A proper IT set-up is essential for a successful competition. Please read & follow carefully!
• This document needs to be forwarded to the responsible persons and companies in charge of
fulfilment. The experts in each field need to have these requirements as soon as possible.
• Every detail is important. If a specification cannot be fulfilled entirely or certain items cannot be
delivered as described: please communicate this beforehand with the IJF IT department. All
changes need approval.
• The installation time and effort are easily underestimated. Finishing the set-up late in the night
before start of competition is risky. All needs to be properly tested.
Set the right priorities!
• If there are any questions, please don’t hesitate to contact
IJF IT department: [email protected]
Introduction
Before and after the event: the equipment needs to be stored and
locked in a safe room in the venue
Accreditation cards
need to be printed, cut
and laminated.
Everything needs to be
ready the day before
the start of
accreditation at the Print all front cards on Turn all Cut all papers two times,
Don’t attach
latest A4 paper (210 x 297 papers and horizontal and vertical in Laminate with
Punch hole(s) lanyards. This
mm) with PDF settings print the middle. All white A6 pouches
for lanyard will be done
„custom scale: 100%“ backsides on borders should have (154x111 mm)
later
(no „fit“ or „shrink“) the back same size
Accreditation Setup
Laminating
machines
Copy
Paper cutter
machine
Hole puncher
R
Lanyards
Checklist
Color laser printer:
Laminating 2 £
• 20 ppm or faster
pouches
• network connection
Complete set of toner
2 £
Copy machine
1 £
Laminating machines
Wireless Color laser Additional Paper 2 £
Internet Paper cutter
printer toner 2 £
Hole puncher
2 £
Paper A4
£
Laminating pouches
Exact size: 154x111 mm £
The room needs to be set-up the evening before the start of accreditation. Lanyards
This includes delivery of all equipment plus the printed and laminated accreditation £
cards 5 Multi-outlet power
£
strips
Wireless Internet
Network IP addresses from printers need to be set manually to 192.168.2.8 and 192.168.2.9 £
The same printers (plus toners) need to be taken afterwards to the draw and then to the venue
Checklist R
Projector
1 Projector (HDMI input, £
3000 ANSI Lumen or more)
LCD Screens Table microphones
2 LCD screens* (50“, HDMI) £
Wireless microphones
1 HDMI switcher (3x in, 1x £
out, seamless switching)
Audio 1
Internet by cable: mixer
HDMI splitter (1x in, 3x out) £
HDMI splitter
dedicated 10 Mbit/s 6 Cabled microphones £
Wireless up- and download
2 Wireless microphones £
internet HDMI cables 1 Audio mixer (+cables) £
XLR Speakers (+cables) £
3 Audio cables £
3 Ground loop isolators £
(for audio signal from laptops)
Printers from IJF Laptops HDMI switcher IJF Streaming HDMI cables £
accreditation Internet wireless £
headphone stereo jacks 3.5 mm from laptops to audio mixer
Internet by cable
(10 Mbit/s up- and download)
£
2 Copy machines £
3.50 m
(50 ppm or faster,
with sorting function)
The same printers (plus toners) must then be taken to the venue Speakers
Power
The electricity planning for the whole event must be done by experts
using professional power distribution equipment. No line is allowed
to come from a simple wall plug!
6x Uninterruptible Power
6x
Supplies (UPS):
• Min. power each UPS: 980 Watts / Simulated
1440 VA sine wave
Pure sine wave
Square
• Waveform Type:
wave
pure Sine wave
Power Plan
= UPS
Laptops
Laptops Equipment
Expert
6x local IP 192.168.2.x
Location x
9x IJF Server 3
Scoreboard 11, 12, 13,...
12x Judogi control 21, 22, 23,...
Warm-up 31, 32, 33,...
