drilling
mud. b (Figure 2-4).
BP did not have a company standard for developing a temporary abandonment plan. For Macondo, BP
considered numerous temporary abandonment plan options in the week or so leading up to
implementation. These changes included the location of the surface plug, which ultimately affected the
negative pressure test conditions used to assess the bottom hole cement integrity (Section 2.3.1) and
displacement of the well.50 Many variations are possible for cement integrity testing, each with
advantages and disadvantages based on the particular circumstances of the well. (See Appendix 2-A,
Deepwater Horizon Blowout Preventer Failure Analysis, for details.) While the various temporary

a
This depth was three times the regulatory maximum listed in MMS regulations (30 C.F.R. § 250.1721(d), 2010).
The Application for Permit to Modify cites concerns with a piece of equipment called a lockdown sleeve (LDS)
for the deviation. Post incident, BP stated in its investigation report that the depth of the surface cement plug was
governed by the procedure for installing the LDS. The crew would hang 3,000 feet of pipe in the well to generate
the 100,000 lbs. of weight necessary for installing the lockdown sleeve (BP, Deepwater Horizon Accident
Investigation Report, September 8, 2010, p. 72). The Chief Counsel’s Report generated by the National
Commission has challenged this assertion, stating other means were available to generate the necessary weight
that would not have allowed the surface cement plug to be set more shallow (National Commission on the BP
Deepwater Horizon Oil Spill and Offshore Drilling, Chief Counsel’s Report: The Gulf Oil Disaster, February 14,
2011, p. 141).
b
See the panel discussion that BP, Transocean, and Halliburton participated in concerning setting cement plugs in
mud versus seawater, National Oil Spill Commission Meeting, November 8, 2010, pp. 209-216.
http://www.oilspillcommission.gov/sites/default/files/documents/Transcript-%20Meeting%205.pdf. Last accessed
July 25, 2013.

25
Macondo Investigation Report Volume 1 June 5, 2014

abandonment options BP explored improved the procedure, the CSB found no explicit risk assessment for
the final procedure used at Macondo.

Figure 2-4. The final Temporary Abandonment configuration intended to remove drilling mud down to
8,367 feet to install a cement plug in seawater.

2.2.1 Cement Integrity Testing and Final Displacement


US regulations require conducting a positive pressure test to verify that no leaks are in the well.a On the
day of the incident, the Deepwater Horizon drilling crew conducted a positive pressure test and

a
During a positive pressure test, a well is pressured up and then held in this condition to see if the pressure is
maintained, indicating no leaks in the casing. If a decrease in pressure is observed, regulations require that either
the well be re-cemented, the casing repaired, or additional casing installed to ensure the well is sealed. 30 CFR
§250.423 (2010 and 2012).

26
Macondo Investigation Report Volume 1 June 5, 2014

determined the Macondo well passed the test.51 A major limitation of a positive pressure test is that it
does not check the cement sealing off the hydrocarbon bearing zones at the very bottom of the well for
inward leakage. a Even though regulations at the time of the incident did not require a negative pressure
test, BP’s final temporary abandonment plan also called for one. b
A negative pressure test can assess the integrity of the bottom-hole cement. It simulates an underbalanced
well by displacing some of the heavy drilling mud from the well and closing the BOP to isolate the
bottom of the well from the hydrostatic pressure exerted by fluids above the BOP. Various methods are
available to accomplish the test, and the specific procedure was left to those planning the process. c Yet,
neither BP nor Transocean management provided the Deepwater Horizon crew with a negative pressure
test procedure that included acceptance criteria to confirm test success or actions to take if any deviations
occurred during the test, d and the risks associated with conducting the negative pressure test were not
formally assessed.
To prepare for the negative pressure test at Macondo, a drillpipe was lowered to the depth identified for
the bottom of the cement plug (Figure 2-4). A viscous and dense water-based Loss Circulation Material
(LCM) followed by seawater was pumped down the drillpipe to displace the mud by pushing it above the
BOP toward the rig. e After stopping displacement and closing the BOP, f the crew observed the pressures
and/or flow from the well four times over three hours. g Each time, they observed unexpected results, so

