Geomining Guide GB
Geomining Guide GB
G E O M I N I N G G U I D E
Table of contents
• 1 - Introduction 1
• 3 - Reserves Estimation 19
• 4 - Mining Plans 27
• 5 - Mining Operations 37
• Appendixes
I - Chemical Analysis 67
III - Variograms 73
IV - Safety Rules 83
V - Rehabilitation Guidelines 97
G E O M I N I N G G U I D E
Introduction
he main objective of the Geomining Guide is to share
G E O M I N I N G G U I D E
Acknowledgment
The CKHC wishes to express its thanks to all the participants
who have helped with the preparation of the Geomining
Guide, in particular M. Niyazi Gundogdu and Jean-Guy Levaque.
G E O M I N I N G G U I D E
Characterization
Exploration &
Exploration
&
Characterization
G E O M I N I N G G U I D E
Exploration and Characterization
Exploration
• All exploration work must be done at the beginning of a project in
order to get a proper regional picture.
• Exploration expenses must be considered as a capital investment.
➔ Exploration is done to ensure the long term viability of a cement
operation. So, a drilling program, designed for the long term, should be
capitalized over this long term period.
➔ Exploration expenses will then be amortized and spread out over a
longer period.
• The second step, which might not be necessary in all cases, consists of
the following actions:
➔ Geological mapping
➔ Surface sampling along the stratigraphical sections
➔ Drilling if needed and when possible
➔ Analysis and preliminary raw mix composition
➔ Estimation of potential reserves.
G E O M I N I N G G U I D E
Exploration and Characterization
Local Scale Exploration
• The following documents must be obtained before any new
exploration program, which is required prior to any new quarry
opening.
➔ Exploration permit
➔ Topographic map with different property ownership, permits and
infrastructures (precision of 1/2000)
➔ Geological map larger than the property limits (precision of 1/2000)
➔ When no regulations exist, the following constraints should be used to
establish a drilling plan:
❿ Buffer zone of 100 m or larger if stated by regulation
❿ Hydrological map
❿ Structural map
❿ Environmental restrictions
❿ Overburden and waste evaluation.
G E O M I N I N G G U I D E
Exploration and Characterization
Topography
• For topographic surveys, the recommended method is an aerial
survey:
➔ Use the standardized UTM (Universal Transverse Mercator) System.
Geophysics
• Geophysics is used:
➔ When there is a need to forecast disruptive structures (fault, karsts, filled
or open cavities)
➔ And in order to avoid high drilling cost in some cases (thick overburden).
• Results may be deceiving in some cases.
• Pros and cons of different methods:
➔ Seismic: good for thick overburden, but costly and difficult to calibrate.
➔ Electromagnetics: good for structural anomalies, low cost but can be
erratic.
➔ Resistivity: more precise but costly.
G E O M I N I N G G U I D E
Exploration and Characterization
Drilling Plan
• Each deposit is unique and standards are therefore difficult to
define.
Drilling Plan
• When there is sufficient information, two cases may occur:
➔ Simple Geology
❿ Sub-horizontal bedding, constant thickness of beds, relatively constant
geochemistry.
➔ Complex Geology
❿ Inclined, folded, faulted bedding, highly variable geochemistry.
• For simple geology, normally there is no need for a regular grid. The
drilling plan should be designed for the necessary structural and
geochemical information about the deposit to be obtained.
G E O M I N I N G G U I D E
Exploration and Characterization
Drilling Plan
• For complex geology, a regular grid is necessary (ex. 100 x 100m).
➔ A regular grid makes it easier to assess the variability and, by reducing the tolerance
angle, gives more credibility to the calculation of variograms.
➔ 5 supplementary drill holes at short distances (e.g. 50 m) would allow the short
horizontal scale of variability to be assessed.
➔ The interpretation of the variogram will show either that the exploration grid is
sufficient for exploitation or that a closer spaced grid is required.
➔ It is a sound practice to establish a small scale grid size within the major directions of
the main grid.
➔ For sub-vertical lithologies, the inclined drilling with a denser grid is necessary to
obtain representative data.
➔ For sub-vertical deposits, a thickness equivalent to the height of the three benches
(30 – 50 m) should be drilled.
Drilling Methods
• Diamond Drill (DDH):
➔ Is the only method to be used for the characterization of a deposit.
➔ Is expensive but provides invaluable information.
➔ Allows better recovery and proper samples for humidity testing.
➔ For holes longer than 15 m, wire line equipment should be used.
➔ Size NQ (4.76 cm) is required; this makes hydrological surveys, physical testing and
hole reduction, core storage and core manipulation easier.
➔ Larger size (10 cm) is necessary to obtain good recovery rates in the
limestone-clay intercalation and in the unconsolidated lithologies.
G E O M I N I N G G U I D E
Exploration and Characterization
Drilling Methods
• Percussion
➔ Blast holes:
❿ Can not be used for modeling.
❿ Can be used to update the short term mining plan.
❿ Vertical blast holes are not representative in vertical formations.
➔ Air Track:
❿ Overburden and waste definition (additional drilling over crests
and valleys).
❿ Testing of the geological model.
❿ Sampling of clay material from karsts.
❿ Drilling in unconsolidated material.
Drilling Methods
• Sampling with destructive drilling methods must be conducted with
great care:
➔ Adapt a sampling device or an automatic sampler
➔ Once a certain depth has been reached
❿ STOP drilling
❿ CLEAN hole with air by moving the rods up and down
❿ MAKE sure that all the cuttings from an upper level reach
the surface in order to avoid contamination
❿ RECOVER all the fines.
G E O M I N I N G G U I D E
Exploration and Characterization
Diamond Drilling Contract Items
• Location
• Type of drilling (Diamond Drill, Rotary, Reverse Circulation, diameter,
etc.)
• Approximate length (total and each drilling +%xx)
• Type of drill machine required
• Inclination measurements
• Diameter of cores versus depth of formation
• Core recovery: 100% unless justified by geology (What to do if less?)
• Type of core boxes (Who shall provide and transport them?)
• Core logging, splitting and photography of core boxes (cores, hole
number and core length)
G E O M I N I N G G U I D E
Exploration and Characterization
Diamond Drilling Contract Items
• Cost:
➔ For overburden, waste and ore (cost/m for different lengths)
➔ For inclination test in case of inclined drilling
➔ For loss of equipment.
• Special Clauses:
➔ Tests: Costs can be saved by combining hydrological tests with drilling like
pumping tests, installation of piezometer, which can be provided by the
drilling company.
➔ Down-the-hole Surveying Equipment: In some cases (karstic ground or
long inclined holes), down-the-hole surveying equipment should be
provided by the drilling company (inclinometer, camera, acid test).
➔ Cementation: In some cases, it can be useful to fill a cavity with cement
in order to drill deeper.
10
Core Logging
• Has to be performed by a geologist on clean cores.
G E O M I N I N G G U I D E
Exploration and Characterization
Core Sampling
• The geologist should define the sampling intervals based on the
logging in order to isolate lithologic units.
11
Core Sampling
• In special cases (e.g. large clay or quartz veins to be separated from
the limestone bed…), sampling may correspond to the second level.
• When a vein or veinlets are at a low angle with the core axis, the
geologist must take half of the vein or veinlets in the split sample in
order to obtain a representative sample.
• The use of a sampling tag system, where all the samples are
indicated, is strongly recommended.
G E O M I N I N G G U I D E
Exploration and Characterization
Core Sampling
0,0
2,0 OVB
4,0
Sample# 1: 3.0 m
6,0
22,0
Sample# 10: 2.0 m
24,0
12
Core Sampling
• Once the sampling intervals are defined and core splitting is done,
one half of the core is kept in the original core box and the other
half is used for analysis.
➔ Core splitter:
❿ Can be expensive (1 000 to 4 000 USD)
❿ Faster to split
❿ Sometimes difficult to produce half core.
➔ Saw:
❿ Variable in price (about 200 USD if using a hand electrical saw)
❿ Longer time to split
❿ Requires a fixed installation with water.
G E O M I N I N G G U I D E
Exploration and Characterization
Sample Preparation
• Crush (Jaw Crusher) the split core samples at 100% passing a Nº 4
sieve (1/4’’ or 6.35 mm).
• Split the crushed sample to obtain 400 grams.
• Keep the rest for other tests or analysis (grindability, burnability…).
• Dry overnight:
➔ 110°C for normal samples
➔ 45°C for samples containing gypsum and samples to be analyzed for SO3
related to sulfides
➔ No drying for samples containing hydrocarbons.
• Grind the sample down to 100 µm with disk pulverizer.
• Split into two replicates for assay and reference.
13
Chemical analysis
• The following elements are to be systematically analyzed for all the
raw materials: SiO2, Al2O3, Fe2O3, CaO, MgO, LOI, SO3, K2O, Na2O,
TiO2, P2O5, TOC, SO3 from sulphide and Chlorine.
G E O M I N I N G G U I D E
Exploration and Characterization
Chemical Analysis
• For analysis of XRF, the fused bead method must be used. Details of
an analytical procedure are given in Appendix I.
14
Geotechnical Studies
• The main purpose is to determine the physical characteristics of the
raw materials during the first drilling campaign.
• This information is necessary in order to design an optimum slope in
the overburden and ore (cohesion, hydrology).
• Many of these parameters are necessary to optimize the blasting
(Young Modulus, Poisson Ratio).
• Some parameters are necessary for the process (density, abrasivity,
humidity).
