Instrument Commissioning Checklist PDF Free
Instrument Commissioning Checklist PDF Free
STANDARD TECHNICAL
SPECIFICATION
FOR
INSTRUMENTATION
INSTALLATION COMMISSIONING
This Standard Technical Specification is subject to change without prior notice. The
most current issue will at all times be located on the Nordural web site,
www.nordural.is
NORÐURÁL - ENGINEERING
STANDARD TECHNICAL SPECIFICATION
NORÐURÁL 00/07/TS010
NORDIC ALUMINUM
CONTENTS
SPECIFICATION PREFACE SHEET _________________________________________ 1
TECHNICAL SPECIFICATION ______________________________________________ 3
1.0 INTRODUCTION ________________________________________________________ 3
2.0 SCOPE__________________________________________________________________ 3
3.0 STANDARDS AND CODES OF PRACTICE __________________________________ 3
40 INSTRUMENT INSTALLATION ___________________________________________ 4
5.0 INSTRUMENT AND CONTROL PANELS ___________________________________ 4
6.0 PLC AND SCADA SYSTEMS ______________________________________________ 5
7.0 INSPECTION AND TESTING______________________________________________ 5
8.0 PRECOMMISSIONING ___________________________________________________ 7
9.0 COMMISSIONING _______________________________________________________ 7
APPENDICES____________________________________________________________ 8
-2-
STANDARD TECHNICAL SPECIFICATION
NORÐURÁL 00/07/TS010
NORDIC ALUMINUM
TECHNICAL SPECIFICATION
1.0 INTRODUCTION
This Specification is issued to give general guidelines and to outline basic requirements
to contractors to cover the testing and pre-commissioning of instrumentation and control
systems. It is intended to ensure that the equipment installed is as specified by the
design and that installation materials are of specified type and quality correctly installed
and in all respects suitable for commissioning to the Engineer's requirements.
In this Document the following words and expressions shall have the meaning
hereby assigned to them except where the context otherwise requires:
Engineer: The Owner or any person or organization employed or engaged at
any time by the Owner and authorized by the Owner, in writing, from time to
time to act on behalf of the Owner in the execution of the items covered by this
Document, in whole or in any part, for any or all purposes provided in this
Technical Specification.
Owner: Norðurál hf (Nordic Aluminum Corporation Ltd.), an independent legal
entity owned by Century Aluminum.
2.0 SCOPE
This procedure together with its appendices covers the scope of work, inspection and
testing of all instrument equipment from arrival on site up to and including pre-
commissioning.
In addition to the requirements of this specification the installation shall comply with:
-3-
STANDARD TECHNICAL SPECIFICATION
NORÐURÁL 00/07/TS010
NORDIC ALUMINUM
40 INSTRUMENT INSTALLATION
The installation of all sensors shall conform to good measuring practice so that a truly
representative signal of the variable is obtained. They must be installed according to
European EN Standards. Equipment shall be positioned to permit easy access for
visual inspection and maintenance but shall be protected from damage by personnel or
passing or falling objects. The equipment shall not be bracketed directly from pipework
or handrails. Care shall be taken to ensure equipment is not damaged or obstructed by
subsequent lagging/steelwork etc.
Provision shall be made for the adequate isolation of impulse lines and for the removal
of sensors for repair or calibration.
Equipment shall in all cases be installed with due regard for the safety of personnel.
When instrument/control panels arrive at site they will normally be prefabricated and
prewired. The Contractor will be responsible for lifting such panels and it shall be the
contractor's responsibility to ensure the panel is correctly positioned and bolted down in
accordance with his requirements.
A dimensional and detailed physical check to ensure that all dimensions are
correct against specifications and drawings.
Checks shall be made to ensure that gland plates are of a size sufficient to
accommodate all cabling and piping and that any internal trunking is of sufficient
size to accommodate any field wiring.
-4-
STANDARD TECHNICAL SPECIFICATION
NORÐURÁL 00/07/TS010
NORDIC ALUMINUM
Warning and general labels shall be checked to see if the descriptions are
correct and these are sufficient.