a
A positive pressure test ensures no outflow from the well into its surroundings. One way to conduct the test entails
closing the blind shear ram in the BOP (with no drillpipe present) and then pumping drilling mud down a pipe that
connects to the BOP below the closed ram to pressure up the well. Cement at the bottom of a well is usually
blocked from this pressure by a device known as a “wiper plug,” which is installed as part of the casing cement
job and which seals against outflow from the well.
b
Regulations have changed post incident to require the negative pressure test, 30 CFR §250.423(c) (2012).
c
Current regulations, 30 CFR §250.423(c), require the operator to submit a procedure and acceptance criteria for
approval.
d
For example, instructions from the Ops Note included a single sentence, “With seawater in the kill close annular
and do a negative test ... 2350 psi differential,” Email communication, “Ops Note,” April 20, 2010, BP-HZN-
BLY00071107, http://www.mdl2179trialdocs.com/releases/release201302281700004/Trocquet_David-
Depo_Bundle.zip, Exhibit 1992. Accessed December 10, 2013.
e
The Chief Counsel Report noted that BP chose to put the LCM into the well to avoid disposing the material as a
hazardous waste pursuant to the Resource Conservation and Recovery Act (National Commission on the BP
Deepwater Horizon Oil Spill and Offshore Drilling, Chief Counsel’s Report: The Gulf Oil Disaster, February 14,
2011, p. 151) . The LCM material had never been tested for this application, there was no operational reason to use
it, and the lost circulation material spacer was pumped into the well to avoid disposal of the material as a
hazardous waste pursuant to the Resource Conservation and Recovery Act. The viscous, gelling nature of the
LCM could have plugged a line the crew used to conduct the negative pressure test, greatly contributing to the
false positive interpretation of the test. See Appendix 2-A for more details.
f
Most likely the lower annular preventer was closed. Witnesses at the hearings before the Deepwater Horizon Joint
Investigation Team gave contradictory recollections: May 27, 2010, p. 36; May 28, 2010, p. 120; August 25,
2010, p. 272.
g
When displacement of the well was stopped to conduct the negative pressure test, as expected some trapped
pressure was in the drillpipe. The crew bled the pressure from the drillpipe, which should have resulted in a zero
pressure reading on the drillpipe. If the hydrocarbon bearing zone at the bottom of the well had been sealed, no
subsequent increase in pressure would have resulted. Pressure did increase and was bled two more times before

27
Macondo Investigation Report Volume 1 June 5, 2014

they made adjustments before deeming the well passed the final test. The crew’s actions suggest they did
not realize that the unexpected readings were indications of a failed negative pressure test and that
integrity of the cement had not been secured. (See Appendix 2-A for details.)
After the final negative pressure test was erroneously accepted as a “pass,” the Deepwater Horizon crew
continued the process of displacement, replacing the drilling mud in the wellbore and riser with seawater
in preparation to set the surface plug. Replacing dense drilling mud with seawater had the effect of
lowering the hydrostatic pressure on the bottom of the well. With the fluid column removed and no
surface plug yet set, the only means left for preventing the hydrocarbons from entering the riser and
eventually making their way up the well to the rig was detection of the kick by the crew and manual
activation of blowout prevention equipment to seal the well.a

2.3 Controlling Pore Pressures with a Blowout Preventer


If the drilling column fluid (mud weight) barrier and the cement barrier both fail, and the well is still open
(no plug installed), drilling crews depend on a blowout preventer (BOP) to control pore pressures. The
BOP has two primary roles during drilling and completion operations. First, it is a tool the drill crew
manually operates to control or regain control of the well during an initial kick by closing one or more
sealing elements. Second, it is an emergency response mitigation device with both manual and automatic
functions meant to shear drillpipe, seal the wellbore, and disconnect the rig from the well. A subsea BOP
(Figure 2-5) can be massive; the Deepwater Horizon BOP was nearly 57 feet tall and weighed
approximately 400 tons. 52 The BOP is anchored to the top of the well casing at the seabed b and is
connected to a drilling rig by a riser. Drilling equipment, drillpipe, tubulars, c and other tools used in the
drilling process are lowered from the rig, through the riser, through the blowout preventer, and into the
well.
While subsea BOPs share general physical characteristics, the actual configuration, the control system,
and the performance requirements are specific to each BOP. The Deepwater Horizon’s BOP was built by
Cameron and had been used on the DWH since the rig began its service in 2001. 53
The BOP components vary in their capabilities. Some seal the well around drillpipe, some seal open holes
(when no drillpipe is present), and others shear the drillpipe and seal the well. The arrangement of these
components within a BOP is based on the characteristics of the offshore operation and the anticipated

the crew used a lack of flow from the well as an indicator of a passed test despite a pressure increase that was
detected in the well.
a
Technically, mechanical float valves also are located at the bottom of the well installed as part of the production
casing. These valves (also called check valves) allow cement used to install casing to flow one way out the bottom
of the casing, but not back up into the casing once cement pumping stops. BSEE does not consider float valves by
themselves a mechanical barrier, but they can and often do hold pressure. Float valves cannot be tested
independently. Thus, they cannot be considered a reliable device, but they have to fail for the well to flow.
b
The National Commission generated a series of animations to depict not only BOP equipment placement and
activation but also helpful drilling practices. See links to animations at http://www.oilspillcommission.gov/chief-
counsels-report. Last accessed July 30, 2013.
c
As defined by Schlumberger Oil Field Glossary (http://www.glossary.oilfield.slb.com/search.cfm), a tubular is “A
generic term pertaining to any type of oilfield pipe, such as drillpipe, drill collars, pup joints, casing, production
tubing and pipeline.”

28
Macondo Investigation Report Volume 1 June 5, 2014

complexities. These components are identified in Figure 2-5, and the specific details of these components
on the Deepwater Horizon BOP are discussed in more detail in Volume 2.

Figure 2-5. The Deepwater Horizon BOP

29
Macondo Investigation Report Volume 1 June 5, 2014

When drilling mud and hydrocarbons began pouring out of the well and onto the Deepwater Horizon, the
drilling crew activated a component called an annular preventer, which should have sealed the space
around the drillpipe and prevented further hydrocarbons from rising above the BOP. a However, well data
indicate that this component failed to seal the well. b Not only did the riser fluids—the hydrocarbons,
drilling mud and seawater—that already passed above the BOP continue to travel up the riser and release
onto the rig floor, but the riser was also being replenished by the flow of even more hydrocarbons through
the leaking component.
Immediately after activating this component, the rig crew also closed the diverter at the top of the riser. 54
When the diverter shut, flow up the riser exiting onto the rig floor was redirected to the diverter piping.
The two potential piping destinations were overboard into Gulf waters or to the Mud-Gas Separator
(MGS). On the day of the incident, the diverter was directed to the MGS. Moments after the diverter was
closed, the MGS was overwhelmed and hydrocarbons began blowing out of four different exit points onto
the rig.
Pressure data c indicate that the crew closed at least one additional sealing component of the BOP called a
pipe ram, which successfully shut in the well but caused the pressure in the drillpipe to build substantially
as evidenced by the surface drillpipe pressure building. (See Volume 2, Section 2.3 for details.) Riser
fluids above the BOP continued to unload onto the rig floor, but their replenishment temporarily ceased.
About two minutes later, the first explosions occurred on the rig and data transmission from the rig to
shore ceased.
In the minutes following the explosion, a crew member pressed the Emergency Disconnect System (EDS)
button on the bridge BOP remote control panel. 55 This maneuver should have activated the BOP
components that would shear the drillpipe, seal the well, and disconnect the rig and riser from the BOP,
thus allowing the DWH to move away from the wellhead. However, there was no indication of EDS
actuation which was likely a result of the explosion damaging the rig-based BOP control systems and
power and communication lines between the rig and the BOP.
The explosion likely activated the AMF/deadman automatic emergency response system. This system
was meant to shear the drillpipe and seal the well, but as evident from the major oil spill that ensued, the
well remained unsealed. The likely activation of the AMF/deadman system and the failure of the BOP to
seal the well is discussed in detail in Volume 2 (Chapter 3) of the CSB Macondo Investigation Report.

