The Use of Asphalt in Hydraulic Engineering 1 PDF
The Use of Asphalt in Hydraulic Engineering 1 PDF
BY
TECHNICAL ADVISORY COMMITTEE ON WATERDEFENCES
Use
The use of asphalt in hydraulic engineering / Technical advisory committee on water-
defences ; Rijkswaterstaat. - The Hague : Rijkswaterstaat, 1985. - 308 p. : app., ill. ; 24
a great contribution to this. In January 1984 the guidelines completed and now, one year
Bibliogr. : p. 225.
Preface
Asphalt products have been used in the Netherlands in hydra uIie engineering for a long
time on a large scale, especially after the great disaster in 1953 when a large part of
western Holland was flooded by the sea. After the disaster a great number of dikes had to
be repaircd very quickly and this was possible with the use of asphalt as arevetment
material. Asphalt could be placed much faster thcn thc materials most cornrnonly uscd in
those days. Further more asphalt is; when desired, more watertight than clay which is
also scarce. Except for bitumen no foreign construction materials are necessary.
SkilI, experience and knowledge were only slightly available in those days and had to be
gained in the course of time. After some years it was thought useful that directives or
recommendations were available. A first attempt to achicve this was made by the
Working Group for Sealed Revetmcnts who finished its work in 1961 with thc
'Preliminary Report'. In 1979 the Technical Advisory Committee on Waterdefences
decided to create new dircctivcs for the use of asphalt in hydraulics. The time was
thought right because of the great developments and knowledge obtained since 1961.
The building of the Delta Works including the Eastcrn Scheldt Storm Surge B~rrier was
a great contribution to this. In January 1984 the guidelines cornpletcd and now, one year
later, .an English translation is published.
The guidelines werc written for Dutch purposes. This means that mostly applications to
dikes, breakwaters and bed protections are csmsidered. Other types as for instanee
reservoir and dam applications are only mentioned without specific details.
Also, reference is made to Dutch standards and directives only. Despite these aspects
these guidelines wiII certainly contribute to a better design, execution, management and
maintcnance for hydraulic asphalt constructions, not only in the Netherlands but also in
other countries, the reason for the translation into the English language.
The translation, which was made possible by the Dutch Ministery of Public Works and
3
Bitumarin B.V., was done by B. Wade. Many thanks to Dr. P. C. Barber (Ceemaid
Serviced Ltd.), C. Davies (MetropolitanBorough of Wirral), Hydraulic Research Ltd.,
J. Harrison (Bitumarinc Ltd.), D. D.. Davidsen (CERC-WES, Vicksburg, MS), Ir.
J. P. J. van der Heide (The Association of Dutch Asphalt Contractors) and Ir. J. A. van
Herpen (Oranjewoud Engineering Consultants) for their contribution and rcmarks. Last
but not least mrs. D. van Eerd and mrs. W. Verhoeven should be mentioned.
I am convineed that these guidelines will help you to a better use of asphalt in hydraulic
engineering.
4
Contents
page
Preface 3
o Introduction . 15
0.1 Format for guidclines ' . 15
0.2 Organization . 16
0.3 Thc tasks and working methods ofWorking-Group 4A . 18
0.4 Recommendations for the future . 19
0.5 Investigations : . 20
3 Bitumen. 30
4 Additives . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 34
5 Mix composition 35
6 Mix properties 36
6.1 General '.. 36
6.2 The degree of permeability . . . . . . . . . . . . . . . .. .. . . . . . . . . . . . 36
6.3 Mechanical properties . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 36
6.3.1 The stiffness modulus 37
6.3.2 The struin at break. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 41
6.3.3 Permanent visco us deformation . . . . . . . . . . . . . . . . . . . . . . . . . . A3
6.3.4 The Poisson-ratio . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . 44
6.3.5 Tcmperature sensitivity . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 44
6.4 Stability .'. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
6.4.1 Stability of the asphalt : ,.. 45
6.4.2 Stability ofthe revetment as a who Ie . .. . . . .. . . . .. . . . . . . .. . 45
6.5 Durability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 45
6.5.1 Aging................................................ 45
6.5.2 'Stripping' . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
6.5.3 Resistance to erosion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 46
6.5.4 Biological resistance 46
6.5.5 Chemical damage , 48
6.5.6 Other forms of damage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 49
6.6 Workability 49
6.7 Environmcntal aspects 51
10 Asphalt mastie ~. . . . . . . . . . . . 68
10.1 Basic materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 68
10.U Sand 68
10.1.2 Filler 68
10.1.3 Bitumen 68
10.1.4 Other constituents 68
10.2 Mixes. . . . . .. . .. . .. . . 68
10.2.1 Mix-design 68
10.2.2 Mix-design tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 70
10.3 Mix properties 71
10.3.1 Viscosity 71
10.3.2 Mechanical properties ; .. . . . 74
10.3.3 Permeability . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 74
10.3.4 Durability . . . . . . . . . . . . . . ... . . . . . .. . . . .. . .. . . . . .. . . . .. . 74
11 Grouting mortars . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 75
IU Basic materials '. . . . . . . . . . . . 76
II.U Sand, filler, bitumen.. . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . 76
11.1.2 Gravel, crushed stone ........... 76
11.1.3 Other constructional aspects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 76
11.2 Mixes. 76
11.2.1 Mix-design 76
11.2.2 Mix-design tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 78
11.3 Mix properties .... ~. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
11.3.1 Stability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
11.3.2 Viscosity '.' . . . . . . . 79
11.3.3 Permeability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
11.3.4 Durability . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 79
23 Mastic... .. .. . 167
23.1 Production 167
23.1.1 The mixing-plant. ..................................... 167
23.1.2 Storage of building materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . 167
23.1.3 Mixing time and temperature . . . . . . . . . . . . . . . . . . . . . . . . . . . . 167
23.1.4 Mix storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 167
23.2 Transport ;............... 167
23.2.1 Means of transport 167
23.2.2 Onsite storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 167
23.3 Application . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 168
23.3.1 Application techniques .... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 168
23.3.2 .
Application temperature . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . 169
24 Grouting mortars . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 170
24.1 Production 170
24.1.1 The mixing-plant . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 170
24.1.2 Storage of building materials . . . . . . . . . . . . . . . . . . . . . . . . . . . . 170
24.1.3 Mixing time and temperaturcs . . . . . . . . . . . . . . . . . . . . . . . . . . . 170
24.1.4 Mix storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 170
24.2 Transport 170
24.2.1 Means of transport :...................... 170
24.2.2 Onsite storage . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 170
24.3 Application . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 171
24.3.1 Application techniques :.............. 171
24.3.2 Application temperature ................................ 173
These guidelines are intended for persons and organizations who wish to inform
themselves about the use of asphalt in hydraulic engineering. Designers, asphalt tech-
nologists, managers, government officials and con tractors will find the information they
need in these guidelines. The general form ofthe guidelines is such that they can also be
used as teaching material.
Originally the subject of the guidelines was the use of asphalt produets as a dike
revetment material. Although this aspect is still covered, in fact the final version has a
much wider scope and includes, namely, all hydraulic engineering applications of
asphalt mixes under Dutch conditions. The title now is, therefore, more suitably 'The use
ofasphalt in hydraulic engineering'. ,
As the title suggests the reader is guided through all aspects invO'lved in the application of
asphalt mixes in hydraulic engineering. lt gives guidelines, design methods, background
information and recommendations. Absolute specifications are not given. Similarly
tender specifications have not been included. For the latter reference should be made to
the work of the Dutch Foundation for Rationalization and Automatization in Road
Construction (RA W), which also publishes standard tender specifications for several
kinds ofhydraulic works, including bituminous applications.
The guidelines are divided into several parts, each comprising a separate topic:
Part A 'Composition and properties of asphalt mixes'. This part deals with the general
technology of the asphalt mixes used in hydraulic engineering. The object is to provide
knowledge and insight into the subject and to give the basic information needed for the
other parts. Material parameters, used in Part C, are also presented here.
Part B 'Material technology'. The asphalt mix types most commonly used in hydraulic
engineering are discussed and evaluated specifically in this part. The subjects covered
include the basic materiais, the way in which the mix composition is decided, the ne-
cessary mix design tests and the mix properties.
15
Part C 'Technical aspects of the design'. This part deals with functional requirements,
the starting points and the loads which develop on and in the material, rclated to the
design ofhydraulic engineering asphalt constructions. Design methods are also discussed
here.
Part D 'Exccution', Execution of the work is considered, for each type of asphalt, sub-
divided into production, transport and placing,
Part E 'Management and Maintcnancc'. This part deals with the management and
maintenance of asphalt revetments. Methods of repair are given after a discussion about
the causes, tracing and prevention of the various types of damage which can occur.
In appendices the theoretical backgrounds to several parts of the guidclines and the
development of design models are given. .
Subdivision of the directives between the several aspccts, is uscd to make the subject
more generally easy to grasp and apply. For practical purposes, however, a subdivision
into material technology, design aspects, execution, management and maintenance
°
might be desirabie per mixtype. A separate table, Table (page 21) had, therefore, been
included in which the mixes are given, directly related to the areas ofapplication. If, for
cxample, only one particular mix type is being considered then it is only necessary to
consult those sections ofthe guidelines indicated in the relevant column of'thc tabie.
0.2 Organlzation
16
As of Ist January, 1981, Ir. J. A. van Herpen was appointed as project leader to
coordinate the work involved and to write the guidelines.
At the time ofpublication (ofthe Dutch version) ofthe guidelines the Working-Groups
were composed as follows: .
On Ist April 1983, Ir. W. J. Heijnen (Delft Soil Mechanics laboratory) and Ing. J. T. de
Vries (Netherlands Water Defences Research Centre) resigncd from the Working- .
Group.
17
Centre) was replaced by Ir. E. H. Ebbens of the same organization and on lûth Sep-
tember 1981, Ing. K. A. C. Mouw (State Delta Works Department) was replaced by Ing.
K. A. van den Hoek. On 25th May 1982, Ing. J. J. van der Plas (The Association ofDutch
Asphalt Contractors) rcsigned in faveur ofIr. J. P. J. van'der Heide and on 26st Juli 1982,
Ir. W. Bandsma (State Road Engineering Department), resigned in favour ofH. J. A. J.
Gruis.
On the resignation ofIng. J. T. de Vries on lst April 1983 (Netherlands Water Defences
Research Centre) the duties of secretary were taken over by Ir. J. A. van Herpen.
In order to realise the directives in a reasonable time a project leader was appointed for a
3 ycar period, beginning lst January 198 I. With thc help ofsome ofthe mcmbcrs ofthe
Working-Group a programme was dr~wn up listing all the aspects ofthe application of
asphalt in hydraulic engineering. Thc first step was to assembie all available information
and then for each type of asphalt a subdivision was made into design methods, material
technology, execution and maintenance.
After the data had been collected an attempt was made to formulate practical rul es for
designing asphalt revetments. This information was then presented in an interim report
to future users - principally dike managers - and members of Working-Group 4, for
comments.
The 'Wave problems on Dikes' and 'Water Movements in Dikes' Working-Groups 1 and
2 of TA Wand also specialists from the Delft Soils Laboratory and the State Road
Engineering Department were consulted on certain aspects.
The guidelines were eventually, drawn up on the basisofthe information obtained and a
draft was presented to the various groups mentioned above for further comment.
Results of research executed by'Working-Group 4A have been used in the guidelines.
This research is discussed further at the end of th is introduction.
18
0.4 Recommendations for the future
During the preparation of the guidelines it became apparent that, for various reasons, it
is possible to improve the present methods of application of asphalt in hydraulic engin-
eering. A number ofrecommendations are therefore given below to assist in future work
of research and development in this field.
Recommendations:
19
OS Investigations
Results, already available from the above investigations, have been included in the
guidelines. Results still to come will be published and will be included within revised
editions of these guidelines.
It should be noted that the above investigations will not cover all the points
recommended for study, and some thought should be given to the remaining aspects for
which information is required. .
20
Table 0 Guideline reference table - The table relates the varia us uses of asphalt in hydraulic
engineering to chapter and paragraph readings for the various mate rial types.
mlx type
grouting lean sand
mortars asphalt
asphal- dense open core
tic mas- ruil) pattem stone- stone mate-
concrete tic grouting grouung avphalt asphatt rial 1,])('["') membranes
Part B basic materialv 9.1 10.1 11.1 12.1 IJ. I 14.1 15.1
Mate-
milt de s Ign 9.2.1 10.2.1 11.2.1 12.2.1 13.2.1 14.2.1 15.2.1
rial
Feehno- mi, de sign tests 9.2.2 10.2.2 11.2.2 12.2.2 13.2.2 14.2.2 15.2.2
lcgy
mie properties 9.3 10.3 11.3 12.3 13.3 14.3 15.3
Pafte devigning a dense
Feehui- avphalt revetment
cal against hydraulic
design uplift pre'iosureo; 20.1 20.1 20.1 20.1 20.1
designing a plate
type a sphalt tevetment app.
against wa ....e impacts 20.2 20.2 20.2 20.1 2u.2 VI 20.2.2
designing under-
w ater bed protee-
tion again ..t upbf't
by waves and
currents 20.3 20.3 20.3 203 20.3
de..igning a 100..('
element re..etment
against w .1,,(' auack 20.4
devigning art a sphalt
revetment against
cutrent 20.5 20.5 20.5 20.5 20.5 20.5 20.5
designing an asphalt
revetrnent agamst
senlement end
scouting 20.6 20.6 206 206 206 206 206
determination of the
maximum slope 20.7 20.7 20.7 20.7 20.7 20.7 20.7
ether 'Ioads' 19.3 19.3 19.3 19.3 19.3 19.3 19.3
Part [) production 22.1 23.1 24.1 25.1 26.1 27.1 28.2
Exe ..
transport 22.2 23.2 24.2 25.2 26.2 27.2 28.3
cunon
placing 22.3 23.3 24.3 25.3 26.3 27.3 29.2
joints. 29.2 29.2 29.2 29.2 29.2 29.2 29.2
c
bet .....een dif-
ferent mate-
't'"' dali 29.3 29.3 29.3 29.3 29.3 29.3 29.3
"Q
21
PART A
Part A deals with the general aspects ofthe composition and properties ofasphalt mixes
which are important in thcir application to hydraulic structures. Thc object of Part A, is
to introduce the subject to the reader and enlighten him, making thc manual more easy to
read, and also to present data about the materials which are relevantto Part C which
deals with design techniques. .
Part A comprises:
A discussion of the individual components of asphalt and their influencc on thc
material as a wholc, Attention is paid to those mix properties which are most
important to hydraulic engineering.
A review of the most frequently used asphalt mixture types in hydraulic structures
and how these types are applicd.
Finally, a discussion of quality con trol including mix-design tests, construction con-
trols and completion checks prior to hunding over thc work to the Client. Included
here is a discussion ofthe way in which samples are taken.
24
1 Mix considerations
bitumen;
mineral aggregate;
additives, if required.
The mineral aggregate is composed ofcrushed stone, gravel, sand or filler or a combin-
ation.
The choice ofthe most suitable composition for a particular application depends mainly
on the requirements which the material has to meet and the associated mix properties,
see Section 6.1.
The mix properties are specified by the composition, th at is, the relative proportions of
the various components, the properties ofthe components themselves, and the properties
which result from the application andcompaction method.
The mine ral aggregate mix contains voids. Initially, the bitumen coats and binds the
various aggregate components together. Ifmore bitumen is applied than is necessary for
coating and binding then the pores will gradually be filled.
Mixes, in which the bitumen only serves as a binder, are referred to as 'underfilled'
mixes, sec Figure 1.1a. The properties of such a mix are directly related to the properties
of the stone skeleton (4). If the proportion of bitumen is increased the voids in the
mineral become filled and the inf1uence of the bitumen on the properties of the mix is
increased while that of the stone skeleton is reduced. With mixes in which the pores are
almost filled with bitumen, sec Figure l.lb, both the stone skeleton and the bitumen
contribute to the mix properties. This type of mix must be compacted, either
mechanically or under its own weight.
'Overfilled' mixtures are those in which the volume ofbitumen is greater than th at ofthe
voids in the mineral aggregate. In such a mix the properties ofthe bitumen predominatc,
the mine ral providing only a certain amount of stiffening, see Figure l.lc. This type of
mix is impermeable and requires na compaction.
25
a- underfilled mix b- intermediate filling c- overfilled mix
_ bitumen E?ZZI mineral aggregate 0 voids
The term 'voids' refers to the volume of pores in the compacted asphalt (5). The voids
ratio, VIM (voids in mix), is given by:
d -d
VIM = 100( ma) vol %
dm
density of the mix without voids (kg/rn'')
density of the mix with voids (kg/rn ')
In general, the smaller the voids ratio (HR) the more resistant is the mix to crosion and
the grcater its durability, A mix with a small voids ratio is better 'sealed' against external
inf1uences such as oxygen, light and water. If'water pcnetrates between the bitumen and
the mineral (through the matcrial) there is a 1055 of adhesion which is rcferred to as
'stripping' .
Exposure to the atmosphere and light ages the bitumen. In this respect, the size of in-
dividual pores and dogree ofinterconncction between voids are also important.
The voids ratio and the distribution of voids also determine whether or not thc mix is
sand and watertight. Although water impcrmcability is not always a functional rcquire-
ment it gives a good indiention of the durability of a mix.
To illustrate:
A mix containing sand with 5%, by rnass, of bitumen anda voids ratio of 25% is
sand-tight, A mix, however, of open stone asphalt with 80%, by mass, of stone and
20%, by mass, of mastic with the same voids ratio is not.
An asphaltic concrete with a voids ratio of 3% can be considercd as absolutely
watertight. In th is case the voids are not interconnected. For the sarnc reasens a
mastic with the relatively large voids ratio of 10% is also watcrtight.
26
2 The mineral aggregate
2.1 General
It is important that there is good adhesion between the bitumen and the mineral
aggregate. There are two kinds of adhesion:
l. Physical adliesion:
This type of adhesion is better if the surface of the mineral aggregate is rough.
2. Chcmical adhesion:
Since bitumen is weakly acidic, better adhesion is obtained with mineral aggregates
which are slightly basic. This property is generally to be found with minerals which
contain a limited amount ofsilica oxide.
It is also very important that dry aggregate is used.
A low voids ratio is ensured in an asphalt mix which is not overfilled by adjusting the
coarse fraction in relation to the sand fraction and by using a well-graded mineral
aggregate: the spaces between the larger particles are then filled by the smaller.
Increasing the fillcr fraction, provided that it does not expand the sand/-stone skeleton,
can produce greater internal stability, Tbe internal stability oftbe material in place can
also bc increased by using an angular material instead of round, for example crushed
stone instead of gravel, crushed sand instead of natural sand.
Tbc quantity of bitumen needed to bind the mineral aggregate depends on the specific
aggregate surface. The specific surface is inversely proportional to the second power of
the partiele diameter.
Mineral aggregate can be subdivided according, to grain size. In the Netherlands the
following terminology is used:
stone fraction, larger than 2 mm;
sand fraction, between 2 mm and 63 firn;
filler fraction, smaller than 63 firn.
The stone fraction comprises crushed stone, that is a rough broken material, or a smooth
round material such as gravel.
Crushed stone and gravel must be able to withstand impact and abrasion during mixing
and compaction. This property depends on:
partiele shape; cubes are the best;
- the strength ofthe mate rial.
27
Angular mate rial has a higher interloeking strength.