A function and calibration check shall be carried out on each instrument. Where
necessary the equipment shall be recalibrated.
All test equipment used shall be certified and certificates made available to
illustrate compliance.
Microprocessor based control systems are not covered by this procedure except in so
far as the tests detailed can be applied to components of a system.
Nevertheless, the basic requirement remains that every input and output signal must be
checked through from its field initiation point to control room display unit or vice versa.
All control functions must be checked for operability in accordance with the
manufacturer's stated performance characteristics.
All checks must be recorded on loop test sheets and the forms as attached may be used
as applicable.
Visual checks shall be made on all primary element installations and impulse piping to
ensure equipment has been installed in accordance with specifications and drawings.
Primary elements and their impulse lines shall be examined for correct location to meet
standard flow metering codes and tank zero datum for contents.
The orientation and access to all sensors shall be inspected to verify correct location in
the plant and serviceability of installation.
Isolation provided shall be checked together with slope on impulse lines i.e. at least 1 in
12.
-5-
STANDARD TECHNICAL SPECIFICATION
NORÐURÁL 00/07/TS010
NORDIC ALUMINUM
Field mounted transmitters shall be check calibrated to ensure they agree with
calibration/functional test certificates, where necessary they shall be re-calibrated.
An inspection shall be made of all junction boxes, earthing checks performed, cabling
arrangements inspected for neatness and accessibility.
A check shall be made that internal connections are as per drawing and are satisfactory.
All cabling and piping shall be inspected against specification and drawings. Wiring
shall be checked for correct materials, correct identification and physical installation
ensuring that kinks and strains have been avoided. Piping shall be inspected likewise.
All fittings and connections shall be inspected for correct installation and possible
absence or misapplication of sealing compounds.
A check shall be made to ensure that signal cabling is adequately segregated from
power cabling. Cable tray, trunking and brackets shall be inspected for firm fixing, no
sharp edges, protection of cut edges and acceptable routing.
Glanding and terminations shall be examined to ensure correctness of same and correct
termination of conductors, screen or shield. All connections shall be inspected for
security.
Insulation and continuity tests shall be carried out core to core for insulation value and
continuity. Testing shall be carried out with approved equipment and before final
connection to electronic equipment.
Pressure tests shall be carried out on all pipework with suitable isolation to protect
connected equipment. For lines containing pressure above 2 bars the pressure tests
decay shall not exceed 66 millibar (1 lb/ins2) in 10 minutes. For lines containing less
than 2 bar, pressure slightly above the maximum to be encountered on normal service
shall be applied through a bubble flow indicator. The bubble rate shall not exceed one
bubble in 10 seconds. After pressure testing, test gauges and equipment shall be
disconnected, connections remade and tested with soap solution when under service
pressure.
-6-
STANDARD TECHNICAL SPECIFICATION
NORÐURÁL 00/07/TS010
NORDIC ALUMINUM
Power supplies, electric and pneumatic shall be inspected to ensure installed supplies
are to specification and the drawings are suitable for supplied equipment. Earthing
facilities as well as fusing/circuit breaker values shall be as required.
A check against specification for type and accessories shall be made to ensure they are
correctly assembled and calibrated. Control valves shall be stroked to verify they
operate correctly over the full range, if incorrect they shall be adjusted accordingly.
Wherever possible they shall be check-calibrated in the contractor's workshop.
8.0 PRECOMMISSIONING
Loop testing shall be carried out to prove the installed instrument system functions
correctly. In general each complete instrument loop shall be tested as a system, where
necessary adjustments shall be made to the calibration. Associated alarms and trips
shall be checked during loop testing.
As part of loop testing various parameters of the panel mounted instruments may
require configuring. This shall be carried out utilising an acceptable configurator.
When loop testing is complete and 'signed off' by the Engineer the complete system
may be considered suitable for hot commissioning.
9.0 COMMISSIONING
Following pre-commissioning and at a time agreed with the Engineer the Contractor
shall have an instrument commissioning engineer available to assist in plant
commissioning.
Test certificates shall be issued to illustrate that complete testing has been completed.
Certificates shall take the form of certificates as illustrated in Appendix A.