a
Witness statements said that the bridge remote control panel indicated that the lower annular was closed. Hearing
before the Deepwater Horizon Joint Investigation, May 28, 2010, p. 145. However, upon recovery, the lower
annular was found open [Bureau of Ocean Energy Management Regulation and Enforcement (BOEMRE), March
11, 2011. Forensic Examination of Deepwater Horizon Blowout Preventer, Report No. EP030842.]
http://www.uscg.mil/hq/cg5/cg545/dw/exhib/DNV%20Report%20EP030842%20for%20BOEMRE%20Volume%
20I.pdf, p. 27. Accessed August 14, 2013.
b
If the annular preventer had sealed, the drillpipe pressure at the surface would have rapidly increased to 5,000+
psig (as when the upper pipe ram sealed at 9:47 p.m.). Rather, the drillpipe pressure fluctuated between 1,800 and
400 psig in this time period.
c
See Appendix 2-A and the National Commission on the BP Deepwater Horizon Oil Spill and Offshore Drilling,
Chief Counsel’s Report: The Gulf Oil Disaster,
http://www.oilspillcommission.gov/sites/default/files/documents/C21462-408_CCR_for_web_0.pdf (February 14,
2011). Accessed August 14, 2013, p.191.

30
Macondo Investigation Report Volume 1 June 5, 2014

2.4 Consequences of Explosion and Fire


Of the Deepwater Horizon crew, 11 suffered fatal injuries from the explosion and fire and 17 others were
critically injured. 56 The Deepwater Horizon rig sank on April 22, 2010, about 36 hours after the initial
explosions. 57 Approximately 5 million barrels of oil were spilled into the Gulf of Mexico. a

a
The total volume of oil spilled has yet to be determined by the U.S. District Court in the multidistrict litigation, but
estimates range from approximately 5 million barrels to 3.2 million barrels. In Re: Oil Spill by the Oil Rig
“Deepwater Horizon” in the Gulf of Mexico, on April 20, 2010, U.S. Br. 1, Jan. 27, 2014, ECF No. 12237; BP Br.
29, Jan. 24, 2014, ECF. No. 12227.

31
Macondo Investigation Report Volume 1 June 5, 2014

References

1
BP, “Exploration and Production,” http://www.bp.com/en/global/corporate/about-bp/bp-worldwide/bp-in-
america/our-us-operations/exploration-and-production.html. Retrieved November 12, 2013.
2
Transocean, http://www.deepwater.com/fw/main/Contract-Drilling-276.html. Retrieved November 12, 2013.
(Website link no longer active.)
3
Proxy Statement and 2012 Annual Report, Transocean, p. AR-9, http://phx.corporate-
ir.net/External.File?item=UGFyZW50SUQ9MTc4NzQ5fENoaWxkSUQ9LTF8VHlwZT0z&t=1.Retrieved
November 1, 2013.
4
Transocean Drilling Contract for the Deepwater Horizon, 1998,
