BIM Spatial Coordination
BIM Spatial Coordination
David E. Quigley
The author, MCAA, MCERF, NECA, The New Horizons Foundation, and
SMACNA shall have neither liability nor responsibility for errors or
omissions, nor is any liability assumed for damages resulting from the use
of the information contained herein. The information contained herein
should not be construed as legal advice. The reader must consult with legal
counsel to determine how laws or decisions discussed herein apply to the
reader’s specific circumstances.
FOREWARD............................................................................................ vii
INTRODUCTION.................................................................................... viii
CHAPTER 1 Spatial Coordination in a BIM Environment......................... 1
CHAPTER 2 BIM and Spatial Coordination Basics.................................. 11
2.1 Project Delivery Methods.............................................................. 11
2.2 Types of models............................................................................. 12
2.3 Types of software........................................................................... 15
2.4 Level of Development Specifications............................................. 16
CHAPTER 3 Building the Team............................................................... 19
3.1. Building an Effective Spatial Coordination Program .................... 19
3.2. Preparing Your BIM Implementation Plan ................................... 20
3.4 Internal Inventory of Skills............................................................. 25
3.5 Internal Communication Procedures ............................................ 28
3.6 Human Resource Requirements.................................................... 32
3.7. Outsourcing.................................................................................. 33
3.8 Working Within the Collaborative Process.................................... 37
CHAPTER 4 BIM Execution Plans........................................................... 39
4.1 The Contents of a BIM Execution Plan........................................... 39
4.2 Model Management Procedures................................................... 52
4.3 Schedules....................................................................................... 59
4.4 Reviewing a BIM Execution Plan.................................................... 61
4.5 Authoring a BIM Execution Plan.................................................... 65
CHAPTER 5 Managing the Process........................................................ 67
5.1 Establishing Norms for the Project................................................ 67
5.2 Setting Up the Project Environment ............................................. 70
5.3 Clash Detection.............................................................................. 75
5.4 Red Flags from the Coordination Process...................................... 83
CHAPTER 6 Documents of Record......................................................... 85
6.1 Working with Documents of Record.............................................. 85
6.2 Receivables from the Design Team................................................ 86
6.3 Internal Receivables from Your Project Team................................ 90
6.4 Inter-Trade Receivables................................................................. 91
6.5 Other Receivables.......................................................................... 93
6.6 Deliverables................................................................................... 93
6.7 Communication with the Design Team.......................................... 98
6.8 Managing Documents During the Coordination Process............. 100
vi Achieving Spatial Coordination Through BIM
The path I followed for the next 35 years gave me a unique perspec-
tive on the power of innovation and technology standards to transform
an industry. I was active in the development of three industry standards.
M y father was a Master Plumber. He The first was the initiative of the U.S. Defense Department to create a
single universal programming language aimed at reducing the cost of
owned and operated a mid-sized
development and maintenance for large defense projects (air, land, and
union plumbing and heating firm in sea). The second was the creation of a graphical user interface standard
western Massachusetts for almost 40 for the UNIX operating system. This open standard made it possible
years. He had me cutting and threading to use software applications on many different hardware platforms,
pipe when I was 8, welding at 15, and eliminating the redundant work required to support them all. The third
pre-fabricating sprinkler systems at 17. was a de facto industry standard from Microsoft to increase software
At 18, I became a union plumber. developer efficiencies by utilizing standard, “intelligent” objects within
an object-oriented design.
A s much as I loved working with my In each case, a large and influential entity—the U.S government, a
consortium of the largest computer manufacturers, and the world’s
father, I felt I had another calling—
largest software publisher—invested significant resources, money, and
teaching and computer technology—
reputation over a long period of time to achieve the same goal: remov-
which I pursued with his full support. ing the barriers to communication between programs and people. Each
recognized that without the intervention of a standard and defining sets
of rules for communicating and sharing data; people to people; people
to software and software to software, the inefficiency and duplication
of effort inherent in following the status quo would grind innovation in
INTRODUCTION these industries to a halt.
Does this sound familiar? The building services industry has been
struggling with the same issues and is the now in the process of adopt-
ing its industry standard—Building Information Modeling—designed
to address the same requirements for better communications, defining
reasonable rules for engagement, setting reliable expectations, and
improving the construction workflow through innovation.
To date, the acceptance, growth, and implementation of BIM across
the construction industry is still in its infancy. To understand how, why,
and at what rate standards are adopted, the work of Everett Rogers,
a world-renowned innovation researcher, is helpful. Rogers identifies
five qualities that can be used to predict the adoption of an innovation
through an industry and its constituencies.
1. Relative advantage: The degree to which an innovation is perceived
as better than the idea it supersedes by a particular group of users, mea-
sured in terms that matter to those users or perceived as advantageous
2. Compatibility with existing values and practices: The degree to
which an innovation is perceived as being consistent with the values,
past experiences and needs of potential adopters
Achieving Spatial Coordination Through BIM ix
* Everett Rogers, Diffusion of Innovations, 5th ed. (New York: Free Press, 2003), pp. 15–16.
** Level of Development Specification ©2013 by BIMForum
x Achieving Spatial Coordination Through BIM
INTRODUCTION BIM is a better way to build. From what I’ve seen in my work on
standards, BIM is here to stay. If you have been waiting on the sidelines,
now is the time to engage, because there is no turning back. Those
MEP contractors who embraced this innovation early have learned
much from their many BIM projects that can be of value to you. That
information is available in this Guide.
The changes that BIM introduced support the fundamental
motivation of every steam and pipe fitter, tin knocker, electrician, and
specialty contractor: the pride in a job well done. It is also worth noting
that these early adopters consistently bring their best game to the table.
It is my hope that other domains in the building process will rise to the
occasion by bringing their A-game to their LOD commitments, joining
the MEP and specialty contractors who are already pushing the industry
to new levels.
David E. Quigley
Milford, New Hampshire
October 2013
Achieving Spatial Coordination Through BIM 1
ss an
e
e
so re
lid oft re
BI rev trod s
de soft rs
V1 e
Lig ngs
d
re
ob e
ar
n tio 2
ar
ct
bl
in ject
ed BI ard war
do d i bor M S iew uce
r
a
V
e
ro Pl
a
M wa
ftw
je
ta
ftw
w
l
in ut
3D CA ftw
ftw
i
al
&
aw
ac n
tio roj BIM ob
ai ea on and soft
aft mp
ht
so
so
so
dr
EP
EP
so D s
tio cu
Dr co
n
n
g
on
2D
sig
tM
sig
op Exe
d
CA
cti
te
de
en
ca
EP
C
te
ad M
d
CN
d
lig
t
de
Co nal ect
di
an
an
el
De
ns s ,
sh
al
t
al
in
ur
cla
ur
Na t P
m ncr ati
3D
ct
ct
s
rly
ite
ite
co
Ea
ch
an lla
ch
er
Ar
Ar
w
Lo
Figure 1.1 History of Spatial Coordination and the MEP Contractor
Spatial Coordination
in a BIM Environment
The adoption of BIM has also brought new challenges. The biggest
one MEP contractors face is in the area of spatial coordination. In this
arena, all industry stakeholders are confronting new business demands
and expectations, adopting new business practices, discarding or
changing old means and methods, and learning to play a new game.
The BIM models reveal what the MEP coordinator in the traditional
process cannot see: the full complexity of the building and its systems
from different perspectives in three dimensions.
The use of BIM technology makes it possible to generate virtual
models of the building and its systems.
When changes are made, the models can be regenerated quickly,
making any ripple effects evident immediately.
It is not easy to execute the processes and make the changes that
will bring the most value from these powerful tools. BIM builds on the
knowledge and skills that have made MEP contractors successful. To be
successful on BIM projects, MEP contractors need to approach spatial
coordination, and ultimately the way they do business, differently.
*McGraw Hill Construction, The Business Value of BIM in North America, 2009.
Printed with permission.
6 Achieving Spatial Coordination Through BIM
Spatial Coordination The new game has the same objective as the old game: to construct
in a BIM Environment a building on time, on budget, and up to code. But, the new game
demands players who can deal with a myriad of new people in new
roles and with what frequently seems like an overwhelming amount
of data.
1.3.2 Clear Lines of Communication
Large volumes of information must be gathered and shared. All mem-
bers of the Coordination Team, (who are called “Project Participants” in
this Guide) must communicate effectively with each other and within
their own companies, both to obtain, confirm, question, analyze, and
modify information used for the project and to recognize the needs,
actions, and consequences of their participation on the project.
Project Participants must learn to speak a common language. For
example, what “the Model” refers to is understood differently by
different people, and without realizing it, Project Participants can be
talking past each other.
1.3.3 The Technical Skills and Experience of the Project Participants
With BIM, the distinct realms of knowledge, expertise, and respon-
sibility of design engineers and MEP contractors have not changed;
engineers remain responsible for design, and contractors remain
responsible for construction-coordinated installation. However, to
participate effectively, MEP contractors need to acquire a level of
modeling skill that is equal to, or greater than, that of engineers. MEP
contractors need to create models with the accuracy and detail required
to coordinate their systems and products within allocated spaces, to lay
out and insert decks and walls for sleeves and inserts, to prefabricate
components racks and assemblies, and to provide the installation crews
with the information and references they will need to efficiently install
their systems.
1.3.4 The Social Skills of the Participants
In a BIM environment, constructive working relationships and the
interpersonal skills that build and nurture them matter more than
ever. Coordination remains a collaborative process, but the team
of contractors with field experience and technical knowledge now
includes stakeholders with different skills and levels of understanding.
Inexperienced but computer-savvy individuals can be put in charge of
large and complex projects. To accomplish assigned tasks, your Project
Team must be able to work with a broad range of personalities whose
agendas may conflict.
Achieving Spatial Coordination Through BIM 7
Spatial Coordination • Chapter 4, “The BIM Execution Plan,” on page 39, is aimed at
in a BIM Environment senior and project management and presents what you should expect
to find within a competent BIM execution plan. The chapter provides
options and suggestions for what to do when you receive an
Execution Plan that is vague, missing critical BIM information
and possibly contains well-known ”red flags.”
• Chapter 5, “Managing the Process,” on page 67, is aimed at project
managers, virtual construction managers or whoever is representing
the firm on a project Coordination Team.
• Chapter 6, “Documents of Record,” on page 85, is aimed at the
senior executives, Project Managers, or Construction Managers who
are responsible for the receivables and deliverables of a firm within
the scope of Design-Bid-Build projects with spatial coordination. The
Guide introduces all the required and many optional documents of
record that are critical to a successful project.
• Chapter 7, “Improving Your Operations,” on page 103, is aimed at
senior operational managers and Project Managers. It introduces the
secondary uses of the data that is generated throughout the building
lifecycle of projects built with BIM through a 3D spatial coordination
process.
• Chapter 8, “Contract Language,” on page 115, is aimed at senior
management responsible for the firm’s contract business. This chapter
explains issues and language within the contract documents that your
firm must identify and fully understand before engaging in any
BIM project.
• Chapter 9, “BIM Technologies for an IT Infrastructure,” on page 129,
is aimed at senior management, IT managers, or whoever is
responsible for your firm’s IT Implementation Plan. The chapter
frames a majority of the key elements needed within a capable IT
infrastructure designed to support spatial coordination and BIM.
However you choose to use the Guide, it is hoped you will come
to see that when the majority of the Project Team agrees to and
follows common coordination practices, your project is more likely
to run smoothly.
Achieving Spatial Coordination Through BIM 11
The Model
The Model The Model
(inc. MEP Models)
MEP Models
The
Model Architect’s Model
The
The Model (Design Team Model)
Model
MEP Model
The
Model Architect’s Model
“The Model”
MEP Models
No
The
Architect’s Model F/M
Model
Model
BIM AND Spatial The domain-specific tools sometimes referred to as “plug-in” soft-
Coordination BASICS ware, are installed “inside” these base platforms. Software publishers
that serve a specific domain—for example, fire protection equipment
or plumbing systems—extend these base platforms to meet the specific
requirements of their respective domains. Rather than invent or rein-
vent a base platform on which domain-specific software operates, these
publishers build functions onto these base platforms to improve and
power their own products.
2.4 Level of Development Thus, the principle: to get the benefits of a domain-specific specialty
Specifications software tool, contractors need to have the base platform, too.
** The definitions for LOD 100, 200, 300, 400, and 500 included in this Specification
represent the updated language that appears in the AIA’s most recent BIM protocol
document, G202–2013, Building Information Modeling Protocol Form. The LOD 100, 200,
300, 400 and 500 definitions are produced by the AIA and have been used by permission.
Copyright © 2013. The American Institute of Architects. All rights reserved. LOD 350 was
developed by the BIMForum working group. Copyright © 2013. The BIMForum and the
American Institute of Architects. All rights reserved
Achieving Spatial Coordination Through BIM 17
BIM AND Spatial Although there are six Levels of Development (100, 200, 300, 350,
Coordination BASICS 400, and 500), the levels most important to MEP contractors are LOD
300, LOD 350, and LOD 400. The definition of what is to be modeled at
these levels is determined at the start of the project and is often found
and referenced in the BIM Execution Plan. Project Participants need to
agree on both the modeling expectations and what the Owner is looking
for as a final BIM deliverable, if required.
Elements that are modeled in a LOD 300 model—such as a 4"
conduit, a wall-mounted plumbing carrier, or a 14x24 rectangular duct—
are modeled as specific elements or composite assemblies at a specific
location and represent an accurate shape and orientation (for example,
thickness) of the specified assembly. For a Design-Bid-Build contrac-
tor, this is a good place to start your detailing activities. Non-geometric
information such as standard ratings and special specifications may also
be attached. A solid model element with accurate thickness and location
that also contains the information usually included in any of these types
of elements satisfies the requirements of LOD 300.
The official description of what the Design Team is expected to
deliver in its Design-Intent Model at LOD 300, is defined as follows:
The model element is graphically represented within the Model as a
specific system, object, or assembly in terms of quantity, size, shape,
location, and orientation. Non-graphical information may also be
attached to the Model Element.*
There is, however, no uniform deliverable product that design firms
are contracted to provide in a Design-Intent Model. What this means in
practical terms is that the information you need to begin your detailing
and coordination work may or may not be delivered in the Design-Intent
Model. There is no guarantee that the design model passed to you
contains accurate, constructible, and coordinated LOD 300 elements.
Therefore, you should rely more on what the Execution Plan and
contract documents define as the set of domain-specific LOD elements
that you should expect to receive. If you cannot find any references to
these details, submit an RFI for clarification.
But regardless of whether the Design-Intent Model provides fully
compliant LOD 300 elements, your task is to use what you can while
working within it and avoid any redesign of it. So part of your BIM
Execution Plan will define the elements that you are contractually
obliged to model if you are to deliver a set of elements at LOD 350
to begin coordination. When coordination is complete, you have the
BIM AND Spatial option to generate elements at LOD 400 within your construction
Coordination BASICS model, which can in turn, be utilized for component or assembly
manufacture, fabrication, and installation.
The official definition of LOD 350 includes all of LOD 300 and adds
some new information (emphasis added):
The model element is graphically represented within the Model as a
specific system, object, or assembly in terms of quantity, size, shape,
location and orientation, and interfaces with other building systems.
Non-graphical information may also be attached to the Model Element.*
The Coordination Team and Project Coordination Manager can expect
that the LOD 350 model elements you have submitted to the first
coordination meeting are ready to be federated into the coordination
model. Your model must include enough detail for installation and
cross-trade coordination.
The official definition of a LOD 400 model includes more detail than
an LOD 350 model (emphasis added):
The model element is graphically represented within the Model as a
specific system, object, or assembly in terms of quantity, size, shape,
location, and orientation with detailing, fabrication, assembly, and
installation information. Non-graphical information may also be
attached to the Model Element.*
For MEP contractors, this model is equivalent to what are often
considered as industry-standard shop drawings. You can use it as a
construction submittal, declaring that it has completed the coordination
process. You are ready to begin manufacturing, fabrication, and
installation, upon sign-off and authorization.
A
• 3.4 Internal Inventory of Skills on page 25
s a senior executive of an MEP
• 3.5 Internal Communication Procedures on page 28
contractor, the responsibility for
building a BIM spatial coordination • 3.6 Human Resource Requirements on page 32
program falls to you. The BIM • 3.7. Outsourcing on page 33
Implementation Plan is the foundation. • 3.8 Working Within the Collaborative Process on page 37
This plan identifies the skills, processes,
and technologies you need to have to 3.1. Building an Effective Spatial Coordination Program
do the work successfully and a schedule Do not wait until you have been awarded a BIM and 3D modeling
for filling the gaps between what spatial coordination project to establish within your company the
you have and what you need. This capabilities that you will need to perform the job accurately and
chapter focuses on the considerations effectively. Spatial coordination with 3D modeling is a valued capabil-
for evaluating the skills and processes of ity of many MEP contracting firms and should be instrumental to your
your current operations. The technology estimating and negotiating process for any project. When you find a
requirement for spatial coordination, 3D modeling, or BIM in a Request
issues are addressed in Chapter 9 on
for Proposal (RFP), you want to be prepared to add to the proposal a
page 129. description of your company’s unique capabilities to complete the job
and fulfill the BIM special requirements of the project.