The contractor shall provide these sheets or his own equivalent to the Engineer before
testing for client verification.
-7-
STANDARD TECHNICAL SPECIFICATION
NORÐURÁL 00/07/TS010
NORDIC ALUMINUM
The certificates must highlight test equipment used with its manufacturer's name, model
number, serial number, test certificate number and issue date as a minimum.
APPENDIX A
-8-
STANDARD TECHNICAL SPECIFICATION
NORÐURÁL 00/07/TS010
NORDIC ALUMINUM
REMARKS
ALARM SYSTEM No
-9-
STANDARD TECHNICAL SPECIFICATION
NORÐURÁL 00/07/TS010
NORDIC ALUMINUM
CALIBRATION CHECK
INPUT READING OR OUTPUT
RISING FALLING
% SPAN ACTUAL
ACTUAL % SPAN ERROR % ACTUAL % SPAN ERROR %
25
75
100
MANUFACTURERS QUOTED ACCURACY %
CONTROLLER CHECK
CONTROL MODE: PROPORTIONAL INTEGRAL DERIVATIVE
ON/OFF DIFF. GAP
CONTROLLER ALIGNMENT CORRECT AUTO/MANUAL CORR.
CONTROL ACTION DIRECT REVERSE
REMARKS
INSTRUMENT TAG No
- 10 -
STANDARD TECHNICAL SPECIFICATION
NORÐURÁL 00/07/TS010
NORDIC ALUMINUM
TAG No RANGE CHECKED WITNESSED DATE TAG No RANGE CHECKED WITNESSED DATE
CHECK SHEET No
- 11 -
STANDARD TECHNICAL SPECIFICATION
NORÐURÁL 00/07/TS010
NORDIC ALUMINUM
MECHANICAL/ELECTRICAL CHECKS
MEASURING ELEMENT: INSTALLATION CORRECT LOCATION CORRECT
ISOLATING VALVES CORRECT MATERIALS CORRECT
TAPPING(S) POSITION CORRECT ORIFICE DIAMETER
IMPULSE CONNECTIONS:
CORRECT TO HOOK UP MATERIALS CORRECT
PRESSURE TESTED TEST PRESSURE
CONNECTIONS: TRACED LAGGED
FIELD INSTRUMENTS
INSTALLATION CORRECT AIR SUPPLY CORRECT
WEATHER PROTECTED POWER SUPPLY CORRECT
PANEL INSTRUMENTS
INSTALLATION CORRECT AIR SUPPLY CORRECT
SCALE/CHART CORRECT POWER SUPPLY CORRECT
CONTROL VALVES
INSTALLATION AND LOCATION CORRECT SIZE AND TYPE CORRECT
STROKE TESTED POSITIONER CHECKED
LIMIT SWITCHES SET I./P. TRANSDUCER CHECKED
AIR SUPPLIES
CONNECTIONS CORRECT TO DRAWINGS BLOWN CLEAR AND LEAK TESTED
TRANSMISSION
PNEU. LINES INSPECTED, BLOWN CLEAR & LEAK TESTED
ELECT. INSULATION CHEKED-CORE TO CORE CORES TO EARTH
CONTINUITY CHEKED LOOP IMPEDANCE CHECKED
EARTH BONDING CHECKED ZENER BARRIERS CORRECT
TEMPERATURE LOOPS
T/C OR R/B CHECKED CABLE TO SECIFICATIONS
CONTINUITY CHECKED LOOP IMPEDANCE CHECKED
GENERAL
SUPPORTS CHECKED TAGGING CORRECT
CHECKED BY: DATE WITNESSED BY DATE
LOOP TEST
TRANSMITTER INPUT TRANSMITTER OUTPUT LOCAL INST. READING PANEL INST. READING
MEASUREMENT
CONTROLLER OUTPUT TRANSDUCER OUTPUT VALVE POSITION O/P CONTROL VALVE POS.
CONTROL
INSTRUMENT TAG No
- 12 -
STANDARD TECHNICAL SPECIFICATION
NORÐURÁL 00/07/TS010
NORDIC ALUMINUM
- 13 -