G E O M I N I N G G U I D E
Exploration and Characterization
Geotechnical Studies
15
Geotechnical Studies
G E O M I N I N G G U I D E
Exploration and Characterization
Geotechnical Studies
16
Hydrogeological Studies
G E O M I N I N G G U I D E
Exploration and Characterization
Specific Physical Parameters for Clinker Production
• The following parameters are mandatory for each raw material and
raw mix and are determined by using the Standard Lafarge Methods:
➔ Raw Materials
❿ Free silica analysis (quantity and size distribution)
❿ Abrasivity
❿ Crushability
❿ Moisture content.
➔ Raw Mix
❿ Grindability
❿ Burnability.
17
G E O M I N I N G G U I D E
Reserves
Estimation
Estimation
Reserves
G E O M I N I N G G U I D E
Reserves Estimation
Definitions
19
Geological Modelling
G E O M I N I N G G U I D E
Reserves Estimation
Geological Modelling
20
Reserves Calculation
G E O M I N I N G G U I D E
Reserves Estimation
Sample Compositing
21
Sample Compositing
G E O M I N I N G G U I D E
Reserves Estimation
Sample Compositing
35
15
30 Mean = 2.5 Mean = 2.5
Var = 5.8 Var = 3.1
Frequency
Frequency
25
20 10
15
10
5
5
0 0
0 2 4 6 8 10 12 0 2 4 6 8 10 12
22
Generation of Blocks
G E O M I N I N G G U I D E
Reserves Estimation
Block Chemistry Estimate
23
G E O M I N I N G G U I D E
Reserves Estimation
Block Chemistry Estimate
24
G E O M I N I N G G U I D E
Reserves Estimation
Block Clinkerability Assessment
25
G E O M I N I N G G U I D E
Mining
Plans
Mining
Plans
G E O M I N I N G G U I D E
Mining Plans
Long-term Mining Plan
27
G E O M I N I N G G U I D E
Mining Plans
Long-term Mining Plan
• When the total reserves are large enough, each quarry should have a
systematic phasing or development sequence, which represents the
step-by-step development over the limit of the proven and/or
probable reserves (or the maximum life of the deposit if possible).
• Phasing should be based on the reserve distribution, the mining
method used, the bench height, the waste to ore ratio, and the
surface topography.
• Phasing or development sequence has to be reviewed every 5 years.
28
G E O M I N I N G G U I D E
Mining Plans
Long-term Mining Plan
29
G E O M I N I N G G U I D E
Mining Plans
Long-term Mining Plan
30
G E O M I N I N G G U I D E
Mining Plans
Short-term Mining Plan
31
G E O M I N I N G G U I D E
Mining Plans
Software
• QMS:
➔ In addition to long term reserves calculation, QMS is also used for long
term mine planning as well as short term planning.
➔ QMS is used in TCs with CORALIS software for long-term and short-term
mine planning.
➔ QMS is also used by TDs where there are enough staff sufficiently
experienced in geology and mining.
• MINECAD:
➔ MineCad, insuring the optimization of raw materials and raw mixes,
allows the implementation of short-term planning.
➔ It is used in the Plants where there are competent quarry staff.
32
Mining Methods
• Mixed Method:
❿ Includes Simultaneous and Successive Methods.
G E O M I N I N G G U I D E
Mining Plans
Mining Methods
• Glory Hole and Rock Slides:
➔ Can only be used for vertically homogeneous deposits.
➔ Are used in cases where the topography is steep.
➔ Allow transportation costs to be reduced.
➔ Glory hole is a combination of opencast with underground mining
system.
➔ Rock slides may create environmental problems due to dust.
• Underground Mining System:
➔ Different methods, conventional or mechanical, can be used depending
on geomechanical characteristics of the rocks and mining cost.
❿ Room and Pillar (recommended), Block caving, Sublevel Stoping,
Sublevel Caving, Vertical Crater Retreat, Shrinkage Stoping and
Cut & Fill.
33
Mining Methods
Overburden
Mineral
G E O M I N I N G G U I D E
Mining Plans
Mining Methods
34
Mining Methods
Waste
Extraction
1
2 Working Slope
3
Hanging Wall
Waste
Foot Wall
Waste
Mineral
Mineral and intercalated waste extraction
tonnage of waste
Cumulative tonnage
Cumulative
2 1
4
Waste 3
5
of waste
Mining sequences:
Cumulative tonnage of mineral 1&2; 3&4… Cumulative
tonnage of mineral
G E O M I N I N G G U I D E
Mining Plans
Mining Methods
A
B
Working Slope C
Cyclic method
35
Mining Methods
Mixed Method
Final Slope
Hanging Wall
Foot Wall
Working Slope
G E O M I N I N G G U I D E
Mining
Operations
Operations
Mining
G E O M I N I N G G U I D E
Mining Operations
Definition
37
CRUSHING
& SIZING
LOADING
DRILLING & HANDLING
& BLASTING
G E O M I N I N G G U I D E
Mining Operations
Main Mining Activities
• Bench Design
• Equipment Management
• Safety
• Rehabilitation
38
Bench Design
• Factors affecting bench orientation:
➔ Dip and strike
➔ Fractures
➔ Geochemical variability orientation.
G E O M I N I N G G U I D E
Mining Operations
Bench Orientation
Quarry heading directions following the strike
Blast holes shall be on the line of the arrow
Reclaiming directions
Stay in same bench as long as possible
39
G E O M I N I N G G U I D E
Mining Operations
Drilling & Blasting
• Type of drilling:
➔ Top hammer (TH) in competent rock (for hole diameter from
76 to 150 mm and depth less than 15 m).
➔ Down-the-hole hammer (DTH) in soft, fragmented, karstic rock
(for hole diameter 150 - 200 mm and depth less than 30 m).
More air, so bigger air compressor is needed for DTH.
➔ Rotary drill (hole diameter > 200 mm and holes depth > 30 m).
40
G E O M I N I N G G U I D E
Mining Operations
Drilling & Blasting
21
1 23 26
24
25 10 9
18 11
19
27
13 12
20
16
14
17
15
Legend :
1 - Bench height 8 - New crest (After mucking) 15 - Toe 22 - Drill cuttings pile
2 - Hole-to-crest 9 - Rear row of boreholes 16 - Hole-to-toe 23 - Stemming
3 - B = Burden 10 - Side break 17 - Subrilling 24 - Column explosive
4 - Borehole Coverage Area = S x B 11 - Intermediate row(s) of boreholes 18 - Exp. column height 25 - Crest
5 - S = Spacing 12 - Crest row of boreholes 19 - Hole depth 26 - Borehole collar
6 - Hole Dia. 13 - Front burden 20 - Floor or final grade 27 - Bottom priming
7 - Back break 14 - Bank angle 21 - Stem height
41
• Detonators:
➔ The booster is a charge into which a detonator is inserted
to initiate a primary charge.
➔ The primer is a booster armed with an initiating charge.
G E O M I N I N G G U I D E
Mining Operations
Drilling & Blasting
• Factor affecting blasting efficiency:
➔ Rock properties
❿Young modulus
❿Poisson ratio
❿Compressive and tensile strength
❿Porosity.
➔ Explosive properties
❿Type (ANFO, emulsion, dynamite)
❿Velocity of detonation
❿Distribution in the column
❿Quantity
❿Delaying.
➔ Blast design
❿Hole diameter length and inclination
❿Pattern
❿Stemming length and material
❿Subdrilling.
42
G E O M I N I N G G U I D E
Mining Operations
Drilling & Blasting
• Blast Design (1):
➔ There is no magical formula to optimize blast design.
➔ The only way to optimize blast is by trials.
❿Choose hole diameter appropriate to bench height.
❿Start with:
– Square pattern (Space and burden in meters = 0.9 x hole
diameter in inches)
– Crushed stemming material (cleaned 20 mm stone)
– Bottom initiation with Nonel (non electric detonetor)
depending on the local law
– and delays:
• 17-25 ms between holes,
43
G E O M I N I N G G U I D E
Mining Operations
Drilling & Blasting
Tight
Hard to dig, poor fragmentation related to
insufficient interval between rows (<35 ms).
Some overbreak
Hard to dig, moderate fragmentation, suitable for shovel
excavation related to short delay interval (35-50 ms) at
Tight,
compact high benches. Good for quality control while reclaiming by
loader in quarries with horizontal or inclined continuous
bedding and suitable for loading at low benches (7-8 m).
Little overbreak
G E O M I N I N G G U I D E
Mining Operations
Loading & Hauling
• Main applications of loading equipment (1):
➔ Wheel Loaders
❿For frequent blasts
❿Multi face loading
❿Sorting and transporting boulders
❿Reclaiming ripped material
❿Polyvalent equipment in the quarry (assistance and aid)
❿Stock forming equipment
❿Needs good floor and lower face profile.
45
G E O M I N I N G G U I D E
Mining Operations
Loading & Hauling
• Main applications of loading equipment (3):
➔ Hydraulic shovels
❿For important blasts (one face loading)
❿Possibility of direct extraction
❿Narrow and difficult working areas
❿Usable in loose underfooting areas
❿For hard materials
❿Cleaning working front (foot, faces)
❿Possibility of “drop ball”*
❿Good adaptation to all type of hauling equipment.
46
Capacity 4-10 m 3
2.5-6 m 3
4-7 m3
G E O M I N I N G G U I D E
Mining Operations
Loading & Hauling
• Selection criteria for distance and slope for hauling equipment (1):
Equipment Distance Slope
47
➔ Scrapers
❿For very bad road conditions (rolling resistance >10%)
❿For earthworks and non-consolidated rocks
❿High dead load
❿Not good for distances longer than 1 km
❿Life time: 15 000 hours.
