Document 3

This document provides instructions for performing a no-load test on a compressor skid. It lists 21 steps to check systems like the lube oil, water, valves, and piping. The test involves pressurizing the compressor with nitrogen, starting it up, monitoring pressures and temperatures, and running it for 10 minutes to check for issues before shutting it down.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
32 views

Document 3

This document provides instructions for performing a no-load test on a compressor skid. It lists 21 steps to check systems like the lube oil, water, valves, and piping. The test involves pressurizing the compressor with nitrogen, starting it up, monitoring pressures and temperatures, and running it for 10 minutes to check for issues before shutting it down.
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

SIAD Macchine Impianti S.p.A.

Società unipersonale soggetta all’attività di


direzione e coordinamento di SIAD S.p.A.
24126 Bergamo, Italy - Via Canovine, 2/4
Tel. +39 035 327611 - Fax +39 035 316131
www.siadmi.com - [email protected]
Capitale Sociale - Share Capital € 25.000.000 i.v. - paid up
P. IVA, C. F., Reg. Impr. Bg - VAT and Fiscal Nr.: (IT) 00228420162
R.E.A. BG-72619 - Export: BG 006107

K33033/10A Project: :
M3 - PROC - NO-LOAD Compiled 14/12/2021 by Paglialunga

Description Ok Note
1 - REVIEW ALL POSSIBLE SOURCES
FOR SUPPLY OF PROCESS GAS TO
COMPRESSOR SKID AND ENSURE THAT
ARE ALL ISOLATED FROM THE
COMPRESSOR DURING THE PERIOD OF
INITIAL START-UP AND RUN IN
2 - CHECK LUBE OIL SYSTEM - LUBE OIL
LEVEL AND RUN MANUAL OIL PUMP IF
ANY
3 - RUNNING(IF PRESENT) THE
ELECTRICAL OIL PIUMP
LUBRIFICATION, IN ORDER TO
LUBRICATE THE INTERNAL
COMPONENTS(CROSSHEAD
LINER)CHECK THE CORRECT WORK OF
THE RELIEF VALVE POSITIONED ON
THE DELIVERY OIL CIRCUIT PUMP, SET
TO 7-8 bar.RUNNING THE ELECTRICAL
PUMP FOR 15-20min AT PRESSURE TO
5-6 bar
4 - DISASSEMBLE THE FRONT
DISTANCE PIECE WINDOWS.
5 - LUBRICATE THE OIL SCRAPER
GROUP IN THE LOWER PART OF THE
DISTANCE PIECE.
6 - CHECK THAT THE WATER PUMP IS
RUNNING AND THAT THE WATER IS
CIRCULATING CORRECTLY
7 - CHECK THAT SUCTION GAS VALVE
IS CLOSED
8 - CHECK THAT COMPRESSOR VALVE
DELIVERY VALVE TO THE CLIENT IS
CLOSED
9 - CHECK RECYCLE VALVE IS FULLY
OPEN AND IN MANUAL OR THAT THE
UNLOADERS ARE IN UNLOAD POSITION
10 - CHECK THAT THE VENT VALVE IS
CLOSED AND IN AUTOMATIC
11 - BY-PASS LOW SUCTION PRESSURE
SWITCH IF NECESSARY
12 - CHECK PERSONNEL ARE NOT
WORKING ON OR AROUND THE
COMPRESSOR
13 - OPEN THE NITROGEN TEST
SUPPLY AND PRESSURIZE THE
COMPRESSOR.
14 - CHECK FOR LEAKAGE ON THE
PIPING AND COMPRESSOR FLANGES.
TIGHT IF NECESSARY.
15 - START THE COMPRESSOR AND
CHECK THAT OIL PRESSURE REACH
THE CORRECT VALUE. IF NOT ADJUST
1/2
SIAD Macchine Impianti S.p.A.
Società unipersonale soggetta all’attività di
direzione e coordinamento di SIAD S.p.A.
24126 Bergamo, Italy - Via Canovine, 2/4
Tel. +39 035 327611 - Fax +39 035 316131
www.siadmi.com - [email protected]
Capitale Sociale - Share Capital € 25.000.000 i.v. - paid up
P. IVA, C. F., Reg. Impr. Bg - VAT and Fiscal Nr.: (IT) 00228420162
R.E.A. BG-72619 - Export: BG 006107

IT.
16 - VERIFY THE CORRETLY WORK OF
THE RELEIF VALVE (PCV)IN THE OIL
CIRCUIT,POSITIONED ON THE
GRANKCASE(DOOR)SET THE RELIEF
VALVE TO 7-8 bar
17 - ENSURE THE ABSENCE OF
UNUSUAL NOISES AT COMPRESOR -
GEARBOX
18 - CHECK OIL LEAKAGE AT THE OIL
LUBE CIRCUIT
19 - RUN THE COMPRESSOR FOR 10
MINUTES
20 - CHECK TEMPERATURES,
PRESSURES AND FILL THE A9 SHEET
WITH ALL AVAILABLE INFORMATIONS
21 - TURN OFF COMPRESSOR

2/2