Revised BOQ R2 - AEMLMDB2018 19008
Revised BOQ R2 - AEMLMDB2018 19008
Construction of Substations
Sr. Description UOM Quantity Rate (Rs.) Amount (Rs.)
Construction of Sub station 7.5 X 4.5 M
Construction of complete substation including Excavation, Foundation super structure,
finishing door& windows etc complete with all respect to operation work as per given
drawing
1. Depth of Excavation - 1.0 m below ground level for trenches.
2. Depth of Column footing - 1.50 m below G.L.
1 3. Height of Plinth - 0.6m above G.L. SQM 303.75
4. Height of Slab above Plinth - 11.25ft. at center.
5. Plum concrete for transformer area in plinth.
6. Internal cable trenches to be covered by Openable R.C.C. Covers/R.C.C. Slab with
chamber
7. Wiring either concealed or with G.I.Pipe to be provided inside s/stn with sufficient light
points
8. Earthing pits
Construction of Sub station 8.5 X 5.5 M
Construction of complete substation including Excavation, Foundation super structure,
finishing door& windows etc complete with all respect to operation work as per given
drawing
1. Depth of Excavation - 1.0 m below ground level for trenches.
2. Depth of Column footing - 1.50m below G.L.
2 3. Height of Plinth - 0.6m above G.L. SQM 374.00
4. Height of Slab above Plinth - 11.25ft. at center.
5. Plum concrete for transformer area in plinth.
6. Internal cable trenches to be covered by Openable R.C.C. Covers/R.C.C. Slab with
chamber
7. Wiring either concealed or with G.I.Pipe to be provided inside s/stn with sufficient light
points
Construction of Sub station 12.5 X 6 M
Construction of complete substation including Excavation, Foundation super structure,
finishing door& windows etc complete with all respect to operation work as per given
drawing
1. Depth of Excavation - 1.0 m below ground level for trenches.
2. Depth of Column footing - 1.50m below G.L.
3 3. Height of Plinth - 0.6m above G.L. SQM 450.00
4. Height of Slab above Plinth - 11.25ft. at center.
5. Plum concrete for transformer area in plinth.
6. Internal cable trenches to be covered by Openable R.C.C. Covers/R.C.C. Slab with
chamber
7. Wiring either concealed or with G.I.Pipe to be provided inside s/stn with sufficient light
points
8. Earthing pits
Construction of Sub station 6.1 X 4.55 M
Construction of complete substation including Excavation, Foundation super structure,
finishing door& windows etc complete with all respect to operation work as per given
drawing
1. Depth of Excavation - 1.0 m below ground level for trenches.
2. Depth of Column footing - 1.50m below G.L.
3. Height of Plinth - 0.6m above G.L.
4 4. Height of Slab above Plinth - 11.25ft. at center. SQM 777.14
5. Plum concrete for transformer area in plinth.
6. Internal cable trenches to be covered by Openable R.C.C. Covers/R.C.C. Slab with
chamber
7. Wiring either concealed or with G.I.Pipe to be provided inside s/stn with sufficient light
points
8. Earthing pits
8 Construction of Cable Trench with slab as per attached drawing RMT 40.00
9 Construction of Cable Trench with RCC pipe RMT 20.00
Extra for consruction of Chambers of size( 0.75 m X 1.2 m internal)inlcuding
10 excavation,soling 230 mm thk,PCC 1:2:4 150 mm thkwith removable RCC M 20 covers of Nos 5.00
0.15 m thick
11 Construction of Cable Trench with removable RCC covers as per attached drawing RMT 5.00
Earthwork in excavation in following types of soil in foundation trenches, basements, water
tanks, drains or trenches of required width for pipes, cables, etc in all kinds of soil including
all labour and equipment, dewatering,shoring, strutting, excavating, lifting, dressing of sides
12 and ramming of bottom including loading and transport to stock area of the excavated
materials within the plant boundary. Only PCC area shall be cosidered for payment.
