Sabah and Labuan Grid Code 2017 - V3
Sabah and Labuan Grid Code 2017 - V3
2017)
Grid Code
For Sabah And Labuan
(Amendments) 2017
Kod/ST/No.3/2016(Pin.2017)
In exercise of the power conferred by Section 50A of the Electricity Supply Act 1990 [Act 447], the
Energy Commission with the approval of the Minister makes the following Code:
Purposes
1. The amendments of this Grid Code are necessary for the following purposes:
i) to facilitate and determine the requirements for connecting large scale solar
photovoltaic plants and other distributed generation into the system; and
Interpretation
2. In this Code the term and expression used shall, unless defined in the Grid Code or the context
otherwise requires, have the same meaning as in the Act or regulation made under it.
3. This Code may be cited as the Grid Code for Sabah & Labuan (Amendments) 2017.
4. The Grid Code for Sabah & Labuan was first issued by the Commission based on the approval
by the Commission on 4 April 2011 and by the Minister on 23 June 2011. The subsequent
amendments of the Code were approved by the Minister on 24 January 2017 and shall come
into force on the date of its registration.
5. This Code shall apply to the System Operator, Single Buyer and any person who is licensed
under Section 9 of the Electricity Supply Act 1990 [Act 447] and connected to the electricity
transmission network or any person connected to, or intends to connect to, the electricity
transmission network located in Sabah and Labuan.
6. The content of the Code which includes all the above amendments shall be as in ANNEX 1, and
shall replace the Grid Code for Sabah and Labuan which was issued in 2011.
7. The Grid Code for Sabah and Labuan issued in 2011 shall continue in full force up to the date of
coming into operation of this amended code.
Interpretation
8. In this Code the term and expression used shall, unless defined in the Grid Code or the context
otherwise requires, have the same meaning as in the Act or regulation made under it.
9. The Energy Commission may issue written notices from time to time in relation to the Code.
10. The Energy Commission may at any time amend, modify, vary or revoke this Code or any part
thereof, under the following circumstances:
2 Scope............................................................................................................................13
2.1 Industry Model ..........................................................................................................................13
PART 2 .................................................................................................................................67
CC6 PROCEDURES FOR APPLICATIONS FOR CONNECTION TO AND USE OF THE Grid System
89
CC6.1 Application and Offer for Connection ...................................................................................89
CC6.2 Complex Transmission Network Connections ......................................................................90
CC6.3 Right to Reject an Application ..............................................................................................90
CC6.4 Connection and Use of System Agreement ..........................................................................91
Metering Code Appendix 1 – Type and Accuracy of Revenue Metering Installations ....... 197
MCA1 General Requirements ....................................................................................... 197
MCA.1.2 Metering Installations Commissioned Prior to The Grid Code Effective Date ...............197
MCA.1.3 Accuracy Requirements for Metering Installations .......................................................197
MCA.1.4 Check Metering ..............................................................................................................199
MCA.1.5 Resolution and Accuracy of Displayed or Captured Data ..............................................200
MCA.1.6 General Design Requirements and Standards ...............................................................200
PREAMBLE
1 INTRODUCTION
This Grid Code,
(a) sets out the procedure which regulates all Users of the Grid System1 in the State of Sabah
and the Federal Territory of Labuan (“Sabah and Labuan”), which comprises the
Transmission Network and directly connected Generating Units, for electrical power and
energy generation and transmission to the Distribution System and directly connected
customers; and
(b) provides criteria guidelines and procedures for Users of the a Grid System to provide
information necessary for the co-ordination, planning, development, maintenance and
operation thereof.
This Grid Code comprises any or all the codes contained in this document and all words and
expression used in this Grid Code shall have the meanings and effect given to them in the, Glossary
and Definition section of the General Conditions.
Figure 1 illustrates how the various Users identified in the Grid Code are connected or associated
with Grid System.
Figure 2 illustrates the participants in the Sabah and Labuan Grid System and the major roles
they are responsible for.
1
Note that besides the interconnected Grid System, there are currently a number of isolated rural Power Systems in Sabah
and Labuan, which are not synchronously joined to the interconnected Power System. All of these various Power Systems
are NOT covered by this Grid Code.
Figure 2 The Main Participants of the Sabah and Labuan Grid System
2 SCOPE
The Grid Code contains procedures to permit the equitable management of the electricity sector in
Sabah and Labuan, taking into account a wide range of operational conditions likely to be
encountered under both normal and exceptional circumstances. It is nevertheless necessary to
recognise that the Grid Code cannot predict and address all possible operational situations.
Generators, Consumers and other Users must therefore understand and accept that the Grid System
Operator (GSO) in such unforeseen circumstances will be required, in the course of the reasonable
and prudent discharging of its responsibilities, to act decisively in pursuance of any one or any
combination of the following general requirements:
(a) The preservation or restoration of the integrity of its Grid System
(b) The compliance by Generators, Grid Owner and Network Owners with obligations
imposed by Licences issued by the Energy Commission;
(c) The avoidance of breakdown, separation, collapse or blackout (total or partial) of the
Power System;
(d) The requirements of safety under all circumstances, including the prevention of personal
injury; and
(e) The prevention of damage to Plant and/or Apparatus or the environment.
The Grid Code does not apply to the Distribution Networks including the Rural Networks as this will
be covered by the Distribution Code. It is important that any HV Apparatus used in these Networks
must be compatible in terms of design standards and equipment standards with the interconnected
Grid System.
Although SESB is the main vertically integrated electricity utility in Sabah and Labuan, the
Grid Code refers to different functions within SESB by naming key functions. This is to clarify
which department and persons within SESB is responsible for complying with the Grid Code.
The key functions are listed below:
(a) The Single Buyer is a department in SESB that is responsible for overseeing the
commercial arrangements entered into with the IPPs. The Single Buyer is not
responsible for rural connected IPPS and interconnected Power System connected
IPPs.
(b) The Grid Owner is a unit within SESB responsible for the operation and
maintenance of the Transmission Network and its associated Plant and Apparatus
for the purpose of providing transmission services, including access to the
Transmission Network to Generators, Distributers and Users of the Grid System.
(c) The Grid System Operator or GSO is the person in SESB responsible for the overall
coordination of the operation, maintenance and control of the interconnected Grid
System amongst all Users. The GSO is also responsible for generation Dispatch
and monitoring and control of this Grid System to ensure that the Grid System is
operated, at all times, reliably, securely, safely and economically.
3.1 GENERAL
The Grid Code is divided into the following codes of practice as contained in Part 2 of this
Schedule:
(a) General Conditions;
(b) Planning Code;
(c) Connection Conditions;
(d) Operating Codes Nos. 1 to 11;
(e) Scheduling and Dispatch Codes Nos. 1 to 3; and
(f) Metering Code.
These are now summarised.
SDC2 Scheduling and Dispatch Code No. 2 Control, Scheduling and Dispatch
SDC3 Scheduling and Dispatch Code No. 3 Frequency and Transfer Control
GENERAL CONDITIONS
GC1 INTRODUCTION
Each specific code of practice of the Grid Code contains the provisions relating specifically to that
particular code. There are also provisions of a more general application to allow the various codes to
operate together. Such provisions are included in this General Conditions (GC).
GC2 INTERPRETATION
GC2.1 GENERAL
In this Grid Code, unless the context otherwise requires:
(a) references to “this Grid Code” or “the Grid Code” are reference to the whole of the
Grid Code, including any schedules or other documents attached to any part of the
Grid Code;
(b) the singular includes the plural and vice versa; and
(c) any one gender includes the others.
References to codes, paragraphs, clauses or schedules are to the codes, paragraphs, clauses
or schedules of this Grid Code:
(a) code, paragraph and schedule headings are for convenience of reference only and
do not form part of and shall neither affect nor be used in the construction of this
Grid Code;
(b) reference to any law, regulation made under any law, standard, secondary
legislation, contract, agreement or other legal document shall be to that item as
amended, modified or replaced from time to time. In particular, any reference to
any licence shall be to that licence as amended, modified or replaced from time to
time and to any rule, document, decision or arrangement promulgated or
established under that licence;
(c) references to the consent or approval of the Energy Commission shall be
references to the approval or consent of the Energy Commission in writing, which
may be given subject to such conditions as may be determined by the regulatory
authority, as that consent or approval may be amended, modified, supplemented
or replaced from time to time and to any proper order, instruction or requirement
or decision of the Energy Commission given, made or issued under it;
(d) all references to specific dates or periods of time shall be calculated according to
the Gregorian calendar and all references to specific dates shall be to the day
commencing on such date at 00:00 hours, such time being Malaysian Standard
Time (UTC/GMT + 8 hours);
(e) where a word or expression is defined in this Grid Code, cognate words and
expressions shall be construed accordingly;
DC direct current
GO Grid Owner
HV high voltage
Hz Hertz
pu per unit
SB Single Buyer
SD1 Schedule Day one (the first dispatch day) of the Weekly
Generation Schedule
week0 week zero, or the programming week before the dispatch week
(w1)
Abnormal System The operating condition of the Grid System where the system
Conditions Frequency and Voltages deviate outside the Normal Operating
Conditions usually under some system fault conditions.
Abnormal Overload The loading of any Plant or Apparatus beyond the limit which a
prudent operator acting reasonably in the circumstances that pertain
at that precise time would consider acceptable.
Act The Electricity Supply Act 1990 (Act 447) and regulations made
thereunder.
Ancillary Service A service as defined in an agreement, other than for the production
of Energy and/or provision of Capacity which is used to operate a
stable and secure Grid System including automatic generation
control, Reactive Power, Operating Reserve, Frequency control,
voltage control and Black Start capability.
Annual Generation The annual report submitted by the Single Buyer to the Energy
Plan Commission providing the generation outage requirements for the
next (5) years.
Average Hot Spell That combination of weather elements within a period of time which
(AHS) Conditions is the average of the observed values of those weather elements
during equivalent periods over many years.
Black Start The procedure necessary for recovery from a Total Blackout or
Partial Blackout.
Black Start Capable A Generating Unit or Power Station, as the case may be, that is
Power Station registered as having Black Start capabilities.
(BSCPS)
Business Days Any day excluding Saturday, Sunday or public holidays in Kota
Kinabalu, Sabah.
Cold Standby Cold standby is a condition of readiness in relation to any CDGU that
is declared available, in an Availability Declaration, to start,
synchronise and attain target Loading all within a period of time
stated in the Availability Declaration.
Committed project Data relating to a User Development submitted by the User to the
Data Grid Owner, and to the Single Buyer once the relevant Agreement
for connection to the Grid System is signed
Connection An agreement between a User and the Grid Owner by which the
Agreement User is connected to the Grid System at a Connection Point.
Connection Site A SESB Transmission Site or a User Site, as the case may be.
The Generation Schedule after all the Transmission Constraints are
Constrained
fully taken into account.
Schedule
Contracted Project The data required to be submitted by the User in accordance with
Data the PC after completion and signing of the relevant Agreement.
Control Phase That period from the issue of the Generation Schedule through to
real time.
Data Collection The data collection system operated by the GSO on behalf of the
System Single Buyer, for use in the calculation of payments due for
wholesale electricity supplied or received.
Demand Control The term demand control is used to describe any or all methods of
achieving a Demand reduction, to maintain the stable and secure
operation of a Power System.
Designed Minimum The output (in whole MW) below which a Generating Unit has no
Operating Level High Frequency Response capability.
Detailed Planning Detailed additional data which the Grid Owner requires under the PC
Data in support of Standard Planning Data. Generally, it is first supplied
once a relevant Agreement is concluded.
Directly Connected A Customer in Sabah or Labuan acting in its capacity as such and
Large Power receiving electricity direct from the Grid System.
Consumers
Disconnection The switching off by manual or automatic means for the purpose of
Demand Control on a Power System or during the automatic
operation of network protection devices.
Dispatcher That person currently on duty and authorised by the GSO to issue
Dispatch Instructions to Generators for the operation of CDGUs.
Distributor A person who is licensed under Section 9 of the Act and is connected
to the Grid System and distributes electricity for the purpose of
enabling a supply to be given to any premises. “Distribute” means to
operate, maintain and distribute electricity through the electricity
distribution network.
Dynamic Spinning The Active Power reserve held on part-loaded Generators operating
Reserve on the Grid System which can automatically be delivered over some
seconds in respond to a fall in System Frequency
Earth Fault Factor At a selected location of a three phase system and for a given System
configuration, the ratio of the highest root mean square phase-to-
earth power frequency voltage on a sound phase during a fault to
earth (affecting one or more phases at any point) to the root mean
square phase-to-earth power frequency voltage which would be
obtained at the selected location without the fault.
Economic Capacity That loading, as determined by the Single Buyer, that represents the
optimum economic loading point for a Generating Unit, taking into
account all variable operating costs.
Energy (Active and Active energy is that instantaneous energy derived from the product
Reactive) of voltage and current and the cosine of voltage-current phase angle
between them which is integrated over time and measured in
watt-hours or multiples thereof.
Energy Commission Suruhanjaya Tenaga, the Energy Commission established under the
Energy Commission Act 2001 (Act 610) and the regulatory authority
for West Malaysia and the Sabah and Labuan energy sector.
Energy The annual Energy Requirements forecast from customers from the
Requirements Distributors, Users and Network Owners required for the
preparation of the annual System Development Plan
Energy Sector The applicable federal and state laws of Malaysia applicable to the
Safety Laws safe operation of a Grid System and safe working of persons on
Plant and/or Apparatus.
Estimated Those data of Standard Planning Data and Detailed Planning Data
Registered Data which upon connection will become an Estimated Registered Data
for the ten (10) succeeding years.
Extra High Voltage V > 230 000 - A voltage normally exceeding 230 000 volts.
Forecast Data Those data of Standard Planning Data and Detailed Planning Data
which will always be forecast values.
Generating Unit A capability chart, registered with the Single Buyer and the GSO,
which shows the MW and Mvar capability limits within which a
Capability Limits Generating Unit will be expected to operate under steady state
conditions.
In the case of a Power Park Module, the capacity chart
registered by the Generator with the Single Buyer, which shows
the active power and reactive power capability limits within
which such Power Park Module will be expected to operate
under steady state condition.
In addition, a Power Park Module output is based upon the
Intermittent power source being at a level which would enable
the Power Park Module to generate at Registered Capacity.
Generating Unit Those parameters listed in SDC1. Appendix 1 under the heading
Scheduling and Generation Scheduling and Dispatch Parameters relating to
Dispatch Dispatch Units.
Parameters (SDP)
Generation The annual report submitted by the Single Buyer to the Energy
Development Plan Commission providing the generation capacity requirements for the
next (10) years in accordance with the Licence requirements.
Generator Circuit A circuit from a power station having a CDGU and the associated
current and voltage transformers which form a Metering Installation
which measure the output from one of more CDGUs using this
circuit.
Grid Code A document that sets out the principles governing the relationship
between the GSO, ST, Grid Owner, Single Buyer and all Users of the
Grid System.
Grid Owner A unit within SESB responsible for the operation and maintenance of
a Transmission Network and its associated Plant and Apparatus for
the purpose of providing transmission services, including access to
the Transmission Network to Generators, Distributers and Users of
the Grid System.
Grid System The person in SESB responsible for the overall coordination of the
Operator or (GSO) operation, maintenance and control of the interconnected Grid
System amongst all Users. The GSO is also responsible for
generation Dispatch and monitoring and control of this Grid System
to ensure that the Grid System is operated, at all times, reliably,
securely, safely and economically.
High Frequency The high frequency response is the automatic decrease in Active
Response Power output of a Generating Unit in response to a Frequency
rise in accordance with the primary control capability and
additional mechanisms for reducing Active Power generation (for
example, fast valving). It is part of the Operating Reserve and is
further described in OC3.4.3
High Voltage 50 000 < V ≤ 230 000 - A voltage normally exceeding medium
voltage but equal to or not exceeding 230 000 volts.
Hot Standby Hot standby is that part of the Non-Spinning Reserve that is in a
condition of readiness such that the hot-standby CDGU is ready to
be Synchronised and attain an instructed Load within a specific
timescale and subsequently maintained such Load continuously.
Interconnector A facility that interconnects the Sabah and Labuan Grid System to
another power system external to the State of Sabah and the
Federal Territory of Labuan.
Interconnected Any person located outside Sabah and Labuan, which owns and
Party operates an Interconnector.