It is important to carefully review the spatial coordination or BIM
requirements before your firm bids on any project. Your estimators
should evaluate the costs of meeting the specification requirements,
your operational personnel should review coordination and related
construction schedules, your detailing or modeling manager should
3.1. Building an Effective identify the special requirements and procedures related to this custom
Spatial Coordination Pro- project, and your executives should analyze the contract terms and
gram associated risk that might apply.
Do you have the trained personnel available to do this? Unfortunately,
most contractors discover that they do not only after they have won
the bid. They assume that the project requires a high-level detailing
process, only to find that the BIM requirements demand much more
time, resources, and expense than anyone had anticipated.
Once burned, smart MEP contractors are quick to adjust to the needs
and demands of their clients and the industry in general. It takes a
concerted effort to understand all the dynamic aspects of spatial
coordination and Building Information Modeling and to recognize how
Owners, General Contractors and Construction Managers, Architects,
and design professionals are positioned to address technology’s new
influence in the construction process.
20 Achieving Spatial Coordination Through BIM
3.2. Preparing Your BIM 3.2. Preparing Your BIM Implementation Plan
Implementation Plan Projects vary in size, composition, and complexity, but your processes,
protocols, and metrics should not. If you were to bid on a project that
requires BIM coordination, do you know which aspects of your busi-
ness can function as they do now? Or which departments or processes
must transform to meet the new demands and expectations? Have your
project teams identified and staffed all the functional areas required for
a BIM project?
If you cannot answer these questions in the affirmative or you simply
do not know, you need to begin work on a BIM Implementation Plan.
A BIM Implementation Plan is a business strategy document that
outlines the resources your company needs to buy and to hire and
identifies the changes to current internal processes that are required
to fully support BIM projects. The first step in preparing this plan is to
inventory the skills and equipment your firm currently has and analyze
how your business data flows within the firm. The second step is to
identify any gaps between what you have and what you need to meet
the demands of current and future BIM projects. The third step is to
prepare a schedule for your organization to evaluate, select, and
incorporate the technologies you will need to adopt.
There are no standard templates for developing this plan; each one
is unique. Because the BIM technologies can transform your company’s
processes, an executive with a broad view of all aspects of the
company’s capabilities and goals should oversee the work. That
executive, in turn, needs to find the champions—the seasoned and
Achieving Spatial Coordination Through BIM 21
BUILDING THE TEAM respected individuals within your company who have the patience
and persistence to keep your plan on task and still meet any immediate
commitments or obligations for your firm.
These plans should describe the existing internal processes for plan-
ning and executing spatial coordination, including communication, data
exchange, and how the information gleaned from the process is applied.
The plan describes how you want these processes to change to meet
new or desired expectations. The plan also makes note of future
opportunities and of any data collection and reuse that might
enhance your business practices. This plan should be prepared with
the expectation that it will be revisited and evolve as the company’s
skills grow and to accommodate new technologies and tools.
If you are new to BIM and do not feel you have a good understand-
ing of what the industry is demanding in your specific area of business,
consider setting up formal discussions with your clients, your peers, your
vendors and your technology providers. What you learn will help you
see where your gaps are, and at the very least, what you need to meet
your immediate needs.
The sections that follow include guidelines that you may want to use
as starting points for various aspects of your Implementation Plan. They
3.3 Roles and Responsibilities focus on the skills and processes that the Implementation Plan must
on the Coordination Team address. The technology issues that the plan must address are covered
in Chapter 9, on page 129.
BUILDING THE TEAM The three critical roles on the Coordination Team are the Project
Coordination Manager, the Model Manager, and the Lead MEP
Subcontractor. On some projects, one person performs more than
one of these roles; on others, the roles are assigned to individuals
employed by different firms. Their basic responsibilities do not change,
but their responsibilities within the current project must be defined and
understood. Their titles well may be different from those used here.
There is also an authorized representative from each of the trades
participating in coordination.
As the needs and expectations of spatial coordination have expanded,
many stakeholders have looked to their MEP contractors to lead or
manage some or all of their coordination efforts. MEP contractors
are often asked to assemble initial drafts of BIM Execution Plans
(see chapter 4 on page 103).
BUILDING THE TEAM The following sections describe the responsibilities of the basic roles
on a Coordination Team.
3.3.1 Project Coordination Manager
The Project Coordination Manager (PCM) is generally responsible
for the oversight and management of the spatial coordination process;
another name for the role is MEP Coordinator. The General Contractor
or Construction Manager generally assumes this role.
The Project Coordination Manager has these responsibilities:
• Managing the Coordination Team to ensure full participation and
adherence to the BIM Execution Plan
• Creating coordination schedules that are based on the project
schedule and agreed to by Project Participants; managing these
schedules to keep them up to date and reconciled
• Obtaining and distributing all contract drawings and documents,
design change drawings and documents, and all CAD and model
files that the Coordination Team needs to create initial models
• Ensuring that all documents, drawings, files, and information from
the design team are current
• Acting as liaison between the Coordination Team and the Architect,
engineers, and Owner.
• Notifying appropriate parties and obtaining resolution from the
Design Team when spatial coordination issues prevent the
Coordination Team from achieving satisfactory coordination in
accordance with the Design-Intent Model or with contract
documents and drawings
• Acting as an arbitrator when members of the Coordination Team
cannot agree to a mutually satisfactory solution to coordination
issues.
3.3.2 Model Manager
The Model Manager is responsible for facilitating coordination meet-
ings and managing the Model. This position may be specified in the BIM
Execution Plan as a unique position; the responsibilities might also be
incorporated into the roles of the Project Coordination Manager or Lead
MEP Contractor. Either way, it is a critical role that must be defined.
It can be filled by the Project Coordination Manager, the General
Contractor or Construction Manager, the Lead MEP subcontractor, the
Architect or Engineer, or an independent BIM specialty subcontractor.
The Model Manager is responsible for these tasks:
• Setting up and maintaining a secure online file-sharing site
• Assembling the initial master model
24 Achieving Spatial Coordination Through BIM
BUILDING THE TEAM • Setting up the initial file structure of the model folders (also known
as model directories) and establishing conventions for naming
project files
• Establishing elevations and the point of origin (or insertion point)
for all models
• Communicating information to the Coordination Team
• Confirming that the model files of all Project Participants align
properly and can be inserted properly into the master model file
• Resolving any model alignment or coordination issues with all
Project Participants
• Maintaining the model throughout the project
• Performing interference/clash-detection checks
• Generating clash detection reports
• Facilitating coordination meetings
It is a best practice for individual firms to generate their own
clash-detection reports and resolve as many conflicts as possible prior
to the coordination meetings. Coordination meetings should focus
on major interferences or design restrictions, not minor, easily resolved
interferences. If attempts to resolve clashes end in stalemate, the
Project Coordination Manager should intercede.
3.3.3 Lead MEP Subcontractor
The responsibilities of the Lead MEP Subcontractor vary across
projects, and the role might not be specified in the contract documents
or the BIM Execution Plan. On some projects, the responsibilities of
the Model Manager are assigned to this role. On others, the Lead MEP
Subcontractor may coordinate the work of other MEP contractors on the
team, modeling the major systems within the Lead MEP Subcontractor’s
scope first and providing that model to other Project Participants, who
then model their own systems.
Any responsibilities assigned to this role must be clearly defined in the
project’s contract documents or BIM Execution Plan. When sequential
modeling is specified, the systems with the greatest coordination
impacts such as sloped piping and large duct work mains are modeled
first; that model, preferably federated with the architectural and
structural system models, is then provided as a “background” for the
modeling of smaller, less bulky systems such as domestic water,
electrical, and fire protection. Alternatively, the BIM Execution Plan
might designate the Lead MEP Subcontractor as the Model Manager,
MEP Coordinator, or MEP Spatial Coordinator.
Achieving Spatial Coordination Through BIM 25
BUILDING THE TEAM Because these roles can be filled by a number of different individuals
in different organizations, it is important that the Coordination Team
sort out the details and agree to their responsibilities. It is highly
recommended that you address these expectations during the bidding
and procurement process because they have an impact on your
financial commitment.
3.3.4 MEP Subcontractor
Each MEP contractor on the Coordination Team must have these
responsibilities and authority:
• Collaborating with the Coordination Team about the requirements
and guidelines of the Execution Plan and all applicable contract
documents
• Modeling prescribed components at full scale, using the required
units insertion points and project orientation, at required elevations,
free from interferences with structure and their own components
• Capable of and authorized to make decisions regarding the placement
and coordination of their components
3.4 Internal Inventory of 3.4 Internal Inventory of Skills
Skills
The inventory of current skills can begin by constructing two
organization charts, one that represents your current staffing and
another designed to support the requirements or goals of your spatial
coordination program. Then compare the charts. The differences should
dictate what to include in your BIM Implementation Plan.
If your company is small to mid-sized, you may only need to assign a
single individual the responsibility of upgrading the firm’s CAD detailing
department to support the required receivables and deliverables. If
your company is large, you might include a thorough review of every
department and how each could be improved to better support the
cooperation and collaboration needed throughout the entire
organization.
The requirements for successful spatial coordination are far more
comprehensive and time-consuming than old-school detailing ever
was. The skills inventory, especially for large contractors, should also
consider when a shift to segmentation of steps or tasks may be pru-
dent or necessary. The practice of assigning one individual to perform
all tasks related to a specific project may need to change; assigning an
individual to similar parts of many tasks is an alternative. This strategy
requires stricter standardization processes, but permits a more focused
use of any individual detailer’s or coordinator’s time and skill and allows
for a more concentrated attention and improved efficiencies to each
individual component.
26 Achieving Spatial Coordination Through BIM
BUILDING THE TEAM To begin your inventory, consider the roles and responsibilities of
an internal team that meets the common requirements for spatial
coordination with 3D modeling.
3.4.1 BIM Manager
Most successful BIM Managers come from within the company and
have a track record of successful construction management in one
form or another. Additional training may be necessary, but having
someone who has demonstrated a strong understanding of construction
management is probably more important than someone with
established CAD skills.
When looking outside the firm, a more likely prospect is a successful
lead detailer or MEP coordinator. These skills and personal attributes
are essential:
• Strong field experience, preferably in layout
• Trade knowledgeable
• Self-motivated, ambitious, hardworking, intelligent
• Computer literate
• Excellent social and communication skills
The BIM Manager typically reports directly to senior management
and has these responsibilities:
• Managing the BIM process
• Supervising coordinators and detailers
• Working internally with estimators, project management, field per-
sonnel, fabrication facilities and externally with Architects, Engineers,
General Contractors, Construction Managers, other trade contractors,
and Owners
• Establishing schedules and budgets
• Monitoring the process to measure compliance with quality
requirements and any other internal metrics established and
defined by the organization
• Filtering clashes and evaluating clash reports prior to coordination
meetings
3.4.2 Lead Detailers or Project Coordinators
Lead detailers require a strong knowledge of construction techniques
and methods; they are often a tradesperson with long experience in
laying out mechanical, electrical, or plumbing systems. Some good lead
detailers also come from drafters and detailers with several years’
experience. These candidates usually rise to the top as their abilities
Achieving Spatial Coordination Through BIM 27
BUILDING THE TEAM and skills develop. If not familiar with your company’s existing CAD
platforms, the best candidate may also require specialized CAD training.
Also of great value is someone who has taken the lead role on multi-
ple projects. These are people who can make or break a project, so their
ability and willingness to accept a great deal of responsibility is essential.
A Lead Detailer or Project Coordinator has these responsibilities:
• Working with the Project Team
• Attending coordination meetings
• Coordinating the efforts of individual detailers assigned to the project
• Reviewing the status of these items with the Project Manager:
o Schedule
o Deliverables
o Submittals
o RFIs
o Design changes
o Cost impacts
3.4.3 Detailers
Many detailers, and indeed some of the most competent ones, come
directly from the field. What they bring is a thorough understanding
of the materials, equipment, and how systems and elements are
connected and installed. Many capable organizations offer afternoon
or early evening classes to their field personnel who are interested in
making the switch.
Competent detailing candidates have also come from architectural
or engineering firms. Entry-level candidates should have a two-year
associate’s degree or equivalent in CAD or BIM technology. Some
construction management programs are offering minors in BIM
technology and almost all are addressing BIM technology in one
form or another. Your local MCAA, SMACNA, or NECA chapter of
affiliate can often guide you to qualified candidates.
Detailers, also known as drafters, have these responsibilities:
• Detailing sections of the model
• Incorporating Design-Intent Models, contract documents and
specifications, and the Project Team’s requests and expectations
into a virtual detailing model that represents the intended MEP
installation for the building
• Understanding and interpreting architectural and structural details
as they affect the MEP installations
28 Achieving Spatial Coordination Through BIM
BUILDING THE TEAM • Identifying interferences with the architectural structural and other
MEP elements
• Generating contract and internal company deliverables from the
model. These deliverables include tagging, dimensioning, and
generating fabrication spools and tickets.
In some companies, the senior detailers do the modeling and the
junior detailers perform the tasks related to extracting deliverables
from the model.
3.4.4 Technical/CAD Manager
This candidate requires a strong CAD and BIM background.
One other consideration, especially with a large department, is
the option to establish a position for a technical manager or technical
lead who works directly for the BIM Manager and takes on the
3.5 Internal Communica- full responsibility for these areas of the model:
tion Procedures • Implementation
• Management
• Troubleshooting
• Training others on the authoring software and related technologies
BUILDING THE TEAM Qualifying design firms and setting project expectations
To screen a potential outsourcing firm, start with the list of questions
here to develop your own list.
1. Do you provide coordination drawings only? __________________
_______________________________________________________
2. Do you attend coordination meetings and who represents your
firm’s interests in the process?______________________________
_______________________________________________________
3. Does your firm require installation drawings, including deck, pad,
insert and sleeve drawings? ________________________________
_______________________________________________________
4. Will the design firm generate material lists with a specific material
scheme for sorting, bagging, and tagging material?_____________
_______________________________________________________
5. To what degree will prefabrication and 2D modeling be taken up
in the process? Will deliverables include equipment, module, and
spool drawings?_________________________________________
_______________________________________________________
6. Will there be a deliverable to support and drive Total Station
surveying equipment?____________________________________
_______________________________________________________
7. Does the design firm use the type of modeling software compatible
with the project specs?____________________________________
_______________________________________________________
8. Who manages the submittal process and will the design firm
produce the “as-builts”?___________________________________
_______________________________________________________
9. What previous spatial coordination projects has the design firm
completed?_____________________________________________
_______________________________________________________
10. Are the design firm’s insurance and bonding capabilities adequate
for the project or does the MEP contractor provide it?___________
_______________________________________________________
36 Achieving Spatial Coordination Through BIM
BUILDING THE TEAM Some firms can meet your needs on small projects, but would be
overwhelmed by large ones. Recognize that in most cases you are
actually contracting with individuals, not firms, and these individuals
must meet the requirements and qualifications that you have for your
own employees.
Once you have chosen a firm or an individual, assign a small or simple
project, or have them supplement your team’s efforts on a current
project so that your personnel can evaluate the work. Your staff needs
to understand the work being delegated to subcontractors or consul-
tants and to convey expectations for performing it. Putting all of this in
writing, with schedules and standards, is important, particularly when
some of the information needed is not available when the consultant
joins the project. Accountability is important, and vigilance is key.
Establishing a relationship with multiple outsourcing firms is also
something to consider. As with any other subcontractor, the more
familiar you are with each other—your respective capabilities, strengths,
and weaknesses—the more flexibility you have with developing the right
approach for a particular job. By developing a strong relationship, your
outsource firm can become nearly as integrated with your BIM struc-
ture as an in-house department. Having multiple options also allows for
competitive balance in pricing. Oftentimes the smaller outsourcing con-
tractors have a limited amount of work that they can take on at a given
time. You do not want to have all of your eggs in one basket, only to find
you have a major project and your outsourcing contractor is unavailable.
If you are an electrical contractor, keep in mind your unique
circumstances if you are considering outsourcing 3D modeling and
coordination work. The limitations of the typical electrical Design-Intent
Model are often schematic; they do not show the connections between
the primary electrical systems and other electrical elements that require
power. Unlike the other trades, an electrical contractor must both model
and provide a level of “pre-design.” When this type of work is out-
sourced, you are potentially at the mercy of how the firm or individual
you’ve hired approaches pre-design as part of the 3D modeling and
coordination process. Before this contractor begins work, you should
gather information from the field to prepare a set of directives for the
contractor to follow and for your team to use when reviewing the
contractor’s work.
Achieving Spatial Coordination Through BIM 37
4.1 The Contents of a BIM 4.1 The Contents of a BIM Execution Plan
Execution Plan
The contents of any Execution Plan reflect the size, complexity,
and schedule of the project and the contractual responsibilities,
deliverables, and competence of the participating individuals and firms.
For any coordination process, a comprehensive BIM Execution Plan
should, at a minimum, cover the following issues:
• Overview of the Process on page 40
• Team goals and Objectives on page 40
• The Organizational Structure of the Coordination Process on page 40
• Project Meetings on page 41
• Document Management and Maintenance on page 44
• Collocation on page 45
40 Achieving Spatial Coordination Through BIM
BIM Execution Plans Each Execution Plan must assign basic leadership roles to specific
individuals and clearly describe their responsibilities and authority.
These roles, although they may have different titles, are presented in
section 3.3, “Roles and Responsibilities on the Coordination Team” on
page 21.
• The Project Coordination Manager
• The Project Model Manager
• The Lead MEP Coordinator
• The individual domain-specific and MEP Project Team leaders
or managers
Note that these roles and any others included in the Execution Plan
can be filled by one or more individuals, or several roles can be assigned
to one person. Regarding these role assignments, it is important to
understand the following:
• All the responsibilities assigned to the role
• Whether all important responsibilities have or have not been
addressed
• Whether the individuals assigned to roles have the experience
and credentials to perform them successfully
4.1.4 Project Meetings
The BIM Execution Plan should provide basic information about
project meetings:
• Which meetings are required
• When and where these meetings will be held
• Who is expected to attend
Some of these meetings are held only once; others are held
throughout the coordination process. Video conferencing software and
web-based meeting applications make it possible to hold some of these
meetings in cyberspace. This might become the standard practice or just
an option to accommodate weather, travel schedules, or emergencies.
1. Kick-Off Meetings
A comprehensive kick-off meeting held before the Coordination
Team begins work is an extremely good idea. To prepare for such a
meeting, many best-in-class Construction Managers meet with the
major contractors to preview their approach and obtain input on
many of the subjects that will be addressed.
For most projects, each MEP contractor sends many representa-
tives to the kick-off meeting. Successful projects invite representatives
from the Owner, the Architect, and the Design Team. When the project
42 Achieving Spatial Coordination Through BIM
BIM Execution Plans is large, complex, or of long duration, a collaboration facilitator often
attends or leads the meeting. The BIM Implementation Plan should
designate who attends this meeting, but at the minimum, your Project
Manager and BIM/Spatial Coordination Manager should attend.
The agenda for this meeting should be provided in advance, giving
each participant adequate time to review it and prepare.
Kick-off meetings often set the tone for collaboration and coopera-
tion, and it is hard to get a second chance to make a first impression and
establish credibility. You company should be represented by experienced
individuals who know the business, understand the expected processes,
and can and will communicate concerns and issues effectively.
First impressions go both ways, and what you observe or learn in the
kick-off meeting may raise concerns about the experience, competence,
flexibility, or practicality of Project Participants or those in leadership
roles, and other red flags. If you or your representatives recognize
challenges ahead that were not addressed, you want to communicate
your concerns to all the appropriate parties.
Document any critical details from these meetings that are included in
the agenda or the hand-outs. Also, review the official minutes to ensure
that any important verbal clarifications or instructions provided during
the meeting are appropriately documented.
If a spatial planning meeting has not been included in either the
Execution Plan or the agenda for the kick-off meeting, the kick-off
meeting is the forum in which to request one.
BIM Execution Plans This meeting is rarely included in a BIM Execution Plan; however, this
exercise can unquestionably expedite the coordination process and is a
proven best practice. If not mentioned during the kick-off meeting, your
firm’s representatives should vigorously request one.
3. Coordination Meetings
Spatial coordination is a meeting-intensive process, and the
coordination meetings are where the bulk of the work is done. Chapter
5, “Managing the Process” on page 67, covers much of this work and
what needs to be in place for the Coordination Team to be successful.
The BIM Execution Plan should provide this information:
• The project schedule
• A list of attendees
• The time and location for the meetings
Your BIM Implementation Plan should indicate the roles and respon-
sibilities of your personnel who attend these meetings. Your project
management staff and your team’s coordination leader should attend
these meetings. If your Project Managers cannot attend every meeting,
they should attend the first few as the project moves forward in order
to understand the tone and context of how these meetings will run
throughout the construction phase.
The trade-offs of physical versus virtual attendance are probably most
important for coordination meetings. The early meetings may benefit
from mandating physical attendance; once the Coordination Team has
learned to work together effectively, virtual attendance can be just as
effective and less burdensome.
BIM Execution Plans Any confusion over what constitutes “normal and expected
coordination” and what constitutes “design or redesign” can contrib-
ute to tension between the Coordination Team and the Design Team.
Meeting with the Design Team early to discuss this subject contributes
to good relations. Push to include a definition of “coordination means
and methods” in your job scope and use it to determine when a change
to the Design-Intent Model constitutes redesign or a design change that
justifies the additional cost of change orders.
Make the Design Team aware of the coordination schedule and
encourage them to make themselves available via online conferencing
should the need arise.
Before coordination is complete, many MEP contractors have found
it useful to offer the principal MEP Design Engineers a thorough
fly-through of the MEP models (Figure 4.1 on page 44). This review
provides these professionals with an understanding of the effort that
has gone into the coordination process and serves to circumvent
unnecessary punch lists or installation questions or critiques.
5. Sign-Off Meetings
Many, if not most, BIM Execution Plans establish sign-off protocols for
the project. Most projects require interim partitioned area sign-offs
of both models and drawings. After these models and drawings are
approved, they should be “locked and archived within the Document
Control system for the project. (For more details, see Chapter 5,
“Managing the Process” on page 67)
4.1.5 Document Management and Maintenance
Most projects today use two separate document control systems; one
stores BIM-related modeling and drawing data, and the other manages
Achieving Spatial Coordination Through BIM 45
BIM Execution Plans other types of documents, such as submittals and RFIs. What informa-
tion is stored in which system varies from project to project.
When working with coordination documents, every Project
Participant needs to be working from the same set of common BIM-
related documents, receive changes made to these documents as soon
as the changes are available, and incorporate the changes into their
own work.
The Project Coordination Manager has several responsibilities in
this area:
• Fulfill any contractual obligations for Documents of Record, as
described in Chapter 6 on page 85.
• Promptly post or otherwise distribute all data pertinent to the goals
of the BIM Execution Plan
• Provide notice and access to all updated documents and records to
all participants
• Maintain complete, accurate, and current files and records of all
version updates, data exchanges, issues and RFI logs, instructions,
and communications and make this information available to all
participants, as needed
• Maintain complete, accurate, and current files and records of all
information provided during the process by all Project Participants
• Provide methodologies for all Participants to copy any Documents of
Record needed to satisfy any company-specific or legal requirement
that may be contained in these files and records
Regarding document management and maintenance, the BIM
Execution Plan should clearly define these items:
• Who will actively manage and maintain all common files and records
• Where these files and records reside (FTP sites or other repositories)
• All access and security protocols
4.1.6 Collocation
Some BIM Execution Plans require that the members of the
Coordination Team, along with personnel of the other major trade
contractors, collocate in a common facility (often referred to as a “BIM
cave”), usually at the construction site. The goal of collocation is to
foster collaboration, promote direct communication, and accelerate the
recognition and resolution of coordination issues.
MEP contractors rarely make the decision to collocate. They do so
because it is usually imposed under the terms of the RFP or contract.
Depending on the contract requirements, collocation can extend to
every member of the Coordination Team involved with the project, to
46 Achieving Spatial Coordination Through BIM
BIM Execution Plans some key members of the team only, or to a scheduled blending of both
scenarios. The length of this arrangement is often left vague, defined as
“until the coordination process is complete.”
Collocating your personnel can have a significant impact on your firm
and its resources. The impact may be positive or negative, but it does
need to be carefully studied before bidding the project and clarified as
needed within the BIM Execution Plan. Limitations or restrictions that
fall outside your normal business practices may be required.
New contracting types such as Integrated Project Delivery (IPD) are
becoming popular. Most of these project delivery processes have clear
expectations that certain key personnel are housed together to achieve
their project goals (Figure 4.2 on page 46).
BIM Execution Plans Also, your collocated staff members may find themselves operating
in a gray zone. Construction Managers may go directly to detailers
with tasks, directions, or critiques that purposely or unintentionally
circumvent your established chain of command. Who will supervise
your collocated personnel?
Collocation also affects your personnel. Can the people who are
not working on the project contact their colleagues with questions on
other projects or for informal mentoring and guidance? Will you need
to supplement your staff to fill the gaps? If so, how will the need to do
more supervision affect the productivity of your remaining staff?
Also, special effort may be needed to provide adequate support to
your collocated staff. For example, detailers can become isolated and
removed from the resources and mentoring they get from working with
the rest of your staff.
When you choose the personnel to send to the BIM cave, you need
to consider the skills and personal attributes that will contribute to the
success of the project.
• Can the individual adapt to a new organizational structure, work
under new supervision, and maintain a proper chain of command
both within the project and your company?
• Does the individual have the discipline to document their work,
maintain adequate daily logs, and resist the distractions and the
constant demands on their time that they may not be accustomed
to in your firm’s environment?
• Can the individual stay within the scope of the coordination process?
Can the individual avoid two common areas of mission creep, namely,
providing design-related solutions without the EOR’s approval and
providing more detail and development than required?
The cost of collocation can be determined more by time spent on site
than the scope of your firm’s contract. Your estimate may have to be
based on the duration of collocation and required staffing rather than
the multipliers you usually use to estimate project coordination. How
will cost tracking and budget objectives be monitored and measured?
Will the Engineers of Record also be collocated? Will they oversee all
design and model developments, and author and sign off on all
coordinated drawings and models?
The size, layout, and technical infrastructure at the collocation site
are factors that impact an effective working environment. Although the
collocation site is temporary, it needs to provide your personnel with
the resources that support the level of productivity that is available in
your office.
48 Achieving Spatial Coordination Through BIM
BIM Execution Plans The site must provide each Project Participant a cool, comfortable,
well-lit, and well-equipped individual workspace; it must also provide a
separate space where the team meets for the clash-detection process.
Avoid cramming people into one conference room or a spare office that
is also used for team meetings.
As for the equipment required, keep in mind that detailers often need
two large monitors for their design software and storage space for con-
struction documents and other records. For clash-detection meetings,
consideration should be given to the type of projector that the budget
and the space can accommodate. A large wall-mounted monitor is rec-
ommended; a high-lumen projector (5,000+ lumens) is another option.
Other equipment includes the infrastructure for remote access, printers,
scanners, and other devices and networks that require shared access.
The management of the file-sharing server deserves attention. This
includes equipment and policies, which are described more fully in
Chapter 9, “BIM Technologies for an IT Infrastructure” on page 129.
These are the basic issues:
1. How it is to be managed?
2. Who is responsible for ensuring that seamless, shared, and easy
access to digital documents is available 24x7 throughout the process?
3. How will the Coordination Team interact with the Design Team?
4. Will proper Documents of Record be kept?
5. Will you have remote access to the Documents of Record?
6. Will your company have copies of all final documents, including
drawing and model revisions?
4.1.7 Receivables
Every BIM Execution Plan must start somewhere. Within the context
of this Guide, the Execution Plan and the spatial coordination process
that follows must begin with the information and documents that
Project Participants receive before they begin work on the Coordination
Team.
Most Execution Plans include a list of receivables that the Design
Team provides to the Coordination Team. This information almost
always includes these items:
• A list of drawings and their version dates
• Comprehensive specifications
• Sections of any Requests for Proposal
• Applicable references
• Copies of or links to appropriate Design-Intent Models
Achieving Spatial Coordination Through BIM 49
BIM Execution Plans On a Design-Bid-Build project, any receivables from the Design Team
that do not achieve the Level of Development that the Coordination
Team expects should be clearly identified at the kick-off meeting so
that appropriate schedule adjustments or scope-of-work issues are
addressed. When Design Teams recognize that their Design-Intent
Models may not satisfy the specified Level of Development or Level of
Detail and fail to notify anyone of this condition early, the Coordination
Team finds itself dragged into the coordination process under far more
difficult circumstances.
4.1.8 Deliverables
Good BIM Execution Plans list or describe the deliverables expected
from the Coordination Team and the format (or software platform) in
which to produce them. These deliverables include the items described
in the project specifications as deliverables to the Owner at the end of
the process, and all documents, drawings, and models required dur-
ing the procurement, prefabrication, construction, and commissioning
phases of the project.
The Level of Development specified for domain-specific Deliverables
and Receivables, which defines what you can expect to receive and then
deliver in a LOD 350 and LOD 400 construction drawing, is an impor-
tant component of a BIM Execution Plan. For example, an Owner might
expect that the LOD 400 construction model delivered as a contract sub-
mittal includes ½" conduit, but electrical industry standards may exclude
the modeling of conduits smaller than 2". Such a disconnection from the
parties who are paying the bills can be a very unpleasant experience.
Another challenge arises when Construction Managers or outside
authorities demand models or annotated drawings from the models
that may never have been clearly described in any documents. Such
demands introduce confusion, delay, and questions of responsibility
into the process. All such deliverables should be clearly delineated in
the BIM Execution Plan.
Each contractor may also have deliverables that, although not shared
with the other participants, are needed for internal purposes, such as
procurement, prefabrication, materials control, task management, and
labor tracking. Some of this information will be derived from your firm’s
input into the coordinated model, and some of it will be derived from
the input of other firms that contribute to this model. When reviewing
a BIM Execution Plan, your staff should also be aware of these
deliverables, particularly their scheduling requirements, and be
willing to communicate your needs to the other members of the
Coordination Team.
50 Achieving Spatial Coordination Through BIM
BIM Execution Plans havoc later on if the Coordination Team encounters them after its own
process is underway. Discussing these situations in detail during a spatial
planning meeting can prove worthwhile and informative to everyone.
Having an established order of precedence should not be construed
by any contractor as a right to claim space or exercise unilateral author-
ity over the other Project Participants. It doesn’t take a lot of experience
to understand that common sense enhanced by technical knowledge
offers the best approach to evaluating and resolving conflicts without
imposing unreasonable costs or impacts on system performance.
Well-thought-out BIM Execution Plans may include several orders of
precedence, each tailored to the requirements of different areas in the
building. For example, installation sequence in a mechanical or electrical
room is significantly different from that in an office or garage space.
Another consideration in determining order of precedence is
the quantity and spatial usage of any particular trade that supplies
material and equipment to a particular type of building. As illustrated
in the LOD 350 model detailed by an electrical contractor in Figure 4.3
on page 51, it makes perfect sense that the first contractor or prece-
dence is the electrical contractor because the most significant amount
of material and equipment is the electrical system. In Figure 4.4 on page
52, the most significant amount of material and equipment comes
from the mechanical contractor, who should expect that similar
consideration to the proper order of precedence be given to the
sheet metal contractor.
BIM Execution Plans Every software application creates files in a proprietary format that
is described by the three-letter extension at the end of the file name.
Generally, these files cannot be opened, viewed, or edited by other soft-
ware applications unless the software publisher has released, licensed,
or otherwise enabled the creation of data file viewers or converters.
This is an obvious problem for a business process that requires people
to share electronic information. To address it, the publishers of most
spatial coordination applications have negotiated with software manu-
facturers of BIM and 3D/CAD applications to incorporate technology
that allows the spatial coordination applications to open files created
in dozens of different proprietary software file formats and to view and
possibly edit the data from those files once imported.
Be aware that this data-exchange “highway” is usually a narrow one-
way street. The data imported into the spatial coordination application is
a subset of the data in the original source file (typically, little more than
the geometry), and it is rarely possible to export files from the spatial
coordination applications back into their native file formats.
Nevertheless, the ability to import geometry from multiple propri-
etary file formats into the spatial coordination application is usually
sufficient to allow the Coordination Team to collaborate, while allowing
individual members to use the modeling application that they prefer.
That said, the greater degree of compatibility among file formats on
a specific project, the more easily information can be shared, and the
richer the shared data set can be.
Another data-format compatibility option can be found in pub-
licly available, open data standards, such as the IFC file format of the
buildingSMART Alliance. Open data standards provide a neutral data
exchange format between proprietary software applications. Software
applications that support open data file standards typically allow users
to import and export files in the open-standard format. In practice, this
does not always work. It all depends upon whether the software
applications support the open-standard file formats are compatible.
It is imperative that each Project Participant identify their native file
format to the Model Manager, and cooperate in any testing that may be
needed to confirm that their data files can be imported correctly into
the spatial coordination application.
Some project specifications may be less flexible, requiring Project
Participants to submit files in a specified format. If a proprietary file
format is specified in the contract documents, be sure to resolve this
issue during the bidding phase. Ignoring or dismissing this requirement
can be a costly mistake (see Chapter 8, “Evaluating Spatial Coordination
Contract Language” on page 115).
Achieving Spatial Coordination Through BIM 55
The file that includes this information can be named this way:
UNHP_A1_L0_ELEC_AEC_2012-07-24_v1
When Model Manager truncates this file name to remove the date and
the version number before updating the model, the file name is short-
ened to this:
UNHP_A1_L0_ELEC_AEC
The file name for the same submission date and version is this:
UNHP_A2_L5_HVAC_MCI_2012-07-24_v1
Achieving Spatial Coordination Through BIM 57
BIM Execution Plans As you can see from this example, a file-naming convention that is
used consistently makes it possible for any team member to scan a list
of files and identify the content and author without having to open a
single file. An important element of a file-naming convention is that the
number of characters (letters or numbers) in each part of the file name
be consistent for all files. The example above uses four characters for
the project name, two for the building area, two for the level, four for
the trade or discipline, and three for the authoring company.
When this convention is followed, scripts can be run on large data sets
of files, which is an extremely useful information management tool.
