Book - Sprayed Concrete - en
Book - Sprayed Concrete - en
Acknowledgement
BASF wishes to thank all colleagues that were involved in the making of this
completely new edition including Atlas Copco MEYCO AG, BASF’s partner for
sprayed concrete equipment. Their broad practical experience from numerous
job sites worldwide, combined with chemistry and material science knowledge,
made this book possible.
Copyright © BASF Construction Chemicals Europe Ltd., 2014
13th edition, March 2014
1. INTRODUCTION 13
1.1. Objectives of this book 14
1.2. History of sprayed concrete 15
1.3. Terms, definitions and abbreviations 17
1.4. Sprayed concrete as an application process 24
1.5. Sprayed concrete as a construction process 27
1.6. The current use of sprayed concrete 29
13
engineering knowledge, committed to accepting challenges and ensur-
ing safety for workers and the environment in the fields of tunneling and
underground mining. BASF’s Master Builders Solutions brand brings
expertise together to create chemical solutions for new construction,
maintenance, repair and renovation of structures. Master Builders
Solutions is built on the experience gained from more than a century in
the construction industry.
14
The techniques and procedures described in this book are based on
many years of practice and experience. No attempt is made to provide
guidelines for the design of sprayed concrete structures or installations.
As procedures vary from one country to another, adjustments may be
required to meet the needs of the specific project.
Sprayed concrete, like many new products, was developed in the 19th
century to meet specific, individual needs. In 1895 Dr Carlton Akeley, the
curator at the Field Museum of Natural Science in Chicago, USA, was
looking for a way to create models of prehistoric animals. The manufac-
ture of a skeleton frame had been successful, but the body shapes could
not be formed using conventional trowelled mortars.
15
Figure 1-1: Early machine for dry-mix sprayed concrete, Oakley 1900
During the use of the early machines a dry mix of sand and cement was
placed into the pressurized chamber. The mix was then conducted from
the chamber to a nozzle where water was added. This method was
therefore labeled the “dry process”. At the same time as the dry process
was being developed, the “True Gun” method evolved. In this technique,
sand and cement had to be fully mixed with water before being pumped
through a completely different machine. This method, which became
known as the “wet process” due to the difference in mixing, was not fully
developed commercially until the later part of the 1970s when Norwegian
contractors developed machines able to apply wet sprayed concrete
robotically in tunneling projects.
16
Figure 1-3: Modern sprayed concrete manipulator (MEYCO Roadrunner)
Regarding terminology, ‘Gunite’ was the original name for the sprayed
mixture of sand and cement. Other terms have been used, including
17
‘sprayed concrete’, ‘shot concrete’ and ‘shotcrete’. When describing
a mix with maximum aggregate size greater than 10 mm, ‘shotcrete’ is
often used. Today, it is the norm to use the term ‘shotcrete’ in the United
States and the term ‘sprayed concrete’ in Europe. The term ‘sprayed
concrete’ is used in this book for every sprayed mixture of cement and
aggregates.
The following definitions cover terms used in this book (in alphabetical
order):
< A AR – Alkali Aggregate Reaction – expansion of siliceous aggregates
AAR/ASR.
< A lkali equivalent (% Na O) – total amount (%) of sodium and potassium
2
ions, calculated as total sodium oxide. Important durability factor.
< A spect ratio, fiber – the ratio of length to diameter of a fiber. The
18
< B
leeding – separation of water from concrete mix with poor mix
design. Negative impact on pumping and performances.
< B
NS – beta(ß)-naphthalenesulfonate – mid-range water-reducing
admixture (MRWR).
< B
ond – adherence of concrete to any substrate.
< C
ylinder filling percentage – degree of filling of the sprayed concrete
also relaxation). The term “specific creep” is often used. It is the creep
strain per unit stress (typically in units of 10-6 -/MPa).
< C
uring – hardening of concrete and treatment of the concrete surface
ing out. Curing agents are sprayed on the surface of fresh concrete.
< D
enier – measure of fiber diameter. It is taken as the mass in grams of
19
durability depending on the exposure environment and properties
desired.
< D
urability factor – percentage of weight loss after 300 freeze-thaw test
cycles.
< E
arly age compressive strength – strength developed by young
< F
resh concrete – concrete that is fully mixed and still in a condition that
< G
GBS – Ground Granulated Blast Furnace Slag (see also GGBFS,
BFS).
< H
ardened concrete – concrete that is in a solid state and which has
20
< Interfacial zone – zone between two layers either of the same material
or between different materials.
< L
eachate – any liquid that, in passing through matter, extracts solutes,
a liquid [51].
< L
ignosulfonate – LS, LRWR water-reducing admixture.
< L
RWR – low-range water-reducing admixture.
< L
S – Lignosulfonate (LRWR plasticizer).
< L
ubrication – lubrication of pumping hoses by a cement slurry or by
< M
icrofiber – a fiber for use in concrete with an equivalent diameter less
< M
S – Microsilica (silica fume) – a fine-grain, very high surface area
< N
on-alkaline sprayed concrete set accelerating admixture – according
hyperplasticizer.
21
< P
umpability – the pumpability of concrete is its ability to move through
pipes and hoses with the help of a pump while maintaining its fresh
and hardened properties. It can be quantified as being better the
lower the necessary pressure to obtain a given flow in a specific con-
figuration and set-up (pump type/capacity, pipes/hoses, diameter/
length etc).
< P
umping aids – chemical pumping aids or viscosity modifying admix-
early stage. Initial and final set are indicators of the speed of hydra-
tion.
< S
et-accelerating admixture – according to EN 934-2: “admixture
< S
lump/slump retention – measure for consistency and workability or
ed to the maximum distance of any point in the cement paste from the
periphery of an air void, measured through the cement paste; units
are mm. The calculation of this parameter assumes that all air voids
present are of uniform size and are evenly distributed through the
cement paste such that the model system has the same total volume
and surface area as the real system.”
< S
prayed concrete – a mixture of cement, aggregate with a maximum
22
< S
prayed concrete admixture – according to EN 934-5: “material
added to the concrete mix before or during the spraying process, in
a quantity not exceeding 5 % by mass of cement, except for sprayed
concrete set accelerating admixture, where the dosage should not
exceed 12 %, to modify the properties of the mix in the fresh and/or
hardened state.”
< S
prayed concrete set accelerating admixture – according to EN 934–5
< S
urface – substrate to which concrete is applied. Can be rock, soil,
< W
ater/cement ratio (w/c) – the weight ratio of water to the weight of
durability factor.
< W
ater reducing/plasticizing admixtures – according to EN 934-2:
dients, including water, are mixed before introduction into the delivery
hose. Compressed air is introduced to the material flow at the nozzle.
If a set accelerator is used it is normally added at the nozzle.
< Y
oung sprayed concrete – sprayed concrete up to an age of 24
hours.
23
1.4. Sprayed concrete as an application process
Economic and technical differences may make one method or the other
more attractive for a particular application. Deciding factors may be
the capital and maintenance costs of equipment, operational features,
suitability of available aggregate and placement characteristics. In the
following Table 1-1 the main features of the wet-mix method and the dry
mix method are compared.
24
Wet-Mix
Main Features Dry-Mix Method
Method
Equipment capital cost + -
Output 0 +
Equipment complexity + 0
Operating cost - +
Conveying distance + 0
Rebound - +
Dust - +
Use of fibers - +
Key: + advantage, 0 neutral, - disadvantage
Wet-mix spraying has been most commonly used as this method gives a
better working environment (high standard of health and safety), a higher
and more consistent quality, and much higher production rates, with
output rates as high as 20 – 30 m3 per hour, and low rebound (less than
10 %). With dry-mix spraying, much higher rebound levels (approx. 30 to
50 %) and lower performance should be expected.
The total cost of the sprayed concrete process is probably the most
disputed issue during the decision process. Some contractors focus
on material and equipment costs and put less emphasis on differences
in labor, while others are willing to consider all imaginable influences,
including savings on total construction time. Where sprayed concrete
volumes are in the order of more than 50,000 m3, the difference in con-
struction time can easily reach several months in a pure calculation of the
time needed to place a certain volume of sprayed concrete onto the tun-
nel wall. The wet-mix process demands higher material costs, which is
compensated by the multiplying effects of low rebound and high output.
The wet-mix method requires a rather simple supply system, using tech-
nology readily available in most countries, such as normal batching plants,
ordinary Portland cements, truck mixers etc. The wet-mix design focuses
on pumpability, low water/cement ratio and open time. The use of acceler-
ating admixtures at the nozzle enables adaptability to given spraying condi-
tions, e.g. position of application and water ingress. The wear costs of the
whole wet-mix process are by far lower than those of dry-mix processes.
25
Cement
Aggregates
Admixtures
Water
Accelerator
Electricity
Compressed air
26
1.5. Sprayed concrete as a construction process
The use of SCL for tunnels in soft ground in urban areas is based on
construction techniques that include sequential excavation, the applica-
tion of sprayed concrete as a primary lining and geotechnical monitoring.
This type of application is relatively recent, compared to its use in rock.
Installation of primary excavation support in soft ground is required as
soon as possible after excavation, in order to maintain stability of the
excavation and in many cases, e.g. in urban areas, to limit settlement and
avoid damage to overlying structures. Excavation work must be divided
27
into sufficiently short stages and rapid completion of primary support,
i.e. rapid closure of the sprayed concrete ring is required. The perform-
ance and safety of the primary support is monitored by instrumentation
to validate its design. The sequence of excavation and face areas may
vary depending on the results of monitoring lining behavior.
< It allows rapid installation of structural support through the shell lining,
structures.
< T he good bonding and self-supporting properties of sprayed con-
BENCH BENCH
INVERT
INVERT
Invert
Temporary backfill in invert during construction
28
1.6. The current use of sprayed concrete
Today, the most relevant areas of use of sprayed concrete are tun-
neling, mining and concrete rehabilitation. In the tunneling and mining
sectors, sprayed concrete has been used both as initial excavation
29
support (mostly seen as temporary tunnel lining) as well as for perma-
nent tunnel lining. Sprayed concrete has become indispensable in the
modern design approach for the concrete lining of tunnels, which treats
the sprayed concrete lining as a permanent structure, e.g. single shell
lining (SSL) and composite shell lining (CSL). The latter includes a spray-
applied waterproofing membrane.
30
2. TYPICAL PROPERTIES AND
PARAMETERS OF SPRAYED
CONCRETE
Sprayed concrete mixtures are of different types, including plain (unre-
inforced), silica fume, blast furnace slag, fiber-reinforced, high-strength
and high-performance, with different hardening properties.
Two of the key parameters for both wet-mix and dry-mix sprayed con-
crete are the water/cement ratio (w/c) and the combined aggregate grad-
ing curve. Most properties of sprayed concrete improve with reduction
of w/c, including its strength, permeability and durability. The addition
of accelerators, silica fume, or other pozzolans changes the physical
properties of sprayed concrete, particularly permeability and durability.
Sprayed concrete’s resistance to freezing and thawing enhances with
the use of air-entraining admixtures, while the use of fibers improves its
toughness. Proper curing is important and improves the mechanical and
physical performance of sprayed concrete.
31
applied sprayed concrete can be expected to be below 0.5. In-situ w/c
ratios usually vary from 0.4 to 0.5. In the case of dry-mix sprayed con-
crete, the w/c ratio should be assessed by the continuous monitoring of
consistence during spraying. See also EN 14487-1 [32].
80
Compressive Strength [MPa]
60
40
20
0
0.3 0.4 0.5 0.6 0.7
Water/Cement ratio
2.2.1. Workability
32
2.2.1.1. Flow
Sufficient flow, measured with a flow table, is a first indicator for workability.
In the same procedure, besides flow, bleeding and / or segregation can
be observed if the consistency is wrong. Bleeding and segregation can
be a consequence of insufficient mix design, which may cause blockages
during pumping. For wet-sprayed concrete, flow should be in the range
of 55–65 cm. High flow values are required for high output machines.
The flow classes of the fresh concrete are given in Table 2-1 based on EN
206-1:2000. The flow table test can be done according to EN 12350-5.
33
increase both slump and slump retention respectively. Particularly due
to long transportation time, working delays and interruptions, slump
retention of 18 – 22 cm can be required for up to 24 hours.
Table 2-2 below shows the slump classes based on EN 206-1: 2000.
Slump testing of fresh concrete can be carried out according to EN
12350-2.
In the following table, the effect of the w/c ratio and water-reducing
admixtures on slump retention is presented.
Slump Retention
Table 2-3: Slump retention of sprayed concrete mixes at different w/c ratios
34
300
250
200
Slump [mm]
150
100
50
0
0 0,5 1 1,5 2 2,5 3 3,5
Time [hours]
Without Admixture
Plasticizer
Superplasticizer
Figure 2-3: Measurement of slump (on the left) and flow (on the right)
35
During a flow test, energy is put into the mix in the form of a ‘dynamic
impact’, generating a behavior more similar to that which occurs in a
real-life situation during pumping and placing. Thus, making a ‘fresh
concrete pie’ provides a better opportunity to observe bleeding and
segregation compared to the slump testing method, where the tested
concrete is left to collapse under its own weight.
It should be emphasized that neither slump nor flow provides a real pic-
ture of consistency, which is essential for pumping purposes.
2.2.1.3. Pumpability
< C
ement and/or paste content (> 420 kg rather than < 400 kg).
< T
ype and amount of mineral additives.
< T
otal mixing water (normally in the range of 180 to 220 liters).
< F
ibers (type and content), which decrease pumpability.
< A
dmixtures (water-reducing and viscosity-modifying admixtures).
36
per shortly before the concrete is pumped. The admixture industry offers
a number of so-called pumping aids or viscosity-modifying admixtures
(see Chapter 3.5.4). Both contribute to better cohesiveness and less
segregation of poor concrete mixes. Adequate equipment and pipe
diameter are further decisive factors. Pumping distances of several hun-
dred meters can be achieved if all the relevant parameters are optimized.
37
< T
ype and dosage of accelerators added to the concrete-mix.
< L
ayer thickness.
< T
emperature of concrete and environment.
100
20
10
5
J3 C
Y 2 B
1 J2
0,5 A
J1
0,2
0,1
6 10 30 1 2 3 6 9 12 24
X Z
Key
X Minutes
Z Hours
Y Compressive strength fG in N
mm2
38
The strength development of the young sprayed concrete can be
specified according to the early-age strength classes J1, J2 or J3 as
described in EN 14487-1 [32], and shown in Figure 2-4.
39
2.3.4. Toughness
Strength Level
Deformation range
(minimum strength, MPa)
Deflection (mm) S1 S2 S3 S4
D1 0.5 to 1
D2 0.5 to 2 1 2 3 4
D3 0.5 to 4
40
2.3.4.2. Energy absorption capacity
41
2.3.6. Bond strength to substrate
Sprayed
concrete layer
Sprayed
Cohesion failure concrete layer
Sprayed
concrete layer Adhesion failure
Substrate Substrate
42
The bond of a second layer of sprayed concrete applied on top of a first
layer depends on the surface quality of the first layer. Therefore, curing
and cleaning dust and/or curing agents from the first concrete layer
are essential. However, commercially available curing agents exhibit
hydrophobic/water-repellent properties and they may act as a separa-
tion layer between the first and the second concrete layer. Their removal
is expensive and not always successful. A possible solution is discussed
further in Chapter 3.5.5.1.
2.3.7. Shrinkage
43
2.3.8. Density
2.3.10. Permeability
44
Permeability Low Average High
(m/sec) < 10 -12 10 -10 - 10 -12 > 10 -10
The diagram below shows the impact of increasing w/c ratio on the
permeability of concrete. Low w/c ratios lead to low permeability of the
concrete. Additionally, permeability can be substantially reduced by the
addition of microsilica and by special admixtures (see Chapter 3.5.5.1).
150
120
Permeability 10 -12 m/s
90
60
30
0
0,35 0,45 0,55 0,65
W/C Ratio
45
of at least 4 % and a maximum air void spacing factor of lower than 0.30
mm, in order to resist rapid freezing-and-thawing cycles (ASTM C 666).
A low w/c ratio, combined with proper air entrainment, is crucial to obtain
a desired durability factor greater than 95 %, which corresponds to less
than or equal to 5 % weight loss after 300 FT cycles (see Figure 2-7).
100
Durability Factor [%]
75
50
25
0
0 1 2 3 4 5 6
Testing the absorption value and the volume of permeable voids is use-
ful to identify poorly compacted sprayed concrete. In addition, a weak
46
or damaged microstructure in the sprayed concrete can be identified
through the absorption test (ASTM C 642). It may be conducted on hard-
ened sprayed concrete to provide an overall indication of its quality.
2.3.13. Durability
47
“Buildable” design
Future environment
and load conditions Modern, relevant
specifications
Site control
Monitoring and action
Capable and
Durable trained applicators
sprayed concrete
Ground and H2O structure
conditions acting
on structure Wet or dry-mix
method?
48
3. CONSTITUENT MATERIALS
AND REQUIREMENTS
As defined in the European Specification for Sprayed Concrete, issued
by EFNARC [29]: “Sprayed concrete is a mixture of cement, aggregate
and water projected pneumatically from a nozzle into place to produce
a dense homogeneous mass. Sprayed concrete normally incorporates
admixtures and may also include additions or fibers or a combination
of these.”
3.1. Cement
49
“Cement is typically made from limestone and clay or shale. These raw
materials are extracted from the quarry, crushed to a very fine powder
and then blended in the correct proportions.
This blended raw material is called the ‘raw feed’ or ‘kiln feed’ and is
heated in a rotary kiln where it reaches a temperature of about 1400 °C
to 1500 °C. In its simplest form, the rotary kiln is a tube up to 200 meters
long and perhaps 6 meters in diameter, with a long flame at one end.
The raw feed enters the kiln at the cool end and gradually passes down
to the hot end, then falls out of the kiln and cools down.
The cement mill grinds the clinker to a fine powder. A small amount of
gypsum – a form of calcium sulfate – is normally ground up with the
clinker. The gypsum controls the setting properties of the cement when
water is added.”
50
Figure 3-1: Cement production process according to [25]
The 27 types in the list of common cements and their notation are
provided by EN-197-1, see [1]. They are grouped into five main cement
types as displayed in the following table. The detailed composition of
each of the 27 products in the family of common cements shall be in
accordance with EN 197-1.
51
MAIN CONSTITUENTS %
Fly
Clinker Slag Micro-
CEMENT TYPE Pozzolan ash Others
content (GBFS) silica
(PFA)
CEM I Portland 95 - 100
CEM II Portland-composite 65 - 94 6 - 35 6 - 10 6 - 35 6 - 35 6 - 35
CEM III Blastfurnace 5 - 64 35 - 95
CEM IV Pozzolanic 45 - 89 11 - 55
CEM V Composite 20 - 64 18 - 50 18 - 50
52
Figure 3-2: Representation of a cross-section of a cement grain [5]
(C3S-Ca3SiO5 , C2S-Ca2SiO4 , C3A-Ca3 Al2O6 , C2(A,F)- Ca2 AlFeO5 )
Alite
Alite is the most important mineral phase of all normal Portland cement
clinkers, of which it constitutes 50–70 %. It is tri-calcium silicate (Ca3SiO5
or C3S) modified in composition and crystal structure by ionic substi-
tutions. It reacts relatively quickly with water, and in normal Portland
cement is the most important of the constituent phases for strength
development; at ages up to 28 days, it is by far the most important.