G E O M I N I N G G U I D E
Mining Operations
Loading & Hauling
• Selection criteria for hauling equipment (3):
➔ Wheel loaders
❿Difficult working conditions for the operator as well as for the
equipment.
Compared to 2% rolling resistance, ~ 30% production loss at
8% rolling resistance.
❿High tire cost.
➔ Belt conveyor
❿Especially for crushed stone
❿Low operation cost
❿High investment.
Best choice when road construction is difficult.
➔ Wagon or rail car
❿Needs loading equipment
❿Low operation cost
❿High investment cost.
48
➔ Articulated trucks
❿Limited payload (<40t)
❿For earth works (tray not well adapted for hard rocks)
❿For bad roads (rolling resistance > 6%) and difficult loading
and unloading zones
❿Good for small sites where road construction can not
be justified.
❿High maintenance cost
❿Life time: 10 000 hours.
G E O M I N I N G G U I D E
Mining Operations
Loading & Hauling
• Matching factors for loading and hauling equipment:
➔ Bench height restriction and required flexibility
➔ Diggability and muck pile configuration
➔ Lift-dump height clearance
➔ Bucket fill factor
➔ Loading cycle time
❿Loader 3-5 passes, Excavator 3-7 passes.
49
60°
Dumper
120°
Front
G E O M I N I N G G U I D E
Mining Operations
Loading & Hauling
• Key indicators for loading and hauling efficiency:
➔ Truck or bucket fill factor (%)
➔ Diggability (sec per cycle and t/h)
➔ Productivity (t/h)
➔ Fuel consumption (liter per hour)
➔ Tire consumption ($/km)
➔ Number of gear changes in cycle
➔ Fleet capacity versus requirement
➔ Total cost for loading and hauling (cost unit per ton).
50
G E O M I N I N G G U I D E
Mining Operations
Loading & Hauling
• Roads and Underfooting:
➔ The quality of roads and underfooting is one of the parameters
for assessing the performances of mining operations.
➔ Roads and underfooting affect production and maintenance
costs.
❿For 1 km road, about 10% production loss at 5% RR* compared
to 3% RR.
❿More tire and fuel consumption, etc.
* Rolling Resistance: force opposed by the road to the progression of the
wheels of the hauling equipment.
G E O M I N I N G G U I D E
Mining Operations
Crushing and Sizing
• Factors affecting crushing & sizing efficiency:
➔ Feed area must always be kept clean.
➔ Wear patterns need to be reviewed frequently along with set
points.
➔ Feeders and their crushers should be interlocked.
➔ Feed should be adjusted to sized materials for vibrating step-
type grizzlies.
➔ The required raw mill power (kWh) is affected by particle size
distribution.
➔ Screens should be sized to 133% the required capacity.
➔ Screens should be specified for wet or dry applications.
➔ Feed must be evenly spread across the screen.
➔ Bed depth should not exceed 4x the deck opening.
52
• Crushing equipment:
Rock Output Crushing
properties Characteristics equipment
Sticky Compaction may choke device at exit Toothed Double Roll
Moist for Hammer, Impact and Jaw crushers Toothed Single Roll
G E O M I N I N G G U I D E
Mining Operations
Crushing and Sizing
• Crushing equipment:
Operation Max Feed Reduction Typical Power (HP) Cost
Size (mm) ratio equipment For 400-600 tph (x 1 000 US$)
53
G E O M I N I N G G U I D E
Mining Operations
Equipment Management
• Has a great impact on mining costs and therefore can not be
neglected.
• The purpose of equipment management is:
➔ To choose the most suitable equipment for the required work
➔ To lengthen equipment life
➔ To minimize downtime
➔ To control service intervals
➔ To improve re-sale value.
54
Equipment Management
• New equipment choice parameters:
➔ Justification of replacement (EVA…)
➔ Compatibility with mining methods and raw materials
characteristics
➔ Type of machine
❿Best operating cost
❿Preventive maintenance requirements and cost
❿Cost-effective repair strategy and after-sale service
❿Equipment and components life expectancy
❿Re-sale value
➔ Benchmarking
➔ Training and implication of operators.
G E O M I N I N G G U I D E
Mining Operations
Equipment Management
• Preventive maintenance recommends tasks and intervals to help to
plan downtime and prevents unexpected failures.
➔ Systematic oil sampling provides analysis of oil contaminants
and trends to identify problem areas.
➔ Inspections and performance evaluation, often done by the
equipment operator on a checklist, help to identify potential
problems and to make some small repairs.
➔ Customized operator training can be a key factor in reducing or
eliminating operator error.
➔ A well kept schedule should be followed to ensure timely
repairs.
➔ A close cooperation between maintenance and operation
people is required for preventive maintenance.
➔ Record keeping provides a history to optimize preventive
maintenance scheduling, predicts maintenance costs for
equipment, and helps select new equipment.
55
Safety
• Proper safety performance is based on team work and good
communication.
• Each quarry must have safety regulations. The following are just
given as an example. See Appendix IV for detailed safety rules which
are applicable in all quarries.
➔ Housekeeping in the quarry
➔ Posted safety policy and rules
➔ Clean operator cabins
➔ Posted emergency procedures and phone numbers
➔ Regular meetings of Safety Operators
➔ Proper road signs and speed limits placed at key areas
➔ “Danger” or “No Trespassing” signs to prevent unauthorized
entry
➔ Back-up signals on all mobile equipment
➔ Working safety guards where required
➔ Personal safety equipment like hard hats, steel-toe boots,
safety glasses.
G E O M I N I N G G U I D E
Raw Material
Raw Mix Audit
G E O M I N I N G G U I D E
Raw Materials & Raw Mix Audit
Introduction
• Audit’s objective
• Plant Characteristics:
➔ Process type
➔ Main equipment
➔ Clinker types and capacity.
• Competitors on the same market
57
Location
• Geographic location of plant and quarries (illustrated on a map).
• Description of the local transportation system (into the plant,
between plant and deposits, around the deposits…).
• Description of the plant and quarries neighborhood (villages, other
inhabited areas, springs, places of worship, cemeteries, historical
monuments, natural parks, other industrial sites…).
• Geomorphologic description (landscape, relief, surface waters…).
• Regional climatic conditions.
G E O M I N I N G G U I D E
Raw Materials & Raw Mix Audit
Regional Geology
• Stratigraphy and lithology with a focus on present and potential raw
material sources (illustrated on a geological map and stratigraphical
column).
• Regional tectonic, seismicity and volcanism.
• Regional hydrogeological conditions.
58
Legal Aspect
• Status of cement raw materials in the mining legislation.
• Land control (for the plant and deposits):
➔ Private properties
➔ Leased lands
➔ Other (depth restriction…).
• Required legal permits (delivered by…, expiration date):
➔ Exploration license
➔ Mining license(s)
➔ Operating license
➔ Other permits (explosives use, public roads use, water
management…).
• Type and amount of taxes for the land and underground use.
• Other data relating to the local regulation.
G E O M I N I N G G U I D E
Raw Materials & Raw Mix Audit
59
Geological Characteristics
• Existing data:
➔ Geological and topographical maps (1:2000 or 1:5000)
➔ Aerial photo frequency, precision of topographical restitution
➔ Geological reports, drill holes, analyses…
• Detailed geological description of the deposit (raw materials,
overburden, karst…).
• Local hydrogeology (surface and underground water).
• Local geotechnical problems (slope instabilities, land-slides…).
G E O M I N I N G G U I D E
Raw Materials & Raw Mix Audit
Reserves
• Reserves tonnage and chemistry (according to official local data):
➔ Proven and probable reserves including their calculation
methods and equivalent in clinker.
• Geological or potential reserves:
➔ Horizontal and vertical extension of the deposit under-mining
➔ Other potential deposits.
• Possibility of acquiring more land to increase reserves and to support
the environment strategy.
60
Quality
• Geochemical characteristics of the extracted raw material from
drilling and sampling programs as well from quarry assaying.
➔ Variability
❿For each of the major oxides, the average and standard
deviation from both the drilling program and the quarry
assays should be given
❿Analyses of the major oxides and LOI including SO3, alkalis,
Cl, P205, pyrite and free quartz
❿Some samples from deposit can be collected to check
geochemistry.
➔ Physical characteristics
❿Density
❿Moisture (seasonal variations)
❿Compression and tensile strength.
G E O M I N I N G G U I D E
Raw Materials & Raw Mix Audit
Mining
• Description of the long and short-term mining plan as well as the
mining method.
• Geometric parameters of the quarry:
➔ Reasons for the orientation of mining fronts
➔ Bench height and general appearance
➔ Floors and haulways conditions
➔ Safety benches and berms protection.
• Extraction mode: Conventional (Drill & Blast) or Mechanical (Ripping…).
• Mobile equipment:
➔ General appearance, type & number, capacity (m/h and
diameter for drill, m3 and hp for others), availability, main
concerns should be given for each of the following:
❿Drill, excavator, loader, truck, bulldozer, grader and other main
service equipment.
• If quarry is sub-contracted, specify general conditions of contract.
61
Mining
• Drilling:
➔ General position of the drill: perpendicular to the bench,
leveled, positioning on hole location
➔ Advance of drilling with respect to blasting.
