BUILT OF RATE
Rate (RM)
Grade
Item Description Qty Unit 15 20 25 30 35 40 45 50
Concrete Works
(Supply Based on Av Price of 2 Quotations*) Lean con Lean con
43 Supply and delivery Readymixed (Ex Site) 1 M3 365.00 375.00 390.00 405.00 420.00 435.00 455.00 475.00
Transportation cost to site(.70/MT/KM) - - - - - - - -
Sub-total 365.00 375.00 390.00 405.00 420.00 435.00 455.00 475.00
Add Wastage 5 % 18.25 18.75 19.50 20.25 21.00 21.75 22.75 23.75
383.25 393.75 409.50 425.25 441.00 456.75 477.75 498.75
Pumping, hosting and Pouring 40.00 40.00 50.00 50.00 50.00 50.00 50.00 50.00
Labour 55.00 55.00 55.00 55.00 55.00 55.00 55.00 55.00
478.25 488.75 514.50 530.25 546.00 561.75 582.75 603.75
Add Profit & Overhead 15 % 72.00 73.00 77.00 80.00 82.00 84.00 87.00 91.00
44 Formwork
Cost/M2 50.00-80.00
Region
45 Steel Reinforcement SDK Base WP29