Rig Specification - SPE - 02 - Upd

This document provides specifications for Rig IOS-SPE #02, a 350 HP truck mounted drilling rig. Key details include: - The rig was manufactured in 2008 in the USA and is ready for use in Siak, Riau, Indonesia. - It has a 350 HP drawwork and can hoist up to 225,000 lbs with its 97 foot mast. - The rig is equipped with mud pumps, tanks, and flow lines to circulate drilling mud including a 400 HP triplex mud pump that can pump between 6-8 bpm.

Uploaded by

Hadi Faisal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
264 views

Rig Specification - SPE - 02 - Upd

This document provides specifications for Rig IOS-SPE #02, a 350 HP truck mounted drilling rig. Key details include: - The rig was manufactured in 2008 in the USA and is ready for use in Siak, Riau, Indonesia. - It has a 350 HP drawwork and can hoist up to 225,000 lbs with its 97 foot mast. - The rig is equipped with mud pumps, tanks, and flow lines to circulate drilling mud including a 400 HP triplex mud pump that can pump between 6-8 bpm.

Uploaded by

Hadi Faisal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

RIG 350 HP IOS – SPE SPECIFICATION

Update: February, 2022

1. General Details
No Description Specification
1 Name of Drill Unit (Rig) Rig IOS-SPE #02
2 Rig Type Truck Mounted Rig
3 Rig Capacity 350 HP
4 Manufacturer Service King
5 Year of Manufacture 2008
6 SKPI/PLO MIGAS : 212/56-331/PLO/DMT/2018
EBTKE : 05.STF/30/SKPI/DEP/2021
7 Place of Manufacture the Midwestern United States (USA)
8 Drawwork 350 HP Self-Propelled Double Drums complete with Hydraulic
Cylinder type for make up and break out Tong, C/W Torque
gauge, Chrono-O-Matic, Hydro-O-Matic Brake, Friction Disk
system for secondary brake and six bolt clamp type dead line
anchor.
9 Rig Availability Ready and available in Siak, Riau Indonesia

2. RIG and Supporting Specification


HOISTING SYSTEM  
1 Rig and Mast - Service King USA 1 Unit
- Mobile Rig, truck mounted.
- Mast clear height 97 feet
- Hook Load Capacity 6 lines 225,000 Lbs
- Racking capacity 7000-ft 2-7/8-in doubles
- Completed with Anti Fall and Climbing Devices, retracted type, match to mast height.
2 Drawwork - Service King USA 1 Set
- Input HP Rating 350HP
- Double drum w/ drilling line & sandline drum
- Completed w/ Auxiliary Brake (Friction Disk Brake)
- Sandline 1,800-m, 9/16” size c/w sure way sand line guide.
3 Swabbing tool and lubricator completed with swivel, pack off & on-off tools, consists of. 1 Set
- various connection union.
- Hydraulic hand pump.
- Type H oil saver c/w rubber.
- Tubular jar + sinker bar.
- Swivel ROPE Socket.

Page 1 of 6
- Mandrel cup rubber.
4 Crown Block Saver with Crown-o-Matic 1 set
5 Crown Block. Hook load capacity 180,000-lbs 1 set
6 IDECO Travelling Block with Hook, load capacity 200,000-lbs 1 set
7 BVM Link for tubing elevator, 1-3/4” X 72" size, Load capacity with 110 Ton (242,550 lbs) 1 set
8 Link for sucker rod elevator 1 set
9 BVM - Elevator  
  - Single elevator for 2-3/8” tubing EUE 2 ea
  - Single elevator for 2-7/8” tubing EUE 2 ea
  - Single elevator for 2-7/8” Drill pipe 2 ea
  - Single elevator for 3-1/2” tubing EUE 2 ea
  - Single elevator 4-1/2” Blank pipe 1 ea
  - Sucker Rod Elevator for 7/8” sucker rod 2 ea
  - Sucker Rod Elevator for 3/4” sucker rod 2 ea
  - Single elevator for 5-1/2” casing c/w 5-1/2” safety clamp (for RIH ESP shroud) 1 ea
10 Air Hoist 1 ea
11 CAVIN - Spider Slip  
  - Dies for 2-3/8” 2 set
  - Dies for 2-7/8” 2 Set
  - Dies for 3-1/2” 2 Set
12 DP slip  
  - Dies for 2-7/8”, 3-1/2" 2 Set
12 Wagner USA - Weight Indicator 1 set
13 Deck floor complete or working platform 1 set
14 V-door 1 set
15 Cat Walk 1 set
16 Pipe Rack 1 set
17 Hydraulic pump for rig 2 set

