Case Problem 4 Workforce
Case Problem 4 Workforce
Workforce Scheduling
Davis Instruments has two manufacturing plants located in Atlanta, Georgia. Product demand varies considerably
from month to month, causing Davis extreme difficulty in workforce scheduling. Recently Davis started hiring
temporary workers supplied by WorkForce Unlimited, a company that specializes in providing temporary
employees for firms in the greater Atlanta area. WorkForce Unlimited offered to provide temporary employees
under three contract options that differ in terms of the length of employment and the cost. The three options are
summarized:
Option Length of Employment Cost
1 One Month $2000
2 Two Month $4800
3 Three Month $7500
Over the next six months, Davis projects the following needs for additional employees:
Month Jan Feb Mar Apr May June
Employees 10 23 19 26 20 14
Needed
Managerial Report
Costs: Contract cost plus training cost
Option Contract Cost Training Cost Total Cost
1 $2000 $875 $2875
2 $4800 $875 $5675
3 $7500 $875 $8375
1. A schedule that shows the number of temporary employees that Davis should hire each month for each
contract option.
This study source was downloaded by 100000856590583 from CourseHero.com on 11-07-2022 09:00:31 GMT -06:00
https://www.coursehero.com/file/14036925/Case-Problem-4-Workforce/
Group 35 2
E1= number of temporary employees hired under Option 1 (one-month contract) in January
E11= number of temporary employees hired under Option 2 (two-month contract) in January
E21= number of temporary employees hired under Option 3 (three-month contract) in January
Jan. Feb. Mar. Apr. May June
Option 1 E1 X X X X X
Option 2 E11 X X X X X
Option 3 E21 X X X X X
E1 + E11 + E21= 10
Constraint 2: Need 23 additional employees in February
E2, E11 and E21 are the number of temporary employees hired under Options 1, 2 and 3 in February.
However, temporary employees hired under Option 2 or Option 3 in January will also be available for
February needs.
Jan. Feb. Mar. Apr. May June
Option 1 X E2 X X X X
Option 2 E11 E12 X X X X
Option 3 E21 E22 X X X X
E11 + E21 + E2 + E12 + E22 = 23
Constraint 3: Need 19 additional employees in March
Jan. Feb. Mar. Apr. May June
Option 1 X X E13 X X X
Option 2 X E12 E13 X X X
Option 3 E21 E22 E23 X X X
E21 + E12 + E22 + E3 + E13 + E23 = 19
Constraint 4: Need 26 additional employees in April
Jan. Feb. Mar. Apr. May June
Option 1 X X X E4 X X
Option 2 X X E13 E14 X X
Option 3 X E22 E23 E24 X X
E22 + E13 + E23 + E4 + E14 + E24 = 26
Constraint 5: Need 20 additional employees in May
Jan. Feb. Mar. Apr. May June
Option 1 X X X X E5 X
Option 2 X X X E14 E15 X
Option 3 X X E23 E24 X X
E23 + E14 + E24 + E5 +E15 = 20
Constraint 6: Need 14 additional employees in June.
Jan. Feb. Mar. Apr. May June
Option 1 X X X X X E6
Option 2 X X X X E15 X
Option 3 X X X E24 X X
E24 + E15 + E6 = 14
This study source was downloaded by 100000856590583 from CourseHero.com on 11-07-2022 09:00:31 GMT -06:00
https://www.coursehero.com/file/14036925/Case-Problem-4-Workforce/
Group 35 3
2. A summary table that shows the number of temporary employees that Davis should hire under each contract
option, the associated contract cost for each option, and the associated training cost for each option. Provide
summary totals showing the total number of temporary employees hired, total contract costs, and total
training costs
Option Number Hired Contract Cost Training Cost Total Cost
1 7 $14,000 $6,125 $20,125
2 3 $14,400 $2,625 $17,025
3 33 $247,500 $28,875 $276,375
Total: $275,900 $37,625 $313,525
3. An explanation of how reducing the cost to train each temporary employee to $700 per month affects the
hiring plan. Discuss the implications that this effect on the hiring plan has for identifying methods for reducing
training costs. How much of a reduction in training costs would be required to change the hiring plan based
on a training cost of $875 per temporary employee? (See Excel Solver Attachment)
4. A recommendation regarding the decision to hire additional full-time employees if Davis can hire 10 full-time
employees at the beginning of January in order to satisfy part of the labor requirements over the next six
months. Assume that Davis can hire full-time employees at $16.50 per hour, including fringe benefits, and
that full-time and temporary employees both work approximately 160 hours per month. What effect would
does the hiring of additional full-time employees have on total labor and training costs over the six-month
period as compared to hiring only temporary employees?
This study source was downloaded by 100000856590583 from CourseHero.com on 11-07-2022 09:00:31 GMT -06:00
https://www.coursehero.com/file/14036925/Case-Problem-4-Workforce/
Group 35 4
If Davis Instruments is hiring 10 full-time employees at the beginning of January, it will reduce the number of
temporary employees needed each month by 10.
Month Ja Fe Ma Ap Ma Jun
n b r r y e
Employees 0 13 9 16 10 4
Needed
Conclusion:
Davis Instruments should not continue to contract with WorkForce for temporary employees and instead hire
10 full-time employees. Hiring 10 full-time employees ($313,192) compare to hiring temporary employees
($313,525) results in $313,192 - $313,525= -$333 cheaper. Davis Instruments will save more money by hiring
10 full-time employees by $333.00 and will only have to pay for a one time training cost per employee after
hiring.
This study source was downloaded by 100000856590583 from CourseHero.com on 11-07-2022 09:00:31 GMT -06:00
https://www.coursehero.com/file/14036925/Case-Problem-4-Workforce/
Powered by TCPDF (www.tcpdf.org)