Ball Mill
Ball Mill
Doll
C O N S U L T I N G L T D
TECHNICAL MEMORANDUM
December 12, 2011
Summary:
Most large tonnage mineral processing facilities consist of a primary SAG milling and secondary ball milling
grinding circuit. There are three principal methodologies for sizing SAG mills that are widely used:
• Bond work index based methods;
• Australian “drop weight test” based methods;
• The SPI/SAGdesign methods.
Each methodology involves a series of grindability laboratory tests and a suite of equations used for mill power
and throughput predictions. This presentation deals only with the Bond work index suite.
The desired outcome of all of these methods is an estimate of the grinding specific energy required to reduce a
rock from a “F80” size to a “P80” size. This energy is expressed as kW·h/tonne, where kW is the grinding energy re-
quired “at the mill shell” multiplied by the inverse of throughput (h/tonne). This energy requirement (for a par -
ticular F80 and P80) is a property of the rock and any difference in specific energy of different comminution
devices is (largely) reflective of the efficiency of the grinding device.
Once the specific energy is determined, the amount of grinding power needed (at the mill shell) is found by mul-
tiplying the specific energy by the desired throughput. Then a motor size and mill geometry is chosen that will
satisfy the power demand at the mill shell.
E =10×Wi
(√ 1
−
1
P 80 √ F 80 ) (1)
1 For the purists, there were two models in existence at the time: the Von Rittinger and Kick models. Neither of
these gave results that matched the observations of specific energy consumption from tumbling mills.
2 F.C. Bond; The Third Theory Of Comminution, Transactions AIME 1952. Available from www.onemine.org
Figure 1: Ball mill for determining Bond ball mill work index
Many people refer to “the” Bond work index when they really mean the Bond ball mill work index. There are two
other Bond work index measurements commonly used: the rod mill work index and the crushing (low-energy im-
pact) work index.
Figure 2: Rod mill for determining Bond rod mill work index
[ ( )]
(0.907×Wi RM −7) F 80
EF4 RM = 1+ −1
( ) ( )
0.5
F 80 14.33 (2)
16000
P 80 Wi RM
[ ( )]
(0.907×Wi BM −7) F 80
EF4 BM = 1+ −1
( ) ( )
0.5
F 80 14.33 (3)
4000
P 80 Wi BM
[
EF5 BM = P 80 +
10.3
1.145×P 80 ] (4)
Values of EF4 can only be greater than 1. If a value evaluates to less than 1, skip that factor and substitute 1 in its
place. The EF5 factor only applies below 75 µm to ball milling, and a value of 1 can be substituted above that P 80.
Combining the Rowland efficiency factors with the three-stage Bond equation gives this overall equation for
grinding specific energy consumption from a primary crusher product size, F 80, to a ball mill cyclone overflow
product size, P80.
E=10×Wi C
(√ 1
−
1
)
10000 √ F 80
+10×Wi RM
( √ 11500 − √101000 )×EF4 RM +10×Wi BM
(√ 1
−
1
P 80 √ 1 500 )
×EF4 BM×EF5 BM
(5)
1 C. Rowland. Chapter 23: The Design and Installation of Comminution Circuits. AIME 1982
[
ESAG = 10×Wi C
(√ 1
−
1
)
PC √ F 80
+10×Wi RM
(√ 1
−
1
PR √PC )
×EF4 RM +10×Wi BM
(√ 1
−
1
110 √ P R) ]
× EF4 BM ×EF5 ×1.25
(7)
( )
1 1
−10×Wi BM − × EF4BM × EF 5
√ 110 √ T 80
The form of this equation is similar to Equation 5, except that it introduces a few new terms and it includes a
factor of 1.25 that accounts for the difference in grinding efficiency of a SAG mill versus a ball mill. The original
Barratt papers do not specify values to use for P C and PR, but we can use the same values as Table 1 of 10 000 µm
and 1500 µm, respectively. The value T80 is the “synthetic” transfer size between the SAG mill and ball mill – a
fines-corrected 80% passing size 2 of the SAG mill product (or the combined SAG mill product and crushed
pebbles if the circuit is sending crushed pebbles to the ball mill circuit, a.k.a. SABC-B operation).
The transfer size is normally set to a value in the range of 1 to 3 mm for a “SABC-A” circuit where the pebbles dis-
charging the SAG mill are screened and crushed in a pebble crusher, then the crushed pebbles are returned to the
SAG mill feed. The recommended design value is 2 mm for T80 in most calculations.
Pebble crushers are considered to be part of the SAG mill portion of the circuit in these calculations. Normally,
the energy that pebble crushers input to the ore breakage is insignificant (on the order of 2% of the overall
SAG+pebble crusher power) and can be neglected.
The SAG mill specific energy consumption is deducted from the total circuit specific energy consumption to get
the ball mill specific energy consumption:
E bm =E total −E SAG (8)
1 D.J. Barratt. An Update On Testing, Scale-up and Sizing Equipment for Autogenous and Semi-Autogenous
Grinding Circuits. 1989 SAG Conference.
2 The actual transfer size you measure in a plant survey will be coarser than this synthetic value. To determine
the fines-corrected T80 from a survey value, perform a “phantom cyclone” or “reduced-recovery” calculation
(see Barratt, 1989).
Pebble Crushers
For initial design purposes, always assume a pebble crusher is required. Determine the size of the pebble crusher
by choosing a crusher that can treat the volumetric flow rate equivalent to 20% of the SAG mill feed. Download
vendor catalogues from their websites to see the volumetric capacities of crushers set at a 13 mm closed side set-
ting.
E=10×Wi C
( √ 10000
1
−
√ 150000 )
1
+10×Wi
( √11500− √101000 )×EF4
RM RM +10×Wi BM
(√ 150
1
−
√ 1 500 )
1
×EF4 BM ×EF5 BM
( 11 )
The EF4 for rod milling evaluates to 0.72, so it doesn't apply. The EF5 for ball milling doesn't apply because the
product size is coarser than 75 µm, and the EF4 for ball milling evaluates to 0.61, so it also doesn't apply. Use a
value of 1 for all the EF factors.
Equation 11 simplifies to: E = 0.67 + 2.01 + 4.63 = 7.31 kWh/tonne
Total SAG and ball mill circuit specific energy consumption: Etotal =8.04 kWh/tonne
Determine the SAG mill specific energy consumption using Equation 7:
[
ESAG = 10×Wi C
(√ 1
−
1
)
10 000 √ F 80 ( √ 1500
+10×Wi RM
1
−
√ 10 000 )
1
×1+10×Wi
( √110
BM
1
−
√ 1500 )
1
]
×1 ×1 ×1.25
−10×Wi
( √ 110
BM
1
−
√
1
2000 )×1×1
( 12 )
Equation 12 simplifies to: ESAG = (0.67 + 2.01 + 5.77) × 1.25 – 6.06 = 4.50 kWh/tonne
1 Doll & Barratt, Choosing the Right Motors for your Mills, Procemin 2010
Exercise #1
Tenke Fungurume Composite 2 has the following grindability results (J. Starkey et al, CMP 2007):
• WiBM=10.4 (metric)
• WiRM=13.5 (metric)
• WiC=11.10 (metric)
Determine a SAG + ball mill circuit to grind primary crusher product of 150 mm to a flotation feed size of 200 µm
at 2500 tonnes/hour.
Exercise #2
Using the milling circuit you determined for Exercise #1, what would be the throughput of Composite #1 if you
feed 150 mm F80 rock to the SAG mill and make a ball mill product P 80 of 200 µm? Assume the SAG mill draws
90% of available power and the ball mill 94% of available power.