The maximum particIe size in an asphalt mix is related to Iayer thiekness and the
production and working mcthods. Generally a large grain size gives better stability but
reduces workability. In addition the danger of segregation is greater. For the stone
properties requircd, reference should be made to the Dutch specifications, Eisen 1978
(6).
Natural sand, crushed sand or a mixture ofboth are used for bituminous mixes. The sand
grain size distribution plays an important part in stability, voids ratio and the binder
requirements for a mix -.Sometimes the grain size distribution is specified. If this is not
the case, laboratory investigations are carried out to determine the sand gradation which
most economically satisfies the requircd mix properties. Often th is can be achieved by
mixing different varieties ofsand.
Sand can be characterized by the mass percentages of sieve fractions lying betwcen, for
example, the 2 mm, 500 urn, 180 Itm and 63 Itm sieve sizes (numbers la, 30, 85 and 24c
respective y). The composition can be shown graphically using the sieve fractions in,
wh at is referrcd to as, the 'sand trianglc', see Figure 2.1.
I. sharp sand
11. very fine sand
III. medium fine sand
IV. medium coarse sand
V. very coarse sand
percentage- .:.clh;:.:ro~u9::.;;h...:S...:,ev;:.:._':-:80,...:1l:...",_
on slev. 63 IJm
28
Sand is said to be better gradcd ifit lies within the shaded area ofthe triangle. This sand
is referred to as Sand A. According to Eisen 1978, the grain size fractions are:
Percentage by mass
Through
Sicve On
size Sieve Desired Lirnits
2rnrn 500llm 25 10-50
500flrn 18Ollrn· 40 30-60
180 urn 63 urn 35 20-45
2.4 Filler
Filler (5):
I. fills the voids of the stone-sand mix producing a more uniformly gradcd matcrial;
2. forms, together with the bitumen, the binder required;
3. has a stiffening effect on the binder which increase; the viscosity and reduces the risk
of segregation.
In general rather f1exible mixes are required for hydraulic structures. 'Wcak' to 'very
weak' filler is uscd, therefore, which requires little bitumen binding and as a result more
'frcc' bitumen is obtained to provide f1exibility. The preferenee is for filler which is hy-
drophobic and has a basic renetion. so that the adhesion between the bitumen and the
stone is improved.
The quantity of filler and its voids ratio largely determine the quantity of bitumen
required. For these reasons, and for optimum workability, the filler must have strictly
controlled requirements such as:
- a constant absorptivity of bitumen;
- a constant nature and quality.
Limestone fillers should bc used for preferenee.
For the propertics required reference should be made to Eisen 1978 (6).
29
3 Bitumen
20-S00·A
PI (pen, pen) = I + 50 . A
in which:
log 800 - log pen
A
T,&k -25
The PI value and the softening point can be determined very simply from two
penetration values using Figure 3.1.
30
I
I -3
-2
Ë 102 / o ,
~
ei
8 2
3
6
c
.2
ë 6
I PI
7
10 20 30 40 50 60 70 80
~ terepercture (oe)
In the low temperature range the Fraass breakingpoint, referred to as 'the brittie
temperature' indicates the consistency.
This number indicates the temperature at which a 0.5 mm thicklayer of bitumen
cracks under a ben ding Ioad.
The higher temperature range is important for the mixing and application of asphalt
mixes. In this conneetion a certain viscosity is essential; the foUowing va lues for
kinematic bitumen viscosity have been determined for different operations (5):
31
I Pascal = I NIm:!
i Poise = 0.1 Pa . s
The stokes unit is also used for kinematic viscosity.
I Stokes = 10--1 m2/s
200.000
\\ \ -.\ -, \ ~ -. --- straight run bitumen
100,OO~ ___ cut-back bitumen
50.000
......... tar-bitumen
20.000
__ _ _ road tar
1~.000
..
,:;-
5.000
E 3,000
.5 2.000
1.0~~
\ '1 ',.'\,. \ -, -, 1\ -, 1\
The quality ofa bitumen must be sueh that hardening is not excessive.lnvestigations into
harderring can be carried out in 'penetration after loss on heating' tests, in which a bitu-
32
men sample is heatcd at 163°C for aperiod of5 hours. For thermostability there should
be very little difference between penetrution before and after the test.
After production at the refinery the bitumen must not be heated abovc 200°C since then
the material propertics can change and certain cracking processes can develop.
Bitumen must not be too hard; the working viscosity should be sufficiently low (about
0.2 pa'. s at 140 tot 160°C) and the Fraass breaking point must not be reached under
critical mechanicalloads at low ternpcratures (8).
For requirements and tests related to bitumen, reference should be made to Eisen 1978
(6) or NEN 3902 (21).
Temperature (0C)
25° 100° llO° \20° \30° 140° 150° 160° \70° 180° 190~ 200°
Bitumen
(pen) Density (1000 kg/rn-)
270/330 1,01 0,97 0,96 0,95 0,95 0,94 0,94 0,93 0,93 0,92
160/210 1,02 0,97 0,96 0,96 0,96 0,95 0,94 0,94 0,93 0,93 0,92 0,92
80/100 1,03 0,97 0,98 0,97 0,97 0,96 0,96 0,95 0,95 0,94 0,93 0,93
45/60 1,04 0,98 0,98 0,97 0,97 0,96 0,96 0,95 0,94 0,94 0,93
20/30 1,05 0,99 0,98 0,97 0,96 0,96 0,96 0,95 0,95 0,94
33
4 Additives
Additives are used to improve adhesion by lowering the surface tension between the
bitumen and the mineral aggregate. This limits stripping.
The effect of the additive is noticcable in the short term but, after about two years, is no
longer apparent. Adhesion-improving additives have been used incidentically in
hydraulic structures. It should be borne in mind that the viscosity can be affectcd.
Propertics such as the viscosity can be affected by the addition of polymers, both
chemically and physically. For the time being, polymers are not used in the hydraulic
applications.
Additives can be added during production and/or before application of asphalt mixes.
When adding to the bitumen, segregation must be preventcd.
34
5 Mix composition
The mix composition is mostly designed on a choice, within certain limits, of partiele
grain size distribution and bitumen content, on the basis of investigations into the
mechanical properties, and by application ofthe basic materials allowed and available.
For different applications the composition is, generally, specificd in thc form of rough
proportions by mass. Thc dctailed composition can thcn be determined from laboratory
and in-situ tests.
There are two general principles involved for dctermining mix composition (9):
I. Design for stability, if a mix of a certain strength is required. Thc bitumen content is,
in this case, adjusted to thc grading of the mineral aggregate,
2. Design for a particular viscosity if a f1exible mix is required. In this case a certain
ovcrfilling ofvoids is esscntial.
35
6 Mix properties
6.1 General
As already stated the choice of mix compositión depends on investigations into the mix
properties. The most important propertjes for use in hydraulic engineering are:
dogree of pcrmeability
mechanical properties
stability
durability
workability and compactability
A dike revetment - ofwhich asphalt can form a part - must be completcly sandtight.
Sometimes a cover layer is also required to be watertight, The voids ratio ofa mix and the
size and oricntation of the voids detennine the degree of penneability of the mix as a
who Ie. The factors which affect the voids are given in Section 1.3.
If a sand-pcrmeable asphalt mix is choscn for arevetment then the sand scal must be
provided by a filter construction. In the case of watertightness a stricter sealing criteria
wiII be essen tial for asphaltic mixes used for sealing water reservoirs than for dike-
rcvetmcnts.
For exarnplc; a 5 cm thick plate ofbituminous mix, with a voids ratio of3% should not
aIIow anywater through when subjected to a water pressure of3 atm for a few hours (12).
For mixes with such a 100y voids ratio special thought must be givcn to the compaction
operatien because of the possibility of initiating cracks in the material.
Asphalt mixes and bitumen appear to have similar mechanical properties. An asphalt .
mix, in the same way as bitumen, is a visco-clastic material which under short duration
loading and at low ternpcratures appears to be clastic; under long duration loads and
higher temperatures it is viscous. Thc visco-elastic property ofasphalt is an advantage for
applications such as in dike revetments; it is stiffunder short duration loads such as wave
impacts but yiclds under long duration loads such as those occurring during settlement.
Remarks
The foIIowing sections give nomograms for detennining the stiffness modulus, the initial
36
strain at break and the Poisson ratio of an asphalt mix. ft should be borne in mind that
these nomograms only give general values. If more accurate values are required it is
better to carry out separate investigations on each mix, including, for example, three or
four-point bending tests and creep tests.
For an elastic material deformation is proportional to the stress applied. The modulus of
elasticity, E, also referred to as Young's Modulus, is often used. This modulus is
independent of temperature and loading duration.
E = alf:
a = stress (N/m2)
e = strain (-)
The nomogram, prepared by Van de Poel, which can be used to determine the stiffness
modulus of bitumen is shown in Figure 6.1.
Since an asphalt mix is visco-elastic the stiffness modulus can also be applied. From
research it appears that there is a conneetion between the S-modulus of bitumen (Shit)
and that of an asphalt mix (Smix)' This relationship is determined, amongst other things
by the volumetrie percentages of the mineral aggregate and the bitumen. The
relationship between Smixand Shit can be shown in what is known as a master curve. An
example ofsuch a curve is given in Figure 6.2.
Over the years various laboratories have carried out research and have developed
nomograms for determining the stiffness modulus of asphalt mixes. The most recent
example of these is give in Figure 6.3.
37
10' 10· 10' 25,10
.. ..
2.10'
.,
-- -
I I
+7 10'
STIFFNESS MODULUS. 11Im2
+6 -<:::: 'tt
+5 10' +5
t4
10' 10' +4
xt3
10 IQ' +3
êZ +2~,0_'
+1
1:>-' +2
o IQ_, +1
•
t= 0, .• o
~ -1
t;; -I
..
z -2~
"' -3
I,
I,
\
1
TEMPEAATUAE DIFFEAEIleE. oe
100 ec IJ 10 2'J Yl .0 'lel b1 1.:) 110 so 1)0 I'C 'n 1~ '40 -so '60 110 180 '''0 lOO
-10 ABOVE T800.... ".1",,1·',1,1,1,' .1 ".I",,!' "1,,,,1,' " ,I,,, ,1", I" " " ' ·1" ,,,..,,, ,.J, ! I BELOWT800 ...
I,
The penetration index (Pil has been defined bv:
Example
20-PI log pen at T 1 - IOypen at T 2 I,
-- = 50 ---'-------=- Opcrating conditions
10+PI T1-T2 I, Température 100C
The stiffness modulus, defined as the ratio stressl
\ Loading time 0.02 secouds
Itrain, is a function C?ftime of loading (frequency). tem-
I
perature difference with TBOO pen, and PI.
\ Characteristics of the bitumen in the mix
TBOO pen is the temperature at which the penetratien would I
be 800. This is obtained by extrapolating the experimental T 800 pen ( ternperature at which the penetration is 800
log penetratien versus temperature line to the penetratien
value 800.
At low temperatuJes and/or high frequencies the stillnes.
\,
,I
0.1 mm) is 64°C
PI I penetration index) is 0
modulus of all bitumen, a,ymptotes to a limit of approximately Connect .02 seconds on time scale with température
3 x 10? Il/m2. \, difference 64-100C on température scale,
Units; \, Record stiffness on network at PI=O
I tl!m2 = 10 dyn/cm2 = The stiffness of the bitumen determined with this
I, 2
1.02 x 105 kgflcm2 = 1.45 x 10-4 tbl in.2 Nomograph is Sb = 2.0 x lcf3 N/m .
1 N ./m2 = 10 P \,
FAEOUWey, He.
K5LA, AuguIt 1953, 3rd edit ion 1972
IJ t, 4 Z
10'0
TIME OF LOADltlG I
Figure 6.1 Nomogram for determining the sliffness modulus ofbilumcn (Van de Poel) (64).
Smix- Sbit curve
tor open stone aSl?halt
Smix
Figure 6.2 Smix - Sbit relation for open stone asphalt (master curve).
The boundary con di tions required for Figure 6.3 are the volumetrie percentages of
bitumen and mineral aggregate. These ean be derived from the mix eomposition in the
following way:
in which:
Vb = volumetrie percentage ofbitumen
Vg = volumetrie percentage of rninèral aggregate
111 = mass percentage
d = density (kg/rn")
da = density ofasphalt mix with voids (kg/rn'')
dm = dcnsity of asphalt mix without voids (kg/rn'')
HR = voids ratio of the asphalt mix
The indices s, Z, f and b refer respeetively to stone, sand, filler and bitumen.
39
STIFFNESS MODULUS
OF THE BITUMINOUS
MIX IN/m2)
80 90
...... b, ::::::". -...
4
70 .... <, <, ,........ <,
MINERAL
AGGREGATE GO.... r-, r-, r-, 1""- "i'>,. r-, 1"- 2
r-, I.........
% VOLUME lVg)
..........
b-. ~ ~---~-----
40 I'.... r-, r-, r-, 1""- ~I
,
r-. i">. , <, ,
20 " 1" " " 95
I" .........
~ .~
r-, r-....... r-, r-, 1""-
<; i"....f'.. r-, r-,
sn FFNESS MODULUS
I R-~"I""
'"
""- 85
OF THE BITUMINOUS
BIN DER (N/m2)
, ...... ,
I Vb I' !:'\ , <,
"-
I <,
I" "
"'- 4
100 40 30 20110 5 -, '"'" ~ r-, <, .......... 1 .......... ......... .........
75-
2
~'\.'\ \ .'\,Ji '1 ~
<,
.........1""- r-,r-, -, 2
-, I\. 1\ 1"- <, <,
.","r-,"" -,
<,
109
"" -, f\.'\\ ""\ \
I I'" -, r-,
G5
-
:=
8
G , I ~ <, <,
::-
"-
'-"~ ~\~I .,1, ......
r-,
4
,,~ <,
Ï'.. 1""- 50
-
-
4
2,""---.---~
~ '" ,,"- ~ 11'.. ~
, -
-
108
8
G
~
CI.~
" ~
~
30
10
=
:
-
-
4 ""-'"
TE::·····.:···1
MiNEÀÀL
\\ ~
~'\ ~
I~
2 80.5 A~G'ÀÈGÀTE
. ~:-:-:"~i '\
."" f'\."' ~ ........
107
8 G.4 I
I
"~ I~,~U~.;~N AIR Va ~
~
,
G VOLUME% "-
5 10 20 30 100
Figurc 6.3 Nomogram for dctcrmining the stiffness modulus of asphalt mixes (Bonnaure et al)
(65).
40
If the dcnsity of the various eomponents is not known precisely the following general
values can be used for initial guidanee:
2,5 Cv)n
Smix = Sbit ( I + n' I _ Cv
in whieh:
11
4, 10
=0.83 log ( ~
1
°)
C = volume of the mineral aggregate
v volume of thc mineral + bitumen
in whieh:
41
the factor a, in gcncral, lies between 3 and 7 and stands for normal,
slightly fat mixes, usually at 5. .
The fatigue relationship between the number of load applications and the initial strain at
failure can be determined from dynamic tests or from Figure 6.4.
The Miner's Law is uscd, for conditions involving varying loads. This states that for each
applicd N loading cycles of a certàin load value on the material, which has a loading
cycle number at failure of N, the amount of damage wiII be proportional to 11/ N. Failure
.will occur when the summatien of the damage amounts reaches a value of l. For a
combination of Nj applied loading cycles of amplitude 0j the failure limit is reachcd
when the following condilion is satisfied (67):
A nomogram has been developed (68) in which the initial strain al failure related to the
asphalt mix parameters Smix, Vb and PI, can be estimated in relation to the number of
load applications, see Figure 6.4. In the nomogram loads which can be considered as
producing constant strain are scparared from those producing constant stress, see the two
different Smix scales.
s.Mf(l@\S,lIlod.Jl,J.s
of tbe ",ic
Figurc 6.4 Nomogram for dctcrmining thc failure strain of asphalt (68).
42
The basis for the nomogram are the formulas:
I. constant strain
2. constant stress
f:o = (0,300 x PI - 0,015 x PI x Vi, + 0,080 x Vi, -:- 0,198) x S,;:;O.28 x lVO.2
in which:
Under longer duration loads asphalt is viscous and permanent deformation can oceur.
The stiffness moduli in this range are low and eannot, in general, be obtained from
Figure 6.3. To determine these parameters it is neeessary to carry out statie and dynamic
tests, such as creep tests, on each particular mix.
Cl
.5 Pm
'U
Cl
.s
_ deformation
43
Much use is made ofwhat is referred to as the Marshall test to determine the resistance to
deformation (6). This test gives only values for comparison with other mixes and not
specific quantities. In these laboratory tests, samples are subjected to specified loads and
the deformation up to failure is rccorded.
The load at failure is referred to as the Marshall-stability, Pm; the deformation which
develops to failure as the Marshall-flow, F~. The relationship between these parameters,
recorded in the test, is given in the Marshall-diagram, see Figure 6.5.
The Poisson-ratio gives the rclationship between the strain in a sideways direction and
the strain in the direction ofthe load. It can be estimated using values of Sbitumen and the
voids-ratio ofthe mix in Figure 6.6 (11).
1.0
08
0.6
0.4
0.2
Poisson
ratio
0.1
0.08
005
8 10 20
~ verets ratio
44
6.4 Stability
If bitumen is laid in a layer on a slope, it will, because of its own weight and viscous
properties, tend to flow down the slope, see Figure 6.7'and Appendix IX. An internal
shear force must be mobilized to resist this flow.
Asphalt is a mixture ofmineral aggregate and bitumen and the internal force which tries
to resist the viscous flow is also developed by the friction between aggregate particles and
is thus, to some extent, dependent on the normal pressure which the particles exert on
each other. The bitumen has a lubricating action as a result of which the intern al
resistance is less than that found in the aggregate alone. The quantity of bitumen in the
mix, therefore, has considerable influence.
The revetment should be so heavy and extensive that it cannot move as a who Ie under
the loads acting.
6.5 Durability
The revetment must, with the course of time, continue to fulfil its function. The charac-
teristic mechanical properties should not deteriorate too much within a reasonable time.
The following aspects will affect this.
6.5.1 Aging
Bitumen hardens with exposure to light and atmosphere. Material properties, such as the
stiffness modulus, strain at failure and viscosity also change. This effect is more notice-
able when the temperature is higher and the voids ratio larger. With a dense asphalt mix,
such as asphaltic concrete, aging only takes place in very thin surface layer.
45
Thc hardening of bitumen which occurs during mixing, handling and placing must be
taken into account when designing the revctment. In general a loss of bitumen pene-
tration of 10 to 25% is to be expected, dcpending on thc type of mix-plant.
6.5.2 'Stripping'
Water can strip the bitumen from the surface ofthe mine ral aggregate and causc thc mix
to deteriorate.
Thc danger of stripping is less wh en the voids ratio is low. From tests (12) it has been
found that, for mixes with a voids ratio ofless than 6% there is no danger ofstripping. For
mixes with a voids ratio of less than 10% there is little dangcr.
A method ofmeasuring the deterioration ofa mix is thc 'Immersion Compression Test'
which originated in American road engineering (39). In this test the compressivc strcngth
of blank samples is compared with thosc that have been kcpt under water of a certain
temperature for a given period. Thc ratio found between thc compressive strengths ofthe
blank and immersed samples is called thc retained stability.
Flowing water can erode asphalt mixes and, especially when solid matter is carried along
the extcnt of crosion as aresuit ofimpact forces on the asphalt surface can be substantial.
