Module - 14 EARTHWORK & MASS DIAGRAM
Module - 14 EARTHWORK & MASS DIAGRAM
EARTHWORK
❑ Cross Sections
❑ Quantities- Excavation and Embankment using
▪ Average End Area Method
▪ Prismoidal Formula
▪ Average End Area Method with
Prismoidal correction
❑ Total Quantities- Topsoil
❑ Shrinkage
Cross Sections
❑ Two Types
1. Existing
2. Proposed
❑ Cross sections tell us the amount of cut and fill at each
station. Existing
Proposed
Quantities
Prismoidal Formula
❑ Excavation- the amount of material that needs to be
❑ Prismoidal formula usually yields smaller volume than
removed from the grade.
does the Average-End Area Method.
❑ Embankment- the amount of material that needs to
❑ The area of the middle section Am is determined by
be added to the grade.
taking cross sections there or by averaging the
❑ Excavation and embankment are calculated with
dimensions of the end cross sections and using these
cross sections using the average end area method.
values to calculate the area. (It is not determined by
averaging the end area).
Average End Area Method
❑ Although the prismoidal formula does provide better
❑ The area between the existing ground and proposed
estimates of the volume of the prismoids, the
ground is calculated at each cross-section.
average-end-area method is more commonly used
❑ The area between two consecutive cross-sections is
because the difference between the two methods is
averaged.
quite small except where abrupt changes in cross-
❑ This area is multiplied by the distance between two
section occurs.
cross-sections.
𝑨𝟏 + 𝑨𝟐 𝑨𝟏 + 𝟒𝑨𝒎 + 𝑨𝟐
𝑽𝑬 = ൬ ൰𝑳 𝑽𝒑 = ൬ ൰𝑳
𝟐 𝟔
𝑤 𝑐 Prismoidal Correction Formula
𝐴= ሺℎ𝐿 + ℎ𝑅 ሻ + ሺ𝑑𝐿 + 𝑑𝑅 ሻ
4 2 ❑ If it is desired to determine the prismoidal volume, it is
Where: easier to use average-end-area method and correct
w – width of the road the results obtained with prismoidal correction
h – height left formula. 𝑳
L
h – height right 𝑪𝒗 = ሺ𝑪𝟏 − 𝑪𝟐 ሻሺ𝒘𝟏 − 𝒘𝟐 ሻ
R 𝟏𝟐
c – height of center line
d – distance from centerline to the left NOTE:
L
𝑽𝑷 = 𝑽𝑬 − 𝑪𝒗 𝑾𝟏 = 𝒅𝒍𝟏 + 𝒅𝒓𝟏
d – distance from centerline to the right 𝑾𝟐 = 𝒅𝒍𝟐 + 𝒅𝒓𝟐
R
Total Quantities
❑ Topsoil- topsoil quantities are not calculated into the Basic Definitions
excavation or embankment. This is a separate value ❑ Mass Diagram- A graphical representation of the
that has to be dealt with separately. cumulative amount of earthwork moved along the
❑ Imported topsoil is needed if the stripping volume centerline and distances over which the earth and
acquired does not fulfill the quantity of topsoil that is materials are to be transported.
proposed.
Shrinkage
❑ Shrinkage is the % additional volume added to the
embankment quantity.
➢ Shrinkage factor may vary from 5% to 20%
depending on the character of the material
involved
𝐹𝑖𝑙𝑙
𝐴𝑑𝑗𝑢𝑠𝑡𝑒𝑑 𝐹𝑖𝑙𝑙 =
ሺ1 − 𝑠ℎ𝑟𝑖𝑛𝑘𝑎𝑔𝑒 𝑓𝑎𝑐𝑡𝑜𝑟ሻ
BORROW PIT
❑ During construction of roads, airports, dams, and
other projects involving earthwork, it is often
necessary to or borrow earth from a designated area
near the project in order to construct embankments.
❑ In construction and civil engineering, a borrow pit,
also known as a sand box, is an area where material
(usually soil, gravel or sand) has been dug for use at
another location
Definitions
❑ Haul- the transportation of excavated material from
its original position to is final location in the work or
other disposal area. This is also know as authorized
haul.
❑ Average haul- determined from mass diagram.
Average haul is the area of the mass diagram
representing the number of cubic yard stations of haul
between balance points divided by the ordinate of the
mass which the yardage is hauled.
❑ Overhaul - the authorized hauling of excavation
beyond the specified free-haul distance.
❑ Free haul -Average haul for project that is free