Hardware Requirements:
• Up-to-date model
• For scoreboards: Operating System Requirements:
o 8 GB RAM • MS Windows 10 Professional
o Resolution 1920x1080 • English language version and keyboard
• 200 GB disk space free • Clean installation
• Network input
• No login password
• HDMI output
• Windows firewall: file and printer sharing exception enabled
• Mouse • No security suite/Antivirus software/3rd party firewall installed
• Screensaver/power saver disabled
• Reduced screen brightness on battery
Monitors
14x
HDMI input
Local Network
SW4
SW3
SW5
SW2
Two cables
(main+backup) needed
from main switch to OB
van. Additional switch
needed to boost signal
if distance too long
SW1
Local Network
Network switches ☐
SW1 Main local switch (24 port) þ
SW2 Middle-mat local switch (8 port) ☐
SW3 Judogi-control local switch (8 port) ☐
SW4 Warm-up area local switch (8 port) ☐
SW5 Optional: TV-graphics local switch (4 port) ☐
Order of cabeling ☐
1 Cable from main local switch to IJF streaming studio place ☐
☐
Judogi control
2 Cables from main local switch to scoreboard laptops mat 1, 2, 3, … IJF streaming
Internet Network
SW9
SW7
IJF main
internet router
SW12
SW8
SW11
All Internet connections need to be wired. Additionally, IJF will create own wireless network
Internet Network
Order of cabeling ☐
11 Cable from main internet switch to middle-mat internet switch ☐
12 Cables from middle-mat internet switch to speakers place ☐ Middle mat
13 Cable from middle-mat switch to event control place ☐ IJF TV team
14 Cable from middle-mat internet switch to staff internet switches ☐
15 Six cables from each staff internet switches to nearby IJF staff places ☐ Judogi control
16 Cable from main internet switch to IJF TV team place ☐ ITV graphics
16 Cable from main internet switch to TV graphics in OB van ☐
18 Cable from main internet switch to judogi-control area ☐
19 Cables from judogi control internet switch to warm-up place (TBC) ☐ Key points:
• Whenever a cable is ready:
o Label with target location
o Ping test
For main internet line do not use IP 192.168.2.x as it is reserved for • No broken clips
the local network!
Scoreboard Setup
LED board
controller
Checklist R
1 LED screen 55“ or bigger £
16:9, HDMI input
MS Windows 10 required! 1 LED board controller £
Splitter
1 converter HDMI to LED £
backup speaker
board input (if needed)
1 HDMI Splitter £
(1x in, 2x out)
1 Laptop £
1 Scoreboard keyboard £
IJF USB DI box, HDMI cables £
Peavey USB-P 1 Big active speaker £
venue speaker XLR audio cables (from £
laptop to backup speaker
Connection from laptop via HDMI out and venue mixer)
LED pannels scoreboard: >200 vertical pixel per meter recommended (min. 96 pixel/meter)
Scoreboard operators
2x
4x
6x
8x
Checklist R
Venue speaker system £
IJF USB DI box, Professional audio £
Peavey USB-P mixer, connected to
venue speaker system
Active speakers with £
amplifier each tatami
XLR cables £
1 Jack connector (¼ Inch) £
Check carefully for ground loop hum and buzzing noises!
Video cabeling
Checklist R
HD-SDI cables BNC HD-SDI video cables £
(RG59, 75 ohm) with BNC
connectors
HD-SDI distributors £
HD-SDI repeater / £
optical fibre converters
HD-SDI test monitor £
Reserve: HD-SDI BNC £
cable role 100-200 m,
BNC connectors &
Use high quality HD-SDI cables (RG59, 75 ohm) crimping tools
Use HD-SDI repeater or BNC <-> optical fibre for long distances!
Video cabeling
PGM PGM
Mat 1 Mat 2 Mat 3 Opposite
dirty clean
front front front
Video cabeling
6x 8x
8x 12x
6x 12x
8x 16x
Streaming Studiov
2.85 m
(from podium)
2.00 m
Frame construction
for IJF green screen
Audio venue
Local network
Stairs Internet
Video signals
Checklist TV R
1 Commentator box £ Checklist R
with intercom 1 Podium (with carpet)
2
£
5.00 m
Headsets £ and stairs
1 Frame construction £
Video signals in £ Turnable
HD-SDI with audio office chairs x Tables like in plan £
embedded: (number depends on
size) with table cloths
• Front cameras
3 Turnable office chairs £
each mat
0.80 m
• PGM dirty 2 Normal chairs £
• PGM clean 1 Barrier
5.00 m £
Information system
Referee Draw Contest order Coach Assistant Live TV from each mat
Only needed for countries where the IJF radios are not allowed to use!
7x
14x
21x
+ +
28x
Checklist R
Radios £
Security headset £
Charger £
Each tatami needs it’s own frequency!
After competition
After the competition is finished our teams still need time to finalise the work
(interviews, video highlight editing, news uploading etc.)
Therefore, it is essential that electricity, internet and lights are kept on and intact until the last working
person from IJF gives green light that it is no longer needed.
Important: Please inform all persons and companies involved in the dismantling on the last day!
Have the save storage room ready for all IJF IT equipment cases!
Make sure you have agreed with the logistic company the pick-up time of the IJF IT equipment!