• Blasting:
➔ Geometric parameters (number of rows, hole per row, hole
layout, hole diameter, burden, spacing, sub-drilling, inclination,
stemming…)
➔ Grid type (square, rectangular or staggered)
➔ Explosive types and characteristics
➔ Column load description and stemming material
➔ Initiation and detonator types
➔ Firing sequence
➔ Consumption of explosives per ton of blasted material
➔ Quantity of oversize blocks and cost ratio (cost of oversize/total
blasting cost)
➔ Average blasted tonnage
➔ Suitability of the blasted rock to the crusher type
➔ Safety measures.
G E O M I N I N G G U I D E
Raw Materials & Raw Mix Audit
Mining
• Loading:
➔ Loading efficiency ( bucket fill factor, cycle time, waiting time,
ease of loading equipment to dig into blasted rock)
➔ Cleanness of the operation
➔ Blending done by the loading if required
➔ Safety of the operation.
• Hauling:
➔ Hauling efficiency ( dumper fill factor, cycle time, waiting time,
rock spills at loading and on roads)
➔ Bunching
➔ Matching of the trucks with the loading and crushing
equipment
➔ The conditions of the haulways (Drainage, crown, curves,
wetting…)
➔ Safety of the operation.
62
Mining
• Crushing:
➔ Type of crusher
➔ Year of construction and general state
➔ Feed size distribution
➔ Type of feeding mechanism and its capacity
➔ Designed and effective production rates
➔ Main crushing related problems
➔ Type of circuits (open or closed)
➔ Re-circulation rate
➔ Suitability of conveying systems
➔ Reliability
➔ Types of screens and their efficiency (when applicable)
➔ Heave and throw of screens
➔ Safety measures around the crusher.
G E O M I N I N G G U I D E
Raw Materials & Raw Mix Audit
Mining
• Cost ($/t):
➔ Blasted material
➔ Delivered material at crusher
➔ Sub-contracted work (when applicable)
➔ Crushed material
➔ Total cost of material delivered to raw mill.
• Staff:
➔ Quarry staff and organization
➔ Capability of staff to control contractors.
63
Environment
• Nuisances:
➔ Ground and air vibration
➔ Dust
➔ Surface and ground water outlet control
➔ Visual impact
➔ Buffer zone.
• Environmental Impact Assessment (EIA) report if available.
• On-going and final reclamation plans.
• Emergency plan.
• Access restriction measures to the quarry.
• Main problem related to environmental protection.
G E O M I N I N G G U I D E
Raw Materials & Raw Mix Audit
Raw-mix
• Description of raw mix line including comments:
➔ Raw material stocks
➔ Prehomo or blending tanks
➔ Bins and feeders
➔ Homogenization.
• Origin, composition, regularity and cost of raw mix additives.
• Current raw-mix composition and analyses (monthly mean values and
standard deviation for 1-2 last years):
➔ Chemical composition
➔ Fineness
➔ Moisture
➔ Raw-mix and clinker uniformity.
• Potential improvement of raw-mix composition and logic.
• Some samples can be collected for each type of raw material, raw
meal and clinker.
64
Quality Control
• Description of control logic:
➔ Sampling points and type (automatic, manual)
➔ Sampling methods (automatic, manual)
➔ Sampling frequency
➔ Analysis frequency
➔ Analyzed parameters
➔ Corrective actions (manual or automatic, software…).
G E O M I N I N G G U I D E
Raw Materials & Raw Mix Audit
Conclusions
• Legal aspect
• Geological characteristics
• Mining plan
• Mining equipment
• Mining cost
• Environment
• Raw-mix
• Quality control
65
G E O M I N I N G G U I D E
Appendix I
Chemical
Analysis
G E O M I N I N G G U I D E
Chemical Analysis
Chemical Analysis
• LOI determination for high-calcium or dolomitic limestone:
➔ Dry at 110°C overnight
➔ A pre-loss at 750° C for 1 hour is performed on the sample so as
to prevent loosing material from effervescent de-carbonation
➔ Then ignition for 1 hour at 1000°C.
• LOI determination for other raw materials:
➔ Dry overnight
❿110°C for normal samples
❿45°C for samples containing gypsum and samples to be analyzed
for SO3 related to sulfides
➔ Ignition for 2 hours at 1000°C.
67
Chemical Analysis
• Preparation of fused beads (method used at CTS):
➔ Pulverize the ignited sample to 100% passing the 300 µm in
order to crush the lumps (mortar and pestle).
➔ The ignited sample 1.0000 +/- 0.0003 is combined with 6.5000
+/- 0.0003 g of lithium tetraborate (anyhdrous) in a small jar.
➔ A glass Leco spoon (0.3g) with lithium nitrate as a fluidity and
oxidizing agent is added.
➔ The above mixture is transferred (carefully and completely) to
a clean crucible and blended with a clean Teflon stirring rod
for 1 minute.
➔ Two drops of Lithium Bromide solution as an anti-wetting agent
is added to the crucible.
➔ The Claisse Fluxers Bis are used to fuse the mixture by heating
Program 1 to 1050°C for 20 minutes and to pour out fused
liquid into a polished mold.
• A glass bead is ready to be analyzed by the XRF after the cooling
period.
G E O M I N I N G G U I D E
Appendix II
Lafarge
Raw Materials
Doctrine
G E O M I N I N G G U I D E
Lafarge Raw Materials Doctrine
Raw Materials
Cement plants belong to heavy industry, and as such,
are built to last. Therefore, they must own or have
control over substantial reserves of raw materials.
Reserves
Each operating unit must have a policy concerning the acquisition
and preservation of its reserves of raw materials (limestone, marl,
clay, sand…).
• Each Operating Unit will define with its Technical Center, its “proven,
probable and potential” reserves in terms of years of clinker produc-
tion at current plant rated capacity (CKHC # 0005).The target is fifty
years of proven and probable reserves for the existing plants (except
justifiable cases such as use of secondary raw materials) and for new
projects.
G E O M I N I N G G U I D E
Lafarge Raw Materials Doctrine
• For each deposit, Operating Units must establish a long term plan for ob-
taining or extending of mining rights, land control and administrative per-
mits.This plan will contain for all areas impacted by the long term mining
plan including buffer zones; the following information:
– property limits,
– expiry dates of mining permits,
– tonnage and chemistry of reserves,
– characteristics of the deposits and their environmental constraints,
– action plans and necessary budget.
• For each deposit Operating Units must establish a long-term plan for min-
ing, based on geological investigations and the following issues:
– long-term optimization,
– economic objectives of mining,
– environmental protection.
70 This plan, periodically updated, will be carried out using the best tools available,
in particular deposit modeling techniques.The Operating Unit is responsible for
implementing these plans.
Each Operating Unit will also implement and maintain a policy of protection
and preservation for deposits which are being mined.This policy will require:
– protecting the environment and maintaining close relations with all con-
cerned (government, local officials, neighborhoods, etc.),
– creation and preservation of buffer zones around operating areas,
– rehabilitation in harmony with the neighboring landscape,
– continuous research for improvement in environmental protection
(i.e. vibration, noise, dust, visual aspect…),
– prohibition of the storage or burial of materials or waste in the quarry
which may pollute the ground water or create other risks,
– mining operations respecting internal and external safety rules,
– a professional supervision of mining operations by plant staff.
G E O M I N I N G G U I D E
Lafarge Raw Materials Doctrine
Definitions
Reserves of raw materials must be certified by
Technical Centers and classified as follows:
Proven Reserves
Reserves in fully controlled land for which we have the mining rights
and the necessary administrative permits for mining operations.
– They have been evaluated on the basis of representative core
drilling and reliable geochemical analyses.
– The revision of the short term mining plan is based on these re-
serves.
Probable Reserves
Reserves in fully controlled land for which we have the mining rights,
but the necessary administrative permits for mining operations may be
incomplete, or reserves in incompletely controlled land for which we
have the mining rights and the necessary administrative permits for
mining operations. 71
Potential Reserves
Reserves in a land which is uncontrolled, but recognized as potentially
miniable after obtaining the necessary permits.
– The necessary geological investigations are not fully carried out
to ensure their quantity, quality and miniability.
– Their technical and economical feasibility is uncertain.
– These reserves have the same value for a competitor as for La-
farge.
References
Related practices can be found in Geomining Guide.
G E O M I N I N G G U I D E
Appendix III
Variograms
G E O M I N I N G G U I D E
Variograms
Absolute Variogram
73
G E O M I N I N G G U I D E
Variograms
Power of Differences
74
Search Angle
• Horizontal Angle:
➔ Azimuth measured in degrees clockwise from north
(0° = north).
• Vertical Angle:
➔ Dip measured in negative degrees down from horizontal
(0° = horizontal).
➔ These angles must be chosen according to the sampling and
drilling patterns (could require many angles, not necessarily at
90º). Also consider the strike, the dip and the intermediate
direction.
G E O M I N I N G G U I D E
Variograms
Tolerance Angle
75
Slicing along X, Y or Z
• Always apply slicing along Z to limit the search for pairs of samples
to more specific stratigraphic horizons (for horizontal deposit).
• This means pairs from the same stratigraphic horizons can be
compared.
• If the deposit is inclined, apply slicing along the direction of the
strata, and try to reduce the tolerance as much as possible along
other directions.
G E O M I N I N G G U I D E
Variograms
Estimation: weights according to distances
Point to be estimated
d1<d2<d3
but sample #3 should have a more
important weight than sample #2
76
G E O M I N I N G G U I D E
Variograms
Section View: inclined layer
77
G E O M I N I N G G U I D E
Variograms
Step Length
• Anisotropic sampling pattern => the step length must depend on the
direction.
