PM Group Assignment
PM Group Assignment
The goal of this project is to construct a two-story bungalow home in Semenyih, Selangor. Thebudget is
fixed at RM 1,110,000.00. This home was supposed to take 24 months to build, but we were able to
finish it by September 28th, 2023. Despite the 24-month time restriction, the project was completed
approximately 18 months without bypassing any of the required requirements. The project began on
April 1, 2022 and will end on September 28, 2023. The bungalow home was built for around 4377
square feet. The bungalow home will be handed over to the customer on September 28th, 2023. To
determine the cost of construction and building development, we consulted many sources, including
home construction cost calculators, worker salaries, material prices, window product ideals, automobile
porch size, and others. The majority of tasks and progress are automatically scheduled using the
Microsoft Project application to ensure that everything goes as planned.
INTRODUCTION
Every project presents its unique characteristics and challenges that need to be taken into consideration
in the process of managing it. Adoption of a project management strategy is always recommended to
take the whole scope of the project into account before proceeding with the individual tasks of the
project. Implementation of a strategic project management approach is useful as it allows for a thorough
planning and scheduling of the project rather than tackling the project on an individual task basis. The
project management process has to take into account the resources available, likelihood of risk factors,
stakeholder analysis, and cost analysis. In this report, the preliminary project management process
would be evaluated and investigated for the construction of a two-storey bungalow home in Semenyih,
Selangor. At this stage of the project, all required aspects of the project will get estimated and identified,
including – identification of risks, cost estimation, and timeline of the project using a critical path
scheduling of tasks.
OBJECTIVES
❖ To construct a quality and attractive bungalow within the time limit and
financialconstraints.
❖ To present the client with the desired dream home.
SCOPE MANAGEMENT
Phase 1: Preliminary Work
❖ The site is initially examined, and a surveyor creates a survey drawing to define the borders,
platform levels, road levels, terrain, flow discharge, and soil condition.
❖ A soil study is carried out to acquire information on the kind of soil existing on the building site
and in the surrounding area.
❖ Following the completion of the soil research, site clearing is performed, in which plants and trees
are rooted out and chopped down to guarantee a clean site.
❖ Then, ground workers construct a site access or access road to facilitate the movement of machinery
and equipment.
❖ Next, a temporary site office and crew facilities should be installed on-site so that personnel may
relax during breaks.
❖ Engineers will inspect for pre-existing utilities such as drainage and manholes before supplying
electricity and water to the site office.
❖ The surveyor lays out the building on a cleared site and translates the lines to profiles that are well
free of any construction activities.
Microsoft Project is the programme we utilized for this project. Developed and offered by Microsoft,
Microsoft Project is a project management application. A project manager can use it to make schedules,
allocate resources, monitor progress, keep tabs on costs and do workload analysis. Microsoft Project is
capable of easing project workflow by:
❖ Eliminating the sluggish and clunky approach of employing handwritten methods when presenting
data
❖ Producing data reports that are simple to analyses and show.
❖ Create a critical route to better monitor project progress.
❖ The programme aids in keeping financial and resource management under control and free of
disruptions by identifying areas of strength and weakness in the company's management.