Providing and laying cast-in-situ plain cement concrete using graded stone aggregate
15 including consolidation, finishing, curing, Complete all as per specification:
1:3:6 (1 cement:3 coarse sand:6 graded stone aggregate 40mm nominal size)
a Cum 18.00
1:2:4 (1 cement:2 coarse sand:4 graded stone aggregate 20mm nominal size)/ Coping
b Cum 29.00
Providing and laying cast-in-situ reinforced cement concrete (up to plinth level in any type of
structure) using graded stone aggregate including consolidation, finishing, curing, Complete
16 all as per specification Cum 11.00
1:1.5:3 (1 cement: 1.5 coarse sand: 3 graded stone aggregate 20mm nominal size) for
foundations, plinth beams, stubs, etc.
Providing and laying cast-in-situ reinforced cement concrete above plinth level (in retaining
walls of any thickness, walls, pillasters, columns, pillars, posts, struts, beams, lintels,
staricase, windoe sills, roofs/ floors with slopes, etc.) using graded stone aggregate including
17 consolidation, finishing, curing, complete as per the specification upto floor level 5:1:1.5:3 (1 Cum 24.00
cement: 1.5 coarse sand: 3 graded stone aggregate 20mm nominal size)
Random rubble masonry with approved quality of stone in foundation and superstructure at
all levels with cement mortar 1:6 (1 cement:6 coarse sand) including levelling up with
18 cement concrete 1:6:12 (1 cement:6 coarse sand: 12 graded stone aggregate 20mm nominal Cum 1.00
size), all complete as directed by the Engineer-in-Charge.
Providing and laying rubble stone soling vertically hand shaked interstices packed with small
19
stone chips ramming and consolidating complete.
a 150mm. thk. Sqm 29.00
b 230mm. thk. Sqm 117.00
Providing & Laying 40 mm thk IPS flooring with CC1:2:4, to the required slope or level and as
per the pattern given including, surface preparation, compaction, smooth finishing with
20 Sqm 60.00
float, curing, cleaning etc complete as per the instructions of the EIC.
Brick work having thickness 230mm or more with class designation 35 bricks in foundation,
plinth and steps including racking out joints and simultaneously pointing below ground level
21 where surfaces shall not be plastered in: Cum 54.00
Cement mortar 1:6 (1 cement : 6 coarse sand)
Cement plaster 12 mm thick for internal walls and trenches with c.m. 1:4 finished smooth
22 over brick wall or concrete surface including hacking, scaffolding, curing, complete. Sqm 226.00
Cement plaster 6 mm thick for ceiling with c.m. 1:3 finished smooth over brick wall or
23 concrete surface including hacking, scaffolding, curing, complete. Sqm 101.00
Sandfaced cement plaster 20mm thick in two coat over exterior masonry and concrete
surface with base coat in c.m.1:4, 12 mm thick and finishing coat should be 8 mm thk in
24 cement morter 1:3 final rendering at all floors and level in quantities as required at site Sqm 241.00
including scaffolding, hacking of concrete surface, curing etc. complete.
Reinforcement for RCC at all levels including supplying cutting, bending, placing and tying in
25 position with 1.6 mm dia soft drawn annealed binding wire etc. Complete as per MT 3.00
specification With rebars
Centering and shuttering including strutting, propping etc. and removal of form work for:
26
Providing and fixing RCC louvers including dressing remarkng edges where necessary.
27 Sqm 1.00
Only Fixing charges of RCC louvers including dressing remarkng edges where necessary (RCC
28 louvers to be supplied free of cost to the contractors by the company at the company’s Sqm 1.00
stores at Santacruz)
29 Providing and fixing RCC Grill (2' X 2'6^ SIZE) 40/ 50mm thick Sqm 15.00
Providing and making water drip mould to slab or chhaja or any other projection complete
30 Rm 63.00
P&A Jadoo Acrylic Distemper confirming to ISI/IGBC and GRIHA specifications with dilution
of 65-70% (v/w) depending on surface conditions. Filling the gaps, holes etc with putty and
then Apply one coat of primer and 2 coats of paint of overall thickness of 100 micron DFT to
the plastered surface including scafolding, cleaning and preparing the surface such that it is
free from chalking, dust, nails, wooden battons, cement splatters, loose dead hanging wires,
grease, loose paint, fungus and algae and any foreign material,etc. All Equipments, switch
31 Sqm 327.00
boards, bulbs, tubelights to be covered by tarpolin/plastic/newspaper or suitable material to
ensure that they are not damaged. After completion of painting, premises to be cleaned and
any left over materials shall be removed/disposed as per EMS and MCGM norms.
