This document provides a detailed estimate for the renovation of a 1-storey residential building in Ormoc City, Philippines. It includes 5 packages for the project components: clearing and demolition, masonry works and plastering, doors and windows, painting works, and plumbing and electrical works. The total estimated cost is 260,712.15 PHP which covers labor, materials, tool rental, hauling, contingency, and contractor's fee.

Uploaded by

Mawe Junrey
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
36 views2 pages

Renovation 2

This document provides a detailed estimate for the renovation of a 1-storey residential building in Ormoc City, Philippines. It includes 5 packages for the project components: clearing and demolition, masonry works and plastering, doors and windows, painting works, and plumbing and electrical works. The total estimated cost is 260,712.15 PHP which covers labor, materials, tool rental, hauling, contingency, and contractor's fee.

Uploaded by

Mawe Junrey
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

DETAILED ESTIMATE

Project : RENOVATION OF 1 STOREY-RESIDENTIAL BUILDING


Location: ST. NINO, ORMOC CITY
Subject : LABOR AND MATERIALS

PACKAGE
Item Description Qty. Unit Unit Cost Labor Total Unit Cost Amount
Materials 30.00%

I CLEARING & DEMOLISHING OTHER STRUCTURES 14,500 14,500

II MASONRY WORKS and Plastering


4" x 8" x 16" CHB 420 pcs 15.00 4.50 19.50 8,190.00
Portland Cement 20 bag 240.00 72.00 312.00 6,240.00
Washed Sand 6 cu.m 1,200.00 360.00 1,560.00 9,360.00
#16 G.I. Tie Wire 2 kgs 110.00 33.00 143.00 286.00
!0mm Dia.x 6m Def. Bars (3.70 Kgs.) 50 Lgths 230.00 69.00 299.00 14,950.00

III DOORS AND WINDOWS


1.20m x 1.20m Sliding Window on analok frame (2 panel) 2 pcs 6,500.00 1,950.00 8,450.00 16,900.00
1.80m x 1.20m Sliding Window on analok frame (3 panel) 2 pcs 8,500.00 2,550.00 11,050.00 22,100.00
1.0m x 2.1 swing Door 4 pcs 5,500.00 1,650.00 7,150.00 28,600.00

IV PAINTING WORKS (246 sq.m)


Latex Paint Boysen 7 gal 850.00 255.00 1,105.00 7,735.00
Gloss Latex 14 gal 778.00 233.40 1,011.40 14,159.60
2" Paint Brush 3 pcs 55.00 16.50 71.50 214.50
4" Paint Brush 3 pcs 95.00 28.50 123.50 370.50
Paint Roller with Pan (7") 3 pcs 120.00 36.00 156.00 468.00
Sand paper 12 sheets 41.00 184.50 225.50 2,706.00
Paint Thinner 1 pcs 420.00 126.00 546.00 546.00
Enamel (Flat) 3 pcs 751.00 225.30 976.30 2,928.90
Enamel (Gloss) 6 pcs 712.00 213.60 925.60 5,553.60

V PLUMBING & ELECTRICAL WORKS - - - - - 18,000.00

Sub-total 173,808.10

III TOOL RENTAL AND HAULING 10.00% 17,380.81


IV CONTINGENCY 15.00% 26,071.22
V CONTRUCTOR'S FEE 25.00% 43,452.03

TOTAL 260,712.15
PREPARED BY:
JUN REY P. MAWE
LISCENCED CIVIL ENGINEER