BIM Execution Plans on a project. Because two people can’t work in the same file
simultaneously, you may need to partition the model based on the
division of labor. A plumbing contractor could partition by splitting the
medium-pressure duct from the low-pressure duct plumbing from piping
systems, and even go as far to separate drainage systems from pressure
plumbing. The trick is to keep the file size manageable, say less than
15 MB, while ensuring that the detailers who work in them can do so
whenever they need to.
4.2.5 Drawing Sectioning and Key Plans
All construction projects need Drawing Sectioning and Key Plans. The
Design Team usually provides these plans, which carry over, in some
fashion, to the 2D deliverables from the coordination process. If there is
a benefit to modifying the numbering, sectioning, or points of reference
from the construction models for these drawings instead of using the
Design Team’s protocols, the kick-off meeting is a good forum to raise
the issue.
The sectioning of drawings, breaking them into logical and manage-
able sections or areas, is often determined by the Design Team’s drafting
criteria, for example, how much area a typical 1/8" or 1/4" scale drawing
covers. Designers may divide their drawings by structural grid lines or
concrete expansion joint locations. Complex areas may be sectioned
into smaller parts when detailed drawings are needed, for example,
for mechanical or electrical rooms.
All sectioned drawings also require the imposition of a point of
reference, usually North arrows.
4.2.6 Default Standards and Tolerances
Detailing and coordination efforts on a project should have
pre-established standards and tolerances by which all participants
on that project should abide. These standards and tolerances should
be discussed and agreed upon during the project’s kick-off meeting.
An example of a common standard for is the layer document in Figure
4.5 on page 57. Examples of common tolerances frequently found
on MEP projects include a set of minimum clearances to be maintained
whenever possible between objects of different systems or structures,
steel fireproofing tolerances, dimensions for areas of influences for
hangers and inserts, “no-dig” zones for foundation areas of repose,
electrical panel clearances, and supplemental clearances for fire-
sprinkler inspection. Annotations for elevations and dimensions are
usually defined to be within 1/8" tolerance, except for underground,
which is not typically at the 1/8" level of precision.
Achieving Spatial Coordination Through BIM 59
BIM Execution Plans procurement release dates, and fabrication release dates. A good
coordination schedule should start from these important milestones
and work backward, making the adjustments required to benefit
the entire construction project. Rarely can this be done without
significant MEP input into a schedule.
• Assuming that the coordination process and model partitioning
must follow, in lock step, the concrete pour sectioning. For MEP
contractors, this can be very difficult if you are working to an
aggressive coordination schedule that has no float available. Some
building systems cannot be coordinated accurately if the starting
point is the middle or the wrong end, for example, coordinating
ductwork branches and mains before knowing where and how
the duct risers fit.
• Assuming that no construction in an area can start until the
coordination process is complete. One of the first elements of a
model that the construction process needs (sleeves and inserts) is
the last thing that is typically added to the Model. Every effort should
be made to coordinate and complete this piece of the Model before
construction starts.
• Tying construction-related coordination schedules to a permit
approval process. This coupling may be necessary for a few elements,
such as seismic or FM (Factory Mutual) approvals, but making direct
links between these activities should be discouraged.
4.3.1 Phasing
Some BIM/Execution Plans lay out a coordination phasing process
that is different from yours or from that of the local construction
industry’s normal detailing and coordinating process. Such phasing
plans can dictate the population of the components and/or intelligence
into your MEP models in a fashion that is inconsistent with your
standard sequencing. This inconsistency can impact your process in
a number of ways:
• Increasing the number of coordination passes or iterations to finalize
an area. Simply by definition, a three- or four-pass process can
require five or more passes just to follow a phasing plan.
• Inserting components into your models at a different point time
than normal, thus requiring additional detailing passes through
your internal models.
• Frustrating your experienced detailers. They know that everything
they produce in an early phase will change because they know what
must happen in a later phase, for example, coordinating duct mains
before the king-studs for doors are in place. Morale can drop when
dealing with professionals under such situations.
Achieving Spatial Coordination Through BIM 61
BIM Execution Plans 4. Adequate time is not allowed for the actual coordination process
BIM is usually squeezed into the coordination process and often,
adequate time is not allowed to complete the process effectively.
5. The coordination model must be “clash free”
Every project has some exposed clashes. There are situations where
the standard layering protocols and standard detailing process always
clash, for example, at connection points for equipment and piping. Mi-
nor clashes often indicate insulation wrapping conflicts or maintenance
clearance intrusions that are a product of the BIM tool and irrelevant
to the actual construction program. Therefore, it is not reasonable to
require or expect that the final coordination model is “clash free.”
(See Chapter 5, “Managing the Process” on page 67.) This is also a
great opportunity for the MEP Participant on the Coordination Team to
bridge the gap between poorly applied technology requirements and
the reality of how valued BIM construction is done in the field.
6. Composite drawings
Creating multi-trade, overlaid, 2D deliverables from the coordination
process is a time-consuming process. Additionally, most 2D deliverables
presented in such a manner are far too cluttered to be useful. Often
structural engineers will find a way to insist that the construction team
deliver such documents for review. The entire Coordination Team needs
to be well aware of any requirement for composite drawings, and the
approval procedures related thereto before any coordination process
begins.
7. Incorporating all changes and modifications during the
coordination process
Any language that imposes an unlimited number of coordination
passes and restricts reimbursement or recovery of the costs beyond the
standard and acceptable industry practice should be questioned and
removed. Attempting to place such a requirement on an MEP contractor
does not differ from the imposition of construction-related unforeseen
circumstances in any appreciable way.
8. Unlimited spatial coordination meetings
Any language that imposes an unlimited number of coordination
meetings and restricts reimbursement or recovery of the costs beyond
the standard and acceptable industry practice should be questioned
and removed. Attempting to place such a duty on MEP contractors
does not differ from the imposition of construction-related unforeseen
circumstances in any appreciable way.
64 Achieving Spatial Coordination Through BIM
BIM Execution Plans 9. Imposition of any team roles and responsibilities beyond your
contracted scope
If your firm is expected or willing to accept any roles and responsi-
bilities relating to the coordination process for the entire project, you
should document clear definitions, expectations, and limitations.
10. Imposition of Design responsibilities
Any language in a BIM Execution Plan that potentially shifts the lines
of authorship or responsibility for design-related activities should be
avoided. For MEP contractors, by definition, the standard and accept-
able industry practice involves fitting construction components into
allocated spaces, not stepping into any design responsibilities.
(See Chapter 5, “Managing the Process” on page 67.)
11. Access to original source files
Some BIM Execution Plans include a requirement for MEP contractors
to turn over their source files for the discretionary use of the Owner and
sometimes the Construction Managers. Many of the source files that
MEP contractors use contain proprietary information that your firm
derives from these files, as well as specialized components that your
firm may have spent considerable funds to develop. If such source files
are requested to be delivered from this process, clarify the amount
of information you are willing to provide. In addition, your company
should have a rigorous scrubbing protocol in place and run any source
files that may include proprietary information before handing them
over. (For more information about scrubbing model files, see Appendix C
on page 156.)
12. Continuous postings and updating
A BIM Execution Plan that stipulates continuous, daily updating
is an indication of problems to come. Except in extreme situations,
updated models should be posted on a published schedule. Keeping
the Coordination Team focused on meeting their expected commitments
and maintaining the sanity of the process is usually far more important
than having a continuous stream of updates. Collecting the appropriate
Documents of Record for such practices can also become unmanage-
able. Some Execution Plans have gone so far as to require continuous
participation in the coordination process, whether or not your personnel
are collocated. Such requirements don’t recognize that actually perform-
ing detailing and clash resolution is still an effort by professionals who
must have the time and space to think through any system placements
or modifications.
Achieving Spatial Coordination Through BIM 65
Managing the Process a. Standard and acceptable industry practice for spatial coordination
performed under the contract documents is a collaborative process
executed between the primary installation contractors and overseen
by the general contractor or construction manager. This practice for
spatial coordination seeks to integrate objects, systems, and compo-
nents into spaces allocated in the contract documents. Standard and
acceptable industry practice for coordination does not include adding
pipe, ductwork, fittings, conduits, cable tray, junction boxes, or other
appurtenances to remedy spatial constraints. Such work falls beyond
the scope of what is considered standard and acceptable industry
practice for coordination and will be performed as expressly directed
pursuant to the terms of the contract. Achievement of spatial coordi-
nation under the contract documents that represents standard and
acceptable practice in the industry assumes:
o The contract drawings have been fully designed and coordinated
by the owner and/or its design professionals such that, if installed
as shown on the contract drawings, the finished product will
result in systems operating as designed by the owner and/or its
design professionals.
o Systems fit within the spaces allocated on the contract drawings as
qualified below.
b. Spatial coordination that is standard and acceptable practice in the
construction industry does not include relocating systems from their
allotted spaces as shown on the contract drawings when such relo-
cations require added materials, shop or field labor, or coordination
time. Any such relocations or alterations of components and/or sys-
tems may compromise the integrity and/or the planned performance
of the system(s) as designed by the owner and/or its design profes-
sionals. Responsibility for the integrity and/or planned performance of
the relocated systems will remain the sole responsibility of the owner
and/or its design professionals.
c. Depending on the complexity of the project, from one to three itera-
tions each of clash identification and attempts at clash resolution are
considered standard and acceptable industry practice for coordina-
tion. Further iterations fall beyond the scope of what is considered
standard and acceptable industry practice for coordination.
d. The physical spaces for electrical, mechanical, sheet metal and
plumbing equipment rooms must be adequate to allow for the
installation of equipment as shown on the contract drawings. All
designed spaces must include clearances in and around equipment
as required by the contract documents, applicable codes and the
equipment manufacturer’s specifications. Adequate spaces must be
Achieving Spatial Coordination Through BIM 69
Managing the Process included in the design to accommodate incoming and outgoing
services to and from the equipment and for maintenance as required
by the contract documents.
Summary: Spatial coordination is a cooperative and collaborative
effort between the design professional, owner, general contractor or
construction manager, and the trade contractors. Normal and expected
spatial coordination performed by the trade contractors after the execu-
tion of a contract is not design. Rather, it is the reflection of the design
in a three dimensional model. Trade contractors rely on complete and
accurate designs when bidding projects in order to provide accurate bid
pricing. In return, trade contractors, such as those represented by the
MCAA, SMACNA, and NECA, using that design, are able to produce
reliable models by which the project can be constructed in a more
efficient, timely and cost effective manner.4
But, to take your task one step further, you should make sure that
your Project Participant colleagues also agree with this definition. Most
unsuccessful projects fail because communication breaks down. Gaining
an understanding of and agreement on the recommendations and
practices in this joint definition is a great starting point for open
communications, which in turn, are based on shared expectations
and a common approach.
5.1.2 Consequences for Dilatory Participation or Refusal to Participate
The success of the coordination process can often depend on the
weakest link. The consequences for parties who are critical to the
success of the coordination effort but do not participate, who are
understaffed, or who are otherwise unable to keep up with the other
Participants should be clearly laid out in the BIM Execution Plan.
If Participants are not active in the coordination process, you need
to understand that this will be a major issue for the project. You want
to make it clear to your senior management as early as possible what
the consequences will be. If the Participants had the opportunity to
contribute to the scheduling of the coordination process but did not
do so, the consequences for holding up the other Participants should
include penalties up to their removal from and replacement on the
project. In areas where the clash-detection tasks have been completed
without their participation, these parties should either model and install
their components around the finalized systems or be expected to reim-
burse the other contractors their added costs to revisit and re-coordi-
nate the completed areas impacted by their lack of involvement.
4
National Institute of Building Sciences buildingSMART alliance, The National BIM
Standard--United States, V2, National Institute of Building Sciences,
www.nationalbimstandard.org, section 5.5.1, accessed April 18, 2013.
70 Achieving Spatial Coordination Through BIM
Managing the Process Hospitals, laboratories, and other heavily concentrated facilities may
require smaller partitions.
Another consideration, specific to the size and partitioning of the
Model has to do with the degree of 3D modeling object representation
used in the process. The specificity of modeling detail should be visited
before partitioning a model for efficiency. Not only is this important
for the usability of the Model, but depending on the specific elements
required to be included (such as hangers, bolts, nuts) the requirement
may have a huge impact on load times.
5.2.4 Coordination Schedules
Realistic coordination schedules that are coupled with the construction
schedule are critical. These schedules should be prepared by the
Construction Manager and the Coordination Team.
Most major construction projects require the partitioning of their
models into manageable sizes to keep the programs from getting too
large for the hardware or software being used, and for setting priorities.
Actual construction installation schedules also require such partitioning.
The coordination and construction installation packages may or may
not be completely aligned. Creating reasonable coordination schedules
that stay ahead of actual construction, yet allow for enough time to
systematically perform coordination, is often what separates the best
construction managers and Project Teams from their competition.
Any workable clash-detection schedule must provide adequate time
for all major participants to perform, at a minimum, these tasks:
• Hold a kick-off meeting and a subsequent spatial planning meeting
for the project
• Obtain and process (scrub) any receivables from the Design Team
• Obtain, process and receive approval on all required submittals
• Evaluate and make a rough-detail model of their systems and
products. This step can require considerable time for MEP contrac-
tors because the nature of their components obliges them to evaluate
entire systems, not just area-by-area sections.
• Run a first-pass clash detection (to bring the initial installation
routings under the guidelines detailed in the LOD 350 specification)
• Modify or correct models for conflicts discovered during the first pass
• Supplement these updated models with support systems
• Run a second-pass clash detection (acknowledge resolution of
first-pass conflicts and review newly added support systems)
• Modify and correct models for conflicts discovered during the
second pass
Achieving Spatial Coordination Through BIM 73
Managing the Process • Supplement updated models for structural and seismic input
(where applicable)
• Supplement updated models for final model approvals
• Run a third-pass pass clash detection
• Annotate or create Documents of Record for sign-offs
• Submit sign-off Documents of Record for engineer’s review
and approval
These schedules must also take into account some tasks that are not
related to clash detection yet can drive the process because of actual
construction schedules or conditions:
• Specialty contractors who need to create fabrication documents
• Creation of installation drawings and details (2D deliverables) for
construction purposes
• Reviews and approvals from governing authorities
• Integration of shop drawings from other entities (for example,
millwork, OFE, kitchen equipment)
You may need to include some “float” to provide the time to
discover, communicate, and resolve any deficiencies in the design-
related receivables or gaps of information that might create
unexpected conflicts and problems.
These schedules may only be as good as the least-involved
contributor. You must hold each participant accountable for their
piece of the exercise. However, such accountability can become
a major issue if any of the major Participants were not given the
opportunity to provide input for these schedules. An inexperienced
Construction Manager could assign a leadership role on the
Coordination Team to a computer-savvy individual who is technically
proficient but lacks the knowledge to understand the amount of work
or effort that certain trades, especially MEP trades, must exert to
manufacture their product and accommodate the process.
5.2.5 Meeting Schedules
Any coordination process is meeting intensive. The BIM Execution
Plan should include a schedule of the meetings to be held throughout
the project. These focused meetings include weekly coordination and
clash-detection meetings, but may also involve separate or combined
meetings for design resolution, scheduling, change implementation,
permit-related issues or milestones, and so on. Such meetings can be
scheduled as separate meetings or rolled into a larger meeting with a
fixed agenda. On many projects, the initial schedule assumes that many
74 Achieving Spatial Coordination Through BIM
Managing the Process issues can be addressed in one large meeting; however, later
developments require separate meetings with a narrow focus to
keep the team effective.
Coordination Meetings
Holding coordination meetings is the norm for the industry. When
they commence and how often they are held will depend on many
factors, but weekly meetings are the common practice. The general
purpose of these gatherings is to perform clash detection on the
Federated Model and to review the status of the many processes
associated with it. This review includes Issues and RFI logs, the
coordination schedule, communications, additions or changes to the
scope, problems, commitments, and so on. These meetings should be
scheduled and led by the Project Coordination Manager. Each meeting
should follow a fixed agenda, which would include old issues and action
items, new issues and action items, and provide ample opportunity to
document any communications, commitments, and concerns raised
during these meetings.
It is a standard practice to hold coordination meetings on the same
day and time so that all participants can prepare for them well in ad-
vance. The venue should be established in the BIM Execution Plan.
The Project Coordination Manager should confirm that the venue has
adequate infrastructure for both physical and virtual participation for
the duration of the project.
As communication technology has developed, the necessity for all
participants to be present physically has diminished. The initial and
early meetings on a project may benefit from mandating this personal
presence, but once a Coordination Team has learned to work together
effectively, allowing Project Participants to attend through video-
conferencing and web-based meeting sites can be just as effective
and less burdensome.
Clash-Detection Meetings
Parties who are interested primarily in the clash-detection section of
the coordination meeting may or may not have participated in the
coordination meetings. Establishing who is expected to participate in
clash detection and their roles in that process, and addressing their
specific issues and concerns can run parallel to the Coordination
Meeting agenda, but should be recognized as a separate program
that requires attention from your firm’s leadership and the Project
Coordination Manager.
Achieving Spatial Coordination Through BIM 75
Managing the Process that you must always refer back to the BIM Execution Plan to identify
contractually what you can expect to receive from the Design-Intent
Model being delivered from the Design Team. Each Design-Intent Model
needs to be assessed individually for the MEP elements it contains and
whether they are at a LOD 300 or not.
There have been and will continue to be situations when a Design
Team presents the Owner and Architect with an LOD 300 Model that
they claim was coordinated within their Design Team and that allows
additional space for LOD 350 and LOD 400 MEP construction modeling.