2 Design Stage
2.1 Layout plan
2.2 Earthwork Plan
2.2.1 Road Plan
2.2.2 Drainage Plan
2.2.3 Water Circulation System
2.2.4 Sewerage System
2.3 Design Submission
2.3.1 Earthwork, road and drainage
2.3.2 Water reticulation to IWK
3 Construction Stage
3.1 Earthwork
3.1.1 Excavation
3.2 Ground Floor
3.2.1 Footing
3.2.2 Framing
3.2.3 Cut and Fill
3.2.4 Piling
3.2.5 Pad-footing
3.2.6 Levelling the plane and fitting
3.2.7 Plumbing drains
3.2.8 Electrical chases
3.2.9 Concrete slab foundation
3.3 Second Floor
3.3.1 Floor beams and column
3.3.2 Pouring Slab and brick works
3.4 Roofing
3.4.1 Framing
3.4.2 Ventilating
3.4.3 Underlay support tray
3.4.4 Underlaying
3.4.5 Battens and Tiles
3.4.6 Verge Units
3.4.7 Roof ridge
3.5 Utilities Installation
3.5.1 Plumbing
3.5.2 Ventilation
3.5.3 Electrical Wiring
3.6 Finishing
3.6.1 Exterior
3.6.1.1 Wall
3.6.1.1 Painting
3.6.1.2 Windows
3.6.1.3 Doors
3.6.2 Interior
3.6.2.1 Floor
3.6.2.2 Wall
3.6.2.2.1 Painting
3.6.2.2.2 Side Skirting
3.6.2.3 Ceiling
3.6.2.4 Electrical Plugs
3.6.2.5 Water Supply
4 Site Decommissioning
4.1 Cleaning
4.2 Handover house
Network Diagram
Tasks List
ID WBS Task Name Duration Start Finish Predecessors Resource Names
0 0 Project RM 1.11 million 2-stor 390 days Fri 1/4/22 Wed 28/9/23
1 1 Preliminary Work 58 days Fri 1/4/22 Tue 21/6/22
2 1.1 Site visit 2 days Fri 1/4/22 Mon 4/4/22
3 1.2 Survey drawing 2 days Fri 1/4/22 Mon 4/4/22
4 1.3 Soil investigation 15 days Fri 8/4/22 Thu 28/4/22 3
5 1.4 Site clearance 15 days Mon 2/5/22 Fri 20/5/22 4
6 1.5 Temporary facilities installatio 20 days Mon 23/5/22 Fri 17/6/22 5
7 2 Design Stage 91 days Tue 31/5/22 Mon 3/10/22
8 2.1 Layout plan 15 days Wed 22/6/22 Tue 12/7/22 2
9 2.2 Earthwork plan 52 days Tue 28/6/22 Tue 30/8/22
10 2.2.1 Road plan 15 days Thu 30/6/22 Wed 20/7/22 8
11 2.2.2 Drainage plan 15 days Thu 7/7/22 Wed 27/7/22 8
12 2.2.3 Water circulation system 15 days Fri 15/7/22 Thu 4/8/22 8
13 2.2.4 Sewerage system 11 days Wed 17/8/22 Tue 30/8/22 12
14 2.3 Design submission 25 days Mon 19/9/22 Fri 21/10/22
15 2.3.1 Earthwork, road and drainage 12 days Mon 19/9/22 Tue 4/10/22 13
16 2.3.2 Water reticulation to IWK 12 days Thu 6/10/22 Fri 21/10/22 13
17 3 Construction Stage 180 days Mon 24/10/22 Fri 30/6/23
18 3.1 Earthwork 14 days Mon 31/10/22 Thu 17/11/22
19 3.1.1 Excavation 14 days Mon 31/10/22 Thu 17/11/22 15,16
20 3.2 Ground floor 65 days Fri 18/11/22 Thu 16/2/23
21 3.2.1 Footing 15 days Fri 18/11/22 Thu 8/12/22 19
22 3.2.2 Framing 15 days Fri 18/11/22 Thu 8/12/22 19
23 3.2.3 Cut and fill 15 days Fri 18/11/22 Thu 8/12/22 19
24 3.2.4 Piling 15 days Fri 9/12/22 Thu 29/12/22 23
25 3.2.5 Pad-footing 15 days Fri 9/12/22 Thu 29/12/22 23
26 3.2.6 Levelling the plane and fitting15 days Fri 9/12/22 Thu 29/12/22 23
27 3.2.7 Plumbing drains 15 days Fri 30/12/22 Thu 19/1/23 26
28 3.2.8 Electrical chases 15 days Fri 30/12/22 Thu 19/1/23 26