Intermittent Power The primary source of power for a Generating Unit that
Source depends on uncontrollable environmental conditions, e.g.
solar, wind or tidal power.
Isolating Device A device for rendering Plant and/or Apparatus into an Isolated
condition.
Largest Power The risk to the Grid System caused by the disconnection of the
Infeed Loss Risk largest Generating Unit or transmission line or Interconnector
carrying the largest amount of power and resulting in significant
Frequency deviation.
Least Cost The schedule of generators prepared for the following day that, at
Generation the time of preparation, would result in least cost operation of the
Schedule Grid System, taking into account all factors specified in SDC1, if
dispatched the following day.
Licence Standards Those standards relating to the reliability, security and quality of
electricity supply prepared by the Licencee pursuant to the
Licence approved by the Energy Commission.
Load Dispatch A dispatch centre and/or control centre responsible for the issuing
Centre or LDC of Dispatch Instructions to CDGUs and coordinating the
Transmission Network operations and Load, including safety
coordination, as the context requires.
Loss of Load A reliability index that indicates the probability that some portion
Probability (LOLP) of the Peak Demand will not be satisfied by the available
generating capacity as per License Standard. It may also be
expressed as an expected duration in a year for which the Peak
Demand is not being met, in which case it is referred as Loss of
Load Expectation (LOLE)
Continuous Rating registered with the Single Buyer at which the Generating Unit can
(MCR) operate continuously without any undue degradation of
operational performance, in accordance with Prudent Utility
Practice.
Medium Voltage 1 000 < V ≤ 50 000 - A voltage normally exceeding low voltage but
equal to or not exceeding 50 000 volts.
Merit Order The prioritised list, produced by the Single Buyer, of CDGUs
declared available, which gives the order in which such CDGUs will
be Loaded by the GSO in accordance with SDC1 and SDC2 in
specific circumstance.
Minimum The minimum stable output (in whole MW) that a CDGU has
Generation registered with the Single Buyer.
N-1 The condition where any one equipment out of all the equipment
in the Grid System is taken off from service or tripped. “N”
signifies total number of equipment in the system. The equipment
could be a generator unit, line, cable, circuit breaker or
transformer.
On a similar definition, “(N-2)” is the condition where any 2
equipment trip simultaneously. “(N-0 )” is the intact condition
where every equipment is service.
Network Owner A person with a User System directly connected to the Grid
System to which Customers and/or Power stations ( not forming
part of the Grid System) are connected, acting in its capacity as a
owner and operator of the User System, but shall not include a
person acting in the capacity of an externally Interconnected
Party.
Nominated Fuel Nominated Fuel is the primary or main fuel of a Power Station or
Generating Plant nominated by the Single Buyer based upon the
calculations made in preparing the Generation Development
Normal Operating The operating condition of the Grid System when the voltage and
Condition frequency at all points on the system are within their normal
limits and the system is secure against outages within
Transmission System Reliability Standards. “Normal Operation”
shall be construed accordingly.
Open Access The provision by the Grid Owner of access to its Network by Users
including, for the avoidance of doubt, prospective Users of a Grid
System.
Operational Effect The term operational effect means any effect on the operation of
the relevant Grid System which will or may cause the Grid System
and/or User installation to operate (or be at a materially increased
risk of operating) differently to the way in which they would or
may have normally operated in the absence of that effect.
Operational The Operational Planning Phase occurs from 5 years down to day
Planning Phase ahead
Partial Blackout The situation existing in a Power Island of the Grid System, when
all Generators in the Power Island have disconnected from the
Power Island and there is no electrical power flowing in the
Power Island.
Peak Demand That hourly period when the Power System Demand achieves or
is forecast to achieve, as the case may be, the highest Demand for
that day.
Planning Data The data associated with the longer term Planning of the
Transmission Network and for calculation of generation adequacy
to meet the Forecast Demand.
Power Island The condition that occurs when parts of the Network including
associated Generating Units become detached electrically from
the rest of the Grid System. This detached System with its
associated Networks and Generating Units is a power island.
Power (Active and Active power is that instantaneous energy derived from the
Reactive) product of voltage, current and the cosine of the phase angle
between voltage and current. It is measured in watts or multiples
thereof. Reactive power is that instantaneous energy derived
from the product of voltage, current and the sine of the phase
angle between voltage and current which is measured in vars or
multiples thereof
Power Park Unit An individual Generating Unit within a Power Park Module.
Power System Equipment controlling the Exciter output in such a way that power
Stabiliser (PSS) oscillations of the Generating Units are dampened. Input variables
may be speed, frequency or power or a combination of these
system quantities.
Prudent Utility The exercise of that degree of skill, diligence, prudence, and
Practice foresight which would reasonably and ordinarily be expected from
a skilled and experienced operator engaged in power utility
activities under the same or similar circumstances.
Registered Data Those data of Standard Planning Data and Detailed Planning
Data which upon connection to the Grid System become fixed
until subject to any subsequent changes
Rural Network Any Network situated in Sabah or Labuan that is Licensed, and is
not capable of being synchronously connected to the
Transmission Network in Sabah and Labuan.
Safety Rules The rules for the establishment of a safe system of working on
mechanical Plant, electrical Apparatus and operational buildings.
Such rules shall comply with Energy Sector Safety Law and
Prudent Utility Practice.
Schedule Day (SD) The 24 hour period starting at 00:00 hours (midnight) of the
scheduled day concerned. The schedule days are designated SD1,
SD2 etc where SD1 is the first day referred to in the programming
process concerned. In specific instances, SD0 will be used to
designate today or present time.
Scheduling and The relevant data required by the Single Buyer and GSO in
Dispatch carrying out the Scheduling and Dispatch of generation in
Parameters or SDP accordance to SDC1.
Self-generator An entity which produces electricity for its own consumption but
may import electrical energy when required or may export excess
generation to the Power System (if permitted in the generating
Licence) which is usually operated in parallel with the Power
System.
Settlements Those function under the control of the Single Buyer that maps
System physical Power System operations into financial operations
through the bulk processing of metering data and Energy and
Power flows and oversees the financial exchanges between the
different parties. “Settlements” shall be construed accordingly.
Significant Incident An Event on the Grid System having an Operational Effect which
results in, or likely to result in, the following:-
Tripping of Plant and/or Apparatus either manually or
automatically;
System Frequency outside statutory limits;
System Voltage outside statutory limits;
System overloads; or
System instability
Single Buyer The department in SESB responsible for initiating the process for
the procurement of new generation and the drafting of new PPAs
for signing between the relevant parties and monitoring of
existing PPAs. The single buyer also has the right to monitoring
Spinning Reserve Those loaded Generating Units, which form part of the Operating
Reserve, that are Synchronised to the Grid System and contribute
to Primary Reserve or Secondary Reserve and/or High Frequency
Response. A full explanation of this is found in OC3.
Stand-by Fuel Stock The stock level for the standby fuel defined by the Single Buyer as
part of the relevant Agreement
System A document submitted by the Grid Owner showing for each of the
Development succeeding ten (10) years the opportunities available for
Statement connecting to and using the Transmission Network and indicating
those parts of the Transmission Network most suited to new
connections and transport of further quantities of electricity.
Total Blackout The situation existing when all CDGUs in a Grid System have
disconnected from the Grid System.
Transfer Level The level of Active Power and/or Active Energy transfer which is
agreed between two parties across an Interconnector.
Transmission The annual plan submitted by the Grid Owner to the Energy
Development Plan Commission providing the transmission network requirements for
the next (10) years in accordance with the Licence requirements.
Use of System An agreement between a User and a Grid Owner by which the
Agreement User uses the Grid System for the transportation of electrical
Energy between agreed entry Point of Common Coupling to the
Network and agreed exit Point of Common Coupling from the
Network.
Working Day Any weekday where banks are open for domestic business in Kota
Kinabalu.
GC3 OBJECTIVES
The objectives of the General Conditions are as follows:
(a) to ensure, insofar as it is possible, that the various sections of the Grid Code work
together for the benefit of all the relevant parties; and
(b) to provide a set of principles governing the status and development of the Grid Code and
related issues as approved by the Energy Commission .
The GCC will establish and comply with its own rules.
The Chairman of the GCC shall consult in writing with Users liable to be affected in relation to all
proposed amendments to the Grid Code and shall submit all proposed amendments to the GCC for
discussion prior to such consideration.
The GCC decisions are not binding on the Energy Commission, but shall have only the nature of an
opinion. Any decision for amendment to the Grid Code must be approved by the Energy
Commission and be published by the GCC in a manner agreed with the Energy Commission.
practicable in the circumstances, consult promptly with all affected Users in an effort to reach
agreement as to what should be done. If agreement cannot be reached in the time available, the
Chairman shall in good faith determine what is to be done and notify all Users affected.
The Chairman shall promptly refer all such unforeseen circumstances and any determination to the
GCC for consideration in accordance with GC4.
GC6.2 DEROGATIONS
If a User finds that it is, or will be, unable to comply with any provision of the Grid Code, then
it shall, without delay, report such non-compliance to the Chairman and shall make such
reasonable efforts as are required to remedy such non-compliance as soon as reasonably
practicable.
The non-compliance may be with reference to Plant and Apparatus:
(a) connected to the Grid System and is caused solely or mainly as a result of a
revision to the Grid Code; and
(b) which is connected, approved to connect or for which approval to connect to the
Grid System is being sought.
When a User believes either that it would be unreasonable (including on the grounds of cost
and technical considerations) to require it to remedy such non-compliance or that it should
be granted an extended period to remedy such non-compliance, it shall promptly submit to
the Chairman a request for derogation from such provision in accordance to GC6.3.
If SESB finds that it is, or will be, unable to comply with any provision of the Grid Code at any
time, then it shall make such reasonable efforts as are required to remedy such
non-compliance as soon as reasonably practicable.
In the case where SESB requests the derogation, it shall promptly submit to the Chairman a
request for derogation from such provision in accordance with GC6.3.
GC7 HIERARCHY
In the event of any irreconcilable conflict between the provisions of the Grid Code and any contract,
agreement, or arrangement between the GSO, or Single Buyer and a User, the following
circumstances shall apply.
(a) If the contract agreement or arrangement exists at the date this Grid Code first comes into
force, it shall prevail over this Grid Code for five years from the date upon which this Grid
Code is first in effect, unless and to the extent:
specifically provided for in the Grid Code or in the contract agreement or
arrangement or;
that the User has agreed to comply with the Grid Code.
(b) In all other cases, the provisions of the Grid Code shall prevail unless the Grid Code
expressly provides otherwise.
(b) if sent by post, from and to any address within Sabah or Labuan, four (4) Business Days
after posting unless otherwise proven; or
(c) if sent by facsimile, subject to confirmation of uninterrupted transmission report, or by e-
mail, one hour after being sent, provided that any transmission sent after 14:00 hours on
any day shall be deemed to have been received at 08:00 hours on the following Business
Day unless the contrary is shown to be the case
GC11.1 GENERAL
If any dispute arises between Users or between the Chairman and any User in relation to this
Grid Code, either party may by notice to the other seek to resolve the dispute by negotiation
in good faith. If the parties fail to resolve any dispute by such negotiations within sixty (60)
calendar days of the giving of a notice under GC10, then:
(a) either party shall be entitled by written notice to the other to require the dispute
to be referred to a meeting of members of the Boards of Directors of the parties
or, if no such directors are present in Sabah or Labuan, the most senior executive
of each party present in Sabah or Labuan;
(b) if either party exercises its right under GC11 paragraph 1 (a), each party shall
procure that the relevant senior executives consider the matter in dispute and
meet with senior executives of the other party within thirty (30) calendar days of
receipt of the written notice of referral to attempt to reach agreement on the
matter in question; or
(c) if the parties fail to resolve any dispute which has been referred to directors/senior
executives under GC11.1 paragraph 1 (a), either party may refer the matter to the
Energy Commission for determination as the Energy Commission sees fit. All
parties shall be bound by any decision of the Energy Commission. If it sees fit the
Energy Commission may:
determine the dispute itself; or
refer the dispute for determination by arbitration.
Any arbitration conducted in accordance with the preceding paragraph shall be conducted in
accordance with RCAKL rules, as modified:
(a) in the City of Kota Kinabalu in Sabah;
(b) in English;
(c) the law applicable to this Grid Code shall be the Laws of Malaysia; and
(d) by a single arbitrator.
Where the Grid Code provides that any dispute or difference of the parties in relation to a
particular matter should be referred to an expert for resolution, such difference or dispute
may not be referred to arbitration unless and until such expert determination has been
sought and obtained.
Any arbitration award shall be final and binding on the parties.
PLANNING CODE
PC1 INTRODUCTION
The Planning Code (PC) specifies the requirements for the supply of information by Distributor and
Users connected or seeking connection to the Grid System. This is required to enable the planning
engineers within the Grid Owner and Single Buyer to undertake the planning and development of
their Networks, which also takes due account of the network development plans required to meet
future generation requirements. It also specifies the technical and design criteria and procedures to
be applied by the Single Buyer, Grid Owner and Network Owner in the planning and development of
a Grid System. All these need to be taken into account by Users connected or seeking connection to
a Grid System in the planning and development of their own User’s installation including Power
Stations.
In addition, the PC establishes the requirements for the Single Buyer to notify the GSO and Grid
Owner of its proposals for future generation capacity through a Generation Development Plan and
for the Grid Owner to notify of its proposals for future transmission development through the
Transmission Development Plan.
For the purpose of the PC the Users referred to above are defined in PC3.
(e) the cumulative effect of a number of such developments referred to in (a), (b) or
(c) by one or more Users including the addition or removal of significant blocks of
Demand.
All Grid System developments must be planned with sufficient lead-time to allow any
necessary consent to be obtained and detailed engineering design, procurement and
construction work to be completed. Therefore, the PC imposes appropriate time scales on
the exchange of information between the User and the appropriate Network Owner.
PC2 OBJECTIVES
The objectives of the Planning Code are to:
enable the Grid System to be planned, designed and constructed economically, reliably,
safely and having regard to sustainable development and the minimising of environmental
impact;
provide for the supply of information required from Users, in order for the Network
Owners to plan the development of the Grid System and to facilitate existing and
proposed connections;
set out requirements for the supply of information in respect of any proposed
development on a User’s Network which may impact on the performance of a Grid
System;
formalise the exchange and specify the requirements of planning data between the Single
Buyer, Grid Owner and Users, which will eventually form the basis of a connection offer
and Connection Agreement;
provide for the supply of information required by the Single Buyer for the optimisation of
future generation capacity planning and procurement of new generation capacity;
to provide the procedures for application for new connections or modification to existing
connections;
provide detailed plans for implementing the Rural Electrification Plan in Sabah, in
accordance with the projects set by the Ministry of Rural and Regional Development; and
to provide sufficient information for a User to assess opportunities for connection and to
plan and develop the Users’ System so as to be compatible with a Grid System.
PC3 SCOPE
The PC applies to the Single Buyer, Grid Owner and GSO, and to Users which in the PC means;
(a) Generator;
(b) Distributor
The Rural Electrification Plan shall indicate how the Ministry of Rural and Regional Development’s
targets for the complete electrification of Sabah shall be achieved.
The production of the Transmission Development Plan, referred to in PC5.3 is the responsibility of
the Grid Owner who will coordinate the inputs from the Users.
Any information relating to changes to an Interconnector will be notified directly by the
Interconnected Party to GSO, Grid Owner or the appropriate Network Owner. Where transmission
Capacity is affected by a proposed change, the Grid Owner and GSO will advise the Single Buyer,
who will include this in the Generation Development Plan as appropriate.
Transmission Network most suited to new connections and transport of further quantities of
electricity. This shall take into account all the developments planned by the Grid Owner and
the developments notified to the Grid Owner by the Users through connection applications
and relevant Connection Agreements.
The System Development Statement which is submitted to the Energy Commission,
identifies and evaluates the opportunities for connection in Sabah and Labuan Grid System.
The document shall at least include but not limited to the following:
(1) Grid System and background to system development;
(2) Aggregated load forecast;
(3) Generation Plant capacity developments including existing approved plant and
plant under construction;
(4) Generating Plant capacity requirements for compliance with Generation Reliability
Standard;
(5) Existing and planned transmission developments including the requirements for
equipment replacement and technology up-gradation;
(6) Transmission Network capability including load flows and system fault levels;
(7) Transmission Network performance information including frequency and voltage
excursions and fault statistics; and
(8) Commentary indicating those parts of the Transmission Network considered most
suited to new connections and transport of further quantities of electricity.