The stresses in the asphalt caused by such impacts, will increasc with the hardness of the
binder. The resistance of thc material to these stresses, howcver, is not directly propor-
tional to the degrec of hardness. From these considerations thc following nile has been
formulated:
The lower thc minimum temperature at which erosion can be expected the softer thc
bitumen should be (12).
46
opportunity for nlgae to attach itself, In or near the tidal zone it is therefore beller
if the seal coat is not blinded with chippings or shell grit.
2. Bladder weed. A covering of bladder weed slows down the drying out process of
the algae.
3. Chemical treaunerus. These methods, unfortunately, are environmentally unac-
ceptable.
Marine borers.
These animals which are to be found in the lower part of the lidal zone, exen during
their growth pressure farces in the cracks and holes where they are established.
47
Musseis can then grow in the spa ces which develop and sa the damage progresses.
This damage can be prevented by:
I. A seal coat as described above.
2. A thin layer of bitumen which kills the organîsms.
Plant damage.
Plurus cao exert considerable force with their roots, and runners, sec Photo 2.
When there are seeds in the subsoil, plants can grow through the asphalt layer. This
effect is strcngly influenced by the type ofsubsoil; in dredged spoil there will be na or
very few seeds. The environment can, also, be important, partienlar in salt or sweet
water areas. lt is possible to treat the soil with a planticide. but in this case tne environ-
ment can be damaged.
A smooth espbalt surface in which there are na cracks or holes offers very few
auachrneru points for seeds which come onto the dike. A good seal coat cao,
therefore. be an important deterrent.
48
concentration ofcarbohydrates must be very high before they can cause real damage. A
surface treatment of road tar or tar bitumen can be used for proteetion but this often is
environmentally unacccptable.
6.6 Workability
In order to obtain the best possible adhesion between the mineral aggregate and the
bitumen the asphalt must be uniformly mixed. To obtain th is the bitumen must have a
low viscosity. This can be achicvcd by:
a. Heating thc bitumen to 150-200°C (viscosity 150-300 mm-/s); th is is then referred to
as 'hot-mix asphalt'. Hot-mix asphalt is prepared in an mix-plant in which the
bitumen is heatcd to a specified viscosity and then mixed with dried and pre-heated
mineral aggregate.
b. The bitumen can bc diluted with a solvent, for example, a suitable petroleum dis-
tillate or can be emulsificd in water; the solvent or the water has to vanish out of
the mate rial beforc the asphalt mix reaches stability.
Under water or in a humid environment these methods are unsuitable. For this
reason they are rarely used in hydraulic structures, except as an emulsion for seal
coats and tack coats. Also the danger of stripping is greater than with hot-mix asphalt,
After production the mix is transported to the site and placed. The specificatien for mix
composition generally depends largcly on thc workability, since total mechanised
handling and compaction. using heavy equipment, is generally not possible.
The viscosity of the mix required for handling is strongly dependent on the viscosity of
the bitumen and, therefore, requiremcnts for the tempcrature are given. Hot-mix asphalt
must be plueed at the correct temperature on account of the time needed for handling
and to achieve an optimal compaction.
For thickcr asphalt layers the cooling pcriod will he longer and, therefore, more time is
availablc for placing and compaction. In th is respect the weather conditions are
important. When mechanical compaction is involved it should be borne in mind th at the
outer and inner surfaces of the layer will be cool while the inside is still hot. The thicker
the layer the stronger is this effect. The possibility of building up the revetment in several
layers can then be considered.
49
Overfilled mixes need not be compacted but underfilled mixes can be compacted in
order to reduce the voids ratio. This process can be achieved by either mechanical
compaction or compaction under the own wcight of the matcrial.
Mechanical compact ion can be carried out by tarnping. or by using rollers or vibrators.
The degree ofcompaction can be affected by:
the bitumen content;
the content and type of filler;
the mineral aggregate content;
the partiele shape of the mineral aggregate;
the partiele size distribution;
the temperature of the asphalt and the surroundings;
the layer thickness;
the weight and type of compaction equipment.
Compaction is more difficult on steep slopcs; the component of thc weight of the roller
vertical to the slope is smaller and the handling of equipment is more complicated.
In order to neutralize the roller weight parallel to the slo pc, the equipment can be
attached to winches located on the crest. Compaction can be carricdout effectively,
without these special provisions on slopcs more flat than I : 4, sec also Section 22.3.1.
From an acsthetic point ofview a smooth finish to the revetment is desirabie. Sometimes,
however, there is a tendency to prolong the compact ion process in an attempt to obtain a
certain smoothness. When th is happens the asphalt can become too cool and (initial)
cracks can develop. Rolling must be siopped if the asphalt becomes 'live', th at is to say,
ifwaves in the asphalt propagate in front ofthe roller.
Ifthe mix is not very workable (initial) cracks can develop aftcr, only a few passes ofthe
roller, especially at the bottom of the slope whcrc the material may start to flow. Rolling
must then be halted to allow the material to cool down. At the same .time the mix
cornposition should be adjusted.
Generally it seems that the compactability is reduced as the stability of the mix is
incrcascd, .
Compaction due to the weight of the material applies with what are known as, gap-
graded mixes. These are mixes for which there is a 'gap' in the mineral aggregate grading
curve; a particular partiele fraction, usually the fine stone fraction, is missing. The coarse
stone fraction farms the stabie skeleton of which the voids are completely filled with
sand mastic - in the case of a dcnsc asphalt mix - or only coated in the case of an open
asphalt mix.
The object is to obtain a mix which draws on the skeleton ofthe coarser stone to provide
satisfactory stability against flow during handling and which, thanks to the viscous
mortar, needs only a small amount of compaction energy to produce the required voids
ratio. The stability of the mix in the completed stage must also be taken into account.
This may possibly be in contradiction to the foregoing requirements.
50
Because they need not be compacted gap-graded mixes can be used at locations where
compaction would be difficult.
The following points relate to the possible darnaging effect of asphalt to the environ-
ment:
51
7 Use of asphalt produets in hydraulic structures
Asphaltic concrete is probably the best known mix type. It is a mixture ofcrushed stones
or gravel, sand and filler in whieh the pores are practically completc1y filled with bitu-
mcn.The voids ratio is 3 to 6%.
In general thc material must be compacted and is unsuitable for application underwatcr
or in the tidal zone. In view ofthe sm all voids ratio rcquircd, sec Section 9.2.1., asphaltic
concrete can be considered to be impermeable.
Asphaltic concrete is applied as a watertight dike revetment above the mean high
water level, and as a lining for canals, reservoirs etc.
7.2 Mustie
Mastic is a mixture of sand, filler and bitumen. There is more bitumen available than
necessary for filling the voids in the sand filler mixture. The mix, therefore, is naturally
dense and need not be cornpacted. Mastic can be poured at working temperatures and is
used, for asphalt slabs above and under water for lining or as bed and toe protection.
When cold, mastic forms a viscous quasi-statie mass.
Grouting mortars are hot-type mixes of sand, filler and bitumen of which there is
more than required to fill the voids in the mineral; stone and gravel can be added if
necessary. These mortars are used for grouing stone revetments above and below wat-
er-level, and also for slab construction.
52
7.4 Dense stone asphalt
Dense stonè asphalt is a gap-graded mixture of stone, sand, filler and bitumen. The
amount of bitumen slightly overfills the mixture. The material is, therefore, water
impermeable.
It is used as bottom and slope proteetion and also in toe construction.
Open stone asphalt is a gap-graded mixture of mastic and stone - a stone frequently
used is limestone 20/40 mmo Mixing is carried out in two stages. First mastie is prepared
and secondly it is mixed with limestone. The mastie binder only coats and eonneets the
limestone particles together.
It is an 'underfilled' mix and, beeause of its open strueture, should not be plaeed under
water except in the form of prefabricated mattresses ..
Lean sand asphalt is a mixture ofsand, often locally obtained, with 3 to 5% bitumen. It is
a greatly 'underfilled' mix and the function of the bitumen is simply to coat the sand
grains and bind them together. After some time the permeability is very similar to the
sand from whieh it is made.
It is used as a eore material for reclamation bunds, filter layers and as permanent or
tcmporary eover layer above and bclow water-level.
7.7 Membranes
53
8 Quality control
Quality control is essential in order to guarantee the quality of the work during the
execution and on completion. Con trol includes mix design tests.before the start ofwork,
production con trol during the execution and checks on completion of a part or the
complete work.
In road construction there are already many instructions and directives for carrying out
quality con trol, for example, those given in Eisen 1978 (6), V.D.e.W. (18) and A.B.C.W.
(19). There are, however, no such official instructions forthe use ofasphalt products in
hydraulic structures. The construction requirements and the working conditions often
appoint con trol checks required (20).
After the tender has been drawn up the definitive mix composition is decided, based on,
(extensive) laboratory investigations. The type of investigation depends on the mix
properties required and the application in prospect. Stability and voids ratio, for
example, will be more relevant to asphaltic concrete revetments, whereas viscosity wiII
be more relevant to a mastic slab.
During the investigations the suitability ofthe basic matcrials given in the tender is also
examined.
The investigations should lead to a technical and economie optimum mix, taking into
account the basic requirements and the matcrials available. Next the planned produc-
tion and working methods are ehecked to confirm that they will yield the best results.
The produetion method for the material and the execution method often determine the
quality and cost of the work.
The mix-design tests on the basic materials are more or less the same for all asphalt
mixes; they include, for example:
an assessment of general information such as the type of material and identification
of its source. The identification of its souree must include the name of the sup-
plier, location ofthe source, the nature ofthe material and the quantity for which the
identification is valid. Eaeh delivery ofconstruction matcrials conform an identifica-
tion ofits souree should be accompanied by a written authorization
investigations into pollution aspects
sieve analyses: stone/gravel; sand; filler
determination ofthe bitumen number and sensitivity ofthe filler to water
determination ofthe penetration and the softening point ofthe bitumen
determination ofthe density ofthe mineral aggregate.
54
...
The design tests for the various mixes differ for each type of asphalt. Refcrence should be
made to Part D, Chapters 9 to 15 inclusive.
Production con trol is necessary to guarantee the quality of the final product.
It includes:
Production controls are normally carried out by the contractor. The principal can also
carry out quality control during the execution of the work. In principle, however, from
the very beginning. the principal should assume that the contractor has mastered the
execution process and maintains good quality control. The control by the principal can
include checking the methods used for production control. This can be in the form of
tests on samples (by an independent organization). For these tests:
The principal carries out acccptance con trol to confirm that the basic requirements have
been satisfied, Ifthe work has not been carried out satisfactorily then penalties should be
imposed.
Acceptance control for road works are dcfined in Eisen 1978 (6) and V.U.C.W. (18). A'
part of this con trol can also be applied to hydraulic structures but obviously cannot be
interpreted in exactly the same way.
55
'"
Acceptancc control is normally carried out after a part or all of the work is ready. Ifthis
is not possible the checks must be carried out during the work.
The parameters which are most frequently checked are given, per mix type, in Table 8.1.
8.4 Sampling
Good sampling technique is essential for rc1iable production and acceptance contro!.
Samples are required of:
a. basic materiais;
b. asphalt mixes.
Sampling and tests must be carried out sufficiently early so that results are available
before the material is used.
FILLER
A.B.C.W. (19) can be used as a guideline on sampling frequency. Samples should be
taken, on arrival, before the material is dumped in the silo. In order to verify the quality,
samples can be taken out of the supply to the mixer.
BITUMEN
The sampling method should be as given in the Dutch standard NEN 3940 (21) and
A.B.C.W. (19).
8.4.2 Mixes
Depending on the particular aspect being investigated, samples should be taken on one
hand, at the mix-plant, and on the other hand, on site.
56
There are two methods for mixer sampling:
al or in the skip
out of the loaded truck.
The methad of samples can be taken in accordance with A.B.C.W. (19) or any other
systems specified in the particular tender.
The method of sampling, out of the completed werk. is often dependent on the
accessibility ofthe material in the structure and the possibility of obtaining samples with
a saw or by taking cores. Usually cores are taken for road construction works, but this is
nol atways possible Ier hydraulic structures. Taking cores is, if possible, in general the
prefered method of sampling (Photo 3).
.,
ë E <J
U
.,c:: '"...
'"
'" ë '"
ti '"
0
c c:: ~:I ~
_"" <:l
0
:-.,
.:.:
u
0
U ~'" .9
0
c- '-6
o .....0-
:s... c::
0
E
'"
c
'";.""
c:;...
'"
'-
0
..c
el)
c
'ëh ~
s.s
>,-
C 0
.0-
e.o5
c ...
.- 0
0
>, 3 -0
'(3 ë.. eo c ",-
"';;c possible sampling
mix ~ :E
0
'Vi ;. ""
-0
'"'" :~ ::l
<TE'" 0'-
",-0 method"
asphaltic x x x x core boring
concrete
asphalt Xl x x core boring
mastic bulk sample
penetratien x x x2 bulk sample
mortar
dense stone x x x core boring
asphalt bulk sample
open in-situ x x x x core boring
stone
prefab. x x x x bulk sample
asphalt
lcan x core boring
sand-asphalt bulk sample
mem- in-situ x x bulk sample
brane
prefab," x x
I Check on layer thickness by core borings or by special thickness probcs, also carried out under water.
2 Desirabie but often impossible to obtain.
3 Testing of the specifications of the manufacturer;
Execution tests, specially joints;
Test on functional requirements:
- impermeability ofthe whole surface, includingjoints
resistance to root growth
- ability to deforrn without leaks devcloping
- durability
- f1exible joints with other structural components.
4 Core borings are preferrcd; these, however, are not always possible. An alternative is bulk
samples per quantity of in-situ matcrial.
58
PARTB
MATERlAL TECHNOLOGY
Summary
Part B discusses aspects of material technology of the various asphalt mixes which arc
most used in hydraulic structures.
These are:
asphaltic concrete;
asphalt mastic;
grouting mortars;
dense stone asphalt;
open stone asphalt;
lcan sand asphalt;
asphalt membranes.
To make this part of the manual more readily applicable it has been subdivided into the
different asphalt types. So that separate sections can be read without cross-reference
sometimes information has been repeated.
Three separate aspects have been discussed for each asphalt type, namely:
The basic matcrials
The matcrials, of which the asphalt type is composed, are discussed together with
rclatcd construction parts.
Mixes
The composition ofthe asphalt and the way in which the mix is designed is described.
The method of mix-design testing is also discussed. These are the investigations which
must be carricd out to determine the most suitable mix composition before the work
can be started,
Mix propertics
The choice of a particular asphalt type is based on the mix properties. Since the
components and the composition vary, the properties ofeach mix type also vary. The
relevant mix propertics are described for each mix type. These properties form the
basis for Part C of the manual which deals with the technical design.
60
9 Asphaltic concrete
9.1.2 Gravel
Because of the fa ct that gravel possibly gives less adhesion and the interrial stability of
the mix is lower in the hot condition, for sorne time the use of gravel was abandoned.
Since the lower internal stability never has been proved sufficiently, however, there is,
for the present, no reason not to use gravel.
Reference should be made to Eisen 1978 (6) as far as this is related to hydraulics.
9.1.3 Sand
In principe every kind of sand can be used. A well-graded sand is desirabie since
otherwise high percentages offiller must be added in order to reduce the voids ratio. This
can lead to mixes which are difficult to handle and are more expensive.
A sand, that lies in the optimum area ofthe sand triangle, Figure 2.1, is well-graded and
satisfies the rcquirements for Sand Type A, given in Eisen 1978 (6).
The following points relate to sands Iying outside the optimum area:
There is no experience with sand that lies to the right of the line for natural sand, sec
Figure 2. I. As far as it is known such natural sands do not occur in the Netherlands.
Sands with à grading stich asthat in Area 11in Figure 2.1 contain the finest fractions
and are very uniformly graded. Because ofthis the mineral mix will have a high voids
ratio and a relatively large amount of additional filler and bitumen would be required
to produce a dense asphalt mix. As aresuit the workability would be adversely
affectcd.
Sands lying in the lower left hand corner of the sand triangle produce good results
provided that the filler content, as indicated by a sand-filler compaction test (En-
gelsmarin method), is increased. Then workable mixes are obtained with a low voids
ratio.
61
- Sands laying in Area V ofthe sand triangle, Figure 2.1, can also pro duce mixes with
good workability. The use ofsuch sands, however, is rather expensive.
Stability during the construction phase can be improved if some of the natural sand is
replaced by crushed sand; this is a more angular matcrial. On the other hand the
workabilitycan be influenced adversely by this.
9.1.4 Filler
'Very weak' fillers are used in hydraulic structures, being fillers with a very low voids
ratio which require relativcly very little bitumen. Ideally limestone fillers should be used
because they give better adhesion in a humid environment.
From experience it appears that mix workability is increased by using 'weak' rather than
'very weak' filler, while there is no noticeable affect on the required voids ratio.
For further information, reference should be made to Eisen 1978 (6).
9.1.5 Bitumen
Concerning the required flexibility of the revetment it has been found that bitumen
80/100 pen is the most suitable in the Nctherlands. For bitumen requirements, sec Eisen
1978 (6).
Asphaltic concrete is, preferably, covered by a seal coat. This can consist of a sealing
layer and/or a surface dressing. Thc function ofthe seal coat is to:
62
9.2 Mixes
In principle the filler content can be chosen so that the voids ratio in the sand-filler mix is
minima!. In practicc, howevcr, for economie reasons, a lower filler content of7 to 8% m,
of the complete asphalt mix, is often chosen. Around the minimum voids ratio value
changes in the filler content have only a lirnited effects on the voids ratio (Figure 9.1). It
is also practical to choose a filler content somcwhat to the left ofthe minimum since filier
contents to the right of the minimum value shown on the curve result in an undesirable
increasc to the volume of the voids.
34
33
~
Ë
~ 32
-c
c
"~ 31
~
<C
2 30
~
"
.~
29 f1ller centent
selec.ted
28
10 ~o 50
.---. moss percentage- of fitter in tht> ~nd - Mier milt
Figurc 9.1' Rclationship between voids ratio in a sand-filler mix and thc filler content in thc mix.
63
The composition of the mineral aggregate content is determined in the way described
above.
The bitumen content selected depends on:
I. The form of the curves which relate voids ratio ofthe mix to the bitumen content, sec
Figure 9.2.
2. The required voids ratio compared with the voids ratio found in Marshall samples,
compacted by 50 to 100 strokes on one side, sec Figure 9.2.
Whether or not a mixture with the chosen bitumen content is also suitable to be placed
and compactcd, also on slopcs, can only be found out in practise. Only limitedinforma-
tion can be obtained about th is aspect by doing slope tests in the laboratory.
With asphaltic concrete used in hydraulic structures, containing for example, Sand A
and/or fine sand it appears that increasing the bitumen content, and thus lowering the
viscosity, lowers the voids ratio to a certain limiting value. A mix with a bitumen content
of 7.5% m in 100% m mineral is difficult to handle because it is insufficiently stabie
in the hot condition.
13
12
11
~ 10
5 strokes
10 strokes
5
~ ~ 20 strokes
_ ~ 50 strckes
100 stroi<es
64
Asphaltic concrete for hydraulic structures sh9~ld be a hot-prepared mix of crushed
stone 6/16 mm, sand, very weak filler and bitumen 80/100 pen for layers less than or
equal to 150 mm thick.For thicker layer crushed stone 6/22 mm should be used.