Belite
Belite constitutes 15–30 % of normal Portland cement clinkers. It is
dicalcium silicate (Ca2SiO4 or C2S) modified by ionic substitutions and
normally present wholly or largely as the ß- polymorph. It reacts slowly
with water, thus contributing little to the strength during the first 28 days,
but substantially to the further increase in strength that occurs at later
ages.
Aluminate
Aluminate constitutes 5–10 % of most normal Portland cement clink-
ers. It is tricalcium aluminate (Ca3Al2O6 or C3A), substantially modified
in composition and sometimes also in structure by ionic substitutions. It
reacts rapidly with water and can cause undesirably rapid setting unless
a set-controlling agent, usually gypsum, is added.
53
Ferrite
Ferrite makes up 5–15 % of normal Portland cement clinkers. It is tet-
racalcium aluminoferrite (Ca 2AlFeO5 or C2AF), substantially modified in
composition by variation in Al/Fe ratio and ionic substitutions. The rate
at which it reacts with water appears to be somewhat variable, perhaps
due to differences in composition or other characteristics, but in gen-
eral is high initially and low or very low at later ages.
C3 A + 3C S + 32 H → C3 A ⋅ (C S ) 3 ⋅ H 32 ∆H = −1350 kJ / kg
C3 S + (3 − x + y ) H → C x SH y + (3 − x)CH ∆H = −500 kJ / kg
C2 S + (2 − x + y ) H → C x SH y + (2 − x)CH ∆H = −250 kJ / kg
C2 AF + CH + 3C S + 31H → C3 ( A, F ) ⋅ (C S ) 3 ⋅ H 32
54
Ettringite (see Figure 3-3), occurs as hexagonal prismatic crystalline; it is
usually the first hydration product to crystallize because of the high sul-
fate/aluminate ratio in the solution phase during the first hour of hydra-
tion. In normal Portland cements which contain 5 to 6 % gypsum, the
precipitation of ettringite contributes to stiffening (loss of consistency),
setting (solidification of the paste) and early strength development.
55
3.1.4.3. Contributions of hydration products
to strength development
Cement Hydration
70 10,000
60 C3S
Compressive Strength [MPa]
40 6,000
C 2S
30 4,000
20
C3A+CSH2 2,000
10
-
C4AF+CSH2
0 0
0 20 40 60 80 100
Time [days]
56
3.1.5. Typical characteristics of cement
related to sprayed concrete
In order to obtain satisfactory results for sprayed concrete, not only the
cement type has to be considered. In addition, there are a number of
other key factors such as clinker content, fineness (Blaine value), C3A
and gypsum contents. These factors are responsible for rapid setting
and early strength development.
Table 3-2: Some key parameters of most commonly used cements for
sprayed concrete
57
CEM I 42,5 N CEM II 42,5 N
Cement Type CEM I CEM II CEM III Accelerated Accelerated
with AFA with AFA
Initial setting time
≥ 45 ≥ 45 ≥ 45 1.5 - 5 2 - 10
(minutes)
Typical initial setting
≈ 110 ≈ 125 ≈ 90 ≈5 ≈2
time (minutes)
Final setting
≤ 375 ≤ 420 ≤ 420 10 - 50 10 - 50
time (minutes)
Typical final setting
≈ 230 ≈ 245 ≈ 190 ≈ 15 ≈ 30
time (minutes)
Table 3-3: Setting times (with and without set accelerators) of cements
based on strength classes
58
Criteria Related aspects and requirements
Economy Cost of construction, return on investment, lifecycle, value
Ecology Resources, land use, emissions, energy
Comfort, health, safety, indoor air quality (products free
Social aspects
from pollutants or even able to absorb them)
Regarding clinker and CO2 reduction, a trend has been observed towards
blended cements. As shown in Figure 3-5, blended ratio increases more
greatly than the overall total global demand for cement. This trend is
expected to continue in coming years.
59
Global cement demand from 2005 to 2015
4.0
+ 4.7 %
3.5
3.0
2.5
Billion Tons
2.0
1.5
1.0 + 6.6 %
0.5
0.0
2005 2010 2015
Year
Global Demand
Blended
Figure 3-5: Global cement demand (billion tons) from 2005 and expec-
tation towards 2015 (source: Fredonia)
3.2. Aggregates
60
Figure 3-6: Round aggregate (left), crushed aggregate (center) and the
sphericity of crushed aggregates (right)
The dry density of aggregate varies between 300 to more than 1700 kg/
m3. Aggregate is classified as:
61
< T
he maximum aggregate size should be limited to 8 or 10 mm,
because of limitations of pumping equipment and to avoid excessive
rebound and resulting material losses.
< A
ggregate grading is also very important, particularly its lower part
of clogging.
< T
oo high content of fine material in the sand increases the water
62
< C
ompared to fine aggregate, coarse aggregate possesses a reduced
< W hen applied at high velocities, it forms craters on the surface of the
63
ISO sieve, sieve size in mm
0.125 0.25 0.5 1.0 2.0 4.0 8.0 16.0 32.0 64.0
0
10
Percentage retaining 20
30
40
50
60
70
80
90
100
0.149 0.297 0.595 1.19 2.38 4.76 9.51 19.0 38.1 76.1
The following Table 3-5 shows recommended grading limits for sprayed
concrete aggregates, with percentage by weight passing individual
sieves. Further recommended aggregate gradation zones can be found
in [29] and [30].
ISO sieve
Percent by weight passing individual sieves
size [mm]
minimum maximum
0.125 4 12
0.25 11 26
0.5 22 50
1.0 37 72
2.0 55 90
4.0 73 100
8.0 90 100
16.0 100 100
64
The percentage of 8 mm aggregate should preferably not exceed 10 %,
since it will rebound when spraying on a hard surface (when starting the
application) or penetrate previously placed concrete, producing craters
which are difficult to fill.
Sand/aggregate Sand/aggregate
Aggregate
percentage percentage Remarks
size [mm]
approx. [%] approx. [%]
In some cases crushed fine
0–2 40 60 aggregates (≤ 2 mm) are
(fine aggregates) used up to 1000 kg/m3
2–4 20
40
4–8 40
(coarse aggregates)
3.3. Additives
The most commonly used additives in sprayed concrete are fly ash,
ground granulated blast furnace slag and silica fume. These additions
shall comply with the relevant European standards or national standards
or regulations valid in the place of use of the sprayed concrete. Where
appropriate standards and/or regulations do not exist, the use of addi-
tives shall comply with the recommendations of the suppliers.
65
The use of additives for permanent structures shall match the require-
ments of EN 206-1 or national standards and regulations valid in the
place of use.
< d ensified
66
< reduction of alkali aggregate reaction (AAR)
< h
igher durability
Due to its fineness and its chemical composition, silica fume is a poz-
zolanic (reactive) material. It does not contribute to either setting or early
strength but to the final strength of sprayed concrete. A typical dosage
in a sprayed concrete mix ranges from 20 to 40 kg/m3. Microsilica can
basically replace a certain amount of cement, but it should be used as
an additive rather than as a cement replacement.
The activity index for silica fume is the ratio (in percent) of the compres-
sive strength of standard mortar bars, prepared with 90 % cement plus
10 % silica fume by mass, to the compressive strength of standard
mortar bars made from cement only (Norwegian Standard NS 3045).
The following diagram in Figure 3-9 shows the strength development of
concrete mixes with different microsilica (MS) contents.
70
60
Compressive Strength [MPa]
50
40
30
20
10
0
1 3 6 28 64 90
Days
0% MS
5% MS
15% MS
67
cal production of higher strength performances (50–60 MPa) can be
achieved by the addition of microsilica, even with reduced cement con-
tent (less than 400 kg/m3). It seems favorable from a technical point of
view to use 5 to 10 % bcw of microsilica.
68
magnesia). It is classified in grades 120 – 100 – 80, based on the slag
activity index (SAI). The chemical composition of the GBFS depends on
the production process and the origin of the raw material.
3.3.4. Limestone
3.3.5. Summary
Rebound
reduc-
Maximal Compressive Rebound tion and
Additive amount strength Permeability reduction build-up
per m3 [% bwc] increase [%] [%] increase in
[%]
69
3.4. Water
Water for mixing shall comply with the requirements of EN 1008 or the
national standards and regulations.
As mentioned in EN 1008 [39], “The quality of the mixing water for pro-
duction of concrete can influence the setting time, the strength devel-
opment of concrete and the protection of the reinforcement against
corrosion. When assessing the suitability of water of unknown quality for
the production of concrete, both the composition of the water and the
application of the concrete to be produced should be considered.”
Mixing water should not contain any substances that may be harmful to
concrete or steel. Harmful substances include. sulfate, chloride, alkali
(Na2O > 1500 mg/l), sugars, oil etc. Potable water should be used for
mixing purposes. According to ACI 506R-05 [30], “If potable water is not
available, the mixing water should be tested to ensure that compressive
strengths of mortar cubes made with it are at least 90 % of that of mortar
cubes made with distilled water (Section 3.4 of ACI 318). Cubes should
be made of equal flow.”
70
Maximum water-soluble chloride-ion
concentration in concrete for corrosion
Type of concrete
protection of reinforcement
[% by weight of cement]
Pre-stressed concrete 0.06
Reinforced concrete exposed to
0.15
chloride in service
Reinforced concrete that will be dry
1.0
or protected from moisture in service
Other 0.3
Curing water is the amount of total water added, which is required for
the full hydration process of cement. A theoretical value of the amount
of water is in the range of a maximum w/c ratio of 0.24. This minimal
amount of water however does not provide satisfactory workability
required for placing. In order to fulfill all requirements, w/c ratios of 0.4
to 0.5 are commonly used. Evaporation of water, especially from the
surface, should be avoided as it leads to insufficient hydration, result-
ing in higher water penetration and lower durability.
71
blood and pig fat, in order to make it more moldable. The results must
have been good, as their constructions are still standing.
Concrete admixtures are older than Portland cement, but it is only dur-
ing the last 30 years that more stringent requirements for higher quality
concrete production have speeded up the development, research and
utilization of admixing materials. Engineered polymer design and new
insights from nanotechnology have brought about several innovations
in high performance concrete admixtures, such as high-range water
reducers / super-plasticizers, viscosity modifying agents and hardening
accelerators used in normal concrete applications.
72
Stiff concrete, consistency class S1 (left); Fluid concrete, consistency
class S5 / S6 and SCC (right)
The wet-mix method (see also Chapter 4.1) is attractive as the concrete is
mixed and water is added under controlled and reproducible conditions,
for instance at a concrete plant. The w/c ratio, one of the fundamental
factors in concrete technology, can be kept under control. One often
forgets, however, that the equipment makes heavy demands on the fresh
concrete, first of all in terms of pumpability. Furthermore, the method
requires a larger amount of fast-setting admixing materials, which may
lead to loss of strength in the final product.
Admixtures are added at the batching plant either after or together with
the mixing water. The mode of action in the concrete mix varies based
on the chemistry and the interaction with the concrete components, first
of all with the cement. Since admixtures are manufactured in a chemical
plant under controlled conditions and a restrictive quality control system,
they usually show a consistent performance under similar and controlled
conditions. Varying conditions affecting the concrete components may
influence their interaction with the admixture in use.
73
industry has developed tools for any specific requirement during recent
decades. Not only performance characteristics but also the safety of
advanced admixtures have been improved.
3.5.2. Plasticizers/superplasticizers
74
0.7
High cement content,
plenty of water
0.6
Plasticizers
0.5
W/C Ratio Superplasticizers
0.4
“Hyperplasticizers”
0.3
0.2
0.1
0
1940’s 1950’s 1960’s 1970’s 1980’s 1990’s Now
As shown in Figure 3-11, during the last few decades there have been sig-
nificant developments in water-reducing admixture technologies and an
increasing awareness of the importance of strict water-binder control.
< L
ow-Range Water Reducers (LRWR) for plasticizers, e.g. based on
lignosulphonate, a by-product from paper manufacturing. Since
lignosulfonate plasticizers display a certain retardation effect, they
may therefore be recommended in hot climate conditions rather than
for cold weather applications and/or high early strength development
requirements. Remember: retarders work against accelerators!
< M
id-Range Water Reducers (MRWR) for superplasticizers, e.g.
75
50
40
30
% WR
20
10
0
LRWR MRWR HRWR
WR Admixture Class
Water
Water reductionby
reduction by Technology
technology
5050
Water reduction %
4040
Waterreduction %
3030
2020
1010
00
LS BNS
BNS MFS
MFS PCE
PCE
WR
WRTechnology
Technology
76
24h Compressive Strength [MPa]
3535 T
W/C 0.5
W/C 0.4
77
into the market. MasterGlenium® is the reference brand for this class
of superplasticizers. It has the capability to provide a very high water
reduction and excellent workability retention, without the usual unwanted
set-retarding side effect.
78
Figure 3-15: Schematic explanation of the conventional dispersing
mechanism and the more recent developments in additional steric
effects
79
This test been carried out with concrete using the same workability
(slump or spread table)
Water reduction
achieved W/C
80
3.5.3. Hydration Control Admixture
Sprayed concrete mixes, wet or dry mixes, only have a useful ‘pot-
life’ of 3 hours maximum or even less at temperatures above +20°C.
Material sprayed after this time will exhibit lower strengths and increased
rebound, due to the commencement of hydration of the cement.
Long trucking distances from the batching plant to the site, delays in
construction schedules as well as plant and equipment breakdowns
ensure that much of the concrete actually sprayed is beyond its potlife.
In addition to this, environmental regulations may well impose restrictions
upon the working hours of batching plants in urban areas, meaning that a
contractor who requires sprayed concrete mixes to be supplied 24 hours
a day may only be able to obtain material for 12 hours each day. Problems
such as these create unnecessary additional construction costs for both
the contractor and the client.
81
dry, to be extended for periods of up to 12 hours. This eliminates many of
the problems associated with the production and application of consist-
ent, high-quality sprayed concrete mixes encountered by contractors,
concrete producers and engineers.
60
50
40
Flow [cm]
30
20
10
0
0 30 60 90 120 150 180 210 240 270 300 330 360 480
Time [minutes]
Plain
Retarder
MasterRoc HCA
82
45
35
30
25
20
0.25 0.5 1 2 4 8 16 32 64 128
Time [hours]
No Chemical Admixture
0.50% MasterRoc HCA
1.00% MasterRoc HCA
< H
igher flexibility for long distance or in high traffic areas or during
work breakdowns at site.
< Less returned concrete (waste), transport and disposal.
< Less cleaning of trucks and disposal of wash water, which can be
reused.
< Reuse of return concrete.
< Improved acceleration performance.
< Up to 10 % less rebound due to the resulting ‘soft surface’.
< Lower cost.
83
MasterRoc HCA is an economical and efficient tool for sprayed concrete
applications, especially for large underground projects.
84
The correct use can provide the sprayed concrete with the following
properties:
< B
etter pumpability (lubricates and prevents bleeding and segrega-
tion).
< R educed wear on pumping equipment and hoses.
85
The use of curing agents involves several requirements, as listed below:
< T
hey shall be solvent-free (for use in confined spaces).
< T
hey shall not negatively influence the bond between sprayed con-
crete layers.
< T
hey shall be applied immediately after placing sprayed concrete.
< T
hey shall be non-flammable.
When treating sprayed concrete with a curing agent, great care must
be taken in cleaning the substrate properly before applying a subse-
quent layer of concrete. Cleaning can be done by passing air and water
through the sprayed concrete equipment nozzle.
Very good outcomes have been achieved with the use of a special
curing agent for sprayed concrete (MasterKure® 112). This product
is solvent free and easy to apply and remove. It is used on many big
projects and in different countries, everywhere with very good results.
The use of specially designed curing agents for sprayed concrete
improves bonding by 30 to 40 % compared to no curing (air curing); it
reduces shrinkage and cracking and also gives a slightly higher density
86
and compressive strength (at 28 days). These results are confirmed
by several laboratory tests and field trials. Even with easy-to-apply
products, curing of sprayed concrete remains a time-consuming job
and is often seen as a hindrance to other tunneling operations.
For many years BASF has been providing the market with an excel-
lent concrete improving admixture, which acts as an internal curing
agent: MasterRoc TCC 735. This product is added to the concrete at
the batching plant and displays similar performances to conventional
curing methods. The benefits resulting from this new technology are
impressive:
< T he time-consuming application and, in the instance of various
87
Bond strength Water Absorption Compressive strength
Cracks
at 28 d [MPa] at 7 d [g/cm2] increase [%]
Uncured 1.02 IF 0.7 - Yes
External
1.5 IF 0.69 > 10 Yes
curing
MasterRoc
2.28 C 0.37 > 10 No
TCC 735
Key: IF: failure within interface (IF) between layers / C: failure within concrete
Curing Method
Type of cost Water curing External curing Internal curing
Material - 14 15
Application
25.2 1 -
(man hours)
Application
280 18 -
(machine)
Removal
- 10.8 -
(man hours)
Removal
- 80 -
(machine)
Total costs
305.20 123.8 15
per m 3 (CHF)
Table 3-13: Cost comparison per m3 (in CHF) of internal curing, external
curing and water curing from a jobsite with more than 200,000 m3 of
wet HPS sprayed concrete
88
3.5.6. Air Entraining Admixtures (AEA)
3.5.7. Accelerators
89
40
20
10
Time
Hardering Accelerator
Set Accelerator
Reference
90
a water soluble chemical providing limited acceleration performance.
Nevertheless, due to its low price, it was used in large volumes most
countries of the world. Silicates cannot be applied at low temperatures
(< 5°C). Setting and strength development is relatively slow compared
to other technologies. After several years, concrete containing silicates
showed serious damage caused by severe leaching of water-soluble
portions of the concrete created by the accelerator. The consequences
were water leaks and, in many cases, blockage of drainages, followed
by costly renovations. The degradation of sprayed concrete led to a very
significant deterioration of the concrete’s properties. Strength losses of
up to 50 % were observed after some time. In addition, due to their high
alkalinity (pH 10 – 11), silicate-based accelerators carry a risk of skin
and eye burns to underground personnel. The application of sprayed
concrete using sodium silicate accelerators causes high rebound rates
and very high dust levels.
3.5.7.2. Aluminates
Due to their high alkalinity (pH 14), the risk of skin and eye burn with
aluminates became so severe that several countries banned the alumi-
nates even as far back as the early nineties. All these findings led finally
to the development of a new class of accelerators (AFAs) in the early
nineties. Similar to the use of sodium silicate, the application of sprayed
concrete using aluminate based accelerators causes high rebound
rates and very high dust levels.