On submission of the annual System Development Statement to the Energy Commission,
the Grid Owner shall brief the Energy Commission on the generation requirements,
connection opportunities and system developments for the next ten (10) years.
agrees in consultation with the Grid Owner may agree in any particular case) of acceptance
of the offer the User shall supply the Detailed Planning Data to the Grid Owner pertaining to
the User Development as listed in Part 2 of the Appendix A.
PC4.5.2 Frequency
The Frequency of the Grid System is nominally maintained at 50Hz. However, due to
the dynamic nature of the Grid System, the Frequency can change rapidly under
Abnormal System Conditions or fault conditions. Frequency limits are tabulated in
this section of the Planning Code. This caters for Normal Operating Conditions and
Abnormal System Conditions where under some System fault conditions, the
Frequency can deviate outside the Normal Operating Conditions for brief periods.
Such conditions are summarised in Table 4.5.2 below.
Table 4.5.2: Frequency Excursions
PC4.5.3 Voltage
PC4.5.3.1 Steady-State Voltage
Table 4.5.3.1 Steady-State Voltage
While the Grid Owner, Distributor and Network Owners shall comply with
the standards listed in (a) to (d) above this will not prevent voltage
fluctuations being experienced by Users due to System faults. Those
industrial Users that intend to use equipment, such as process control
equipment, that is likely to malfunction during voltage dips should consider
installing some form of energy storage device to maintain the voltage level
inside the factory during the fault clearance and System recovery times.
PC4.5.4 Harmonics
Harmonics are normally produced by Apparatus operated by Users, which are
generating waveforms that distort the fundamental 50 Hz sine wave. Such harmonic
generation can damage other User’s Apparatus or can result in the failure of
Network Owner’s Apparatus.
The limits for harmonic levels are given in but not limited to the following
documents:
(a) IEC 61000-3-6 (1996-10) “Assessment of emission limits for fluctuating
loads in MV and HV power systems”; and
PC4.5.5 Protection
PC4. 5.5.1 Protection Fault Clearing Time Criteria
Total fault clearance times include time for relay operation, circuit breaker
operation, and telecommunication signalling. For the overhead line
protection the fault clearing times should not be more than the followings:
(a) for the 500 kV lines, 5 cycles (100 ms);
(c) for the 132 kV lines, 7.5 cycles (150 ms); and
500 50kA, 1s
132 31.5kA, 3s
40kA, 3s for Power Station and 132kV within a 500kV
substation
33 25kA, 3s
PC5.0 GENERAL
The Grid Owner shall annually prepare the System Development Statement, which shall
include a Demand Forecast, Generation Development Plan and Transmission Development
Plan to identify the system developments required to ensure compliance with the Licence
Standards for submission to the Energy Commission in accordance with the procedures and
data received from Users as described in this PC5 and elsewhere in this Planning Code.
Each User shall submit Standard Planning Data and Detailed Planning Data, as more
particularly specified in PCA.1 and PCA.2. Where the User has more than one Connection
Point then appropriate data is required for each Connection Point. Data shall be annually
submitted by the Users by the end of August in the current year “Year 0” and for each year of
the ten (10) succeeding years.
The Users shall submit data in writing on “by exception” basis submitting only the relevant
changes to the data from the previous data submission or by declaring “no change” if this is
the case. It is the responsibility of the User to submit accurate data in relation to its planned
developments and the timescales in which these developments will be implemented. The
Users also have the responsibility of notifying any changes to their planned developments
without waiting for the annual data submission.
In order to enable an agreement to be reached with the User over any change and/or
developments proposed, the Grid Owner shall notify each User of any material modifications
arising from the outcome of the annual Transmission Development Plan that may concern
that particular User.
A full Planning Data submission must be provided by a User when applying for a new
connection or modifications to an existing connection to the Transmission Network. This
data shall include any changes to the User Network and the operating regime. In these
submissions the User must always provide Standard Planning Data. Provision of the Detailed
Planning Data shall be at the request and in accordance with the requirements of the Grid
Owner.
The notification shall also include a full timetable for the implementation and effective date
at which the proposed connection or modifications will become fully operational.
To enable Users to model the Transmission Network in relation to short circuit current
contributions, the Grid Owner is required to submit to Users the relevant Network Data.
The data will be given by August of each year and will cover the following ten (10) years.
that would be required shall be calculated based upon marginal generation costs to
meet the particular Demand.
In preparing the annual Generation Development Plan, the Single Buyer shall use
appropriate parameters for the existing generating plant submitted in accordance
with the provisions of this PC and data relating to performance and availability of
such plant as continually recorded by the GSO. For any plant, which has as yet not
been planned, the Single Buyer shall use typical parameters applicable to such plant
in international practice. The list of data to be used in Single Buyer studies in relation
to the Generation Reliability Standard is included in Appendix A.
Single Buyer will include a 10 years generation development for Rural Network. For
the Rural Networks, the development may adopt a lower reliability standard of
greater than 1.5 days per year in consideration of sustainable economic
development. Single Buyer shall declare its planning criteria adopted for Rural
Networks System, which is not connected to the main grid.
PC7.0 GENERAL
It is the responsibility of the User to submit accurate data in relation to its planned
developments and the timescales in which these developments will be implemented. The
Users also have the responsibility of notifying any changes to their planned developments
without waiting for the annual data submission.
The Grid Owner shall provide the relevant Planning Data (as detailed out in Appendix A) as
and when finalized to the GSO to the extent these are required for operational planning and
scheduling.
This data, together with other data held by the Grid Owner relating to the Grid System will
form the background against which new applications by any User will be considered and
against which planning of the Grid System will be undertaken. Accordingly, Committed
project Data will not be treated as confidential to the extent that the Grid Owner is obliged
to use it:
(1) in the preparation of the System Development Statement and in any further
information given pursuant to the System Development Statement;
(2) when considering and/or advising on applications (or possible applications) of
other Users. This use, could include making use of it by giving data from it, both
orally and in writing, to other Users making an application or considering or
discussing a possible application which is, in the Grid Owner's view, relevant to
that other application or possible application;
(3) for the GSO’s operational planning purposes; or
(4) under the terms of an Interconnection Agreement to pass it on as part of system
information on the Grid System.
To reflect the three (3) types of data referred to above, Contracted Project Data is itself
divided into:
(1) those items of Standard Planning Data and Detailed Planning Data which will
always be Forecast Data, known as Forecast Data; and
(2) those items of Standard Planning Data and Detailed Planning Data which upon
connection become fixed (subject to any subsequent changes), known as
Registered Data; and
(3) those items of Standard Planning Data and Detailed Planning Data which for the
purposes of the Plant and/or Apparatus concerned as at the date of submission are
Registered Data but which for the ten (10) succeeding years will be an estimate of
what is expected, known as Estimated Registered Data, as more particularly
provided in the Appendix A.
Contracted Project Data, together with other data held by the Grid Owner relating to the
Grid System, will form the background against which new applications will be considered
and against which planning of the Grid System will be undertaken. Accordingly, Contracted
Project Data will not be treated as confidential to the extent that the Grid Owner is obliged
to use it:
(1) in the preparation of the System Development Statement and in any further
information given pursuant to the System Development Statement;
(2) when considering and/or advising on applications (or possible applications) of
other Users. This use, could include making use of it by giving data from it, both
orally and in writing, to other Users making an application or considering or
discussing a possible application which is, in Grid Owner's view, relevant to that
other application or possible application; (3) for the GSO’s operational planning
purposes; or
(3) under the terms of an Interconnection Agreement to pass it on as part of system
information on the Transmission Network.
PART 1
PC A1.1.1 General
All Users shall provide the Grid Owner with details specified in PC7 relating
to their User Network.
(i) User Network Layout
Users shall supply single line diagrams showing the existing and proposed
arrangements of the main connections and primary systems showing
equipment ratings and where available numbering and nomenclature.
(ii) Short Circuit Infeed
User shall supply the following information;
(i) the maximum 3-phase short circuit current injected into the
Transmission Network; and
PC A1.2.1 General
All Users with Demand in excess of 1 MW shall provide the Grid Owner with
Demand, both current and forecast, as specified in this Planning Code provided that
all forecasted maximum Demand levels submitted to the Grid Owner by Users shall
be on the basis of corrected Average Hot Spell (AHS) Conditions.
In order that the Grid Owner is able to estimate the diversified total Demand at
various times throughout the year, each User shall provide such additional forecasts
Demand data as the Grid Owner may reasonably request.
sensitivity of User Demand to any voltage and frequency variations on the Grid
System;
The maximum harmonic content which the User would expect its Demand to impose
on the Grid System; and the average and maximum phase unbalance which the User
would expect its Demand to impose on the Grid System, shall also be supplied.
d) The magnitude of the largest step changes in Demand (Active and Reactive
Power) both increasing and decreasing;
PC A1.3.1 General
All Generating Unit and Power Station data submitted to the Grid Owner shall be in
a form approved by the Grid Owner. Where the User has undertaken modelling of
the Grid System then the Grid Owner should be advised of this and the results of the
modelling including an electronic copy of the modelling data made available to the
Grid Owner. For the avoidance of doubt the User is not required under the PC to
provide the modelling software to the Grid Owner, unless it so chooses.
Where a Generating Unit connects to the User’s Network, the output from this
Generating Unit is to be taken into account by the User in its Demand profile
submission to the Grid Owner, except where such Generating Unit is subject to
Central Dispatch. In the case where Generating Units are not subject to Central
Dispatch, the User must inform the Grid Owner of the number of Generating Units
together with their total Capacity. On receipt of such data, the User may be further
required, at the Grid Owner’s discretion, to provide details of the Generating Units
together with their energy output profile.
PC A1.4.1 General
All Power Park Module data submitted to the Grid Owner shall be in a form
approved by the Grid Owner. Where the User has undertaken modelling of the Grid
System then the Grid Owner should be advised of this and the results of the
modelling including an electronic copy of the modelling data made available to the
Grid Owner. For the avoidance of doubt the User is not required under the PC to
provide the modelling software to the Grid Owner, unless it so chooses. Single line
diagram of the power station, block diagrams of the power park module models, the
dynamic models and its transfer functions are to be submitted.
Figure PPM.3 Schematic diagram of a dynamic model of a Power Park Module and its control
arrangement
Figure PPM.4 Power Park Module Active Power Response Capability Due to Frequency
Figure PPM.5 Power Park Module Reactive Power Requirement at Normal Operation
Figure PPM.6 Power Park Module Low and High Voltage Ride Through Requirement
Figure PPM.7 Reactive Power Requirement at Normal Operation Condition of System Voltage
PART 2
PA A2.1.1 General
All Users shall provide the appropriate Grid Owner with the details as specified in
PCA2.1.
c) Phasing arrangements;
d) Earthing arrangements;
b) the additional maximum 3-phase short circuit infeed from any induction
motors connected to the User's Network; and
c) a full description, including estimated settings, for all relays and protection
systems installed or to be installed on the Generating Unit, Generating
Unit transformer, station transformers and their associated connections;
d) for Generating Units having (or intending to have) a circuit breaker on the
circuit leading to the generator terminals, at the same voltage, clearance
times for electrical faults within the Generating Unit zone; and
e) The most probable fault clearance time for electrical faults on the User’s
Network.
PC A2.2.1 General
All Users with demand shall provide the Grid Owner with the Demand both current
and forecast specified in this PCA2.2.
All forecast maximum Demand levels submitted to the Grid Owner by Users shall be
on the basis of average climatic conditions; and
So that the Grid Owner is able to estimate the diversified total Demand at various
times throughout the year, each User shall provide such additional forecast Demand
data as the Grid Owner may reasonable request.
PC A2.3.1 General
All Generators with Power Stations which have a site rating Capacity of 5 MW and
above shall provide the Grid Owner with details as specified in this PCA2.3.
PC A2.4.1 General
Notwithstanding the Standard Planning Data and Detailed Planning Data set out in
this Appendix, the Grid Owner may require additional data from Users. This will be
to represent correctly the performance of Plant and Apparatus on the Grid System
where the present data submissions would, in the Grid Owner’s reasonable opinion,
prove insufficient for the purpose of producing meaningful system studies for the
relevant parties.
As the Single Buyer is responsible for the overall coordination of new generation
planning, then any data required by it will be requested through the relevant Grid
Owner. In addition, if the Single Buyer requires additional data then it will request
such data through the applicable Grid Owner.
CONNECTION CONDITIONS
CC1 INTRODUCTION
The Connection Conditions (CC) specify the minimum technical, design and certain operational
criteria which must be complied with by the Users connected to, or seeking connection to a Grid
System. They also set out the procedures by which the Grid Owner, Network Owner and Distributor
will seek to ensure compliance with these criteria as a requirement for the granting of approval for
the connection of a User to a Grid System.
The procedures by which the Network Owner and Users may commence discussions on a
Connection Agreement are reflected in the Planning Code section of this Grid Code. Each
Connection Agreement shall require Users to comply with the terms of this Grid Code and the Grid
Owner will not grant approval for the User to connect to the Grid Owner’s Network until the User
has satisfied the Grid Owner that the criteria laid down by this CC have been met.
The provisions of the CC shall apply to all connections to the Transmission Networks:
(a) existing connections at the date when this Grid Code comes into effect;
(b) existing connection at the date of commencement of the Network Owner’s approval,
where these dates precede the date in (a) above; and
(c) connections as established or modified thereafter.
CC2 OBJECTIVES
The Connection Conditions are designed to ensure that:
(a) no new or modified connection will impose unacceptable effects upon a Grid System or
any User Network nor will it be subject itself to unacceptable effects by its connection to
the Grid System; and
(b) the basic rules for connection treat all Users of an equivalent category in a non-
discriminatory fashion, and enable Distributor, Network Owners and the Users to comply
with their statutory and Licence obligations.
CC3 SCOPE
The CC applies to the GSO, Grid Owner, and Single Buyer and to Users which in this Connection
Conditions means:
(a) Generators, including Generator with Power Park Module (other than those which only
have Embedded Minor Generating Plant)
(b) Distributors
(c) Network Owner
(d) Directly Connected Large Power Consumers.
(e) Parties seeking Connection to the Transmission or User System, whose prospective
activities would place them in any of the above categories of User will, either pursuant to a
Licence or as a result of an application for supply, become bound by this CC prior to their
providing or receiving Ancillary Services and/or producing or consuming Energy.
Other voltage performance requirement such as load unbalance for traction load,
maximum allowable flicker severity due to voltage fluctuation are stipulated in
License standards and are to be complied with by Users’ at the Point of Common
Coupling .
It may be necessary for Grid Owner and GSO to evaluate the fluctuation of voltage
and unbalance voltage on the Transmission Network and User Network, especially
when Grid Owner or User is connecting equipment such as arc furnace and traction
equipment. At the Grid Owner and GSO’s request, each User is required to submit
data and/or results of evaluation studies and measurement with respect to the
Connection Site, prior to connection and post connection.
CC5.2.1 General
The technical requirements for parallel operation of Consumer’s Generating Units
not subject to Dispatch by the GSO shall be as follows:
(a) Each Generating Unit must be capable of continuously supplying its output
within the System frequency range given in the Planning Code and License
Standards.
(b) The output voltage limits of Generating Units must not cause excessive
voltage excursions in excess of ± 5% of nominal. Voltage regulating
equipment shall be installed by the User to maintain the output voltage
level of its Generating Units within limits.
(c) The speed governor of each Generating Unit must be capable of operating
in accordance to the Licence Standards and to be approved by the GSO or
Distributor, such approval not to be unreasonably withheld.
(d) The isolation and earthing requirements shall be in accordance with the
Grid Owner’s current guideline documents or in the absence of such
documents the Tenaga Nasional Berhad guidelines.
CC5.3.1 Introduction
This section sets out the technical and design criteria and performance requirements
for Generating Units (whether directly connected to the Grid System or Embedded)
which each Generator must ensure are complied with in relation to its Generating
Units, but does not apply to any plant group with a total registered capacity of less
than 30MW for synchronous units and less than 5MW for Power Park Module, hydro
units and renewable energy plant not designed for Frequency and voltage control.
References to Generating Units in this CC6.4 on the connection Agreement condition
should be read accordingly. In such cases the Grid Owner and GSO shall provide
appropriate provisions for inclusion in the relevant Agreement.
All Generating Units must also be capable of operating at any point within the
capability chart corrected for the site conditions. The short circuit ratio of Generating
Units shall be not less than 0.5.
