URS For Coating Machine
URS For Coating Machine
PRODUCTION DEPARTMENT
USER REQUIREMENT
SPECIFICATION
Page 1 of 11
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
CONTENT
S.No. Description
Page 2 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
Production
Production
Quality Assurance
Engineering
Head Engineering
Head Manufacturing
Head Quality
Page 3 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
2.0 Objective:
The purpose of this document is to ensure that all the critical aspects of the Equipment,
cGMP & Safety features have been considered in designing the equipment/instrument and is
properly documented.
3.0 Responsibilities:
In accordance with the document, following functions shall be responsible for initiation and
finalization of Equipment user requirement specification. When the work is carried by
contract/ consulting staff, all the work is to be performed under the oversight of
…………….
• To be reviewed by Head of the user department and functional department ( Engineering &
Quality assurance)
Page 4 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
07. Non metallic contact parts 1. Any material with food grade quality having no
Potential impact on the products.
2. Durable.
3. Must be easily cleanable.
08. Motor & Electrical installations As per machine requirement
09. Machine assemblies Must be covered with SS 304 with matt finish.
10. Machine adjustments Setting with Zero clearance with good accuracy.
11. Packaging & Transport Should be packed and transported in such a way to avoid
any damage during transportation.
12. No. of requirements 02
Page 5 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
7. Hot air with two stage Filtration unit & HEPA filter unit YES
6.1 Training
Page 6 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
Page 7 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
8.1 In accordance with cGMP guidelines the units must be easy to clean, to disinfect, and where
necessary, to sterilize.
8.2 The Supplier should guarantee that, if required, a service team can be on site within one
working day.
8.3 The design should be such as to allow mechanical cleaning of the surface and that the
cleanliness of the surface can be checked easily.
8.4 All machine parts, in particular instrumentation, should be constructed so that they can be
easily removed and calibrated.
8.5 All special tools required for running and maintenance should be best.
8.6 A spare parts delivery guarantee with in time.
10.1 Units described in the specific system requirements including all YES
necessary controls and instrumentation.
10.2 The complete mechanical and electrical installation. YES
10.3 The Connections to all the necessary utilities, exhaust, and Yes
waste lines necessary for its operation.
10.4 All piping and cabling of the units itself. YES
10.5 Wiring and cable run: all wiring and cable run is part of the YES
supply. ………… will supply the main power switches to be
located in correspondence to the electrical and control cabinets
delivered by the equipment supplier.
Page 8 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
10.10 All special tools necessary for use and maintenance of the YES
supplied equipment.
10.11 A complete set of two years spare parts should be listed quoted YES
and offered as option.
10.12 All test activities as specified in this document. YES
11.1 General
11.2.1 The commissioning tests will be carried out in accordance with a YES
written test plan developed by the supplier with clearly stated test
procedures and acceptance criteria.
11.2.2 The contractor will approve successfully completed tests and will YES
specify items requiring additional work. Representatives from
Page 9 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
Page 10 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
11.2.15 The commissioning should demonstrate that the system supplied by YES
the contractor has been properly installed and that the functions are
in accordance with ………………... User Requirements
specifications, Vendors System specifications Manuals and other
Documentation.
Page 11 of 12
PHARMA SCHOLARS
PRODUCTION DEPARTMENT
13.0 GAURANTEE/WARRANTEE
Page 12 of 12