Cluster 2 Study Guide
Cluster 2 Study Guide
1. Determine the type and size cable that will be used (sheated, insulated, armoured)
2. Method of installation (Surface or conduit wiring)
3. The Full load current for each circuit
4. Whether the installation is single phase or three phase
5. Type and class of over current protection( fuse or circuit breaker)
In planning the layout point should be considered before starting the actual Installation.
1. Pipe run of other trades should be taken into consideration (example gas and water pipes)
2. Make sure that you and the customer sign off on what is on the drawing
3. Make allowance for future expansion
4. Conduit specification and size is determine in compliance with the js21
5. Determine conduit location base of specification on the drawing
6. Ensure that proper OH&s procedures are followed
7. Ensure that consultation with the appropriate personel is carried out and that task is coordinated in an effective manner
8. Determine and obtain all tool for the job in accordance with established procedures
9. Conduit should be erected before any wire is drawn in.
10. Bends on the conduits should no be less than 21/2 times the outside diameter of the conduit.
11.Identify safety hazards and follow procedures
Marking out
1. The position of switches and outlets should be clearly marked out, particular care should be taken of the position and
location of the distribution board.
2. Horizontal Conduit runs can now be struck using a chalk line, when struck against the wall leaves a mark.
3. Vertical conduit runs is strucked using a vertical plumb line.
4. First job after marking out is complete in to cut the wall and insert conduits and boxes
In this industry you must conform to established standards to ensure quality, therefore whenever you engage in any type of
project the following must be observed.
1. The quality of the work must be done in accordance with drawings, specification and standards.
2. The observance of guidelines
3. Results of the project must meet initial specification
How to work out the number of cables that can hold in a trunking.
is a length of insulated single conductor (solid or stranded), or two or more conductors each having its own insulation, which
are laid up together.
Flexible cable:
Flexible cord:
this is a flexible cord in which the cross sectional area of the conductor does not exceed 4mm.
A wire is
A long thin single piece of metal that is used to carry electric current.
Conductor:
A conductors is a material which offers low resistance to the flow of electric current. Conductors use to carry electric current
must have the following properties
Service main
Is the cable that runs from the meter socket to the distribution panel
Circuit.
An arrangement of conductors for the purpose of carrying current.
Branch circuit.
That portion of a circuit extending beyond the final overcurrent devices in
the circuit.
Subcircuit.
That portion of a circuit extending beyond the final circuit breaker or set of
fuses.
Final circuit.
A circuit connected directly to current-using equipment, or to a socket outlet or socket outlets or other outlet point for the connection of such
equipment.
Ambient Temperature
There should be adequate space in which to install, maintain, and operate the switchboard. A clear space of not less than 0.8 m should be
available in front of any switchboard.
Every distribution panel shall be installed and maintained in an accessible position and (where possible) in dry, well ventilated situations
where flammable or explosive dust, vapour, or gas cannot accumulate, and shall be arranged to prevent the access of corrosive fumes.
No distribution panel shall be erected above a stove, laundry, copper, tub, wash boiler, or the like, nor in a bathroom, life well, freezing
chamber, or cooling chamber.
No distribution panel shall be erected in a lavatory, on or under a stairway, unless the switchboard is totally enclosed in metal except that any
switchboard may be erected beneath a stairway built of fireproof materials.
Where the permanent distribution board for a building is installed at an early stage in the construction of the building, it is important that the
distribution panel be protected during building operations to minimise the accumulation of dust, dirt, or grit that can cause later damage to
the Distribution panel or its components. Cleaning of the interior of the distribution panel may be necessary before final commissioning.
The local code (JS21) of regulations requires that the following minimum specifications be met when installing service conductors and equipment:
See JS21 Table 5 for details on the minimum clearance for the installation of aerial conductors.
Height for installation of meter socket from ground - 1.8 m(5feet 9inches)
Height for installation of a distribution panel from ground - 1.7m(5feet 6inches)
Height of switches -1.4m (4.5feet)
Convenience plugs (counter tops) -1.2m (4 feet)
Wall mounted lights -2.3m (7.5feet)
Wall mounted plugs -0.5m (1.5 feet)
Minimum size of service main conductors - 6 mm2
Identification of conductors
The colour green or (green and yellow) shall be used only as earth conductors (grounds wire)
The colours (Black, Blue or white) cable shall be used as neutral conductors
The colour Red and Brown shall be used as live or (phase) conductors
Category of buildings to be protected against lightening
Test between the connection to earth other metal parts of the installation
All conductors have a continuous path for electricity to flow.
Polarity test
Test the position of single pole switch and circuit breakers to ensure that a switch or circuit breaker is not connected to
the neutral or earth conductors. Switches and circuit breakers must always be connected to the live (phase) conductor.
METERING
Metering in domestic installations is done by means of inline meters
100 A, 120V, 2 wire - used to meter 1PH, 2 wire systems i.e. phase to neutral
100 A, 240 V, 3 wire - used to meter 1PH, 3 wire system, i.e. two phases and neutral
200 A, 240 V, 3 wire - used to meter the usage of currents over 100 A
Figure 1.4 Typical Earth Inspection Pit
Meters may be
• surface mounted – mounted on the surface of the building or other structure
• flush mounted – installed within the fabric of the building such as concrete
Wiring meter sockets
The incoming service main conductors are connected to the line terminals (FromPothead)
The outgoing service terminals going to the disconnect switch are connected to the load
terminals. (To Main breaker in distribution panel)
The exact wiring of the socket depends on the distribution system being supplied
(a) 1PH, 2 Wire meter socket (b) 1PH, 3 Wire meter socket
Figure 1. Illustration of wiring of 1PH, meter socket using the 4 Jaw meter socket
Line 1 Line 2
Neutral
The Vernier Caliper is a precision instrument that can be used to measure internal and external distances extremely accurately.
Figure 1.5c Wiring of a typical 1PH, 3W meter socket to pothead
Micrometer
The micrometer is a precision measuring instrument, used by engineers. Each revolution of the rachet moves the spindle
face 0.5mm towards the anvil face. The object to be measured is placed between the anvil face and the spindle face. The
rachet is turned clockwise until the object is ‘trapped’ between these two surfaces and the rachet makes a ‘clicking’ noise.
This means that the rachet cannot be tightened anymore and the measurement can be read.