The Generating Unit and/or CCGT Module must be capable of continuously maintain
Active Power output for System Frequency changes within the range 50.5 to 49.5 Hz;
The Active Power output under steady state conditions of any Generating Unit
directly connected to the Grid System should not be affected by voltage changes in
the normal operating range specified in paragraph PC4.5.3. The Reactive Power
output under steady state conditions should be fully available within the voltage
range of ± 10% at 500kV, 275kV and 132kV and lower voltages.
For Power Park Module, the reactive power requirement under normal steady state
voltage conditions as shown in Figure PPM.7 should be fully available.
Power Park Module must response to active power and reactive power dispatch
instruction given by GSO either by telephone or electronic signal to operate at
maximum generation output or at lower generation output within capability curve.
tuning study report to the Grid Owner and GSO at least three (3) months
before commissioning of the Generating Unit.
(xiii) The control arrangements provided for Frequency and Voltage control
shall continue to operate stably during disturbances experienced by the
Grid System without inadvertently tripping the turbine and/or prime
mower or the Generator and disconnecting it from the Grid System.
The low voltage and high voltage ride through characteristics must comply with the
minimum requirement as shown in Figure PPM.6 in PCA1.4 Appendix or as specified
in the connection agreement.
CC5.4.1 Introduction
This part of the Grid Code describes the technical and design criteria and
performance requirements for Distributors, Directly Connected Customers, and
Network Owner
CC6 PROCEDURES FOR APPLICATIONS FOR CONNECTION TO AND USE OF THE GRID SYSTEM
CC6.1.1 Application Procedure for New Connection and Use of the Grid
System
Any person or User seeking to establish new or modified arrangements for
connection and or use of the Grid System must make an application on the standard
application form available from the Grid Owner of the Network concerned and
Single Buyer on request. The application should include:
(a) a description of the User Network to be connected to the Grid System or
of the modifications to User Network already connected to the Grid
System. Both cases are termed “Development” in this CC;
(b) the relevant Standard Planning Data as listed in Part 1 of Appendix A of
the Planning Code; and
(c) the desired completion date of the proposed Development.
the establishment of the proposed new or modified connection to and/or use of the
Grid System.
The offer shall specify, and the terms shall take account of, any works required for
the extension or reinforcement of the Grid System necessitated by the applicant’s
proposed activities.
The offer must be accepted by the applicant User within the period stated in the
offer, otherwise the offer automatically lapses.
Acceptance of the offer renders the Network Owner’s works related to that User
Development committed and binds both parties to the terms of the offer.
Within 28 calendar days (or such longer period as the Grid Owner may agree in any
particular case) of acceptance of the offer, the User shall supply the Detailed
Planning Data pertaining to the Development as listed in Part 2 of Appendix A of the
Planning Code. Any significant changes to this information, compared with the
preliminary data agreed by the Grid Owner will need to be agreed by the appropriate
Network Owner. The Grid Owner will be responsible under these circumstances for
accepting the Users results and will notify the Single Buyer and GSO of any changes
in the Users data where appropriate.
OC1.1 INTRODUCTION
Accurate Demand forecasting is essential for the procurement of sufficient Generation to
cater for the Demand for electricity. Operating Code No. 1 (OC1) outlines the obligations on
the Single Buyer, GSO and Users regarding the preparation of Demand forecasts of Active
Power, Reactive Power and Active Energy of the Grid System for operational purpose. OC1
sets out the time scales within Operation Planning and Operation Control periods in which
Users shall provide forecasts of Demand and Energy to the Single Buyer so that the relevant
operational plans can be prepared.
The following distinct phases are used to define the Demand forecasting periods:
(1) Operational Planning Phase covers several time frames of operation from 5-year
ahead to the start of the Control Operational Phase as follows:
i) 5-Year ahead forecast monthly
ii) 1-year ahead forecast - hourly
iii) 1-Month ahead forecast – hourly
iv) 10-Day ahead forecast – half hourly
v) 1-Day ahead forecast – half hourly
Single Buyer is responsible for all the above mentioned Demand Forecasts and the GSO
needs to use these Demand Forecasts to perform system studies to check for system
security.
(2) Operational Control Phase covers the real time operation period, that is:
i) Hour ahead forecast – half hourly
GSO is responsible for the demand forecast during Operational Control Phase.
(3) Post Operational Control Phase is the phase following real time operation.
In OC1, Week 0 means the current week at any time, Week 1 means the next week at any
time, Week 2 means the week after Week 1. For operational purposes, each year shall start
on 1st January and shall use the Gregorian calendar.
OC1.2 OBJECTIVES
The objectives of OC1 are:
(a) to enable matching of Generation and Demand in operation;
(b) to ensure the provision of data to the Single Buyer by Users for Operational
Planning purposes; and
(c) to provide for the factors to be taken into account by the GSO when Demand
forecasting is conducted during Operational Control Phase operation.
OC1.3 SCOPE
OC1 applies to the GSO, the Single Buyer and the following Users:
(a) Generators with CDGU’s, including Generators with Power Park Module;
(b) Generators connected directly to the Grid System or indirectly via Distribution
Network, with Generating Units not subject to Dispatch by the GSO, with total on-
site generation capacity equal to or above 1 MW where the GSO considers it
necessary;
(c) Large Power Consumers, where the GSO considers it necessary;
(d) Interconnected Parties;
(e) Distributors and
(f) Network Owners where the GSO considers it necessary.
(c) The Distributor shall notify the Single Buyer immediately of any
significant changes to the data submitted above.
(ii) Other Users
The relevant Users identified in OC1.3 (b) and (c) shall submit to the
Distributor by the end of June each year electronic files, in a format agreed
in writing by the Distributor, detailing the following:
(a) For Large Power Consumers, they have to inform the Distributor
of any planned changes that will alter the Demand by an amount
equal to or greater than ± 1 MW during Year 1 at the respective
interfaces.
(b) Generators with non-CDGUs (including Self-Generators) having
total on-site generation capacity equal to or greater than 5 MW
may be required to provide the Single Buyer, through the
Distributor or Network Owner, relevant generation output
information when reasonably required by the Single Buyer.
Such requirement to provide information pursuant to OC1.4.2 does not
remove the obligation for a User to notify the Single Buyer of any changes in
Demand data in accordance with the respective Connection Agreement.
(iii) Interconnected Party
It is the responsibility of the Single Buyer to request in the manner and
format that have been specified in the relevant Agreement with each
Interconnected Party of the hourly Active Power Demand to be imported
from or exported to the Interconnected Party over the total time period
agreed in the relevant Agreement.
OC2.1 INTRODUCTION
Operational Planning involves planning through various time scales, the matching of
generation capacity with forecast Demand pursuant to OC1 together with a reserve of
generation to provide for the necessary Operating Reserves, in order to maintain the
security of the Grid System taking into account:
(a) planned outages of Generating Units, including Power Park Modules;
(b) planned outages and operational constraints on parts of the Transmission
Network;
(c) planned outages of Large Power Consumers; and
(d) transfers of capacity between the Grid System and any Interconnected Parties.
Operating Code No. 2 (OC2) is concerned with the coordination between the GSO and Users
through the various time scales of planned outages of Plant and Apparatus on the User
System which may affect the operation of the Grid System.
Operational Planning Phase covers several time frames of operation from 5-year ahead to
the start of the Control Operational Phase as follows:
i) 5-Year ahead Operation Plan
ii) 1-Month Operation Plan
iii) 10-Day ahead forecast Operation Plan
iv) 1-Day ahead forecast Operation Plan
OC2.2 OBJECTIVES
The objectives of OC2 are:
(a) to enable the GSO to coordinate generation and transmission outages to achieve
safe, reliable and economic operation and minimise constraints;
(b) to set out the operational planning procedure including information required and
a typical timetable for the coordination of planned outage requirements for
Generators;
(c) to set out the operational planning procedure including information required and
a typical timetable for the coordination of planned outage requirements for other
Users that will have an effect on the operation of the Grid System; and
(d) to establish the responsibility of the Single Buyer to produce the relevant
operation plans.
OC2.3 SCOPE
OC2 applies to the Single Buyer, GSO and the following Users:
(a) Grid Owner;
(b) Network Owners;
(c) Generators with CDGUs, including Generator owning Power Park Modules;
(d) Generators with Generating Units not subject to Dispatch by the GSO with total
on-site generation capacity equal to or greater than 1 MW where the GSO
considers it necessary;
(e) Distributor;
(f) Large Power Consumers where the GSO considers it necessary; and
(g) Interconnected Parties.
OC2.4.1 Generators
In each Year, by the end of August Year 0, each Generator with CDGUs shall provide
the GSO with an "Indicative Generator Maintenance Schedule" which covers Year 3
up to Year 5. The schedule will contain the following information:
(1) Identity of the CDGU;
(2) MW not available;
(3) Other Apparatus affected by the same outage;
(4) Duration of outage;
(5) Preferred start and end date;
(6) State whether the planned outage is flexible, if so, provide the earliest
start date and latest finishing date;
(7) State whether the planned outage is due to statutory obligation (for
example for pressure vessel inspection/boiler check), if so, the latest date
the outage must be taken; and
(8) To state detail of any test which may affect the performance of the Grid
System or the Single Buyer’s operational plan or risk of tripping.
In each Year by the end of August of Year 0, each Generator with CDGUs shall also
provide the GSO with a “Provisional Generator Maintenance Schedule”which
covers Year 1 on a daily basis which for the avoidance of doubt means providing
information for each day of Year 1 beginning 1st of January and ending 31st of
December of Year 2. This schedule shall be submitted, in a format agreed by the
GSO, and take account of the Operational Plan described in OC2.5, comprising of:
(1) type of outages for each CDGU;
(2) the period of each outage consistent with the Operational Plan; and
(3) any other outages as required by statutory organisations or for statutory
reasons.
All Users shall submit details of any changes made to the information provided
above to the GSO as soon as practicable.
Grid System operation. The Grid Owner shall not unreasonably refuse such
requests.
By the end of December of Year 0 the GSO will draw up a Final Transmission
Network outage schedule covering Years 1 to 5. The plan for Year 1 becomes the
final plan for Year 0 when by expiry of time, Year 1 becomes Year 0.
The GSO will notify each User in writing of those aspects of the schedule which may
operationally affect such User including in particular proposed start dates and end
dates of relevant Transmission Network outages.
The GSO will also indicate where a need may exist to use Operational Intertripping,
emergency switching, emergency Demand management or other measures
including restrictions (and reasons for such restrictions) on the Dispatch of the units
to allow the security of the Total System to be maintained within the Licence
Standards.
It should be noted that the actual status of Grid System may be affected by other
factors which may not be known at the time of the plan as well as during the update,
thus GSO may change the planned outage schedule when in GSO’s opinion such
changes are necessary in order to maintain secure and reliable Grid System
operations.
(2) the expected start date and start time of the Unplanned Outage;
(3) the estimated return to service time and date of the Plant and Apparatus
affected, and the time and date of the removal of any temporary capacity
restrictions; and
(4) details of possible restrictions, or risk of trip, on other Plant and Apparatus due to
the Unplanned Outage.
The GSO may request for changes to be made to an Unplanned Outage programme when in
the opinion of the GSO such Unplanned Outage would adversely affect the security of the
Total System. The party will send a written confirmation to the GSO agreement or
disagreement of the new Unplanned Outage date and time in writing but where this is not
possible, it may be provided by telephone or other electronic means provided that a written
record of the agreement or disagreement is kept by the GSO and the party.
For a Forced Outage, the GSO shall take all reasonable measures to maintain the integrity
and security of the Grid System.
By 1700 hours each Monday, Tuesday, Wednesday and Thursday the GSO shall prepare a
final Transmission Network outage programme for the following day.
OC3.1 INTRODUCTION
In order to keep the Frequency of the Grid System close to the nominal Frequency of 50.0Hz,
the balance between demand and generation has to be maintained at all times. Thus GSO
not only has to keep sufficient generation to satisfy the System Demand and Losses but also:
additional Spinning Reserve needs to be maintained to cater for demand forecast
error as well as large disturbances especially tripping of large Generating Units or
large demand; and,
Contingency Reserve to cover for the loss of the Spinning Reserve once such reserve
has diminished.
OC3 describes various types of reserve which have to be available in a number of time
scales, which the GSO is expected to utilise in the provision of the Operating Reserve
OC3.2 OBJECTIVE
The objective of OC3 describes the types of reserves which shall be utilised by the GSO to
ensure safe and reliable operation of the Grid System.
Responses of the System to the changes of Frequency cover various time frames:
Instantaneous inertia response of the System as the frequency changes;
Governor response of Synchronised Generating Units; this is also known as primary
response which is the additional MW output available from the Generating Units 5
seconds after initial event and should be sustained for the next 25 seconds)
AGC response or manual adjustment of Generating Units MW output; this is also
known as the secondary response of the Generating Units which is the additional
MW output available from the Generating Units 30 seconds after the event and
should be sustained for next 30 minutes
OC3.3 SCOPE
This Code applies to the GSO and the following Users:
(1) Single Buyer;
(2) Generators with CDGUs;
(3) Distributors, Network Owners and Directly Connected Customers who have
agreed to undertake Demand Control; and
(4) Interconnected Parties.
90 5 5
Note: For combined cycle Generating Units the Rated MW Capacity shall be based on the aggregated
declared MW Capacity of each Generating Unit.
The Distributed Control System (DCS) of the power plant must not restrict or limit
generation output, delay the response time or modify the deadband setting and range of
spinning reserve response, unless it is approved by GSO.
Sufficient Spinning Reserve has to be kept to ensure that there is no loss of demand
should one of the above mentioned contingencies arise.
Generators shall register this data, in the format agreed with the Grid Owner and GSO
under the Planning Code (PC) which is termed as the Registered Data and verified under
OC10 and any revisions thereto shall also be notified under PC and SDC1.
OC4.1 INTRODUCTION
Operating Code No. 4 (OC4) is concerned with the procedures to be followed by the GSO
and Users to initiate reductions in Demand in the event that generation is insufficient to
meet forecast or real-time Demand, or shortfall of generation due to tripping of Generating
Units or tripping of an importing Interconnector. In addition, these provisions shall be used
by the GSO to prevent an Abnormal Overload of Apparatus or Plant within the Grid System,
or to prevent a voltage collapse.
Demand Control shall include but not limited to the following actions on load or demand:
(1) Automatic load or demand shedding;
(2) Manual load or demand shedding including Demand Side Management (DSM);
and
(3) Reduction of load through voltage reduction
OC4.2 OBJECTIVES
The objective of OC4 is to establish procedures such that the GSO in consultation with the
Grid Owner shall endeavour, as far as practicable, to spread Demand reductions equitably.
OC4.3 SCOPE
OC4 applies to the GSO and the following Users:
(a) Generators;
(b) Grid Owner;
(c) Distributors;
(d) Directly Connected Customers;
(e) Single Buyer;
(f) Interconnected Parties.
and Demand may cause excessive power transfers across the Grid System. Should such
transfers endanger the stability of the Grid System or cause a risk of damaging its Plant or
Apparatus, the pattern of Demand reduction shall be adjusted to secure the Grid System,
notwithstanding the inequalities of Disconnection that may arise from such adjustments.
that normal operation can be resumed. The GSO will inform Generators with CDGUs when
normal Scheduling and Dispatch in accordance with the SDCs is to be re-implemented, as
soon as reasonably practicable.
Demand Control will be achieved by telephone instructions in the case of instructed
Demand Control, to each relevant User and by direct switching by the GSO in the case of
manual Demand Control.
Whether a Yellow, Orange or Red warning has been issued or not each relevant User shall
abide by the instructions of the GSO with regard to Demand Control without delay.
The Demand Control must be achieved as far as possible uniformly across all Grid Supply
Points unless otherwise instructed by the GSO.
In circumstances of protracted shortage of generation or where a statutory instruction has
been given (e.g. a fuel security period) and when a reduction in Demand is envisaged by the
GSO to be prolonged, the GSO will notify the relevant Users of the expected duration.
Each User shall abide by the instructions of the GSO with regard to the restoration of
Demand under this OC4.5 without delay. The User shall not restore Demand until it has
received such instruction from GSO. The restoration of Demand must be carried out within
two (2) minutes of the instruction being given by the GSO.