29 3.2.9 Concrete slab foundation 20 days Fri 20/1/23 Thu 16/2/23 27,28
30 3.3 Second floor 40 days Mon 20/2/23 Fri 14/4/23
31 3.3.1 Floor beams and column 20 days Mon 20/2/23 Fri 17/3/23 29
32 3.3.2 Pouring slab and brick works20 days Mon 20/3/23 Fri 14/4/23 31
33 3.4 Roofing 27 days Mon 17/4/23 Tue 23/5/23
34 3.4.1 Framing 10 days Mon 17/4/23 Fri 28/4/23 32
35 3.4.2 Ventilating 5 days Tue 2/5/23 Mon 8/5/23 34
36 3.4.3 Underlay support tray 5 days Tue 2/5/23 Mon 8/5/23 34
37 3.4.4 Underlaying 5 days Tue 9/5/23 Mon 15/5/23 36
38 3.4.5 Battens and tiles 5 days Tue 9/5/23 Mon 15/5/23 36
39 3.4.6 Verge units 5 days Tue 9/5/23 Mon 15/5/23 36
40 3.4.7 Roof ridge 7 days Tue 16/5/23 Wed 24/5/23 39
41 3.5 Utilities instatllation 7 days Wed 24/5/23 Thu 1/6/23 33
42 3.5.1 Plumbing 7 days Wed 24/5/23 Thu 1/6/23 32
43 3.5.2 Ventilation 7 days Mon 28/3/22 Thu 1/6/23 32
44 3.5.3 Electrical wiring 7 days Mon 28/3/22 Thu 1/6/23 32
45 3.6 Finishing 31 days Mon 5/6/23 Mon 17/7/23
46 3.6.1 Exterior 14 days Wed 28/6/23 Mon 17/7/23
47 3.6.1.1 Wall 14 days Wed 28/6/23 Mon 17/7/23
48 3.6.1.1.1 Painting 14 days Wed 28/6/23 Mon 17/7/23 33
49 3.6.1.2 Windows 5 days Wed 28/6/23 Tue 4/7/23 33
50 3.6.1.3 Doors 5 days Wed 28/6/23 Tue 4/7/23 33
51 3.6.2 Interior 27 days Mon 5/6/23 Tue 11/7/23 33
52 3.6.2.1 Floor 10 days Wed 28/6/23 Tue 11/7/23 33
53 3.6.2.2 Wall 22 days Mon 5/6/23 Tue 4/7/23
54 3.6.2.2.1 Painting 5 days Mon 5/6/23 Fri 9/6/23 40
55 3.6.2.2.2 Side skirting 5 days Wed 28/6/23 Tue 4/7/23 40
56 3.6.2.3 Ceiling 7 days Mon 12/6/23 Tue 20/6/23 54
57 3.6.2.4 Electrical plugs 2 days Mon 12/6/23 Tue 13/6/23 54
58 3.6.2.5 Water supply 7 days Mon 12/6/23 Tue 20/6/23 54
59 4 Site Decommissioning 61 days Thu 6/7/23 Thu 28/9/23 17
60 4.1 Cleaning 60 days Mon 10/7/23 Fri 22/9/23
61 4.2 Handover house 1 day Wed 28/9/23 Wed 28/9/23 60
2.1 Cement
0.45 cement bag is used per sq ft of construction. So, the 1380 Bags 14.40 19,872
cement used is needed to cover 3050.8 sqft of the house
2.2 Sand
Used to fill the surface and prepare RCC, cement, and plaster.
Red burnt clay bricks 120 ton 32 3,840
2.3 Usage of bricks is based on 10 bricks for 9 ft wall and the
amount that is needed to be covered for the whole house is
3050.8 sq ft.
Reinforcement steel bars (rebar) 30600 piece 0.450 13,770
2.4 Reinforcement steel bars to be used for 1 sq ft areais 3kg. So,
to cover the whole area 9150 kg steel is needed.
2.6 ¾ Aggregates
Used along sand and cement
900 sq ft 18.6 8615
2.7 Flooring
590 tiles 62.80 37,052
2.71 Flooring tiles
Flooring tiles that are needed to cover around 3000 sq ft of
area. An additional skirting material as well as tiles for the
stairs and to be wasted is around 950 sq ft. Tiles that will be
used 800 x 800mm, and would be made of porcelain
2.71 Tiles adhesives 106 bags 25.50 2703
A 18kg bag of adhesives can cover +/- 2.5 m2.
