100% found this document useful (1 vote)
182 views9 pages

Laying and Maintenance of Track

The document discusses the laying and maintenance of railway tracks. It provides details on: 1. The process of laying tracks, including verifying the subgrade, using track laying machines, and the output of high-speed machines. 2. Maintenance of tracks is necessary over time to address degradation and ensure safety and comfort. Maintenance addresses geometrical and mechanical parameters. 3. Track defects are differences between actual and theoretical track characteristics and are addressed through maintenance to restore the track geometry.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
182 views9 pages

Laying and Maintenance of Track

The document discusses the laying and maintenance of railway tracks. It provides details on: 1. The process of laying tracks, including verifying the subgrade, using track laying machines, and the output of high-speed machines. 2. Maintenance of tracks is necessary over time to address degradation and ensure safety and comfort. Maintenance addresses geometrical and mechanical parameters. 3. Track defects are differences between actual and theoretical track characteristics and are addressed through maintenance to restore the track geometry.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

12/22/2016

Laying of track
 Before laying the track, it should be verified

LECTURE 9 that the subgrade has been properly


compacted and that the transverse slope (3-
LAYING AND MAINTENANCE OF TRACK
5%) is correctly given
 There are many types of track laying
machines
 A high-speed laying machine (with a workshift
of 6 hours) can achieve an average output of
1.3 km per shift.
 With peak output of 1.5 – 2 km per shift

1 2

Laying of track Laying of track


 Before laying the track, it should be verified
that the subgrade has been properly Sequence of construction of the various track
works
compacted and that the transverse slope (3-
At it’s simplest;
5%) is correctly given
 There are many types of track laying
i. Prepare the subgrade
machines ii. Place and compact all layers up to
 A high-speed laying machine (with a workshift sub-ballast
of 6 hours) can achieve an average output of iii. Place two strips of ballast
1.3 km per shift. iv. Seat sleepers on ballast
 With peak output of 1.5 – 2 km per shift

3 4

1
12/22/2016

Laying of track
Laying of track
v. Place pads on sleepers Note also that;
vi. Place rails in correct alignment Several of these processes can be
vii. Attach fastening devices automated. Clearly it is important to
viii. Weld up/bolt rail sections achieve a good smooth alignment and
ix. Place more ballast around the sleepers machines assist greatly.
x. Tamp (see later) – essentially a
levelling process
xi. Let the trains compact the ballast for
you
5 6

Track maintenance Track maintenance


 After the various railways system components
 Geometrical parameters, the degradation of
start operating, degradation begins and, after
which is usually reversible
a certain time, mtce becomes necessary.
 Mechanical parameters which in most cases
 Track mtce affects both train safety and
cannot be restored without parts replacement
passenger comfort (rails, fasteners, sleepers, welds, etc.)
 With respect to safety, maintenance should be  For lines with 20,000 – 40,000 tons/day,
preventive restoration of geometrical characteristics is done
 Regarding comfort, mtce should be corrective after a traffic load of about 40 – 50 million tons
 The above objectives depend on two  While rails are replaced after about 500 – 600
parameters. million tons.
7 8

2
12/22/2016

Track maintenance Track maintenance

 Deviation between the actual and theoretical Track defects


values of geometrical track characteristics are Longitudinal defect (LD) – (a)
termed track defects  Is the difference between the theoretical and the
 Their restoration is accomplished through track real value of track elevation (Fig. 9.1)
mtce. Transverse defect (TD) – (b)
 Track defects should be distinguished from rail  Is the difference between the theoretical and the
defects real value of cant (Fig. 9.1)
Horizontal defect (HD) – (c)
 Is the horizontal deviation of the real position of
the track from its theoretical position (Fig. 9.1)
9 10

Track maintenance

Vegetation and weed control


Vegetation control
 There are several methods for controlling growth
of vegetation along the track, the following two
are effective
 Chemical means (herbicides – chlorate)
 Installation of an asphalt layer under the
ballast and on the side paths