This is not always the case; the state of the Model should be confirmed,
and if deficient, be raised as an issue as soon as it becomes apparent.
Many coordination projects are derailed, delayed, or overwhelmed
when the Design Team has not allocated sufficient space to accommo-
date the MEP systems that are designated for the architectural space
provided for them.
5.3.1 When to Start the Clash Detection Process
Starting clash detection too soon creates different problems from
starting too late, but both waste time and money.
Work should not begin until all major participants are on board
and engaged, until all models are at LOD 350, and until significant
information is available or decisions have been made (for example,
underground plumbing drainage systems must wait until wall locations
and dimensions are locked down). Starting too soon sentences the
Coordination Team to multiple clash-detection passes with no time
off for good behavior.
On the other hand, construction schedules that do not provide
adequate time to perform all the necessary activities often mean that
shortcuts must be taken. Areas may have to be skipped, coordination
may have to be piecemeal or not performed systematically, which can
be far more difficult for contractors who install systems than for those
who install components.
When all major participants contribute to the clash-detection
schedule, the results are better—and far less expensive—for everyone.
5.3.2 Coordination Protocols
Clash detection can begin when all requirements of the Execution
Plan have been developed, reviewed, and acknowledged by the
Coordination Team, and a schedule for this program is developed
and agreed upon.
Comprehensive logic diagrams of this process can be developed
for any project. On large projects with long construction schedules,
creating these diagrams in collaboration with all major Participants
Achieving Spatial Coordination Through BIM 77
Prioritization
As the Coordination Team becomes more experienced in performing
clash detections, Participants learn which work products to include and
exclude from their first-pass models.
Best practices stipulate that the clash-detection process for commer-
cial facilities begin by resolving gross conflicts and work its way to minor
conflicts. Nonmovable systems, large-volume components (such as duct
mains), and gravity systems normally take precedence in space-claiming
and in clash resolution.
Areas that are unusually complex, of high density, or where significant
design problems arise may need to be separated from the regular
clash-detection program and be managed independently of the balance
of these areas and their associated schedules.
The construction schedule or installation means and methods
can change the clash detection or installation priorities causing the
acceleration or delay of an area. Large equipment installations or
deferred approval components might have this impact. When the clash
detection process is affected, or gets behind, regardless of the reasons,
a careful evaluation of the impact of the various costs of deviating from
any standard protocols should be made.
Conflicts
Conflicts will always arise. An initial clash-detection exercise
generates literally thousands of conflicts in an area. This is to be
expected, especially when members of the Coordination Team have
not worked together before, or simply lack the experience to populate
their models in a sequence that will allow them to effectively coordinate
with other stakeholders.
Coordination Teams often recognize conflicts within the Design-Intent
Models received at the start of a project. Even elementary but serious
conflicts such as gravity systems and structures may be presented and
described as LOD 300 elements. If the systems as designed, but before
any contractor coordination efforts begin, do not fit within the allocated
ceiling space or if the walls are not wide enough to accommodate riser
Achieving Spatial Coordination Through BIM 79
Managing the Process pipe or conduits, such issues often indicate that adequate design
coordination did not take place or was not a serious concern of the
Design Team. Again, establishing with the Design Team at the outset
that the purpose of clash-detection is not to complete the design should
help establish the ground rules of all stakeholders to perform to the
level expected.
One method of minimizing conflicts is to spend extra time “planning
the planning.” Have the Coordination Team commit to baseline space
allocation, routing, and rules set forth in the BIM Execution Plan. These
preliminary meetings also help new participants to recognize that
spatial coordination encompasses more than product-to-product clash
resolution, but extends to product-to-access clearances, code spaces,
hanger locations, and so on.
Planning-the-planning exercises often help everyone to agree upon
certain default situations (fireproofing tolerances, common PORs, and
so on) and work as a team from a common starting point.
5.3.5 The Process of Clash Resolution
Resolving “clashes” should be a team effort, making adjustments to
the benefit of the construction project and all parties to it. Although the
BIM Execution Plan should clearly establish a baseline order of prece-
dence for component installation, a certain level of give-and-take is
required of all Project Participants. Common sense should always prevail
in any clash-resolution process. It is unreasonable to expect a 40"x20"
duct to be offset around a 1" water line. On the other hand, that same
40"x20" duct may need to move to accommodate a 10" gravity storm
drain pipe that needs slope to drain.
Should any individual participant or firm decide to adjust to clashes
only when it works to their advantage, the Project Coordination
Manager or the Construction Manager may need to become involved.
You should also be wary of those who might attempt to stand on
preapprovals of governing agencies, such as for sprinkler systems,
to justify their unwillingness to modify or change their routing. If they
submit their plan for agency approval before the coordination process
is complete, they may have to resubmit a modified plan. This is not
unusual; changes in scope constitute similar considerations.
If consensus cannot be reached during these meetings, the Project
Coordination Manager may be called upon to exercise the authority
to resolve the issue. If the impacts of these resolutions are significant
enough, you should follow your company’s procedures for elevating
the issue.
80 Achieving Spatial Coordination Through BIM
Managing the Process Clash reports can be generated within the virtual design coordination
software and distributed to the Coordination Team to track the responsi-
bility for resolution of trade work where residual clashes are present.
Clash reports should be generated before and after clash detection
meetings; however this process should not begin until after the second
pass. Restraint is prudent because of the extremely large number of
conflicts and clashes that are usually encountered before the official
clash detection process is underway.
The process of clash resolution can very easily become the point
where contractors extend their efforts across the line that separates
coordination from design. Spatial solutions can be visualized, but
system impacts are harder to define. When these circumstances arise,
it is always better to have the Design Team ready and willing to partici-
pate. The Coordination Team does not need to wait while designers
go through various what-if scenarios; instead, it has the authority to
approve spatial modifications with the expectation to re-evaluate any
calculations or system performance criteria used initially and confirm
this conflict does not impact those calculations or criteria.
The Project Coordination Manager should keep the minutes of these
meetings and post or distribute the resolutions of all major conflicts.
Resolution of major clashes should be documented and tracked in a
manner that is consistent with the required Documents of Record and
that can be audited.
“Clash Free”
Inexperienced Project Participants and Project Coordination Managers
can get bogged down with the number of clashes and can lose focus on
resolving the large and critical clashes that must be remedied first. Some
insist on models that are completely “clash free.”
Attempts to create truly clash-free coordination models are, in most
cases, a waste of time. Minimum insulation overlaps, minor challenges
to access zones, and similar conflicts are costly to correct and irrelevant
to the use of the Model. The primary use of coordination models is to be
a tool to assist in construction.
5.3.6 The Number of Clash Detection Passes or Coordination Iterations
The number of area coordination iterations that a contractor must
participate in has a direct and significant effect on the costs and time
required to perform clash detection and complete the coordination
process.
A rule of thumb that contractors use in commercial Design-Bid-Build
projects is that they should be able to complete the coordination
process in approximately three passes per partitioned area. Certain
Achieving Spatial Coordination Through BIM 81
Managing the Process types of projects may require a few more, but even these should be
recognized and acknowledged in an RFP or a kick-off meeting.
The scope of each pass is as follows:
• The first pass identifies gross initial conflicts
• The second pass identifies remaining conflicts, new conflicts created
by the addition of new support or seismic components into the model
or non-resolved conflicts from the initial pass
• The third pass identifies remaining conflicts, and their resolution will
permit the publication and sign-off of the construction model.
On Design-Bid-Build projects, there exists an expectation that the
Design-Intent Model received by the Coordination Team has already
undergone adequate design coordination and is presented at an LOD
300 standard. Projects delivered on a Design-Assist or Design-Build basis
may require more or fewer passes, but neither should be open ended or
left to someone’s guess.
Managing the Process • The information that MEP contractors are working from, such
as structural steel drawings, are design drawings, not the final
fabrication shop drawings. This can require revisiting coordinated
areas after receipt.
• The process is bogged down in revisions or changes of scope. Often
the cost of re-coordinating an area is greater than the cost to make
the modification itself.
• Deferred approvals by governing agencies force certain systems,
such as seismic restraint systems, to follow an additional path that
is separate from the coordination process. (This is not an excuse
for nonparticipation.)
Regardless of the cause, every Project Participant should recognize
that too many passes can and will add cost and time to their efforts.
Contractually stipulated documentation and notification requirements
may easily apply under such circumstances.
5.3.7 Communication and Collaboration Among the Trades
Every Project Participant should actively work with the other
Participants, both during and outside regular meetings, to resolve actual
or potential clashes. Without this collaboration, a coordination process
can be seriously delayed or impeded. Although your firm may not be
directly contracted with these other participants, and you may not
have the ability to obtain or demand their cooperation, most trade
contractors are willing to work together when they feel that they are
being treated fairly.
The pertinent information can be exchanged in person, via email,
telephone calls, or other methods. Every contractor involved should
train their personnel to recognize which adjustments made during these
communications are necessary to document and which are not.
The style of some Construction Managers is to demand that all
communications relative to any project be directed through them.
This behavior is counter to what contributes to the success of a
coordination process; no such restriction on the flow of information
should be instigated.
Achieving Spatial Coordination Through BIM 83
Managing the Process 5.4 Red Flags from the Coordination Process
There are various indicators that experienced Project Participants
recognize in the early coordination process that may signal problems
ahead.
1. No BIM Execution Plan for project
2. Scheduling issues:
a. Coordination schedules were created without input from the
Coordination Team.
b. Coordination and construction schedules are decoupled.
5.4 Red Flags from the Co-
ordination Process c. Schedules are unreasonable, unachievable, or poorly thought out
3. Design issues:
a. The model element receivables from the Design Team are not at
LOD 300
b. Design Team resists or refuses to participate when asked
or needed
c. Resolution of design issues takes far too long
d. Lack of real collaboration with Design Team
e. Changes to the design drawings are not documented with
revision clouds
4. An absence of a systematic issues-resolution process
5. Project Management issues:
a. PCM has little or no experience in the role
b. PCM has little construction knowledge
c. PCM does not understand Levels of Development in the models
d. PCM does not have adequate authority
e. PCM is reluctant to or resists taking issues to the Design Team
f. PCM tends to permit coordination to morph into design
g. PCM makes decisions without appropriate authority or Design
Team confirmation
h. Nonstandard coordination standards used
i. PCM forbids free communications between participants
j. Disorganization of processes and documents: no meeting agendas
or minutes, documents of record
k. PCM makes offline exceptions to MEP contractors or other smaller
subcontractors
84 Achieving Spatial Coordination Through BIM
A
This chapter highlights the important Document of Record and
ll construction projects have
describes their place in the MEP contractor’s operations. This
Documents of Record, which range
information is useful if you are a senior executive, Project Manager,
from contracts to daily time sheets. or Construction Manager responsible for these Documents of Record.
Coordination programs use and
generate Documents of Record that
• 6.1 Working with Documents of Record on page 85
are necessary to meet a variety of
obligations that all MEP contractors • 6.2 Receivables from the Design Team on page 86
have. • 6.3 Internal Receivables from Your Project Team on page 90
• 6.4 Inter-Trade Receivables on page 91
• 6.5 Other Receivables on page 93
• 6.6 Deliverables on page 93
• 6.7 Communication with the Design Team on page 98
• 6.8 Managing Documents During the Coordination Process on page 100
6.1 Working with
Documents of Re-
cord 6.1 Working with Documents of Record
Some of the pertinent Documents of Record are easy to find in an
RFP package, while others may be scattered or difficult to identify from
the volume of information that is often provided. Many of your clients
require you to use their unique forms and documents during the
coordination process.
Rules and definitions surrounding any documents that are to be
delivered as part of the coordination process may be significantly
different from project to project and may include a greater number
of stakeholders, including departments in your company.
By no means do all Documents of Record relate to the coordination
process, but many important ones do. These documents are usually
the contractual baseline for all coordination efforts.
The success of any coordination process requires disciplined
management of project documents. The documentation processes
require someone with authority to manage, provide clear and
appropriate instructions, and push resolution of issues and to define
and document problems, changes, and impacts caused by or to the
coordination process.
86 Achieving Spatial Coordination Through BIM
Documents of Record were created after the 2D drawings were completed; however, at times
this language is used because the Models provided by the Design Team
are either more current than the drawings provided or vice versa. Look
to the BIM Execution Plan for clarifications regarding the ability to rely
upon any Design-Intent Model.
6.2.4 Fabrication Models
Having the Design Team’s Design-Intent Models available at the start
of the coordination process is good; having actual fabrication and erec-
tion drawings from the actual suppliers of certain building systems or
components is better. Some trades (for example, structural steel) may
have been released for fabrication before coordination begins. These
trades rarely participate in any coordination efforts and the other trades
are often obligated to work around their drawings. However, the trades
that do not participate often have comprehensive fabrication models;
obtaining and using these models instead of the respective Design-
Intent Models allows better and more accurate coordination.
Maintaining open communication and cooperation with these fabrica-
tion and erection contractors benefits the Coordination Team. Although
they may not be flexible with their plans and drawings after fabrication
is completed, before fabrication is finished they are often willing to work
with the Coordination Team and to make desired changes in the same
manner as other trade contractors do.
When these trades do not provide their fabrication models or
drawings in a timely fashion and the Coordination Team begins work
from the structural Design-Intent Models and drawings that are avail-
able, a quality control or re-coordination effort may be required to
review and respond to actual fabricated conditions. This review may
require additional coordination passes through complete and
coordinated areas, which can become expensive.
6.2.5 Piping and Instrumentation Diagrams
Often, coordination efforts must begin with only general layouts and
piping and instrumentation diagrams (P&IDs) available (Figure 6.1 on
page 89). This situation is far more common on industrial projects
than commercial projects.
Although stand-alone P&IDs do not meet the requirements of an LOD
300 receivable, they should reflect all the piping, including the physical
sequence of branches, reducers, valves, equipment, instrumentation,
and control interlocks. The P&ID may be used to operate the process
system.
Achieving Spatial Coordination Through BIM 89
IAS
(Instrument Air Supply)
FT
FV-3-3040 10
From Transfer Pump Mixer To Reactor
P-201 IAS M-08 R-102
(Instrument Air Supply)
S
Sample Point
FT
11
From Transfer Pump FV-3-3041
P-201
Piping & Instrumentation
Diagram (P&ID)
www.EngineeringToolBox.com
Documents of Record Whenever possible, this submittal data should be uploaded and
maintained at the Coordination Team’s file-sharing location. Other trade
contractors often need valuable data that can be derived only from your
firm’s internal deliverables.
6.3.2 Certified Drawings
The critical nature of the dimensions and weight of certain pieces of
equipment may be integral to the success of an MEP coordination effort.
This equipment may be furnished by the contractors or other parties.
Often manufacturers have purchase-order language, or boilerplate
terms, that permits them to deviate from the information they might
provide during the normal course of any product approval process.
When there is a need for such information to be absolutely accurate,
you can request or require your vendors to provide certified drawings.
Certified drawings should include all details of the equipment includ-
ing exact connection information for all piping, duct, and electrical con-
nections. Some manufacturers will provide a 3D model for this, also.
Documents of Record coordinated trades. Obtaining this important data early can truly
expedite the coordination process.
6.4.2 Wall and Ceiling Framing
Having the details for the interior finishes is helpful for any com-
plete or comprehensive commercial model. Interior finish contractors
can now create accurate models of all elements of their construction,
including wall and ceiling details, supports, and bracing. This information
is needed to coordinate wall openings and the placement of ceiling-
mounted items.
When the coordinated MEP models are properly used to communi-
cate construction scheduling and sequencing, including the complete
framing details in them also enhances the ability of all affected parties
to distinguish priority installation walls from the walls that follow MEP
overhead installations, to accurately reflect soffit framing requirements,
to indicate king-stud supports and clearances, and to indicate other criti-
cal means and methods of installation. When the framing contractors
have not participated in the coordination process and the renderings
and details from the Design Team are the only information available
during the process, considerable rework and re-coordination is required.
The participation of the specialty subcontractors should be the same
as all other participating parties; the precedence of their installations,
their claim to or allocation of space, and the proper sequence of popu-
lating their models should be addressed in the BIM Execution Plan.
6.4.3 Curtain Wall
Manufacturers and installing contractors of curtain walls are now
providing object models for the elements of curtain walls, including
specific bracing and connection details. This information is often needed
to adequately model or coordinate overhead rough-ins or exterior wall
risers. Also, the bracing and framing of curtain walls is sometimes not
accounted for adequately in the Design-Intent Model. This information
can be very helpful for coordination.
6.4.4 Interior Finishes
Many commercial projects have custom millwork, casework, or
furniture-like items that can impact the layout and placement of MEP
rough-ins and services. Having fabrication or erection shop drawings
available for the coordination efforts is preferred, but this information
is rarely available during the early phases of the coordination process.
If the design documents are not adequately followed, a review and
re-coordination effort might be required.
Achieving Spatial Coordination Through BIM 93
6.5 Other Receivables 6.5.1 Equipment or Products Furnished by the Owner or Others
Owners or other parties who are not actively participating in the
coordination process may furnish equipment or systems that require
coordination over and above the information furnished by the Design
Team. Such equipment includes, but is not limited to, the following:
• Kitchen equipment
• Medical equipment
• Laboratory equipment and furniture
• Kitchen equipment
• Process equipment
Again, having the wrong or incorrect design information to adequately
coordinate the MEP rough-ins or systems can require re-coordination.