In practice, in the last few years, a bitumen of6.5% m has often been used to improve
the workability, especially the stability in the hot condition.
When asphaltic concrete is in place the voids ratio should not be greater than 6% m on
slopes steeper than I : 4 and not greater than 5% m on slop es of 1: 4 or less.
% by mass
thru sieve on sicvc required min. max. toleranee
C 22.4 2mm 50 48 55
2mm 63 firn 42 37 47 :!:5
631lm - 8 7 10 :!:1
bitumen content
in 100% mineral 7 6.5 7.5 :!:0.5
The voids ratios above give, in general, mixes which are durable and have good wor-
kability.
In practice often for aesthetic reasons, mixes are compacted too long and too heavily so
that initial cracks develop (59, 89). This can normally be prevented by using a good
compaction method, sec Sectien 22.3.1. Ifthe required voids ratio is so small or thc layer
thickness is so large that cracking cannotbe avoided even with a good compaction
method then the revetment must be laid in several Iayers, In general. thc thinner the
layer the beller the compaction. Naturally good cohesion must then be provided bet-
ween the layers. This can lead to problems during exccution if dry sands blows onto the
surface being preparcd. Dry sand and other'pollutants must, thcrcfore, first be removed.
At locations where dry sand is not a problem the method using severallayers produces
good results and is to be recommended when compaction problems are anticipated. The
layers can be built up of the same material or from different matcrials which are
matchcd. For th is aspect reference should be made to the various cover layer construc-
tions used for dams and roadworks.
For conditions in the Netherlands the first solution is often adequate.
65
In Eisen 1978 only the investigation of voids ratio is required; after compaction ac-
cording to a Marshall test, the voids ratio should be not more than 4%. In order to
achieve better compaclion results and to have more time available for compaction the
mix should be such that it can be compacted at the highest possible tcmperatures.
Mix-design tests can include a numbcr of'sections, such as:
investigation of the voids ratio of the sand-filler mix with, for cxamplc, the Engels-
mann apparatus;
determination of the voids ratio of thc asphaltic concrete mix;
comparative investigations by Marshall tests.
Mix propertics can be investigatcd by varying the mass percentages of thc various
components within the given lirnits. Normally, however, only the effect of the bitumen
content is investigatcd.
From the rcsults of these invcstigations the mix can bc designed. Wh en the mix has been
dccidcd thc inf1uence of the tolerances should be invcstigated, for examplc by carrying
out two tests on mixes with the designed mineral composition; one with 0.5% by mass
more bitumen and one with 0.5% by mass less bitumen. If it appears that problems may
develop then the mix composition should be modified.
A written statement must be given ofthe composition ofthe asphalt to be dclivered to the
site. Thc tolcrances, for use with this composition, as given in Table 9.1, should also be
declared. If it appears that the composition of the asphalt has to be changed during the
execution, th en these changes should be reported in writing and the tolerances should be
restatcd,
Reference should be made to Section 8.1 for the investigations to be carried out on the
basic materiais.
66
Figure 6.4. gives general values for the initial strain at failure. This value can also be
determined for cach stiffness of modulus by .experiments.
Since the Marshall test only gives an indiention of the stability and flow properties of
mixes it is only usabic for comparison purposes, for example, in conneetion with con-
struction and con trol.
9.3.2 Permeability
9.3.3 Durability
CHEMICAL RESISTANCE
Bituminous materials are chemically resistant except to a limited number of carbohy-
drates. Beforc these can cause any damage to a dense asphaltic concrete p1ix the
concentrations in the surface water must be very high. A seal coat of road tar or
tar-bitumen can limit the effects. The environmental aspects, discussed in Section 6.7,
are then also relevant here.
IlIOLOGICAL RESISTANCE
Sec Sectien 6.5.4.
67
10 Asphalt mastic
10.1.1 Sand
Provided the mix propertics are satisfaetory, in principle, all sand types ean be used.
For the sand requirements refcrenee should be made to Eisen 1978 (6).
10.1.2 Pilier
Filler should be weak or very weak. Sinee the filler strongly determines the viseosity of
the mastie it should have a uniform quality and a constant absorption capacity. Sec also
Eisen 1978 (6).
10.1.3 Bitumen
The type and quantity of bitumen greatly influenee the viseosity of the mastic. A
bitumen which is no harder than pen 80/100 is reeommended. See also Eisen 1978 (6).
10.2 Mixes
10.2.1 Mix design
Mastic is a mix of60 to 70% by mass sand, 15 to 25% by mass filler and about 20% by mass
bitumen. lt is an overfillcd mix whieh, in itself, has the properties of a highly viseous
fluid, Mastie mix design is bascd, therefore, not on stability but on viseosity.
Mastic requiremcnts, see (23), includc: .
I. The mix must be pourableat high temperatures. This depends on the viseosity at
placing temperatures; in practice the viscosity is between 10 and 200 Pa . s.
The mastie must have sueh a viseosity that, for cxample, it can be poured through a
pi pc.
If placing tempcratures are too high vapour-filled bubbles dcvclop in thc material
when it is applicd under water. These subsequently heal by mastie flow.
68
Calculations show that, dcpending on the pipe and nozzle diameters, thc rnastic
viscosity should not be higher than 200 Pa. s for it to flow through a vertical pipe
under its own weight and without the excess pressure becoming too large (23), see also
Appendix VIII. On the other hand, however, the viscosity must not be so low that
water can intrudc into the nozzle. Naturally both upper and lower limits to viscosity
depend on the water depth.
Wh en working with a closed hopper bucket or a crane the viscosity should be 30 to
100 Pa . s under water and 50 to 200 Pa . s above water. The viscosity should not be so
low that, on slopes of I : 10 above water and I : 7 under water, excessive hot flow
develop down the slope. On the other hand the flow shuuld be sufficient to form a
continuous layer.
A viscosity between 80 and 150 Pa . s at the placing temperature is sufficient to ensure
this. (sec Table 10.1).
2. After cooling down to normal ternperatures the mastic viseosity should be sufficiently
high to ensure that it only flows within particular limits, For this temperature, slope
and layer thickness have to be taken in account. From calculations it appears th at, for
a 10 cm thick plate on à slope of I : 10 to flow a few decimetres in 7 years, the viscosity
would have to be at least 109 Pa. s, sec also Appendix IX. (See Table 10.1).
Some examples of mastic mixes used in the Netherlands for slab construction are:
Grevclingen Dam
• sand 63-65% by mass
• filler 15-17% by mass
• bitumen 280/320 20%
Eastern Scheldt Storm Surge Barricr
• sand 62 % by mass sand 64 % by mass
• filler 20.5% by mass filler 17.5% by mass
• bitumen 160/210 17.5% by muss bitumen 80/200 18.5% by mass
Viscosity at 130°C, 30 to Pa . s.
69
10.2.2 Mix-design tests
Mix-design tests to determine the mix composition are mostly based on the Kerkhoven
Method.
First of all the optimum sand/filler proportion is found using the Engelsmann apparatus
and based on this value a sornewhat smal1er filler content is selectcd, sec Section 9.2. I.
The tests with the Engelsmann apparatus are carried out to determine the smallest voids
ratio in the sand/filler mix in order to ensure that the related bitumen content is the
smallest possible. The bitumen content is determined from the Vsf-faetor, whieh, in its
turn, is found from Figure 10.4., sec Section' 10.3. I.
The viscosity at high tcmperatures, 120 to 170°C, is found using the Kerkhoven viseosity
meter (Figure 10.1.). With this meter, the time taken for one litre of mastic to flow out is
measured, in seeonds.
I
I 153
I 195
I 3 00
I .>: -
25
~
sa
I
i
I reecsur es in mm
11 viseosity (Pa. s)
p bulk density (kg/rn'')
g aeeeleration due to gravity (mi SZ)
( outflow time (s)
70
I. the influence of variations in mix composition within given lirnits, on the mastie
properties.
2. the influence ofvariations in the grading ofthe sand on the mastie properties.
temperature (Oe)
Remarks
the tests give only the viscosities at the test temperatures and not at the normal
tcmperatures
the measuring accuraey is not very great.
The designer and the user should have a more usabie metlied to supplement the
Kerkhoven method. Research into th is is al most completed.
10.3.1 Viscosity
Mcasurements of mustie viscosity have been made by Kerkhoven (22). With this the
measured relative viscosity, 11mhlbit (11m = viscosity of the mix. 1Jbit = viscosity of the
bitumen) is related to thc bulk volume of the sand/filler mix (Vsf),
71
The Vsf can be determined using:
100 F+M
Vsf = 100 _ Hm . F + M + B' 100%
in which:
The Vsf represents the solid phase of the mix, that is, the bulk volume of the sand/fillcr
mix in which the voids are filled with fixed bitumen, see Figure 10.3.
-,---
.. tr oo " liquid phase
bitumen
1--- - - 1-- ----- 1-
B
fixad
F
• - - - - --
.
M
B
sand • solid phase
F+M filler
Mcasuremcnts have been made, using the Kerkhoven method, on a large number of
mastic samples made up from four different sand types, including dune and river sand,
mixed in different proportions with filler and bitumen 50/60 and tested at 140°C and
40°C (22).
Kerkhoven used the Marshall compaction hammer to compact the sand/filler mix, a
method which produced a lower voids ratio than the Engelsmann apparatus. The latter
method, however, gives better agreement with values obtained in practiee (4), sec Figure
10.4.
It appears that the viseosity ofa mastic, as a first approximation, ean be deterrnined using
the Vsf formula. A simple dryeompaction test, based on Engelsmann, ean then be used
to detcrmine the voids ratio ofthe mineral aggregate. The relative volumetrie proportion
of filler to bitumen only influences the viseosity at higher temperatures and only then
when the proportion is 0.20 to 0.25 or less. These low proportions are, in fact, scldom
72
found. With a low rclative volume offiller to bitumen it is possible to design a mix with
a relatively low viscosity at working temperatures and a high viscosity at normal tem-
peratures.
F/B _ Volumeoffiller
- Volume of bitumen
10l,
I1
8 11
--- viscosity at working temperatures(FIS >0.25)1 I
6
- . - viscosity at working temperatures[FIS<0.2~l "
l,
- - - viscosity at lower temperatures 1 1
~1
\V sand-liller. Marshall compaction 11//
I I
2 CD sand - lilier • Engelsmann compaction 1 1
/ /
/ 1
FIS = volume ol filler / /
103 volume of bitumen / /
/ /
8 / /
6 /
I
/
:ö / /
-
F"
E
F"
l,
I
I
/5. /
I
I
2 /
/ I
/ I
/
102
CD/
I 3.
8 cD
6
t:
101
50 60 70 80 90 100 110
Vsf
The viscosities at working and normal temperatures are very closely related. An easily
workable mix will, in general, have greater flow at low temperatures. The flow charac-
teristics of mixes at normal temperatures, therefore, can only be compared when the
mixes have the same viscosities at working temperatures.
73
10.3.2 Meeltanical properties
Thc stiffness modulus and the strain at break of a mastic mix can be detcrmincd, very
generally. using the methods discussed in Sections 6.3.1 and 6.3.2.
10.3.3 Permeability
Mastic is an overfilled mix and is, thus, dense. Air bubbles can form in the mix as aresuIt
ofthc preparation process which generally do not affect thc impermcability. Thcrc may
weil be a voids ratio of 7 to 12% but the voids are not in contact with each other.
Air bubbles can, howevcr, have an effect on the viscosity. An increase in the air content
can cause a reduction of the rclative viscosity.
10.3.4 Durability
Because thc mastic is overfillcd, the mix is, in itsclf, scaled and therefore very durablc .
. .
74
11 Grouting mortars
Thrcc ways in which an asphalt mortar can bc uscd to grout stonc are:
b pcttorn grouting
I I
~~-
75
11.1 Basic materials
2. Filters
A sand and watertight construction cannot a1ways be guaranteed even with fuUy grouted
stone and, therefore, a1so in re1ation to the execution of the work a filter is
recommended. When a filter cloth is used tbc temperature of the grouting mortar, which
wiJl touch the cloth, shou1d not be too high. For a po1ypropy1ene cloth the maximum
temperature is about 140°C.
11.2 Mixes
11.2.1 Mix-design
A grouting mortar is an asphalt mastic or an homogeneous mix ofmastic with gravel or
stone. The use of gravel or stone is dependent on the dimensions of the stone to be
penetrated. Gravel or stone serve to:
76
1. reduce the quantity ofmastic needed;
2. prevent thc mortar sagging onto the slopc;
3. limit, sometimes, the grouting depth.
Mix-design is often a question of experience. Ouring execution the mix viscosity should
be sufficiently low, in the range 30 to 80 Pa . s, for the mortar to be handled and the stone
grouted without it sagging onto the slo pc.
After execution the viscosity should be so high that flow at ambient temperatures is
limitcd. Calculations indicate that, to reduce the flow ofmastic in rubble 80/100 kg, on a
slope of I : 5 in a 7 year period to a minimum, a mortar viscosity of 109 Pa". sis needed. In
general the viseosity required wiII lie between 106 and 109 Pa. s, depending on the
tempcrature, slope angle and dimensions ofthe stone (23).
The flow properties depend on the eomposition ofthe grouting mortar in relation to the
dimensions of the stone and the slope-angle, If the flow of the hot mastie in the voids
between the stones is regarded as Iaminar flow through a pipe, the following relationship
ean be used to find the grouting depth (78):
in whieh:
The design ofthe grouting mortar is dircctly rclated to the wcight and dimensions ofthe
stone to be grouted. The type of applieation is also important, forexample, when
grouting is to be carried out under water sinee the mix cools down quickly and the time
available for grouting is shorter. Experienee gained wh en construeting the breakwaters
at IJmuiden indieates that, in order to obtain a grouting depth oftwo layers ofstone, the
relationship between the maximum partiele size in the mix, dS5' and the minimum
partiele size of the stone d15, should be (27):
- above water-level, d151 dS5 = 5 to 10;
- below water-level, d15/ d85 = 10 to 20.
The design of the mastic is earried out in the way described under mix design tests, sec
Seetion 10.3.1. The optimum sand/filler proportion is determined from tests with
the Engelsmann apparatus, the grouting depth required being achieved by varying the
bitumen, gravellrubble, sand and filler proportions, the mixing temperature and the bi-
tumen hardness.
In order to aehieve a satisfaetory grouting depth a minimum of 50 to 55% mastic is
77
required in ihc mortar, depending on the partic1e size distribution ofthe gravel or stone
and the other cornponents (60).
The maximum partic1e size ofthe stone or gravel ofthe grouting mortar is determined by
the mixing equiprncnt to be used. For normal asphalt mix-plants the maximum particic
size is 50 to 60 mmo For coarser matcrials special equipment is needed.
For good 'surf ace' penetration at least 113 ofthe voids ofthe revetment should be filled
(the upper layer being completely fillcd) (37). For 'pattern' penetration 50 to 80% of the
revetment surface should be covered. With fully grouting all the voids are filled.
A grouting mortar has the tendency to scgregate, sec Figure 11.2. Wh en used for slab
construction it is essential to distinguish between the properties of the mastie and the
properties of the segregated grouting mortar.
The performance of a segregated grouting mortar is determined by the mineral partic1e
skeleton and the degree of self-compaction. If th is compaction is limited thc mastic
properties predominate. With good compaction, however, it is thc partiele skeleton
which predominates.
I I
rncs nc
~
Figure 11.2 Segregated grouting mortar.
Table 11.1 Grouting mortar often used for stone 5/40 kg.
by mass %
gravcl4/16 30
sand A 61
very weak filler 9
bitumen 80/l00 on 100% mineral
78
11.3 Mix properties
11.3.1 Stability
By adding crushed stone or gravel a good quality mix can be produced which has only a
limited cold flow. This can be investigated by large scale slope tests. These tests should be
of sufficiently long duration and the test site weIl chosen.
Above water-level slopes ofupto I : 1.7 can be grouted, below water-level the maximum
slope is I : 3. By grouting carried out in layers these slopes can be increased to I : land
I : 1.5.
11.3.2 Viscosity
The viscosity of'grouting mortar is determined in the same way as the viscosity of mastic,
see Section 10.3.1. The working viscosity will, in generallie between 10 and 100 Pa . s.
1ol.3.3 Penneability
Grouting mortar, being overfilled, is, in itself impermeable. Pcrmeability of the revet-
ment is dependant on the degree of penetration. One can only speak of 'impermcablc',
however, in relation to fully grouting and even th is cannot be guaranteed in all cases.
When designing for hydrostatic uplift complete water impermeability should be
assumed.
When a permeable revetment is required, then preferably not more than 70% of the
crushed stone surface should be grouted. Good mix composition and execution is
essential to ensure that the grouting mortar does not remain in the top layer or sags and
thus forms a dense layer.
11.3.4 Durability
The durability of the grouting mortar is determined by that of the stone and that of the
mortar itself. For the stone the requirement is that it is, in itself, durable (49). For the
dura~ility ofthe mortar reference should be made to Section 10.3.4.
79
12 Dense stone asphalt
Since dense stone asphalt is a slightly overfilled mix it is, on the who Ie, not important
what kind of stone is used. Good adhesion is obtained with limestone.
Limestone 20/40 mm is often used. Use ofthis size is based on the fact that:
it is the maximum size which can be used in conventional asphalt mixers (maximum
about 60 mm);
it is a type which is generally available;
it is suitable for the layer thicknesses typically used;
The stone or gravel requirements are based on (49):
the oversize;
the undersize;
the proportion of filler;
the quantity of flat pieces;
the frost and weather resistance;
hardness;
purity;
a uniform grading;
12.2 Mixes
80
is that compact ion takes places undcr its own weight. Gap-grading is important for
underwater applications where the cooling phaseand, thus the time available for placing
the mix is relativcly short.
The ability to form a dense stabie revetment by self-compaction depends on:
the viscosity of the asphalt mortar (mastie or grouting mortar);
the proportion of stones to asphalt mortar,
The stones form a skeleton which gives a certain stability to the mix in the hot ph ase,
while the mortarhas a binding and load-sprcading funetion. The viscosity ofthe mortar
is important in both the hot and cold phases,
A rclativcly low viscosity is essenrial at werking temperatures to ensure that the stone
asphalt has good workability.
After cooling down the viscosity must be rclatively high in order to prevent any
excessive cold flow.
Generally. deponding on stone size and grading, the mix comprises 50 to 70% by mass
stone and 50 to 30% by rnass mortar. With lower stone contents a stiffer mortar should be
used. For mortar design, sec Section 10.2 and 11.2.
The layer thickness is also a detcrmining factor in the choice of stone size.
Examples of a few dense stone asphalt mixes used are given in Table 12. I.
Table 12.1 Percentages by mass of dcnse stone asphalt and mortar mixes used for the Eastern
Scheldt storm surge barricr and IJmuiden breakwaters.
IJmuiden
Eastcrn ScheIdt below water abovc water
Asphalt mix (rnass %)
- limestonc 10/60 kg - 46.0 -
- limestone \110 kg - 20.0 74.5
- limestone 20/40 mm 60.0 - -
- mortar 40.0 34.0 25.5
rnortar (mass %)
- wcll-gradcd mine ral - 66.0 67.0
- local sand 64.0 - -
- vcry wcak liIler 17.0 15.0 15.5
- asphalt bitumen 801\00 19.0 19.0 17.5
81
The stone size is selected, in principle, based on the layer thickness required. A
number of mixes are then made with various stone contents and different mortar
compositions and, thus, different viscosities. If the stone size is too large for labo-
ratory invcstigation then tests can bc made at the mix-plant.
