Inspection and Test Plan: Asawer&Zpeb Description of Work: DC System and Ups

This document is an inspection and test plan for the DC system and uninterruptible power supply (UPS) of a project. It outlines inspection activities, acceptance criteria, verification documents, and responsibilities of the subcontractor, contractor, and owner for items like material control, battery installation, panel installation, and inspection/testing. Key points include checking materials, installation of battery racks and panels, output voltage and charging settings, and procedures for battery charging and data recording. Responsibilities are assigned as hold, witness, surveillance or review points.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
52 views

Inspection and Test Plan: Asawer&Zpeb Description of Work: DC System and Ups

This document is an inspection and test plan for the DC system and uninterruptible power supply (UPS) of a project. It outlines inspection activities, acceptance criteria, verification documents, and responsibilities of the subcontractor, contractor, and owner for items like material control, battery installation, panel installation, and inspection/testing. Key points include checking materials, installation of battery racks and panels, output voltage and charging settings, and procedures for battery charging and data recording. Responsibilities are assigned as hold, witness, surveillance or review points.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

ASAWER PHASE III UPSTREAM SURFACE FACILITIES KEYI FPF PROJECT PMC

& CONTRACT No.: Petro-Energy/11/2008-5250


ZPEB Petro-Energy
INSPECTION AND TEST PLAN- DC SYSTEM AND UPS REV.0
DOCUMENT NO.: KE3-PRO-ELC-0908-6011

Contract No. :
ASAWER&ZPEB INSPECTION AND TEST PLAN Petro-Energy/11/2008-5250

DISCIPLINE : KE3-PRO-ELC-0908-6011
DESCRIPTION OF WORK : DC SYSTEM AND UPS
ELECTRICAL REV : 0

COMMENTS DEFINITION OF INSPECTION AND TEST PLAN SYMBOLS APPLICABLE TO ALL SIGNATORIES

SUB-CONTRACTOR= SHENZHEN VICOM TECHNOLOGY CO.LTD


CONTRACTOR= ASAWER - ZPEB CONSORTIUM
OWNER= PETRO-ENERGY

“H” - HOLD: A point beyond which work shall not proceed without formal approval by the appropriate inspectorate. Achievement
of “H” points shall be notified to OWNER in accordance with the contract.

“W” - WITNESS: A point beyond which work may proceed without formal documented approval by any of the inspectorate.
Achievement of “W” points shall be notified to OWNER in accordance with the contract.

“S” - SURVEILLANCE: A point where others may carry out surveillance of work in progress and documentation associated on an
unscheduled basis, with no notification required by any party and without amendment to the scheduled
production program.

“R” - REVIEW: The documents are to be submitted to the appropriate inspectorate for review by OWNER. Note that where a
document is subject to OWNER approval, work shall not proceed until OWNER approval is given.

REMARKS

Page 1 of 5
ASAWER PHASE III UPSTREAM SURFACE FACILITIES KEYI FPF PROJECT PMC
& CONTRACT No.: Petro-Energy/11/2008-5250
ZPEB Petro-Energy
INSPECTION AND TEST PLAN- DC SYSTEM AND UPS REV.0
DOCUMENT NO.: KE3-PRO-ELC-0908-6011

CONTRACT :NO
ASAWER&ZPEB
INSPECTION AND TEST PLAN Petro-Energy/11/2008-5250

DISCIPLINE : KE3-PRO-ELC-0908-6011
DESCRIPTION OF WORK : DC SYSTEM AND UPS
ELECTRICAL REV.0

Item Inspection Activity and Specific Acceptance Criteria, Verifying


ACTIVITY SUB- CONTRACTOR PMC/OWNER
No. Check Point Area Code & Standard Document CONTRACTOR
1.0 Material 1.1Check all the materials . KE3-PRO-0908-6011 ICL-E-010 H R S/R
control
2.0 Battery 2.1Prior to the battery installation, KE3-PRO-0908-6011 ICL-E-010 H S S
installation the housing building will have
been completed.
2.2Check the installation of KE3-MRQ-ELC-0908-6083 ICL-E-010 H S S
battery racks.
2.3Check battery arrangement, KE3-MRQ-ELC-0908-6083 ICL-E-010 H S S
jointing and polarity.
2.4Prior to filling electrolyte, construction drawing ICL-E-010 H S S
check the gravity and ratio.