91
3.5.7.3. Alkali-free accelerators (AFA)
In the early 90s, BASF (former MBT) decided to develop new technolo-
gies fulfilling both requirements (very low alkali contents and low alkalin-
ity expressed as low pH). The first generation of AFAs did not exhibit very
impressive performances in terms of setting and early and final strength.
Today, there is a range of products that fulfills almost any requirements.
Figure 3-21 shows sodium equivalents of alkali-free accelerators com-
pared to conventional technologies.
25 25
Sodium Equivalent Na2O [%]
20 20
Sodium Equivalent, Na2 O [%]
15 15
10 10
5 5
0 0
Silicate Aluminate Alkalifree
Silicate Aluminate
Accelerator Technology
Alkalifree
Accelerator Technology
92
Initial Final
Approx. Approx. Typical
Accelerator Set 2) Set 2) Rebound
pH value Na2O dosage Dust Durability
type CEM I CEM I (wet-mix)
[-] [%] [% bwc]
52.5 52.5
poor; risk
Silicates 11 - 13 > 10 .- 30’ 8 - 15 high high
of ASR
moderate
Aluminates 13 - 14 ≤ 20 60 - 90’’ 3 - 4’ 3-6 high high / poor; risk
of ASR
Low rebound is not only dependent on mix design and application com-
petence, but also on accelerator technology. Fast setting and hardening
creates a relatively hard surface, whereas slower hardening at the very
early stage leads to a softer surface able to absorb some of the spraying
energy. Lower rebound is the result, which is very favorable for several
reasons.
Setting
93
3. Weigh MasterGlenium® T801 or similar superplasticizer (project related).
4. Weigh 300 g cement (+20°C ±1°C).
5. Mix very intensively for 2 mins until a homogeneous paste is
obtained.
6. Add 3–10 g of accelerator (project related) and mix for max 5 s.
7. Immediately after mixing: fill a test cup, place it under the manual
Vicat needle and start measuring the penetration.
8. Record initial set (needle stops 1–2 mm from the bottom of the
cement paste).
9. Record final set (needle cannot penetrate into the cement paste).
The tables below show typical setting results of CEM I or CEM II using
an alkali-free accelerator (see also Figure 3-24).
94
9. Fill the prism form on a vibration table for 30 s to avoid bad compac
tion.
10. Place it under the manual Vicat needle and start measuring the pen-
etration.
11. Record initial set (needle stops 1–2 mm from the bottom of the
cement mortar).
12. Record final set (needle cannot penetrate into the cement mortar).
13. Measure the compressive strength at 6 hours and at 24 hours.
For a fair evaluation of setting times, among other factors, cement type
plays a crucial role. Figure 3-22 below shows setting performances of
a Portland (CEM I) versus a Portland Slag cement (CEM II). The values
shown are measured averages from a number of different cements,
accelerated with various alkali-free accelerators. As the graph shows,
the results can vary within a relatively large range.
95
50
30
20
10
0
Initial Setting Final Setting
CEM I
CEM II
Figure 3-22: Setting times of selected cement types (CEM I and CEM II)
In addition to the cement type, the strength class (fineness) plays a very
important role as shown in Figure 3-23 below.
96
Typical setting of different cement types
400
400
200
200 initial s etting
final s etting
100
100
00
C E MCEM
I 5 2 . 5I 52.5 C E M II 42.5 CEM II 42.5
Initial setting
Final setting
97
25
25 Final Set
Initial/Final Set [min]
16
12
Initial Set
8
W/C= 0.45 Dosage at Site
4
0
4 6 8 10 12
Accelerator Dosage [%]
98
Typical average Strength Development of
Set Accelerator Technologies
40
Compressive Strength [MPa]
30
20
10
0
Aluminate Silicate AFA
1h
6 hrs
24 hrs
7 days
99
Compressive Strength [MPa]
60
50
40
30
20
10
0
3 24 28 d 90 d 360 d
Time [days]
Silicate
Aluminate
AFA
100
Compressive Strength of Sprayed Concrete
50
MasterRoc SA Product A
20
Compressive strength (N/mm2)
MasterRoc SA Product B
15,0
MasterRoc SA Product C
10
MasterRoc SA Product D
5 5,0
2 2,0
1.0 J3
0,5
0.5
J2
0,2
0.2
J1
0,1
0.1
2 6 10 30 1 2 3 6 9 12 24
Minute Hour
Dosing
Dosing of accelerators has to be adjusted to performance requirements.
Normally, very high dosages provide faster setting and higher early
strength, but often lower final strength. Overdosing has to be avoided,
because it carries the risk of fast setting followed by a dormant period
and, even worse, by no hardening of the concrete at all. According to the
author’s experience in the field, the same happens when the content of
gypsum in the cement is lower than 1.8 %.
101
considered. At hot temperatures cooling may be required, whereas at
low temperatures (less than 5 °C) the hydration process is significantly
delayed. Performance development may not be sufficient.
Alkalinity and alkali content are two independent properties. For sprayed
concrete accelerators, however, the term alkali-free should have only
one meaning: the set accelerator contains less than 1% by weight of
Na2O equivalent, which represents only sodium and potassium content
as described in DIN EN 480-1 2. Lithium does not seem to have a nega-
tive effect and it is therefore ignored.
The reason to aim for this is that this will reduce the risk of alkali cations
reacting with sensitive minerals (dissolvable silica, SiO2) that are some-
times in the concrete aggregates. If such a reaction takes place, aggre-
gate grains will fracture due to expansion. This may have a detrimental
effect on the sprayed concrete matrix.
102
strong acids (pH value 0–2). This can be expressed as acidic, aggres-
sive or corrosive. One can also distinguish between corrosive to metal
and corrosive to human skin and eyes. The background for the impor-
tance of this property is working safety and the working environment.
High alkali contents, however, can have a negative impact on alkali-
sensitive aggregates (see Chapter 3.2).
pH Scale
0 4 7 10 14
Safe to human body
Aggressive to Aggressive to
concrete and steel aluminium
Alkali-free Conventional
accelerators accelerators
Modified sodium
silicate accelerators
Speed of setting and rapid early strength development are the two most
crucial requirements for sprayed concrete in tunneling and mining con-
struction; these are mainly achieved by using set accelerators. Recent
studies and investigations have focused on the chemical interaction and
mechanisms between set accelerators and cements relating to kinetics,
thermodynamics and microstructure development (see [13] to [23]).
103
There are two main types of set accelerator, namely alkaline set accel-
erators (see [14] to [16]) and alkali-free set accelerators (see [16] to [23]).
The active agent of the alkali-free accelerator shows a high reactivity
when mixed with cement. When the alkali-free set accelerator is added
to the concrete mix, it reacts immediately with cement to form a variety
of hydration products. Ettringite, one of the first hydration products,
which consumes an increased amount of water, is responsible for the
rapid setting and fast strength development of sprayed concrete (see
[13], [16] to [23]).
Due to the high cost and demanding conditions of time, space and
effort necessary for full-scale trials to test sprayed concrete, the setting
properties of cements in combination with appropriate admixtures (e.g.
accelerators, plasticizers and retarders) are typically first tested in the
laboratory in the form of cement paste or as components of a standard
mortar.
The main goal of such laboratory tests is the identification of the cor-
rect proportion of admixtures to be used in combination with a specific
cement to obtain the desired properties of setting and compressive
strength development, typically with the additional constraint of cost
optimization. Such desired properties are usually defined by an appro-
priate standardized specification, depending on the specific application
intended for the sprayed concrete.
104
3.6.1.1. Standard materials preparation for laboratory scale testing
3.6.1.1.1. Mortar
Figure 3-29: Mold used to produce standard mortar prisms for physical
testing
105
Figure 3-30: Mortar prism sample obtained from the mold
106
Initial and final setting times are measured using a Vicat needle consist-
ing of a cylinder weighing 300 ± 1g and a needle point with a diameter
of 1.13 ± 0.05 mm. The initial setting time is defined as the time at which
a paste or mortar deposited in the mold begins to oppose resistance to
penetration by the Vicat needle. In practice, the Vicat needle is allowed
to fall by gravity after being placed as near as possible to the upper part
of the material; only when the needle does not touch the bottom of the
mold due to the resistance of the material has the setting started. Due
to the poor homogeneity of the materials under investigation, especially
when using fast setting admixtures, the test is repeated four times, and
initial setting is said to have taken place only when at least three out of
four trials are positive.
Final setting, on the other hand, is defined as having taken place when
the Vicat needle, in contact with the upper side of the material, is not
breaking its structure but only leaves the print of the pressure of the
point of the needle. It is clear that while this is a qualitative definition
of the setting of cement or mortar, indicating the beginning of a phase
transition (and therefore the moment when cement will not drip from
a vertical or even a perpendicular surface), the quantitative definitions
of initial and final setting times depend fully on the instrument used (its
weight and the diameter of the needle).
Figure 3-31: Initial setting (on the left) and final setting (on the right),
measured with the Vicat needle
107
3.6.1.2.3. Compressive strength
Initial and final setting times, along with compressive strengths at 6h, 1
day, 7 days and 28 days allow the identification of characteristic points
of cement paste or mortar hydration and therefore of their phase transi-
tion. Indeed such values can give information on the quality of cement or
mortar, and its interactions with accelerators. Nonetheless it is possible
and desirable to monitor the state of phase transition of cement in a con-
tinuous manner using automatic computer-interfaced penetrometers
(see Figure 3-33).
Such instruments are not yet commercially available, but constitute the
result of an effort by BASF to improve the quality and speed of materials
testing. The resulting curve expresses the development of resistance
108
to penetration, in Newtons (y-axis), against time (x-axis). The force is
depicted as the average value from the four needles. The two curves
refer to two different set accelerators (see Figure 3-34). These curves
can be correlated to the development of strength of the material. Such
measurements can be performed at different penetration speeds for
a maximum of 36 hours, and are especially suitable for mortar testing
where accelerating admixtures are present.
109
GP Cement W/C 0.45
2500
Averange Force [Newton]
2000
1500
1000
Set accelerator A (7%)
500
0
0 5 10 15 20 25
Time [min]
110
Portland cement + MasterRoc SA X180/L, w/c = 0.5
Figure 3-35: Rate of heat evolution for given Portland cement with and
without set accelerator (on the left)
111
3.6.2. Full-scale testing of sprayed concrete
in controlled conditions
112
Figure 3-37: Spraying tests laboratory with model section of tunnel and
concrete spraying and mixing machines
113
Such assessment is performed using different tools, according to the
stage of setting/hardening reached by the material. Current tests are
based on needle penetration or nail extraction. In the first range from 0 to
1 MPa equivalent a MEYCO penetrometer may be used, which consists
of a cylinder containing a piston and calibrated spring, and ending with
a needle (see Figure 3-38). The compression of the spring after insertion
of the ring can be measured, indicating the resistance to penetration.
See also Chapter 8 for more information. More sophisticated devices
can be used which are based on a similar principle, but which transfer
the values of resistance to penetration electronically to a computer.
Hilti guns are then used to insert needles, the resistance of which to
extraction will provide a value for the hardening reached by the sprayed
concrete (see Figure 3-39). The MPa equivalent resistance values are
inserted in a table against the time, and provide curves that represent
the setting and hardening characteristics of sprayed concrete.
Figure 3-38: Use of MEYCO penetrometer (on the left) and more
sophisticated equipment (on the right) to assess setting and hardening
of sprayed concrete (measurement of very early strength up to 1 MPa)
114
Figure 3-39: Use of Hilti guns to assess setting and hardening of
sprayed concrete (measurement of early strengths greater than 2 MPa)
115
acting on the concrete lining. As a structural material in sprayed con-
crete, reinforcement is designed using the same criteria that apply to
conventional concrete. It is generally in the form of mesh and it is recom-
mended for thick layers (≥ 50 mm). Usually, a reinforcing mesh of 50 to
150 mm with a wire diameter of no more than 10 mm is widely accepted.
Reinforcing bars are seldom used in sprayed concrete sections with a
thickness of less than 40 mm.
Small reinforcing bars combined with mesh are used in zones where
mesh alone would not be structurally sufficient for the application, e.g.
in curved and irregular surfaces, where uniform spacing and cover are
critical. The number of layers of mesh required for thicker sections can
be reduced by a suitably designed combination of bars and mesh.
The use of lattice girders (arches) allows the control of the excavation
profile. They also provide support for spiling (if required), ensure correct
positioning and properly secure the mesh reinforcement before the
sprayed concrete is applied, additionally providing an initial safeguard
against rock falling out of the crown. Lattice girders are available in
high yield steel, in preformed configurations of three or four main bars.
Separation of the lattice girder in pieces is necessary to suit the differ-
ent stages of excavation and support. The pieces are bolted together
or lapped to form the whole arch after complete excavation. Design
requirements will determine whether installation of a continuous lattice
arch covering the whole excavation section is required.
116
reinforcement should be according to the job specification or applicable
building codes, taking into account environmental influences.
Fibers in the concrete mix at normal addition rates can improve flexural
and shear toughness, and resistance to impact. Stainless steel fib-
ers increase thermal shock resistance and resistance to temperature
cycling damage and crack development in sprayed concrete. The sus-
ceptibility of sprayed concrete to plastic shrinkage cracking can be
reduced by the addition of synthetic fibers.
117
consequence, performance will be lost over time. Carbon fibers are not
used mainly due to their high cost. As the most commonly used types
of fibers are steel and synthetic polymer fibers, only these types are
considered here.
Figure 3-40: Different fiber types. On the left, steel fibers are shown. On
the center and right, synthetic fibers are shown.
According to ACI 506.1R-08 [31] fibers for use in sprayed concrete are
usually divided into two groups according to their diameter. Fibers with
equivalent diameters greater than 0.3 mm are classified as macrofibers,
while fibers with diameters of less than or equal to 0.3 mm are known as
microfibers. The fineness of microfibers is described by the unit denier.
Typical synthetic fibers used in sprayed concrete have a denier of 6,
which corresponds to an equivalent diameter of 32 μm (0.0032 mm).
1 See Sprayed Concrete ACI Committee 506, Guide to Fiber-Reinforced Shotcrete ACI
506.1R-08, 2008, Page 2f
118
Macrofibers can be characterized by their aspect ratio (the ratio of
length to diameter of a fiber). Typical aspect ratios of macrofibers for
sprayed concrete vary from 40 to 65 for common fiber lengths (19 to 50
mm). Most of the macrofibers used in sprayed concrete are either steel
or synthetic fibers. Steel fibers are generally between 19 to 35 mm in
length and have an equivalent diameter between 0.4 and 0.8 mm. The
length of synthetic macrofibers can vary from between 40 to 50 mm and
their equivalent diameters are similar to those of steel fibers.
Classification of Fibers
EN 14889
119
load-bearing capacity of a concrete structure. According to EN 14889,
fibers are classified as shown in Figure 3-41.
Steel fibers are currently the most commonly used fibers in sprayed con-
crete. They present clear advantages over mesh as reinforcing agents,
mainly because they are small and evenly distributed through the entire
concrete layer. Steel fiber reinforced concrete is thus a viscous material
offering improved distribution of cracks and tension.
The main reason for using steel fibers in sprayed concrete is to increase
the ductility of the material. Whereas high flexural strength can be pro-
duced without fibers, ductility is a function of the type and amount of
steel fibers. Long fibers (> 25 mm) and relatively high dosages (40–75
kg/m3) are preferable.
120
Figure 3-42: Example of steel fibers (length 30 mm) as used for rein-
forcement of sprayed concrete linings
of crack propagation.
< Increased bonding capacity compared to plain or mesh reinforced
sprayed concrete.
There are several types and qualities of steel fibers available on the mar-
ket, but only a few types meet the requirements set for fiber-reinforced
sprayed concrete. Critical and important parameters relating to steel
fibers are:
< Geometry of the fiber.
121
In practice, a thin and long fiber with high steel quality (the same or
higher than ordinary reinforcement) is required. The length of steel fib-
ers shall not exceed 2/3 of the internal diameter of the pipes or hoses
used unless a test has demonstrated that longer fibers can be sprayed
without blockage. Typical steel fibers that can meet the requirements
for steel fiber reinforced sprayed concrete are Dramix 30/50 and 40/50
as well as Novotex 0730 (0.7 x 30 mm).
Rock support includes the constant risk of unexpected loads and defor-
mation. The best possible safety margin is achieved by the highest pos-
sible fracture energy (ductility) of the sprayed concrete layer.
P
Load P
Unreinforced
Deformation
Whereas the addition of ordinary steel fibers doubles the fracture ener-
gy of unreinforced sprayed concrete, modern steel fiber technology
improves it by 50 to 200 times. In practical terms, this means that with
modern steel fiber technology a sprayed concrete layer may crack and
deform and still have a lot of bearing capacity left, so that under normal
122
circumstances there is ample time available to notice cracks/deforma-
tions and to take appropriate construction measures.
The fracture energy of steel fibers is also higher than that of wire mesh.
This has been proven by a large scale test run at the beginning of the
1980s by the independent Norwegian Technical Research Association
(NTNF), see Figure 3-44 .
300
250
Mesh failure
200
* Flexural fraction
Load P [kN]
* Bond break
150
100
*
50
0
0 5 10 15 20 25 30 35 40 45 50 mm
Deformation [mm]
Steel fibers
wire mesh
Figure 3-44: Comparison of the fracture energy of steel fibers and wire mesh
P
Granite stone block Granite stone block
10 cm 10 cm
123
concrete layer with centric applied wire mesh (continuous line). Both
types of reinforced sprayed concrete layers were applied on three gran-
ite stone blocks (see Figure 3-45). After 28 days the middle block was
exposed to various loads (P). The resulting deformation was measured.
The test shows that the fracture energy of the steel fiber reinforced
sprayed concrete is much higher than that of traditional wire mesh rein-
forced sprayed concrete.
The danger arising from the uncertainty about the wire mesh qual-
ity actually used and the problem of the shadow effect can be easily
avoided by using steel fiber reinforcement, which lends itself very well
to wet-mix sprayed concrete, and at a lower cost, too. In rock support,
where one always has to allow for deformation, this feature is a very
strong asset of the wet-mix method.
ers made necessary by the use of wire mesh can be avoided, and no
delay is caused to other tunneling operations.
124
< S
avings on sprayed concrete used: with steel fibers the required
thickness of sprayed concrete can be applied over the whole sur-
face, independent of the irregularity of the substrate. The increased
rebound caused by wire mesh and the effect of shadows behind the
mesh are avoided.
Steel fibers require the knowledge and skill of practical mix design:
< F iber-reinforced sprayed concrete requires the use of microsilica and
The main benefit of steel fibers for durability over mesh reinforced
concrete is that, in severe environments, steel fibers will not support
the common galvanic corrosion cells which often lead to considerable
125
damage to conventionally reinforced tunnel linings. The risk of concrete
spalling due to corrosion is eliminated as the increase in volume caused
by the corroded fiber is insufficient. Additionally, fibers (which are dis-
crete) are protected by the alkalinity of cement. There is, therefore, no
mechanism for the propagation of corrosion activity, as reviewed by
numerous case histories and research studies of structures exposed to
highly saline and freeze-thaw environments. It is therefore unnecessary
to opt for stainless steel fibers to achieve durability.