In order to obtain an impression ofthe hot-flow characteristics slopc tests are carried out
at the required slope,
For asphalt morlar investigations reference should be made to Sections 10.2.1 en 11.2.1.
Dense stone asphalt is an overfilled mix of asphalt mortar (mastic with or without
crushed stone or gravel) and crushed stone which gets its stability from a limited amount
of scgrcgation,
The stability and workability are, in fact, two contrary propertics which are dependent
on:
stone content;
maximum stone size;
stone size distribution;
the viscosity of'thc asphalt mortar at working ternpcratures.
By incrcasing the stone content and the stone size and using a low viscous asphalt mortar,
the stones settie more quickly under their own weight on the slope, there by producing,
more quickly a larger interlock in the stone skeleton. In this way it is possible to design a
mix which is easier to work with and in which the stones settle quickly producing a
greatcr stability in the hot condition than with a mix of smaller stones and a more viscous
mastic.
Use of larger stones givcs a rough surface which has more holding points for waves and
currents.
At normal temperatures the material is viscous, except under very short pcriod loads,
Application on stccp slopes can, bccause ofthe limited stability, be difficult.
The Iines in Figure 12.1 show viscosity related to percentage of stone for various mixes
under the same conditions.
Table 12.2 gives the composition of the va rio us mixes referred to in Figure 12.1.
Tests have been carried out by the Delta Department of Rijkswaterstaat with stone
asphalt.Iayer thickness 0.5 m, on a slo pc of I : 4, at normal tcmperatures. In these tests, a
limestone/mastic mixture, rclativc proportions 65/35, even after a few weeks, showed no
noticeablc deformation.
A mix with limcstone/mastic proportions of 60/40, however, did show some defor-
mation. The compositions ofthe mixes, which we re tested, arc given in Table 12.3.
82
asphaltic concrete.
stone 5 -1Smm
_ ·Ie stone
Figure 12.1 Stab~lity (workability) and composition ofsome asphalt mixes (14).
83
Table 12.3 Composition ofstone asphalt mixes, percentage byweight (24).
weight
mix composition percentage
Mix I limestone 20/40 mrn 65
mastic 35
mastic: Sand A 62
Filler 19
Bitumen 80/100 19
Mix2 lirnestone 20/40 rnrn 60
mastic 40
mustie: Sand A 62
Filler 18
Bitumen 160/210 20
12.3.3 Durability
The mix is dcnse and, therefore, has a good durability. In this respect the density ofthe
layer surface is very important.
84
13 Open stone asphalt
Open stone asphalt is used in the tidal zone and above high water and, also, in the form
of pre-fabricated mattresses under water. The product is patented under the name
'Fixtone',
Because ofthe need for good adhesion, only limestone is used in open stone asphalt. The
gradation most frequently used is 20/40 mmo See also under dense stone asphalt, Section
12.1.
13.1.2 Gravel
In view of the lower adhesion obtained with gravel it is not used in open stone asphalt,
13.1.3 Sand
In principle every kind of sand can be used provided it does not contuin any foreign
matter.
13.1.4 Filler
Preferably the filler must be weak, Limestone filler is preferred. Sec also Eisen 1978 (60).
13.1.5 Bitumen
a. Filter material
Open stone asphalt is so perrneable that it cannot be eonsidered as sand-tight and a
filter must, thcrefore, be used. This can be in the form of:
à granular filter;
a filtercloth
a filter of lean sand asphalt.
85
The filtering propertics of lean sand asphalt and filtercloth best kept in hand. A
filtercloth can, if it acts as reinforcement, have a negative effect, sec Section 20.6.
b. Reinforcing is generally used with open stone asphait mattresses to prevent breaking
during handling. The reinforcing comprises metal gauze or similar material. Steel
cables or synthetie ropes are plaeed underthe mattress for earrying. These are
removed wh en the mattress is in place. Lifting eables whieh are ineorporated into the
mattress ean also be used.
Mattresses must be manufactured very earefully insueh a way that there can be no
direet contact between the reinforeing and the filtercloth. Rust, from steel cables has a
negative effect on the filtercloth ageing process. The minimum. thickness of the
mattress, when using limestone 20/40 mm, is 12 cm; the reinforcing is then 6 cm
above the fiitercloth.
13.2 Mixes
Open stone asphalt is an underfiIIed mix oflimestonc and mastic. Manufacture is in two
phases: first the mastic is prepared and then it is mixed with the preheated stone fraetion.
By using this method of mixing the mastie can be spread very homogeneously over the
surface of the crushcd stone and all the contact surfaces between the stones can be
fixed with a minimum quantity of the mastic. The production of open stone asphait
requires aceurate con trol of the mix composition; espeeially the mastic is very important
for the overal quality. In addition, it is important that the stone does not contain any un-
dersized pieces.
The stone/mastic ratio in the mix is largcly based on the viscosity ofthe asphalt mastie. If
the viscosity is low, mixing is casier but, thcn, only a limited quantity ofmastic is retained
by the stones. The excess ofthe mastie sags and seals the lowest part ofthe layer. With a
stiffmastic mixing is more diffieult but more mastie is retained and the tendcncy to sag is
reduced.
The lower limit ofthe asphalt mastie/stone ratio is determined by the minimum quantity
ofmastic which is needed to completcly coat the stones. This quantity depcnds, to a large
extent, on the mastie viseosity and the mineral grading. The upper limit of the asphalt
mastie/stene ratio is determined by thc extent 10 whieh the mastie tends to sag (20).
In general the composition, is:
- mastie 20% by mass
- limestone 20/40 80% by mass.
For mastic design, sec also Sectien 10.2.
In praetice, the mastie/stone ratio is determined by a sag test in whieh mastie is added to
the mix and the quantity notcd at which the mix is still 'open'. A particular quantity of
86
thc mix is plueed in a tall tube and, after cooling, tbc amount ofasphalt mastic above and
below is recorded using extraction methods and visual observations. In practice the
mastic percentage lies between 17 and 21% by mass.
Typical open stone asphalt mixes are given in Tablc 13.1.
Table 13.1 Composition of open stone asphalt mixes used for the Eastem Scheldt Project.
The stone skeleton of the mix has less stability than a loose pile of stones but the mastic
add a viseous property which, depending on the deformation speed, gives extra
87
stability so that the total stability is larger than for loose stoncs. Wh en deformation occurs
quickly the material reacts elastically.
An impression of the stability ean be obtained by moulding a quantity of the mix using
wooden formwork at the slo pc required and noting how it performs at working tem-
pcratures and in cold conditions.
It appears that:
I. Undcr hot conditions (I100-120°C) mixes with limestone are stabie on steeper slopes
(I : I) than mixes with gravel (I : 1.5). This is due to thc greatcr interlocking of the
limestonc fragments.
2. For long-pcried norm al conditions (30°-40°), howevcr, gravel is more stabie. This is
bccause the contact surfaces between gravel particlcs, being round, are largcr than for
thc angular limcstonc and the adhcsion, thcrcforc, is greatcr. With good compaction,
however, the stability oflimestone mixes can bc improved. In practice compaction is
not carried out.
The viscous behaviour of the mix is strongly determined by the viscosity of the mastie.
The upper limit of thc mastie percentage is dctcrmined by the degrce of saggin aftcr
placing or by the minimum voids ratio required, sec Section 13.2.1. For mast ie a viscosity
of40 Pa. s at 140°C is dcsirablc. Thc limits to viscosity, depcriding amongst other things
on thc measuring mcthod, lie between 30 and 80 Pa . s.
Mix propertics such as breaking strain, stiffness modulus etc., va lues whieh are neeessary
for ealculating an open stone asphalt rcvetment can be cstirnated, generally, with the
help of Figures 13.1 and 13.2.
These figures are based on invcstigations into the propertics of open stone asphalt (72).
Thc voids ratio of open stone asphalt is, generally, between 20 to 25%. The material is,
thus, very permcabie. The water permeability whieh is ofthe same order ofmagnitude as
th at of loosely dumpcd stone of the same nature can be measuredusing a permeability
test carried out with an apparatus designed for large samples.
The permeability dcpcnds on:
the stone grading;
thc mastie/stene ratio.
Invcstigations indicate that, under normal conditions, thc flow in open stone asphalt is
between laminar and turbulent. If open stone asphalt is used with a filtercloth, the
pcrmeability ofthe strueture will be largely deterrnined by thc pcrmcability of the cloth.
88
'08
",-
s
-.z Ë
In
,~7
J I I
'02
, ,
103
! I I " I
Sb.! IN/m2)
! t
Figure 13.1 Smix-Sbilrelationship for open asphalt, determined from the results of ereep and
dynamic tests.
..
o
c
~--
~
,~ 10-3
:~
- Smlx(N/m2)
Figure 13.2 The relationship between the stiffness modulus for n = 10, the initial strain and the
number of loading cycles required to break.
13.3.4 Durability
Open stone asphalt, as the name suggests, is an open mix and the durability thcreforc, is
of great importancc.
89
The durability is also deterrriined by th at of the stone for which there are standard
durability requirements.
For the mix itselfthe following must be taken into account:
a. Aging
This manifests itself in
reduced adhesion between the stone and the mastie ('stripping');
- aging ofthe mastic layer itself;
- sensitivity ofthe total mix.
b. Erosion. This can be investigated with flow tests.
c. Biological attack, This should be investigated with plant penetration tests.
d. Chemical attack, by, for example, polluted water which:
reduces adhesion;
- attacks the mortar.
Some petroleum produets weaken bituminous materiais. This process will occur more
quickly with open mixes. Marshall tests on cylinders of open stone asphalt, which have
been placed for a certain time in a bath containing hot water with 1.5%m oil, indicated
only a limited change in the mechanical properties (30).
The laboratory of the Bundesanstalt für Wasserbau at Karlsruhe has carried out various
tests related to temperature resistance durability (62):
Freeze/thaw tests on open stone asphalt cylinders did not show any damage to the
material.
90
14 Lean sand asphalt
14.1.1 Smul
14.1.2 Bi/lil/Wil
A bitumen which is too hard can lead 10 higher working temperatures. For application
under water, however, this is undesirable. At temperatures over 100°C the water will
boil. This can neutralize the adhesion required between the bitumen and the mineral, see
Scction 14.3.4.
The use of filler, and the associated change in bitumen content, gives, in gcneral, a
strenger material with grealer resistance to erosion which can be used as a permanent
rcvetmcnt. The water permeability is greatly reduced and, since compaction is then
necessary it cannot be applied under water.
14.2 Mixes
Lcan sand asphalt is generally a mix of sand and bitumen, the most frequently used
91
bitumen content being 2 to 6% by mass. The bitumen functions as a binder and tends to
concentrate on the contact surfaces between the particles. In order to obtain a certain
film thickness, the total surface area ofthe mineral particles has to be taken into account
as well as the bitumen content (34).
So, for example, in a hot mix lean sand asphalt, with a mean partiele diameter of 0.1 mm
and a bitumen content of 4% m, the particles have a film thickness of 1 to 2 urn.
The pattern of the voids of the original sand is changed by the addition of the bitumen;
the extent, however, is unknown. Adding of filler above a certain level results in
enlargmcnt of the voids. Only by heavy compaction the voids between the sand grains
are fillcd in such a way with a stiffer mortar, that they are reduced noticably.
Mix design, aimed particularlyon durability and water permeability, is based mainly on
experience. Factors which can influe?ce the properties ofiean sand asphalt are (32): .
1. The bitumen content. This is the critical factor, since:
a. The strenth increases as the bitumen content is decreased;
b. The resistance to wear increases with increasing bitumen content;
c. The permeability decreases with increasing bitumen content;
d. When altering the bitumen content the deformation characteristics change.
A bitumen content of 3% m is definitely the lower limit. It must not be any lower,
since then the durability is strongly rcduccd. A bitumen content of 5% m is the
maximum since a higher percentage produces a lcan sand asphalt which is too 'fat'
which, depending on the application, reduces strength too much. A bitumen content
of 3% m is adequate for teinporary work; for permanent work and filter layers the
content should be between 4 and 5% m.
2. Degree of compaction. A high degree of compaction increases the wear resistance and
the deformation and strength properties but lowers the permeability.
In addition to investigations into basic materials mix design tests can comprise a
comparison with known lean sand asphalt. These investigations can incl~de:
1. Permeability;
2. Erosion.tests (by rolling or by water-jet);
3. Retained stability;
4. Marshall tests;
5. Triaxial tests.
14.3.1 Stability
The stability, in relation to forces aplied slowly is less than for natural sand. With forces
92
which are applied more quickly the stability is greater, see also Section 20.7.
The stiffness modulus of the mix is dependent on the duration of loading and the
temperature and is related to die mineral content and the stiffness modulus of the
bitumen.
Because of the high voids ratio of Ican sand asphalt the bitumen hardening process is
faster than for most dense mixes. Creep tests, carried out on samples taken from al: I
scale test which comprised 96% m fine sand and 4% m bitumen at temperatures of 15°
and 20°C, indicated the values shown in Figures 14.1 and 14.2 (32).
14.3.3 Permeability
Because ofthe limited quantity of bitumen in the mix the sand grains are only covered by
a thin film of bitumen a few microns thick. The bitumen tends to concentrate on the
contact surfaces between the grains, This is the cause ofthe fact that, depending on the
compaction, grain composition and shape, the iean sand asphalt has a high permeability.
With the low degree of compaction which is found in practice the permeability tends to
be similar to the sand of which it is made. With dry lean sand asphalt an 'initial
resistance' has to be overcome before the ultimate permeability can be reached.
o lob core et G
lS C
93
10
loodlng 0.01 MN/m2
c
o
u
o
~
"
103
loadlng durenen (s)
14.3.4 Durability
The durability ofthe lean sand asphalt depends on the permanent binding effect ofthe
bitumen.
For applications under water working temperatures above 100°C have an undesirable
effect on durability, sec Sectien 14.2.2.
The following phcnomcna and properties are relevant to durability ofiean sand asphalt.
94
100
~ 7S
~
~
50
~
ë
~
2S
0 12 14
__ time (we-eks)
95
15 Bitumen membranes
Bitumen membranes are used for making canals, watercourses and banks watertight.
There are two methods of execution:
in situ;
pre-fabricated.
15.l.l Fil/er
Some times filler is used to increase the stability of membranes. The filler has to be in
conneetion with the other matcrials us ed.
15.1.2 Bitumen
The selection of thc bitumen type depends on the application - for example, at low
working temperatures or for a certain desired deformation. For application of blown
bitumen, sec (35) and Section 15.2.1.
15.1.3 Additives
96
3. A wenring surface finish, amongst other things to increase the friction.
This can be achieved by scattering the surface with: .
- sand;
- fine stone particles.
4. lt is advisable to use blown bitumen for welding thc membranes together.
At present membranc design is done empirically, using 'trial and error' methods. Mix
design involves tests on the membrane in the conditioris in whieh it will be used.
There are two types of membranes:
97
5
6_-----1IIIIIi~ I. paper
2. bitumen
3. reinforcing
3 4. bitumen
2 _ 5. polyester film
6. bitumen
7. polyethylcne strip
8. sprinkled sand
15.3.1 Stability
15.3.2 Viscosity
The viscosity ofthe bitumen is important in relation to:
I. the stability of the membrane and the proteetion layer;
2. the workability.
For the viscosity of bitumen reference should be made to Chapter 3.
15.3.3 Permeability
The membrane and the seams must be and must remain watertight under the maximum
specified loads. This property can he investigated using a vacuum meter.
The memhrane must also rernain impcrmcable under deformation.
15.3.4 Durability
The memhrane must he durahle. In this respect the following propertics are relevant:
98
PARTC
Part edeals with the technical aspects of the design of asphalt revetments used in
hydraulic engineering.
Such revetments must satisfy a number ofrequirements in order to function properly. A
review of these functional requirements is given; the designer should take no te ofwhich
of these requirements to apply to a particular situation.
The functional requirements are partly deduced from the loads which can be exerted on
an asphalt revetment. The loads can be distinguished into loads related to the hydraulic
conditions such as water-levels, waves and currents, loads arising from the settlement of
a dikebody and the subsoil and erosion ofthe foreshore and other loads. The influence of
these loads on an asphalt structure are discussed.
Dike design is based on a numberof starting points. In the Netherlands for some
situations these are established; in other situations, however, not. A summary of the
present 'state of the art' is given.
A very important factor in the design and construction of an asphalt revetment is the
nature ofthe dike body and the subsoiI. A paragraph is devoted to the aspects which play
a role in this subject. An attempt is made to indicate in which way the situation can be
influenced favourable.
An asphalt revetment is normally dimensioned on the basis of the loads which result
from the hydraulic conditions, settlements and scouring and, sornctimes, on other loads.
The dimensioning methods for the most relevant conditions are given. The following
situations are discussed:
100
16 The functional requirements of an asphalt revetment
The function ofa dikc is to proteet the area behind from floading. In order to proteet the
dike body, which is generally built up from soil, against erosion it is often provided with
arevetment. Since the revetment is, at the same time, a par! of the dike it can also fulfil
other functions as, for cxample, watertightness. In general, for design purposes, the
revetment may not be used to increase the safety of the dike body, in itself, against
slipping.
An asphalt revetment must, in order to function satisfactorily, fulfil various require-
ments; requirements which stem"partially from the loads which can be cxerted. These
requirements are:
I. The revetment must be so that material from the dikc body cannot pass through it.
Sometimes the requirement is that the revetment should be watertight.
2. The rcvetment must be able to withstand:
waves generated by wind and ships;
- currents and material catried with it such as sand, stones and driftwood;
- uplift water pressures (only applicable to a relatively watertight revetment);
3. The revetment must be able to adjust to settlements and scouring, within limits,
and must remain in contact with the subsoil.
4. The revetment must be stabie.
It should not slip down from the slope, also, during construction. It should, also, be
stabie, as a whoIc, so that it cannot be carried away by the loads which act upon it.
This implies a certain dimension and weight.
5. The revetment must be weather and water resistant to erosion, corrosion, light, wind,
temperature, and ice. The environment should not be able to damage the revetment
or vice versa.
6. Thc revetment must be durable, that is, it must continue to function throughout its
design life.
7. The revetment should, preferably, be aesthetically acceptable. This condition, how-
ever, if it is contrary to other requirements, should never be overriding.
8. In addition the following should be taken into account and guardcd against:
biological damagc by plants, animals and sea organisms;
chemical damage by pollutcd or salt water;
possible land traffic, during construction and when completcd;
vandalism;
rccrcational activities;
vesscls and anchors.
101
The above requirements must, in principle, be satisfied. This is possible by composing
the revetment of one or more materiais. Often, because the various requirements
demand different revetment properties, a compromise must be sought.
The combination ofthe revetment and the dike body determine whether or not the dike
functions satisfactorily, also in the coarse of time. Also it should be possible to construct
the revetment under tolocal conditions. The dike body itsc1f should be such th at a
reasonable cheap, well-functioning revetment can be achieved.
102
17 The dike body
a. The bearing capacity of the dike body determines among others the performance of a
revetment under wave attack and other forces, and, therefore, plays a large role in the
dimensioning. If the bearing capacity is large then often the thickness of the rcvct-
ment can be reduced.