6.5.2 Facilities Management Input
Obtaining input into the construction coordination efforts from the
Facilities Maintenance personnel before starting the coordination pro-
cess can be very useful. Knowing what these clients expect and incor-
porating some of their standards for access and work space, or simply
knowing how they might be using your completed model after turnover
can help avoid frustrations and problems at the end of a project.
6.6 Deliverables 6.6 Deliverables
Deliverables are the models, documents, and other information
that are derived from or delivered after the coordination process is
completed. These documents are contractually required, expected by
specific industry stakeholders, or needed for your company’s internal
operations. The specific details, the schedule, and which parties will
use these deliverables and for what purposes should be stipulated in
the BIM Execution Plan or contract documents.
Common deliverables include the following:
• Sign-off documents
• Complete and coordinated construction models
• Coordinated 2D shop drawings
• Hanger and insert drawings
• Sleeve and block-out drawings
• Pad or foundation drawings
• Point load drawings
94 Achieving Spatial Coordination Through BIM
Documents of Record are derived from multiple sources, the Project Coordination Manager
should be the party assembling and submitting these to the structural
engineers for their review and approval.
6.6.11 Total Station
Robotic style layout equipment is now being used for MEP layout
operations. This equipment can also be used for sleeves, hangers,
concrete pads, and underground piping systems. There are innumerable
uses of precise layout information derived from the coordinated
models. This system of layout is commonly known as Total Station.
Information from a coordinated model is used to identify layout points
such as hangers. These points are identified and numbered, and carry
specific information such as hanger insert type and diameter. The ro-
botic system is set up on the job site, and control points are established.
The identified points are then established using a laser pointing system
delivered by the robotic unit; when the point is identified, the specific
hanger can be set. The goal is to set all sleeves, hangers, and other items
on decks before concrete pours. When a crew is proficient in using this
type of equipment, several hundred items can be set in one day. Items
can be set before a concrete pour or afterward, and then transposed up
and installed using drilling and setting methods. Setting items before
concrete pours is the preferred method.
6.6.12 Bills of Materials
Bills of Materials (BOMs) can be extracted from the model throughout
the process. Although the software processes makes it easy to create
many of these BOMs, they should be reviewed before they are released.
These BOMs can be used for accurate purchasing, tagging, packaging,
estimating, creating look-ahead task estimates, estimate validation,
labor tracking, and many other purposes.
6.6.13 Fabrication Drawings and Details
When coordination is complete, your model is signed-off, and you re-
ceive authorization to begin manufacturing, fabrication, and installation;
your construction model is now considered to be at LOD 400. Fabrication
drawings can take various forms and may include single spools, multiple
spools, spool maps, equipment skids, plumbing in wall batteries, and
hangers and hanger racks. A complete list of prefabrication deliverables
should be made available to the team at the spatial planning meeting.
This is an area where involving the skilled trades in determining what
and how to prefabricate is absolutely essential to its success.
6.6.14 Turnover Packages
Deliverables to be “turned over” at the end of the project are
normally defined in the project specifications. Some of the documents
required for these packages relate to the spatial coordination process:
98 Achieving Spatial Coordination Through BIM
Documents of Record Your Project Team must also recognize that participating in the
coordination process does not remove or replace any contractually
imposed notification requirements.
6.7.5 Archiving Documents
You want to establish a system for capturing and filing the receivables
for any project.
Long after a project’s Document Control program has closed, you
may a need to retrieve all the information pertaining to receivables,
deliverables, and other important Documents of Record. Every
contractor who participates in the coordination process should
obtain the project files at the end the project.
6.7.6 Archiving Models
Give special attention to capturing and archiving any models received,
created, or delivered from the Coordination Team. Modeling hardware
continues to improve, and software programs are updated regularly,
often more than once per calendar year. Newly published versions of
software do not always fully support earlier versions.
The march of progress can also wreak havoc on any program used
to archive or maintain the models used on large or long-term projects.
Attempts to access models created even five years earlier can often be
stymied because current hardware or software cannot open or modify
them.
In addition to internal storage of these files, which can be extremely
large, maintain hard copies also. If you believe that a project’s model
files have considerable future value, consider archiving the computers
that currently run these programs.
6.8 Managing Documents
6.8 Managing Documents During the Coordination Process
During the Coordination
Process New and critical pieces of information arrive, often daily, during the
course of a normal coordination process. These documents may include
drawings, sketches, RFIs, and addendums. You should be prepared at
the outset to properly manage the documentation and data files.
Management includes providing timely notification of updates and new
information and providing access to this data to all Project Participants.
6.8.2 Web-Based Document Control Programs
Most large projects use web-based document control software
that is usually managed by the Construction Management firm. These
programs can be simple or very sophisticated. These programs need
to be organized and managed effectively, otherwise participants can
be overwhelmed by the sheer volume of information that they are
expected to review; they may not be able to find information they need,
Achieving Spatial Coordination Through BIM 101
Documents of Record on your setup, hyperlinks can go a long way toward simplifying searches
for the most current information.
6.8.5 Meeting Minutes
Accurate minutes of all spatial coordination meetings should be kept.
The Project Coordination Manager should maintain the official set of
minutes, and distribute them to the team for review and approval. All
matters requiring action should be documented with applicable due
dates indicated.
You are well served to maintain your own minutes and notes. This
practice permits an internal reminder to distribute the action items
and changes to those individuals within their organization that may be
affected by issues broached during these meetings. Having the Project
Manager or his trained representative participate in all coordination
meetings is advantageous because many detailers and/or modelers are
not usually trained to keep adequate notes or to recognize issues that
might involve additional costs or time.
Achieving Spatial Coordination Through BIM 103
Benefits of BIM Beyond drives the shop’s plasma cutting table and coil lines for manufacturing
Spatial Coordination the objects. There are many other types of fabrication that are gener-
ated from the process of spatial coordination, such as plumbing fixture
batteries, piping main racks, hangers, equipment hook-ups, pipe cuts,
and hanger points for robotic layout.
In each case, an MEP contractor can use the data by-product to
automate a unique prefabrication or fabrication process, eliminating
potential human error, reducing manual input, and gaining greater
manufacturing efficiency. For more information about using this data
for fabrication, many tutorials, articles, and papers are available on the
Internet and through MCAA, SMACNA, and NECA. (See Appendix D on
page 160 for contact and reference information.)
7.1.2 Data from the Design-Intent Model
When you begin any project, you have two originating sources of
digital data: the project’s Design-Intent Model and your firm’s estimate.
The Design-Intent Model arrives either as part of the bid documenta-
tion or, once you’ve won the job, as part of the contract documentation.
Typically, the Model arrives after the bid was awarded in the form of a
Level of Development 300 model. (For details on LOD, see section 2.3 on
page 15).
The Design-Intent Model is created in one of a handful of industry
software packages, including Autodesk’s Revit MEP, Bentley’s AECOsim,
or Graphisoft’s ArchiCAD. These MEP design platforms provide function-
ality that allows you to collect pertinent MEP object and system services
data directly from the document. (See Appendix C, “Scrubbing the
Design Model” on page 156.)
Many MEP contractors lack both the software to open this model
and the skills to extract from it the project data that they need. Instead,
they invest hours in creating and assembling this data, and because this
process is largely manual, opportunities for introducing errors abound,
and corrections or revisions take more time than they have to.
This is a common mistake, though an understandable one. Historically,
these platforms have yielded little value to MEP contractors, who had no
incentive to invest any time or money in them. But Design Teams now
use them to create higher quality models, which gives you more reasons
than ever to develop basic competency with these design platforms.
The skills needed to extract MEP object data to assist estimating (for
quantity and material take-off) or to populate your virtual design and
project management process can be acquired in a few days. The value
of having personnel on your project team who can collect data is
significant, particularly with respect to many of the initial requirements
and tasks of the Project Manager.
Achieving Spatial Coordination Through BIM 105
Benefits of BIM Beyond on the project and who is in the position to do something about
Spatial Coordination whatever may need to be altered or changed.
Recognizing that the project has been in motion for months, you
want to discuss is construction schedule first. A common mistake that
first-time or inexperienced Project Managers make is to agree to a
construction schedule that is not aligned with what your firm’s resources
could possibly accomplish within that timeframe. Therefore, before
you agree to any milestone in the construction schedule, you must
have confidence that your Project Team has the time and resources
to meet them.
Many experienced MEP contractors suggest that the initial focus in
this meeting should be on the concrete pour schedule. Keep in mind
that the Construction Manager, the General Contractor, and the con-
crete subcontractor are on the same page regarding the schedule, a
schedule that was more than likely created without input from you or
the other MEP trades. Ensuring that your virtual CAD department has
enough time to complete your hanger points and project model before
the scheduled pour date is a great advantage in cost and labor savings.
If you aren’t able to complete and receive sign-off of your coordinated
hanger model in time, you will be forced to drill each hanger point after
the pour at greater expense and labor. If there is even a slight chance
that your detailers will not complete their coordinated hanger points
schedule in time, this meeting is the only opportunity you have to
address it with the Construction Manager before the kick-off meeting.
The general philosophy that guides spatial coordination with 3D
modeling is the expectation that all participants are willing to work
collaboratively. This point is worth emphasizing during your meeting
with the Construction Manager if it doesn’t appear that you can meet
the concrete pour schedule. There may be a way to negotiate a later
date, allowing your CAD detailers to complete the hanger points in time.
If no relief is available and the schedule cannot be extended, there is
value in knowing that this issue exists and that you may have other
options. One option, if you can present information to establish that the
pour date is unreasonable within a normal virtual design process, your
firm might be in a position to issue an RFI, and potentially seek mon-
etary compensation. Another option, if the Coordination Team is falling
behind the pour schedule, is to skip an area, especially if it has numer-
ous design issues delaying coordination sign-off, and come back to it
later using traditional installation methods. This will allow you to get
ahead of the pour rather than staying behind it for the entire project.
Achieving Spatial Coordination Through BIM 109
Benefits of BIM Beyond company, and to the entire project. The Project Team member closest
Spatial Coordination to the data is responsible for adding it to the worksheet accurately as it
becomes available. (For more information about tools and technologies
that can help facilitate this process, see Chapter 9 on page 129.)
When you have received sign-off authorization to begin manufac-
turing, you now have a real lineal footage of ductwork, total pounds,
number of fittings, and number of hours projected for the job. You can
use that data to calculate a metric of “average lineal feet per hour” for
the project per space, per zone, per drawing. If you collect and review
data every two weeks, you will understand where you are with respect
to costs and schedule. Specifically, you’ll be able to measure your
performance in important areas:
• Track productivity of your firm’s field installation teams against what
was planned
• Determine whether any mitigating outside circumstances (perhaps
created by another party or by an internal company conflict)
contributed to less-than-expected results
• Gauge the health of your portion of the project at any time
• Determine whether additional steps need to be taken to minimize
impact an issue in the field may have on the overall project results
When creating the template for these worksheets, be sure that all
updated cells automatically populate any cells associated with and
hyperlinked to them. This property supports expanded reporting and
analysis. For example, it is useful to view a plotted graph that aggregates
data taken from individual cells and worksheets and compares it with
historical data from previous collections. In addition, use the data to
populate a standard nongraphed contextual report with quantitative
data generated from an algorithm that represents measured data,
such as the total completed lineal feet during week 4 on the project
for Installation Team One.
A one-stop software solution that automates all of the tasks required
to manage a PM Estimate through the lifecycle of a project is currently
not available. Technology and software publishers are targeting this
need, and the first sets of tools are expected to enter the market soon.
In the meantime, expect that inputting this data is a manual process
and may take up to one man-day to collect, collate, and place into the
worksheet for review. If you review progress every two weeks, this
updating is needed less often than if you review it weekly.
112 Achieving Spatial Coordination Through BIM
Benefits of BIM Beyond Moving your firm away from fiddling with disparate departmental
Spatial Coordination databases toward sharing and exchanging data with confidence requires
technical skills and knowledge of the applications and their database
structures. The best recommendation is to take small steps and to
engage the assistance of your software publishers. Instead of tackling
all of your databases at once, work to align your estimating software
data with your virtual CAD content data. The many combinations of
estimating software and CAD authoring software makes it impossible
to explain how you might do that for the combination used in your
firm. However, there are some basic rules to the process.
First, establish a unique identifier within each database that you
will use to map and link the two database structures. There are two
mechanical content aggregators who could provide identifiers that
can be adopted to provide this map and link between application data-
bases. The aggregators are Trade Service (Trimble) and its PIK code, and
Harrison Publishing House with its HPH code. Appending any of these
identifiers to the data in your existing databases provides a mechanism
that your firm can use to align the content libraries of your applications
with each another.
Second, consider how to update the content for both databases as
an ongoing process. Setting this up is where the experience and skill of
your application software publisher becomes invaluable because each
application has its own methods for accommodating updates.
Managing this deluge of data requires significant changes in your
operations. Yet, in so many ways, the benefits far outweigh the costs.
If you step up to these challenges, you will have better managed, more
efficient, and more successful projects. And that success should bring
more opportunities and more projects.
Achieving Spatial Coordination Through BIM 115
The cost and effort of entering into the BIM process is substantial. If
8 you are considering taking your company in that direction, you need to
CHAPTER 8 believe that it’s worth it. When the MEP “pioneers” finished their BIM
Evaluating projects, they discovered how the all that they had invested pays off.
EValuating Spatial
Coordination Contract They had replaced nonstandard practices and communication patterns
Language with linear, repeatable operating procedures. They knew where to get
the data they need from previous bids and projects and how to repur-
pose it. They knew how to recognize the unreasonable risks in vague
Evaluating Spatial While the best BIM and spatial coordination requirements are
Coordination Contract Language prescriptive, detailed, and clear, you must always be on the lookout
for vague or inconsistent requirements. Most, if not all, of the spatial
coordination requirements can be communicated clearly. If any bidding
information is unclear, you should not assume that the terms are
unimportant or inconsequential. Instead, you should submit detailed
questions to remove uncertainty during the pre-bid clarification period
so that you can develop a sound approach to the bid. If the BIM or
spatial coordination requirements cannot be clarified prior to bid
submission, you may want to mitigate risks by qualifying your
proposal accordingly. Similarly, if any of the requirements are clear,
but inconsistent, you should seek to resolve the potential conflict
or any misinterpretation through the pre-bid question period by
submitting an RFI or other documentation vehicle.
Any subcontracts that potentially tie your duties and responsibilities
to those contained within the prime contract between the Owner
and the General Contractor should be assessed to ensure there are
no inconsistencies. You should attempt to resolve any questions you
have by submitting an RFI in the manner as noted above or by other
appropriate means.
The failure to ensure a precise understanding of the coordination
requirements may saddle your firm with additional or different
obligations than those you thought you were agreeing to; in turn,
the obligations that you actually undertake can give rise to added,
unanticipated costs to meet the coordination requirements and increase
your exposure to certain legal liabilities. MEP contractors who have not
taken these steps have found themselves obligated to scope, process,
or other requirements that they did not anticipate simply because they
did not give the spatial coordination/BIM sections of an RFP adequate
attention.
The ability to successfully and profitably bid and complete a
project may depend on having clear and well-defined expectations for
the spatial coordination requirements. To this end, your firm should
provide pricing that is adequate and appropriate to meet the
requirements, clarify expectations, or qualify the bid in the event
of ambiguous or missing requirements.
8.1.2 Risks Associated with Vague or Inconsistent
Contract Requirements
The quality and clarity of BIM and spatial coordination requirements
can vary widely for many reasons. At times, the BIM/spatial coordination
knowledge or proficiency of the author of such requirements becomes
evident. Although the technology is no longer new, it is still unfamiliar
118 Achieving Spatial Coordination Through BIM
Evaluating Spatial to many Owners, contract managers, and specification writers. Truly
Coordination Contract Language “standard” specifications or requirements for spatial coordination have
yet to be developed and adopted industry-wide.
Beyond the Owner’s design or specification authoring team, require-
ments also can vary considerably between Construction Managers or
General Contractors who each may have their own levels of BIM sophis-
tication, style, preferences, and demands when it comes to spatial coor-
dination. MEP contractors that work with various Owners and Construc-
tion Managers simultaneously often find themselves working under a
multiplicity of rules, requirements, or expectations across different jobs
on a daily basis. Understanding and managing all this can be quite a
juggling act.
Sometimes the requirements for BIM or spatial coordination process-
es are scattered throughout the RFP documents or specifications and
cannot be located easily. Under such circumstances, it is not uncommon
to find contradictory or confusing language. A typical RFP may be the
work of many people, each with their own particular area of expertise.
The modeling and spatial coordination requirements may be written
by a “BIM specialist” while the “boilerplate” coordination and submit-
tal requirements may be written by a skilled, but traditional, building
systems coordinator. These different perspectives can result in an RFP
that contains inconsistent requirements that call for both traditional,
paper-based, coordination submittals and BIM-based spatial coordina-
tion processes and submittals, leaving the contractor unsure of which
obligation it must follow.
Other samples of confusing language may include using the terms
“BIM” and “CAD” interchangeably, which can create a great deal of
confusion, or require the MEP contractor to “use BIM” on the project
without otherwise specifying why or how it is intended to be used.