http://www.mdl2179trialdocs.com/releases/release201305171200030/TREX-004271.pdf. Retrieved December 5,
2013.
5
Transocean Drilling Contract for the Deepwater Horizon, 1998,
http://www.mdl2179trialdocs.com/releases/release201305171200030/TREX-004271.pdf. Retrieved December 5,
2013.
6
Transocean Drilling Contract for the Deepwater Horizon, 1998, BP-HZN-M8100021478,
http://www.mdl2179trialdocs.com/releases/release201305171200030/TREX-004271.pdf. Retrieved December 5,
2013.
7
Transocean Drilling Contract for the Deepwater Horizon, 1998, BP-HZN-M8100021480,
http://www.mdl2179trialdocs.com/releases/release201305171200030/TREX-004271.pdf. Retrieved December 5,
2013.
8
Contract for Gulf of Mexico Strategic Performances Unit Offshore Well Services between BP Exploration and
Production, Inc. and Halliburton Energy Services, Inc., BP-HZN-CSB00175428 - BP-HZN-CSB00175972.
9
BP Annual Report and Form 20-F 2012, p. 55.
http://www.bp.com/content/dam/bp/pdf/investors/BP_Annual_Report_and_Form_20F_2012.pdf. Retrieved
November 12, 2013; http://www.bp.com/en/global/corporate/about-bp/bp-worldwide/bp-in-america/our-us-
operations/refining.html. Retrieved November 12, 2013; “BP at a Glance,”
http://www.bp.com/sectiongenericarticle.do?categoryId=3&contentId=2006926. Retrieved November 12, 2013;
Proxy Statement and 2012 Annual Report, Transocean, pp. AR-7 & AR-9, http://phx.corporate-
ir.net/External.File?item=UGFyZW50SUQ9MTc4NzQ5fENoaWxkSUQ9LTF8VHlwZT0z&t=1. Retrieved
November 12, 2013; 2012 Annual Report, Halliburton, p. 38, http://phx.corporate-
ir.net/External.File?item=UGFyZW50SUQ9MTc2OTU5fENoaWxkSUQ9LTF8VHlwZT0z&t=1, Retrieved
November 12, 2013; http://www.halliburton.com/en-US/about-us/history-of-halliburton-of-halliburton.page?node-
id=hgeyxt5y; 2012 Annual Report, Cameron, pp 29, http://investors.c-a-
m.com/file.php/88/2012+Annual+Report_1fc62ad8-a436-4016-bd33-82432de12d66.pdf. Retrieved November 12,
2013.
10
U.S. Department of Interior, “Salazar Divides MMS’s Three Conflicting Missions,”
http://www.doi.gov/news/pressreleases/Salazar-Divides-MMSs-Three-Conflicting-Missions.cfm. Retrieved
December 12, 2012.
11
The Secretary of the Interior, Order No. 3299, Establishment of the Bureau of Ocean Energy Management, the
Bureau of Safety and Environmental Enforcement, and the Office of Natural Resources Revenue, May 19, 2010,
http://www.doi.gov/deepwaterhorizon/loader.cfm?csModule=security/getfile&PageID=32475. Retrieved December
5, 2013.
12
Bureau of Safety and Environmental Engineering, “BSEE History,” http://www.bsee.gov/About-BSEE/BSEE-
History/Reorganization/Reorganization.aspx. Retrieved December 12, 2012.