2.8 Finishers
Doors
2.92 Sliding doors 46,982.32 46,982.32
Door frame
Doorknob, locks, and trim panels 5.5 %
Automatic gates (semi)
Plumbing
Waterproofing
2.93 PVC pipes
Cast iron pipe 5.5 %
Galvanized steel 46,982.32 46,982.32
pipe
Insulating materials
Showers and pumps
Sinks
Electrical
Sockets
Lightings
2.94 Ceiling Fans
Air 6.8 %
conditioners 58,087.32 58,087.32
Automatic gate installation
Sanitary
Bathtub 5.0
2.95 Toilet bowl % 42,711.20 42,711.20
Toilet sinks
Bidet
2.10 Miscellaneous
2.12 Others
Screws, nails, plywood, breakers, corner guards, 3 % 14,800.50 14,800.50
hooks,long screws, and pins
TOTAL RM355,0
98.78
Calculations for materials
a) For Item 2.0: Main construction items
i) 2.1 Cements
Size of plot = 3050.8 sq ft Cement bags needed for 1 sq ft of plot
= 0.45Cement bags needed = 3050.8 sq ft × 0.45
= 1373 bags
Because there may be additional bags needed, the numbers of bags are rounded up to 1380 bags.
ii) 2.2 Sands
Estimated sand quantity required to cover the ground during
earthworks. = 4800cubic ft
i) Floor tiles
Total area of tiles needed to cover for ground floor and first floor of bungalow is 3000 sq ft
with additional 950 sq ft for skirting materials.
Total tiles needed = 370 m2 ÷ 0.64 m2 = 578.12 tiles = 570 tiles (round off)
i) 2.91 Windows
Costs approximately 3% of total cost of construction = 0.04 × RM 854,224
= RM25,626.72
ii) 2.92 Doors
Costs approximately 5.5% of total cost of construction = 0.055 × RM 854,224
= RM46,982.32
v) 2.95 Sanitary
Costs approximately 5% of total cost of construction = 0.05 × RM 854,224
= RM42,711.20
❖ Cement is an adhesive material since it is used to hold aggregates together all the time. It is
one among the mostoften used building materials. It can be used alone, but it's most employed
in mortar and concrete, when it's combined with an inert ingredient called aggregate. This
type of cement is made up of finely powdered particlesthat harden when combined with water.
▪ Sand
❖ Sand is often utilized in construction because it may provide other elements bulk, rigidity,
and stability. It is widely utilized in the preparation of concrete for use in building
construction. A foundation layer termed as 'blinding' is put over a layer of hardcore, which is
also formed of sand. The purpose is to offer a clean, level, and dry surface for building
activities.
❖ These materials are formed by compressing wet clay into molds and then drying and firing it
in kilns. A solid hardened clay is used in this sort of brick. When used in walls, it must be
plastered with mortar. Other applicationsinclude masonry walls, foundation, and columns.
❖ Reinforced concrete building constructions employ rebar, which is a mesh of steel wires. It's
used to reinforce and hold concrete in place. This is since concrete is compressive but weak
in tension. Steel is utilized as rebar because its deformation at high temperatures is
approximately identical to that of concrete. In building construction, rebar might be used as
main or secondary reinforcement.
▪ ¾ Aggregates
❖ Aggregates are a component of composite materials like concrete and asphalt concrete, and
they act as support to increase the overall strength of the composite material. And is used in
construction to make concrete by combining it with cement, bitumen, lime, or another
adhesive. Gravel, crushed stone, sand, recycled concrete, and geosynthetic aggregates are all
included. It might be organic, synthetic, or recycled.
▪ Windows
❖ Windows let in light and allow individuals to view what's going on outside their home. They
are glass-enclosedholes that provide for ventilation. Louvre and casement windows are the
types of windows used in this home. Louvres are made from a series of parallel panels of
glazing that are suspended on center pivots spaced evenly down the vertical jambs and may
be opened and closed with a crank or lever. With relatively tiny projections, they provide
adequate ventilation. Casement windows, on the other hand, are hinged on the exterior. It is
particularly useful for natural ventilation in hot areas.
• Doors
❖ Any home or structure would be incomplete without doors. Its main function is to regulate
entry to the doorwayand so offer security. Hinged doors are ubiquitous; however, slides or
swing doors can be used to move them. We picked a swing door for the front entrance and a
slide door for the side and back doors for this home. This allows the owner to guarantee that
only those who have permission to open them from the outside may do so.
▪ Plumbing
❖ A plumbing system is a set of pipes built in your house for the distribution of water and the
removal of waterborne wastes. A plumbing system's water-carrying pipes and other materials
must be sturdy, corrosion resistant, and long-lasting enough to outlast the estimated life of the
structure in which they are placed. We employ PVC pipes, Poli pipes, wrought iron pipes, and
galvanized steel pipes for this reason. These pipes are long-lasting and will survive for a long
period.