Each relevant User will notify the GSO in writing that it has complied with instructions of the
GSO under this OC4.5, within ten (10) minutes of so doing, together with an estimation of
the Demand Reduction or restoration achieved, as the case may be.
around 10% of the Grid System total Peak Demand or otherwise as determined by
the GSO in accordance with the requirements of the Grid System. The purpose of
this is to seek to limit the consequences of potential voltage instability.
Each User shall upon the instruction of the GSO implement, test, and maintain
automatic voltage load shedding to the quanta as specified by GSO.
The GSO shall monitor the performance of the under voltage load shedding scheme
using data from system disturbances. Users shall make available all the data by
which the GSO can monitor the performance of the scheme. GSO has to conduct
annual review of the automatic under frequency load shedding scheme.
OC5.1 INTRODUCTION
Operating Code No. 5 (OC5) sets out the requirements for the exchange of information in
relation to the Operations and/or Events on the Grid System or a User installation, which
have had or may have an Operational Effect on the Grid System or other User’s installation
and not the reason why.
When reporting an Event or Operation that has occurred on the Grid System which has
been caused by (or exacerbated by) an Operation or Event on a User's System, GSO in
reporting the Event or Operation on the Grid System to another User can pass on what it
has been told by the first User in relation to the Operation or Event on the first User's
System.
OC5.2 OBJECTIVES
The objectives of OC5 is to ensure that the exchange of information that is needed in order
that possible risks arising from the Operations and/or Events on the Grid System and/or
User installations can be assessed and appropriate action taken. OC5 does not seek to deal
with any actions arising from the exchange of information but rather only with that
exchange;
OC5.3 SCOPE
OC5 applies to the GSO and Users which in OC5 means:
(a) Network Owner;
(b) Generators;
(c) All Generators with Generating Units not subject to Dispatch by the GSO, with
total on-site generation capacity greater than or equal to 1.0 MW where the GSO
considers it necessary;
(d) Large Power Consumers where the GSO considers it necessary; and
(e) Interconnected Parties.
The term Operational Effect means any effect that the operation of a System which will or
may cause the Grid System or other User’s system to operate (or be at a materially
increased risk of operating) differently to the way in which it would or may have normally
operated in the absence of that effect.
(a) the operation of Plant and/or Apparatus in excess of its capability or which may
present a hazard to personnel;
(b) activation of an alarm or indication of an abnormal operating condition;
(c) adverse weather condition;
(d) breakdown of, or faults on, or temporary changes in, the capability of Plant and/or
Apparatus;
(e) breakdown of, or faults on, control, communication and metering equipment;
(f) increased risk of unplanned protection operation; and
(g) abnormal operating parameters, such as governor problem, fuel system trouble,
high temperature, etc.
Significant Incidents shall be reported in writing to the affected parties in accordance with
OC6.
OC6.1 INTRODUCTION
Operating Code No. 6 (OC6) sets out the requirements for reporting of Significant Incidents.
OC6 also provides for joint investigation of Significant Incidents by the Users involved and
the GSO.
OC6.2 OBJECTIVES
The objectives of OC6 are:
(a) to facilitate the provision of detailed information in reporting Significant
Incidents; and
(b) to facilitate joint investigations of Significant Incident by GSO and relevant
Users.
OC6.3 SCOPE
OC6 applies to the GSO and the following Users:
(a) Single Buyer;
(b) Grid Owner;
(c) All Generators;
(d) Network Owners;
(e) Large Power Consumers where the GSO considers it necessary; and
(f) Interconnected Parties.
contact locations and the communication channels, the GSO and User shall promptly inform
each other in writing.
In the case of an Event which has been reported to the GSO under OC5 by the User and
subsequently determined to be a Significant Incident by the GSO or User, a written report
shall be given to the GSO by the User involved in accordance with OC6.5.
In the case of an Event which has been reported to the User under OC5 by the GSO and
subsequently determined to be a Significant Incident by the GSO or User, a written report
shall be given to the User involved by the GSO in accordance with OC6.5.
In all cases, the GSO shall be responsible for the writing the final report before issuing to all
relevant parties, including the Energy Commission.
additional time up to two (2) calendar months to carry out the relevant
investigations and submit the final report
The preliminary and final Significant Incident report shall be circulated by the GSO
to other relevant Users and the Energy Commission. In the case of Significant
Incidents affecting the operation of a CDGU or an Interconnected Party a copy of
the report shall also be submitted to the Single Buyer.
OC7.1 INTRODUCTION
Operating Code No.7 is concerned with the considerations that need to be taken in
developing a System Restoration Plan for the Grid System after a Partial or Total Blackout.
OC 7 requires the GSO working with Grid Owner and other relevant Users to develop a
System Restoration Plan. This Plan has to be reviewed annually. OC 7 covers the strategy for
speedy and efficient restoration and some of the major considerations in developing the
Restoration Plan.
As there will always be unanticipated problems and/or issues encountered during the
restoration process, GSO is expected to modify the restoration procedures. Thus it is
important that all Users have to abide by the instructions given by GSO unless to do so
would endanger life or would cause damage to Plant or Apparatus.
OC7.2 OBJECTIVES
The objective of OC7 is to ensure that in the event of a Partial Blackout or a Total Blackout
normal supplies can be restored to all Consumers as quickly and as safely as practicable.
OC7.3 SCOPE
OC7 applies to the Single Buyer, GSO, and the following Users:
(a) Grid Owner;
(b) Network Owners;
(c) Generators;
(d) Distributors;
(e) Large Power Consumers identified by the GSO who may be involved in the
restoration process; and
(f) Interconnected Party
circuit breakers at affected (blacked out) substations are opened. The second strategy is the
“selective opened” where only a few selected breakers are opened in the affected
substations.
The “all opened” strategy is used for power station switchyards and GIS substations. The
advantages of this strategy are:
simpler and safer configuration to re-energize.
large voltage and frequency deviations due to inadvertent load pickup is less likely to
occur.
The closing mechanism of circuit breakers is either using compressed air or charged up
springs. If all the circuit breakers are opened during the blackout event, there is a possibility
that the remaining compressed air or the remaining charge of the battery is insufficient for
the proper operation of the circuit breaker closing mechanism. This will cause a delay in
energising the substation as standby Generators need to be used to run the compressor to
charge up the air or charge up the battery.
With the “selective opened” strategy the above mentioned potential problem can be
avoided. The “selective opened” switching strategy, can be further divided into two
categories:
Where all circuit breakers are opened except one incoming HV circuit breaker, the
HV circuit breaker of one transformer and its associated LV circuit breaker which is
connected to the station LV auxiliary bus bar. The substation auxiliary supply will
immediately come alive when the HV line is energised from the remote end. Thus AC
supply is immediately available to run the air compressor or to charge the batteries.
Where all circuit breakers in the affected substation remain in the close positions so
that once the remote end circuit breaker is closed the substation is normalised. This
strategy can only be used if GSO is sure that the total load of the substation is equal
to or less than 5% of the gross capacity of all the Synchronised Generators of the
subsystem or system. The advantage of using this approach is that there will be less
switching operations required and hence helps to speed up the restoration time.
Whether GSO adopt “all opened” or “selective opened” strategy in breaking up the
transmission network to form Power Islands for speedy restoration, it is imperative that the
circuit breakers of the lines connecting two substations at the borders of the Power Islands
must be opened at both ends to avoid inadvertent crash synchronisation during restoration.
It is important that all Users identified under OC7 make themselves fully aware of the
System Restoration Plan, as failure to act in accordance with the GSO’s instructions will risk
further delay in the restoration.
Once a line has been energised successfully, it is best to give supply to some
local load to reduce the voltages. Successive energisation of a line followed
by that of a load will be a good strategy to control the voltages to within
acceptable ranges.
GSO needs to balance the reactive supply and reactive demand of the
System by continuously monitoring of bus bars voltages throughout the
System.
Only energise lines that will carry significant load. Energising extra lines will
generate unwanted VARs.
Voltages at the transmission substations should be maintained at the
minimum possible levels (below 1.0pu) to reduce line charging currents of
unloaded or under loaded transmission lines.
Tap changers of transformers should be adjusted to nominal tap before the
transformers are energised.
Ferroresonance may occur upon energizing a line or while picking up a
transformer from an unloaded line.
Reduction in proper relaying protection reliability due to insufficient fault
current.
Both systems must be in a stable state and both frequencies must be near to
50.0 Hz
A voltage difference of about 0.05pu or less between the Power Islands.
A frequency difference between two Power Islands shall be less than 0.15
Hz.
After synchronising two Power Islands, nominate a particular Power Station to do
the frequency control for the combined larger Island. If the frequency regulation
burden becomes too large for a particular Power Station, the frequency regulation
should be transferred to a larger Power Station. If more than one Power Station
controls frequency, there would be a hunting effect. Units not assigned to regulate
frequency should be constantly re-dispatched to keep each regulating unit’s MW
output level at the middle of its regulating range.
Each Generator shall continue to operates its CDGUs in accordance with the last Dispatch
Instruction issued by the GSO but shall use all reasonable endeavours to maintain the Grid
System Frequency close to 50 Hz by monitoring Frequency and increasing or decreasing the
output of its CDGUs as necessary until such time as new Dispatch Instructions are received
from the GSO.
The GSO shall prepare all the necessary plans and procedures and from time to time conduct
the necessary exercises to ensure that a satisfactory change-over can be achieved without
prejudicing the integrity of the Grid System.
OC8.1 INTRODUCTION
Operating Code No.8 specifies the procedures to be used by the GSO and Users for the
co-ordination, establishment and maintenance of necessary Safety Precautions when
work and/or test is to be carried out on the Grid System or a User System and when
there is a need for Safety Precautions on HV Apparatus on the other User System or
Grid System for this work to be carried out safely.
In this OC8 the term “work” includes testing, other than System Tests which are
covered by OC11.
OC8.2 OBJECTIVES
The objectives of OC8 is to ensure safe working conditions for personnel working on or
in close proximity to Plant and Apparatus on the Transmission Network or User
Network or personnel who may have to work on or use the equipment at the interface
between the Transmission Network and a User Network where isolation and/or
earthing is required from both Systems.
OC8.3 SCOPE
OC8 applies to the GOS and the following Users:
(a) Generators;
(b) Network Owner;
(c) Large Power Consumers directly connected to the Transmission
Network;
(d) Interconnected Parties and
(e) any other party reasonably specified by the GSO.
OC8.4 PROCEDURES
OC8 does not seek to impose a particular set of Safety Rules on the GSO, Grid Owner
and other Users. The Safety Rules to be adopted and used by the GSO, Grid Owner
and each User shall be those chosen by each party’s management.
At all Connection Points, the Safety Rules to be used by both the Grid Owner and the
relevant Users shall be as determined by the Grid Owner after consultation with the
GSO.
For each of the Connection Site, GSO and the relevant User shall formulate a sequence
of switching for safe isolation and earthing in order to achieve the necessary Safety
Precautions for the issuance of RISP as well as the switching sequence to normalise
back the system after the cancellation of RISP. These switching sequences and the
relevant Single Line Diagrams of the Connection Site are to be included in the
Interconnection Operation Manual for that Site.
2
The Isolation Notice shall warn against interfering with the point of isolation, in accordance with Energy
Sector Safety Laws.
other party, then that other party will make such changes as soon as
reasonably practicable. Approval may not be withheld because the party
required to approve reasonably believes the provisions relating to Isolation
and/or Earthing are too stringent.
If, following approval, a party wishes to change the provisions in its Local
Safety Instructions relating to Isolation and/or Earthing, it must inform the
other party. If the change is to make the provisions more stringent, then the
other party merely has to note the changes. If the change is to make the
provisions less stringent, then the other party needs to approve the new
provisions.
The procedures for the establishment of safety coordination by the GSO with
an Interconnected Party are set out in an Interconnector Agreement with the
Interconnected Party.
Part 1
1.1 H.V. APPARATUS IDENTIFICATION
1.2 I, ............................................…………………………………………...(the Requesting Safety Coordinator) located at
......................................................…………… declare that I would like to carry out work on the following Apparatus:
........................................................................................................................................……………………………
1.3 Mr………………………………..(the Implementing Safety Coordinator) has declared that he will carry out work on the
following Apparatus:
………………………………………………………………………………………………………..…………………………………………………………………
1.4 SAFETY PRECAUTIONS ESTABLISHED BY THE REQUESTING SAFETY COORDINATOR : State location, nomenclature,
and number of each point of isolation and earthing to be implemented.
ISOLATION : ………………………………………………………………………………………………………..
EARTHING : ………………………………………………………………………………………………………..
1.5 SAFETY PRECAUTIONS REQUESTED BY THE REQUESTING SAFETY COORDINATOR ISOLATION :
State location, nomenclature, and number of each point of isolation requested.
ISOLATION : ……………………………………………………………………………………………………….
EARTHING : ……………………………………………………………………………………………………….
Part 2
2.1 CONFIRMATION OF ISOLATION AND EARTHING BY REQUESTING SAFETY COORDINATOR AND IMPLEMENTING
SAFETY COORDINATOR.
2.2 I, ................................…………....(the Requesting Safety Coordinator), located at ..................................…………….
confirm to ………………………..(the Implementing Safety Coordinator) located at ……………………………that the SAFETY
PRECAUTION as mentioned in Section 1.4 of this RISP has been established. The switches have been immobilised,
locked and Notices have been affixed.
2.3 Mr....................................(the Implementing Safety Coordinator), located at........................................................
has confirmed to me that the SAFETY PRECAUTIONS as mentioned in section 1.5 has been established.
The switches have been immoblised, locked, and Notices have been affixed.
No instructions will be issued at locations as specified in 1.4 and 1.5 for their removal until this RISP is cancelled
under Part 3.
Part 3
3.1 CANCELLATION
Cancellation of this RISP must only be done after both parties have confirmed completion of work as mentioned in
Section 1.2 and 1.3.
3.2 I, …………………………………… (the Requesting Safety Coordinator), located at …………………………………....declared that
the work as mentioned in Section 1.2 is completed.
Signed : ....................................…….. Date : ...........................……
The Requesting Safety Coordinator. Time:...................................
3.3 Mr. ………………….(the Implementing Safety Coordinator), located at ………………………, has confirmed that the work as
mentioned as Section 1.3 is complete.
Signed : ......................................… Date : ...........................……
The Requesting Safety Coordinator. Time:.....................................
3.4 I, ……………………………………. (the Requesting Safety Coordinator), located at ………………………….. and Mr.
……………………………………(the Implementing Safety Coordinator), located at ………………. Agree that This RISP is
hereby cancelled.
Signed : .........................................…… Date : .........................…
The Requesting Safety Coordinator. Time:....................................…..
Part 2
2.1 CONFIRMATION OF ISOLATION AND EARTHING BY REQUESTING SAFETY COORDINATOR AND IMPLEMENTING
SAFETY COORDINATOR.
2.2 Mr, ................................……....(the Requesting Safety Coordinator), located at ..................................……… .has
confirmed to me ……………………..(the Implementing Safety Coordinator) located at ……………………………that the
SAFETY PRECAUTION as mentioned in Section 1.4 of this RISP has been established. The switches have been
immobilised, locked and Notices have been affixed.
2.3 I,.....................................(the Implementing Safety Coordinator), located at...............................................….have
confirmed to Mr……………………………(the Requesting Safety Coordinator), located at……………………….that the SAFETY
PRECAUTIONS as mentioned in section 1.5 has been established.
The switches have been immoblised, locked, and Notices have been affixed.
No instructions will be issued at locations as specified in 1.4 and 1.5 for their removal until this RISP is cancelled
under Part 3.
Part 3
3.1 CANCELLATION
Cancellation of this RISP must only be done after both parties have confirmed completion of work as mentioned in
Section 1.2 and 1.3.
3.2 Mr,…………………………………… (the Requesting Safety Coordinator), located at ………………………...has .confirmed that
the work as mentioned in Section 1.2 is completed.
Signed : .........................................…….. Date : ...........................……
The Implementing Safety Coordinator. Time:......................................
3.3 I, ………………….(the Implementing Safety Coordinator), located at ………………………, has confirm that the work as
mentioned as Section 1.3 is complete.
Signed : ..................................... Date : ...........................……
The Implementing Safety Coordinator. Time:......................................
3.4 Mr, ……………………………………. (the Requesting Safety Coordinator), located at ………………………….. and I,.
……………………………………(the Implementing Safety Coordinator), located at ………………. agree that This RISP is
hereby cancelled.
Signed : ..................................… Date : ...........................….