➔ Sample spacing along the hole is much smaller than sample
spacing between holes.
• Clustered drilling pattern => several step lengths.
Distance of Reliability
• The distance of reliability can depend on the direction (if the study
area is rectangular).
• Set to one-half the length of the area to insure that the vector h and
increments xi - xi+h characterize the whole study area, and not only
the edge points.
78
Step Length
G E O M I N I N G G U I D E
Variograms
Variogram Modeling
79
Variogram Modeling
G E O M I N I N G G U I D E
Variograms
Variogram Models
1.50
1.25
1.00
(h)
0.75
0.50 Sph
0.25 Exp
Gaus
0.00
0 50 100 150 200 250 300
Distance (h)
80
Variogram Components
1.50
1.25
1.00
C1, sill
(h)
0.75
0.50
Range
0.25
C0, nugget effect
0.00
0 50 100 150 200 250 300
Distance (h)
G E O M I N I N G G U I D E
Variograms
Calculation and Modeling Strategy
81
G E O M I N I N G G U I D E
Appendix IV
Safety
Rules
G E O M I N I N G G U I D E
Modified from Safety Manual of Western Mobile Inc.,
Denver Colorado, USA (1996).
G E O M I N I N G G U I D E
Safety Rules
Accident Reporting
83
Personal Protection
G E O M I N I N G G U I D E
Safety Rules
Personal Protection
• When the danger of falling more than two (2) meters exists, an
approved safety belt (or harness) with a lifeline suitably attached and
fastened to a secure point shall be worn.
• Approved hearing protectors shall be worn where the Management
requires it.
• Approved respiratory protection shall be worn where the
Management requires it.
• Clothing will be appropriate to working conditions. Hair, including
facial hair, must be contained around rotating equipment and/or
moving machine parts.
84
Cleanup
G E O M I N I N G G U I D E
Safety Rules
Electricity
85
Electricity
G E O M I N I N G G U I D E
Safety Rules
Electricity
• Mobile equipment shall not run over power cables unless the cable
are properly bridged or protected.
• Blasting circuits shall be:
➔ Insulated
➔ Ungrounded
➔ Isolated from all other conductive elements.
• Circuits shall be protected against excessive overload by fuses or
circuit breakers of the correct type and capacity.
• Power wires and cables shall be insulated adequately where they pass
into and out of electrical compartments.
86
Electricity
• Cables shall enter metal frames of motors, splice boxes, and electrical
compartments only through proper fittings.
• Dry wooden platforms, insulating mats, or other electrically non
conductive material shall be kept in place at all switchboards and
power control switches where shock hazards exist.
• Permanent splices and repairs made in power cables, including the
ground conductor where provided, shall be:
➔ Mechanically strong with electrical conductivity as near as
possible as that of the original
➔ Insulated to a degree at least equal to that of the original and
sealed to exclude moisture
➔ Provided with damage protection as near as possible to that of
the original, including good bonding to the outer jacket.
G E O M I N I N G G U I D E
Safety Rules
Electricity
87
Explosives
G E O M I N I N G G U I D E
Safety Rules
Fire Prevention and Control
88
G E O M I N I N G G U I D E
Safety Rules
Machinery, Equipment and Tools
89
G E O M I N I N G G U I D E
Safety Rules
Material Handling and Storage
90
Mechanical Guards
G E O M I N I N G G U I D E
Safety Rules
Mobile Equipment
91
Mobile Equipment
G E O M I N I N G G U I D E
Safety Rules
Mobile Equipment
92
G E O M I N I N G G U I D E
Safety Rules
Travelways, Escapeways and Ladder/Stairs
93
G E O M I N I N G G U I D E
Safety Rules
Welding and Cutting
94
G E O M I N I N G G U I D E
Safety Rules
Excavation – Trenching
95
Miscellaneous
G E O M I N I N G G U I D E
Safety Rules
Miscellaneous
• Employees shall use proper lifting techniques: lift with your legs,
keep your back straight, keep the load close to your body, do not lift
and twist with a load, get help if a load is too heavy.
• Any employee who is operating any company equipment at any time
while taking, using or consuming prescribed drugs must notify his/her
supervisor prior to using or operating company equipment.
• Employees are not allowed to walk up conveyors.
• To work from a conveyor you must be tied off with a harness.
96
G E O M I N I N G G U I D E
Appendix V
Rehabilitation
Guidelines
Taken from
Strategic Quarry Rehabilitation Project (SQRP) of the Group
G E O M I N I N G G U I D E
Site Selection
1
º
N
Objective
To assess major issues before applying for a permit: geology, water
E
regime, biodiversity, landscape, heritage, archaeology, human
N
environment, zoning by-laws.
I
To assess the project's ability to be integrated into the environment and
L
the local community's ability to accept it.
E
Application
D
All future quarries and extensions.
I
U
Principles
G
An environmental survey must be carried out before opening any new
quarry or major extension.
The survey will include:
• An ecological assessment (flora and fauna)
• A detailed geological assessment including hydrogeology and
hydrology
• Transport infrastructure (roads, waterways, rail) and proximity to
market
• Human environment: sufficient distance from urbanized areas;
compatibility with urban planning documents and constraints 97
G E O M I N I N G G U I D E
Site Selection
– archaeological investigation,
– physical constraints (cemeteries, pipes, etc.),
– ceremonial and sacred grounds of indigenous peoples.
Costs
• Cost depends on country, size, history, etc. Can vary from US$10K to >
US$100K.
Experts to contact
Name Division/region/sector Country Phone nº
Ron FOSTER Aggregates United Kingdom 44 1 530 241 088
Serge DALLAS Aggregates France 33 1 40 95 69 30
Yves DERREAL Cement France 33 1 49 11 40 40
Philippe CHEVALIER Gypsum France 33 4 90 21 21 81
G E O M I N I N G G U I D E
Choice of Rehabilitation Objectives
2
º
and Future Use
N
E
Objective
The rehabilitation objectives and future use must be socially and
N
environmentally beneficial, as well as technically and economically
I
feasible.
L
E
Application
D
All quarries in any geographical context.
I
Principles
U
The rehabilitation project must be designed according to the following
G
criteria:
– ecological considerations (see Guideline nº 1),
– geological and hydrogeological contexts,
– surrounding landscape (see Guideline nº 14),
– habitat creation and biodiversity enhancement when possible,
– economic feasibility,
– social and cultural preferences and opportunities.
Costs
Geological studies (see Guideline n° 1)
Landscape studies: 7 000 to 20 000 €
Ecological survey: 3 000 to 8 000 €
G E O M I N I N G G U I D E
Choice of Rehabilitation Objectives
and Future Use
Experts to contact
Name Division/region/sector Country Phone nº
Ron FOSTER Aggregates United Kingdom 44 1 530 241 088
Yves DERREAL Cement France 33 1 49 11 40 40
Georg THOMAS Roofing Germany 49 6171 61 26 42
Arnaud COLSON Aggregates France 33 1 40 95 69 00
100
G E O M I N I N G G U I D E
Visual Simulation
3
º
N
Objective
To facilitate choices and validate the concept. To enable the visual
E
amenity of the site to be considered at successive stages as the mineral
N
working and rehabilitation progress in order to communicate with the
I
authorities and the general public.
L
E
Application
D
Any quarry where the landscape is expected to be a major issue and
where the use of such techniques is relevant.
I
U
Principles
G
• Involve landscape architects in the project.
• Transfer geological, topographical and hydraulic data to a simulation
software program.
• Quantify the deposits to be mined:
Topsoil/Subsoil/Overburden/Mineral.
• Use aerial and/or line-of-sight photography coupled with landscape
design software.
Costs
• Software (AMAP): 15 000 €.
• For visual simulation:
– overall modeling 3 000 to 10 000 €,
– cost per visualisation point: 2 000 €
• For visual animation (approx. 3 minutes):
– visual only: 15 000 €,
– audiovisual: 20 000 €.
Those software programs are complex and should be contracted out.
G E O M I N I N G G U I D E
Visual Simulation
List of reference documents
Atelier Architecture Environnement
1999-2000, Carrière de la Malle – Variante de réaménagement paysager,
LAFARGE GRANULATS PROVENCE available at Marseille (13 – France).
TUP/GVA (P. Thebault): CD ROM about the rehabilitation of Port La
Nouvelle, St Pierre La Cour, Le Teil, available at Lafarge ciment St Cloud
Tavernola.
Experts to contact
Name Division/region/sector Country Phone n°
Claire PAJON Aggregates France 33 1 40 95 69 00
Jean Pierre GRASSI Gypsum France 33 4 90 69 71 14
Jean-Guy LEVAQUE Cement North America 1 514 738 1202
Louis DESCOMBES Cement France 33 4 75 49 60 23
G E O M I N I N G G U I D E
Rehabilitation Plan
4
º
N
Objective
The rehabilitation plan describes the series of phased operations that
E
make the future use of the site possible. The rehabilitation plan is used
N
as an internal and external communications tool. It is a fundamental
I
document for the quarry manager.
L
E
Application
D
All quarries are required (under the Lafarge Rehabilitation Policy) to
have a rehabilitation plan, which must be updated periodically.
I
U
Principles
G
The rehabilitation plan is essential to the implementation of the policy.
It must be part of or coordinated with the mining plan.
• Support from local stakeholders is necessary.
• The rehabilitation plan should be defined taking the extraction
program and the after-use into account (see Guideline nº 2).