These differences can result in spatial coordination requirements
8.2 Specific Legal Consider- in bid or contract documents that are vague, contradictory, not
ations Concerning Spatial coordinated, or inconsistent with other requirements. Such vague
Coordination or inconsistent requirements create risk for bidders and require close
attention to minimize exposure relative to costs, risks, and liability.
Evaluating Spatial remodel as well. Or, alternatively, you will have to absorb the cost of
Coordination Contract Language adding resources to accelerate the additional work to avoid delaying
the project. These coordination requirements, when couched within
the MEP contractor’s larger contractual obligations, can significantly
increase legal risk.
MEP contractors sometimes find that the terms of a contract between
an Owner and the Design Team significantly influences the flow and the
quality of information received from the Design Team, specifically, the
amount of information, its LOD-defined elements, or how complete and
reliable it is. Flow-down provisions from a MEP contractor’s contract
from a Construction Manager may also have flow-down references
from the design contracts.
8.2.3 Coordination Morphing into Design
The lack of industry standards and precise definitions for spatial
coordination tasks also increases legal risk because the ambiguity
creates room for Owners, Construction Managers, and Designers to
argue that the contractor’s bid or the contractual language requires
the MEP contractor to do more than the MEP contractor ultimately may
be willing to do. One very important permutation of this issue arises
when a party argues that the MEP contractor actually took on, or is
responsible for, design work. Actual design work is well beyond spatial
coordination, but the lines can get blurred with ease through the use of
certain contract language or as “adjustments” are made in the course
of a project.
You should always be aware of this issue because assuming responsi-
bility for design imposes an array of additional and different obligations
on your firm and increases risk. For example, engineers and design
professionals generally must have a license, and also carry different
insurance; your employees, in attempting to help coordinate a project,
may accidently venture into territories where insurance coverage does
not extend. Your firm’s failure to meet federal, state, or local design-
related requirements may also violate certain laws, as well as your
agreement in the contract to comply with these laws. These breaches
and violations all can result in significant consequences for an unwary
contractor.
To help distinguish coordination from design, the National Institute
of Building Sciences has issued National BIM Standard V2, which notes
that coordination is the implementation of design, but MEP contractors
still must remain mindful that any conduct that trends toward design
work greatly increases legal exposure. For example, some contracts may
require the MEP contractor to provide “design assist” services, which
is a nebulous concept that lurks somewhere between coordination
Achieving Spatial Coordination Through BIM 121
Evaluating Spatial and actual design. Similarly, a request for “value engineering” pushes
Coordination Contract Language the contractor into another area of considerable concern and unclear
boundaries. In an effort to win work, you also may be tempted to send
proposals or scope documents that state your firm can help “to design”
or “engineer” a project or a solution. The use of such words, however,
can have unintended consequences later when a court is forced to
assess what the parties intended when forming the agreement. In this
regard, it is critical to choose your words carefully when addressing such
issues, and make certain to describe tasks as coordination only and to
stop short of hallmarks of true design work. Moreover, once integrated
into the Design Team, you lose the “firewall” that usually exists between
the Owner’s designers and the installing trade contractors, and it is
much harder for you to argue that you installed all items properly and
a defective condition or other issue is tied just to design.
At the very least, you should insist that your Engineers of Record be
involved with, review, and approve any changes or modifications of the
systems as designed that were made to accommodate the constraints
imposed by the multi-trade construction spatial coordination process.
8.2.4 Accepting Contract Administration Responsibilities
Your firm also should seek to understand, before you sign the
contract, whether the other trade contractors and the Construction
Manager’s Project Coordination Manager on the project are knowledge-
able in spatial coordination tasks and BIM. If they are not, this can slow
down the process or cause repeated modeling efforts, which can cost
you time and money.
But perhaps the greater risk of working with unsophisticated parties
is that the more experienced contractor (often the MEP) is often asked
or required to administer the spatial coordination effort for the entire
project or a significant portion thereof. If the individual coordination
leaders or others on the project are computer literate, but lack the
actual trade or social skills necessary to manage an efficient coordina-
tion process, your firm may choose to accept this role and lead the MEP
spatial coordination process for the entire team when you feel that,
despite the added time required for this role, it will be more effective
and efficient to have a streamlined and well-coordinated process.
Although this makes logical sense, you must bear in mind that taking
on this role increases your exposure and legal risk because your firm has
now essentially assumed an administrative role and responsibility for a
portion or the entire spatial coordination product, and may therefore
be liable for delays to or errors in the final product. Such an administra-
tive role also may consume far more time and effort than anticipated if
the other trades truly are unsophisticated or the project experiences a
122 Achieving Spatial Coordination Through BIM
Evaluating Spatial large number of changes. The MEP contractor therefore needs to weigh
Coordination Contract Language these items carefully before taking a lead role in the spatial coordination
process.
Often MEP contractors, by contract or by choice, undertake certain
tasks that by definition encompass the work products of multiple trades,
inclusive of parties not under contract to their firm. The assembly of
composite drawings can be such a responsibility. MEP contractors
should insist that, although they may take on these types of tasks
the responsibility for the accuracy and completeness of the individual
elements of these assemblies remains with the originators and that
any risks associated with such actions remain with the individual
contributing contractors and the General Contractor.
Evaluating Spatial 2. Any requirement for utilization of a modeling software platform that
Coordination Contract Language differs from standards or industry norms. Some Owners or Clients are
looking for an Integrated Model instead of a Federated Model for both
the construction coordination efforts as well as for their project model
deliverables. Most MEP contractors create models within their own
specialized software, which permits their work product to be
“federated” into a viewable model by other model review software.
Having an “integrated model” requirement can impose significant
challenges to how your models must be created, the internal value
of such models and/or how these must be translated into a Client’s
integrated platform.
3. Any language that stipulates that the cost of all materials and instal-
lation needed to accommodate spatial coordination adjustments be
absorbed by the bidding contractors. In the usual Design-Bid-Build
project, the general purpose of construction spatial coordination is to
reduce trade interferences, eliminate rework, optimize construction
sequencing, and enhance prefabrication and installation of components
or systems. The obligation of any Project Participant should be limited
to a requirement that it coordinate its system with those of all other
Participant members in advance of installation.
Spatial coordination is not an acceptable vehicle to impose unreason-
able or unfair duties upon the participants. A requirement such as that
noted above does not differ in any significant way from a requirement
that the MEP contractor accept the risk of unforeseen circumstances or
actions beyond its control that occur during the construction process. If
this type of language appears in any RFP or document, you should take
appropriate actions to remove it, or at least draw a tight box around any
financial exposures that might arise relative to its coordination efforts.
If the scope of work of any individual team member increases
because of the spatial coordination process, then that person should
be entitled to fair compensation under generally accepted practices
and protocols. The MCAA, SMACNA, and NECA Industry Associations
all publish manuals covering such matters.
4. Any requirement that imposes a duty that all project
participants attend an unlimited or unspecified number of spatial
coordination meetings at no additional cost, regardless of quantity
or causation. As with any requirement to attend progress meetings of
any kind, spatial coordination meetings should be limited in number
unless the project team member has failed to meet the obligations for
participating in the spatial coordination process. Having unlimited ac-
cess to a MEP contractor’s spatial coordination and management time
and resources, without regard to the cause or necessity to repeat the
coordination process, is one of the major causes of cost and time budget
overruns in a business.
Achieving Spatial Coordination Through BIM 125
Evaluating Spatial 5. A requirement that every MEP contractor submit models that are
Coordination Contract Language “completely” or “100%” clash free. This is both an LOD and a
“degree of coordination” issue. Even the best model-review software
has built-in clashes where disconnected systems meet. In addition,
certain inconsequential elements of building systems can be placed,
and easily modified as needed, in the field without prior coordination.
It is not practical to expend coordination time and resources modeling
such loose, random, or minor items. The goal of spatial coordination
using BIM is to identify, and eliminate or mitigate, physical interferences
between building systems that would cause undue delay or rework
during construction. A mandate for a “clash free” model can cause
many project coordination programs to degenerate, focusing solely
on getting to zero. Such mandates usually indicate the author’s
inexperience or misunderstanding of how and why these efforts
are being expended.
6. Any requirement for construction models to be delivered in a format
for integration to the building’s facilities management systems.
Single-sentence requirements for this type of deliverable are
written by people who may not understand what they are asking of
the MEP contractor; unfortunately, they are becoming more common.
Any requirement that as-built information be delivered for purposes
other than recording the structure as actually constructed needs to
be spelled out in very precise detail. There are numerous facilities
management software applications but very few, if any, that are fully
integrated with authoring or model-review software platforms. Placing
intelligent components into MEP models so that facilities maintenance
programs can be populated from the same data source can be an
extremely complicated and time-consuming process. More often than
not, achieving such integration is beyond the means and skills of most
MEP detailers.
7. Any requirement for a MEP contractor to waive its rights to
remedies for erroneous information delivered by the Design Team or
third parties. Not long ago, design models were simple 3D renderings
of 2D design drawings. Technology has reversed this process, and
designers now create their drawings from their models. Design models
are, in most cases, just advanced or more developed versions of the
2D design drawings provided to a contractor as a Document of Record
for construction. There are certain industry-wide expectations for the
LOD of the model elements, which can be found in both the AIA and
BIM Forum references. On Design-Bid-Build projects, it should not have
to be the obligation of the MEP contractor to validate that the drawings
126 Achieving Spatial Coordination Through BIM
Evaluating Spatial received from the Design Team exactly match the design models that
Coordination Contract Language also are provided to coordinate the project. However, many specifica-
tions and contracts place the burden of such validation squarely upon
the parties using these models. If there are differences between these
documents, hopefully they are clearly identified in the RFP. Both the
models and the drawings provided by the Design Team should, without
question, be constructible.
A common-sense argument can be made here: if an Owner expects
its project construction team members to engage in a collaborative
process that will result in well-coordinated building systems prior to
construction, then the installation contractors should be able to rely
on the information provided by the Owner or the Design Team for that
purpose. Additionally, spatial coordination is supposed to be a
collaborative process; collaboration does not mean that the risks
of one party’s oversights, errors, or deficient control measures should
be borne by another party.
8. Any requirement for bearing the cost of distribution of drawings to
noncontracted parties. The cost of distribution of 2D drawings
created post-coordination can be substantial on certain projects.
Beyond being a financial burden, however, many times such language
also implies an administrative duty to provide such a distribution in
a timely manner and to all affected parties. This can become a very
complex responsibility. If your firm has been assigned such duties in
the project contract, you should obtain very clear instructions from
your Client as to when, how often, and to whom these distributions
should be delivered.
9. Any language that imposes a requirement to deliver proprietary
information to the Owner, Construction Manager, or other third party.
Many “source files” that MEP contractors use contain proprietary
information that the MEP contractor derives from these files, as well
as specialized component creations that it has spent considerable
funds developing. If an Owner requires delivery of such source files,
you should clarify early on the amount of information you are willing to
provide. In addition, your firm should have a clear “scrubbing protocol”
in place before handing over any source files that might contain such
proprietary information. (For details on scrubbing source files, see
Appendix C on page 156.)
When reviewing project documents, take care to look for clauses that
impose these requirements, and remove them from the contract, edit
them to minimize such risks, or otherwise price the project accordingly.
Achieving Spatial Coordination Through BIM 127
Y
scope can range from solving immediate problems to long-range
ou are a senior executive or perhaps
planning. This IT Implementation Plan is one of the components to
a virtual detailing manager and are
your BIM Implementation Plan. (See Chapter 3, “Building the Team”
responsible for building an IT infrastruc- on page 19.)
ture. You task is to support the require-
The management and maintenance of the databases, drawing files,
ments and work of your virtual detailing software, and hardware has a substantial, ongoing cost, but will yield
and construction project teams. increased profits if done correctly.
Network ID Make and OS RAM CPU Type CPU Hard Drive Installed
(Main user) Model Speed Total/Free Applications
Next, collect the information in Table 9.2 on page 130 for all the
software that is currently installed on your laptops, PCs, and servers.
Physical Inventory
Gather this information for each piece of hardware; include the PCs,
laptops, servers, monitors, printers:
Achieving Spatial Coordination Through BIM 131
Software Inventory
Gather this information for each software application or package in-
stalled on the hardware:
• Application (for example, AutoCAD 2014, Navisworks Manage 2014,
Microsoft Office 2010)
• License number (that is, registration and license details for managing
subscriptions and service)
• Number of users that the license supports
• Support contract Information:
o Start and end dates
o Support phone number
Server Information
Gather this information for each server:
• Operating system
• Administrator login identity and password
• IP address
• Server-installed applications, (for example, Microsoft SQL, Microsoft
Exchange, accounting software)
• Active Directory domain
• DHCP scope
• Drive/partition volume information
Network Information
Create an IP Map that includes this information:
• Static IP device assignments (usually printers)
• Router/firewall information along with user name and password
• For firewalls:
o Support contract information for updates
o Contact information for assistance
132 Achieving Spatial Coordination Through BIM
User Information
Gather this information about your users:
• User name
• Login information for each account that accesses the network
resources (for example, a file server)
• For a small environment, password information, as applicable
• Name of computer used to access the network
• Network resources permitted to access (for example, directories on
the server, printers, and software applications)
Email Information
• Primary and secondary domains
• Anti-spam and anti-virus software, if applicable
• Complete list of all email account addresses, including any generic
addresses such as info@ or sales@ and whether they are configured
as mail forwards or mail aliases.
• Type of mail server (for example, POP3, IMAP, Microsoft Exchange,
Office365, Google Apps for Business)
• Name of Internet service provider
• Name of computer consultant
• Name of web hosting company
• Name and location of internal email system
• Name and location of local file server
Achieving Spatial Coordination Through BIM 133
BIM Technologies for Participant must use computer hardware and equipment that both
an IT Infrastructure supports effective participation in the project and allows the contrac-
tor to adhere to the project schedule and coordination meetings. Some
Execution Plans also require Project Participants to provide, set up, and
maintain computer workstations on site for the duration of the project.
An Execution Plan may also require Project Participants to attend
coordination meetings with laptops capable of making changes or
adjustments to their models during the meeting.
Meeting these requirements always costs more than it first appears,
especially when you have similar requirements for multiple projects.
But purchasing hardware components that meet only the minimum re-
quirements may be a false economy; such equipment soon hampers the
speed and effectiveness of the people who use it, and eventually, of the
coordination process itself. If your IT budget has additional funds, spend
them on the hardware; a PC or laptop that supports high-performance
3D modeling maximizes the productivity of your representative and
the team.
Component Desktop Laptop
Processors 2nd Generation Intel® Core™ 3rd Generation Intel® Core™
i7-3930K (12M) i7-3840QM (8MB
Cache, Overclocked up to 4.1 GHz) Cache, Overclocked up to 3.8 GHz
Operating system Windows® 7 Professional, Windows® 7 Professional,
64Bit, English 64Bit, English
Memory 16GB Quad Channel DDR3 16GB Quad Channel DDR3
at 1600MHz at 1600MHz
Video card 1.25GB GDDR5 NVIDIA® GeForce® 2GB GDDR5 NVIDIA® GeForce®
GTX 560 Ti (OR SIMILAR) GTX 660M (OR SIMILAR)
Hard drive 256GB SATA 6Gb/s Solid State Drive 256GB SATA 6Gb/s Solid State Drive
Networking (server to client) NIC (network interface card) 1Gbps NIC (network interface card) 1Gbps
(Gigabits per second) (Gigabits per second)
BIM Technologies for Each MEP design is unique and created by individuals and design
an IT Infrastructure firms that deliver the work at different points along the spectrum of
completeness. Some Design-Intent Models will contain a great deal
of object data and other models will include very little. In recent years,
design quality in North America has continued to improve, providing
partners with more and more useful object data.
9.4.2 Project Review Software
One important feature of project review (or model review) software
is the capability to aggregate the individual models designed with the
preferred authoring software application of each Project Participant into
a Federated Model. Once all of the models are aggregated, the Project
Team can begin running clash detection across all domains and partici-
pant models. Each software platform of this type offers a unique set of
additional functions. These are your primary options for project review
software:
• Autodesk Navisworks
• Bentley Navigator
• Solibri
• Tekla BIMsightBIMsite
Even though the project and its clash-detection activities are driven
by the Coordination Team and you provide your construction model to
the team via your domain-specific CAD authoring tool, you will need, at
a minimum, one copy of the project review software identified in the
BIM Execution Plan. The purpose is to allow you to perform clash detec-
tion and model review outside the scheduled coordination meetings
while using the same project review platform. The Project Coordination
Manager assumes that you have completed preliminary clash detection
before you submit your model. This practice allows you to identify and
correct the easy and trivial clashes beforehand, leaving only the more
difficult issues to be resolved at meetings. In addition to the software,
you also need to make sure that your firm has an individual in-house
who understands the aggregation process and the project review soft-
ware. This individual should also have some experience with or the skills
to manage documents and multiple models.