The properties of the soi! such as the modulus of clasticity, the modulus of subgrade
reaction and Poisson's ratio are important, sec Appendix V. They themselves are in-
fluenced by the amount of compacting of the dike body. These propertics can be
determined from, for example, plate bearing tests.
b. A high degree of compaction can, amongst other things, a/vert the softening of a
saturated or almost saturated soil by impact loads, for cxample wave attack, which
can cause loss ofbearing capacity,
A relative proctor density of95-100%, down to a depth ofabout 2 m, can, in general,
in sand reduce the possibility of softening to an acceptable minimum.
Bad, permcabIe, wet soil is prone to weakcning; the presence of mud, in this context,
is undesirable.
c. The perrneability ofthe sandbed is important in conneetion with groundwater flow in
the dike body and, consequential uplift pressures under a relatively watertight
revetment. lt is also important in conneetion with likely softening ofthe sand body.
d. The placing above water of an open asphalt mix on a saturated sandbed can, through
the influx of water, result in the early development of stripping. Vibration compac-
tion can soften a loosely packcd saturated sandbody. Under impermeabie mixes, as
asphaltic concrete, uplift pressures can develop whiie the asphalt is still soft. This
situation can, for cxample, occur by the deliverywater from hydraulic filling work.
e. The dike body should have sufficient bearing capacity to support construction
activities, If the sandbed has little resistance to dcformation it is difficult to compact
and, construction equipment can cause track impressions ('rutting').
After the sandbed has been compacted and made smooth it should not be driven over
or care should be taken to ensure that it is not disturbed.
The dike body is often formed of sand which is reasonably easy to compact. A
* Although this chapter is directly related to the dike body the contents are also applicable
wherever an asphalt revctrncnt is constructcd on an earth structurc.
103
good cornpacteö subsoil gives fewer problems while compacting the revetment, initial
cracking is limited and the voids ratio required easier to achieve.
In some areas in the Netherlands it has been common practice to only smoothen the
sandbed with a bulldozer. This, however, only produces a lirnited improvement on
the original density, On several dike projects. tests have shown that, even at consid-
erabie depth, the compaction was low. It is. in fact, beller to build up the sandbody in
thin layers. with bulldozers. The dike face can th en he profiled accurateIy, also with
bulldozers. Ir this does not produce the compaction required, then a vibration roller
should be used. For th is process it is recommended that the sandbed is first sprayed
with water (Photo 4).
The best dike body construction method, however, is to dump an excess of mate rial.
and then. after ruis has been compacted, to produce the profile required by grading.
The application of a day underlayer is not recommended because of its weak
consistency nnd the possibility of Trost heave'. Ifan asphalt revetment is to be built on
an existing clay revetrnent this should be of a good quality, otherwise it should be
removed. lnvestigations ofthe quality are desirabie.
There are generally na problems with underlayers of inert mine waste or lean sand
asphalt. There can be some problems when laying an asphalt revetment on mine
waste in eenneetion with obtaining an equet revetment thickness.
104
Subsoil can be improved by:
mechanical compaction;
physicallmechanical treatment; an improvement of the partiele skeleton in
combination with mechanical compaction. This method has not yet, generally
been used in hydraulic structures, but perhaps it will be in the future.
f. After constructing the revetment the dike body will tend to settle. If.it has not been
weIl compacted or if there are clay or peat layers in the subsoil, the settlement can be
large and irregular. If the bed, is at the same time highly permeable then it is possible
that thc grain stress only reeovers slowly and that the bearing capacity of the bed
temporarily appears to be insufficient. This effect must certainly be taken into
account with dayey subsoils; good drainage in this case is essential (17). With very
permeable material the situation does not develop.
Thc bearing capacity of a ground mass can be measured using C.B.R. tests, soundings, o'r
plate-bearing tests. It is reeommended that laboratory investigations are carried out to
determine values of permeability, proetor density, friction factors, etc. Sufficient meas-
urements should be made to obtain rcpresentative values.
For the present the Rijkswaterstaat makes the following recommendations for
eompaeting subsoil: The minimum compaction should be 95% ofthe maximum praetor
density. The ave rage compaction should be 98%.
105
18. Design basis
18.1 Safetyaspects
The philosophy of dike revetment design sterns from several starting points. Although
these starting points vary from situation to situation, in the Netherlands, generally. the
following can be posed:
In the report of the Delta Commission (83) for sea dikes, the most extreme conditions
are established by the design level. If the water-level reaehes this design level then,
according to the Delta Commission, there should still be a considerable factor of
safety against breaching. This implies that a revetment, as far that it is essential for the
functioning for the dike, must be able to resist a design water-level with a large
probability. During a storm in which thc design level is reached not all parts of the
dike are loaded to a maximum. The maximum and most critica I wave impact loads
developa little below still water-level. The maximum uplift pressure under the
revetment will occur some hours after the maximum water-level has been reached.
Dune toe protection.
No general basic rules have been formulated for the use of asphalt in dune toe
protection. The effect of dune toe proteetion on erosion during the design conditions
is still to a large extent unknown.
When designing against dune erosion the basis should be the same as that used for sca
dikes. The most important function of dune toe proteetion was often to limit dune
coast erosion.
River dikes.
The following is stated in the report of the River Dikes Commission (84): 'The
commission recommends that improvements to river dikes should be based on a
leading water-level rclatcd to a Rhine discharge of 16,500 m3/s at Lobith. This dis-
charge occurs with a frequency of about 111250'. In the directives for river dikes
(Leidraad Rivierdijken), published by the Dutch Technical Advisory Committee on
Water Defences (Technische Adviescommissie voor de Waterkeringen) in 1984, it is
stresscd, as in the report by the Delta Cornmission, that there should be a large factor
of safety against possible brcaching in design water-level conditions.
Canal dikes and ernbankments, etc.
Dikes and embankments along canals, lakes, reclaimed arcas and polder reservoirs
form a type ofprotection works ofwhich the object is to proteet against a permanently
high water-level. These dikcs are often of limited dimensions. With the exccption of
bow waves from passing ships, there is generally very little wave aetion on these
structures. Exceptions to this are the dikes around large Iakcs, such as the IJsselmeer,
106
where there can be considerabie ware attack and high water-levels can develop in
relation to wind set-up.
The choice between the two depends on the experience of the designer: does he accept
that a certain amount of risk is delegated to the con trol and maintenance by other partics,
and also by economie factors: lighter structures cost less to build but more to maintain.
At the same time, the safety of the structure during the construction period should be
borne in mind and the possibility ofstructural Iailure in this period should be anticipatcd
in the design and method ofconstruction. A solution can often be found by choosing a
favourable time ofthe ycar, construction sequence and method ofexecution.
A dike rcvctmcntis dimensioned with .the help of theoretical modeIs in which certain
basic variables are used to determine design dimensions, such as the revetment thickness.
The basic variables describe, on one hand, the different loads on the structure: waves,
water-levels, structural weight, ctc.; and, on the ether hand, the structural properties:
material properties, geometry, etc.
If the basic varia bles are specific deterministic quantities there are no problems related
to the calculation, apart from the choice of a good theoretical model.
The theory statcs that thc structure in that case will not fail ifthe - deterministic -loads
are less than the - determenistic - strength.
The difficulty lies in the fact that thc basic variables are stochastic quantities, that is,
variables. Loads and stresses are, therefore also stochastic properties. The problem can
be defined as follows: the structure must be designed in such a way that the probability
of failure is acceptably smal!. For this type of design there are three different methods
available (2):
1. The (semi) - deterministic method
In this method the basic load-related parameters are assumed to be adequately high
and thus 'safe' values. Often aver,?-geor safe values are selectcd for the strcngth
properties. The choice of 'safe' loading is mainly based on experience.
107
2. The quasi-probabilistic method
In this method 'safe', what are referred to as 'characteristic' values are assumed for all
basic variables. The characteristic load is, for exarnple, defined as the load which has
5% probability of being cxceeded during the lifetime of the structure. The charac-
teristic strength propertics are then those values which have a 5% probability ofbeing
less than the lower limit, sec also Figure 18.1.
In the building and construction world the margin between characteristic loading
and strength can be given by using partial safety coefficients. Partial safety
coefficients, as defined in 1.5.0. 2394, are then transposed by multiplication into the
total safety coefficient:
m
YIOlal = n
, i=1
Ypartil i
stre09th probabihty
den'ilty function
- loading J strength
I charocteris.hc
strength prope-rty
In practice it appears that, at present, the method most used is somewhere between
deterministic and quasi-probalistic. Variations in the loads are taken into account but
not the structural strength properties.
For loading variables values are mostly selected which have an extremcly low probability
of being exceeded. Avcrage or characteristic values are often assumed for strength
properties.
108
19 Loads
A number of different kinds of loads can be exerted on an asphalt revetment. These can
be roughly subdivided into loads caused by hydraulic conditions, loads resulting from
settlement and scouring and loads due to other factors. In general, revetment design is
based on the first two categories and also on other loading types which develop regularly
or can be expected to occur with reasonable probability. Sometimes it is not practical to
design for certain loads, because, although they are very large it is cheaper to repair the
revetment or to take preventative measures.
The most important conditions and the related loads are treated gene rally in thc
following sections. The most common types of loads and methods of design are dis-
cussed in subsequent chapters.
19.1.1 Water-levels
The water-levels in front ofa dike may vary. For dikes on the co ast, in inlets and estuaries
this variation will mainly be caused by tides, winds or both in combination. In the upper
reaches ofrivers the water-level is mainly determined by the discharge; this can also have
effect in lower reaches. In canals, waterways and polder reservoirs water-level variations
are due, principally, to inflow and outflow through locks, to rainfall, and to waves caused
by ships; in lakes and reservoirs water-level variations are caused by the in- and outflow
of water and by wind (I). Wind gcnerated waves also give short-term water-level
variations.
The duration ofa change in water-level can vary greatly. Variations due to wind and ship
waves last only a few seconds, tidal variations on the other hand have periods of several
109
hours, long-term wind effect can last a few hours or days and river discharges can affect
the water-level for days to weeks on end.
A phreatic line is set up in the dike body in conneetion with the water-level in front ofthe
dike. Variations in the water-level produce changes in the phreatic level. The extent of
these changes depends, amongst other things, on the duration and extent of water-level
changes, thc geometry and permeability of the subsoil and the dike body, and the
relative permeabilty of the cover layer. When the water-level outside the dike is lower
than the phreatic line and water cannot flow freely out ofthe dike because the revetment
is relativcly impermeable then uplift pressures can develop under 'the revetment. This
will tend to lift the revetment. In this situation the revetment should be designed as dis-
cussed in Section 20.1.
The soil under the phreatic line is saturated. Weak soil under the cover layer can, under
a sudden lead, bc softened and lose its bearing capacity. Although this phenomenon
should be taken into account in the dike design, in general it is not practical for it to form
a basis for revetment dimensioning.
The maximum allowable slope angle is also dependent on the water-level in front ofand
in the dike, see Sectien 20.7.
F~nally the water-level also affects the wave elimate and the currents at the dike.
19.1.2 JVaves
Waves, at least those dealt with in this section, are generated by wind. The factors
affecting waves include the wind speed, the fetch, the wind duration and the water dcpth.
A wave can be expressed in terms of:
IlO
icant wave height (Jlsig)' This is the avcrage of the highest third of the observed waves.
This value agrees weIl with the wave height which, based on a Raylcigh distribu-
tion ofwaves in a wave field, is exceeded by 13.5% ofthe waves.
1. Deep water
The wave movement is not influenced by the waterdepth; the speed ofpropagation is
related only to the wave period. The movement ofwater particles in the wave at the
bottom, is not notiecabie.
2. Shallow water
The waves are greatly influenced by the bottom; the wave cclerity is determined by
the water depth alone. The horizontal velocity of the water particles in the wave is
independent of the vertical position of the partiele and is very strong at the bottom.
3. Intermediate water
The wave movement is influenced by both the wave period and the water depth.
Generally these categories are expressed as:
As the waterdepth (d) deercases a wave ofheight H travelling from deep to shallow water
will increase in height to a certain limiting value given by H Id = y, y is the breaker in-
dex, after which the wave starts to break, sec Figure 19.1.
A wave approaching a dike slope will, depending on the water depth in front ofthe dike,
the wave length, and the wave height have already brok en or will break on the dike face.
In the case ofthe latter the breaking process wiIl be influenced also by the dike slopc.
There are a number of breaker types:
1. Spilling breakers:
The wave front, in th is case, is steep but not vertical. The wave begins to collapse at
the crest and the breaking mass of water runs into the trough of the preceding wave
and up the wave slopc.
2. Plunging breakers:
A 'tongue' extends out from the crest and falls freely into the preceding wave trough
or onto the dike face.
3. Surging breakers:
These develop with low waves and steep dike slopcs. The wave builds up like a
plunging breaker but before the crest tongue has formed the toe of the breaker surges
up the slope and the breaker develops no further.
It is possible to get an impression ofwhich type ofbreaker will devclop with the helpof
the so-called ~ parameter.
111
in which:
d H = wave height
d = wave depth
L = wave length
Hb = breaking wave height
db = water depth ot breaking I
A dike revetment must be able to resist the forces exerted by waves. In the design
distinction is made between plate-type structures and structures built up of loose elc-
ments.
Plute-type revetments are, for example, asphaltic concrete revetments, mastic slabs, fully
grouted rubble layers, open and dense stone .asphalt revetments and layers of
lean sandasphalt.
The largest loads which waves exert on a plute-type revetment are impacts from plunging
breakers. The dimensioning method is given in Section 20.2. Structures built up from
loose clements are for example pattern grouted riprap revetments. Riprap slopes, with
surface grouting form, an intermediate type of structure between fully grouted riprap
and pattem grouted riprap.
Water flowing on and off the revetment can cause shear which has an abrasive effect.
This aspect is discussed in Section 20.5.
At the same time pressure differences can be built up by wave movement across a
relatively waterimpermeable revetment. This results in upward prcssures which tend to
112
lift the revetmcnt and reduces the resistance to slipping. The pressure differences can
also produce a hydraulic gradicnt in the groundwater which can cause the move ment of
sand along and/or through the revetment, The result can be a cavity under the re-
vetment.
There are no spccific dimensioning methods to deal with this phenomenon. A saturated
subsoil can be softened by a sudden loading, for exarnple, a wave impact, and lose its
benring capacity.
The water movements in a wave, whether or not it has brokcn, can erode the bed at the
toe ofa dike. In order to prevent this a bed proteetion is often constructed. Ifthe bottom
proteetion is extended to whcre the wave movements are too weak to transport the sand
particlcs, thcrc will bc no problems provided that therc are no other streng currents
present. To guard against erosion the bed proteetion should bc sufficiently long so that
any scouring stops at some distance from the dike toe. This aspect is discussed further in
Sectien 20.6.2.
A dcnsc underwater bottorn proteetion can bc lifted up by differences in prcssure,
above and below, caused by translatory or standing waves. This phenornenon is
discussed further in Sectien 20.3.2.
It is usual to design arcvetment for extreme conditions referred to as the design
boundary conditions. \Vhat should not bc overlookcd, howevcr, is th at wave farces,
although they are not always extremc1y large, can occur frequently and that a lot of
minor damages can eventually lead to failure. Since asphalt is sensitive to fatigue
- the strcngthreduces in relation to the loading frequency - this propcrty should not be
overlooked in the design.
Waves, acting on arcvetment ofloose elemcnts, such as riprap, will exert certain forces.
Thc flow pattern causcd by wave action on thc rcvctrncnt is complicated and, as aresuit,
it is not possible to give a good theoretical assissment of the problem. Formulas for
determining the weight of revctmcnt elcmcnts under wave attack are wholly or partly
empirica!. An example is theHudson formula, sec Section 20.4.
19.1.3 Currents
Flowing water can have an eroding effect on an asphalt revctment apart from th at
caused by material which it is transporting. Pieces of wood, stone, etc., being carried by
the water, can hit the revctmcnt and cause damage, especially in the breaker zone, sec
also Section 7.5.3.
113
Flowing water can get hold on the side of thin asphalt plates to flap. At the same time the
pressure differences which develop on a platetype, watertight bed proteetion can cause it
to lift. Methods of design against this arc given in Section 20.3.
As.is the case with wave actionit is not possible to adequately describe the loads on a
loose clement revetment due to currents, thcoretically. Thc weight of the revetment
clements must be determined using formulas developed empirically.
N on-stcady flows, because of thc fluctuations can induce fatigue loads onto an asphalt
revetment. The effect of currcnts on the different types of asphalt is trcated in Section
20.5.
Finally, currents can crodc thc bottom in front ofa dike and the toe can be undcrmincd.
This can be prevented by using a bottom protcction, sec Section 20.6.2.
19.2.1 Settlement
Settlcment is caused by the deformation ofthe dike body and the subsoil. The revetment
must, within limits, be able to adjust to irregular settlcment. Since it is a viscous material
the ability to adjust is determined by its composition. Overfilled mixes, such as mastic,
are very flexible, whereas mixes in which the voids are not completely filled with bi-
tumen, such as asphaltic concrete, are less. .
If the speed of irregular settlement is great then the asphalt platc cannot adjust
immediatcly and a cavity will develop under the cover layer. Thcn, ifthe bending stress
caused in the material exceeds the maximum allowable, the structure will fail. This
manifcsts itsclf in crack development around the edgcs of the settlement. Large scttle-
ments can cause significant changes in the thickness and material propertics of the
original revetment. Simultaneously other forces, for exarnple, a wave impact on the
revetmcnt before it has adjustcd to the settlement of the subsoil can cause extra tension
and possible structural failure. It is very important th at such settlernents remain as small
as possible. A methad of designing a plute-type rcvetmcnt to cape with settlcmcnts is
given in Section 20.6.1.
Settlements of the dike body itself, can be lirnited by using appropriate construction
methods: construction of the sandbcd in layers, prcferably with a certain amount of
e?,cess material to be removed by grading, will ensure th at it is well-compacted, sec also
Chapter 18.
Subsoil settlements, to some extent, must bc accepted. If'unacceptably large settlcment is
expected, th en it may be possible to improvc the siibsoil or to excavate and replace it.
It is important th at any subsoil discontinuities, for example, old watercourses, which
could lead to uneven sett\ements, are taken into account (Photo 5, 6, 7). Also joint
construction, should not be overlookcd in relation to this. Because of fa ulty construction,
material can vanish from the dikc body and cavitics can dcvclop undcr the revctmcnt.
114
In genera! an asphalt revetment is as most materials unable to adapt to cavities which
develop quickly. ldenlly the dike design should be such mat cavities cannot appeaL
19.2.2 Scouring
Scouring mostry develops when material in front of the dike is eroded by. for example.
waves or currents. Erosion can propagatc under the revetment. It can be 50 exrensive and
rast that revetments, for exa mple asphaltic concrete and grouted riprap. cannot adjust.
The dike should be öesigned in such a way that scouring cannot develop, with, for
Puoto 5 Deforrnation of all esphaltic concrete revenuent caused by irregular seulement of the dike
body
115
Photo 6
The eau se of the senlement
116
example, a suitable toe and bed proteetion. Asphalt mastie, being a fairly viscous
material whieh ean adapt to relatively large scouring, is often used as bed protection.
Design methods for th is iype of application are given in Section 20.6.2., see also
Photo 8.
Table 19.1 reviews other important 'loading types' which can affect the various revet-
ment matcrials. The numbers in the table refer to thc, remarks given below. These
factors must be taken into account. In general. however, there are no definite rul es
which can be applicd.