• Gradual reclamation will spread the costs of rehabilitation over the
lifetime of the site. It must be illustrated with detailed phase plans.
• For cement operations, the rehabilitation plan must be defined in
collaboration with the relevant Technical Centers or departments.
103
• Coordination with the mining plan, as well as supervision and
monitoring of earthmoving, should minimize the displacement of plant
and equipment (see Guideline nº 9) and prevent environmental
damage.
G E O M I N I N G G U I D E
Rehabilitation Plan
• Simulation tools and models.
• Map of the site showing measures prescribed by the planning
permission.
• Use of past examples and published research documents.
• Supervision and monitoring, included in the rehabilitation budget
and systematically carried out (frequency to be set according to site
characteristics: for example, every second year for cement quarries,
every year for sand and gravel pits).
Costs
Vary considerably, and use of consultants can be expensive. In-house
expertise could be used for advice.
In North America: US$ 20 000 to 80 000.
Experts to contact
Name Division/region/sector Country Phone n°
Bernard BOURGUE Aggregates France 33 4 95 09 45 00
Ron FOSTER Aggregates UK 44 1 530 241 088
Claire PAJON Aggregates France 33 1 40 95 69 00
Yves DERREAL Cement France 33 1 49 11 40 40
René HALLER Cement Kenya 254 11 48 61 55
Jean-Guy LEVAQUE Cement North America 1 514 738 1202
G E O M I N I N G G U I D E
Consultation with Authorities,
5
º
Associations and Neighbors
N
before Application
E
N
I
Objective
L
To identify key stakeholders.
To seek the approval of the local community, statutory and non-
E
statutory agencies, by presenting them with proposals and being
D
prepared to consider their concerns and requirements.
I
To obtain acceptable conditions within a reasonable timeframe in
U
order to draw up the operation plan.
G
Application
All quarries requiring a new or modified approved plan.
Principles
• Determine the main concerns of the community and the authorities.
• Justify the choice of the site and [operation plan (including
rehabilitation): economics, geography, environment (see Guideline
nº 1 and 2).
• Ensure that all consultees understand the facts of a proposed 105
development.
• After hearing the concerns of authorities, associations and neighbors,
modify the application and proceed with a new consultation to
present the modifications following this new application. Therefore,
this is an iterative process and may require a series of consultations.
G E O M I N I N G G U I D E
Consultation with Authorities,
Associations and Neighbors
before Application
Costs
• Documents.
• Time devoted to presentation (can save time later).
• Opportunity cost (mitigation).
Experts to contact
Name Division/region/sector Country Phone n°
Arnaud COLSON Aggregates France 33 1 40 95 69 30
Jean-Claude MARCOU Aggregates France 33 1 60 73 54 40
Bernard BOURGUE Aggregates France 33 4 95 09 45 54
Andi HODGSON Aggregates UK 44 1 530 24 11 16
Yves DERREAL Cement France 33 1 49 11 40 40
Patrick PARIS Cement France 33 1 49 11 43 37
Denis SCHMID Gypsum France 33 4 90 21 21 28
G E O M I N I N G G U I D E
Dialogue With Local Community
6
º
During Permitting Procedure
N
E
Objective
N
Once the operation plan has been developed, and before its approval,
I
the objective is to reach a consensus with the local community.
L
E
Application
D
All quarries needing a new or modified approved plan.
I
U
Principles
G
To reach consensus:
– presentation of the main characteristics of the project,
– ensure that consultees are made aware of the facts using reliable
data,
– understand possible political implications,
– support community access to independent expertise.
Costs
Time and documents devoted to presentation.
G E O M I N I N G G U I D E
Dialogue With Local Community
During Permitting Procedure
List of show cases for this guideline
Site Division Region/dep. Country Comment
GUERNES/ Aggregates Yvelines France For extension on
SANDRANCOURT Flicourt
LLYNCLYS Aggregates Shropshire UK
LA GRANDE-PAROISSE Cement Seine-et-Marne France
MONTMORENCY Gypsum Val-d’Oise France Early and close
contact with
neighbours authorities
and associations
HOPPEGARTEN Roofing Brandenburg Germany
Experts to contact
Name Division/region/sector Country Phone n°
Pierre PROY Aggregates France 33 3 44 38 30 00
Dominique EVRARD Aggregates France 33 4 72 24 46 25
Jean-Claude MARCOU Aggregates France 33 1 60 73 54 40
108 Patrick PARIS Cement France 33 1 49 11 43 37
Denis SCHMID Gypsum France 33 4 90 21 21 28
Andi HODGSON Aggregates UK 44 1 530 24 11 16
G E O M I N I N G G U I D E
Implementation of the
7
º
Rehabilitation Plan
N
E
Objective
N
Define and allocate the resources and measures needed to implement
the rehabilitation plan in line with its budget and schedule.
I
L
Application
E
All quarries before the beginning of any rehabilitation phase.
D
I
Principles
U
• Gradual restoration should be implemented as identified in the
G
rehabilitation program (see Guideline nº 4).
• The person responsible for the rehabilitation should understand and/or
apply:
– the existing mining plan,
– all the rehabilitation processes required by the approved plan
(earthmoving, vegetation…),
– management of contractors,
– the potential benefits (or damage) that can result from
rehabilitation operations if they are successful or not, especially in
terms of coordinating equipment and supplies with climatic 109
constraints,
– the internal and external skills required for providing advice and
guidance,
– make sure adequate funds are accrued and allocated in a timely
fashion, in accordance with Group policy and procedures.
Costs
A good program that is properly implemented avoids additional costs.
US$ 5 000 to10 000 /ha without transport or rough grading of raw
material.
G E O M I N I N G G U I D E
Implementation of the
Rehabilitation Plan
List of reference documents
Mineral Planning Guidance (UK)
Experts to contact
Name Division/region/sector Country Phone n°
Hervé CHIAVERINI Aggregates France 33 2 32 54 70 75
Claire MORICE Aggregates France 33 1 34 97 02 70
Bernard BOURGUE Aggregates France 33 4 95 09 45 54
110
Jean-Guy LEVAQUE Cement North America 1 514 738 1202
Pierre MATEU Gypsum France 33 1 60 26 64 04
Yves DERREAL Cement France 33 1 49 11 40 77
David PARK Aggregates UK 44 1 7406 54 461
Stephan NICOLAY Roofing Germany 49 6171 61 24 36
Frédéric THOUE Cement (CTI) Worldwide 33 4 74 82 18 04
G E O M I N I N G G U I D E
Control, Monitoring and Reporting
8
º
N
Objective
Guarantee the sustainability of the plan and apply corrective measures.
E
Monitor and report the progress and cost of the rehabilitation to ensure
N
that they are compliant with the rehabilitation plan.
I
Record the history (annual diary) of the rehabilitation work.
L
E
Application
D
All quarries in the process of rehabilitation.
I
Principles
U
• Inspection and monitoring: by the person responsible for the
G
rehabilitation, who should immediately report any problems of
implementation or excessive cost to a higher authority, before the
situation gets out of hand.
• Ensure that the rehabilitation work is carried out in accordance with
company and regulatory safety and environmental requirements.
• Reporting is done by the person in charge of the rehabilitation: the
local management chooses the recipient according to the type of
operations.
• Identify improved practices and update Guideline.
111
Costs
• Time devoted to the operations.
• Consultants.
G E O M I N I N G G U I D E
Control, Monitoring and Reporting
List of reference documents
Observatoire du paysage,
Mission paysage, Ministère de l’Aménagement du Territoire et de
l’Environnement (France) / LAFARGE – ISO 14004 standard.
G E O M I N I N G G U I D E
Earthmoving (general considerations)
9
º
N
Objective
To minimize the costs of earthmoving through the use of appropriate
E
techniques and machinery.
N
The technical objectives for successful handling are mentioned in
I
Guideline nos. 10, 11 and 12.
L
E
Application
D
All quarries in which materials are stripped and handled.
I
Principles
U
Adhering to planned works which have been agreed with regulatory
G
bodies.
• Use equipment appropriate for each type of earthmoving operation.
• If possible, choose the right climate conditions to handle materials.
• Coordinated rehabilitation can minimize intermediate storage and
double handling of materials.
• Provide some access roads or paths: this must be planned early to
avoid additional costs.
Costs
Blasting: 0.40 to 0.60 €/t (can be necessary for waste from crystalline
rock quarries).
Loading + transport + grading: 1.5 €/m3.
Extraction: 0.50 €/t if necessary, with a shovel.
Loading: 0.30 to 0.40 €/t.
Bulldozer: 800 €/day.
G E O M I N I N G G U I D E
Earthmoving (general considerations)
List of reference documents
B. ODENT, M. LANSIART 1999, Remise en état des carrières : principes
généraux, recommandations techniques et exemples par types
d’exploitation, Ministère de l’Aménagement du Territoire et de
l’Environnement (France), 64 pages.
Experts to contact
114
Name Division/region/sector Country Phone n°
Arnaud COLSON Aggregates France 33 1 40 95 69 30
Ron FOSTER Aggregates UK 44 1 530 241 088
Roger HYNES Aggregates UK 44 1 707 356 000
Frédéric THOUE Cement CTI 33 4 74 82 18 04
Ghislain JOUBAND Gypsum France 33 1 60 26 64 04
G E O M I N I N G G U I D E
Soil Handling
0
1
º
Objective
N
Preserve the quality and productivity of soil.
E
Application
N
Quarries in which soil is handled, stockpiled or returned to the site.
I
L
Principles
E
• Segregate materials whenever possible: at least topsoil, and possibly
D
subsoil if such soil level can be distinguished.