POWER & ELECTRICAL SYSTEM  


1 Generator Set 2 Unit
CAT 3406 Generator with diesel engine, Rating @ 250 - 350 KVA at 50 or 60 Hz, complete with, All of
- Cooling system electrical
- Air cleaner equipment
- Safety Equipment: safety shutdown switch, Hydraulic Mechanism, Flame arrester muffler, Dynamo explosion
stater 24 Volt – Must be rated to power all Rig and third-party electrical equipment at 90% max. proof and
rating. refer to IADC
- Completed with maintenance record regulation
2 Philip - Rig Lighting 12 EA
- Explosion Proof Lights standing lamp
- Appropriate to night safety operation min 1500
- Mast light complete Watt

CIRCULATING SYSTEM  
1 Mud Pump - Work Force and National 1 Set
400 Hp Triplex pump
- Able to give pump pressure up to 3000-psi
Page 2 of 6
- Able to give pump rate 6-bpm up to 8-bpm- Completed w/ calibrated heavy duty pressure gauge-
Completed w/ certified safety relieve valve
- completed with shear pin - Completed w/ centrifugal feeder pump
- 1 pump able to give 0.5-bpm rate
- Completed with spart part liner, piston and rubber size 4”, 4-1/2”, 5”.
- Completed with connection to 4” line WECO for COMPANY’s cementing unit
2 Salt Water Tank 2 units
- Tank capacity 200-bbls
- Complete with agitator
- Able to set-up tank in parallel position
3 DOC Tank 1 unit
-  Tank capacity 200-bbls
- Completed with screen
4 Influx Tank 1 unit
- Tank capacity 150-bbls
5 Trip Tank 1 unit
- Tank capacity max 20-bbls
- Volume channel indicator: 0.5-bbls per inch
6 Hopper 1 set
- Complete with electrical centrifugal pump
- Connected to SW tank
7 Pump Flow Line
- 2” chicksan w/ min rating 5000-psi 1 set
- 3” flexible hose w/ min rating 5000-psi length 30 – 40 FT each 1 set
- 3" flow line 1 load
- Rating 5000 psi
- Length: min. 155-ft from the well
- Connection: thread or quick coupling
- Complete with cross-over 2-7/8” x 2” LP
8 3" Stand Pipe, rating 5000-psi 1 ea
9 Kelly Hose, rating 5000-psi 1 ea

BLOW OUT PREVENTER SYSTEM  


1 BOP completed with valid certificated  
Hydril, 7-1/16” x 3000-psi Annular completed with rubber element and ring gasket. 1 set
Shaffer, 7-1/16” x 3000-psi Double Ram (Pipe & Blind) 1 Set each
Completed with:
- 3-1/2” single pipe ram block
- 2-7/8” single pipe ram block
- 2-3/8” single pipe ram block
- Provide spare rubber element each size and ring gasket
2 Koomey Type 80 – Accumulator 1 set
suitable for BOP Stack
- Capacity of reservoir tank: 380-Gals
- Accumulator Bottles: 8-ea (10-gals/bottle)
- Rating 3,000-psi
- Master Control Set: 4-Stations
- Driven charge pumps: Electric driven pumps and air operated pumps
- Length of control hose: min 150-ft
- Control line suitcases completed with armor.
- Alarm System
Page 3 of 6
- Emergency Air Compressor for air supply to pneumatic pump accumulator
3 Inside BOP 1 ea
- Tested & Certificate for up to 5000-psi
- Complete w/ 2-7/8” EUE, 2-3/8” EUE connection
4 Safety valve 2 ea
- Tested & Certificate for up to 5000-psi
- Complete w/ 2-7/8” EUE, 2-3/8” EUE, 2-7/8” IF, 3-1/2” IF connection
5 FMC - Class III Manifold 1 set
- At least three ways of fluid
- Working pressure 5000-psi
- Min. 5 gate valve + 1 adjustable choke
6 Poor Boy Separator / Mud Gas Separator  
7 Flaring 1 set
- Flare Line and stack system
- Length: min. 155-ft from the well
- Connection: Flanged-end or welded
8 Sucker Rod BOP completed with hook sucker rod (SR), shackle, element packing spare   1 ea
9  Casing Flange Adaptor C/w Stud bolt
& nut 
- Adaptor 7-1/16” 2000 psi x 7-1/16” 3000 psi 1
- Adaptor 7-1/16” 3000psi x 7-1/16” 5000 psi 1

DRILLING & ROTATING EQUIPMENT  


1 LOGAN - Power Swivel & CAT Engine Power Pack Unit 1 unit
- Static load rating 120 Ton
- Right & Left torque limit (min. 8100 lbs.ft)
- Has connection to various size of tubing, DP, and DC
- Completed with maintenance record
2 King Swivel 1 unit
- Static load rating 120 Ton
- Standard stem connection 3-1/2 IF
3 BHA (Class: New or premium c/w thread protector) inspected and
certificated

