Duration is amount of time that elapses between the time the task is started and the time it is completed.
Duration is measured in hours (or days, weeks, etc.) It does not take into account the number of people performing the task
http://www.stellman-greene.com
Overhead is any effort that does not go to the core activities of the task but is still required in order for the people to perform it a sort of real world cost of actually doing the work.
Two people performing a task will require more effort than one person doing the same task Assigning two people to the task requires more effort, but the task has a shorter duration
http://www.stellman-greene.com
http://www.stellman-greene.com
http://www.stellman-greene.com
http://www.stellman-greene.com
http://www.stellman-greene.com
http://www.stellman-greene.com
http://www.stellman-greene.com
10
http://www.stellman-greene.com
11
http://www.stellman-greene.com
12
Project metrics
The baseline is the version of the schedule that has been approved
The schedule will change based on the actual work done by the project team. When the deadline of the revised schedule is later than that of the baseline, the project has slipped.
Variance is the difference between the estimated effort in the baseline and the actual effort performed by the team.
http://www.stellman-greene.com 13 Andrew Stellman & Jennifer Greene
Project metrics
Earned value management tracks the project by considering effort earned against a budget only after it has actually been performed
The budgeted cost for work scheduled (BCWS) is the estimated effort of the actual tasks that appear on the schedule to date. The actual cost of work performed (ACWP) is the effort spent on the tasks in the schedule that have actually been completed by the development team members. Variance = BCWS ACWP
http://www.stellman-greene.com 14 Andrew Stellman & Jennifer Greene
Project metrics
The cost performance index is used to compare projects with each other or to compare phases within a project
CPI is calculated by dividing BCWS / ACWP (budgeted cost for work scheduled/actual cost for work performed) and multiplying by 100 to express it as a percentage. A CPI of 100% means that the estimated cost was exactly right and the project came in exactly on budget. A CPI under 100%, the work cost less effort than planned; a CPI greater than 100% means that the estimate was not adequate for the work involved.
For example, if the programming tasks took twice as long as estimated but every other type of task in the project took less time than estimated, the total variance for the project might still be low. However, the problem can still be pinpointed by calculating the CPI for each phase of development.
http://www.stellman-greene.com