I
• Soil handling requires appropriate climatic conditions.
U
• Avoid excessive handling, to preserve soil integrity and minimize costs.
G
List of proven techniques available
• Comply with planning conditions, which may specify moisture criteria
and machinery to be used.
• If topsoil and subsoil can be distinguished from each other, the two
materials must be removed separately, and replaced in sequence to
restore the soil profile. In some cases, when the topsoil layer is too thin,
both layers can be removed as one.
• Topsoil and subsoil thickness vary from site to site. Consult soil surveys 115
or ask restoration managers or suitably qualified people.
• Climate conditions: the soil should not be handled when it is too wet or
too dry, to avoid compaction and loss of structure. The ideal moisture
content or soil plasticity limits are based on local knowledge, as soil
characteristics vary from region to region.
• For nature conservation objectives, it can be better to strip topsoil after
native vegetation has set seed, in order to maximize the stores NdT:
seeds in the soil.
• If possible, soil must be placed directly on areas to be reclaimed.
• If soil must be stored, the location of stockpiles must be planned to
avoid excessive handling. Stockpiles must be close to areas to be
reclaimed, and away from drainage channels. They must not exceed
2 to 3 m height (according to the type of soil and climate). When
stored for long periods of time (more than 1 year), topsoil piles must
be seeded and stabilized to protect the soil from erosion, discourage
weeds and maintain active microorganisms.
• Once the soil has been placed on the site or stockpiled, heavy
machinery must not be allowed to travel over it.
Costs
See Guideline nº 9.
G E O M I N I N G G U I D E
Soil Handling
List of reference documents
MICHALSKI, M.F.P. et al.
1987, Rehabilitation of pits and quarries for fish and wildlife, Ministry
of Natural Resources of Ontario, Land Management Branch, 59 pages.
STROHMAYER, Patti
1999, Soil stockpiling for reclamation and restoration activities after
mining and construction, University of Minnesota, Department of
Horticultural Science, H5015 Restoration ecology,
Restoration and Reclamation Review 1999 @
www.hort.agri.umn.edu/ h5015/rrr.htm.
116
Site Division Region/dep. Country Comment
BUCKDEN Aggregates Cambridgeshire UK
PRASVILLE Aggregates Eure-et-Loir France Agricultural
rehabilitation
FRANGEY Cement Yonne France
MAZAN Gypsum Vaucluse France Management of
soil deficit
Experts to contact
Name Division/region/sector Country Phone n°
Ron D. FOSTER Aggregates UK 44 1 530 241 088
Roger HYNES Aggregates UK 44 1 707 356 000
Hervé CHIAVERINI Aggregates France 33 2 32 54 70 70
Stephan NICOLAY Roofing Germany 49 61 71 61 24 36
Khalid SAMAKA Cement France 33 3 86 54 61 77
Jean-Pierre GRASSI Gypsum France 33 4 90 69 71 14
Jean-Guy LEVAQUE Cement North America 1 514 738 1202
G E O M I N I N G G U I D E
Overburden / Waste rock
1
1
º
Objective
N
To optimize handling by placing overburden or waste rock in its final
location.
E
To maintain availability and quality of materials for rehabilitation.
N
I
Application
L
Any quarry / All quarries.
E
D
Principles
I
• If possible, handle overburden/waste rock only once.
• The implementation of the rehabilitation plan should take visual
U
impact into account, and preserve the accessibility of reserves.
G
• Overburden storage must conform to a stable engineering design.
• Avoid any erosion or landslide hazard.
• Avoid compaction, in the case of agricultural or forestry restoration.
Costs
See Guideline nº 9.
G E O M I N I N G G U I D E
Overburden / Waste rock
List of reference documents
CFEG
October 1994, Projet de comblement d’un talweg : étude géotechnique
(Rivolet Quarry, Rhône, France) – available at Millery (France).
BRGM
March 1990, Carrière de La Patte (Rhône, France) : établissement du
projet de stabilisation et de stockage de stériles – available at Millery
(France).
CETE Lyon
November 1992, Carrière de La Patte (Rhône, France) : mise en dépôt
de matériaux – available at Millery (France).
MICHALSKI, M.F.P. et al.
1987, Rehabilitation of pits and quarries for fish and wildlife, Ministry
of Natural Resources of Ontario, Land Management Branch, 59 pages.
STROHMAYER, Patti
1999, Soil stockpiling for reclamation and restoration activities after
mining and construction, University of Minnesota, Department of
Horticultural Science, H5015 Restoration ecology, Restoration and
Reclamation Review 1999 @
www.hort.agri.umn.edu/h5015/rrr.htm.
118
List of show cases for this guideline
Site Division Region/dep. Country Comment
QUATRO BARRAS Aggregates Curitiba Brazil
RIVOLET Aggregates Rhône France Stability study for
a future pile
MOUNTSORREL Aggregates UK
MATOZINHOS Cement Minas Gerais Brazil
ST-CONSTANT Cement Québec Canada 3D golf course
ST-PIERRE-LA-COUR Cement Mayenne France
VILLEVAUDE Gypsum Seine-et-Marne France Management of
soil deficit
Experts to contact
Name Division/region/sector Country Phone n°
Jean-Luc BOURGUET Aggregates France 33 1 40 95 69 30
Jean-Christophe Cement France 33 2 43 66 44 47
FAUCHADOUR
Ghislain JOUBAND Gypsum France 33 1 60 26 64 04
Jaïr FERNANDES Cement Brazil 55 21 217 31 00
Jean-Guy LEVAQUE Cement North America 1 514 738 1202
G E O M I N I N G G U I D E
Grading and Contouring
2
1
º
N
Objective
Create stable landforms that can be integrated into the existing
E
environment and landscape.
N
Application
I
L
All quarries.
E
Principles
D
The proposed landforms should take the following aspects into
I
account:
U
– local/regional geomorphology,
G
– proposed restoration design (included in planning permission),
– stability of the materials deposited,
– soil erosion hazards,
– biodiversity,
– integration within the surrounding landscape (see Guideline
nº 14), whether final landforms are natural-looking or not: some
artificial cliffs are now even classified as valuable features that
must be protected.
119
G E O M I N I N G G U I D E
Grading and Contouring
Costs
Bulldozer, grader or shovel: 600 to 800 €/day.
Experts to contact
Name Division/region/sector Country Phone n°
Bernard BOURGUE Aggregates France 33 4 95 09 45 00
Ron D. FOSTER Aggregates UK 44 1 530 241 088
Roger HYNES Aggregates UK 44 1 707 356 000
Rogelio DUPONT Cement France 33 2 32 79 20 40
Pierre MATEU Gypsum France 33 1 60 26 64 04
Stephan NICOLAY Roofing Germany 49 6171 61 24 36
Jean-Guy LEVAQUE Cement North America 1 514 738 1202
G E O M I N I N G G U I D E
Landscape Integration of Visual
3
1
and Acoustic Barriers
º
N
Objective
E
Integrate permanent visual and acoustic barriers into the rehabilitation
N
plan.
I
Application
L
This practice can be applied to sites where permanent visual and
E
acoustic barriers have to be set.
D
I
Principles
U
• Mask critical viewpoints of the future or existing quarry.
G
• Integrate barriers into the surrounding environment (see Guideline
nº 14).
• If possible, create these barriers before opening the site, especially if
the barriers are intended to be built or topped with vegetation.
Costs
See Guideline nº 9 (earthmoving), Guideline nº 20 (seeding), Guideline
nº 21 (planting).
G E O M I N I N G G U I D E
Landscape Integration of Visual
and Acoustic Barriers
List of show cases for this guideline
Site Division Region/dep. Country Comment
BAIXAS Aggregates Pyrénées- France Visual berm
Orientales
MOUNTSORREL Aggregates Leicestershire UK
ST-CONSTANT Cement Québec Canada
LE HAVRE Cement Seine-Maritime France Natural relief
CARRESSE Gypsum Pyrénées- France Visual berms
Atlantiques
WHITLINGHAM Aggregates Norfolk UK
HOPPEGARTEN Roofing Brandenburg Germany
Experts to contact
Name Division/region/sector Country Phone n°
Bernard BOURGUE Aggregates France 33 4 95 09 45 54
Yves DERREAL Cement France 33 1 49 11 40 40
122 Jean-Louis BARON Gypsum France 33 5 59 38 49 40
Stephan NICOLAY Roofing Germany 49 6171 61 24 36
Jean-Guy LEVAQUE Cement North America 1 514 738 1202
Ron FOSTER Aggregates UK 44 1 530 241 088
G E O M I N I N G G U I D E
Landscape Integration
4
1
º
Objective
N
To integrate the site into the surrounding landscape, during and after
mineral extraction.
E
N
Application
I
All quarries and sand and gravel pits.
L
E
Principles
D
• Define the landscape context: criteria based on physical, historical,
I
social and biological characteristics of the site and region.
U
• Determine the site characteristics.
• Establish a list of skilled landscape experts according to the region.
G
• Be wary of trends (e.g., regular alignments of conifers are nowadays
inadvisable in many cases): solutions must be adapted to specific site
conditions reflected in the inventories.
Costs
Landscape studies with visual simulation: about 7 000 to 20 000 € (see
Guideline nº 2 and 3).
G E O M I N I N G G U I D E
Landscape Integration
COMON Marie-Laure
1998, Paysage et aménagement de carrières, UNPG
Comité National de la Charte (France) – available at Issy.
