Microtunneling Method Statement Booklet
Microtunneling Method Statement Booklet
Method of Operation
METHOD OF OPERATION - MICROTUNNELING
2|
PLANETARY GEARBOX
ELECTRIC MOTOR
Figure 2. Center drive MTBM contains a single motor that drives a planetary gearbox coupled to a drive shaft.
Figure 3. Face access periphery drive MTBMs contain four interior motors on the periphery of the gear ring with pinions on a slewing bearing
(some components removed for visibility).
3
Face-access, periphery drive MTBMs feature
higher power and torque for the larger diameter
pipe installations, and an access door at the cutter 1
head with back loaded tooling mounts (see Figure
4) to replace worn tooling on extended drives.
These MTBMs come with an on-board electric over
hydraulic power pack for cutter head drive in low, 1
medium, and high torque for accurate control in
changeable geology.
Figure 5. MTBM crushing cone 1) high pressure jetting nozzles, 2) slurry inlets,
and 3) slurry cutting nozzles.
4|
SOFT GROUND MIXED GROUND ROCK
CUTTER HEAD CUTTER HEAD CUTTER HEAD
For soft, wet, easily displaceable ground For varying, soft to high compressive For high compressive strength geology
Bullet Bit Tooling strength geology Disc Cutters and Bucket Scrappers
Disc Cutters and Bullet Bit Tooling
SOIL DIGESTION AND SLURRY CIRCULATION rates using sensors, flow meters and pit valves in the
closed loop slurry system. Balancing the input and
The MTBM excavates spoil at the face of the bore output of the slurry by volume and pressure is vital
while simultaneous pipe segments are installed in for effective and accurate advancement and to avoid
the launch shaft and thrust forward by the hydraulic overloading the cutter head or removing too much
cylinders on the jacking frame. The MTBM’s rotating soil thereby causing settlement.
cutter head is steerable, and bi-directional for
precise ground excavation.
6|
PREPARING THE SHAFTS
The reception shaft or exit shaft is often prepared Figure 10. The MTBM is typically launched through a shaft seal to prevent
with a retrieval shaft seal mounted on the shaft wall subsidence from entering the launch shaft.
at the anticipated MTBM emergence location.
JACKING FRAMES
8|
PUMPS
A slurry booster pump is often placed within the
Slurry is circulated through the microtunneling MTBM to aid in transporting the heavy, soil-laden
lines with feed, return and booster pumps that are slurry from the MTBM to the launch shaft.
regulated through the control container’s variable
frequency drives. A high-pressure jetting pump provides high velocity
jetting through the microtunneling utility lines to the
The slurry feed pump is located on the surface near MTBM cutter face to break down clay and silty soil,
the slurry tanks, settlement ponds or separation clean the crushing chamber and assist with spoil
plant. The slurry feed pump pushes the slurry water intake and flow.
to the MTBM for slurry injection in the crushing
chamber.
SLURRY
FEED PUMP
SLURRY
ACTIVE SLURRY
BOOSTER
TARGET RETURN
PUMP
PUMP ACTIVE
GUIDANCE
SYSTEM
ACTIVE
TARGET JACKING FRAME
Figure 13. The jacking frame is positioned in the base of the launch shaft on line and grade and its hydraulic cylinders advance the MTBM and pipe.
Figure 14. Propulsion or Jacking and Lubrication Cans exert even jacking force Figure 15. A pipe clamp is used when microtunneling within a body of water
for smooth advancement and house lubrication feed valves for the MTBM. to hold the previous pipe segment in place and contend with buoyant forces.
10 |
ABIS Control Skid
Bentonite Pump
Automated Injection Automated Injection Automated Injection Automated Injection Automated Injection Automated Injection
Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve Ball Valve
Bentonite Flow Assembly #6 Assembly #5 Assembly #4 Assembly #3 Assembly #2 Assembly #1
Figure 16: The ABIS system is used to automatically deliver bentonite at specific intervals from a touch screen monitor.
12 |
AZ100 TOTAL GUIDANCE SYSTEM measurement prisms to provide reference points for
guidance system location and azimuth.
Exclusive to Akkerman, the AZ100 Total Guidance
System (TGS) is an azimuth based tunneling After an initial underground survey has been
navigation system with self-leveling station units conducted, reference prisms are installed on the
that is used for extended and curved tunneling, launch shaft wall to determine bearing. Next the
pipe jacking and microtunneling applications. It shaft station and prism are placed on a self-leveling
comprises individual, self leveling, station units tribrach according to the design axis behind the
that maintain a location measurement connection thrust wall (see Figure 20). The first pipe station is
throughout the alignment without continuous added at 300-linear feet (see Figure 21, 22) and
manual surveying. The system interfaces with additional pipe stations are added as required along
the standard Akkerman MTBM target but can be the alignment to maintain a line of sight among
configured with any manufacturer’s target. stations. On average, a 1,000-3,500-linear feet
range of distance can be achieved and is dependent
The most significant point of differentiation between upon prism size, tunnel diameter and atmospherics.
the AZ100 TGS and other tunneling navigation
systems is that an initial survey to ascertain tunnel The AZ100 TGS has proven to be most economical
starting and end points is the only survey that is on straight and curved critical alignments exceeding
required; therefore, downtime is pointedly reduced 700-feet, for any 48-inch ID or larger microtunneling
for uninterrupted mining. project or 72-inch minimum pipe jacking or tunneling
operation. After a contractor’s initial investment, the
The system comprises a jacking shaft station pipe and station units can be modified for a large
and several pipe stations that look to stationary variety of project designs.
Microtunneling Control Container
Measurement Prism
TGS--100
Shaft Station Laser Target
Tribrach
Station Network Unit (SNU)
MTBM
Jacking Shaft
Figure 20: The AZ100 TGS shaft station is positioned behind the thrust block in a microtunneling operation.
Pipe Station
Measurement Prism
TGS-100
Laser Target
Power & LAN
Jacking Shaft
Figure 21: The AZ100 TGS pipe stations are added throughout the tunnel to maintain a line of sight between all stations.
Measurement
Reference Prism
Prism
Pipe
Station #1
Shaft
Station
Reference
Prism TGS-100
Target
Jacking Shaft
Receiving Shaft
Measurement
Prism
Pipe Pipe
Station #2 Station #1
Reference
Prism
TGS-100
Target
Shaft
Reference Station
Prism
Receiving Shaft
Jacking Shaft
Figure 22: AZ100 TGS station unit set-ups on straight and curved alignments.
14 |
NOTES: