Term Sheet
Term Sheet
This indicative term sheet shall be used for continued discussions purposes only and does not constitute a commitment of
the Bank to arrange, finance or syndicate the financing or an agreement of the Bank to prepare, negotiate, execute or
deliver such a commitment. This indicative term sheet is subject to in all respects (i) the successful completion of the credit
assessment/evaluation or due diligence exercise and the results being satisfactory to the Bank and (ii) the approval by
approving authorities of the Bank and (iii) the terms and conditions of a formal documentation to be entered into in
connection with the proposed Facility.
The terms and conditions of this financing proposal, including the amount and interest/profit rate may be modified or
supplemented by the Bank at its sole discretion at any time and from time to time during the course of the credit
assessment/evaluation or due diligence or as a result of changed market conditions or otherwise.
3.Submission of formal valuation report from our panel valuer indicating the property’s total
Open Market Value (OMV) of not less than RM66mil, failing which the Bank reserves the
rights to reduce the facility limit accordingly.
7.Reimbursement is allowed subject to documentary evidence that Borrower has paid Banks
portion.
8.In compliance with the Housing Developers (Control and Licensing) Act 1966, a valid
developers license has been obtained for the specific project.
10.The Bank's panel solicitor to confirm that the Bank's interest as the Developers Financier
are protected with respect to the execution of the JVA between Borrower and Landowners
For BG-I 1
1. To drawdown upon completion of legal documentation
For TF 1
2. TL 1 to be released subject to documentary evidence to that Borrower has paid the
RM10.0mil on land owner’s cash entitlement as per the JV Agreement Supplementary
Agreement (clause 5.1.6).
For TF 2
3. The Bank is to visit the site and be satisfied on the progress of the work before releasing
against the architect's certificates.
4. Quantity Surveyor/ Consulting Engineer/ Architect to certify that the construction cost of
is reasonable.
For TF 3
1. Drawdown is subject to relevant approval from the authorities has been obtained.
a. Building Plan
b. Advertising Permit & developer’s license
c. Conversion Premium is paid & land is converted
2. You are to submit the final development plan (as approved by the relevant authorities)
with details such as the types and total number of units to be developed and the
respective selling price. In the event the actual development plan upon launching
defers significantly from the proposed plan submitted to the Bank at the point of loan
processing, the Bank reserves the right to vary any of the approved terms and
conditions.
3. To notify the appointment of main contractor to the Bank and submission of company
profile.
4. Etiqa is to be given first rights of refusal to insure/covering various risks for the project.
5. The Bank is to visit the site and be satisfied on the progress of the work before
releasing against the architect's certificates.
TF 3
1. Tranches 1 = RM 40.0 million upon sales achievement of 30%
2. Tranches 2 = RM 60.0 million upon sales achievement of 50%
3. Tranches 3 = RM 40.0 million upon sales achievement of 65%
Other T & C
1. Submission of quarterly progress report for the project with confirmation of sales units
& construction progress.
2. The Borrower shall not without Maybanks prior consent, change its Project Economics,
which may result in the variation of more than 10% (+/-) of Gross Development Value
and Gross Development Cost throughout the tenure of the Facilities, failing which
Maybank reserves the right to review the Facilities.
3. The Borrower shall inform Maybank on the change or in the case of termination,
appointment of new or replacement of registered contractor and/or professionals
engaged for the Proposed Development within 14 days from the occurrence of the said
event.
4. The Borrower shall inform Maybank on the cancellation / variation of SPA Sales
Achievement within 14 days under the project financing sales conditions imposed.
5. A fee equivalent to 1.5% of the penalty fee shall be imposed in the event that the
Facilities are prepaid from
Repayment TF 1
1. Proposed Grace period of 12 months from the facility release date
2. Interest charged during the grace period
3. 35% redemption sum per unit or 48 monthly instalment of RM534,000-00 each, whichever
is higher/earlier.
4. During the loan tenure, including Grace Period, interest is to be serve via SI until full
settlement.
TF 2
1. Proposed Grace period of 12 months from facility release date
2. Interest charged during the grace period
3. 35% redemption sum per unit or 36 monthly instalment of RM1,092,000-00 each,
whichever is higher / earlier
4. During the loan tenure, including Grace Period, interest is to be serve via SI until full
settlement
TF 3
1. Proposed Grace period of 12 months from facility release date
2. Interest charged during the grace period
3. 35% redemption sum per unit or 36 monthly instalment of RM4,364,000-00 each,
whichever is higher / earlier
4. During the loan tenure, including Grace Period, interest is to be serve via SI until full
settlement.
BG-I 1
To recoup via redemption sum upon full settlement of TF 1 at RM22.0 million, TF 2 and TF 3