32
Macondo Investigation Report Volume 1 June 5, 2014

13
Secretary of the Interior, Order No. 3302, Change of the Name of the Minerals Management Service to the Bureau
of Ocean Energy Management, Regulation and Enforcement, June 18, 2010,
http://www.doi.gov/deepwaterhorizon/loader.cfm?csModule=security/getfile&PageID=32475. Retrieved December
5. 2013.
14
Bureau of Safety and Environmental Engineering, “BSEE History,” http://www.bsee.gov/About-BSEE/BSEE-
History/index.aspx. Retrieved 12 December 2012.
15
Oil and Gas Sulphur Operations in the Outer Continental Shelf—Increased Safety Measures for Energy
Development on the Outer Continental Shelf; Final Rule, Docket ID BOEM–2010–0034, 75 Federal Register 198
(October 15, 2010), pp. 63,345-63,377.
16
Oil and Gas and Sulphur Operations in the Outer Continental Shelf—Increased Safety Measures for Energy
Development on the Outer Continental Shelf; Final Rule, Docket ID BOEM–2012–0002, 77 Federal Register 163
(August 22, 2012), pp. 50,856-50,901.
17
Final Rule, Oil and Gas and Sulphur Operations in the Outer Continental Shelf—Safety and Environmental
Management Systems, 75 Federal Register (October 15, 2010), p. 63,610.
18
Final Rule, Oil and Gas and Sulphur Operations in the Outer Continental Shelf—Revisions to Safety and
Environmental Management Systems, Docket ID: BSEE-2012-0011, 78 Federal Register 66 (April 5, 2013), pp.
20,423-20,443.
19
Minerals Management Service, High Bids Ranked by Bid Amount, Mar.19, 2008; (OCS Number G32306),
http://www.boem.gov/uploadedFiles/BOEM/Oil_and_Gas_Energy_Program/Leasing/Regional_Leasing/Gulf_of_M
exico_Region/lsesale/206/rpt4_206.pdf. Lease ownership was shared with two other companies, Anadarko
Petroleum (25%) and MOEX Offshore (10%); Macondo Prospect Well Participation Agreement Deepwater Gulf of
Mexico (Exhibit 2852), http://www.mdl2179trialdocs.com/releases/release201302281700004/Strife_Stuart-
Depo_Bundle.zip.
20
Application for Permit to Drill a New Well Approval, Lease G32306, Area/Block MC 252. Publically accessed at
http://www.mdl2179trialdocs.com/releases/release201302281700004/TREX-04021.pdf.
21
MMS Control Number N-09349 (BP-HZN-CSB00093568), April 6, 2009.
http://www.defenders.org/sites/default/files/publications/gulf_oil_disaster_complaint_exhibit_3_plan.pdf.;
Application for Permit to Drill a New Well Approval, Lease G32306, Area/Block MC 252. Publically accessed at
http://www.mdl2179trialdocs.com/releases/release201302281700004/TREX-04021.pdf.
22
Transocean, IADC Daily Drilling Report, Marianas, Report No.7 (October 6, 2009); Transocean, IADC Daily
Drilling Report, Marianas, Report No.30 (October 29, 2009).
23
Transocean, IADC Daily Drilling Report, Marianas, Report No.40 (November 8, 2009). BP-HZN-CSB00180108;
Transocean, IADC Daily Drilling Report, Signal Shipyard, Report No.1 (November 27, 2009). TRN-USCG_MMS-
00011799
24
Transocean, IADC Daily Drilling Report, Deepwater Horizon, Report No. 1 (January 31, 2010). TRN-USCG
MMS-00011510- TRN-USCG MMS-00011513
25
Transocean, IADC Daily Drilling Report, Deepwater Horizon, Report No.12 (February 11, 2010). BP-HZN-
CSB00055037- BP-HZN-CSB00055041
26
Initial Exploration Plan, Mississippi Canyon Block 252, OCS-G 32306 (Exhibit 6181). Publicly accessed at
http://www.mdl2179trialdocs.com/releases/release201302281700004/Tooms_Paul-Depo_Bundle.zip.
27
Application for Permit to Drill a New Well Approval, Lease G32306, Area/Block MC 252. Publicly accessed at
http://www.mdl2179trialdocs.com/releases/release201302281700004/TREX-04021.pdf , confirmed with CSB
interview.
28
Internal BP document, Gulf of Mexico SPU Well Planning Process Macondo, Wells Decision Support Package,
Stage Gate 1, 4/14/2009. (BP-HZN-CSB00182207)