Plain steel fibers exposed at the concrete surface will tend to leave rust
spots. Therefore, for cosmetic and safety reasons, it is recommended
that permanent steel fiber reinforced sprayed concrete linings are pro-
tected by a thin finishing mortar layer containing the new Enduro /
MasterFiber ® SP 540 polymer fibers for thermal cracking control.
Normal short polymer fibers are resistant and durable in the concrete
environment. For applications where only reinforcement against shrink-
age, and in particular plastic shrinkage, is asked for, as in sprayed
concrete repair, polymer fibers are well suited. They are very efficient at
distributing micro-cracks during the plastic phase of hardening and they
also help to reduce rebound in wet-mix spraying. In addition, polymer
fibers have a positive influence in fire scenarios as they reduce concrete
spalling.
Recently, a new type of polymer fiber has been developed. These struc-
tural polymer fibers (SP fibers) are more similar to steel fibers in terms
of shape and length. They are produced from high quality materials and
typically delivered in lengths of 30 to 50 mm. Many test results and appli-
cations in Australia, Canada, South Africa, Norway and other European
countries have shown that this type of fiber can reach adequate tough-
ness if dosed in the range of 5 to 10 kg/m3. Tests with this dosage
range show that SP fibers can reach approximately 900 to 1,200 Joules
according to the EFNARC panel test (600 mm square and 100 mm thick
panel). Here, energy absorbed in Joules up to a deflection of 25 mm is
the standard performance criteria used. This result is more or less equal
to the result achieved with 30 to 40 kg/m3 of high quality steel fibers.
126
These new SP fibers are already widely used in the mining industry
around the world and are now increasingly utilized in sprayed con-
crete linings in tunneling. BASF promotes its fibers under the names of
MasterFiber SP 530 / SP 540 / SP 550 (fiber lengths 30 mm, 40 mm, and
50 mm, respectively) and MasterFiber SP 640 / SP 650 / SP 665 (fiber
lengths 40 mm, 50 mm, and 65 mm, respectively).
The results from a comparison EFNARC panel test made with Novotex
0730 steel fibers (dosage 65 kg/m3) and MasterFiber SP 550 fibers
(dosage 9 kg/m3) are shown in the following Table 3-17. Identical mix
design, w/c ratio, spraying equipment, nozzleman and accelerator type
were used for all three mixes (Mix 1 using setting accelerator MasterRoc
SA 160, Mixes 2 and 3 using setting accelerator MasterRoc SA 170). All
panels were stored under identical curing conditions.
127
Energy
Mean absorption
Peak load
Mixes Panel no. thickness at
(N)
(mm) deflection
of 25 mm (J)
Mix 1: 1 99 65 927 1 068
MasterFiber SP 550
2 98 70 229 1 095
(9 kg / m3)
Mean
MasterRoc SA 160 . 68 078 1 082
value
Mix 2: 1 99 66 333 1 149
MasterFiber SP 550
2 100 78 282 1 315
(9 kg / m3)
Mean
MasterRoc SA 170 . 72 308 1 232
value
Mix 3: 1 102 94 560 1 459
Novotex 0730 steel fibres
2 101 92 341 1 522
(65 kg / m3)
Mean
MasterRoc SA 170 . 93 451 1 491
value
Table 3-17: Results from a comparison panel test (EFNARC) made with
Novotex 0730 steel fibers (dosage 65 kg/m3) and MasterFiber SP 550
fibers (dosage 9 kg/m3)
The Round Determinate Panel (RDP) test was introduced in 2001. Here,
the calculated energy absorption at a deflection of 40 mm is reported as
the standard assessment. As reported in [54], RDP and EFNARC panel
test results are usually compared at a set deflection (40 mm and 25 mm
respectively). While two fibers may have equal performance at these
deflections, they may differ significantly at lower or higher deflections.
Usually SP fibers work well at higher deflections, while steel fibers work
better at lower deflections (see Figure 3-47).
128
Approximately
equal
1400 15kg/m3 cost/m3
structural
synthetic fiber
1200
60kg/m3 high
performance
1000 steel fiber
800
600
400
200
0
0 10 20 30 40 50 60 70 80
Low deflection Medium deflection High deflection
< L ower wear and tear on spraying parts (wear plate, pump cylinders,
The most common argument against the use of SP fibers in civil tun-
nel linings is concern about the magnitude of creep-related deflections
129
likely to occur in the long term under gravity loading. The creep behavior
of SP fibers and of steel fibers (steel fibers are also subject to creeping!)
has been studied by Dr Stefan Bernhard in a long-term investigation
program. The test is described in his paper [47], where he concludes
that:
“SP fibres are designed and have been shown to provide similar resist-
ance to load deformation as steel fibres. Creep only becomes an issue
if and when the sprayed concrete cracks. If a crack develops in steel
fibre reinforced concrete, it creates the opportunity for corrosion and
loss of performance in ductility. If the load continues, the load energy
will continue to be absorbed, but there is a risk of sudden rupture. If a
crack develops in SP fibre reinforced concrete there is no corrosion risk.
If the load continues, the fibres will stretch rather than suddenly fail, and
in doing so will continue to absorb the load energy. The cracked sprayed
concrete can be observed and action taken to remedy the cause of the
problem before this capability is exhausted”.
In the following Table 3-18 the results from a comparison test made
with Enduro SP fibers in three different dosages (5, 7, and 9 kg/m3) is
presented. Identical mix design, accelerator (MasterRoc® SA 162) and
spraying equipment (manipulator) were used for all three mixes. The
toughness test was performed according to the EFNARC panel test.
Table 3-18: Results from a comparison test made with Enduro SP fibers
in three different dosages. Toughness test performed according to the
EFNARC panel test.
130
A combination of normal/short (fibrin) polymer fibers with the new SP
fibers is probably the ideal reinforcement for sprayed concrete in terms
of mechanical performance (reduction of plastic shrinkage, improved
bond, reduced spalling during a fire, improved ductility/load bear-
ing capacity) and economical advantages (less cost per m3 applied,
improved durability).
In many cases, fibers are specified to reduce the amount and spacing
of bar reinforcement or to avoid its use completely. The latter requires
specification of construction joints in the design, since the overlapping
of fibers is not possible at construction joints (e.g. between crown,
bench and invert), and conventional reinforcement, mostly by means
of welded wire meshes, has to be installed additionally.2
2 See EFNARC European Specification for sprayed concrete, Guidelines for specifiers and
contractors, 1999, Page 9
131
since fibers differ in material, length and shape. These should be rec-
ommended by the suppliers of fibers and then confirmed by trial tests.
The quantity of fibers rebounding, and hence the final amount of fibers
in the sprayed concrete, is affected by changes in the quality of the
fresh concrete. For the same post-crack performance, fiber dosages
in the wet-mix process are sometimes lower than in the dry-mix proc-
ess, because the rebound of macrofibers in wet-mix sprayed concrete
is typically less than for dry-mix sprayed concrete.
132
4. SPRAYED CONCRETE
METHODS
The dry-mix method was the established method for constructing
sprayed concrete linings until the mid 1990s, when the wet-mix method
began to be used more widely. Due to the benefits of the wet-mix method,
many contractors who were involved in underground or ground-support
projects with large volumes of sprayed concrete made the change from
dry-mix to wet-mix spraying.
Austria and Germany were traditionally very strong dry-mix areas. The
dry-mix technology was widely used and significantly developed in these
countries. New systems within the dry-mix method were developed,
using extremely fast-setting cement types (without gypsum). However,
these countries have also changed to the wet-mix method. Many large-
scale projects have been completed successfully with this method.
The first large-scale projects using wet-mix sprayed concrete were
133
Königshainer Berge, Ditschhardt Tunnel, TLM (Irlahüll, Schellenberg,
Euerwang), a part of the Highspeed Railway Link Nuremberg–Ingolstadt
(650,000 m3), Sieberg Tunnel and Blisadona Tunnel, both in Austria. In
these countries, the shift from dry-mix to wet-mix spraying took longer
than in Switzerland, where it happened in less than two years.
The following sections briefly describe the wet-mix and the dry-mix
methods.
In the early days, wet spraying had a bad reputation: because of poor
equipment and little knowledge of the method., concrete of very poor
quality was produced. In order to allow the mix to pass through the
equipment, very high water contents were used, with w/c ratios of up
to 1.0.
134
4.1.1. Description
m
5
)
m
1,
-2
(1
Liquid Wet
accelerator mix
Concrete,
dense stream
Liquid accelerator
Dosing pump
Compressed air
At the nozzle, located at the end of the hose, air is added to the con-
crete mix flow at a rate of 7 to 12 m3/minute and at a pressure of 7 bar,
depending on whether the spraying is performed manually or by a
robotic manipulator. The air is added to increase the speed of the con-
crete mix flow so that good compaction and adherence to the substrate
or surface are achieved. The velocity of a wet-mix concrete stream out of
135
a standard MEYCO nozzle, measured with an output of 12 m3/h, varies
from 30 to 50 m/s. In addition to the air, liquid setting accelerators are
added at the nozzle to provide fast setting of the sprayed concrete (early
strength development) and high-build characteristics.
A mistake often made with the wet spraying method is that not enough
air is added to the concrete mix. Air is frequently added at a rate of less
than 7 m3/minute, which gives bad results for compressive strength,
adherence and rebound. For manipulator spraying, addition of air at
rates of up to 12 m3/ minute is necessary.
Spraying under severe rock conditions was one of the aspects that
brought about the development of the wet-mix method. The safety risk
was often unacceptable without a spraying manipulator and the use of
steel-fiber reinforcement. This topic is covered in Chapter 10.3.
4.1.4. Quality
136
Since the concrete is prepared in the same way as for normal concrete,
it is possible to check and control the w/c ratio and thus the quality at any
time. Hence, it is easier to produce sprayed concrete of uniform quality
throughout the spraying process.
The quality range in wet-mix spraying is fairly stable with a low spread of
results. With dry-mix spraying this is more problematic. By using water-
reducing admixtures (low w/c ratio) and microsilica, peak compressive
strengths of wet sprayed concrete can be as high as 100 MPa.
environment.
< It allows the use of steel fibers/structural synthetic fibers and advanced
new admixtures.
< T hicker layers because of effective use of the admixing materials.
< P ractical average long term capacity per spray machine is normally 4
137
< H
ydration control admixtures can extend the working life of wet mix
by up to 12 hours, which gives great flexibility to the system, and
prevents need for cleaning out the system after each application.
< Improved bonding and higher compressive strength (with very lit-
tle variation in results). The final strength requirements for wet-mix
sprayed concrete can be specified in the same way as for conven-
tional concrete.
< M uch larger production and consequently improved overall economy
quality.
< L imited open time/workability (only limited interruption). This can be
admixtures.
< If not site batching, dependence on local batching plants to dose
specific types and volumes and provide higher level of quality control
during batching.
< H igher initial investment for machine.
Due to many years of experience with the dry-mix method, there is now
a great deal of know-how available. It is extremely important that the
materials, equipment and application techniques used are selected to
give the best possible results with regards to quality and economy.
Even though dry spraying is the older of the two spraying technologies, it
has been possible to continually extend the field of application because
of ongoing developments in machine and material technology. In the
future it is expected that the dry spraying process will continue to play an
important role. Main applications will be for projects with relatively small
138
volumes and/or very flexible requirements, such as concrete repair,
which is considered the strongest market for the dry-mix process.
Additionally, long conveying distances suit the dry-mix process and,
consequently, this method remains in use in many mines worldwide.
4.2.1. Description
In the dry mix method, cement and aggregate are batched at a site-
based plant or pre-batched and oven dried into silos or bags, mixed and
fed into a purpose-built machine in which the mixture is pressurized,
metered into a stream of compressed air and transported through
hoses or pipes to a nozzle for application. At the nozzle, mixing water
for hydration is added to the mixture (at the discretion of the nozzleman)
prior to projecting it continuously into place (see Figure 4-2).
139
Dry spray method (typical set up)
(1 5 m
)
m
1,
-2
Dry
mix
Compressed
Air Concrete,
thin stream
Water
Dosing pump
Liquid accelerator
Liquid accelerator
Apart from accelerators, the only other admixtures used in the dry
spraying method are dust binders. These powder admixtures – as
the name implies – reduce dust formation. In practice, however, these
agents have only achieved limited acceptance.
The concrete mix is jetted from the nozzle at high velocity onto the
substrate surface. The velocity of a concrete mix stream, which comes
out of a standard MEYCO nozzle, varies from 70 to 100 m/s (see also
Chapter 8 of this book).
Basically, three different types of dry-mix methods have been used [55]:
140
II. Dry method with quick cement and moist aggregates (method DM):
this method requires in-situ mixing.
III. Dry method with quick cement and oven-dried aggregates (method
DD): dry-mix is delivered to the site in silos.
141
ried out to reduce dust and rebound, however, of course with additional
cost. Many contractors have eliminated this method after their first major
application, while others remain heavily committed. The advantages are
most evident for short tunnels (with lengths limited to 400 m).
The dry-mix method is a simple system, with few mechanical and mix
design issues that can go wrong. This fact has often been the reason for
the selection of the dry-mix process in the past. However, the method
does have some disadvantages. These are summarized as follows:
< T
he relatively high costs due to wear and tear on the rotor machines
(especially on rubber gaskets and friction discs). By correct set-up of
the machines and by changing parts in time (and with skilled grind-
ing), these costs can be kept within reasonable limits.
< T he environmental and safety impact of the high concentrations of
dust generated by the system must be taken into account. This can
be considerably reduced by ensuring a favorable natural moisture
content (or adequate pre-wetting) and by using dust binders. Water
pressure boosting pumps can also help with this issue. These pumps
intensify the water pressure during mixing at the nozzle. Combined
with the use of improved water rings, it is possible to ensure good
and steady wetting of the dry material at the nozzle. Depending on
the system, the hydraulic pressure rises to about 80 bar. Such appli-
ances are expensive and relatively susceptible to breakdown. In our
experience, systems with a pressure of 10 to 15 bar are usually fully
adequate.
< In addition to the formation of dust at the nozzle, attention to the
impact of the dust from the feeding system on the machine is
required. In this respect, traditional double-chamber machines are
advantageous. Rotor machines can, however, be dust-proofed to a
large extent, or even completely, by various means, such as fitting a
rotor dust collector or by continuously lubricating the rubber gaskets
(intermittent lubrication).
< T he relatively high degree of rebound. Depending on the application
142
using new kinds of additives and admixtures. Microsilica or hydration
control systems like MasterRoc HCA have a positive effect. Average
losses can thus be reduced but still remain much higher than with the
wet spraying process.
< T
he low output capacity of the equipment (max. 10 m3 per hour) is
mix spraying because of the resulting high fiber rebound (> 50 %).
143
Disadvantages of the dry-mix method:
< Spraying capacity limited to max. 10 m3/h (practical).
< Demands a higher volume of compressed air (+100 % versus wet mix
method).
< High operating cost per cubic meter sprayed.
placed concrete.
< Use of steel fibers not favorable due to high rebound (> 50 %).
144
5. MIX DESIGN
The mix values shall refer to the concrete after it has been sprayed on
the surface, and must consider the influence of adding water and accel-
erator admixtures during the spraying process, as well as the effect of
rebound during application.
< Adequate concrete cover over reinforcement (not valid for fibers).
145
environmental and working conditions to which it is exposed during its
anticipated service life:
(1) C
hoice of proper constituents, without harmful components, or those
(2) D
esign of a concrete composition that satisfies all specified perform-
ance criteria.
The alkali content of cement and admixtures shall comply with the
requirements of current national standards in the place of use of the
sprayed concrete.
(1) T
he maximum w/c ratio shall be limited to 0.55.
146
(2) The minimum cement content shall be 300 kg/m3.
In all cases, basic data for sprayed concrete shall be indicated and addi-
tional data shall be presented when required.
147
5.3.1. Data for specifying designed mixes
< R esidual strength and/or energy absorption capacity (only for fiber-
< S
pecial requirements for cement properties (e.g. sulfate-resistant
cement).
< Maximum w/c ratio related to exposure classes.
< F
irst-peak flexural strength and ultimate flexural strength (for fiber-
For prescribed sprayed concrete mixes, the basic data shall be specified
according to EN 14487-1:
< C ement type and class.
148
< F
iber
characteristics and fiber content (for fiber-reinforced sprayed
concrete).
< S
pecial requirements regarding the temperature of the basic mix
Running laboratory trials for mixtures is not practical for the dry-mix
method. Repeating as-shot conditions for the wet-mix method is also a
problem. Hence, field trials and pre-construction testing should be used
for qualifying mixture proportions. Guidance for mixture proportioning is
provided by national standards or recommendations.
149
be applied in all cases, because minor variations in one component of
the mix can have a large impact on the mix performance.
5.4.1. Wet-mix
< W /c ratio ideally between 0.4 and 0.45, but below 0.5.
150
Low Flow High Flow
Higher pulsation due to: Lower pulsation due to:
• lower cylinder filling percentage • higher cylinder filling percentage
• less flowability of the sprayed concrete • higher flowability of the sprayed con-
mix crete mix
Quality aspects:
Quality aspects:
• higher uniformity, less layering of
• more layering
sprayed concrete on the wall
• poor and uneven distribution of acceler-
• better distribution of accelerator in the
ator in the concrete due to high viscosity
concrete due to low viscosity concrete
concrete and increased pulsation
and lower pulsation
Environment, health and safety (EHS): Environment, health and safety (EHS):
• increased dust creation during spraying • less dust creation during spraying due to
due to pulsation lower pulsation
• increased risk of blockages due to • reduced risk of blockages due to better
higher pumping pressures flowability of the sprayed concrete mix
Economy: Economy:
• higher rebound • lower rebound
• higher equipment wear and tear • lower equipment wear and tear
Productivity: Productivity:
• lower output due to lower cylinder • higher output due to higher cylinder
filling percentage and higher pumping filling percentage and lower pumping
pressures pressures
• more blockages due to higher pulsation • less blockages due to lower pulsation
and higher pumping pressures and lower pumping pressures
• more cleaning of equipment required • less cleaning of equipment required due
due to stiffening concrete to reduced concrete build-up
For the purposes of durability and pumpability, the w/c ratio of nor-
mal wet-mix sprayed concrete should be lower than 0.5. Where the
wet-mix sprayed concrete will be subjected to freezing and thawing
in saturated conditions, air-entraining admixtures should be added to
the mix. Before pumping, a total air content of 6 % in the mix is usually
desirable (for more details see Chapter 3.5.6). Further guidance on the
proportioning of wet-mix sprayed concrete is also provided in the previ-
ous Chapters 2 and 3.