117
3 An anchorwhieh is dragging or has hooked up on the edge ofthe revetment can cause damage.
Falling anchors can punch a hole in the revetment. If the asphalt structure is designed as a
watertight layer then this type of damage cannot be allowed and anchoring here must be
forbidden. Alternativc1y the revetment should be design cd to rcsist these loads.
3.1 Sunken pipclines, syphons and underwater mains are occasionally protected against anchors
by using a grouted 'rip-rap or mastie cover.
It has been found that a 1350 kg Danforth anchor will not break through a 900 mm thiek layer
ofrip-rap (10/60 kg). The danger ofbreaking through is much less with a fully grouted layer of
stone. An anchor tends to slide on a mastie apron and, therefore, do no harm. Investigations
indicate that the thickness of the proteetion construction, rc1ated to a layer of rip-rap 10/60 kg
with a thiekness of am depending on anchor size, should be (26):
- fully grouted a thiekness ofO.5a m
- mastie slab a thickness of 1I3a m.
4 Floating debris and ice can hit the revetment and damage it. Damage can be avoidcd, as much
as possible, by:
- using arcvetment with a suitable bitumen hardness, a smooth surface, and adequate
thiekness;
- the timc1y removal of debris from the dike face slo pc.
5 Normally a dike is accessible for recreational activities and the design should, therefore,
inc1ude amongst others:
- special parking places ifthe revetment is inadequate against the Ionding ofcars
- a hard binder, a minimum number of'gripping' points and a good quality surface finish to
prevent vandalism.
6 The design should take into account traffic on the dike during both the construction phase and
on completion. Construction access roads should be provided. In addition the size ofthe dike
and its components, the method of construction and the mixes should be adequate. Specific
dimensions can be derived by using conventional road construction rnethods (94).
7 Since asphalt is visco-clastic permanent features, such as pipelines etc. can cause deformations
which eventually may lead to damage. Special provisions should be made.
8 The breaking of stones out of the revetrnent can be limited by using large stones and good
grouting.
9 Since lean sand-asphalt filter layers and cores are ultimatc1y covercd, they are only prone to
damage dunng the construction ph asc. Damage to filter layers duringconstruclion, may not be
allowed.
10 Individual stones can be jerked relativc1y easilyout of the revetment.
118
20 Design methods
In the following sections design methods are given for the most common applications of
asphalt rcvctrnents, including:
A dense asphalt revetment against hydraulic uplift pressures resulting from quasi-
static conditions.
A plute-type asphalt rcvetment against wave impacts.
A dense underwater bed proteetion against uplift pressures caused by currents and
waves.
A surface- or pattern-grouted crushed stone layer against wave action.
An asphalt revetment against currents.
An asphalt revetment adapting to irregular settlement and scouring.
Determination of the maximum dike face slope is also discussed.
Design methods are not given for all types of loading situations. The methods de-
scribed can probably also be applied to loadings other than those discussed.
119
• Uplift pressures can develop during construction and for some considerable time
afterwards if in the vicinity of the revetment, sand is moved by means of hy-
draulic transport.
Dynamic conditions:
Uplift pressure develops in the dike body when the water-level outside is lowered
locally, over a very short time period, by a passing ship.
• Uplift pressures develop wh en wind waves produce changes in water-level on the
dike face.
Dynamic conditions which can cause uplift water pressures are not discussed further
here. Often the time interval in which they act is sa small that insufficient water can flow
to develop pressures of any consequence. Further information is given in Section 20.3.
the height, duration, and form oftime-dependent boundary conditions such as storm
surges and tides in front of the dike, and the potential on the rearside of the dike: the
polder level, the drainage ditch level, etc.;
the permeability and the differences in permeability ofthe soil in and under the dike
body;
the dike geometry: dimensions; dike face slopc; berms; toe level;
the water storage capacity of the subsoil;
the level of the foreshore in front of the dike;
the level ofany impermeable layers, for example, clay, in the subsoil;
the length of any sheetpiling in the toe;
the presence and type of any drainage systems in the toe or elsewhere in the dike
body.
A drainage system is somctimes installed in the dike to 'contrcl groundwater move-
ments. By using a toe drainage it is possible to completcly or partly prevent the
build-up of uplift pressure. It is important that such drainage systems continue to
function throughout the lifetime of the structure.
Bccausc many ofthe above factors are variabie it is not possible to give general rules for
determining the amount of uplift pressure which can develop. It is always advisable,
certainly for large projects, for sites where the subsoil is not homogeneaus, when a
permeabie layer is present under the revetment, or if the revetment design is very
different fram that schematised in Figure 20.1 to determine the uplift pressures using
electrical analogues (52, 53, 85) or a finite clement method of calculation (79).
The Van der Veer method can be used to obtain a very prcliminary estimation ofuplift
pressures. This methad has, however, drawbacks, the most important being:
120
The groundwater level has to be estimated.
The revetment must be schematized as shown in Figure 20.1.
The Van der Veer method often gives va lues which appear to be too low in comparison
with electrical analogue results.
0)=0
Figure 20.1 Schematization of the revetment for the Van der Veer formula.
T!J.e maximum uplift pressure is determined for stationary flow, - constant horizontal
supply of groundwàter - and non-stationary flow (51). The maximum uplift pressure, P,
develops at the waterline:
121
The coefficient c is given by:
stationary flow:
c= v 1- --(v
a+v
)"/0
non-stationary flow
with
c= n1 arccos [ ( v
2 a+v
),,/0 - I] with () = arctg (11)
tt
+ 2"
stationary flow:
c- _ V ( a+q+v
1- v ):</0
non-stationary flow:
I
c= - arccos
tt [2 ( a+q+v
v ):</0 _ I]
.~
. '. v .
a a
Figurc 20.2 Schcmatization of' a toe proteetion and a sheet pilc wall
122
When making a preliminary estimate for tides and storm surges the parameter v, can be
taken as 50% of the difference between the highest and the averuge outside water-levels.
For long-term water-level differences, such as in reservoirs and in high water conditions
in rivers \' is taken as 100% of the difference.
20.1.2 Design
DESIGN CRITERIA
Wh at is the effect of hydraulic uplift pressures on a dense asphalt revetment?
a. If the weight component of the revetment down the dike face is greatcr than the
frictional resistance then the rcvetmcnt will tend to slide locally. The revetment will
hang 'on higher parts and rest on lower parts where the frictional resistance is still
sufficiently large. As aresuIt deformation - stress and struin - will develop (53).
Bccause the asphalt is viscous the deformation will be permanent. With a series of
loading cycles the deformation can become so large that the material will yield. In
addition signs offatigue will appear.
The area of greatest uplift pressure will move together with the outside water level
down the dike slope. The section ofrevetment which originally supported tbe section
above will, at a certain condition, also slide. With successive high waters the revet-
ment will, thus, tend to creep like a caterpillar down the slope.
b. If'the hydraulic uplift pressure is larger than the weight component normal to the dike
face then upward forces will develop which can lift the revetment. In the resulting
cavity underneath the revetment, sand movements can take pi ace which prevent the
rcvetrnent from returning to its original profile. Because these sand movements are
downwards there is a tendency for bulges to develop down the slope and subsidences
on the upper parts. In view of the characteristics of asphalt the buiging can on the
long-term or with regular loading, be considerable and continuing.
The following design criteria can be set out:
I. Sliding criteria
The revctment should be designed so that it does not slide under frequently occurring
loading situations such as spring tides,
2. Uplift criteria
In loading situations which occur rarely, such as storm surges, the component of the
weight of the revetment, normal to the dike face should be greater than the uplift
pressurc caused by the water.
3. Equilibrium criteria
The revetmcnt must be in equilibrium as a whoie.
Remarks
In order to limit the uplift pressures an open revetment can be used in the area on the
dike face where the grcatest pressures occur, mostly in the tidal zone.
123
The uplift water pressures can be schematized as shown in Figure 20.3. The uplift
pressure must be determined by the designer. Determination of the maximum uplift
pressure (<Jwo) is treated in Section 20.1.1. The variation of the pressure can also be
determined using an electric analogue or a finite clement calculation. The term <Jwo' used
in the following formulae represents the maximum hydraulic uplift pressure. The Van
der Veer mcthod and the electrical analogue give the maximum potential difference, p,
in metres of water, at the surface of the revetment. The uplift water pressure, <Jwo• is then
obtained by adding h cos exto the value of pand multiplying the whole by Pwg (80), sec
also Appendix lIl.
\
\
cW : Pw· 9 Ip + hcosa 1
The dimensions ofthe revetment can be obtained using the following formulas, sec also
Appendix lIl.
I. Sliding criterion
f·<1v.o
11> (}".g'(fcos a-sin a)
2. Uplift criterion
124
reduced. In this case the maximum value of the hydraulic uplift prcssurewhich would
be reached in the most extreme conditions can be used.
Symbols used:
h revetment thickness (m)
(Jwo maximum uplift pressure (Nz m'')
For the sliding criterion (Jwo is determined for frequcntly occurring con-
ditions; for thc uplift criterion, conditions which occur vcry rarcly are uscd
a slopc of dikc face (dgr)
Pa asphalt bulk dcnsity (kg/rn'')
Pw density ofwater (kg/rn")
g acccleration due to gravity
f coefficient of friction: f = 'tg 9 if 9>0, else f = tg 0
9. angle of intcrnal friction of the subsoil (dgr)
(} angle of friction between the revetment and the subsoil (dgr).
3. Equilibrium criterion
See Section 20.7.
TOE PROTECTION
Mustie, in the form of a horizontal or al most horizontal slab, can be used in front of the
toe of a dike, see figure 20.4.
Ifa mastie slab is sealed directly onto the toe ofa dense revetment very high uplift water
pressures can develop under the whole construction and a very thick revetment would be
required. Ta avoid this an open 'berm' can be used between the slab and the toe or good
drainage must be provided.
slab
Figurc 20.4 Hydraulic uplift pressures under a slab at the front of a dikc.
125
The uplift criterion applies to the slab.
In the first approximation:
,,>---- (Jw
In which:
aw = maximum uplift water pressure under the slab (N/mZ)
h slab thickness (m)
Ga bulk density of mastic (kg/m-')
g acccleration due to gravity (m/s-)
Cl: = angle of inclination of the slab (dgr)
If it is likely that scouring occurs and the slab has to adjust to this (Figure 20.5), thc
following checks must be made (4):
slab
.' ."
open eenstrucnon
GROUTEDRtP-RAP(crushed stone)
In thc past it was often recommended that, in that part of the dike face where thc largest
hydraulic uplift pressures would occur and where the sliding criterion would be ex-
ceeded (in the Netherlands, in the tidal zone), not to use revetments like asphaltic con-
crete. Material with a more definitc skeleton structure such as (grouted) tip-rap was
recommended. \Vith such a material the normal strcsses are transferred beller to the toe,
An asphalt revetment with a definite skeleton structure will behave less viscous than a
mix in which all the particles are coated with bitumen. (Another solution, ifit is possible,
is a watcr-pcrmeable revctment.)
A fully groutcd stone layer has relatively large intcrnal stability. Therefore, in the past,
thc design was never based on the sliding criterion; under extreme conditions the de-
126
sign was bascd, simplyon uplift. It is essential that the revetment is well supported
by, for example, a toe construction.
A fully grouted stone layer is, in principle, impermeable, although due to lack of
adhesion between the stone and the grouting mortar, there will be a certain amount of
permeability. No account ofthis should be taken inthe design.
ASPHALTIC MEMBRANES
Asphaltic membranes must be watertight and must remain so under the water pressures
which develop. The value ofthe limiting pressure can be found from a permeability test;
sec, for example (35) or derived from the manufacturer's specifications. It should not be
possible for uplift water pressures to lift a membrane, that is, the proteetion layer should
be sufficiently heavy. The dimensions of the proteetion layer can be found using uplift
criteria:
aw
h~----
Q .g. cosa
In which:
A wave impact occurs when a mass ofwater from a plunging breaker strikes the slope at
127
great speed. A wave impact is, in fact, regarded as a pressure which acts over a certain
width, To obtain the appropriate dimensions the impact is schematized as a line load.
P = p'b
where:
- Maximum pressure
P=Gw·g·q·/f
in which:
slopc q
I: 2 2.3
I: 3 2.7
I: 4 2.3
I: 6 2
The schematized width over which the maximum pressure is considered to act:
b = 0.4· IJ
128
The duration of the pressure effect, t sec, is, depending on the particular model:
slope ::; I : 3; t = 0.06 . HII2
slope 2':1 : 4; t = 0.18 'HII2
The length of the wave impact is dependent on the angle of wave approach to the
. slope and the speed of propagation of the wave. The larger these factors are, the
shorter is the impact length.
-' A breaking wave hits the slope at a distance MI below still water level (SWL), see
Figure 20.6. The 'area' in which /j./z lies is shown in Figure 20.7.
1:4 1:5
stcpe 1: n
Figure 20.7 The point, uh below SWL, where the wave impact hits the slopc, related to the wave
height Hand plotted against the slope 1 : n.
In the above the parameter H is the height of a single wave. In practice the load on the
revetment wil! be due to an irregular wave train containing a large number ofwaves of
different height and frequencies of occurrence. The significant wave height, Hs, which
characterises a particular wave field can be used for determining the wave impact. The
129
number of times that this wave occurs is selected so that the samc total 'fatigue load' is
reachcd as th at caused by the wave field as a wholc, sec Appendix 1.2.The calculation of
wave impact should take into account the fact that only a small number of waves in the
field will cause actually an impact on the revetment.
a. Statie; that is loads which are always present. The way in which a construction reacts
to statie loads depends, amongst other things, on the size of the load, the stiffness of
the revetrncnt and the subsoil, and the thickness of the revetment.
b. Dynamie; that is time-dependent loads. In addition to the factors mentioned above
under statie loads the speed, frequeney and type of loading, the density of the
revetment material and thc damping and dircctly rclated mass ofthe subsoil are also
important. Wh en the rcvetmcnt is frequently loaded the asphalt propertics are alter-
cd: the strain at break reduces. This phenomenon is known as fatigue.
In th is manual the statie solution is applied to the sclccted schernatization, sec Appendix
U.I. The number of loading eycles is taken into account in the calculation of the
breaking strength of the matcrial. The duration of loading is incorporated into the
stiffness modulus of the asphalt mix.
The loading is schematized as a line load. Since, in praetiee, the wave impact is a
distributed load, corrections are applicd.
This schematization is not so suitable for eomplieated constructions (varying layer
thiekness, rnulti-layer systcms, joints etc.). In these situations a more extensive calcu-
lation involving, for example, finite clement methods can offer the best solution.
When designing it is essential to know the asphalt and subsoil properties. Preferably
data should be obtained by earrying out specific tests for cach design. Ifsuch tests are not
possible, use can be made of the general values given in Tables 20.1 and 20.3. The
matcrials used in thc construction should then be carefully checked against these values.
130
Tablc 20.1 Moduli of stiffncss and related initial stresses and strains at break for different asphalt types. (With the exeeption of open stone
asphalt, the values are deterrnined using Figures 6.1., 6.3., and 6.4. with whieh values for the lower loading cycles have been
extra pola ted),
Initial strain at failure Initial stress at break
number ofloading cycles number ofloading cyc1es
mix stiffness
type modulus N/m2 I 100 1000 10000 100000 1 100 1000 10000 100000
Asphaltic
concrete _. 7: 109 . 1.2· 10-3 5.2' 10-4 3.4 . 10-4 2.5' 10-4 1.6· 10-4 8.4· 106 3.6' 106 2.4· 106 1.8· lOG i.t lOG
Asphaltic
mastic 1.109 8.6· 10-3 3.4.10.3: '2.2' 10-3 1.4· 10-3 8.6' 10-1 8.6' lOG 3.4· lOG 2.2' lOG 1.4 . lOG 8.6' HP
Densc stonc /
asphalt 4.5' 109 2.3' 10-3 9.2' 10-4 5.8' 10-4 3.7' 10-4 2.3 . 10-4 1.107 4.1' 106 2.6· 106 1.6· 106 I· 106
/
Openstone /
asphalt 7, IO~ 3.4· 10-3 1.3. 10-3 7.9· 10-4 4.8' 10-4 3.0' 10-4 2.4· 106 9.1 . lOS 5.5 . lOS 3.4· 105 2.1 . lo-~
Lean /
sandasphalt 1.109 1.1 . 10-3 4.2' 10-4 2.6' 10-4 1.7· 10-1 '1'.1. 10-1 1· lOG 4.2' 105 2.6 . Io-~ 1.7· 105 1.105
-
Vol
Table 20.2 Mix eompositions of the asphalt types given in Table 20.1.
Asphaltic
concrete 46.9 39.5 7.5 6.1 5
mastie - 64 17 19 0
Dense stone
asphalt 60 25.6 6.8 7.6 5
Open stone
asphalt 82.9 9.9 4.4 3.1 31
Lean
sand asphalt - 96 - 4 30
The asphalt properties - modulus ofstiffness and stress at break - are temperature and
loading duration dependent. Since the heavy storms, against which the revetment is
mostly designed, occur mostly in the winter season a temperature criterion ofSoC can be
accepted (13). The loading duration is wave height-dependent and can be deduced from
Section 20.2.1. Variations in this parameter, within practicallimits, have little effect on
asphalt properties. .
Some properties of the most used asphalt types are given in Table 20.1.; the mix
compositions of these types are given in Table 20.2. Bitumen 80/100 is used by which an
unfavorable loss in penetration is. taken into account. The temperature is fixed at SOC
and the loading period 3 seconds.
The stresses at break for loading cycles ofiess than 10,000 are found by linear extra po-
lation on a log-scale. Although th is mcthod is not completely correct it gives presumably
safe values.
Table 20.3 General values for the modulus of subgrade reaetion of differentsoil types.
132
For strongly deviating mix compositions, temperatures and loading conditions the mix
eompositions can be determined using the method given in Part A, Sections 6.3.\. and
6.3.2. The Poissons ratio of the mix follows from Section 6.3.4.
The parameter defining the subsoil is referred to as the modulus of subgrade reaction.
General values of th is parameter are given in Table 20.3. (10, 50).
20.2.4 Design
Design criteria are selected sueh that the stresses and strains developing in an asphalt
plate ofa certain thick~.ess due to bending moments do not exceed the allowable values.
Plate thiekness can be determined using the calculation model developed in Appendix
l.I. for a plate of constant thickness on a delaycd reacting elastic subsoil.
The formula reads:
h = 0,75. V2716 . (I - I v)
2 • ( P)4 . (~)
(Tb C
in which:
Usually the revetment isxlesigned for a design parameter ·such as the significant
wave height, lis, which characterises the wave elimate in a severe storm or at an
extremcly high design water level.
If the revetment is also subjected to loads ofa normal daily wave elimate then this should
be taken into account in the layer thickness calculated with the design Hs. A method for
doing this which gives safe values for Dutch conditions is given in Appendix 1.2.3.
Distinction should be made between:
\. Thàt part of the revetment on which only the design condition, Hs' 'acts. No
correction is necessary here.
2. That part on which the design conditions act together with the normal wave climate.
3. That part on which only the normal wave elimate acts (and not the design wave).
That part ofthe revetment which, for example, lies above the (spring) tide zone is classed
in Category \. The revetment in the (spring) tide zone is acted on by the normal wave
elimate but, in general. not by the design wave, Hç; which occurs at higher water levels.
