0% found this document useful (0 votes)
39 views

04 Project Schedules

The document discusses key concepts for project scheduling including defining a project schedule, estimating effort vs duration, identifying slack and overhead, building a schedule by allocating resources and identifying dependencies, optimizing the schedule, and using metrics like variance and cost performance index to track progress. It explains that a project schedule links tasks to resources, and must be based on estimates and a work breakdown structure. Key steps in building a schedule are allocating resources, identifying task dependencies, creating a Gantt chart, reconciling the schedule with project needs, and optimizing the critical path and resource allocation.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
39 views

04 Project Schedules

The document discusses key concepts for project scheduling including defining a project schedule, estimating effort vs duration, identifying slack and overhead, building a schedule by allocating resources and identifying dependencies, optimizing the schedule, and using metrics like variance and cost performance index to track progress. It explains that a project schedule links tasks to resources, and must be based on estimates and a work breakdown structure. Key steps in building a schedule are allocating resources, identifying task dependencies, creating a Gantt chart, reconciling the schedule with project needs, and optimizing the critical path and resource allocation.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 15

Applied Software Project Management

Applied Software Project Management


Project Schedules

http://www.stellman-greene.com

Andrew Stellman & Jennifer Greene

Applied Software Project Management

What is a project schedule?


The project schedule is a calendar that links the tasks to be done with the resources that will do them.
Before a project schedule can be created, the project manager must have a work breakdown structure (WBS) and estimates. The schedule is part of the project plan.

http://www.stellman-greene.com

Andrew Stellman & Jennifer Greene

Applied Software Project Management

Scheduling concepts: Effort vs. Duration


Effort represents the work required to perform a task.
Effort is measured in person-hours (or person-days, personweeks, etc.) It represents the total number of hours that each person spent working on the task.

Duration is amount of time that elapses between the time the task is started and the time it is completed.
Duration is measured in hours (or days, weeks, etc.) It does not take into account the number of people performing the task

http://www.stellman-greene.com

Andrew Stellman & Jennifer Greene

Applied Software Project Management

Scheduling concepts: Slack and Overhead


Slack is the amount of time which any of the tasks can be delayed without causing the due date of the final task in the sequence to be delayed as well.
A tight schedule has very little slack; a delay in any task will cause a delay in the due date Parkinsons Law: Work expands so as to fill the time available for its completion.

Overhead is any effort that does not go to the core activities of the task but is still required in order for the people to perform it a sort of real world cost of actually doing the work.
Two people performing a task will require more effort than one person doing the same task Assigning two people to the task requires more effort, but the task has a shorter duration

http://www.stellman-greene.com

Andrew Stellman & Jennifer Greene

Applied Software Project Management

Building the project schedule


Allocate resources
For each task in the WBS, one or more resources must be assigned Choose person or people for each task based on qualifications, familiarity and availability Take overhead into account when calculating the duration of each task

http://www.stellman-greene.com

Andrew Stellman & Jennifer Greene

Applied Software Project Management

Building the project schedule


Identify dependencies
A task has a dependency if it involves an activity, resource or work product which is subsequently required by another task Tasks may have dependencies because they require the same resource

http://www.stellman-greene.com

Andrew Stellman & Jennifer Greene

Applied Software Project Management

Building the project schedule


Identify dependencies (continued)
Every dependency has a predecessor, or a task that must be begun, in progress, or completed, for another task to begin Identify the type of predecessor for each dependency

http://www.stellman-greene.com

Andrew Stellman & Jennifer Greene

Applied Software Project Management

Building the project schedule


Create the schedule
Most project schedules are represented using a Gantt chart The Gantt chart shows tasks, dependencies and milestones using different shapes

http://www.stellman-greene.com

Andrew Stellman & Jennifer Greene

Applied Software Project Management

Building the project schedule


Reconcile the schedule with the organizations needs
Once resources are allocated to each task, a final date can be calculated If this date is unacceptable, the project plan must change Either additional resources must be allocated to the project or the scope must be cut down Brooks Law: Nine women cannot have a baby in one month.
In other words, some tasks can only be done by one person, no matter how critical they are.

http://www.stellman-greene.com

Andrew Stellman & Jennifer Greene

Applied Software Project Management

Building the project schedule


Add review meetings to the schedule
Progress reviews are meetings held regularly to check the progress of a project versus it's scheduled progress. Milestone reviews are meetings which the project manager schedules in advance to coincide with project events.
The most common way for project managers to handle milestone reviews is to schedule them to occur after the last task in a project phase (such as the end of design or programming).

http://www.stellman-greene.com

10

Andrew Stellman & Jennifer Greene

Applied Software Project Management

Building the project schedule


Step 4: Optimize the schedule
The critical path is the sequence of tasks that represent the minimum time required to complete the project.
If a task is only on the critical path when delaying that task will delay the project. Allocating resources to tasks on the critical path will reduce the project schedule; allocating them to other tasks will have less effect.

A resource is over-allocated if more than 100% allocated to multiple tasks simultaneously


If any resource is over-allocated, it means that there is a dependency between two tasks which was not discovered. When this happens, the schedule is guaranteed to be inaccurate. Find and fix over-allocated resources.

http://www.stellman-greene.com

11

Andrew Stellman & Jennifer Greene

Applied Software Project Management

Dont abuse buffers


A buffer is a task added to the schedule with no specific purpose except to account for unexpected delays.
This practice involves either adding extra tasks or padding existing tasks at strategic points in the schedule where overruns are expected. Buffers can be useful:
On a year-long project, every programmer will take two weeks of vacation Buffers can be used to account for this known delay

Buffers are often abused


The idea that overruns are expected means that there is an implicit assumption that the estimate is incorrect. Buffers should not be used to add time to compensate for an inaccurate estimate.

http://www.stellman-greene.com

12

Andrew Stellman & Jennifer Greene

Applied Software Project Management

Project metrics
The baseline is the version of the schedule that has been approved
The schedule will change based on the actual work done by the project team. When the deadline of the revised schedule is later than that of the baseline, the project has slipped.

Variance is the difference between the estimated effort in the baseline and the actual effort performed by the team.
http://www.stellman-greene.com 13 Andrew Stellman & Jennifer Greene

Applied Software Project Management

Project metrics
Earned value management tracks the project by considering effort earned against a budget only after it has actually been performed
The budgeted cost for work scheduled (BCWS) is the estimated effort of the actual tasks that appear on the schedule to date. The actual cost of work performed (ACWP) is the effort spent on the tasks in the schedule that have actually been completed by the development team members. Variance = BCWS ACWP
http://www.stellman-greene.com 14 Andrew Stellman & Jennifer Greene

Applied Software Project Management

Project metrics
The cost performance index is used to compare projects with each other or to compare phases within a project
CPI is calculated by dividing BCWS / ACWP (budgeted cost for work scheduled/actual cost for work performed) and multiplying by 100 to express it as a percentage. A CPI of 100% means that the estimated cost was exactly right and the project came in exactly on budget. A CPI under 100%, the work cost less effort than planned; a CPI greater than 100% means that the estimate was not adequate for the work involved.
For example, if the programming tasks took twice as long as estimated but every other type of task in the project took less time than estimated, the total variance for the project might still be low. However, the problem can still be pinpointed by calculating the CPI for each phase of development.

http://www.stellman-greene.com

15

Andrew Stellman & Jennifer Greene