CD M&W 2008 Ed - Sect 7 - Sealing Devices - MCTs
CD M&W 2008 Ed - Sect 7 - Sealing Devices - MCTs
SEALING DEVICES
7.1 General
7.1.1 Cables, conduits, pipes and ducts routing across the CD bounds of
protection shall comply with the protective requirements governed by
the respective bounds of protection as specified.
7.1.4 MCTs could be used for cables and conduits penetrating through the
following CD boundaries:
7.1.5
a) CD bounds of blast & gas protection
b) CD bounds of blast protection
c) CD bounds of gas protection
7.1.5 Pipes routing across the CD bounds of blast protection and bounds of
blast & gas protection shall be cast in or pressure grouted at the
structural penetrations. Where this is not possible, the use of MCTs for
pipes penetrating these CD boundaries shall be submitted to the
Engineer for approval. Pipes routing across the CD bounds of gas
protection could either be cast in/ pressure grouted at the structural
penetrations or routed through MCTs.
7.1.6 Surface-mounted and core-drilled MCTs shall not be used unless prior
approval has been obtained from the Engineer.
7.1.7 Twenty percent (20%) spare capacity in MCTs shall be provided for
future expansion. The spare capacity will be based on the area of
unused rubber blocks (spare blocks) as a percentage of the total area
of the rubber blocks (both the insert blocks and spare blocks).
May 2008
MW/7/2
7.1.9 The Contractors shall ensure that the MCTs are installed in a manner in
compliance with the requirements covered in Section 7.3 and 7.4.
a) frame
b) fishtails
c) insert/spare blocks
d) stay/anchor plates
e) compression unit
The type and size of MCTs frames shall be selected to meet different
services penetration requirements. Only type/size of MCT frames
approved by the Engineer shall be installed in CD shelters. The MCT
frames shall be made of hot-dip galvanised steel or stainless steel.
For cast-in MCTs, fishtails shall be welded on the frames to secure the
frames to the concrete structure. For surface-mounted MCTs, proper
gaskets and sealant shall be provided to ensure gas-tightness at the
CD boundaries. Approved anchor bolts shall be used to mount these
MCTs to the concrete surface.
May 2008
MW/7/3
7.2.3 Fishtails
Fishtails shall be provided for cast-in MCT frames to secure the frames
to the concrete structure. Fishtails shall be evenly distributed around
the MCT frames to ensure proper securing to the concrete structure.
For MCT frames with packing space (usable space within MCT frame
for packing of insert/ spare blocks) smaller than 120 x 120 mm, 4 nos.
fishtails shall be provided. For MCT frames with packing space equal to
or larger than 120 x 120 mm, 6 nos. fishtails shall be provided. The
fishtails shall be continuously welded to the MCT frame at an
approximate angle of 45 degree.
Insert/ spare blocks are used in the packing of the services routing
through the MCTs. Two insert blocks (halves) are used for the packing
of each service. Spare blocks are used to fill up the remaining space in
the MCTs.
May 2008
MW/7/4
May 2008
MW/7/5
May 2008
MW/7/6
c) The void space for the MCT plug could be created by core-
drilling or the use of a cast-in galvanised steel pipe sleeve.
Where pipe sleeves are used at the CD bounds of blast & gas
protection or bounds of gas protection, puddle flanges shall be
provided on these pipe sleeves. These puddle flanges shall be
continuously welded to the pipe sleeves;
d) To ensure that the diameter of the opening conforms with the
tolerance standard specified by the MCTs manufacturers;
e) To insert the MCT plug into the opening;
f) To lay the services through the MCT plug;
g) To pack the insert/spare blocks. Suitable lubricant shall be
applied to the surfaces of the insert/spare blocks to improve the
ease of installation and ensure proper sealing of the MCT;
h) To complete the packing of the insert/spare blocks, and tighten
the bolts on the MCT plug in a diagonal sequence to complete
the seal.
a) For cast-in MCTs, the MCT frames and fishtails shall be tied to
the surrounding reinforcement bars to ensure that the frames are
properly secured to the structure during casting. Reinforcement-
bars shall also be used to support the polyform moulds/ box-up/
lead-in pipes during the casting of the MCT frames to ensure
proper alignment of the MCT frames and void space behind the
frames. The outer surface of the MCT frames shall flush with the
external surfaces of the CD walls/slabs;
May 2008
MW/7/7
c) For MCT plugs, the tolerance of the hole/pipe sleeve shall follow
exactly the MCT manufacturer’s specifications to ensure proper
sealing of the MCT plugs. Puddle flanges on the pipe sleeves
shall be continuously welded to the pipe sleeves. The
compression bolts shall be tightened in a diagonally opposite
manner to ensure uniform and proper compression of the
system;
b) Inner surface of the frame shall be smooth and free from dust/
corrosion. Concrete slag around the MCT frames shall be
removed to accommodate the insertion and movement of the
stay/anchor plates during packing;
f) The bolts of the compression unit shall be tightened till the front
face of the said unit flushes with the frame surface to ensure
sufficient compression of the MCT;
May 2008
MW/7/8
7.5.1 Type tests shall be conducted for the type/size of MCTs to be installed
in CD shelters to verify compliance with CD requirements. These type
tests shall include blast-resistance test, gas-tightness test and ageing
test conducted in independent test agencies. Detailed test procedures
shall be submitted for Engineer’s review and acceptance.