5.4.2. Dry-mix
151
als are used and adequate proportioning data from previous experi-
ence are provided. This approach is sufficient for many small projects
where preconstruction testing would be too expensive. Preconstruction
tests are required if data from previous experience are not available,
the design criteria is affected by properties other than strength, or if
design requirements are different from one part of the work to another.
Preconstruction testing is also recommended to determine the mix
proportions if gradation or quality of the aggregate and the amount and
spacing of reinforcement may influence the mix design.
Field trials are necessary to define the final cement content of the mix
(see ACI 506.4R for details of the methodology).
Cement content
Water/cement ratio
152
already in the aggregate. Unlike the wet-spraying method, in the dry-
spraying method there is no clear-cut set value for the water/cement
ratio, because the amount of mixing water is controlled and regulated
by the nozzleman. This is frequently considered to be a great disadvan-
tage. In practice, however, the water/cement factor is fairly constant, as
there is a limited scope for varying the mixing water quantity: if too little
water is added, the result is an immediate excess of dust; if too much
water is added, the sprayed concrete does not adhere to the surface
but runs down it instead.
Where work is carried out properly, the w/c ratio varies only slightly and
remains below 0.5. In a best-case scenario (aggregates requiring low
water quantity, sufficient cement content), it is even possible to manu-
facture sprayed concrete with a w/c ratio lower than 0.4.
Admixtures
Apart from accelerators, the only other admixtures used in the dry
spraying method are dust binders. These powder admixtures – as
the name implies – reduce dust formation. In practice, however, these
agents have only achieved limited acceptance.
153
As it is well known from construction technology, accelerating the rate of
cement hydration inevitably results in a reduction in 28-day strengths. In
order to obtain a consistently high quality of sprayed concrete, it is thus
essential to ensure that the lowest possible quantity of accelerator is
added as consistently as possible. The accelerator proportion must be
determined in each case in relation to the amount of cement used.
The best way of ensuring the precise dosage of accelerator during appli-
cation is to use liquid products (such as MasterRoc® AFAs). These are
measured into the mixing water and thus added to the dry material at the
nozzle. To obtain a steady dosage, however, it is essential to use a suit-
able dosing system even with liquid accelerators. Where it is necessary
to pre-mix the water and accelerator, machines are only suitable up to
a point. Since the water/accelerator ratio is fixed, the dosage is altered
in relation to the weight of the cement every time the water addition is
adjusted by the nozzleman. However, it is both necessary and important
to adjust the water quantity, for instance in order to respond to variations
in the natural moisture of the aggregate or in the behavior of the water
flow on the surface.
154
proportion to the capacity of the spraying machine quite independently
of the water flow setting (e.g. MEYCO® Dosa TDC).
Additives
Fibers
155
density tests) and proceeding as described in the following example
from ACI 506R-05:
< Cement: Type I
1,800 kg/m3
If the results of the conformity tests do not comply with the require-
ments, additional testing on cores taken from the sprayed concrete
lining, or a combination of tests on cores and non-destructive tests on
the structure, shall be required.
156
6. BATCHING, MIXING AND
TRANSPORTATION
6.1. Batching
In dry-mix sprayed concrete, the moisture content of the fine and coarse
aggregate should be chosen to allow a uniform rate of the aggregate-
cement mixture without slugging or hose plugging. The most favorable
moisture content generally varies from 3 to 6 % or more if silica fume is
used. The sand should be dried or wetted as required. Large fluctua-
tions in moisture content should be avoided.
6.1.1. Admixtures
157
dered or liquid admixtures can be added at the batching stage. Liquid
accelerators can be added at the nozzle in the air supply by means of
a proportioning device. In this method, quick-set accelerators are only
introduced at the nozzle (see also Chapter 4.1.1). In the dry-mix method,
powdered admixtures are added during the batching or mixing stage,
while liquid admixtures are introduced at the nozzle with the mixing
water (see also Chapter 4.2.1).
6.1.2. Fibers
< S
pecialized ingredients have been specified (more easily controlled
in a bagging facility).
The requirements for mixing equipment and the mixing of sprayed con-
crete fall under the same standards as for normal concrete making.
158
As per EN 206, the measurement of cement, aggregates, water and
silica fume must be within a ± 3 % and ± 5 % accuracy for admixtures
dosed at < 5 % of cement mass. Required accuracy for fiber dosing is
± 5 %. Calibration of scales and flow meters must take place at regular
intervals or before use if any parts of the installations have been disturbed
outside of normal usage.
The production of sprayed concrete mixes does not present too many
challenges for experienced concrete suppliers.
Many types of mixing plants are used for the mixing of sprayed con-
crete, varying from large established ready-mix stations to containerized
mobile plants. The majority of mixing stations use weigh batching sys-
tems, normally with a shaft type or pan type mixer. Volumetric batching
systems with screw type mixers are also used, though in smaller scale
operations. From a quality control and consistency point of view, good
efficient weigh batching systems are the preferred method.
Aggregate storage and handling at the mixing plants must be such that
the risk of cross contamination or inclusion of larger aggregates from
normal concrete production into the sprayed concrete mixes is reduced
to a minimum. Large oversized aggregates can cause blockages in the
spraying equipment.
Many concrete mixing plants have the ability to heat the mixing water
and in some cases also the sand and aggregates when mixing concrete
during the winter months.
159
segregation, excessive water evaporation, inclusion of unwanted water
or freezing. To avoid this, trans-mixers or agitators mounted on trucks or
purpose built heavy-duty carriers are used for transportation.
160
7. PLACEMENT OF SPRAYED
CONCRETE
Placement of sprayed concrete should produce a homogeneous, dense
sprayed concrete texture and a closed, even surface. It is very important
to use appropriate placement techniques to ensure quality sprayed
concrete.
The mix delivered to the pump should be checked for batch time, work-
ability (wet-mix) and temperature (preferably higher than +15 °C). The
minimum surface temperature should be higher than +5 °C before any
spraying can start. All delivery lines from the pump to the nozzle should
be securely fixed and fully lubricated with grout. If delays occur, the
workability of the mix should be checked on a regular basis to determine
if it is still fresh and pumpable. Under no circumstances should water
be added to the mixer, or old mixes that have undergone hydration be
used. The use of hydration control admixtures, such as MasterRoc HCA
Stabiliser, is therefore recommended at all times.
161
the correct air pressure and volume for the specific spraying operation
should be evaluated by the nozzleman and adjusted accordingly.
Prior to the application of sprayed concrete, the crew and the nozzle-
man should be aware of the required properties of the sprayed con-
crete lining. This may include the required thickness and profile, and
knowledge of any safety-critical elements of the lining that need careful
attention during spraying and require good compaction of the sprayed
concrete to ensure lining stability e.g. complex construction joints for
sidewall drift construction.
162
wards. Sprayed concrete overspray from the previous advance that is
loosely adhered to mesh and steel arches should also be removed.
Earth surfaces
163
Wash-out of freshly sprayed concrete due to water seepage should be
prevented. Seepage control should be achieved by using conduits to
channel the water before sprayed concrete is applied.
Rock surfaces
Concrete surfaces
164
of water from the substrate into the underlying masonry is decisive. If
this is not done, severe cracking of the sprayed concrete can occur. To
prevent this problem, the masonry surface should be dampened before
applying the concrete.
7.1.2. Reinforcement
If more than one layer of mesh is required, the first layer should be
covered with sprayed concrete before the second layer is placed. The
anchor or tie should extend to the second layer. The sheet of mesh
should be placed in the center of the sprayed concrete layer, unless
otherwise specified.
The minimum cover over reinforcement bars should comply with job
specifications or applicable building codes. Where possible, bar spaces
should be chosen to allow spraying the concrete at a slight angle from
either side of the bar. Intersecting reinforcing bars should be firmly tied
165
to one another and to their anchors and adequately supported to limit
vibration to a minimum during concrete placement, which can cause
the sagging of plastic sprayed concrete, create voids and reduce in-situ
strengths. Large knots of tie wire must be avoided to minimize the for-
mation of sand pockets and voids in the sprayed concrete.
7.1.3. Joints
As mentioned in [56]:
“If a tunnel cannot be safety constructed using full-face excavation,
the face is subdivided into smaller headings…Subdivision of the face
introduces joints into the lining. For structural integrity there must be
continuity of the steel reinforcement across these joints. Traditionally
this was achieved using complex arrangements of overlapping bars…
It is difficult to build these joints without damaging the lap bars in the
process and without trapping rebound when spraying. As a result the
quality of the joints was sometimes poor – both in terms of structural
capacity and watertightness.”
166
7.1.4. Protection of adjacent surfaces
< T
he nozzleman.
< C
ontrol of mixing water.
< N
ozzle velocity and nozzle technique.
In the wet-mix method, slugging does not happen unless the as-delivered
material is inadequately mixed, or if accelerators are added at the nozzle.
A buildup of material can be caused by the reaction of cement dust/resi-
due with small amounts of accelerator, causing slugging. Therefore, the
pump operator should control the pump to uniformly deliver the wet-mix
at the required rate. In addition, he should monitor the concrete being
delivered to the pump hopper for appropriate consistency.
167
the work (signal for air, or stop). Unsuitable sprayed concrete which
results from slugging should be removed by the crew.
The nozzleman should have clear access and visibility from a safe, sta-
ble place. Thus, utilities and other obstructions should be moved before
placing sprayed concrete. Appropriate lighting should be provided. If
platforms are used, these should meet all applicable safety standards.
In the dry-mix method, the nozzleman should add enough water at the
nozzle so that the surface of the sprayed concrete presents a slight
gloss. If too much water is added, the sprayed concrete can sag,
slough or drop out, depending on the position of the work. A dry, dark,
sandy surface with no gloss results if too little water is added. In this
situation, rebound and the probability of sand pockets increase, finish-
ing becomes difficult, and weak and laminated sprayed concrete is
produced. To ensure effective water control, the water pressure at the
nozzle should be considerably greater than the air pressure.
In the wet-mix method, the nozzleman does not have to control the water
content. The flow and/or the slump of the mix should be controlled to
comply with the recommended or specified ranges (see Chapter 2.2.1).
168
arms, greater distances are sometimes allowed. The velocity of a wet-
mix concrete stream out of a standard MEYCO nozzle (measured with a
maximal output of 12 m3/h) varies from 30 to 50 m/s.
With dry mixes, material velocity at the nozzle is determined by the vol-
ume and pressure of available air, hose diameter and length, size of noz-
zle tip, type of material and the application rate used. The concrete mix
is jetted from the nozzle at high velocity onto the substrate surface. The
velocity of a concrete mix stream that comes out of a standard MEYCO
nozzle varies from 70 to 100 m/s.
7.2.7. Execution
One of the skills of the nozzleman is to recognize the need for applying
sprayed concrete in a manner that minimizes the risk of loosened blocks
falling into the tunnel work area, but also to prevent the concrete from
169
sagging or even falling out of the crown sections. To meet this goal, the
nozzleman should firstly fill all overbreaks and zones of substrate weak-
ness, such as fissures, faults and gravel zones. The sooner this action
is taken after excavation, the safer the workplace.
170
7.2.7.1. Mechanized wet-mix spraying
Many of the factors that cause high rebound values, poor compaction,
loss of structural performance and hence increased project costs are
attributed to the performance of the nozzleman, in particular when
working with handheld nozzle systems using the dry-mix process.
171
Figure 7-1: MEYCO spraying manipulator – correct angle and distance
for reduction in rebound and enhanced quality
172
Sprayed concrete structures are heavily reliant on human competence
during construction, and therefore the design should reflect this by
considering the ‘buildability’ of these structures using sprayed con-
crete. Designing ‘buildability’ ensures that safety and durability-critical
elements are either designed out or simplified for ease of construction
on the jobsite. Furthermore, design teams should be aware of the limita-
tions of construction processes, and be familiar with the likely material
performance.
173
Application onto reinforced vertical surfaces (e.g. tunnel bench) should
begin at the bottom and fill corners. If possible, the first layer should
completely encase the reinforcement. Following layers should be thin
enough to avoid sloughing and sagging. The tolerable thickness of fol-
lowing layers depends primarily on the plasticity of the sprayed concrete
and the texture of the substrate surface.
174
considered to reduce rebound and improve quality.
Figure 7-2 attempts to illustrate some of the major factors that can affect
the degree of rebound produced by both wet and dry-mix sprayed
concrete during the spraying process. In the case of dry-mix, the val-
ues given are conservative. It has been assumed that the mix design,
particularly the aggregate grading and water-cement ratio, is optimized.
The amount of rebound is broken down into four major factors:
< N ozzle angle to substrate.
175
Application Techniques - Important Factors
100 Poor
Rebound & Quality
50
Average
Good
10
Excellent
Figure 7-3: Nozzle angle has a dramatic effect on rebound. The dis-
tance of nozzle to substrate influences rebound and compaction.
The distance between the nozzle and the substrate should be between
1 and 2 m, as indicated in Figure 7-3. If the nozzle is closer than this,
the projected concrete will tend to tear off the freshly placed material. If
176
the nozzle distance is reduced, the output should be lowered and the
nozzle moved faster. Furthermore, if the nozzle distance is extended to
3 m, for example, then the energy to compact the concrete is severely
reduced, again resulting in excessive rebound, poor compaction and
low strengths. Handheld applications will tend to lower the air output to
maintain the correct nozzle-to-substrate distance, this in turn also has
detrimental effects on the quality of the sprayed concrete.
Accelerator dosage as shown in Figure 7-2 can also affect the degree
of rebound. Too little accelerator will not provide adequate setting and
strength development, so that freshly applied concrete may be ‘shot off’
by the next pass of the nozzle, as it remains too soft. By definition, this
is not strictly rebound, but should be avoided at all times.
Further factors that can influence the degree of rebound and hence the
quality of sprayed concrete are summarized as follows.
177
concrete be applied through complete reinforcement cages.
Air volume, pressure and delivery: Air volume and pressure should
be those set by the manufacturer of the sprayed concrete equipment.
Air supply lines should be the size defined for the system, and nozzles
need to be checked for wear as this detrimentally affects the output
velocity of the sprayed concrete. The air-accelerator injection turbo
needs to be designed to optimize thorough mixing with the dense con-
crete stream at the nozzle.
< H eavy rain causing washouts or sloughing of the fresh sprayed con-
crete.
7.3. Finishing
Sprayed concrete does not have enough water to provide the required
particle lubrication for effective finishing. However, a high-quality sur-
face can be provided by means of careful finishing by skilled, experi-
enced craftsmen. The finishing of wet-mix and dry-mix requires similar
procedures, but it is somewhat easier with wet-mix due to its higher
water content.
178
The sprayed finish is the natural finish left by the nozzle after the sprayed
concrete is brought to approximate line and grade. The resulting tex-
tured, uneven surface is suitable for many applications. If a better align-
ment, appearance or smoothness is specified, the sprayed concrete is
placed a little beyond the guide strips or forms. When screeded with a
rod or trowel, it stiffens properly without cracking of the surface. Excess
material on the surface should be trimmed, sliced or scraped to true line
and grade. If any additional layers of sprayed concrete are to be applied
over the surface, it should be prepared adequately by removing surface
laitance, e.g. by means of waterblasting, sandblasting or other accept-
able methods. Guidance strips should then be removed. All impressions
they leave should be removed by means of floating.
Should a finer finish be desired, a flash coat may be used. This is a thin
surface coating up to 6 mm thick which is applied to the surface of the
sprayed concrete (left about 6 mm below the desired thickness), either
immediately after screeding or later on. Then finishing is carried out as
described previously.
Wood float, rubber float, brush or steel trowel may be used to finish the
flash or finish coat. Where a plaster coat is required later on, the finished
sprayed concrete should be left open-textured after trimming, slicing or
screeding, in order to guarantee a proper bond. Smooth zones should
be properly scarified or broomed.
179
7.3.1. Screed and float finish
Regarding highway tunnels, the required surface reflectance for the tunnel
sidewalls up to a height of 4 m from the road surface demands a smooth
finish, high reflectance and an average light color. Above this zone, the
crown sections of the tunnel are dark colored and of low reflectance.
< P rovides a limit for the cleaning machine and hides a soiled appear-
180
finish is to install sidewall cladding. Cladding systems composed of
vitreous enamel on steel plate are generally acknowledged to be the
most suitable for tunnel environments. Vitreous enamel (VE) cladding
is durable, impact resistant, easy to clean, chemically inert and fire
proof. The particular benefit of VE is that it is not a coating but is fused
to the steel plate, forming a robust integrated surface with a permanent
colorfast finish. Such cladding systems can provide a method to screen
and protect communication and electrical services, and allow a lower
surface finish to be specified for the sprayed concrete tunnel linings.
7.4. Tolerances
7.5. Curing
The curing period may depend on the properties required of the con-
crete, the purpose for which it is to be used, and the ambient condi-
tions, i.e. the temperature and relative humidity of the surrounding
atmosphere.
181
construction method.”
One would think that tunnels have ideal curing conditions with high
humidity (due to normal water leakage), no wind and no sun exposure.
However, this is not the case. In fact, tunnels and other underground
construction projects have some of the worst conditions for curing due
to ventilation that continuously blows dry air (cold or hot) into the tunnel.
It can be compared to concrete exposed to a windy area.
Curing is one of the basic and most important jobs in sprayed concrete
for underground support due to the large cement content of the mix and
the requirement for fast hydration and high early strength development,
which lead to rapid heat generation, causing relatively high shrinkage
and increasing the cracking potential of the applied concrete. Other rea-
sons for proper curing are the danger of rapid drying out due to heavy
ventilation in the tunnel and the application of sprayed concrete in thin
layers. Therefore, sprayed concrete should always be cured properly by
means of an efficient method, especially in tunnels.
182
Long Term Strength Development
80
183
are normally sprayed directly onto concrete surfaces, drying to form a
relatively impermeable membrane, which retards moisture loss from
the concrete. This solution is efficient and effective and may be applied
to freshly placed concrete. More details are provided in Chapter 3.5.5
Curing agents.
184
low air humidity will cause higher than normal evaporation of water
from the fresh concrete.
< Increased rate of flow loss.
< G enerally increased rate of set.
Once the sprayed concrete is at the jobsite, placing, finishing and cur-
ing procedures are the same as those for concrete. Where screeding
and finishing is required, they should be done as soon as the condition
of the sprayed concrete permits. Curing should start immediately after
finishing is completed. During all phases of the installation procedure,
the temperature of the sprayed concrete should ideally be maintained
between 10 °C and 40 °C.
185
temperature during curing should be maintained above 5 °C.
186
8. SPRAYED CONCRETE
EQUIPMENT
The need for numerous technical solutions, as well as high risks and time
pressure are typical of the underground environment. Consequently, the
contractor needs a competent and reliable partner. However, quality
products alone are not enough. Only with a balanced utilization of reli-
able equipment, high performance products and competent service
can the required quality and efficiency be achieved.