- 4-3/4" Drill Collar completed with safety clamp 10 ea


- 3.5" Drill pipe 9.5 PPF 150 jts
- Premium class grade G completed with drift
- All of drill collar completed w/ handling equipment (DC elevator, lifting sub, safety chain, clam, and
pipe wiper)
Drilling Sub
- Provide complete drilling sub and crossover to run all of string for DC and DP.
4 Lower Kelly cock 1 ea
5 Casing Scrapper  
- 5-1/2” casing scrapper
- 7” casing scrapper 1 ea
6 Maverick - Power Tong 2 set
- Able to connect & disconnect string 5 sets
- Completed w/ calibrated torque gauge 5 sets
- Dies for Tubing 2-3/8”
- Dies for Tubing 2-7/8”
- Dies for Tubing 3-1/2”

Page 4 of 6
- Dies for DP 2-7/8”
7 Westco - SR Power Tong 1 set
- Able to connect & disconnect string
- Completed w/ calibrated torque gauge
8 BVM - Manual DP tong completed with torque meter 1set
9 Kunci tong (Kunci buaya) dari 2-7/8” s/d 5-1/2 completed with torque meter and spare 1 set

FISHING TOOL  
1 Over shoot  
- Over shoot for 2-7/8” tubing 1 set
Set of basket grapple for fishing 2-7/8” body, upset pin, and box
- Over shoot for 2-3/8” tubing 1 set
Set of basket grapple for fishing 2-3/8” body, upset pin, and box
- Over shoot for 3-1/2“tubing 1 set
Set of basket Grapple for fishing 3” body, upset pin, and box
2 Junk Basket for casing 5-1/2”  
3 Junk Basket minimum 4-3/4“ for casing 7” 2 ea
4 Impression Block  
- impression block for 5-1/2” casing
- impression block for 7” casing
5 5-1/2”, 7” Magnet able to connect to string and sand line 1 ea

SAFETY EQUIPMENT  
1 Engine Safety Device  1 set
- All of engines must have overspeed shutdown devices, spark arrest mufflers
2 APAR
- 150-lbs dry powder fire extinguisher 1 ea
- 10-lbs dry powder fire extinguisher 12 ea
3 Eye Wash 5 set
4 Gas Detector, Provided last calibration 1 set
5 Warning Sign, as required 1 load
6 Escape lines, DBI SALA – Slow Speed type 1 set
7 LEWIS - Climbing belt (body harness) 2 set
8 LEWIS - Lightning Arrester Complete with megger test equipment 1 set
9 Windsock 2 ea
10 First Aid Kit (P3K) 4 load
11 Personnel gas badge, Provide for minimum quantity of crew onsite 1 set
12 High Impact Glove for rig personnel  1 load
13 SCBA 2 set
14 ELSA 4 set

SUPPORTING EQUIPMENT  
1 Well Site Portacamp 1 set
- 2 beds complete for Coyman & Engineer
- Completed w/ Air Conditioner in each room
- Completed w/ water dispenser
- Completed w/ toilet
Page 5 of 6
2 Rig Supt Office Portacamp 1 set
- 1 bed complete for Rig Supt
- Completed w/ Air Conditioner in each room
- Completed w/ water dispenser
- Completed w/ toilet
3 Crew Portacamp for accommodation during on duty 1 set (depend
- full set portacamp for on duty personnel on total crew
- Completed w/ Air Conditioner in each room onsite)
- Completed w/ water dispenser
- Completed w/ toilet
4 Muster point crew and security post 1 set
5 Fuel tank 1 unit
- Complete w/ fuel transfer pump and metering
- Capacity 10,000-ltr
6 Warehouse 1 unit
7 Tool Box 2 set
8 Welding machine 1 Set
9 BPV setting tool completed with lubricator 1 set
10 WC portable 1 unit
11 Barton chart recorder rating 5,000-psi completed with Barton paper and scale in minute (not day)  1 set
12 Digital pressure gauge, rating 5,000psi 1 set
13 Mud balance 1 set
14 Turbidity Meter 1 set
15 Salinity Meter 1 set
16 Mars Funnel 1 set
17 PH Meter / lakmus paper 1 set
18 Tubing Stripper 2-7/8”, 3-1/2” completed with rubber 1 set
19 Radio communication  
- HT gas proof 4 unit
- Radio Base 1 unit
20 Bug blower water resistant 1 set
21 Derrick Tape scale FT (not meter) include back up 1 ea

Page 6 of 6