9.4.3 Domain- or Trade-Specific Software Applications
Unlike the other types of software, you can choose the applications
specific to your trade, based on your needs and requirements and the
functionality and capabilities the software provides. All that the Project
Team requires is that your domain-specific software can be used in all
of the Coordination Team software. These are the common domain
authoring and estimating tools:
Achieving Spatial Coordination Through BIM 137
Fire Protection
• AutoSprink
• Fireacad
• HydraCAD
• Sprinkcad
BIM Technologies for There are two types of cloud-based software applications. The first
an IT Infrastructure type provides additional data storage and file backup services over the
web and outside your company’s network. The second type represents
user-based applications that your company does not own or install.
These applications provide one or more software services and run over
a set of redundant servers owned by a service company that manages
the application’s delivery to you and to other users. One of the major
benefits of this type of software is that you no longer keep your files
on a jump drive or on any of the computers you use. The files are now
stored and accessed from an Internet server and accessed through a
browser window. The only part of the application that runs on your
computer is through a browser, for example, Internet Explorer, Google
Chrome, or Safari. The application runs exceptionally fast and is not
constrained by the hardware configuration or limitations of your PC,
laptop, or tablet. Typically, these applications are affordably priced and
require minimal system administration, which is ideal for most small
MEP companies.
This type of software offers many benefits:
• All of the system management functions such as software updates,
backups, downtime, hardware issues are handled by the provider; the
software runs in a redundant network of servers so if one server goes
down another takes over with no loss of data.
• Less expensive because you pay only for what you use
• No downtime
• Access data from any location where you have an Internet connection
• Offers more collaboration functions and capabilities
• Supports multi-team and multi-site requirement
• Facilitates better communications between the field and the shop
• Centralized information distribution and sharing (specific to orders,
archives, construction documentation, document management, time
cards, delivery and construction schedules)
• Standardized ordering
• Many SaaS applications support full collaboration, in other words,
multiple people can work on the same file at the same time
(for example, Google Docs)
• Lower downtime and support costs
• Reduction of human errors via digital orders and invoices
• Better cash flow via faster and more accurate invoicing and costing
• Faster roll-out of new services and tools
140 Achieving Spatial Coordination Through BIM
BIM Technologies for The list that follows includes a few of the options you might consider
an IT Infrastructure for cloud applications. Some are exclusively used for storage and system
management (backing up your critical models and files); others pro-
vide an array of collaboration and communications services. The most
important benefit of these software applications is that users can get to
whatever data they need anytime and anywhere (providing they have
access to the Internet, which in some projects is not always the case.)
a. BIM 360 glue
b. BIM 360 field
c. GlobalScape
d. Gmail
e. Google Docs
f. Gotomeeting
g. Hightail
h. Microsoft Lync
i. Microsoft OneNote
j. Office 2010
k. ShareFile
l. SharePoint
m. Webex
BIM Technologies for Do some careful analysis of the initial cost, associated annual sub-
an IT Infrastructure scription, and stand-alone versus network licensing. In terms of network
licensing (more expensive) versus stand-alone licensing (less expensive),
the general rule of thumb is that network licensing presents a better
return on investment when you have a large number of users (more
than 8) who use the application on a daily basis. This is the case because
the number of total users who require access to the application on any
specific day or time will never equal the total number of your firm’s
users and, therefore, you can purchase fewer network licenses. Another
advantage of network licensing is that it makes system management
and the software upgrading process much easier to manage.
BIM Technologies for Because he went home late (doing the install the evening before) he
an IT Infrastructure arrived at the office 30 minutes late in the morning. A circle of detailers
were standing around the office of the Lead Detailer. Joe walked up and
asked what the meeting was about. They all turned to him and said
that when each of them opened their drawings that morning, the
CAD authoring tool displayed a message: “Your SQL database has been
updated, do you want the new database?” Each answered yes. The
application repopulated the objects on their drawings and every single
object had moved. When the Lead Detailer opened the current team
Federated Model, the same thing happened. And no one could open up
any of their old drawings. Two calendar days and seven days of actual
work were lost. Weekly backups were scheduled to run the day the
problem was discovered.
This has happened many times, with different applications and for
different reasons, but it doesn’t have to happen. There are measures
and precautions that should be brought to the attention to the person
responsible for IT. And this is first question: Do we need to upgrade the
application?
The rule of thumb is never upgrade from a version of any software
application in the middle of a project, unless you absolutely have to.
And yet, in some situations, an upgrade might be your best option.
• The new version includes functionality that will greatly reduce the
burden, workload, or expense of at least one of your construction
departments.
• The upgrade fixes a known bug that is contributing to errors and ex-
pense in your workflow, construction documentation, prefabrication
and fabrication MTOs (material take-offs/BOMs ) and downloads to
CNC machines.
• The communication between you and others on the Project Team is
broken and the upgrade will greatly improve collaboration, the shar-
ing of models, and the exchange of data
There are a few other benefits to upgrading:
• The project will run more smoothly, with fewer system performance
issues.
• There will be minimal to no disruption of service through the
lifecycle of the project.
• The project team will have more confidence in project plans,
schedules, and deliverables.
• You will have more confidence in your workflow and the quality
of the finished product.
Achieving Spatial Coordination Through BIM 143
BIM Technologies for At the beginning of a new project, if you are responsible for your
an IT Infrastructure firm’s virtual detailing, make sure that when different departments
(that is, plumbing, sheet metal, and so on) share the same domain-
specific application that each department runs it separately. This allows
you to update, or not, the software based on the benefits and need of
each individual detailing department and this allows you to update the
software application for one of your detailing departments while not
creating a problem or issues for another. If this is the framework of your
IT infrastructure, you are diversifying your risk. Each MEP domain in your
business uses, to some degree, different aspects of the same software
application. A great reason to upgrade for one department may create
problems and risk for another. If each domain’s software applications
are separated, you are less exposed and better able to support the
individual requirements of each of your MEP departments.
9.6.1 Preparing for an Upgrade
Begin with research. First, search the web for issues pertaining to the
software you want to upgrade. These issues might be posted by the
software publisher or by its users; many publishers provide blogs and
free technical Q&A. Depending on the kind of license you have, you
may be able to contact the software publisher directly for unlimited
telephone support. Do both, but make sure you have current market
knowledge of what to expect from the installation process and later,
the interoperability with other software applications.
Next, test the upgrade independently, but not on the production
server. Never install untested software on your firm’s data, communica-
tion, or application server, all of which may be installed on the same
machine. Instead, find a PC or workstation whose installed software
environment represents the environment used by the team and take
it off the network.
Make a “ghost” image of that environment on a drive. “Ghost” soft-
ware is a disk-cloning application that’s an excellent tool when you need
to replicate complete running software environments. Building a clone
testing system will save time if you have to re-create a copy of every-
thing running on a computer. Now, install the upgrade and start testing.
What do you test for? You test the basic functions of every critical
software tool that the Project Team uses to complete its work. You open
files, add elements to them, or perform the operations of the tool you
are upgrading. Save these files and close them; then open them. If you
see what you expect to see and become confident that the upgrade will
have no impact, install the upgrade on your production server.
144 Achieving Spatial Coordination Through BIM
BIM Technologies for 9.7 Making the Right Decision for Your Firm
an IT Infrastructure
Making the right decision about the software to purchase requires a
team effort of due diligence, market research, and product evaluation
specific to the needs of your firm. As you evaluate your options,
consider also that the management and maintenance of the databases,
drawing files, software and hardware has a substantial, ongoing cost,
but will yield increased profits if done correctly.
9.7 Making the Right Deci- To make it easier consider the following process:
sion for Your Firm
Step 1: Build your firm’s IT Implementation Plan.
Prepare your IT Implementation plan, including your IT inventory of
hardware and software.
BIM Technologies for Step 5: Review all of the data and make a decision, acquire
an IT Infrastructure software and begin training.
Review what you learned from the product demonstration, from
conversations with users, and comments in technology blogs about the
product and the publisher. Determine how well the application matches
your requirements and how accommodating the licensing and pricing is
compared to other solutions. Then, choose the application that best fits
your needs.
Achieving Spatial Coordination Through BIM 147
The most prodigious and active contributor from the start (long
before me) to where we are today with the official release of the GUIDE
and the person I owe the most appreciation to for the depth of his input
F unny thing about asking industry and his draft editorial reviews of each chapter and for every one of the
Acknowledgements three major reviews is Steve Shirley, CEO of University Mechanical and
professionals to band together to
Engineering Contractors in El Cajon, California. The Guide was originally
create something that will literally envisioned by Steve as the Chair of the MCAA BIM committee more
help their industry become more than two years ago. He has been one of the earliest MEP pioneers in
skilled. While showcasing their personal the use of BIM and other technology-based solutions to enhance his
professionalism, folks from competing company’s operations and profitability.
companies gave this project time The Mechanical Contractors Association of America (MCAA) fielded
and devotion that I could never have great professional team I received much help from Richard Anderson,
obtained elsewhere. To say I thank John Attebury, Michael P. Cannistraro, Rod Foley, Mike Feutz, Dan Lovell,
these volunteers and honor them is an Pete Mackenzie, Frank D. Musica, Brian J. Muggy, Ian O’Doherty,
Al Prowse, Steve Shirley, and Stacy Zerr.
understatement. To say that the industry
owes them a debt it can’t repay is To the powerhouse of professionals from the National Electrical
a humbling truth. Contractors Association (NECA), I am grateful to Josh Brill, Craig Clark,
Denis St. Pierre, Adam Davis, Bryan Inglish, Dan Maimonis, and Joseph
Vernice for casting helpful light in some of the dark corners of this
subject.
Last, but not least (and they still take up the most LOD space) are the
professionals from the Sheet Metal and Air Conditioning Contractors
National Association (SMACNA). Paul J. Alexander, Matt Cramer, Richard
Freeman and Steve Hunt shared their many lessons and best practices
from their engagements with BIM.
The consistent dedication of three MEP contributors filled this Guide
with many practical ideas. They spent countless hours in meetings with
me and reviewing many drafts. Pete Mackenzie, a well-recognized
trainer in BIM on behalf of MCAA, made significant contributions and
was the only task force member who actively participated in almost
every chapter committee meeting. On the electrical side (NECA),
Josh Brill brought great insight and showed me how the concerns of
his discipline are the same and also different. My debt to the sheet
metal industry (SMACNA) for Steve Hunt and his willingness to help
the industry take this giant leap forward, raising the awareness and
capabilities of tradesmen, is probably larger than I can repay.
Special thanks to David Francis, MEP Chairman to the BIM Forum
LOD Specification, for helping me understand how the LOD specification
is being understood and used in the field and for his continued
representation and support of the MEP contractor in all of his open
standards efforts.
148 Achieving Spatial Coordination Through BIM
ACKNOWLEDGEMENTS Joe Perraton at Pointone Media, who shared his many ideas for
how cloud-based software applications can decrease MEP contractor
expenses while improving collaborative processes, filled some large
gaps in my knowledge.
My predecessor, Michael Tardiff, who started the project one year ago
had other demands to meet, and he graciously passed the project me.
His willingness to share all that he had learned (quite a lot) in the short
time he spent with the project got me off on the right foot.
I also want to recognize the excellent work that the Guide’s
editor, Susan Hunziker, and the graphic designer, Cyndi Carr of
Visual Persuasion, LLC, brought to the effort. Their unique skills
and special touch helped to make this document a product the three
MEP associations will be proud of.
I am deeply indebted to the association directors— Dennis Langley
of MCAA, Tom Soles of SMACNA , and Dan Walter of NECA. Their
unequivocal support and their unfettered access made this book
possible and far better than it could have been. They made sure that
I had direction, content, and examples from the top professionals in
each of their associations.
Three organizations were willing to put their money where their
mouths are. MCERF, The New Horizons Foundation, and the NECA
believed in the need for this Guide and provided the funds to bring
their shared vision to reality. I believe that in time, their desire to serve
a greater good by raising the knowledge and skills of the entire MEP
and specialty contractor segment of the construction industry will
create new opportunities for all.
Achieving Spatial Coordination Through BIM 149
THE APPENDIXES all those systems and components that have been modeled, you
may not interfere or obstruct with the installation of modeled
components, and after that it’s first come, first served. In short,
you have to get in around every system that was modeled.
Achieving Spatial Coordination Through BIM 153
Software publishers
Design Platform Software
Autodesk— http://www.autodesk.com
AutoCAD
AutoCAD MEP
Architectural Desktop
Revit MEP
Bentley—http://www.bentley.com
AECOsim Building Designer
Graphisoft —http://www.graphisoft.com
Archicad
Trimble—http://mep.trimble.com/products
Trimble Pipe Designer 3D
Trimble Duct Designer 3D
Trimble Accubid Enterprise Estimating
Trimble AutoBid Mechanical
Trimble AutoBid Sheetmetal
Vulcan – Sheet Metal CAM cutting software
MetaLab—http://www.practicad.com/
PractiCAM: a sheet metal manufacturing and estimating solution
PractiCAD: a design, drafting, and detailing tool for the HVAC and
sheet metal industries. AutoCAD-driven
Drawtech—http://drawtech.com/
Drawtech 7
Drawtech CAM
162 Achieving Spatial Coordination Through BIM
Shopdata—http://www.shopdata.com/
Quickduct CAD
Quickduct CAM
Intellicad—http://www.intellicad.org/
IntelliCAD 7
SYSque—http://sysque.net/
Pipe and Duct design and fabrication inside Revit MEP
Fire protection
Fireacad—http://www.fireacad.com/index.htm
HydraCAD—http://www.hydratecinc.com/
AutoSprink—http://www.autosprink.com/
Sprinkcad—https://www.sprinkcad.com/
Industry Resources
Trade Associations
MCAA—http://www.mcaa.org
SMACNA—http://www.smacna.org
NECA—http://www.necanet.org
National Institute of Building Sciences
National Institute of Building Sciences—http://www.nibs.org/
N
ational BIM Standard – United States V2—
http://www.nationalbimstandard.org/
JBIM - Journal of Building Information Modeling—
http://www.wbdg.org/references/jbim.php
163 Achieving Spatial Coordination Through BIM
BIM Forum
AGC BIM Resources—
http://bimforum.org/resources/agc-bim-resources/ JBIM - Journal of
BIM Tools Matrix—http://bimforum.org/wp-content/up-
loads/2011/02/BIM_Tools_Matrix.pdf
B
uilding Information Modeling—
http://www.wbdg.org/references/jbim.php
Contract language
ConsensusDocs—https://www.consensusdocs.org/
Other resources
A
IA Document E202 – BIM Level of Development
http://www.aia.org/contractdocs/training/bim/aias078742
CAD Authoring
Software A computer application used to depict the physical
appearance and properties of objects included in a
building or building system. Also known as detailing
software.
165 Achieving Spatial Coordination Through BIM
GLOSSARY Communications
Protocols A particular way of storing and organizing data in a
computer and in software applications so that people
and other applications can be easily access and share
the data.
CNC
machining A process used in manufacturing sheet metal or pipe
in which computers are used to control machine
tools. CNC stands for Computer Numerical Control.
Under CNC Machining, shop and fabrication machine
tools function through numerical control.
Domain-specific CAD authoring tools contain a library
of virtual objects. Every object maintains its unique
geometry and attributes, which represent how it is
to be manufactured, using an industry standard
information exchange called G-Code. G-Code
controls exact positioning and velocity of the tool.
Design-Bid-
Build A method of project delivery in which the Owner
procures a design and bid package from a designer
and solicits independent bids for the construction
of the building.
Design
consultant A
n engineer on a construction project who is
responsible for performing and overseeing the
design of structural, mechanical, electrical, HVAC,
and fire protection systems.
Achieving Spatial Coordination Through BIM 166
Digital
sign-off A mathematical key in a document file that, when
selected by an authorized individual, constitutes a
legally binding signature of an individual or company.
Disruptive
innovation A product or service that creates a new market
and value chain, eventually displacing an earlier
technology and the processes that depended on or
supported it. The term is used to describe changes
to a product or service in ways that the market does
not expect.
Federated
Model The Design-Intent Model that is extended by
aggregating multiple models. Each model represents
the work of different domains and the Coordination
Team. A Federated Model is typically aggregated and
viewed with project review software.
Federated
Construction-Only
Model A variant of the Federated Model that stops at
construction LOD 400 when there is no contractual
obligation to supply any further deliverables to the
Owner.
File-naming
conventions A set of rules for constructing unique and descriptive
names for digital files. The rules specify the order and
the length of words, phrases, or abbreviations used in
the name.
GLOSSARY Information
exchange Digital data that is passed from one party to another
in the BIM process. The parties involved have agreed
upon and understand what information will be
exchanged.
Integrated
Model The Design-Intent Model that is extended by all
Project Participants, who are using the same software
platform to design and detail it in all phases of the
project lifecycle.
Inter-
Operability The exchange of information between software
applications, between people, and between people
and a software application by direct communication
without interference.
GLOSSARY Modified
Federated
Model A variant of the Federated Model in which the models
of building systems produced by MEP contractors are
integrated into the Design-Intent Model by the
Design Team.
Open
Standards Non-proprietary protocols and data structures that
support the exchange of digital data and information
across domains, people, and software applications.
Project review
software A software application platform that provides the
tools that Coordination Teams use to coordinate their
system designs, resolve conflicts between domains,
and plan projects prior to construction or renovation.
Quantity
take-off To count, measure, and extract any or all of the
identified elements contained in a 3D model.
Schedule A
sequence of activities that are based on a
construction plan and represent decisions by the
Construction Manager, General Contractor, or
Coordination Team.