BILL NO. 1
GENERAL
The Works contained in the Contract shall include the provision of all labour,
materials, constructional plant, temporary or permanent works as required
in the Contract.
The items as set out in the Bill of Quantities shall apply to the whole of the
Works contained in the Contract and the Contractor shall allow for compliance
with the same and for any cost incurred in connection therewith.
The amounts inserted by the Contractor for such items shall be deemed to
apply to the whole of the Works carried out under this Contract.
Each item shall be individually priced. Bulk pricing for sections, trades,
groups or pages of items shall not be allowed and no subsequent claims for
loss or expense and/or profit shall be entertained for failure to comply
with this clause.
The rates and prices inserted in the Bill of Quantities shall include cost of
the works described, all risks, liabilities and obligations set forth or implied
in the Contract Document and shall be deemed to include the following,
unless expressly stated otherwise:
d) the usage of plants and machineries and all costs in connection therewith;
C/C … RM -
f) the provision of all temporary works and all costs in connection therewith
unless separately provided for in the Bill of Quantities;
i) all royalties and dues which the Contractor may be required to pay;
ii) wastage;
Where any priced item in the B.Q. but has not been executed on site by the
Contractor, the cost of such priced item shall accordingly be deducted from
the Contract Sum.
All items priced shall be deemed to include compliance with the provisions of the
contract, statutes, regulation, by-laws or any order or directive issued by public
authority or public service company and other related legislation currently in force.
Notwithstanding the above clauses, the S.O. reserves the right to request from
the Contractor the detailed breakdown of the pricing for items or rates in the B.Q.
for his perusal. The detailed breakdown pricing may be used as a basis for the
administration of the Contract
MEASUREMENT
UNPRICED ITEMS
Where any item is left unpriced, it shall be deemed that the cost of such item has
been allowed for elsewhere within this document. No subsequent claims arising
out of expense and/or loss incurred against such unpriced item shall be
entertained.
C/C … RM -
a) in the case of works or services executed : for allowing the use of existing
working space, access, temporary roads, erected scaffolding, sanitary,
welfare and other facilities existing on Site and the provision of protection,
water, electricity for lighting and clearing away rubbish and debris arising
from the work;
The rates and prices shall, unless otherwise stated, include for the costs of
compliance with any restrictions imposed on the programming of the Works by
the Government and Local Authorities and other relevant authorities dealing with
phasing sequence of operations, method of construction, safety and health and
liaison and access.
The rates and prices shall include for a testing laboratory or an accredited
laboratory approved by SIRIM, equipment and staff for carrying out the tests, tests
and the effects on the progress of the Works for the carrying out of all trials,
sampling and tests whether specified in the Contract Document or otherwise in
order to ensure compliance with the requirements of the Specification except
where separately itemised in the Bill of Quantities.
The Contractor shall include in his rates and prices for taking measures to locate
the actual position and provide support and full protection of existing services and
mains and other equipment and machineries during the progress of the Works.
The Contractor shall inform the S.O. of all arrangements with all Statutory and
Public Utility Authorities.
The rates shall include any costs arising from and in connection with the
execution of work under water wherever required unless otherwise stated.
C/C … RM -
PHRASEOLOGY
PROVISIONAL SUMS
CURRENCY OF PAYMENT
TEMPORARY DIVERSIONS
ABBREVIATIONS
a) mm : milimetre
b) m : metre
c) m2 : square metre
d) m3 : cubic metre
e) kg : kilogramme
f) tonne : metric ton
g) No. : Number
h) L.S. : Lump Sum
i) P.C. Sum : Prime Cost Sum
j) P.S. : Provisional Sum
k) RM : Ringgit Malaysia
C/C … RM -
SCOPE OF WORKS
xiii) All other works not listed above but are required to be done as per Tender
Document, Specifications and Drawings.
LOCATION OF SITE
The site for the proposed Works is located within existing Institut Kemahiran Islam
Malaysia Sarawak (IKMAS) at Telaga Air, Kuching, Sarawak as shown on the Site
Plan Drawing.
C/C … RM -
Project Signboard
A The Contractor shall provide, erect, paint and maintain a project signboard as
specified.
B The Contractor shall employ a licensed surveyor to carry out site surveys before
commencement and setting out of the Works.
C The Contractor shall enquire from the various authorities and make arrangements
for the disconnection, removal, relocation and reconnection of services and pay
all necessary cost and fees in connection therewith and make good all damage as
specified.
Construction Plan
D The Contractor shall submit to the S.O. for his approval the following as specified :
a) Programme of Works
b) Method statements
d) Schedules
e) Quality Assurance Plan for Works Contract worth RM10 Million and
above
C/C … RM -
Contractor's Plant
A The Contractor shall provide, erect, keep insured, maintain and remove on
completion all requisite scaffolding, hoist, cranage, construction plant, ladder,
staging, tarpaulins, et cetera (excluding piling and pile testing equipment), as
necessary for the execution of the Works.
B The Contractor shall provide adequate power and water supplies for the execution
of the works including paying all associated costs and fees as specified.