In April 2013 MEYCO Equipment was taken over by Atlas Copco Rock
Drills AB. Both companies, BASF and Atlas Copco, wished to cooper-
ate regarding the further development of sprayed concrete equipment
and thus signed a cooperation agreement to cover the basic conditions
of future joint development projects.
There are two basic spraying methods – the wet-mix and the dry-mix
method (see Chapter 4). Since these two methods have distinct charac-
teristics, so do the required spraying machines.
187
Criteria Wet-Mix Method Dry-Mix Method
Working and operating worse (high dust
good
conditions formation)
Production capacity high low
Quality of applied sprayed
high lower
concrete
Worldwide application ratio of
90% 10%
sprayed concrete in tunnels
Tendency of sprayed concrete
increasing decreasing
application
Rebound lower (< 10%) higher (approx. 20-40%)
Equipment cost higher lower
Abrasion of wear parts low high
by means of spraying by means of spraying
Application
manipulator and manual manipulator and manual
Method of flow dense-flow method thin-flow method
Air consumption lower higher
Output theoretical 3 - 30m³/h 1 – 20 m³/h
Output practical 3 - 24m³/h 1 – 10 m³/h
Sprayed concrete at wall after
< 23m³/h < 8 m³/h
rebound
Many different types of pumps were tested and used in the past, such
as rotor machines, hose pumps (squeeze pumps), rotor/stator pumps,
piston pumps with ball valves, etc. The thin stream, low density method
with rotor machines was often used in the past, but nowadays can only
be seen on rare occasions. Today, wet spraying machine technology
is based on the proven double piston principle with S-tube design,
whether electric or diesel powered.
188
Figure 8-1: Double piston pump with S-shaped swing tube
accelerators.
< Have minimal wear cost per cubic meter.
< H
ave a compressed air volume approx. 50 % lower by the same
< P
rovide practical spraying capacities ranging from 3–24 m3/h (with
< P
rovide a considerably higher dosage accuracy of liquid accelerator.
MEYCO Altera
189
Figure 8-2: MEYCO Altera double piston pump
MEYCO Suprema
190
and analyzed separately using the MEYCO Data system. The MEYCO
Dosa TDC system guarantees exact regulation of dosing in relation to
the spraying volume.
rial output adjustment, with the result that the pulsation over the
full range of the material flow is reduced to a minimum and is hardly
noticeable at the nozzle.
< T
he PLC system supervises, coordinates and controls all functions
of the machine. It also allows the checking and control of data, which
can also be printed out, e.g. dosing quantity of accelerator, output
capacity etc. Errors within the hydraulic or electrical systems will
be indicated on the display and the causes of malfunctions can be
determined through the help program of the PLC.
< T
he MEYCO Dosa TDC dosing system for liquid accelerator is an
191
Sprayed concrete delivery at pump outlet Sprayed concrete delivery to nozzle
1 2 1 2
Cylinder 1 Cylinder 2
Conventional system
without push-over
Accelerator
1 2 1 2
Cylinder 1 Cylinder 2
Conventional system 3 3
without push-over
Accelerator
1 2 1 2
Cylinder 1 Cylinder 2
MEYCO Suprema 3 3
Accelerator
192
USB-Stick
PLC Computer
Display
customer
Potentiometer
concrete flow Spraying nozzle
SPS
PLC
Amplifier card
Required value of additive
prop. value
Input
+/- 0...25%
Actual value
Flowmeter
of additive
Frequency converter
M Dosing pump
integr. PI-controller
Accelerator
Figure 8-4: Working principle of the MEYCO Dosa TDC (Total Dosing
Control) system
193
Figure 8-5: MEYCO Suprema, built as trailer version
machine is in operation.
< W hen a blockage in the conveying line is being detected, the machine
first goes into reverse mode (to release pressure) before going into
idle mode.
< E lectric control system built to the latest safety standards according
194
Figure 8-6: MEYCO Suprema, built as standalone version
195
basic rules. To grasp this easily, the reader may use the following practi-
cal general checklist for wet-spraying.
blockages.
< K
eep the hopper full to the grill so that air cannot be sucked in.
< T
he vibrator should be used to pass the material through the screen,
gation.
< W
hen the spraying operation is stopped or completed, the nozzle
< T
he hopper grill must be kept clean.
Machines that work on the rotor principle are the type most generally
used nowadays.
196
Typical dry spraying machines:
< A
re robust and have a simple design.
< A
llow user friendly operation.
< H
ave quite high wear cost per cubic meter.
< R
equire sufficient air supply.
< G
enerate approx. 20–40 % rebound material (waste material).
< D
o have an increased counter pressure in the machine and dust
< A
llow cleaning of the system without water.
< A
re available powered by electric or compressed air motor.
The dry mix is filled into the feed hopper (1). As the rotor revolves, the
mix alternately falls by its own weight through a feed slot into one of the
rotor chambers (2) below. While one of the chambers is being filled,
compressed air (p) is blown from above into the other (full) chamber. The
mix is discharged into the outlet opening (3) and blown at a pressure of
3 to 6 bar through the conveying pipeline to the spraying nozzle, where
the mixing water is added. The top and bottom of the rotor are sealed
with rubber discs.
Capacity is defined by the size of the rotor used multiplied by the speed
of the rotor (rpm).
197
1
2 2
3 1: Feeding hopper
2: Rotor
3: Outlet
p: Pressurized air
198
Figure 8-10: MEYCO Piccola/MEYCO GM: typical rotor dry-mix spray-
ing machines
There are more parameters determining the size of the conveying tube:
the granulometry of the dry-mix, the grain shape of the aggregates,
compressed air supply, the conveying distance and height.
The following rule of thumb for determining the correct hose and nozzle
diameter is recommended: the maximum grain size in the concrete mix
shall never be bigger than 1/3 of the inside diameter of the conveying
line.
199
Figure 8-11: Various nozzles for dry-mix spraying
Good quality sprayed concrete can be achieved with the use of dry-
mix spraying equipment. However, if the installed lining reinforcement
(including lattice girders and lapping of reinforcement) is to be sprayed,
quality-related problems arise due to the high level of rebound. This is
the opposite situation to most repair applications, because of the high
early strength development requirements in tunnel support which yield
to higher rebound.
200
8.3. Mobile spraying equipment
Some of the reasons behind the change from the dry to the wet-spraying
process are the limitation of output, quality of the applied material and
safety considerations.
The first spraying manipulator designs were based on crane booms but
it was recognized that the forces impacting the boom during spraying are
different to those for which a crane boom is normally designed. As for the
chassis, it was obvious to use the equipment which was already avail-
able on site, such as trucks and other utility vehicles. The disadvantage
of this kind of carrier was the height of the platform to mount the sprayed
concrete pump, the space to mount all accessories and a suitable power
takeoff to drive the equipment from the truck engine.
8.3.1. Carriers
201
< T
urning radius: minimal turning radius of the equipment, including any
and ramps.
With the change from the dry to the wet-spraying process, the industry
realized that not only does the sprayed concrete pump play an impor-
tant role in the whole process, but also in the mechanization of the actual
application of the material.
wear on joints.
< M
inimal dimensions of boom for tramming.
< S
traightforward kinematics with minimal joints for effortless operation.
< C
hoose manipulator with correct working range for tunnel profile to
avoid spraying at the limit of the boom, which has negative effects on
the spraying angle thus quality.
< G
ood lighting as visibility is generally quite limited during spraying;
202
< L
ight but sturdy remote control including main functions with high
quality cable or radio link.
203
8.3.2.1. Basic spraying booms
The first true spraying booms were introduced to the market at the
beginning of the 1980s. Equipment manufacturers around the globe
came up with various designs of spraying booms, some based on
converted concrete-placing booms, others with some kind of spraying
lance installed on drill booms. In 1983, MEYCO Equipment introduced
MEYCO Robojet to the market as one of the first specially designed
sprayed concrete booms.
204
Today, most designs consist of a main boom with attached spraying
lance to facilitate spraying parallel to the surface. Additionally, an auto-
matic parallel adjustment of the lance is available on most booms to
reduce the manipulations necessary during spraying while moving up
and down the profile.
For very narrow tunnels, such as those found in mines, hydropower pro-
jects and escape tunnels, it is sometimes necessary to spray side drifts
or safety bays while standing in the main drive. Booms constructed
according to the rollover principle, such as the MEYCO Minima, have
proved to be a good option.
205
Figure 8-15: MEYCO Minima
When the overall dimensions are limited, booms with several extensions
driven by hydraulic tandem cylinders are a good solution. The very
versatile MEYCO Rama spraying boom can be mounted on almost any
suitable carrier, shaft installation or TBM.
206
8.3.2.3. Computer-assisted booms
With the change from dry to wet spraying at the beginning of the 1980s
and the accompanying need for spraying booms to handle the weight
of the nozzle and hoses, the industry sought more and more automa-
tion of spraying equipment to cope with the demands for defined and/or
guaranteed layer thickness and to reduce the number of underground
personnel exposed to the spraying process.
207
< K
eeping the stand-off distance between the nozzle and application
surface constant.
< Keeping the correct spraying angle even with uneven profiles.
< Leading the nozzle with a constant speed over the wall.
< Guaranteeing 100 % coverage of the application area.
All this was needed alongside continuous operation 24/7 and the appli-
cation of high volumes in changing geometries.
The need for the industry to move towards robotic equipment led to the
development of MEYCO Logica technology. This technology is based
on the well-known kinematic principles of the MEYCO Robojet boom
and has been developed in cooperation with the tunneling industry and
academia.
208
purely manual to semi-automatic and fully automatic, within selected
underground areas. The fully automatic mode can be vital where condi-
tions are extremely dangerous.
The aim of this system is not primarily to automate the whole job of
spraying, but to simplify the task and enable the operator to use the
robot as an intelligent tool, working in an efficient way to achieve a high
level of quality. With the correct angle of application and a constant
spraying distance, a remarkable reduction in rebound and therefore
cost savings can be achieved.
209
Operator panel and onboard visualization
210
Figure 8-20: Graphic user interface of MEYCO Logica
Simulation
< C
ost savings: reduction of time, labor, rebound material and operator
training, and through using only one machine for measuring the tun-
nel profile and spraying.
< Increased output: due to automation, continuously high output, inde-
pendent of the operator’s skill, rock surface conditions and visibility.
211
< Improved working conditions: with the simplified and ergonomic
remote control, the operator focuses more on visual quality control
of the spraying than on manipulator movements, due to the computer
assisted system.
< Increased and constant quality: the nozzle is automatically kept at
the correct distance and angle, even in bad visibility areas, resulting
in better compaction and less rebound.
212
Figure 8-21: Installation on a tunnel boring machine (TBM)
The mounting of shaft manipulators has a lot in common with ring con-
structions made for TBM manipulators. The big difference is the angle
and direction in which the carrier vehicle, in this case a stage, is either
lowered or raised within a vertical borehole. As in the case of TBM ring
constructions, the manipulator must be an integral part of a coordinated
sprayed concrete system. Depending on the diameter of the hole, a cen-
trally mounted lance or a ring running around the stage would be used.
213
Figure 8-22: Shaft-sinking installation
< E
limination of time-consuming installation and removal of scaffold-
214
< C
ost savings through rebound reduction leading to less material
wastage and cleaning time.
< Improved accuracy of the finished sprayed concrete surface topology,
through use of manipulators designed for easier spraying operation.
< B etter working conditions for the nozzleman and team due to protec-
altitude.
< F
ilter system at air intake (cyclone and fine filter).
< O
il absorber or oil free compressor type.
< C
ooling capacity for compressor oil and compressed air (capacity
Air volume and pressure are important for high quality sprayed concrete.
It should be ensured that the diameter of the air hose is big enough, so
pressure loss in the line is reduced to an acceptable level.
215
mum grain size and the vertical elevation, as well as on the moisture
contained in the mix. If the dry-mix sprayed concrete machine is driven
by a compressed air motor, air consumption will increase by about 5
m3/min.
m3 / min m3 / min
13 30
11 25 Ø 90
Ø 80
9 9 Ø 65
Ø 50
7 7
Ø 50
5 5
Ø 40
3 3
Ø 32
Ø 25
1 1
0 0
0 20 40 60 80 100 120 140 160 0 100 200 300 400 500 600
Figure 8-23: Air requirements for dry spraying with MEYCO Piccola (left)
and MEYCO GM (right)
As a rule of thumb, the air requirements for dry spraying can be calcu-
lated as follows:
< Air consumption: nominal output of compressor.
< F or sites higher than 500 m above sea level, add 3 % to air volume for
the first 1000 m. For every successive 1000 m add 5 % to air volume.
< Volume weight of the conveyed mix: 1.8 t/m3
216
such as the MEYCO Potenza are equipped with a compressor that has
a nominal output of 11.5 m3/min at a pressure of 0.6 MPa.
14.0
13.0
Air volume [m3/min]
12.0
11.0
10.0
9.0
8.0
7.0
6.0
5.0
4.0
0 5 10 15 20 25 30
Pump output [m3/min]
Figure 8-24: Air requirements for wet spraying (based on author’s prac-
tical experience)
Table 8-2: Air volumes and pressures for dry and wet spraying
217
8.5.1. Dosing equipment for wet-mix spraying
MEYCO Dosa
The MEYCO Dosa TDC (Total Dosing Control) system fulfils these
demands and, in addition, it provides the possibility of fine-tuning the
dosage according to prevailing conditions (see also Chapter 8.1, MEYCO
Suprema).
218
< O
verpressure switch for safety and as a remote control to stop the
pump during application.
< S
ystem separator to prevent dangerous reverse pumping of accelera-
< F
ree access to the most important parts for service works.
< E
asy operation and low maintenance.
Due to their easy handling and dry running capabilities, hose pumps (syno-
nym: peristaltic or Bredel) are commonly used for dry-mix spraying.
219
Dosing systems such as the MEYCO Dosa system have proved to
delivery accelerator to an accuracy of 5 % or better.
Only with the correct conveying and nozzle systems, adapted to the
type of application (wet-mix/dry-mix method, mechanized/hand appli-
cation) and the accelerator used, can low wear and outstanding quality
of the in-situ sprayed concrete be obtained.
220
From a safety point of view, it is important that wet-mix spraying hoses
and couplings are of the highest quality. They should be high-pressure
tested and certified.
221
data, including generation of reports and data storage, can be made
in the office later on.
To measure the strength development of fresh concrete, several sys-
tems have been developed and offered to the market. Two of the most
common measurement instruments to gauge early strength will be
described in this section.
222
Figure 8-27: MEYCO Data
223
Penetration needle method
224
17 to 56 MPa) were calibrated. Generally only the Standard-method
should be used, in order to avoid confusion on the job-site.
Both the Penetration needle and the Stud driving method have been
successfully proved on tunnel jobsites all over the world.
Power
Strength
setting Max.
range Method Cartridge Mix Specification*
DX 450- aggregate
[MPa]
SCT
mixed
dolomitic
Penetration 0–8 limestone EN 14488-2
0.2–1.2 needle - - 0–11 (not ÖVBB 2006
method 0–16 relevant ÖVBB 1999
for this
method)
Stud driving White***, mixed
1–8 method Hilti Special- 1* 0–8/11 dolomitic ÖVBB 1999
DX 450 method limestone
mixed
0–8/11 EN 14488-2
dolomitic
Stud driving Green 0–16 ÖVBB 2006
limestone
2–16 method Hilti Standard- 1*
DX 450-SCT method hard
0–16 aggregate EN 14488-2
(diabase)
Stud driving Yellow mixed
17–56 method Hilti Special- 2* 0–8/11 dolomitic ÖVBB 2006
DX 450-SCT method limestone
225
Table 8-3: Summary of test methods for measuring the early strength of
sprayed concrete (Source: Hilti Operating Instructions)
Pull-out test
The latest developments in the field of sprayed concrete pumps are the
minimization of pulsation and higher outputs. In addition, tighter inte-
226
gration of the various systems found on a spraying rig into the control
system has been achieved, including data logging possibilities.
227
Figure 8-31: Prism installed on MEYCO Robojet Logica
Requests from the industry clearly show the need to exchange data
between underground equipment and higher level systems. Data log-
ging systems such as those for wet concrete pumps (see Chapter 8.7.1)
or other machine parameters and information about actual profiles help
to speed up the whole process as the acquisition time is reduced in
general and data collection is reduced to only one piece of equipment,
such as profile data in the case of the MEYCO Logica.
228
to remove the material from the surface, such as compressed air with
water, mechanical scalers and high-pressure water scaling equipment.
If the rock strength is very high, hydraulic hammers are used to bring
down any unwanted material. This sometimes dangerous and time-
consuming procedure is often used in deep mining operations.
229
Figure 8-32: MEYCO high pressure water cleaning
230
Figure 8-33: MEYCO high-pressure water scaling
231
9. TESTING AND QUALITY CONTROL
The placing of concrete by means of spraying is a unique method with
many unusual applications which require careful attention to detail from
design through to construction. Therefore, the establishment of quality-
control procedures is fundamental to ensure the functionality of the final
product as designed and a satisfactory life expectancy. Different factors
determine the quality of sprayed concrete, i.e. design, materials, appli-
cation equipment, craftsmanship and installation techniques.1
9.2. Materials
1 See ACI Committee 506, Guide to Shotcrete ACI 506R-05, 2005, Page 35f
232
9.3. Application equipment
9.4. Craftsmanship
9.5. Inspection
233
10. SAFETY, HEALTH AND ECOLOGY
Cement can cause dry and cracked skin, dermatitis and alkali burns.
Regarding admixtures, caustic accelerators in particular may create
additional hazards. Therefore, all underground personnel should use
proper protective devices, ointments and adequate clothing. Enclosed
areas require special caution.
234
10.2. Chemical admixtures and complementary products
With the introduction of the wet-mix method, the change in the working
atmosphere was evident, and the amount of fine dust is now normally
below the maximum allowed value.
235
35
Common limit value 6 mg/m3
30
5
3
0
DD ovendry DM moist WA wet
Min.
Mean
Max.
Over the last two decades the change to wet-mix spraying in combina-
tion with modern mix-design competences, utilizing advanced admix-
tures technologies and alkali-free accelerators, has greatly improved the
underground working environment, including air quality.
236
North Cape (1998), MasterRoc
SA 160 liquid AFA, output
approx. 15m3/hour: WET-MIX
237
Relative dust intensity Spraying Capacity Number of
Spraying System
[mg / m 3 of air] [m 3 / h] Nozzles
1. Dry-mix 12.6 13.5 2
2. Dry-mix 6.6 6.8 1
3. Wet-mix 3.3 15.4 1
10.4. Environment
238
10.5. Conclusions
239
11. PERMANENT SPRAYED
CONCRETE TUNNEL LININGS
Sprayed concrete single shell linings (SSL) have been built since tun-
neling based on NATM was introduced, e.g. for the construction of water
tunnels, caverns and transportation tunnels. The main design issues
were related to the structural interaction between the primary (outer) lin-
ing and secondary (inner) lining, which are usually built at different times
and thus subjected to different stresses and strains, as well as to the
watertightness of the sprayed concrete lining.