133
This part is c1assed in Category 3. Dikes with a deep foreshore can be c1assed in
Category 2.
General values of layer thickness are given in Figures 20.8. to 20.12. for some standard
mixes, for various significant design wave heights and subsoil parameters. These valucs
are based on assumptions for application in Dutch conditions, see Appendix 1.2.2.
The assumptions are:
Hs(m) ns
2 9900
3 8000
4 6950
5 6200
6 5670
7 5250
8 4900
9 4630
10 4400
In order to obtain an optimum design or ifthe design conditions differ greatly from these
assumptions, then the calculation of layer thickness can deviate from the method used
for Fig1;1res20.8. to 20.12. .
Adaptations can be made by:
- ..
changing the mix composition;
treating/compacting the subsoil;
changing the dike geometry.
It is then essential to carry out extra checks on site and in the laboratory. This wiII also
indicate the programme for the execution requirements.
134
t 0.8
0.8 0.8
'"c: Hs(m!
'";S
<J 0.1. Hs(m) 0.1.
Hslm)
6
6
ë 5 6
~ 0.2 0.2 5 5
I. I.
c; I.
> 3 3 3
e
0
107 108
modulus of
109
subgrade
2
0
107
reaction
108
IN/m3 )
109
2
:l======
107 108
=2
109
Figurc 20.8 Necessary layer thickness for a revetment of esphaltic concrete, plotred against the
modulus of subgrade reaction and for various significant wave hcight and slopcs (sec
the text above for the basis ofthe graph).
0.8
'"c:
Hslml
'"
<J
;S
0.1. Hslml 0.1.
6
ë 6
5
E 0.2 0.2 5
I.
c; I,
> 3 3
e 2 2
0
108 109 107 108 109
modulus of subgrade reaction I N/m3)
Figure 20.9 Neccssary laycr thickness for a revetment of mastic, plotred against the modulus of
subgrade reaction and for various significant wave heights and slopes (sec the tcxt
above for the basis ofthe graph),
135
t 0.8 0.8 0.8
Figure 20.10 Necessary layer thickness for a revetment of dense stone asphalt plotted against the
modulus of subgrade reaction and for various significant wave heights and slopcs
(sec the text above for the basis of the graph).
ijl
Cl Hslm)
c Hs(m)
:Q 0.8 6 0.8 0.8 Hs\m)
:5 6
6
ë 5 5
0.4 0.4 5
tOt======~
4
4
3
----2 -----2 3
o o
107 108 109 107 108
modulus of subgrade reaction (N/m3)
Figure 20.11 Nccessary laycr thickness for arcvetment of open stone asphalt plotted against the
modulus of subgrade reaction and for va rious significant wave heights and slopes
(sec the text above for the basis ofthe graph),
136
1.0 1..0 1..0
]
IJl
~ 2.0
c
.Y.
U
6 Hslml
;S 6
5 6
ë 1.0 1.0 5 1.0
'" I. 5
E I.
<;; 4
3 3
e> 2 2
3
2
0 0 0
107 108 109 107 108 109 107 108 109
modulus of subgrade renetion I N/m3)
Figure 20.12 Necessary layer thickness for a revetment of lean sand asphalt plotred against the
modulus of subgrade reaction and for various significant wave heights and slopes
(see the text above for the basis ofthe graph).
137
20.3 Design of underwater bed proteetion against hydraulic uplift pressures caused by
currents and waves
A mastic slab is often used to proteet the bed against erosion caused by currents.
In extreme situations fluctuations in the flow of water and groundwater can create
pressure differences across a bed protection. If the pressure abovc a revetment plus its
weight is less than the pressure underneath, the revetm~nt will tend to be lifted (81).
This should be prevented. If a slab lifts a cavity develops underneath into which water
flows, the cxtcnt depending on the duration of the pressure difference. Because of the
viscous propertics of the asphalt mix it will deform. Depending on the duration and the
quantity ofinflowing water, the deformation can be so large that the slab breaks.
A simple solution to this problem cannot be given since the pressures which dcvelop vary
from situation to situation. For simple cases the water pressurè can probably be es-
timated using simple formulas. For more complicated cases an extensive calculation
program me or an clectrical analogue can offer the solution.
More important than the lifting ofthe revetment by exccss water pressure is the stability
of the edges of a bed proteetion ormattress, sec Section 20.3.2 and 20.5.
(Jw H
h~-·-
9' (Ja 2 (1< L)
in which:
h = thickness ofbed proteetion (m)
(Jw = density ofwater (kg/rn'')
138
(Ja = bulk density ofbed proteetion material (kg/rn'')
H = wave height (m)
I = length ofthe bed proteetion in the wave direction (m)
L = wavelength (m)
b. The wavelength is much shorter than the length of the bed proteetion.
In order to prevent the slab from being raised its weight must be greater than the maxi-
mum uplift pressure underneath. An uplift pressure is caused by the pressure re-
sulting from the wave action abovethe slab being,locally, less than the groundwater
pressure below. The time-dependent pore water movements, which strongly
determine the groundwater pressures, cause considerable damping to this effect
(41,79), An approximation for this system is given in Appendix 11.With the formula
derived, it is possible to estimate the thickness ofrevetment required. In the example,
worked out in the appendix, it can be seen that the damping due to groundwater
movements is very large.
Under normalconditions the phenomena of lifting by wave action is not of major
. importance; More important is the possibility of scouring at the edges of the bed
proteetion as a result of erosion. If the sand at the edges is unstable i t is recommended
that the watertight bed proteetion is overlapped at the edges with an open sand-tight
revetment.
(Ja' g.H)
w= KD·À ) -cotg e
in which:
W = weight of an element (N)
(Ja= density ofan element (kg/m'')
g = acceleration due to gravitytm/s'')
H = wave height (m)
.1 = relative density of an element
.1 = {Ja-Ow
{JN
139
Remarks
Surface-grouted stone
If the size or weight of crushed stone is barely inadequate to satisfy the wave
conditions thcn the safety of the revetment can be increased by fixing the stone with
an asphalt grout.
Ifabout 30~ ofthe voids in the stone is covercd, the Ko value can be multiplied by I
to 1.5.
Note: In principle thc revetment does not consist of individual clements and th is
method should not, in fact, be applicd. In practice, however, it works weil and gives
satisfactory results.
Pattern-grouting
If about 60% of the total surface is filled the Ko factor can be multiplied by 5 to 7.
From model investigations it appears that a relativcly smaller increase in stability is
obtained by grouting more than 50% of the surface ofthe crushed stone. Grouting 50
to 70% of the total voids in the stone laycr appears to give the best results (27).
The revaluating ofthe Ko factor is very dependent on the execution and care must be
taken to ensure that the grout does not remain in the surface of the stones or sags
completcly through the cover layer.
Prototype tests with high waves, Hsig up to 8 m, demonstrate that, because of the
enormous forces developed by breaking waves in the clefts between the stones, the
grouted lumps themselves can be split and shell-shaped pieces can brake off. This
type of construction, therefore, should not be used in arcas of heavy wave attack; it
has proved to be successful, however, in waves of 3 to 5 m (4).
140
For reasons of safety it is recommended that three layers ofbroken stone are used, only
the top two being grouted. A few loose stone will probably be washed away by the waves
but th is will not be dangerous. If a lump of grouted stones is washed away the third layer
will still proteet the core since it is held fast by the overlying grouted lumps (27).
Ideally the KD value should be found from model tests.
Grouting produces a smoother revetment surface and, as a result, there is more wave
uprush, The crest, thcrcfore, needs to be higher. An indication of this is given in Table
20.4.
Tablc 20.4 ,
Wavc uprush on ccrtain slope surfaces comparcd with a smooth surfacc.
The possible forces which can bc caused by flowing water are given in Section 19.1.3. The
performance of various asphalt types under such forces is discussed in the present
section,
Under normal conditions an asphalt revetrnent is very resistant to flowing water.
Considerabie damage however can develop, for examplc, if the water carries hard
objects such as stones. In addition currents can lift the edges of a plate or mattress and
cause to turn them over. This can be prevented by, for cxarnple, increasing the weight of
the edges or by burying them.
MASTIC
Mastic is an overfilled mix with a relatively low stiffness. The stresses caused by impacts
from debris etc. carried by the flow are generally small and can be withstood. It is
important, however, that the edges of the plate are not made to flap by the current. This
can be prevented by:
141
I. burying the cdges of the plate so that the eurrent ean gain no purehase on it.
2. dumping erushed stone on the cdges. These pieees will then penetrate into the mastie
layer until thcy are in equilibrium. This proeess is dependent on the differenee in
density between the stone and the mastie, the shape ofthe stones and the viscosity of
the mastie. (The penetration into a layer of'stoncs takes longer than of loose stones.)
Investigations indieate that a few eentimeters ofmastie slab originally 20 em thick still
remained under the stone, dumped under water, plaeed five years ago (88). -
A mastie slab ean be built up from a number of separate layers laid like rooftiles over
eaeh other. Ifthcre is not good adhesion between these layers, beeause ofthc presenee of
sand pollutions or inadequate heat transfer, flowing water ean get hold ofthe unattaehed
scctions, lift them and break them off (81).
GROUTING ~IORTARS
The following formula is aften used for designing loose erushed stone against sta-
tionary or quasi-stationary flow (25):
in which:
142
OPEN STONE ASPHALT
Information about the rcsistance of open stone asphalt to currents is, as yet, not
complete. Investigations have produced the following results:
With the stationary and quasi-stationary flow very limited crosion was observed after
34 hours with current veloeities of6 mis, (6). The damage which did occur consisted
mainly of the loosening of limestone particles.
The material has also been tested with currents generated by ships' screws. These tests
were made on a bank revetment of 12 cm lean sand asphalt under a cover of 18 cm
open stone asphalt in the Rhcin-Main-Donau Canal, The currents we re produced by .
the screws ofa cargo ship with a draught of2 mand an 800 HP motor at full strength
for 5 minutes. No damage ocurred.
Investigations have been carricd out into the rcsistance of open stone asphalt to wave
attack, which showed that under normal tide conditions and also over a long period
the material did not erode.
The cdges of an open stone asphalt mattress can flap when the critical stcady flow
velocity (2.5 to 3 mis for a IS cm thick mattress) is exceeded. This can be prevented by
making the edges henvier. This phenomena of flapping can occur with all types of
siabs and mattresses.
143
20.6 Designing an asphalt revetment against irregular settlement and scouring
Deponding on the speed of settling and the propertics of the asphalt, an asphalt revet-
ment will not immediately adapt to irregular settlcment. After some time, however,
provided that there is no break, the revetment willlie again on the subsoil. The bending
ofthe asphalt plate due to irregular settlcment and the time taken for it to adjust can be
determined using simp le formulas derived by mechanics (50).
Ifthe surface ofthe settlement is assumed to be circular, the time taken for the revetment
to adjust, I, can be determined using the following formula. By repeating the calculation
a number of times with related values of the stiffness modulus, I can be approximated:
13 16·v·h2
--= 2 4 (sec Appendix IV.I)
S(/,T) 3·Ga·g·(I-u )'11
in which:
Ua = density ofthe asphalt (kg/rn")
g acceleration due to gravity (rn/s-)
1I Poisson's ratio for asphalt
h thickness ofthe revetment (m)
11 horizontal speed ofsettling (mis)
v vertical speed of settling (mis)
time (s)
time at which settling begins: I = 0
S stiffness modulus of asphalt, time and temperature dependent. The
related time, can for example, be fixed at 0.5 I
The speed of settling (v and 11) is assumed to be constant, sec also Figure 20.13.
I a , a
144
The largest bending stress will develop just before the plate touches the bed, see
Appendix IV. I. The bending stress is then:
3 . (la • g. 112 • tf
Ub = 4."
t1 = adjustment time
If the expansion of the settling has stopped before the revetment can adjust:
If the allowable stress at break, Ob rnax- is smaller than the stress which develops, Ob, then
the revetment will fail before the material can adapt to the subsoil surfacc.
The bend in the plate can also be so big that, after a long time, the deforrnation capacity
is exceeded and the plate breaks.
The presence of a cavity under the revetment can in conjunction with other loads, for
example, a wave impact, cause extra stress. This can lead to failure.
In addition large settlements can lead to a reduction in the layer thickness (viscous flow)
which reduces the strength of the revetment.
If the asphalt revetment is to follow irrcgular settlement without cracking this will
depend on the speed ofsettling and the asphalt propertics.
Asphalt mastic is a very suitable material for adjusting to irregular settlement because
it is reasonably viscous. In the above mentioned formulas the stiffness modulus Scan
be rcplaccd by 37]/t in whieh 7] is the value ofthe viscosity ofthe mastic, sec Appendix
IV.2.
Grouted crushed stone must be able ot adjust to irregular settiement without losing its
cohesion. It is more able to do th is when the voids are completely filled.
It is important that open stone mattresses remain in contact. with the subsoiI. If the
mattress is anchorcd, stresses can devclop in certain sections which in combination
withwave induced forces can lead to failure.
Because ofits limited ability to adjust and in view ofits function great careis needed
when using lean sand asphalt as a filter layer or revetrnent. Failure will not develop,
initially, because oflarge deformation but because oftoo great a deformation speed.
Because of its large bulk wh en lean sand asphalt is used as a core material, its ability
to adapt to settlement is of much less significanee than that of a sand asphalt filter
layer. Thc care should bc designed to act monolithically undcr diffcrcntial scttlement,
see also Appendix V. Thc tension level and the deformation speed should, howcver,
~~~~. .
145
An asphaltic membranc which adjusts to settlements will stretch, sec Figure 20.14. If
the extension is 111 and the original length I then the strain is MI I (that is .
111 = V11112 + I1x2 - I1x).
This strain must not exceed the maximum allowable value.
Reinforcing in the membrane enables the strain whieh otherwise would concentrate
in one pi ace and could lead to excessive extension.
I
------------,
----------1
I
I
6.x
20.6.2 Scouring
Scouring usually takes place so quickly that the asphalt rcvetrncnt cannot adjust, The
dike should, thcrefore, bc design cd in such a way th at the revctrncnt cannot be
undermined, for cxample, by providing a good toe and bed protection.
Bccausc ofits good viscosity, asphalt mastic can, to a large extent adjust to underrnining,
sec Photo 8, and is, therefore, often applicd as bed protection.
Ifscouring occurs at the end of a mastic apron it will bend, sec Figure 20.15. The time for
the end of the plate to reach the bottom of the hole can be determined from the
following:
in which:
146
Photo 8 The effects ofscouring on a mustic slab
lil)
-
.-- , ./ ,
I
scourmg speed ,..,.
-- Vlm;I//
-- ~_-=-_-_-""'~~ - -- - ----1
Pigure 20.\5 Scouting of a mastic slab (schematic).
The largest bending stresses will develop ut a distance /(1) from the end of the slab just
befare the end of the slab setnes onto the bed of the scour hole. Ir these stresses exceed
the limiting value the revcunent will break.
in which:
147
As soon as the end of thc slab touches the bed, in principle, the scouring process stops.
Thc mastic slab, howevcr, does not lic everywhere in contact with the bed and in between
the slab and the bed there ma)' be cavities.
The length over which the slab is not supported is increased since the bed underneath
adjusts to its own natural flatter slopc. The slab will then bend further to complete its
adjustment. Ncw strcsses develop in the slab which in combination with the reduced slab
thickness can lead to failure. In practice a crack can dcvclop at A, sec Figure 20.16.
Figure 20.16 Bending of a mastie slab after the end has settled onto the seour hole.
Failure can also occur in a runstic slab lying on a sand bed which over1ies a cIay layer. In
this situation wave pressures cannot propagate through the clay layer and will build up to
eau se large uplift pressures under the mastic slab.
Sand under the slab can be lost through cracks and as aresuIt undermining can proceed.
llecause of the stiffness propertics of the material cracks are more likely to develop in
winter than in summer. In warmer periods it is possible for the cracks to flow together
and re-scal.
The reduction oflayer thickness due to viscous flow should not be overlookcd.
The length of a mastic slab in front of a dike must be sa large that the toe cannot be
undermined and the slope stability is endangered.
In order to prevent the revetment sliding off the dike body (Photo 9), the slope angle
must be less than the angle of internal friction. For a relatively impermeable revetment,
the slo pc angle in places where water is likcly to occur behind the revetment, should be
na larger than:
148
in which:
For a slope of cohesiouless material where groundwater can flow out Freely, in order to
prevent slope instability the angle shauld be (84):
in which:
The allowable slope is also determined by the iuternal stabilityofthe mix itself, in both
the construction and the completed phnse. The method of construction can ntso be a
deterrnining factor in the choice of slope.
149
ASPIIALTIC CONCRETE
Depending on the mix composition asphaltic concrete is stablc on a slope of about I : 1.7
even when hot (3, 22). After completion the mix is stabIe at the sarne angle. The
construct ion method, particularly the applicability of the construction equipment, is
generally the limiting factor.
lIlASTIC
Mastie is, preferably, used on a horizontal subsoil. For a lean mastie the .maximurn
allowablc slope is about \00 and for a fat mix 5°, depending on the duration and
temperature regime.
PATTERN-GROUTING
The grouted areas of stone must bestabIe under the prevailing eonditions. The areas
must satisfaetorily loek up the interlying stones. It is, thus, important th at the grouted
areas remain as lumps. The mix composition and the method ofexeeution must be sueh
th at the grout does not stay in the upper layers or sags completely through the layer.
FULLY GROUTING
Beeause ofits internal skeleton this type of revetment has high stability, sec also Chapter
II.
150
2. For constructions in which deformation is not important the only limitation is safety.
The resistance to failure ofgranular materials is characterized by the angle ofinternal
friction, 9, and the cohesion, c. ,
The failure mechanism can be studled using, for example, a slip circle analysis or the
Prandtl wegde method.
For present purposes the equilibrium method is used to calculate the stability of the
material in which it is assumed that deformations remain sufficiently sm all if the
relationship between the shear stresses which develop and the maximum allowable shear
stress is equal or less than 0.75. For bituminous products the stability problem is more
complicated because of the viscosity. A time-dependent component must be taken into
account.
Investigations have been carricd out on lean sand asphalt made from sand from the
Eastern Scheldt and 3 to 4% bitumen 80/100. The object was (32):
I. To establish the minimum angle ofinternal friction, 9 and thus the stress situation for
which the deformation speeds are smal!. Under such shear stresses 9 was in the range
20° to 24°.
2. To establish the maximum angle of internal friction, 9 that is, the situation when
deviator-stresses produce deformation speeds which do not become smaller but
remain constant or increase. Under such shear stresses, 9 was in the range 30° to 34 0.
3. To establish relationships between the stress conditions and deformations and
deformation speed between the maximurn and minimum.
There are several ways in which the failure criteria can be established:
151
ASPIIALTIC MEMBRANES
Asphaltic membranes are general1y covered. In situ prepared membranes are often
covered with earth; prefabricated membranes with earth, rubble, concrete, asphalt, etc.
The fol1owing failure mechanisms can develop:
I. The membrane causes the proteetion layer to slide off.
To prevent th is the friction component along the membrane should be larger than
the weight component of the proteetion down the slope, that is:
inwhich:
f the friction component between the membrane and the subsoil or proteetion
layer
Ct = the slope angle of the membrane
2. The shear stress transfer over the membrane can cause such large deformations that it
can result in changing geometry or damage of the protection.
The deformations which develop 'as a result of shear forces acting on the membrane
should not exceed certain limits, see Appendix VII.
152