33
Macondo Investigation Report Volume 1 June 5, 2014

29
Transocean Website, Fleet Specifications, Retrieved June 9, 2010. (Internet link no longer active.)
30
Deepwater Horizon Equipment List, April 27, 2009 (BP-HZN-CSB00020850).
31
Transocean Drilling Contract for the Deepwater Horizon, 1998. Publicly accessed at
http://www.mdl2179trialdocs.com/releases/release201305171200030/TREX-004271.pdf. Retrieved December 5,
2013.
32
Transocean Personnel-on-Board as of 20 Apr 2010 17:09:15 (TRN-USCG_MMS-00030435 – 00030441);
confirmed accurate with Weatherford September 1, 2010 response to the CSB interrogatory subpoena request for
information concerning personnel on board.
33
Transocean Personnel-on-Board as of 20 Apr 2010 17:09:15 (TRN-USCG_MMS-00030435 – 00030441);
[Persons on Board (POB); Well Control Handbook, Issue 3, rev.1, March 31, 2009 [TREX 1454]; Macondo Well
Incident – Transocean Investigation Report, Volume 1, p.17; Deepwater Horizon Operations Integrity Case, Section
2,Transocean Management System—HSE Management, Issue 1 (March 1, 2008) [TRN-MDL-02865361]; Contract
for Gulf of Mexico Strategic Performance Unit Offshore Well Services between BP Exploration and Production,
Inc., and Halliburton Energy Services, Inc., Section 3, Appendix 5, p.121 [BP-HZN-2179MDL00335470].
34
BP plc (BP), Deepwater Horizon Accident Investigation Report, September 8, 2010,
http://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&cts=1331666404195&ved=0CCkQFjAA
&url=https%3A%2F%2Fptop.only.wip.la%3A443%2Fhttp%2Fwww.bp.com%2Fliveassets%2Fbp_internet%2Fglobalbp%2Fglobalbp_uk_english%2Finci
dent_response%2FSTAGING%2Flocal_assets%2Fdownloads_pdfs%2FDeepwater_Horizon_Accident_Investigatio
n_Report.pdf&ei=x55fT7qYJunIsQKFqPSMCA&usg=AFQjCNE4cEa7fTYS0DYjDfGY60zekb6cqw. Accessed
March 12, 2012, and p. 9. Accessed August 14, 2013.
35
National Commission on the BP Deepwater Horizon Oil Spill and Offshore Drilling, Chief Counsel’s Report: The
Gulf Oil Disaster, February 17, 2011, p. 18,
http://www.oilspillcommission.gov/sites/default/files/documents/C21462-408_CCR_for_web_0.pdf. Accessed
August 14, 2013.
36
IADC, http://www.iadclexicon.org/drilling-margin/. Accessed May 28, 2014.
37
Transocean, Well Control Handbook - Level: L1B, Issue #3, Revision #1 - HQS-OPS-HP-01, pp BP-HZN-
2179MDL00330790. Publicly accessed at
http://www.mdl2179trialdocs.com/releases/release201303071500008/TREX-00596.pdf.
38
§250.414 (c) (2010 and 2012).
39
§250.427(b) (2010 and 2012).
40
Department of the Interior, Report Regarding the Causes of the April 20, 2010 Macondo Well Blowout, September
14, 2011, http://docs.lib.noaa.gov/noaa_documents/DWH_IR/reports/dwhfinal.pdf. Accessed December 9, 2013.
41
Offshore Well Construction, 1st ed. Austin: University of Texas, 2005: p. 3.1; R. Mitchell and S.Miska,
Fundamentals of Drilling Engineering, Society of Petroleum Engineers, 2011: p. 385.
42
D. Izon, E.P. Danenberger, and M. Mayes, “Absence of Fatalities in Blowouts Encouraging in MMS Study of
OCS Incidents, 1992 – 2006,” Drilling Contractor, July/August 2007, pp.84-90.
43
S. Christman, Email and telephone communications (2013).
44
BP p.l.c., Deepwater Horizon Accident Investigation Report, September 8, 2010, p. 16,
http://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&cts=1331666404195&ved=0CCkQFjAA
&url=https%3A%2F%2Fptop.only.wip.la%3A443%2Fhttp%2Fwww.bp.com%2Fliveassets%2Fbp_internet%2Fglobalbp%2Fglobalbp_uk_english%2Finci
dent_response%2FSTAGING%2Flocal_assets%2Fdownloads_pdfs%2FDeepwater_Horizon_Accident_Investigatio
n_Report.pdf&ei=x55fT7qYJunIsQKFqPSMCA&usg=AFQjCNE4cEa7fTYS0DYjDfGY60zekb6cqw. Accessed
March 12, 2012.

