Prolongation Cost
Prolongation Cost
Claims for lost overheads and profit are common in construction arbitrations
involving delay and disruption. When the completion of the Works in question was
caused by the Employer’s delay, Contractors often include a claim for lost
contribution to head office overheads and the lost opportunity to earn profit (either on
the project which is the subject of the claim or on another project)
(see Prolongation Claims in Construction Disputes).[1]
Under most standard forms of construction contracts, lost profits are typically not
recoverable. Instead, Contractors typically frame their claim for lost profits as a claim
for damages for breach of contract.[8] An appropriate rate of profit is often taken
from a Contractor’s audited accounts for the previous three financial years. As both
overheads and profits are computed using the same set of accounting data, they are
normally formulated as the same category of claim.[9]
However, as correctly pointed out by experts and commentators, there are obvious
difficulties associated with estimating profits which could have been earned on work
which has not been secured. In practice, reference is usually made to past records of
profitability, which is, however, merely indicative evidence of a contractor’s capability
to earn profits.[10]
In order to recover unabsorbed overheads and lost profit, the Contractor must be
able to demonstrate:[11]
that it has failed to recover its overheads and earn the profit it could
reasonably have expected during the period of prolongation; and
that it has been unable to recover such overheads and earn such profit
because its resources were tied up by Employer Risk Events.
The SCL Delay Protocol further clarifies that the Contractor must demonstrate that
there was other revenue and profit-earning work available which, had it not been for
the Employer’s delay, it would have secured.[12] In other words, as one leading
commentator on construction law and practice in Singapore explains, to sustain a
claim for loss of profit or offsite overheads, a Contractor must first show that “for the
critical period of the delay, market conditions in the construction industry were
sufficiently favourable at the relevant point in time, so that it is reasonable to expect
that the resources which were tied up in the delayed project could have been
deployed to earn a profit and to enable him to recover his head office overheads on
such work as could be reasonably secured at the material time.”[13] Whether the
Contractor will succeed in this essentially depends on if the Contractor can
demonstrate that it had reasonable prospects of securing such work.
The most commonly-used formulas to calculate head office overheads and lost profit
are the Hudson, Emden and Eichleay formulas. Further guidance on how to use
each of these three formulas is provided in Appendix A to the SCL Delay Protocol.
The Society of Construction Law has also provided a useful spreadsheet to assist
with using the formulas.
The oldest formula for the calculation of lost overheads and profits is the Hudson
formula, first mentioned in Hudson’s Building and Engineering Contracts.[15] The
Hudson formula has been extensively cited, and used, especially in the United
Kingdom and other common law jurisdictions. The Hudson formula is constructed in
a very simplified manner to calculate overheads and profits as follows:[16]
The Eichleay Formula for the Calculation of Overheads and ProfitThe Eichleay
Formula, named after the case where it was used for the first time (Eichleay
Corp (Appeal of ASBCA 5138 60-2 BCA 2668 (1960)), is more commonly used in
the United States. The Eichleay formula includes an additional step to enable
determination of the percentage to be used for fixed overheads contribution:
The Eichleay formula assumes an average weekly turnover that is derived from the
final billing for the works in question and the actual, instead of anticipated, period to
perform these works.[22] This is its main advantage, as the head office overheads
and profits recovery inherent in the contract are not duplicated in the formula result.
However, like the Hudson formula, the Eichleay formula assumes that head office
overheads are distributed in a consistent manner throughout the contract.
There are conceptual issues with all three formulas, which is why they are frequently
criticized by experts as inaccurate or unreliable. In the absence of a better way to
calculate lost overheads and profits, however, caused by the Contractor’s lack of
sufficient documentation and/or records, the use of all three formulas has been
widely accepted in construction disputes around the world.
[9] Singapore Law and Practice of Construction Contracts, Chow Kok Fong
(5th Edn, 2018), para. 10.157.
[10] Singapore Law and Practice of Construction Contracts, Chow Kok Fong
(5th Edn, 2018), para. 10.161.
[13] Singapore Law and Practice of Construction Contracts, Chow Kok Fong
(5th Edn, 2018), para. 10.163.
[14] Singapore Law and Practice of Construction Contracts, Chow Kok Fong
(5th Edn, 2018), para. 10.163.
[15] Hudson’s Building and Engineering Contracts (10th Edn, 1970 (Sweet &
Maxwell), p 599 and re-stated 13th edition, para 6-070.
[18] The Sad Truth About Overheads and Profit Claims available at:
https://www.adjudication.org/resources/articles/sad-truth-about-overheads-profit-
claims
[19] Singapore Law and Practice of Construction Contracts, Chow Kok Fong
(5th Edn, 2018), para. 10.184.
[21] The Sad Truth About Overheads and Profit Claims available at:
https://www.adjudication.org/resources/articles/sad-truth-about-overheads-profit-
claims
[22] The Sad Truth About Overheads and Profit Claims available at:
https://www.adjudication.org/resources/articles/sad-truth-about-overheads-profit-
claims