3.0 Panel 3.1Check panel foundation.


installation KE3-MRQ-ELC-0908-6083 ICL-E-010 H S S
3.2Check the installation of panel.
KE3-MRQ-ELC-0908-6083
ICL-E-010 H S S
3.3Check the connection between
KE3-MRQ-ELC-0908-6083
earthing system with shell of ICL-E-010 H S S
panel
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R -Review

Page 2 of 5
ASAWER PHASE III UPSTREAM SURFACE FACILITIES KEYI FPF PROJECT PMC
& CONTRACT No.: Petro-Energy/11/2008-5250
ZPEB Petro-Energy
INSPECTION AND TEST PLAN- DC SYSTEM AND UPS REV.0
DOCUMENT NO.: KE3-PRO-ELC-0908-6011

CONTRACT :NO
ASAWER&ZPEB
INSPECTION AND TEST PLAN Petro-Energy/11/2008-5250

DISCIPLINE : KE3-PRO-ELC-0P908-6011
DESCRIPTION OF WORK : DC SYSTEM AND UPS
ELECTRICAL REV.0

Item Inspection Activity and Specific Acceptance Criteria, Verifying SUB-


ACTIVITY CONTRACTOR PMC/OWNER
No. Check Point Area Code& Standard Document CONTRACTOR
4.0 Inspectio 4.1Check the output voltage, float KE3-MRQ-ELC-0908-6083 ICL-E-010 H S S
n and test charge setting, automatic boost Manu. ’Instructions
charge for DC battery charger.
4.2Check the charging current, KE3-MRQ-ELC-0908-6083 ICL-E-010 H S S
protection circuits, transfer Manu.’ Instructions
between float charge with boost
charge, all meters and alarming.
4.3Check inverter system and static
switch, and check its output KE3-MRQ-ELC-0908-6083 ICL-E-010 H S S
voltage &frequency. IEC623 Form-E012
IEC896 ICL-E-010
4.5Check charging voltage of
battery, float and equalizing IEC623 ICL-E-010 H S S
charge settings. Form-E012
4.6Check the procedures of battery
charge, data record. IEC896 ICL-E-010 H R R
4.7After charging, check the Form-E012
voltage of cell. If necessary, the ICL-E-010
unqualified cells should be IEC623 H S S
disposed of separately. IEC896 ICL-E-012
Definitions of Inspection & Test plan Symbols: H -Hold W -Witness Point S -Surveillance R -Review

Page 3 of 5
ASAWER PHASE III UPSTREAM SURFACE FACILITIES KEYI FPF PROJECT PMC
& CONTRACT No.: Petro-Energy/11/2008-5250
ZPEB Petro-Energy
INSPECTION AND TEST PLAN- DC SYSTEM AND UPS REV.0
DOCUMENT NO.: KE3-PRO-ELC-0908-6011

DC SYSTEM AND UPS


(ICL - E - 010)
ProjectTitle:____________________________Date:_____________________________
Unit:__________________________________Location:__________________________
EquipmentNo:__________________________Manufacturer:______________________
DrawingNo.:____________________________RecordNo.________________________

No. Description Conclusion

1. Check acceptance of materials.

2. Check the foundation of control panel, and check cable entrances.

3. Check the installation of control panel.


Check the internal elements of panel, fuses capacity and protection
4.
devices.
5. Check phase sequence.

6. Check the cable laying report.

7. Check the connection between earthing system with panel.


Check charging current, out put voltage of inverter panel and
8.
frequency .
9. Check functional test of UPS panels

10. Check all the meters, trouble alarming indication.

11. Check test running.

12
Check the connection between the batteries with pannels

SUB-CONTRACTOR CONTRACTOR
APPROVAL PMC/OWNER
(VICOM) (ASAWER/ZPEB)

SIGNATURE

DATE

BATTERY CHARGING RECORD


Page 4 of 5
ASAWER PHASE III UPSTREAM SURFACE FACILITIES KEYI FPF PROJECT PMC
& CONTRACT No.: Petro-Energy/11/2008-5250
ZPEB Petro-Energy
INSPECTION AND TEST PLAN- DC SYSTEM AND UPS REV.0
DOCUMENT NO.: KE3-PRO-ELC-0908-6011

(FORM - E - 012)

Project Title: _____________________ Date : ______________________________


Unit:_____________________________ Location:____________________________
Battery type:______________________ Manufacturer: ________________________
Battery voltage : ___________________ Rated capacity: _______________________
Battery quantities: _________________ test personal : ________________________
Drawing No.: _____________________ Record No. __________________________
Record duration :__________________ Start time:____ _______________________
end time:________________________
Battery No. No. No. No. No. No. No. No. No. No. No.
Voltage Current Volt Volt Volt Volt Volt Volt Volt Volt Volt Volt
Time
V A (V) (V) (V) (V) (V) (V) (V) (V) (V) (V)

SUB-CONTRACTOR CONTRACTOR
APPROVAL (VICOM) (ASAWER/ZPEB)
PMC/OWNER

SIGNATURE
DATE

Page 5 of 5