Days Amount
Item Number Equipment Quantity Required Rate (RM) (RM)
4.1 Measuring Tape 3 \ 5 15
4.2 Chalk Line 12 \ 18 216
4.3 Drill 2 \ 250 500
4.4 Hammer 4 \ 25 100
4.5 Hand saw 4 \ 50 200
Portable Cement
4.6 Mixer 1 \ 2500 2500
Concrete
4.7 Vibrator 1 \ 3000 3000
4.8 Spade 1 \ 90 90
4.9 Screed Board 5 \ 30 150
4.10 Penetrometer 1 \ 460 460
Bar Bending
4.11 Machine 2 40 35 2800
4.12 Table Saw 2 \ 500 1000
4.13 Safety Glasses 10 \ 50 500
4.14 Utility Knife 5 \ 85 425
4.15 Rotary Hammer 5 \ 350 1750
4.16 Caulk Gun 5 \ 10 50
4.17 Level 5 \ 300 1500
4.18 Scaffolding 50 65 8 26000
4.19 Square Ruler 5 \ 20 100
4.20 Screwdriver 5 \ 20 100
Rose Brick
4.21 Trowels 5 \ 25 125
4.22 Carpenter Level 3 \ 20 60
4.23 Brick Jointer 15 \ 50 750
Masonry
4.24 Brushes 5 \ 10 50
4.25 Sled Runners 5 \ 160 800
4.26 Stapler 5 \ 20 100
4.27 Lorry 2 8 450 7200
4.28 Crane 1 30 1200 36000
4.29 Metal Bender 1 \ 250 250
4.30 Metal Cutter 5 \ 200 1000
4.31 Paint Brushes 5 \ 20 100
4.32 Ladders 6 \ 250 1500
4.33 Tape 50 \ 5 250
4.34 Masking 30 \ 3 90
4.35 Carpenter's Glue 20 \ 10 200
4.36 Jigsaw 5 \ 300 1500
4.37 Miter Saw 5 \ 350 1750
Pressure Test
4.38 Pump 1 \ 700 700
4.39 Clamp Tool 4 \ 150 600
Electric Pipe
4.40 Threaded 2 \ 2500 5000
Steel Pipe
4.41 Wrench 5 \ 60 300
Pipe Bending
4.42 Machine 1 \ 6200 6200
4.43 Pipe Cutter 4 \ 30 120
4.44 Gloves 5 \ 20 100
4.45 Floor Cleaner 20 \ 25 500
4.46 Trowel 5 \ 20 100
4.47 Flaring Pliers 5 \ 80 400
4.48 Wheelbarrow 5 \ 150 750
4.49 Shovel 2 \ 100 200
4.50 Hoe 5 \ 20 100
4.51 Shears 5 \ 20 100
4.52 Backhoe 1 30 900 27000
4.53 Dumper 1 15 850 12750
4.54 Excavator 1 15 1100 16500
Vibrating Plate
4.55 Compactor 1 2 50 100
4.56 Paver 1 15 750 11250
4.57 Grader 1 6 600 3600
Hydraulic Drop
4.58 Hammer 1 12 1600 19200
4.59 Dump Truck 1 15 800 12000
Multipurpose
4.6 Excavator 1 12 1300 15600
Pneumatic
4.61 Hammer 1 \ 250 250
Concrete Mixer
4.62 Truck 1 5 750 3750
Total Amount RM 230,351
Sample Calculation for Part 4:
Amount: 1 Amount: 4
Days Required: 15 Days Required: (Purchased=4)
Rate: 1100 Rate: 150
Cost = Amount*Days Cost = Amount*Days
Required*Rate Required*Rate
= 1*15*1100 =RM 16500 = 1*4*150 =RM 600
Cost Summary
Total Cost:
The entire cost of constructing a bungalow in 360 days is calculated by adding the costs of
land,materials, worker salaries, and equipment would be RM 1, 078, 760.28
Equipment’s Justification
• This small machine is used to homogeneously consolidate concrete, sand or rock, and water
to make concrete, much like any other solid blend. However, portable solid mixer is the best
option for completing small-scale soliddevelopment jobs as well as serving as a reinforcement
for larger projects.