The Implementing Safety Coordinator. Time:....................................….
OC9.1 INTRODUCTION
Numbering and nomenclature of Apparatus in the Grid System facilitates safe
operation and control of the Grid System by the GSO. Operating Code No.9 (OC9)
sets out the requirement for numbering and nomenclature of HV Apparatus
located in Transmission Network and User Network.
All Apparatus in the Grid System that are and will be under the control of the
GSO shall have numbering and nomenclature in accordance with the system
specified in this OC9 or as determined by the GSO.
The numbering and nomenclature of each item of HV Apparatus shall be included
in the Single Line Diagram prepared for each Site of the Grid Owner or User Site.
The numbering and names are also used in the labelling of equipment including,
towers, apparatus, control panels and diagrams.
OC9.2 OBJECTIVE
The objective of this OC9 is to ensure the safe and effective operation of the Grid
System and to reduce the risk of human error by requiring that the numbering and
nomenclature of all HV Apparatus of Grid Owner’s Transmission Network and User's
HV Apparatus at Connection Points shall be in accordance with the system used by the
GSO as specified in this OC9. This is to provide consistent and unambiguous numbering
and nomenclature for apparatus in the Grid System
OC9.3 SCOPE
OC9 applies to the GSO and the following Users:
(b) Generators;
(c) Distributors
(d) Network Owner directly connected to the Transmission Network
(e) Large Power Consumers directly connected to the Transmission
Network; and
(f) Interconnected Parties.
OC9.4.1 General
The term "User Site" means a site owned (or occupied pursuant to a lease,
licence or other agreement) by a User in which there is a Grid Supply Point. For
the avoidance of doubt, where a site is owned by the Grid Owner but occupied
by other User, the site is a User Site.
The term "Site of the Grid Owner” means a site owned (or occupied pursuant
to a lease, licence or other agreement) by the Grid Owner which there is a Grid
Supply Point. For the avoidance of doubt, where a site is owned by a User but
occupied by the Grid Owner, the site is Site of the Grid Owner.
The notification will be made in writing to the GSO and shall consist of a
proposed Operation Diagram incorporating the proposed new HV Apparatus of
the User to be installed.
The GSO will respond in writing to the User within two (2) months and provide
details of the numbering and nomenclature which the User shall adopt for that
HV Apparatus. The User shall adopt the numbering and nomenclature within
six (6) months of the details being provided by the GSO. GSO is to inform other
affected Users about the changes.
OC9.4.3 Changes
Where the GSO in its reasonable opinion has decided that it needs to change
the existing numbering or nomenclature of HV Apparatus of the Grid Owner
on other User's Site or of User's HV Apparatus at Grid Supply Point:
a) the provisions of paragraph OC9.4.1 shall apply to such change of
numbering or nomenclature of HV Apparatus of the Grid Owner
with any necessary amendments to those provisions to reflect that
only a change is being made; and
b) in the case of a change in the numbering or nomenclature of User's
HV Apparatus on a Grid Supply Point, the GSO will notify the User of
the numbering and/or nomenclature the User shall adopt for that HV
Apparatus (the notification to be in a form similar to that envisaged
under OC9.4.1) at least eight (8) months prior to the change being
needed and the User will respond in writing to the GSO within two
(2) months of the receipt of the notification, confirming receipt. The
User shall then inform any other effected or related User, and shall
adopt the numbering and nomenclature within six (6) months of the
details being provided by the GSO.
When either the Grid Owner or other User installs HV Apparatus which is the
subject of OC9, the Grid Owner or other User, as the case may be, shall be
responsible for the provision and erection of clear and unambiguous labelling
showing the numbering and nomenclature.
Where a User is required by OC9 to change the numbering and/or
nomenclature of HV Apparatus which is the subject of OC9, the User will be
responsible for the provision and erection of clear and unambiguous labelling
by the required date.
Where the Grid Owner changes the numbering and/or nomenclature of its HV
Apparatus which is the subject of OC9, the Grid Owner will be responsible for
the provision and erection of clear and unambiguous labelling showing the
numbering and nomenclature by the required date.
The GSO will not change its system of numbering and nomenclature in use
other than to reflect new or newly adopted technology or HV Apparatus.
< End of the Operating Code No.9: Numbering and Nomenclature >
1 STATIONS
1.1 Substation (Switching or Transformer Substation)
(a) No substation shall be given the same name or any name that can be confused
with any other substation or Power Station on the Grid System.
(b) Where two or more substations are in the same vicinity, each substation may be
named independently. The substations can be given the same name followed by
its respective voltage or suitable suffix.
e.g. Beaufort
Inanam
Penampang North
Penampang South
Kota Kinabalu 66kV
Kota Kinabalu 132kV
1.2 Generating Units
(a) No Power Station shall be given the same name or any name that can be
confused with any other substation or Power Station on the Grid System.
(b) Where two or more Power Stations are in the same vicinity, each Power Station
may be named independently. The generating stations can be given the same
name followed by suitable suffix:
e.g. Kota Kinabalu
Sepangar
Sepangar A
Sepangar B
2 CIRCUITS
2.1 Designations
(a) A circuit connecting two substations at different locations shall be designated by
the names of the two substations concerned:
e.g. Penampang – Beaufort
(b) A circuit connecting three or more substations, i.e., a circuit with tee offs, shall
be designated by the names of all the substation locations concerned:
e.g. Penampang – Beaufort– Pangi
(c) Parallel circuits between the same substations shall be designated in accordance
with Paragraphs a) or b) above and shall be numbered consecutively:
e.g. Penampang – Inanam 1
Penampang – Inanam 2
Penampang – Beaufort – Pangi 1
(d) Where two substations are interconnected by different voltage levels than the
respective nominal voltage should be used as suffixes:
e.g. Kolopis - Segaluid 275 kV
Kolopis - Segaluid 132 kV
2.2 Labelling
Switchgear panels, protection equipment panels, and metering panels associated with a
circuit shall be labelled in accordance with the preceding paragraphs, except that the location
of the equipment concerned shall be omitted. At substations where the line is terminated
with a transformer, the designation of the transformer or transformer bank shall be followed
by the circuit designation in brackets:
3 BUSBARS
The numbering and nomenclature of busbars other than those associated with generating
plant auxiliaries shall be as follows:
a) Nominal busbar voltage (275 kV, 132 kV, etc.);
b) Busbar identification (Main Busbar, Reserve Busbar, Transfer Bus);
c) Busbar number or section number (1,2,3, etc.) e.g. 275 kV Main Busbar 1;
d) Sections of busbars of the same nominal voltage and identification shall be
numbered consecutively from one end of the substation to the other. Main and
reserve busbars shall have corresponding numbering;
e) In the case of substations where one section of reserve busbar is common to two
sections of main busbar, the section of reserve busbar shall bear the numbers of
both corresponding sections of main busbar:
e.g. 275 kV Main Busbar 1
275 kV Main Busbar 2
275 kV Reserve Busbar 1/2
f) The busbar section number shall be omitted in those cases where the busbar
identification for a particular voltage is applicable to a single busbar having no
sectioning facilities:
e.g. 275kV Main Busbar
4 TRANSFORMERS
The numbering and nomenclature of transformers connected to the Grid System other than
those directly associated with Generating Units and auxiliaries and, shall be as follows:
a) A transmission transformer shall be designated by the nominal voltage ratio of its
windings. All transmission transformers and local station transformers shall be
numbered uniquely in relation to each other and to other transformers at a
particular location:
e.g. 275/132/11 kV Transformer 1
275/132/11 kV Transformer 2
132/11 kV Station Transformer 1
132/11 kV Station Transformer 2
66/11 kV Station Transformer 1
The number and nomenclature of transformers directly associated with Generating Units shall
be as follows:
a) A transformer connecting a Generating Unit to the Transmission Network shall
be designated as Generator Transformer and shall be numbered the same as the
associated generator:
e.g. Generator Transformer 1
b) A transformer that provides Power Station auxiliary supply but is not directly
connected to a Generating Unit, shall be designated Station Transformer. All
such transformers shall be numbered consecutively at a particular location
e.g. Station Transformer 1
c) A transformer that provides Power Station auxiliary supply and is directly
connected to a Generating Unit shall be designated Unit Transformer and shall
be numbered the same as the associated Generator:
e.g. Unit Transformer 1
d) Other transformers associated with Power Station auxiliaries shall be designated
according to their service. Where appropriate, transformers shall be numbered
the same as the associated Generating Unit, consecutive letters being added
where necessary. Otherwise, transformers shall be numbered consecutively for
each designation throughout the Power Station:
e.g. Plant Transformer 1
5 OPEN-TYPE SWITCHGEAR
The nomenclature of 132kV switchgear, including the isolators and earthing switches, shall be
the name and number of the associated equipment followed by a description of the function of
the particular item of switchgear:
e.g. Kepayan Feeder No. 1 Circuit Breaker
Kepayan Feeder No. 2 Main Busbar Isolator
The numbering of 132 kV switchgear, including isolators and earthing switches, shall be three
numbers:
a) The first number shall be used to denote the sequence of switch groups in any
one class in a substation:
i. In the case of a Generator Circuit, the first number shall be the generator
number.
ii. In the case of a transformer circuit connecting busbars at the same
location, the first number shall be the number of the transformer or
transformer bank.
iii. If possible, the switch groups of line circuits shall be numbered
consecutively from an end of the substation that is not designed to be
extended. The lower switchgear group number shall follow the lower line
circuit number and the switchgear group number of a particular line
circuit shall be the same at both ends.
iv. A transformer circuit connecting busbars at different locations (i.e.
transformer feeder or transformer interconnector) shall be considered as
a transformer circuit at the location of the transformer only, with the
exception that line numbering be applied in the case of an earthing
switch on the line side of the circuit isolator. Other terminations of the
circuit shall be considered as a line circuit.
b) The second number shall be used to denote the class of switch group as given in
the table below:
TABLE I
0 Line
1 Transformer high voltage side
2 Main busbar section or Interconnector (within a substation)
3 Busbar coupler
4 Static shunt compensators (e.g. reactors, capacitors, etc.)
5 Static series compensators (e.g. reactors, capacitors, etc.)
6 Reserve busbar section
7 Rectification equipment
8 Transformer low voltage side
9 Generator Synchronous compensator
Switchgear inserted in lines associated with teed circuits at a location other than the
high voltage terminations of the circuits shall be considered as a main busbar section.
c) The third number shall be used to denote the function of the switch in the group
as given in the table below:
TABLE II
Conventional isolator numbering shall be used where a switching isolator is provided primarily
as a point of isolation within the requirements of the Safety Rules.
d) Where more than one item in a group qualifies for a particular number the
number shall be suffixed by consecutive termination letters, commencing from
the circuit inwards to the busbar selector isolators.
e) In the case of banked circuits, the number shall be suffixed by the identification
letter of the appropriate circuit in those instances where the items are not
common to all the circuits of the bank. In general, a suffix shall not be used for
items common to all circuits of the bank except in those instances where the
number is repeated, when an appropriate letter suffix shall be added.
f) In the case of multiple earthing switches used in gas insulated switchgear (GIS)
the same earthing switch number is to be used followed by suffix in alphabetical
order a, b and c
a) A letter shall precede two numbers and shall be used to denote the class of
switch group as given in the following table:
TABLE III
L Line
H Transformer high voltage side
S Main busbar section or Interconnector (within a substation)
W Busbar coupler
R Static shunt compensators (e.g., reactors, capacitors, etc.)
P Reserve busbar section
Z Rectification equipment
M Generator or Synchronous Compensator
T Transformer low voltage side
Switchgear inserted in lines associated with teed circuits at a location other than the high
voltage terminations of the circuits shall be considered as a main busbar section.
b) The first number shall be used to denote the sequence of switch groups in any
one class in a substation. The number shall be derived in accordance with Section
5.1a.
c) The second number shall be used to denote the function of the switch in the
group as given in Table II.
The numbering and nomenclature of busbar section, busbar coupler, busbar interconnector
switches and busbar reactor switches shall be as follows:
a) Switchgear provided for coupling main and reserve busbars shall be named BUS
COUPLER preceded by the nominal busbar voltage and followed by the section
number(s):
e.g. 11 kV Bus Coupler 33kV
b) Switchgear provided for sectioning main or reserve busbars shall be named BUS
SECTION preceded by the nominal busbar voltage and identification and followed
by the adjacent section numbers:
SYMBOLS
CLASS TITLE
275 kV 132 kV LV
Static Shunt Compensator Circuit Breaker R*0 *40 *R0
Compensator Compensator Earthing Switch R*1 *41 *R1
Compensator Isolator R*3 *43 *R3
Main Busbar Selector Isolator (1st choice) R*4 *44 *R4
Compensator Circuit Breaker (where 2 per R*5 *45 *R5
compensator)
Reserve Busbar Selector Isolator (1st choice) R*6 *46 *R6
Circuit Breaker Isolator (Busbar side)
Main Busbar Selector Isolator (2nd choice) R*7 *47 *R7
Compensator Tie Busbar Isolator or Busbar Selector R*8 *48 *R8
Isolator (2nd choice) R*9 *49 *R9
Transformer Transformer Circuit Breaker T*0 *80 *T0
Low Transformer Earthing Switch T*1 *81 *T1
Voltage Side Transformer Isolator T*3 *83 *T3
Main Busbar Selector Isolator T*4 *84 *T4
Switching Isolator + T*5 *85 *T5
Reserve Busbar Selector Isolator T*6 *86 *T6
Generators Generator Circuit Breaker (where 2 per generator, M*0 *90 *M0
main Busbar)
Generator Transformer Earthing Switch M*1 *91 *M1
Bypass Isolator
Generator Transformer Isolator M*2 *92 *M2
Main Busbar Selector Isolator M*3 *93 *M3
Generator circuit Breaker (where 2 per generator M*4 *94 *M4
(reserve Busbar)) M*5 *95 *M5
Reserve Busbar Selector Isolator M*6 *96 *M6
Circuit Breaker Isolator (Busbar side) M*7 *97 *M7
Synchronous Synchronous Compensator-Main Circuit Breaker *M01
Compensators Synchronous Compensator-Starting Circuit Breaker *M02
Synchronous Compensator-Running Circuit Breaker
Synchronous Compensator Isolator *M03
*M3
Auxiliary Isolator associated with certain miscellaneous *A3
Equipment auxiliary equipment e.g. VT’s
OC10.1 INTRODUCTION
Operating Code No. 10 (OC10) specifies the procedures to be followed by the GSO, the
Single Buyer and the Users in coordinating and carrying out tests and monitoring to
ensure compliance by Users covering all parts of the Connection Codes, Generating
Unit Scheduling and Dispatch Code, as well as Ancillary Service Duties including
response to frequency, reactive capability, Fast Start Capability and Black Start
capability.
The GSO and the Single Buyer are responsible for facilitating and coordinating the
required testing and monitoring. The User is responsible for carrying out the test and
or monitoring in accordance with the relevant Agreement and or specifications issued
by the GSO and the Single Buyer.
Any User or the Single Buyer may propose any of the tests set out in this OC10 or any
relevant Agreements to be carried out and such request shall be made to the GSO. The
GSO shall consider such request and may approve and facilitate the test with due
regard to the safety, security and integrity of the Grid System.
OC10.2 OBJECTIVES
The objectives of OC10 is to establish procedures for the GSO and the Single Buyer to
facilitate, coordinate and/or carry out testing and monitoring the Grid System or the
User’s system at the Grid Supply Point to ensure compliance all parts of the
Connection Codes, Generating Unit Scheduling and Dispatch Code, as well as Ancillary
Service Duties including response to frequency, reactive capability, Fast Start
Capability and Black Start capability.
OC10.3 SCOPE
OC10 applies to the Single Buyer, GSO, Grid Owner and the following Users:
(1) Generators, including Generator with Power Park Module;
(2) Grid Owner;
(3) Distributor;
(4) Network Owners and
(5) Directly Connected Customers
The requirement for specific testing and/or monitoring may be initiated by the on
receipt of complaints by a User as to the quality of supply on its Grid System or by the
GSO where in the reasonable opinion of the GSO, such tests are necessary.
In certain situations, the GSO may require the testing and or monitoring to take place
at the point of connection of a User with the Grid System. This may require the User
to allow the GSO a right of access on to the User's property to perform the necessary
tests and/or monitoring on any equipment at the Supply Connection Point and/or
other equipment on the User's System where the GSO, deems necessary; such right to
be exercised reasonably five (5) Business Days after a prior written notice has been
served on the User.