During the last two decades, significant progress has been made in
concrete technology (mix design), with advanced admixtures (e.g.
water reduction, alkali-free accelerators), as well as in the application
of sprayed concrete, with sophisticated spraying robots, in waterproof-
ing (spray applied membranes) and the passive fire protection of tunnel
linings. Also, numerical design techniques have improved. All these
factors have enabled designers to use sprayed concrete linings increas-
ingly for long-term service life. Designers have started to replace the
traditional double-shell lining system with permanent sprayed concrete
lining (SCL) systems, i.e. a composite shell lining or single shell lining
(see Figure 11-1).
240
Permanent SC Linings:
Double Shell Lining Innovation Single / Composite Shell Lining
Figure 11-1: Change in the design of tunnel linings and related key
change drivers
Because sprayed concrete primary linings have not usually been con-
sidered part of the permanent tunnel lining, specification of primary
linings has often led to the supply of low-quality sprayed concrete.
However, uniform, high-quality sprayed concrete linings can be con-
structed. It is now a matter of proper decision-making and specification
as well as execution control.
241
11.1. General requirements for
permanent sprayed concrete
The primary (outer) lining shall fulfill the requirements of structural safety
and guarantee durability (e.g. limit crack width). Additionally, the sec-
ondary (inner) lining shall ensure serviceability.
242
11.2. Durability issues
243
Factors Design Team Construction Team
Human Independent design checking Monitoring, review and
factors Design review during construction implementation during construction
Quality assurance / Quality control Quality assurance / Quality control
Risk assessment Risk assessment
Competence Competence
Supervision
Training
Structural Construction sequences Mix design (incl. accelerator type)
factors Permanent ground reinforcement Application methods
Joint and inter-layer details Equipment choice and performance
Physical and chemical exposure Curing methods
Tunnel design life and purpose Ground improvement
Design parameters and time effects
Mesh reinforcement or fibers
Waterproofing methods
Profile geometry
Material properties
244
11.2.3. Durability and tunnel use
Table 11-2 summarizes the principal factors that affect the durability of
tunnel linings for normal use in different types of tunnels.
Sulfate resistance was tested by SINTEF, Norway. The results are sum-
marized in Key:
- none (no sulfate resistance): more than 0.1 % expansion
- moderate sulfate resistance: between 0.05 % and 0.1 % expansion
- high sulfate resistance: less than 0.05 % expansion
245
Cement Type OPC OPC OPC OPC SR
Aggregates: alkali-silica non non slightly
reactive reactive
reactivity reactive reactive reactive
Microsilica 0% 6% 0% 6% 0 % and 6 %
W / C ratio 0.45 0.47 0.52 0.48 0.45 to 0.48
Modified sodium silicate
moderate high none high high
accelerator (5%)
Modified sodium silicate
none high none high high
accelerator (10%)
alkali-free accelerator (5%) high high none high high
alkali-free accelerator
moderate high none high high
(10%)
Key:
- none (no sulfate resistance): more than 0.1 % expansion
- moderate sulfate resistance: between 0.05 % and 0.1 % expansion
- high sulfate resistance: less than 0.05 % expansion
246
attack by both the tunnel’s internal and external environments, pro-
ducing durable sprayed concrete linings depends not only on material
specification, but also on detailing and the design of the lining.
The design of the lining, as well as the national standards for materi-
als where the sprayed concrete is used, should be adapted to satisfy
durability requirements. The best possible design solution should be
provided based on the available practical technology.
< M
aterials (type of cement, type of aggregate, type and dosage of
< W
orkmanship (compaction, finishing, curing etc.)
High profile fires have happened in tunnels, for example the Channel
Tunnel, the Storebælt running tunnel, the Mont Blanc Tunnel, and the
Tauern and Gotthard tunnels, resulting in a significant loss of life in some
cases, especially in the Mont Blanc and Gotthard tunnels. Structural
damage to tunnels involves repair work at elevated costs as well as
extended periods of no operation due to tunnel closure (see Table
247
11-4), to which one can add the negative effects on tourism, the micro-
economy, the value of the structures etc.
Fire safety in tunnels applies to both the safety of people and the safety of
the structures. Active fire suppression systems include water sprinklers,
water mists and foam deluge systems, all of which are activated by early
warning sensors in the event of a fire. The theory is to reduce the fire
before it gets out of control. New developments and research programs
have proven the efficiency of those systems in controlling the heat release
rate and fire spread. Nevertheless, active fire suppression systems are
not designed for the protection of structural concrete linings.
248
tural integrity of the concrete lining was impaired. In order to achieve
high durability requirements for permanent tunnel linings, concrete is
designed to have low permeability, which leads to poor performance
during a fire and a higher probability of spalling. This was evident in
the dramatic Channel Tunnel fire in November 1996, which resulted in
almost complete loss of the concrete section.
There are many ways to protect a structure from the negative effects
of heat, however thermal barriers emerge as the most robust and fit-
for-purpose solution to protect against both the mechanism of spalling
and that of strength loss caused by the exposure of concrete structures
to elevated temperatures. The temperature at the interface concrete-
passive fire protection should not exceed 350 °C as this is the critical
point of strength loss for concrete. The temperature of steel bars in the
concrete should not exceed 250 °C for the same reason.
249
can be installed directly onto the substrate as a fully bonded system,
without the necessity of mechanical fixing, or as a mechanically bonded
system in high risk areas or where surface preparation is not possible,
or as a combination of the two.
Fire load
Interface temperature
Steel cover
250
is typically always limited. If applied as a fully bonded sprayed thermal
barrier, it ensures continuity of the concrete structure.
251
resulting reduction of the required thickness of the secondary (inner)
lining leads to a lower volume of excavation, less lining material and
reduced construction time.
Clients have also supported further developments with the use of SCL
and permanent steel-fiber reinforced sprayed concrete for the sec-
ondary (inner) lining at the Heathrow Express crossover cavern or the
252
single shell linings at Terminal 5 of the Heathrow Express project (2002).
SCL has been repeatedly designed into recent projects such as the
Dublin Port Tunnel, Kings Cross, Hindhead Road Tunnel, Thames Water
(Hampton shaft), Victoria Station Update and Crossrail.
From a global perspective, permanent SCL has been used for differ-
ent purposes, i.e. the construction of escape tunnels, cross passages,
metro stations and tunnels, sub-sea road tunnels and road and railway
tunnels. Permanent SCL design has also been introduced for the pur-
pose of tunnel rehabilitation, mainly in Switzerland.
11.5. Conclusions
The designer also has a key role to play. The important issues in this
instance are to understand the sprayed concrete application process
and not to over-specify material properties. The key to achieving durabil-
ity is through designing buildable designs by keeping details as simple
as possible.
253
Wet-mix sprayed concrete applied using modern, high-performance,
environmentally safe admixtures and equipment provides the tunnel
industry with an economical tool to construct permanent, durable sin-
gle-shell linings. The construction process has become highly auto-
mated, thereby significantly reducing the degree of human influence
that has prevented clients from considering sprayed concrete as a
permanent support in the past.
With the increased use of durable sprayed concrete linings, new tech-
nologies to promote and maintain their use have entered the market
recently. These systems enhance watertightness and provide high-
performance passive fire protection.
254
during the mid 1990s. This trend is set to increase further as design and
construction teams become more familiar with modern sprayed con-
crete technology and the durable concrete that can be produced.
255
12. Outlook
256
sprayed concrete application also forms an important part of the training
centers. Structured training programs are being carried out with both
theoretical and practical parts, including application training according
to international standards, local standards and also project specific
standards. Life size equipment or simulators are used, where future
operators will learn the basics of operation in a controlled environment
without having to worry about delaying the tunneling advance, wasting
costly concrete or worse, causing substandard spraying that will have
to be removed from the tunnel at later stage. Today, trained and certified
people are a requirement and not an option.
Emerging markets such as Asia, Russia, Africa and South America will
bring a new and necessary acceptance of sprayed concrete. It can be
expected that development in these markets will bring new challenges
and requirements, and sprayed concrete will provide the answer to a
certain number of them.
The main aim of the industry over the coming years will be to create
public awareness and consequently, acceptance of the importance of
tunneling and the use of underground space. BASF, with its MasterRoc
solutions, is contributing its share to this development.
257
13. PROJECT REFERENCES
EUROPE
< C
ontractor: Hæhre Entreprenør AS
< Construction period: 2010 – 2013
13.1.1. Description
< 4
hours: > 4 MPa
258
13.1.3. Mix Design
< C
ement: 460 kg (CEM II/A-V 42.5 R)
< A
ggregate (0 – 8 mm): 1524 kg
< M
icro-silica: 18 kg
< P
P fibers (50 mm): 5 kg
< S
uperplasticizer: 5.7 kg
< H
ydration control: MasterRoc TCC 735: 5 kg
< A
ccelerator: MasterRoc SA 168: 6 %
< W
/(C+S) binder ratio: 0.45
< R
ebound: < 3 %
< S
lump: 200 mm
< C
ontractor: New Boliden
13.2.1. Description
The Boliden mines extract zinc, copper, lead, silver and gold, with a
total of 200’000 m3 of excavation per year. Sprayed concrete is applied
for the transport and production tunnels of the mine. All of the admix-
tures are delivered from the surface down to the mine by a tank on the
sprayed concrete transmixer, and at site are pumped pneumatically to
the sprayed concrete rig.
< C
oncrete Supplier: Dahlgrens Bygg Betong
< C
ement (OPC): 490 kg
< A
ggregate: 0 – 8 mm
< S
uperplasticizer: MasterGlenium 186: 1%
< H
ydration control: MasterRoc HCA: 0.40 - 0.60 %
< A
ccelerator: MasterRoc SA 168: 6 - 8%
259
< S
teelfibers Beakert: 50 kg
< W
/C ratio: 0.42
< S
lump: 200 +/– 25 mm
< A
pplication thickness: 100 – 150 mm
< C
ontractor: Strabag
< C
onstruction period: 2001 - 2011
13.3.1. Description
During the construction of the longest railway tunnel in the world, the
use of construction chemicals supplied by BASF has been essential to
ensure efficiency, durability, safety and a sustainable approach to con-
struction. From 2017 onwards, the Gotthard Base Tunnel will shorten
the traveling time between Zurich and Milan by one hour. In addition,
freight trains will be able to travel with twice the load and speed due
to the track’s lesser incline. This means that people and goods will be
able to cross the Alps faster, more safely and in a more environmentally
friendly way. A total of 415’000 m3 of sprayed concrete was used for the
section of the tunnel between Erstfeld and Sedrun.
< C
ement (CEM II/A-LL 32.5 R): 415 kg/m3
< Sand 0/1 mm: 39 %
260
< Sand 1/4 mm: 28 %
< Aggregate 4/8 mm: 33 %
< Micro-silica: MasterRoc MS 660: 70 kg/m3
< Superplasticizer: MasterRheobuild 3535 SP: 1.2 %
< Hydration control: MasterRoc HCA 10: 0.5 %
< Accelerator: MasterRoc SA 160: 6 %
< W/C ratio: 0.44
< Thickness applied: 5 – 20 cm
< Spread table: ~ 60 cm
< C
ontractor: JV STRABAG JÄGER
< C
onstruction period: 2011 – 2014
13.4.1. Description
261
< 1 hour: > 0.6 MPa
< 6
hours: > 1.8 MPa
< 24 hours: > 5 MPa
< 28 days: > 25 MPa
< C
ement: 280 kg (CEM I 52,5 R SP)
< F
ly Ash: 140 kg (Fluamix C)
< A
ggregate (0 – 8 mm): 1695 kg
< A
ir Entrainer: 0.5 kg
< S
uperplasticizer: 2.5 kg
< H
ydration Control: 1.5 kg
< A
ccelerator: MasterRoc SA 186: 7 %
< W
/(C+S) binder ratio: 0.5
< T
hickness applied: 15 - 20 cm
< F
low: 580 mm
< C
ontractor: JV Züblin – Baresel – Hinteregger - Oestu Stettin
< C
onstruction period: 2008 – 2011
13.5.1. Description
The Schwäbisch Gmünd Tunnel is a bypass road tunnel for the city of
Schwäbisch Gmünd located to the south east of Stuttgart. The tunnel
has two lanes and a parallel emergency and rescue tunnel. The overall
length is 2.2 km. The excavation was done using the drill and blast
method with a support consisting of lattice girders, mesh, sprayed
concrete and rock bolts.
< 6
hours: > 1.8 MPa
262
< 28 days: > 25 MPa
< C
ement: 380 kg (CEM II A-LL 42,5 R)
< A
ggregate (0 – 8 mm): 1579 kg
< S
uperplasticizer: 4.7 kg
< A
ccelerator: MasterRoc SA 183: 7 %
< W
/(C+S) binder ratio: 0.51
< T
hickness applied: 15 - 20 cm
< F
low: 600 mm
< C
ontractor: Balfour Beatty
< C
onsultant – Mott MacDonald
< C
onstruction period: 2008 - 2011
13.6.1. Description
263
13.6.3. Mix Design
< C
ement: 390 kg (Ketton)
< F
ly ash: 50 kg
< S
teel fiber: 30 kg (Dramix)
< M
icro-silica: EMSAC 500 S: 50 kg
< S
uperplasticizer: MasterGlenium 5: 2.8 liters
< H
ydration control: MasterRoc HCA: 2.5 liters
< A
ccelerator: MasterRoc SA 160: 7%
< W
/C ratio: 0.38
< O
wner: Grand Lyon, assisted by Egis Tunnel
< D
esigner: Setec
< C
onstruction company: VINCI - Spie Batignolles JV
< C
onstruction period: 2010 – 2014
13.7.1. Description
264
13.7.3. Mix Design
< C
ement: 380 kg (CEM I – 52.5 PMES Vicat St Egrève)
< Aggregate: 1750 kg (sand 0/4 and crushed aggregates 4/10)
< Fiber: MasterFiber SP 650 (5 kg)
< Superplasticizer: MasterPolyheed 510 (3.8 liters, 0.8%)
< Accelerator: MasterRoc SA 167 (26 kg, 7%)
< W/C ratio: 0.47
< Slump: 20 cm
< O
wner: ASF, assisted by Egis Tunnel
< Designer: Setec
< Contractor:
< Violay Tunnels: VINCI – Eiffage TP JV
< Bussière and Chalosset Tunnels: Razel – Spie Batignolles JV
< Construction period: 2009 – 2012
13.8.1. Description
Declared of public utility on April 17, 2003, the A89 which runs from
Balbigny to the Tour de Salvagny is a highway interconnection about
50 km long. This project is part of the great cross link from the Atlantic
to the Rhone-Alpes region, and includes the excavation of 3 tunnels by
drill and blast method: Violay tunnels: 2 x 3’900 m, Bussière tunnels: 2
x 1’030 m and Chalosset tunnels: 2 s 700 m. The project used BASF’s
MasterRoc SA 167 for the application of the sprayed concrete lining for
its performances.
265
< 28 days: 35 MPa
< C
ement: 410 kg (CEM I – 52.5 PMES Vicat St Egrève and Lafarge Val
d’Azergues)
< Aggregate: 1710 kg (sand 0/4 and crushed aggregates 4/10)
< Superplasticizer: MasterPolyheed 500 (2 liters, 0.5%)
< Accelerator: MasterRoc SA 167 (28 kg, 7%)
< W/C ratio: 0.50
< Slump: 18 cm
< O
wner: Generalitat de Cataluña
< Contractor: Dragados
< Construction period: 2010 - 2011
13.9.1. Description
The C-15 Highway project is part of the 67 km long Eix Diagonal Project
for the C-25 Highway, which will join some important towns in the
south of the Barcelona province with the north of Catalonia, improv-
ing the freight traffic through Catalonia to France. The project consists
of 3 tunnels: Montgros (2 x 1’600m), Costa Bernarda (2 x 350 m) and
Rocaforadada (2 x 350 m). A total of 30’000 m3 of sprayed concrete was
applied in two or three layers of 10 – 15 cm. A better safety environment
inside the tunnel was create for the personnel than with the traditional
aluminate, and compressive strength much higher than the nominal (fck
= 30.0 MPa) was achieved, thanks to the accelerator MasterRoc SA 167.
266
Compressive strength achieved:
< 2
4 hours: 13.5 MPa
< C
oncrete supplier: Hormigones Roca
< Cement (CEM I 42.5 R): 425 kg
< Aggregate (6 - 12 mm): 355 kg
< Sand (0/4 mm): 1155 kg
< Sand (0/2 mm): 270 kg
< Water: 180 liters
< Superplasticizer: MasterGlenium TC 1394: 1% 4.25 kg (4 liters)
< Accelerator: MasterRoc SA 167: 6 %
< W/C ratio: 0.42
< O
wner: Spanish government / ADIF
< Contractor: UTE Ontígola (ACCIONA-Obras Subterráneas)
< Construction period: 2008 - 2010
13.10.1. Description
The El Regajal tunnel (2’080 meters long), is part of the new line of the
high speed railway to the east of the country from Madrid. It is a very
important project for the Spanish government. Located in the south
of the Madrid province, this tunnel has been built to pass through an
important ecological area without creating any damage to the environ-
ment. The accelerator MasterRoc SA 167 and nano-silica MasterRoc
MS 685 met the requirements established for the jobsite. A thickness of
more than 20 cm was applied in several parts of the tunnel, and a total
of 40’000 m3 of sprayed concrete was applied.
267
< 24 hours: > 12 MPa
< 3 days: > 30 MPa
< Fck: 40 MPa
< C
oncrete supplier: own concrete plant
< Cement (CEM I 52,5 R/SR): 475 kg
< Aggregate (6/12mm): 320 kg
< Sand (0/4 mm): 1025 kg
< Sand (0/2 mm): 350 kg
< Water: 180 liters
< Fiber: MasterFiber 545: 6 kg
< Micro-silica: MasterRoc MS 685: 1,5% 7.1 kg (6.2 liters)
< Superplasticizer: MasterGlenium TC 1370 SK: 1.2% 5.7 kg (5.5 liters)
< Accelerator: MasterRoc SA 167: 6 %
< W/C ratio: 0.39
< O
wner: RFI (Rete Ferroviaria Italiana) Rome
< Designer: Italferr Rome
< Construction company: Pacchiosi (Rome)
< Construction period: 2008 - 2011
13.11.1. Description
268
13.11.2. Specifications / strength achievement
< C
ement: 500 kg (42.5R type A-LL)
< Aggregate: 540 kg (crushed sand 0/6)
< Water: 210 liters
< Superplasticizer: MasterGlenium SKY 624: 4.5 liters
< Accelerator: MasterRoc SA 167: 40 kg (8% cement content)
< W/C ratio: 0.42
< Slump:
ASIA-PACIFIC
< O
wner: Land Transport Authority, Singapore
< Construction period: 2007 – 2010
13.12.1. Description
C905 was located in the heart of the Singapore Business District adja-
cent to Marina Bay and consisted of 2.1 km of new metro tunnels for
both the Circle and Downtown lines. The sprayed concrete work includ-
ed one 90m and two stacked 30m by 7m diameter tunnels with a total
269
volume of 2550m3. The tunnels were constructed in traditional heading,
bench and invert with rounds of maximum 1m. Following completion
of the temporary lining, the tunnels were subsequently completed with
permanent precast concrete tunnel segments. Travel times from the
ready mixed concrete plant to site were dependent on traffic conditions.