Fig. 9.1: Track defects


11 12

3
12/22/2016

Track maintenance Track maintenance


Weed control Weed control
 Weeds can cause serious detrimental effects on  Herbicides are extensively used, particularly
the ballast and the subgrade by: hormone selective weedkillers
 Contaminating the ballast with dirt and
vegetation debris, which affect free drainage
 Accelerating the decay of components such as
concrete sleepers, not only by chemical action
but the expansion of roots in cracks and
crevices
 By obscuring the track, and thus defects
normally observed by naked eye would not
have been seen on routine visual inspections
13 14

Railway Maintenance Processes


1st Maintenance requirements
 A railway trackbed is not rigid. Correct track levels
 Ballast, sub-ballast and subgrade are unbound  If settlement occurs, then it is certain that some
materials. differential settlement will be present.
 Long-term movements are expected, most  Perhaps the ballast may be uniform but the
notably settlement. underlying subgrade certainly is not – neither are
the rails.
 The result - some sleepers will settle more quickly
What Maintenance is Needed? than others.

15 16

4
12/22/2016

2nd Maintenance requirements 3rd Maintenance requirements


Clean or replace ballast Restore shape of rail head
Railway ballast is not protected.
Steel rails are put under enormous stress
Dirt gets in from the atmosphere,
trains and from the subgrade soil from train wheels.
underneath. Sometimes this causes changes to the
The ballast can even break down shape of the rail head.
itself. Effects to the ride quality and, eventually,
Ballast slowly changes in nature, the safety of trains.
becoming more like soil. This should
take many years.
17 18

4th Maintenance requirements TAMPING

Replace rails  Tamping takes place by vibrating ballast


Rail head shape can only be corrected around each sleeper.
(by grinding) a certain number of times.
If too much material is lost from the rail  Tamping is carried out every year or so,
head, it can no longer safely fulfil its role. sometimes much more often.
Not only that but cracks will eventually
initiate in the rails.  Tamping induces ballast breakdown.
The rail has to be replaced for safety
reasons.
19 20

5
12/22/2016

TAMPING … TAMPING …

 The tamping machine is the most Advantages:


important track maintenance device.  The automated process is relatively rapid
 It restores the line and level of the track.  It restores the line and level of the track

Disadvantages:
 Leaves the ballast in a loosened state
 Immediate settlement is expected.
 Temporary speed restrictions is required.
 Creates more fine material.

21 22

TAMPING … TAMPING …

23 24

6
12/22/2016

TAMPING … STONE BLOWING


The Principle:
Small size stones are blown down into any
gap which exists between the bottom of
the sleeper and the ballast.

25 26

STONE BLOWING … BALLAST CLEANING

Stone Blowing Vs Tamping:  Eventually, after several cycles of


 Stone blowing avoids disturbance of the tamping and years of train load
ballast. application, the ballast will need to be
 Therefore, little immediate settlement cleaned and, probably, partially
and no ballast damage. replaced.
BUT  This is carried out using a ballast
cleaning machine.
 Stone blowing is more expensive
 It cannot be used with steel sleepers

27 28

7
12/22/2016

BALLAST CLEANING … BALLAST CLEANING …

The Principle:
 The ballast cleaner is a self-contained
unit.
 It progresses along the track at about 4
kph.
 Being slow, it is therefore expensive.

29 30

BALLAST CLEANING … Causes/sources of Contamination

The Principle:
 Ballast cleaning would normally be
followed by tamping to restore the
correct level to the track.

31 32

8
12/22/2016

Causes of Contamination … Causes of Contamination …

A:Dirt from the atmosphere: B: Due to contact stresses:


 It may be wind-blown or it may fall
directly from passing trains.  Results to a gradual breakdown of the
 Amounts to as much as a millimetre or material, f(stone strength, track
two a year. stiffness and number and weight of
 Washed down to the bottom of the axle loads).
ballast layer to less permeable
material.

33 34

Causes of Contamination … Causes of Contamination …

C:Tamping
 Damages the ballast, causing large
numbers of fractures in critical areas.
D:From the subgrade soil
 If not separated from the ballast (e.g. by
a sand blanket or a geotextile), the two
materials will mix.
 Ballast will tend to sink into the soils as
soil (in the form of slurry) is pumped (see
35 photo – next slide). 36

You might also like