After such testing and or monitoring has taken place, the GSO will advise the User
involved in writing within ninety (90) calendar days or such a period mutually agreed
between the parties and will make available the results of such tests to the User.
If the results of such a test show that the User is operating outside the technical
parameters specified in the Grid Code, the User will be informed accordingly in writing.
The GSO shall agree with the User a suitable timeframe to resolve those problems on
its User System, failing to do so may lead to the de-energisation of the User System as
indicated in the terms of the Connection Agreement.
OC10.6.1 General
The GSO or Single Buyer will monitor:
(a) the performance of CDGUs against the parameters registered as
generation Scheduling and Dispatch Parameters (SDP) under
SDC1 and other appropriate agreements;
(b) compliance by Generators with the CC; and
(c) the provision by Generators of Ancillary Services which they are
required to provide.
time, and would not, in the absence of exceptional circumstances, expect any
of the other CDGUs at the Black Start Station to be directly affected by the
BS Generating Unit Test.
(i) BS Generating Unit Tests
Where local conditions require variations in this procedure the Generator shall
submit alternative proposals, in writing, for the GSO’s prior approval. The
following procedure shall, so far as practicable, be carried out in the following
sequence for Black Start Tests:
(a) The relevant Black Start Generating Unit (BSGU) shall be
Synchronised and Loaded;
(b) All the auxiliary gas turbines and or auxiliary diesel engines and
or auxiliary hydro generator in the Black Start Station in which
that BSGU is situated, shall be shut down;
(c) The BSGU shall be de-Loaded and de-Synchronised and all
alternating current electrical supplies to its auxiliaries shall be
disconnected;
(d) The auxiliary gas turbine(s) or auxiliary diesel engine(s) to the
relevant BSGU shall be started, and shall re-energise the unit
board of the relevant BSGU;
(e) The auxiliaries of the relevant BSGU shall be fed by the auxiliary
gas turbine(s) or auxiliary diesel engine(s) or auxiliary hydro-
generator, via the BSGU’s unit board, to enable the relevant
BSGU to return to synchronous speed; and
(f) The relevant BSGU shall be Synchronised to the Power System
but not Loaded, unless the appropriate instruction has been
given by the GSO or Single Buyer under SDC2.
(ii) BS Station Tests
The following procedure shall, so far as practicable, be carried out in the
following sequence for Black Start Tests:
(a) All Generating Units at the Black Start Power Station, other than
the Generating Unit on which the Black Start Test is to be
carried out (BSGU) and all the auxiliary gas turbines and or
auxiliary diesel engines and or auxiliary hydro Generators at the
Black Start Power Station, shall be shut down;
(b) The relevant BSGUs shall be Synchronised and Loaded;
(c) The relevant BSGUs shall be de-Loaded and de-Synchronised;
(d) All external alternating current electrical supplies to the unit
board of the relevant BSGUs and to the station board of the
relevant Black Start Power Station shall be disconnected;
(e) An auxiliary gas turbine or auxiliary diesel engine or auxiliary
hydro generator at the Black Start Power Station shall be
started, and shall re-energise either directly, or via the station
board, or the unit board of the relevant BSGU; and
(f) The provisions of items (e) and (f) in OC10.7.5 (i) above shall
thereafter be followed.
All Black Start Tests shall be carried out at the time specified by the GSO or
Single Buyer and shall be undertaken in a manner approved by the GSO or
Single Buyer.
or delay its approval of the Generator proposed date and time submitted. The
Generator shall then be subjected to the relevant test procedures outlined in
OC10.7.
OC10.7.8 Tests for Generators and Power Park Module Prior to
Commercial Operation Date
Before the Commercial Operation Date (COD), Generator and Power Park
Module shall conduct the following tests to prove the full compliance of the
required performance:
i. Grid Frequency Variation
ii. Reactive Power
iii. Grid Voltage Variation
iv. Fault Detection and Clearing Limits
v. High Frequency MW Response
vi. Ramp Rate
vii. Power Quality of Service
viii. Facility Parameters and Characteristics
ix. Machine Model Validation
x. Automatic Generation Control
xi. Power System Stabiliser
Generator or Power Park Module must submit a proposed site test procedure
for Grid Owner and GSO’s review in accordance with the provisions of the
connection Agreement. The test procedures shall be based on the latest
revision of SESB Testing Guidelines for Generator and Power Park Modules (as
amended from time to time).
Where the tests required under this paragraph are not addressed in the SESB’s
Testing Guidelines for Generator and Power Park Modules, Generator shall
propose to GSO appropriate test procedures based on the relevant standards
and guidelines in accordance with the provisions of this Agreement and
acceptance. In the absence of any such standards or guidelines, Prudent Utility
Practices or OEM standards shall, subject to the prior written consent of the
GSO and Grid Owner, be applied by Generators.
OC11.1 INTRODUCTION
Operating Code No. 11 (OC11) sets out the responsibilities and procedures for
arranging and carrying out System Tests which may have a significant impact upon the
Grid System or the User’s System including an Interconnected Party’s.
A “System Test” is a test which involves either a simulated or a controlled application
of irregular, unusual or extreme conditions on the Grid System or a User’s System. In
addition it includes commissioning and or acceptance tests on Plant and Apparatus to
be carried out by GSO or by Users which may have a significant impact upon the Grid
System, other User Systems or the wider Power System.
To minimise disruption to the operation of the Grid System and to other User Systems,
it is necessary that these tests be subjected to central coordination and control by the
GSO.
Testing of a minor nature carried out on isolated Systems or those carried out by the
GSO or Single Buyer in order to assess compliance of Users with their design, operating
and connection requirements as specified in this Grid Code and in their Connection
Agreement are covered by OC10.
OC11.2 OBJECTIVES
The objectives of OC11 are to;
(a) ensure that the procedures for arranging, facilitating and carrying out
System Tests do not, so far as is practicable, threaten the safety of
personnel or members of the public and minimise the possibility of
damage to Plant or Apparatus or the security of the Grid System; and
(b) set out procedures for preparing and carrying out System Tests and
(c) set out procedures for reporting of System Tests.
OC11.3 SCOPE
OC11 applies to the Single Buyer, GSO and the following Users:
(a) All Generators;
(b) Grid Owner;
(c) Large Power Consumers where the GSO considers it necessary; and
(d) Interconnected Parties.
procedure. “Minimal Effect” means that any distortion to voltage and frequency at
Connection Points does not exceed the standards contained in this Code.
System Test and shall, if possible, agree with the Test Proposer (if the Test
Coordinator was not appointed by the Test Proposer), the GSO and all Users
identified by the GSO under OC11.3.1 another suitable time and date. If he
cannot reach such Agreement, the Test Coordinator shall reconvene the Test
Committee as soon as practicable, which will endeavour to arrange another
suitable time and date for the System Test, in which case the relevant
provisions of OC11 shall apply.
SDC1.1 INTRODUCTION
Scheduling and Dispatch Code No.1 (SDC1) sets out the procedure for;
(a) The weekly and daily notification by the Generators to the GSO and Single
Buyer of the Availability of any of their CDGU in an Availability Declaration;
(b) the weekly and daily notification to the GSO and Single Buyer of whether
there is any CDGU which differs from the last Generating Unit Scheduling
and Dispatch Parameters (SDP), in respect of the following Schedule Day by
each Generator in a SDP Notice;
(c) The weekly and daily notification of Power export availability or import
requests and price information by Interconnected Parties to the Single
Buyer;
(d) the submission of certain Network Data to the GSO, by each Network Owner
or User with a Network directly connected to the Transmission Network to
which Generating Units are connected (to allow consideration of Network
constraints);
(e) the submission of certain Network Data to the GSO, as applicable by each
Distributor, Network Owners or User with a Network directly connected to
the Distribution Network to which Generating Units are connected (to allow
consideration of distribution restrictions);
(f) the submission by Distributor, Network Owners and Users to the GSO of
Demand Control information (in accordance with OC4);
(g) agreement on Power and Energy flows between Sabah or Labuan and
Interconnected Parties by the Single Buyer following discussions with the
GSO;
(i) the production of a Least Cost Generation Schedule, which schedule, for the
avoidance of doubt, in this SDC 1, means Unit Commitment and Generating
Unit dispatch level.
SDC1.2 OBJECTIVES
To enable the Single Buyer and GSO to prepare a generation schedule based on a least
cost, dispatch model (or models) which, amongst other things, models variable costs,
fuel cost heat rate, gas volume and gas pressure constraints, other fuel constraints,
reservoir lake level, riparian flow requirement, hydro/thermal optimization,
intermittent power of Power Park Module and is used in the Scheduling and Dispatch
process and thereby ensures:
(a) the integrity of the interconnected Grid System;
(c) that there is sufficient available generating Capacity to meet Grid System
Demand with an appropriate margin of reserve;
(d) to enable the preparation and issue of an day ahead Generation Schedule;
(g) maximise possible use of Energy from hydro-power stations taking due
account of river riparian flow requirement, reservoir levels and seasonal
variations, and which is based upon long term water inflow records and
(h) to maintain sufficient solid and liquid fuel stocks and optimise hydro
reservoir depletion to meet fuel-contract requirement.
In the case where fuel prices are subsidized, the price to be used for scheduling shall
be the price decided by the government.
SDC1.3 SCOPE
SDC1 applies to the Single Buyer, GSO, and to Users which in SDC1 are:
(a) Generators with a CDGU, including Generator with Power Park Modules;
(b) Generators with a Generating Unit larger than 1MW not subject to central
dispatch where the GSO considers it necessary;
(c) Generators with Black Start Generating Units or Black Start Stations;
(h) Large Power Consumers who can provide Demand Control in real time.
SDC1 does not apply to any Rural Networks which are not connected to Transmission
Network.
SDC1.4 PROCEDURE
SDC1.4.1 Applicability
Schedules and other information supplied by the Single Buyer to the User, or
Declarations and other information supplied by the User to the Single Buyer,
as the case may be, under this SDC1 shall be supplied on the current Working
Day for the following Working Day.
Where the day(s) following the current Working Day is a Non-Working Day,
Schedules and other information supplied by the Single Buyer to the User, or
Declarations and other information supplied by the User to the Single Buyer,
as the case may be, under this SDC1 shall be supplied on the current Working
Day for each of the Non-Working day(s) between the current Working Day and
the next Working Day.
For the purposes of this SDC1.4.1, a Non-Working Day shall mean a Saturday,
Sunday or public holiday.
(8) other factors that may mean that a CDGU is chosen other than in
accordance with the Least Cost Operation:
(i) adverse weather is anticipated;
(ii) a Yellow Warning has been issued;
(iii) Demand Control has been instructed by the GSO; or
(iv) a Total Blackout or Partial Blackout exists.
A written record all of these adjustments must be kept by the GSO, for a period
of at least twelve (12) months.
The Synchronizing and De-Synchronizing times shown in the Generation Unit
Commitment Plan are indicative only and it should be borne in mind that the
Dispatch Instructions could reflect more or different CDGU than in the Unit
Commitment Plan. The GSO may issue Dispatch Instructions in respect of any
CDGU in accordance with its Declared Availability. Generators must ensure
that their Generating Units are able to be synchronized at the times Scheduled
when so dispatched by the GSO by issue of a Dispatch Instruction.
The Generation Unit Commitment will be issued to Generators by 1700 hours
each day for the following day or days, provided that all necessary information
was made available by 0900 hours. The GSO may instruct CDGUs before the
issue of the Generation Schedule for the Schedule Day to which the instruction
relates, if the length of Notice to Synchronise requires the instruction to be
given at the time. The Generation Unit Commitment received by each
Generator will contain only information relating to its CDGUs.
The records of Dispatch, Dispatch Instruction, least cost Unconstrained and
Constrained Schedule, for each day will be used by the Single Buyer for
settlement purposes. In the case of any change of Generation Scheduling and
Dispatch Parameters from the relevant Agreement, these shall be notified to
the Single Buyer
If a revision to an Availability Declaration, Generation Scheduling and
Dispatch Parameters or Other Relevant Generation Data is received by the
Single Buyer prior to 1700 hours on the day prior to the relevant Schedule Day
or Schedule Days, the Single Buyer shall, if there is sufficient time prior to the
issue of the Generation Schedule, take into account the revised Availability
Declaration, Generation Scheduling and Dispatch Parameters or Generation
If a revision in Availability Declaration, Generation Scheduling and Dispatch
Parameters or Other Relevant Generation Data is received by the GSO and the
Single Buyer on or after 1700 hours in each Scheduling day but before the end
of the next following Schedule Day or Schedule Days, the GSO and the Single
Buyer shall, if it reschedules the CDGUs available to generate, take into
account the revised Availability Declaration, Generation Scheduling and
Dispatch Parameters or Other Relevant Generation Data in that rescheduling.
submit to the Single Buyer in writing (or by such electronic data transmission
facilities as have been agreed with the Single Buyer) the following:
(a) details of any special factors which in the reasonable opinion of the
Generator may have a material effect or present an enhanced risk of
a material effect on the likely output of such CDGU’s. Such factors
may include risks or potential interruptions to CDGU fuel supplies or
developing plant problems. This information will normally only be
used to assist in determining the appropriate level of Operating
Reserve that is required under OC3;
(b) any temporary changes, and their possible duration, to the
Registered Data of such CDGU;
(c) any temporary changes, and their possible duration, to the
availability of Ancillary Services;
(d) details of any CDGU's commissioning or recommisioning or changes
in the commissioning or recommissioning programmes submitted
earlier.
Any data which has been subjected to the Data Validity and Default Rules (whether or
not amended or determined in accordance with those rules) which is inconsistent with
other data will be amended in accordance with the Data Consistency Rules.
In the event that any data item of a CDGU is amended or determined in accordance
with this SDC1.6, the appropriate data items will be made available to the Generator.
It is the responsibility of the User to submit accurate data and also to notify the Single
Buyer immediately of any changes to their data.
outage planning especially during weekends, hydro allocation over a week, peaking
plant cycling and day ahead Generation Schedule.
Initially, Single Buyer prepares a preliminary unconstraint Ten (10) days ahead plan.
This is followed by a constrained Ten (10) days ahead plan. GSO and Single Buyer
subsequently arrange an outage coordination meeting to agree on outage requests
from Generators and Grid Owner, so that outage plan will not cause unacceptable
impact to Grid System security. The revised Ten (10) days ahead plan after the above
meeting is the final Ten (10) day ahead plan.
Single Buyer shall prepared preliminary Ten (10) days ahead plan by 1500hours of
Thursday of week 0 for and get it ready as a reference for coordination meeting to
decide on planned outages. The decision made during the coordination of the outages
will be taken into consideration for the preparation of the final Ten (10) days ahead
plan. Single Buyer will issue the final Ten (10) days ahead plan by 0900 hour of Friday
of week 0.
The final Ten (10) days ahead plan is the basis for the preparation of the day ahead
Generation Schedule. This also provides for the nomination of the gas and fuel
requirement, import and export transaction across interconnections and Demand
Control.
The final Ten (10) days ahead plan will contain the following information:
a. Demand and Energy Forecast
f. Spinning Reserve
Single Buyer will issue the final Ten (10) days ahead plan to GSO. Generators and Grid
Owner will be informed of the approved outages by GSO. Gas nomination will be
declared to the gas supplier by Single Buyer. GSO will decide on the information to be
released to other Users on need basis, where it is relevant.
SDC1 – APPENDIX 1
(b) in the case of hydro sets and also gas turbines, the time from initiation of a start to
achieving Dispatch Load.
In addition the following basic data requires to be confirmed if there has been any change since
the last Availability declaration;
(a) Minimum Generation in MW;
Where required by the GSO two-shifting limitations (limitations on the number of start-ups per
Schedule Day) will be included as follows;
(a) Minimum on-time;
(d) Maximum Loading rates for the various levels of warmth and for up to two output
ranges including soak times where appropriate;
(f) The MW and MVAr capability limits within which the CDGU is able to operate as
shown in the relevant Generator Performance Chart;
(g) Maximum number of on-Load cycles per 24 hour period, together with the maximum
Load increases involved; and
(h) In the case of gas turbines and Diesels only, the declared Peak Capacity. Sufficient
data should also be supplied to allow the LDC to temperature correct this impaired
Capacity figure to forecast ambient temperature.