Brick jointer
• A brick jointer is a finishing tool for smoothing mortar-filled seams between bricks. Hold
the handle of a BrickJointer against the divider with the outside of the level edge. To smooth
the joints uniformly, press and run the Brick Jointer along perpends and mortar beds. step
in as a back-up for large-scale development projects
• Water meters, plumbing lines, pressure vessels, solar systems, and sprinkler frameworks
are all tested usingthese physically worked hydrostatic test pumps in both residential and
commercial constructions. The test syphons are adaptable and may be used to evaluate
small to medium-sized water system structures.
Backhoe
Excavator
• Burrowing channels, openings, and installations are the most common applications for a tractor,
which allows it todo these tasks far more successfully and efficiently than any other piece of
heavy equipment. Because of the vast range of enterprises, they are used for, including ranger
service, mining, and a wide range of development, firms from a variety of industries may be
looking for backhoes for sale in North Carolina. Aside from burrowing, backhoes are
commonly used for tasks such as demolition, excavating streams, material handling, or
generally really challenging item labor.
• The job of the Transit Concrete Mixer Truck is to retain the solid in a fluid state until it
reaches the point of conveyance at the construction site by spinning the drum. The solid
elements are mixed in a drum blender in theTravel Mixer. The blending is done by sharp
edges attached to the inside of the portable drum.
• For masonry and cement, they are reasonable. Hot Dip Galvanized (HD): These nails contain
a zinc coating that helps to prevent consumption. Regardless, the coating will wear off over
time, and the nails will eventually rust.They're typically used in open-air settings and can
withstand moisture.
Resource management
Resource management is an integral part of any project as the success of a project depends on the
quality of the resource utilization approach. For this project, the resources required are fairly
straightforward and therefore, the material and equipment needed are known in advance such as
skimmers, water pump, etc. and these equipment does not require specific resource utilization. The
resources that require management include cost and time, which are managed by setting a contractor
to complete the task at a fixed price with the labor working through the contractor. In this manner, even
if the project takes longer than estimated, the cost would be afforded by the contractor from profit
margin. In the project scheduling using Gantt chart, parallel activities are designed in order to ensure
that the resources are always busy with work with minimal wastage of time or human resources. The
resources required in this are detailed in the following table:
Table 1 - Resource management
Task Resources required Management tactic
Cleaning and repair Three workers, one manager The manager on-site will keep the
Digging for setting the Four workers, machinery, and any worker falls sick or cannot
construction
As is the case in any project management scenario, some risks are inherent in the project of refurbishing
the garden area of an abandoned house by establishing a swimming pool and a seating area next to it.
It is possible through good strategic management of the undertake project to minimize the risk, but it
is impossible to completely eliminate all the risks associated. These risk factors that are likely attached
with the project can cause disruption in project quality, cause delay in completion, and even make the
project over-budget. As the objective of the owner is to use the swimming pool as a luxury feature in
order to increase the price of the house in the demand season, the project sponsor does not want the
project to go over budget, have a bad quality of construction, or cause delay. Any of these three negative
elements would contribute significantly to worsening of the profit-making ability of the project
sponsor.
To account for this situation involving risk that are related to the project, performing a structured risk
management is a recommended operation. Strategic risk management policy is a management approach
in which all the risks that have a possibility of occurrence are identified beforehand to increase
preparedness. After identifying all of the risks, the next step taken in strategic risk management process
is to make efforts to mitigate the risks and develop a contingency plan to deal with the risk factors. All
of these processes are performed with the intent to make the project least susceptive of negative impact
of risk factors.
In this project of developing a swimming pool in the abandon house garden area, the process of risk
management is performed using the method of risk registers. The table formulated below represents a
risk register for this project, which identifies relevant risks regarding this project while also noting the
mitigation strategy and contingency plan.
Complexity Assessment
The complexity analysis conducted is based on the task that is necessary to carry out the project. Each segment
of the task is accompanied with a description and its complexity is ranked from low to high. The ranking of
low complexity indicates that the task is easier to be carried out, while tasks with high complexity indicate that
more time and effort have to be put into the thinking process of the task, to overcome the nature of its
complexity. The complexity analysis shown in the table below covers both the technical complexity of a task
and the business complexity.
REFERENCES
V. Price of materials -
http://quantitysurveyoronline.com.my/materials-prices.html