Through the use of BASF ’s MasterGlenium T 803 and MasterRoc HCA,
the sprayed concrete workability was maintained at suitable levels for
application to be carried out while also ensuring the high compressive
strength requirements were met.
< C
oncrete Supplier: Pan-United Concrete Pte Ltd
< Cement: OPC – 490 kg
< Superplasticizer: MasterGlenium T 803 – 900 ml / 100 kg
< Hydration control: MasterRoc HCA: 0.45 – 0.65 %
< Accelerator: MasterRoc SA 160: 6 %
< W/C ratio: 0.4
< Slump: 200 +/– 25 mm
< Application thickness: 100 – 150 mm
< O
wner: Northern Railway
< Construction period: 2005 – 2011
13.13.1. Description
The Pirpanjal Railway Tunnel is India’s longest and Asia’s second long-
est railway tunnel. The 11 km long “Pir Panjal” tunnel between Banihal
and Qazigund is part of the 340 km long railway project in Jammu and
Kashmir, which will link the Valley with the rest of the country. The dis-
tance between Banihal and Qazigund will be reduced to about 16km
once the tunnel becomes operational. The rail link, declared a National
270
Project in 2002, will provide an all-weather means of transport in an area
which is snow-bound for a significant part of the year.
< C
oncrete Supplier: Site Mix
< Cement: 475 kg Ambuja 53 grade OPC
< Superplasticizer: MasterRheobuild SP1: 1.7% by weight of cement
< Accelerator: MasterRoc SA 160: 8 %
< W/C ratio: 0.39
< Application thickness: 150 – 160 mm
< Slump: 130 – 140 mm
< C
ontractor: Sinohydro Bureau No. 3
< Construction period: 2011 – 2013
13.14.1. Description
271
< 7 days: > 26 MPa
< 28 days: > 32 MPa (sprayed panel)
< C
ement: 430 kg
< Sand (0 - 5mm): 700 kg
< Aggregate (5 – 10mm): 850 kg
< Superplasticizer: PCE MasterRheoplus 26 R: 1.0%
< Accelerator: MasterRoc SA 160: 6 – 8% (weight of binder)
< W/C ratio: 0.43
< Slump: 15 – 18 cm (with open time of 2 hours)
< O
wner: Perilya Ltd.
13.15.1. Description
The Broken Hill ore body is «world class», having produced more than
200 million tonnes of ore over the 120 years since mining commenced
in 1885.
The mine produces two products, a zinc concentrate and a lead con-
centrate. Concentrates from Broken Hill are a premium coarse-grained
product, being of low complexity and containing a grade of about 50
per cent zinc in the zinc concentrate and 70 per cent lead in the lead
concentrate.
The Perilya Mine was the first mine in Australia to use MasterGlenium
SKY 8703 in their sprayed concrete mix. They identified superior slump
retention, compressive strength gain and the rheology of the sprayed
concrete to be the main indicators in changing from RHEOBUILD 1000
NT to MasterGlenium SKY 8703.
Perilya have recently commissioned a new batch plant and slick line for
their sprayed concrete operations.
272
13.15.3. Mix Design
< C
ement: ABCL HE: 450 kg
< Aggregate (7 mm): 445 kg
< Cracker Dust: 180 kg
< Sand: 1000 kg
< Water: 200 l
< Fiber: 6 kg
< Plasticizer: MasterPozzolith 370 C: 1680 ml
< Superplasticizer: MasterGlenium SKY 8703: 4000 ml
< Hydration control: MasterRoc HCA: 3000 ml
< Accelerator: MasterRoc SA 160: 4 – 8 %
< W/C ratio: 0.45
< Slump – slick line: 210 – 250 mm
< Surface mix: 180 – 220 mm
< O
wner: BHP Billiton
13.16.1. Description
< C
ement: ABCL GP: 470 kg
< Aggregate (7 – 10 mm): 314 kg
273
< Cracker Dust: 530 kg
< Sand: Clinton: 700 kg
< Fiber: 40 kg
< Plasticizer: MasterPozzolith 370 C: 2625 ml
< Hydration control: MasterRoc HCA: 1500 ml
< Superplasticizer: MasterRheobuild 1000 NT: 4000 ml
< Accelerator: MasterRoc SA 167: 4 %
< W/C ratio: 0.45
< Slump: 170 – 200 mm
NORTH AMERICA
< C
ontractor: Kiewit Construction
< Construction period: 2006 to 2010
13.17.1. Description
274
< 7 day first crack flexural strength: 4.83 MPa
< C
ement: 446 kg (sources varied, Type II/V)
< Aggregate (3/8): 477 kg (Vulcan)
< Sand: 1230 kg (Hanson)
< Superplasticizer: MasterRheobuild 1000: 2.9 l
< Hydration control: MasterRoc HCA: 443 ml
< Accelerator: MasterRoc SA 160: 6 %
< W/C ratio: 0.40
< Fiber: 5 kg EPC Shogun (later BC-54)
< Slump: 80 mm
< C
ontractor: Strabag
< Construction period: 2006 – 2012
13.18.1. Description
275
13.18.3. Mix Design
< B
inder: 20 %
< Micro-silica: 8 %
< ACI aggreagate gradation no. 2: 1’750 kg
< Superplasticizer: PS 1466: 2 – 3 kg
< Hydration control: MasterRoc HCA: 3 – 4 kg
< Accelerator: MasterRoc SA 160: 5 – 7 %
< W/B ratio: 0.40
< Slump: 200 mm+
< C
ontractor: S3 II (JF Shea, Schiavone and Skanska Joint Venture)
< Construction period: Mid 2008 to the end of 2009
13.19.1. Description
< C
ement: 350 kg (LaFarge Type I/II)
276
< Silica Fume: 23 kg
< #8 Stone: 465 kg (Tilcon)
< Sand: 812 kg (Roanoke)
< Water: 127 l
< Superplasticizer: MasterGlenium 7500: 2 kg
< Hydration control: MasterRoc HCA: 1.6 kg
< Accelerator: MasterRoc SA 160: 4 – 8 %
< W/C ratio:
< Slump: 203 mm
< C
ontractor: Engineering and Construction Innovations, Inc.
13.20.1. Description
The Soudan Mine was decommissioned in the 1960’s and has since
been used as a research facility for the University of Minnesota and as a
tourist attraction and park. Early in 2011 a fire occurred at the bottom of
the shaft which destroyed much of the old wood bracing that provided
ground support. The owner decided to “shotcrete” the area where
the fire occurred to provide new support of the ground. The sprayed
concrete was batched on surface using a volumetric mixer. It was then
pumped through a 51mm line down the 700m shaft to the point of place-
ment. To prevent segregation during pumping and the subsequent free
fall of the sprayed concrete down the vertical slick line, two 360 degree
loops were installed in the line to slow the drop. The remoteness of the
project and the difficult working conditions made this a challenging yet
interesting project.
< 2
8 day compressive strength specifications: 34 MPa
< High slump (250 mm) required for pumping purposes
< Need to maintain cohesion of the mix during the pumping process
< N
eed to be able to pump 2100 feet through a 5 cm slick line vertically
277
13.20.3. Mix Design
< C
ement: 398 kg
< Sand: 1123 kg
< V
iscosity modifier: RHEOMAC SF100: 23 kg, RHEOMAC UW 450:
1.1 liters
< Superplasticizer: MasterGlenium 7500: 2.1 liters
< Hydration control: MasterRoc HCA: 1.1 liters
< Accelerator: MasterRoc SA 160: 6 %
< W/C ratio: 0.42
< Slump: 250 mm
< C
ontractor: ICA and FCC (CONNET)
< Construction period: 2009 – 2012
13.21.1. Description
< C
ement: 340 kg (CPC 30R)
< Aggregate (3/8): 560 kg (basalt)
278
< Sand: 1020 kg (basalt)
< Fiber: 35 kg (Macaferri, metalic)
< Water reducer: MasterPolyheed 746: 8cc per kg of cement
< H
ydration control: MasterRoc HCA: 4cc per kg of cement
SOUTH AMERICA
< C
ontractor: Dragados
< Construction period: 2009 - 2011
13.22.1. Description
The government of the city of Buenos Aires extends its metro network
yearly. The extension of Line A was done by the Spanish contractor
Dragados who decided to work with BASF, due to the company’s expe-
rience in Argentina on these types of projects. A total of 60’000 m3 of
sprayed concrete was used for this single shell tunnel lining.
< C
ement type I: 400 kg
< Fine sand: 542 kg
< Crushed sand: 684 kg
< Aggregate (coarse, max 12 mm): 400 kg
< Water: 178 liters
< Plasticizer: MasterGlenium TC 1301: 0.88 kg
< Superplasticizer: 1.6 kg
279
< Hydration control: MasterRoc HCA 29: 1.8 kg
< Accelerator: MasterRoc SA 160: 6%
< First layer: 10 – 15 cm
< Final lining: 30 – 100 cm
< Rebound: +/- 10 %
< Slump: > 20 cm
< C
ontractor: Odebrecht
< Construction period: 2009 – 2012
13.23.1. Description
< C
ement: 475 kg (CEM II/A-V 42.5 R)
< Micro-silica: 40 kg
< Aggregate (0–10 mm): 1650 kg
< Water reducer: MasterPolyheed 248: 11 cc per kg of cement
< Plasticizer: MasterPozzolith 2237R: 2 cc per kg cement
< Accelerator: MasterRoc SA 160: 7 %
< W/(C+S) binder ratio: 0.36
< Slump: > 200 mm
280
13.24. Metro Line 4, Santiago, Chile
< C
ontractors: Vial & Vives, Tecsa, Ferrovial, Besalco, Sacyr
< Construction period: 2004 - 2006
13.24.1. Description
< C
ement: 400 kg (CEM II/A-V 42.5 R)
< Aggregate (0–10 mm): 1600 kg
< Viscosity modifier: RHEOMAC SF 100: 30 kg
< Superplasticizer: MasterGlenium TC 1303: 3.7 – 5.4 kg
< Hydration control: MasterRoc HCA 29: 2 kg
< Accelerator: MasterRoc SA 160: 7 %
< W/B ratio: 0.46
< Rebound: < 5 %
< Slump: 150 – 200 mm
< C
ontractors: Unicon, Robocon
281
13.25.1. Description
< C
ement: 360 kg (CEM II/A-V 42.5 R)
< Lime filler: 40 kg
< Aggregate (0–10 mm): 1590 kg
< Superplasticizer: MasterGlenium 1300: 4 kg
< Hydration control: MasterRoc HCA 29: 2 kg
< Accelerator: MasterRoc SA 160: 5 %
< W/(C+S) binder ratio: 0.45
< Thickness applied: > 50 mm
< Rebound: < 5 %
< Slump: 15 – 20 cm
< O
wner: Isagen
< Construction period: 2010 – 2012
13.26.1. Description
This large scale power plant is located at the Amoya River in the central
Colombian region of Tolima, and with an annual output of 510 gigawatt
hours it is estimated to become the most profitable hydropower project
282
in the history of the country. The Amoya River hydropower project is
divided into three main segments: the retaining section is composed
of a dam as well as a sand trap and a gravel trap. The tunnel section
comprises an 8.5 km long intake tunnel and an outlet tunnel of about 2.8
km in length. The third section, the machine room, houses two turbines
with about 40 kilowatts each.
< C
oncrete Supplier: own concrete plants
< Cement: 465 kg (OPC)
< Superplasticizer: MasterGlenium C355: 4.42 liters
< Plasticizer: MasterPolyheed 710: 0.4 – 0.8 %
< Accelerator: MasterRoc SA 160: 6 %
< W/C ratio: 0.45
< Slump: 200 +/– 25 mm
< Application thickness: 100 – 150 mm
283
14. BIBLIOGRAPHY
[1]
Cement – part 1: Composition, specifications and conformity criteria
for common cement, DIN EN 197-1:2011-11, 2011.
[6] J. Stark, Zement und Kalk, Basel, Switzerland: Birkhäuser Verlag,
2000.
[11] J.J. Thomas, H.M Jennings, J.J. Chen, “Influence of nucleation see-
ding on the hydration mechanisms of tricalcium silicate and cement,” J.
Phys. Chem. C 113 (11), pp. 4327-4334, 2009.
284
[13] Q. Xu et al, “Set acceleration and early strength development control for
sprayed concrete applications, Final Report of Project EBA410026/A-
075-I,” BASF Construction Chemicals, Zürich, 2008.
[14] Q. Xu, J. Stark, “Effect of an alkaline shotcrete accelerator on the hydra-
tion of cement pastes,” Advances in Cement Research, vol. 17, No. 1,
pp. 1-8, 2005.
[15] Q. Xu, J. Stark, “A model of early cement hydration with an alkaline
setting accelerator,” Cement International, vol. 3, No. 4, pp. 92-105,
2005.
[17] Q. Xu, J. Stark, “Qualification of cement hydration when using an alkali-
free setting accelerator,” Zement-Kalk-Gips, vol. 58, No. 10, pp. 68-79,
2005.
[19] Q. Xu, “Sprayed Concrete: Alkali Free Set Accelerating Admixtures,” in
16. Internationale Baustofftagung (IBAUSIL), Weimar, 2006, pp. 735-
742.
[20] Q. Xu, “Alkali Free Set Accelerating Admixtures for Sprayed Concrete
Application,” in 12th International Congress of the Chemistry of Cement,
Montreal, 2007.
[21] Q. Xu, J. Stark, “The chemical action of Al(OH)3 accelerators on the
early hydration of Portland cements,” Zement-Kalk-Gips, vol. 61, No. 3,
pp. 01-11, 2007.
[22] Q. Xu, A. Walliser, “Setting and strength control for sprayed concrete
applications” presented at the 3rd Innovation Days BASF EB, Trostberg,
Germany, 21-22 Oct. 2008.
285
[23] Q. Xu, “Chemical Effect of Set Accelerators on Early Cement Hydration,”
presented at the European Cement Research Academy Seminar –
cement and admixtures, Düsseldorf, Germany, Apr. 2009.
[24] http://www.understanding-cement.com/manufacturing.html
[25] http://www.inlandcanada.com/NR/exeres/3E7E96B8-1DF4-4F8D-
A5CA-0FC35A4BDBD5.htm
[26] http://www.cmu.edu/architecture/research/cbpd/absic-cbpd.html
[27] http://www.cement.org/tech/cct_mixing_water.asp.
[29]
EFNARC Sprayed Concrete Technical Committee, European
Specification for Sprayed Concrete, EFNARC, 1996.
[32]
Sprayed concrete – Part 1: Definitions, specifications and conformity,
EN 14487-1, Nov. 2005.
[34]
Testing sprayed concrete – Part 3: Flexural strengths (first peak, ulti-
mate and residual) of fibre reinforced beam specimens, EN 14488-3,
Apr. 2006.
[35]
Testing sprayed concrete – Part 5: Determination of energy absorp-
tion capacity of fibre reinforced slab specimens, EN 14488-5, Apr.
2006.
[36] M. Karakus, R.J. Fowell, “An insight into the New Austrian Tunneling
286
Method (NATM),” in 7th Regional Rock Mechanics Symposium, Sivas,
Turkey, 2004.
[39]
M ixing water for concrete. Specification for sampling, testing and
assessing the suitability of water, including water recovered from pro-
cesses in the concrete industry, as mixing water for concrete, EN
1008:2002, Oct. 2002.
[40] http://www.cmu.edu/architecture/research/cbpd/absic-cbpd.html
[43] H.F.W. Taylor, Cement Chemistry, 2nd Edition, Thomas Telford, 1997.
287
[48] W. Lukas, “Anforderungen an den Spritzbeton,” Schriftenreihe des
Österreichischen Betonvereins, no. 35, 1998.
[52] http://www.concrete.net.au
[53] The British Tunnel Society and Institution of Civil Engineers, Tunnel
Lining Design Guide, London, United Kingdom: Thomas Telford Ltd.,
2004.
[54] F. Papworth, “Design guidelines for the use of fibre reinforced shotcrete
in ground support,” in Proc. of Our World in Concrete and Structures,
Singapore, Singapore, 2002.
[55] W. Aldrian, P. Schubert, “Wet against dry systems – a dynamic develop-
ment in German speaking countries,” in Proc. of the Third International
Symposium on Sprayed Concrete, Gol, Norway, 1999.
288
289
290
291
292
Master Builders Solutions from
BASF for the Construction Industry
MasterAir MasterInject MasterSeal
Complete solutions for Solutions for concrete injection Solutions for waterproofing
air-entrained concrete and sealing
MasterKure
MasterBrace Solutions for concrete curing MasterRoc
Solutions for concrete strengthening Solutions for underground
MasterLife
construction
MasterCast Solutions for enhanced durability
Solutions for the manufactured MasterSet
MasterMatrix Solutions for retardation control
concrete product industry
Advanced rheology control solutions
MasterCem for self-consolidating concrete MasterSure
Solutions for cement manufacture Solutions for workability control
MasterPel
MasterEmaco Solutions for watertight concrete MasterTop
Solutions for concrete repair Solutions for industrial and
MasterPolyheed
commercial floors
MasterFinish Solutions for high-performance
Solutions for formwork treatment concrete Master X-Seed
Advanced accelerator solutions for
MasterFlow MasterPozzolith
pre-cast concrete
Solutions for precision grouting Solutions for water-reduced
concrete Ucrete
MasterFiber Flooring solutions for harsh
Comprehensive solutions for MasterProtect
environments
fiber-reonforced concrete Solutions for concrete protection
MasterGlenium MasterRheobuild
Solution for hyperplasticized Solutions for superplasticized
concrete concrete
Headquarters
BASF SE BASF Construction Chemicals BASF Australia Ltd
Underground Construction 23700 Chagrin Boulevard 11 Stanton Road
Salzachstrasse 2-12 Beachwood, OH 44122, USA Seven Hills NSW 2147, Australia
68199 Mannheim, Germany Phone +1-216-839 7500 Phone +61 2 8811 4200
Phone +49 621 60 91013 Fax +1-216-839 8821 Fax +61 2 8811 3299
E-mail [email protected] E-mail [email protected]
BASF Construction Chemicals UAE LLC BASF SA BASF Construction Chemicals Asia Pacific
P.O. Box 37127 Avenida das Nações Unidas, 33 Tuas Avenue 11
Dubai Investment Park 14.171, Morumbi Singapore 639090
Al Hibab Road, Jebel Ali 04794-000 São Paulo – SP, Brazil Phone +65 6861 6766
Dubai, United Arab Emirates Phone +55 11 2718 5507 E-mail [email protected]
Phone +971 4 8090800 E-mail [email protected]