For each hydro CDGU and thermal CDGU with a fuel take-or-pay agreement;
(a) Minimum Take (MW.hr) per Schedule Day; and
SDC2.1 INTRODUCTION
Scheduling and Dispatch Code No. 2 (SDC2) which is complementary to SDC1 and SDC3,
sets out the following procedures;
(a) to issue Dispatch Instructions to Generators in respect of their CDGUs ;
(c) to achieve optimisation of overall Grid System operations by the GSO for the
Scheduled Day.
SDC2.2 OBJECTIVES
The procedure for the issue of Dispatch Instructions to Generators by the GSO,
confirmation, approval and execution of energy transfers with Interconnected Parties,
utilizing the Least Cost Generation Schedule derived from SDC1, as prepared by Single
Buyer, is intended to enable, power system demand to be continuously met with an
appropriate margin of reserve to maintain the integrity of the Grid System together
with the necessary security and quality of supply.
It is also intended to allow the GSO to maintain a coordinating role over the System as
a whole, maximising system security on the Transmission Network, while optimising
generation costs to meet Grid System Demand.
SDC2.3 SCOPE
SDC2 applies to the Single Buyer, GSO, Grid Owner and to all Users which in SDC2
means;
(a) Generators having Generating Units subject to Central Dispatch, including
Power Park Module;
(b) Generators with a Generating Unit larger than 1MW not subject to central
dispatch where the GSO considers it necessary;
(f) Large Power Consumers who can provide Demand Control in real time.
SDC2.4 PROCEDURE
Subject as provided below, the factors used in the Dispatch phase in assessing
which CDGU to Dispatch in conjunction with the Least Cost Generation
Schedule, will be those used by the GSO in compiling the schedules under
SDC1.
Additional factors that the GSO will also take into consideration before
changing the Constrained Schedule are:
(a) those where a Generator has failed to comply with a Dispatch
Instruction given after the issue of the Day ahead Generation
Schedule;
(c) the need for Generating Units to be operated for monitoring, testing
or investigation purposes under OC10 or at the request of a User
under OC10 or for commissioning or acceptance tests under OC11;
(d) requests from the Single Buyer for an increase or decrease in energy
Transfer Level across the Interconnectors;
(e) requests from the Single Buyer for a change to the operation of a
specific CDGU;
These factors may result in some CDGUs being dispatched out of Merit Order.
In the event of two or more CDGUs having the identical submitted data in
accordance with SDC1, then the GSO will first select for Dispatch the one which
is in the GSO’s reasonable judgement the most appropriate at that time within
the philosophy of this Grid Code. This will give rise to a reduction in
transmission losses, higher system reliability and enhance fuel security.
SDC2.5.1 Introduction
Dispatch Instructions relating to the Scheduled Day can be issued by the GSO
at any time during the period beginning immediately after the issue of the
Generation Schedule in respect of that Scheduled Day. The GSO may,
however, issue Dispatch Instructions in relation to a CDGU prior to the issue of
Generation Schedule containing that Generating Unit.
The GSO will issue Dispatch Instructions directly to the Power Station’s
Approved Person for the Dispatch of each CDGU. The GSO may issue Dispatch
Instructions for any CDGU, including Power Park Module which has been
declared available in an Availability Declaration even if that Generating Unit
was not included in the Generation Schedule.
Dispatch Instructions will take into account Availability Declaration and
Generating Unit Operating Characteristics.
The GSO will use all reasonable endeavours to meet the Transfer Level
requested by the Single Buyer.
are not in accordance with the applicable Declared Availability to the GSO
regarding non-acceptance of Dispatch Instructions.
In the event that in carrying out the Dispatch Instructions, an unforeseen
problem arises, caused on safety grounds (relating to personnel or plant), the
GSO must be notified without delay by telephone.
(b) each Generator must utilise the relevant Dispatch parameters when
complying with Dispatch Instructions; and
SDC2.7 REPORTING
As part of the settlement process the GSO will provide a report of the actual real time
performance of each CDGU to the Single Buyer.
The GSO shall also provide requisite operational data in a format as specified by the
Grid Code Committee/Grid Operation Subcommittee to enable them to perform their
functions as per GC4 and GC6.
< End of Scheduling and Dispatch Code 2: Control Scheduling and Dispatch >
SDC3.1 INTRODUCTION
SDC3 sets out the procedure for the GSO to use in relation to Users to undertake the
direction of System Frequency control. System Frequency will normally be controlled
by AGC signals sent from the LDC, or by Dispatch of and response from CDGU’s
operating in Frequency Sensitive Mode, except where:
(1) there has been a failure in the AGC for whatever reasons; or
(2) a CDGU does not have the capability to accept AGC signals.
Frequency may also be controlled by control of Demand.
The requirements for Frequency control are determined by the consequences and
effectiveness of generation Scheduling and Dispatch. Accordingly, SDC3 is
complementary to SDC1 and SDC2.
SDC3.2 OBJECTIVES
The procedure for the GSO to direct System Frequency Control and is intended to
enable (as far as possible) the GSO to meet the statutory requirements of System
Frequency Control, and to manage tie line control in accordance with relevant
Agreements with Interconnected Parties.
SDC3.3 SCOPE
SDC3 applies to the Single Buyer, GSO, and Users, which in SDC3 means;
(a) Generators with CDGUs, including Power Park Module;
(d) Distributor
SDC3.4 PROCEDURE
Each CDGU producing Active Power must operate at all times in Frequency Sensitive
Mode i.e. each CDGU must at all times have the capability to automatically to provide
response to changes in Frequency in accordance with the requirements of CCs in order
to contribute to containing and correcting the System Frequency within the statutory
requirements of Frequency control.
A System Frequency induced change in the Active Power output of a CDGU which
assists recovery to Target Frequency must not be countermanded by a Generator or
the Generating Unit control system except where it is done purely on safety grounds
(relating to either personnel or plant).
(c) maintaining (as far as it is able) the electric time error within 20
seconds.
< End of Scheduling and Dispatch Code 3: Frequency and Transfer Control >
METERING CODE
MC1 INTRODUCTION
This Metering Code (MC) specifies the minimum technical design and operation criteria to be
complied with for metering and data collection equipment and associated procedures required for
the proper recording and safe keeping of metering data.
MC2 OBJECTIVES
The objectives of the Metering Code are to establish the:
(a) standards to be met in the provision, location, installation, operation, testing and
maintenance of Metering Installations;
(b) obligations of the parties bound by the Metering Code in relation to ownership and
management of Metering Installations and the provision and use of Meter data; and
(c) responsibilities of all parties bound by the Metering Code in relation to the storage,
collection and exchange of Meter data.
MC3 SCOPE
The Metering Code applies to the Single Buyer, GSO and the following Users:
(a) Grid Owner;
(b) Distributors;
(c) Network Owners;
(d) Generators;
(e) Large Power Consumers directly connected to the Grid; and
(f) Interconnected Parties.
MC4 REQUIREMENTS
MC4.1 GENERAL
two locations will be calculated by the Single Buyer in Agreement with the User. The
Metering Installation shall be capable of being interrogated both locally and
remotely.
The Revenue Metering Data for Active Energy and Reactive Energy and Active
Power and Reactive Power shall be recorded, stored at data registers on-site every
thirty (30) minutes and automatically collected once a day by the Data Collection
System of the Single Buyer. The onsite electronic data registers shall have the
capability to communicate with the Automatic Data Collection System and
adequate capacity to store at least forty five (45) days of on-site data to provide
back-up for any interruptions to the Automatic Data Collection System.
The Revenue Metering shall be the primary source of data for Billing purposes.
Revenue Metering shall comprise of a Main Meter to measure and record the
required data and a Check Meter to validate the readings from the Main Meter as
back-up metering at all Connection Points.
The Revenue Metering Data collected by the Automatic Data Collection System is
required for Billing purposes by the Single Buyer.
(iv) panel on which the Meters and associated Data Loggers are mounted;
(v) communication and communication interface equipment;
(vi) Metering accessories (for example, but not limited to, metering fuses,
test blocks)
(vii) secure auxiliary supplies to Meters and other equipment;
(viii) monitoring and alarm equipment; and
(ix) facility to keep the installation secure, clean and dry; as agreed
between the GSO and the Single Buyer as the case may be and the
User in the relevant Agreement.
(d) the accuracy of the Metering Installation and the parameters to be measured at
each Connection Point shall be determined as indicated in Appendix 1;
(e) The person as nominated under the relevant Agreements shall have the
responsibility for the provision of Metering Installations and spares as may be
required, for Connection Points directly connected to the Transmission Network;
(f) All costs of the Metering Installation are covered as per the relevant Agreement;
(g) The party responsible for the Metering Installation is the Single Buyer;
(h) The Single Buyer shall:
ensure that the Revenue Metering Installations and Check Meter
Installations are provided, installed and maintained in accordance with
Appendix 1;
ensure that the components, accuracy and testing of each of the
Metering Installations complies with the requirements of this
Metering Code;
where one of the Metering Installations is described as a Type 1
Metering Installation in Appendix 1 arrange for the provision of an
alarm monitoring feature to cover any failure of any critical
components of the Metering Installation including the reduction of
voltage input and loss of auxiliary supplies;
coordinate the electronic accessibility of each Metering Installation in
a manner as to prevent congestion during Metering Data collection.
(i) Metering Installations shall comply with this Metering Code and shall be:
physically secure and protected from tampering;
registered with the Single Buyer;
capable of providing Metering Data for electronic transfer to the
Metering Database of the Single Buyer;
(j) Energy Data shall be based on units of kilowatt-hours (kWh) (Active Energy) and
kilovar-hours (kVArh) (Reactive Energy) and shall be collated at each Billing Period
by the Single Buyer and validated in accordance with standard procedure
according to the relevant Agreement;
(k) wherever required and installed in accordance with this Metering Code, Check
Meters shall be used to provide Metering Data whenever the Main Metering fails;
(l) each Network Owner and User with a User System shall be entitled to receive
Metering Data as recorded by the Single Buyer in respect of the Metering Points
on their network or system;
(p) In relation to the provisions of this Metering Code, noncompliance will be dealt with
by using the Derogation Procedure set out in the General Conditions GC6 of the Grid
Code.
MC5 OWNERSHIP
The person nominated under the relevant Agreement shall design, supply, install and test the
Revenue Metering Installation at that Connection Point.
If the Single Buyer does not own the premises where the Metering Installation is located, then the
owner of that premises will provide:
(a) 24-hour access and adequate space for the Metering and associated communications
equipment;
(b) reliable auxiliary power supplies; and
(c) current transformers (CT) and voltage transformers (VT) compliant with this Metering
Code and as agreed by the Single Buyer.
In relation to a connection between the Transmission Network and a User Network the Single Buyer
shall own the Revenue Metering Installation.
A Check Metering Installation is required to have the same degree of accuracy as the
Revenue Metering Installation.
The target availability of measurement transformers and Metering Installations shall be 99%
per annum and the target availability of the communication link shall be 95% per annum
unless otherwise agreed between the Single Buyer and the User.
The Metering Installation shall be in accordance with and conform to relevant Technical
Specifications and Standards as agreed by the Single Buyer and included in the relevant
Agreement. These Technical Specifications and Standards shall include:
(a) relevant Malaysian National Standards (MS);
(b) relevant International, European technical standards, such as IEC, ISO and EN; and
(c) other relevant national standards such as BS, DIN and ASA.
MC7.1 COMMISSIONING
Where commissioning of new Metering equipment or a Modification to existing Metering
equipment is required the User shall notify the Single Buyer or the Single Buyer shall notify
the User, as the case may be, and any Associated Users of the details of the new Metering
Installation and Modifications to the existing Metering Installation at least one (1) calendar
month prior to the commissioning date. The User also shall, prior to the commissioning,
undertake inspection, calibration and component testing in accordance with this MC7 to
ensure compliance of the Metering Installation with the provisions of the Metering Code
and the requirements and procedures detailed in Appendix 2 of this Metering Code.
A User shall make a reasonable request for testing of any Metering Installation and the
Single Buyer shall not refuse any reasonable request.
The Single Buyer must verify the results of all tests carried out in accordance with Appendix
2 recorded in the Metering Register in respect of each Metering Installation and shall
arrange for sufficient audit testing of Metering Installation as the Single Buyer considers
necessary for assessing whether the accuracy of each Metering Installation complies with
the requirements of this Metering Code.
Each User shall provide the auditor of the Single Buyer with unrestricted access to each
Metering Installation for which it is responsible for the purpose of the routine testing of
such Metering Installation. The Single Buyer shall give notice in advance in accordance with
the relevant Agreement for such testing and the notice shall specify:
(a) the name of the person who will be carrying out the testing on behalf of the Single
Buyer; and
(b) the date of the test and the time at which the test is expected to commence and
conclude.
The auditor of the Single Buyer shall respect all of the User’s safety and security
requirements when conducting the audit tests on the Metering Installation.
The Single Buyer shall make the test results associated with a Metering Installation
available to any person as soon as practicable if that person is considered by the Single
Buyer to have sufficient interest in the results.
The Single Buyer may carry out periodic, random or unannounced audits of Metering
Installations to confirm compliance with this Metering Code. The Single Buyer shall be given
unrestricted access to Metering Installations by all Users for the purpose of carrying such
audits. The Single Buyer shall ensure that the person(s) carrying out such audits respect the
User’s security and safety requirements.
(b) the time between the current billing period and one (1) month preceding the time
when the error was detected; or
(c) as otherwise agreed in accordance to the relevant Agreement.
If a test or audit of a Metering Installation demonstrates a measurement error of less than
two (2) times the error permitted by Appendix 1, no substitution of readings shall be
required unless, in the reasonable opinion of the Single Buyer, a particular party would be
significantly affected if no substitution were made.
If any substitution is required under MC9.5, the Single Buyer must provide substitute
readings to effect a correction for that error in respect of the period since the error was
deemed to have occurred in accordance with MC9.5.
MC10 CONFIDENTIALITY
Metering Data and the passwords are confidential data and shall be treated as confidential
information in accordance with this Metering Code by all persons bound by the Grid Code.
enable the GSO to monitor the dynamic behaviour of the Generating Plant and Spinning Reserve.
Such information shall be presented continuously to SCADA, event recorders and such other
equipment as may be developed and utilised by the GSO. The GSO shall hold all such information as
confidential.
MC13 DISPUTES
Disputes concerning and in relation to this Metering Code shall be dealt with in accordance with the
procedures set out in the General Conditions of this Grid Code.
% Power Factor
Rated
Unity 0.866 Lag 0.5 Lag Zero
Load
Active Active Reactive Active Reactive Reactive
% Power Factor
Rated
Unity 0.866 Lag 0.5 Lag Zero
Load
Active Active Reactive Active Reactive Reactive
(Note: All measurements in Tables 2 and 3 are to be referred to 25degrees Celsius under
Meter laboratory conditions.)
A Check Metering Installation shall include the provision of a separate Metering Installation
using separate current transformer cores and separate secondary windings. The accuracy of
Check Metering Installation shall be the same as the Main Metering Installation.
Wherever the Check Metering Installation accuracy level duplicates the Main Metering
Installation accuracy level, the validated data set of the Main Metering Installation shall be
used to determine the Energy Measurement. Where the Main Metering Installation data set
cannot be validated due to errors in excess of those prescribed in this Appendix the
provisions of MC9.5 shall apply.
The physical arrangement of Check Metering shall be agreed between the Single Buyer and
the User and recorded in the Connection Agreement.
Check Metering Installation may be supplied from secondary circuits used for other
purposes and may have a lower level of accuracy than Revenue Metering Installation as
agreed between the Single Buyer and the User. The accuracy of Check Metering Installation
shall not exceed twice the level prescribed in this Appendix 1 for the Revenue Metering
Installation.
discussion and approval at the Grid Code Committee in accordance with the procedures
outlined in General Conditions (GC) of this Grid Code.
The Single Buyer shall provide the test results to the User in accordance with the relevant
Agreement and to each Associated User upon request.
Unless otherwise agreed by the Single Buyer and User, the following test and inspection
intervals shall be observed by the Single Buyer.
Type 1 Type 2
CT 10 years 10 years
VT 10 years 10 years
Convention for Import and Export of Active Energy and Reactive Energy
For the avoidance of doubt, Export in relation to the Transmission Network is the flow of
Active Energy as viewed by a Generator is away from the Generator.
For the terms (sinθ) and (cosθ) specified in MC.A.2.1 reference shall be made to the ISO
Document “Guide to the Expression of Uncertainty for Measurement”.