34
Macondo Investigation Report Volume 1 June 5, 2014

45
BP p.l.c., Deepwater Horizon Accident Investigation Report, September 8, 2010, p. 33,
http://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&cts=1331666404195&ved=0CCkQFjAA
&url=https%3A%2F%2Fptop.only.wip.la%3A443%2Fhttp%2Fwww.bp.com%2Fliveassets%2Fbp_internet%2Fglobalbp%2Fglobalbp_uk_english%2Finci
dent_response%2FSTAGING%2Flocal_assets%2Fdownloads_pdfs%2FDeepwater_Horizon_Accident_Investigatio
n_Report.pdf&ei=x55fT7qYJunIsQKFqPSMCA&usg=AFQjCNE4cEa7fTYS0DYjDfGY60zekb6cqw. Accessed
March 12, 2012.
46
30 C.F.R. § 250.1721(d) (2012).
47
30 C.F.R. § 250.1721(d) (2012).
48
Application for Permit to Modify, Lease G32306, Area/Block MC 252,
http://www.mdl2179trialdocs.com/releases/release201305171200030/TREX-004032.pdf. Accessed August 8, 2010.
49
Application for Permit to Modify, Lease G32306, Area/Block MC 252,
http://www.mdl2179trialdocs.com/releases/release201305171200030/TREX-004032.pdf. Accessed August 8, 2010.
50
Internal BP email, http://www.mdl2179trialdocs.com/releases/release201303141200012/TREX-00537.pdf.
Accessed August 8, 2010; Internal BP email,
http://www.mdl2179trialdocs.com/releases/release201303141200012/TREX-00097.pdf. Accessed August 8, 2010;
Application for Permit to Modify, Lease G32306, Area/Block MC 252,
http://www.mdl2179trialdocs.com/releases/release201305171200030/TREX-004032.pdf. Accessed August 8, 2010;
Macondo Drilling Production lnterval BP01 rev1,
http://www.mdl2179trialdocs.com/releases/release201303141200012/TREX-00836.pdf. Accessed August 8, 2010;
Macondo Drilling Production lnterval BP01 rev2,
http://www.mdl2179trialdocs.com/releases/release201303141200012/TREX-00545.pdf. Accessed August 8, 2010;
Transocean report, pp. 80-86, MC 252 #1 STOOBP01 - Macondo Prospect; 7" x 9-7/8" Interval; Version H.1, April
12; p. 10; BP-HZN-CSB00022750; Emails, February 28. Fowler to Stoltz, et. al., and replies; BP-HZN-
BLY00062447; Email, April 14, 2:07 p.m.: Morel to Wilson and Sepulvado; BP-HZN-CSB00160178; MC 252 #1
STOOBP01 - Macondo Prospect; 7" x 9-7/8" Interval, Version H.2, April 15; p. 8; BP-HZN-C S B00027980; MMS
Form 124 APM; MC 252 #1; Temporary Abandonment Procedure _RevA.doc 4/16; BP-HZN-CSB00163048;
Email, April 18, 10:37 a.m.: Morel to Guide, and reply; BP-HZN-BLY00070087; Email Ops note, April 20, 10:43
a.m.: Morel to Vidrine, et. al.; BP-HZN-CSB00056581.
51
Transocean, IADC Daily Drilling Report, Deepwater Horizon, Report No.34, April 20, 2010, 10:30 am – 12:00
p.m. TRN-USCG_MMS-00011644 - TRN-USCG_MMS-00011648.
52
Bureau of Ocean Energy Management Regulation and Enforcement (BOEMRE), March 11, 2011. Forensic
Examination of Deepwater Horizon Blowout Preventer, Report No. EP030842, p. 15.
http://www.uscg.mil/hq/cg5/cg545/dw/exhib/DNV%20Report%20EP030842%20for%20BOEMRE%20Volume%2
0I.pdf. Accessed March 12, 2012.
53
Transocean, Macondo Well Incident: Transocean Investigation Report Volume II, June 2011,
https://www.deepwater.com/_filelib/FileCabinet/pdfs/12_TRANSOCEAN_Vol_2.pdf, Appendix H. Accessed
December 9, 2013.
54
Hearing before the Deepwater Horizon Joint Investigation, May 29, 2010, p. 10.
(http://www.mdl2179trialdocs.com/releases/release201304110900026/TREX-37031.pdf, pp. BP-HZN-
BLY00377488 – 489. Accessed August 9, 2013. The interview notes state “gas buster,” which is another name used
for the MGS.
55
Hearing before the Deepwater Horizon Joint Investigation, May 28, 2010, p. 145; Hearing before the Deepwater
Horizon Joint Investigation, May 27, 2010, pp. 11 and 190.
56
BP plc (BP), Deepwater Horizon accident investigation report, September 8, 2010,
http://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=1&cts=1331666404195&ved=0CCkQFjAA
&url=https%3A%2F%2Fptop.only.wip.la%3A443%2Fhttp%2Fwww.bp.com%2Fliveassets%2Fbp_internet%2Fglobalbp%2Fglobalbp_uk_english%2Finci
dent_response%2FSTAGING%2Flocal_assets%2Fdownloads_pdfs%2FDeepwater_Horizon_Accident_Investigatio

35
Macondo Investigation Report Volume 1 June 5, 2014

n_Report.pdf&ei=x55fT7qYJunIsQKFqPSMCA&usg=AFQjCNE4cEa7fTYS0DYjDfGY60zekb6cqw. Accessed
March 12, 2012, and p. 9, accessed August 14, 2013.
57
National Commission on the BP Deepwater Horizon Oil Spill and Offshore Drilling, Chief Counsel’s Report: The
Gulf Oil Disaster, February 17, 2011, p. 18,
http://www.oilspillcommission.gov/sites/default/files/documents/C21462-408_CCR_for_web_0.pdf. Accessed
August 14, 2013.

36
Macondo Investigation Report Volume 1 June 5, 2014

37

You might also like