7.5.2.2 The Contractor shall submit all relevant information on the independent
testing agency such as organisation, testing facilities, track record, etc.
for approval. The testing agency shall have the necessary expertise,
experience, equipment and apparatus to carry out the required test.
The testing agency shall be required to certify that the MCTs have
successfully passed the type test in accordance with the requirements
specified herein.
Shock tube tests shall be carried out to ascertain the blast resistance of
the MCTs. The shock tube shall generate a shock wave to simulate air
blast of the required intensity and the MCTs shall be subject to the
impact of the shock waves to test its integrity and reliability.
May 2008
MW/7/9
MCTs shall be set up in a manner such that that surface of the MCT to
be installed in the CD Shelter facing the blast would be experiencing
the blast in the test. Blast test shall be carried out on MCTs filled with
an approved number of services (cables, conduits and pipes).
Pressure transducers
600 400
AE
MCT
Diaphragm
The MCT shall be subjected to a test shock wave with a minimum peak
reflected overpressure Pmax of 40 bar with a minimum reflected impulse
May 2008
MW/7/10
t
to 3.5ms<t1<5
ms
Pressure Profile for Shock Tube Tests ( Reflected Pressure )
May 2008
MW/7/11
In general, the gas-tightness test shall include, but not limited to, the
following procedures:
7.6.1 Contractors shall conduct on-site tests to verify the proper installation of
the MCTs. This site testing shall verify the gas-tightness performance of
the MCTs after installation, ie. with the services in place.
Contractors shall submit detailed test procedures, test set-up and test
instrumentation for review and approval.
The test procedure for the on-site testing shall include the following:
May 2008
MW/7/12
Each group of MCTs would be accepted if the selected MCT passes the
leakage test. If the selected MCT fails the leakage test, another three
MCTs shall be randomly selected from the same group for testing. If all
the three MCTs pass the leakage test, the group of MCTs would be
accepted and rectification works shall be carried out for the failed MCT.
In an event when any one of the three MCTs fails the leakage test,
rectification works shall be carried out for the entire group of MCTs, and
the testing procedure would be repeated after the rectification works.
7.7.1 The contractors shall make submission on the selection and installation
of the MCTs for the Engineer’s approval prior to commencement of
works.
May 2008
MW/7/13
g) Workmanship specifications;
j) MCT filling plans that illustrate the types, sizes and configuration
of services routing through each MCT frame;
k) Job references.
May 2008
MW/7/14
7.8.1 General
Table 7.2 lists the possible options of penetration details and refers to
the typical penetration details shown in Fig's 7.3-1 to 7.3-12.
Fig 7.2 indicates corresponding example locations on an example
shelter layout.
For any water pipe penetrating through a CD bound of blast & gas
protection / bound of blast protection / bound of gas protection, an
isolation valve shall be provided on the water pipe in the zone of blast &
gas protection / zone of blast protection / zone of gas protection
respectively just before pipe penetration through the bound of
protection. Please refer to Figure 7.1-1 for illustration.
Any dry pipe penetrating through a CD bound of blast & gas protection /
bound of blast protection / bound of gas protection shall be provided
with a removable short pipe section in the zone of blast & gas protection
/ zone of blast protection / zone of gas protection respectively just
before pipe penetration through the bound of protection. During
conversion to CD operations, the pipe section shall
May 2008
MW/7/15
May 2008
MW/7/16
May 2008
May 2008
MW/7/17
Details 2a; b
Cables MCT, cast-in Figures
& 7.3-3, -4
Example 1, conduits
Figure 7.2 MCT, core-drilled Detail 3 Requires Engineer's
Figures 9.3-5 approval
May 2008
MW/7/19
gas protection
(v) Ducts Welded flange Detail 7
(Weldable) plate with Figure 7.3-9
expansion anchor
bolts
Pipes
Air-tight boundary (weldable and Details 1 to 8
of AHU-intake plenum non-weldable) Same details as Fig's 9.3-1
(AIP) & bounds of gas to 9.3-10
cables & protection
conduits
May 2008
MW/7/20
May 2008
MW/7/21
Cables, conduit
(For conduits, see sketch below)
Rubber blocks
Flexible
Rubber Block conduit
BLAST SIDE
May 2008
MW/7/22
MCT
Rubber block
BLAST
SIDE
May 2008
MW/7/23
Sealant
Welded flange
Void (or grout)
Welded pipe
Expansion anchor
Reinforced concrete wall/ slab
Sealant
Edge distance
CD approved to suit anchor bolt
anchor bolt
Rubber block
MCT frame
Edge distance
to suit anchor bolt
Sealant
May 2008
MW/7/24
Sealant
Sealant
Sealant
May 2008
MW/7/25
SECTION
External wall
Pressure grouting
Stop valve
May 2008