Site Security
C The Contractor shall provide all necessary personnel and lighting for the security
of the site at all times until completion of the whole Works as specified.
D The Contractor shall provide and maintain all necessary temporary roads,
culverts, tracks, bridges, et cetera for access to and within the Site as specified.
E The Contractor shall maintain all access including existing roads, bridges, drains,
culverts, roadside furniture, and all other appurtenances and services on such
roads throughout the construction period. The Contractor shall make good any
above mentioned item damaged by any work carried out by him.
F The Contractor shall locate the actual position and provide support and full
protection of existing services and mains during the progress of the Works.
The Contractor shall inform the S.O. of all arrangements with the various
authorities.
G The Contractor shall ensure the safety, health and welfare at work of all his
workmen as specified.
H The Contractor shall provide and maintain all temporary accommodation and
facilities including temporary lighting, plumbing, water storage, sanitary and
sewerage for his labour and staff living on Site as specified.
C/C … RM -
A The Contractor shall provide and maintain Contractor’s office and storage on the
Site in positions as approved by the S.O. and as specified.
B The Contractor shall provide and maintain everything necessary for proper
protection of materials and Works from any damage by weather.
Progress Photographs
D The Contractor shall take progress photographs and submit to the S.O. as
specified.
E The Contractor shall provide/erect a testing laboratory within the site or rent a
premise or propose an accredited laboratory approved by SIRIM as specified.
The Laboratory shall be equipped with the necessary equipment and staff
required to carry out the tests as identified in APPENDIX A/4
(List of Laboratory Equipment).
F The Contractor shall provide and maintain a site office or relocatable site office
or rent a premise for the use of the JKR supervisory staff which shall meet the
requirement of the JKR design as specified.
G The Contractor shall provide a permanent telephone at the S.O.’s site office
for the sole use of the S.O. and his representatives as specified.
H The Contractor shall provide all such instruments, equipment and survey
personnel as specified throughout the duration of the original Contract Period
until 6 months after the issuance of the Certificate of Practical completion as
per SO required.
C/C … RM -
C The Contractor shall provide the equipment and facilities as listed as specified
in APPENDIX A/2 for the use of the S.O., his representatives and staff throughout
the Contract Period.
E The Contractor shall supply, erect, maintain and remove on completion of the
Works, scaffolding and working platform with safety nettings, catch platforms,
safety barricades, fencing, railing, screen wire netting and toe board, guardrails or
board fences and sufficient illuminations, all as specified.
F The Contractor shall supply, erect, maintain and remove on completion of the
Works, adequate, protective and security hoarding, scaffolding and working
platform with safety nettings and such other safety measures necessary to
ensure the safety of the workers, personnel, public and others at or within the
vicinity of the Site, all constructed and specified as per detailed drawings.
G The Contractor shall ensure the safety, health and welfare at work site as
specified including but not limited to :
b) Pest control including keeping the site clean and dry to prevent
breeding of mosquitoes, rodents, insects and vermin of any kind.
C/C … RM -
A *The Contractor shall employ a Safety and Health Officer (SHO) registered with
DOSH for the entire contract period to be stationed fulltime at the site (for works
exceeding RM 20 million contract value.
* Delete if not applicable
B The Contractor shall employ a Site Safety Supervisor (SSS) registered with
DOSH to be stationed a minimum of 15 hours a week at the site for the entire
duration of the construction period.
C The Contractor shall submit 5 copies of Safety and Health Plan (S-Plan)
as required in APPENDIX A/5 as specified.
D The Contractor shall submit 5 copies of monthly Safety and Health Report
as required in APPENDIX A/6 as specified.
E The Contractor shall provide and maintain adequate traffic safety and control
including signages, warning lights and flagmen as necessary.
F The Contractor shall make every effort to keep the Site in a reasonably clean and
tidy condition for the duration of the Works as specified.
As-Built Drawings
H Pursuant to the terms of the contract, the Contractor shall provide and
deliver to the S.O. approved As-built Drawings in the term of:
C/C … RM -
A The Contractor shall clear and clean the Works including existing roads,
drains bounding the Site of any debris, earth, et cetera, and make good
all damages upon completion as specified.
C/C … RM -
Form of Contract
A The Contractor shall refer to the Standard Form of Contract for further information.
The Contractor may price here for all expenses involved in complying with the
terms of this Clauses, otherwise such expenses are deemed to be
included elsewhere.
Clause No. 13
B Performance Bond
Clause No.15
Clause No. 16
Clause No. 17
Clause No. 18
F Insurance of Works
Clause No.22
Clause No. 35
C/C … RM -
A The Contractor shall keep constantly on the Site for the full duration of the
Contract a competent, efficient, suitably qualified, experienced and good
character Site Agent and his assistants in each trade as may be necessary,
who must be capable of receiving instruction in Bahasa Malaysia, and in default
it shall be the responsibility of the Contractor to provide replacement for them
and all wages and other expenses in connection with the employment of such
replacement site agent and assistants. Any directions, explanations or
instructions given to such site agent by the S.O. shall be deemed to have been
given to the Contractor under this Contract provide all necessary superintending
order.