Providing and applying two coats of futura with approved make and shade over one coat of
32 cement primer for external surface of the structure. Sqm 241.00
P & F steel louvered (partly) MS sheet doors as per secifications and drawing consisting of
ISMC75x40, ISA50x50x6, 16SWG MS sheet, 5mm thick MS Strip, GI wire mesh, fixtures,
34 Sqm 24.00
fastening etc., including painting with 2 coats of synthetic enamel paint over one coat of red
oxide primer, etc. complete
P&F GI Strip of 50x6mm size inside plinth beams and columns during construction work for
35 providing earthing to the equipments as shown in the drawings, complete. Rm 1.00
P & F light points with angle holder and switches on board with 1 sqmm copper wire with
36 PVC coating drawn in PVC pipe/ casing and caping. Nos 12.00
P & F 15 Amps 3 pin plug points with copper wire with PVC coating drawin in PVC pipe/
37 casing and caping. Nos 2.00
P & F 30 Amps Main Switch or 15 Amps iron clad DP switch and cable of 3/20 5m long
38 Nos 2.00
Laying of bentonite paste (bentonite 1:6 Water) in earthing pits. Bentonite will be supplied
39 by REL. Nos 8.00
S&I 6/16A Switched Socket for Substation wiring in M.S.Conduit or concealed including
removal of broken holders,pvc conduits unwanted wiring and safe disposal at Zonal store
49 locations specified by Engineer-in-charge. and as per EMS norms. Nos 2.00
S&I 30 amps Main switch for substation wiring in M.S.Conduit or concealed including
removal of broken holders,pvc conduits unwanted wiring and safe disposal at Zonal store
50 Nos 2.00
locations specified by Engineer-in-charge. and as per EMS norms.
Supplying and fixing (3 and half point board) sunmica switch board 12x10 inch with old
black round 3 no. of switches,1 no of socket and batton holder. With one no of
51 Nos 2.00
fuse.including 2 X 2.5 sqmm pvc copper armoured cable to give supply to board including
removal of broken holders,pvc conduits unwanted wiring and safe disposal as per EMS
norms.
P&F Substation Name plate and Safety Boards
For substation Name plate -
1) Providing and fixing 2' x 1' vitrified tile flushed and levelled with the external portion of
substation wall as per location approved by Engineer in charge.
2) Supplying and sticking of sunboard of 3mm thickness and size 2' x 1' with printing of
substation name of size as per Engineer in charge & RELIANCE monogram by 3M two way
tape on that vitirified tile.
For Safety Boards -
52 1) Supplying and fixing of Polycarbonate sheet of thickness 3mm with 3M paper with both NOS. 2.00
way tape for sticking of First aid chart (2' x 2'), Fire extinguisher (10" x 3") and Fire bucket
board (10" x 3") as per location approved by Engineer in charge
2) Supplying and sticking of 3 Nos. of sunboard with printing of of Fire extinguisher, Fire
bucket and First aid chart of 3mm thickness and of size as per Engineer in charge by two way
tape on that polycarbonate sheet.
P&F Galvanised precoated roofing Providing and fixing 0.8 mm thick (TCT) galvanised
,precoated trapezoidal,Jindal make Roofing Sheet profiled sheet with high durable polyester
coated (H.D.P)which is ultraviolet rays resistant, corrosion resistant& weather resistant of
approved make.Coating should be of average 20 micron thick of H.D.P and Epoxy coating of
5 micron thick avg. at top & bottom avg. 5 micron thick of epoxy coating of approved shade
on hot dip galvanised profile sheet with 220GSM substrate steel as per IS-277 & IS-513
made to long lengths with adequate lap fixed with self taping G.I screw of HILT make or
equivalent with anti cyclone special device of EPDM lining under screws/or J/L or ""U""
53 hooks bolt and nuts of 8mm dia with neopasine and bitumen washer one GI screw to be Sqm 60.00
fixed at intermediate support and every alternate pitch with S/S & S/T screws
for side stitching at 300mm to 400mm center on every side top of sheet including necessary
ridges etc.complete as per the direction of Engineer-in-charge . (Note: only effective length
& width excluding over lapping (plan area) will be measured for payment & nothing extra
will be paid for over-lapping).
Amount (Rs.) -
Taxes -
-
Gross Total (Rs.) -