Experts to contact
Name Division/region/sector Country Phone n°
Bernard BOURGUE Aggregates France 33 4 95 09 45 00
G E O M I N I N G G U I D E
Soil Erosion Control
5
1
º
Objective
N
Prevent erosion on re-created landforms in order to avoid landslides, loss
of soil and discharge of solids outside the site.
E
N
Application
I
All quarries and sand and gravel pits where soils need to be stabilized.
L
E
Principles
D
• Erosion control measures should be implemented as soon as possible.
I
• Erosion control should be properly engineered.
U
• Remediation is much more expensive than prevention.
• Gentle slopes, where possible, are cheaper and more efficient than
G
more sophisticated products.
• Take the main hydrological network into account and maintain it if
possible.
• Take erosion control techniques into account prior to earthmoving
operations.
• Adapt the techniques to climate conditions: the erosion hazard is
higher in a Mediterranean climate than in an oceanic one.
125
List of proven techniques available
• Grading of slopes and general topography management is the main
factor of erosion control (Guideline nº 12).
• Bioengineering:
– Some plants have an appropriate root system to stabilize soils. They
can be set up by the following means: seeding (see Guideline nº 20),
planting (see Guideline nº 21), live staking or live fascine.
– Slopes with slumps, headcuts and gullies can also be repaired by
branch packing (wood stakes + layers of vegetative cuttings
interlaid with compacted soil).
• Manufactured erosion control products:
– Mulches: degradable material consisting of straw, hay and other
plant debris, possibly sprayed with a bonding agent, or even
applied hydraulically (hydromulches).
– Meshes, used to stabilize slopes or to prevent soil erosion:
degradable open weave geotextile (coconut fiber, jute) rather than
polypropylene.
– Erosion control blankets.
• River-erosion hazard near sand and gravel pits: see Guideline nº 16.
• Rip-rap (massive stone wall), gabion or armored stone.
• Wind-breaks for wind erosion.
G E O M I N I N G G U I D E
Soil Erosion Control
Costs
– seeding: see Guideline nº 20.
– planting: see Guideline nº 21.
– mulches: 0.1 €/m2.
– geotextile: 1 €/m2
Experts to contact
Name Division/region/sector Country Phone n°
Bernard BOURGUE Aggregates France 33 4 95 09 45 00
Bruno BIANCO Cement France 33 4 72 54 11 65
Jean-Louis BARON Gypsum France 33 5 59 38 49 40
G E O M I N I N G G U I D E
Shore Protection
6
1
º
Objective
N
To avoid scour of the banks of pits, sea shores and riverbanks due to
wave action, currents and water level changes, as well as regressive
E
erosion during and after exploitation.
N
I
Application
L
All sites located on shores.
E
D
Principles
I
• Use shore protection techniques to reduce wave action, encourage
sediment deposition, and stabilize the shore.
U
• Adapt protection techniques to river dynamics.
G
• Avoid any obstacle to riverfloods.
• Critical factors for shoreline and bank stability are:
– lake level and geometry,
– groundwater flow direction and velocity,
– surface roughness,
– prevailing winds,
– climatic conditions and seasonal weather variation.
Reduce wave action and stabilize the shore or riverbank, especially at
vulnerable points. 127
G E O M I N I N G G U I D E
Shore Protection
Costs
• rock blocks: € 25 – 40/t (supply +placing).
Experts to contact
Name Division/region/sector Country Phone n°
Dominique EVRARD Aggregates France 33 4 72 24 46 25
Jean-Guy LEVAQUE Cement Canada 1 514 738 1202
G E O M I N I N G G U I D E
Storm Water Management
7
1
º
Objective
N
Control major discharge of water collected in the quarry.
E
Application
N
All quarries.
I
L
Principles
E
Prepare a water management plan.
D
• Storm water control: establish drainage strategies to avoid
I
concentration of streams and therefore erosion (see Guideline nº 15)
U
and excessive suspended solids.
G
• Ensure that long-term devices (drainage layers, pipes, paths…) cannot
be threatened by natural phenomena: where possible, choose devices
that require minimal maintenance.
Costs
Site specific.
G E O M I N I N G G U I D E
Storm Water Management
List of showcases for this guideline
Site Division Region/dep. Country Comment
BELLEGARDE Aggregates Gard France Flood retention
basins
MARFIELD Aggregates North Yorkshire UK Regulation of water
level in ponds
INHAUMA Aggregates Rio Brazil
MATOZINHOS Cement Minas Gerais Brazil
MONTES-CLAROS Cement Brazil Collection of water
for the plant needs
PORT-LA-NOUVELLE Cement Aude France
MAZAN Gypsum Vaucluse France Flood control basin
HOPPEGARTEN Roofing Brandenburg Germany
Experts to contact
Name Division/region/sector Country Phone n°
Bernard BOURGUE Aggregates France 33 4 95 09 45 54
Jaïr FERNANDES Cement Brazil 55 21 217 31 00
Jean-Pierre GRASSI Gypsum France 33 4 90 69 71 14
130
David PARK Aggregates UK 44 740 65 44 61
G E O M I N I N G G U I D E
Water Quality Protection
8
1
º
Objective
N
To preserve the quality of aquifers and bodies of water whenever lakes
and wetlands are created.
E
N
Application
I
All quarries having a link with aquifers and natural bodies of water.
L
E
Principles
D
• Avoid any operation that could generate pollution.
I
• Strict management of any landfill operations taking place in wet
U
environments (lakes, marshes, etc.). See Guideline n° 22.
• Monitor water quality.
G
• Lake size and depth have an influence on nutrient levels.
• Quarry management can have a major influence on water quality.
Costs
• Piezometer: € 2 000
• Water sampling and analysis: € > 400
• Hydrogeological surveys: € > 50 000
Jean-Luc BOURGUET
1997, Chronique de la piézométrie et de la qualité des eaux de la nappe
du Garon, Internal document, available at Millery (France).
Philippe BARDOT
1999, Rapport d’expertise hydrogéologique : compatibilité des
exploitations des ressources en granulats et en eau de la vallée du Garon,
35 pages + annexes, available at Millery (France).
G E O M I N I N G G U I D E
Water Quality Protection
Bernard DONVILLE
2000, La Carrière de Saint-Caprais (Haute-Garonne) : 20 ans de suivi
hydrogéologique – LAFARGE GRANULATS – available at Issy or Toulouse
(France).
Experts to contact
Name Division/region/sector Country Phone n°
Jean-Luc BOURGUET Paris France 33 1 40 95 69 30
G E O M I N I N G G U I D E
Soil Preparation
9
1
º
Objective
N
To safeguard and/or improve soil characteristics and where possible
to establish self-sustaining vegetation.
E
N
Application
I
All quarries with soil used for rehabilitation.
L
E
Principles
D
• Preserve, restore and/or enhance soil properties in accordance with the
I
initial characteristics.
U
• Original topsoil should be preserved.
• Encourage natural regeneration processes in line with biodiversity
G
objectives.
• Monitor crop production to adjust fertilization.
• Preparation should not be at the expense of the environment.
Costs
– Chemical fertilizers: added to hydroseeding: additional cost
about € 0.1/m2.
agricultural technique: € 0.02 /m2.
– Amendments: lime, about € 400 /ha.
G E O M I N I N G G U I D E
Soil Preparation
CEMAGREF TPG
1999/2000, Techniques de réaménagement agricole et forestier.
MICHALSKI, M.F.P. et al.
1987, Rehabilitation of pits and quarries for fish and wildlife,
Ministry of Natural Resources of Ontario, Land Management Branch,
59 pages.
REUTER, Ron
1997, Sewage sludge as an organic amendment for reclaiming surface
mine wastes, University of Minnesota, Department of Horticultural
Science, H5015 Restoration ecology, Restoration and Rehabilitation
Review 1997 @
www.hort.agri.umn.edu/h5015/rrr.htm
STURGES, Susan
1997, The use of mycorrhizae in mined land rehabilitation, University of
134 Minnesota, Department of Horticultural Science, H5015 Restoration
ecology, Restoration and Rehabilitation Review 1997 @
www.hort.agri.umn.edu/ h5015/rrr.htm
Experts to contact
Name Division/region/sector Country Phone n°
Hervé CHIAVERINI Aggregates France 33 2 32 54 70 75
Yves DERREAL Cement France 33 1 49 11 40 40
Jean-Guy LEVAQUE Cement North America 1 514 738 1202
Ron FOSTER Aggregates UK 44 1 530 241 088
G E O M I N I N G G U I D E
Seeding
0
2
º
Objective
N
To establish vegetation by seeding in reclaimed areas.
E
Application
N
All quarries.
I
L
Principles
E
1. Natural recolonization:
D
– organic topsoil contains residual seed bank,
I
– recolonization can be achieved by the natural spread of seeds.
U
2. Seeding:
G
– indigenous seeds harvested in the vicinity,
– commercial seeds bought for this specific purpose (check origin).
Costs
Agricultural seeding of purchased seeds (including seeds): 0.02 €/m2.
Hydroseeding: 0.3 to 0.4 €/m2.
Additional costs: harvest of local seeds: 0.02 to 0.2 €/m2,
difficult access or very poor topsoil up to 0.2 €/m2.
CEMAGREF
2000 (in progress), Synthèse bibliographique des techniques
d’aménagement agricole et forestier.
G E O M I N I N G G U I D E
Seeding
List of showcases for this guideline
Site Division Region/dep. Country Comment
AIX-EN-PROVENCE Aggregates Bouches-du- France Ssuccessful seeding in
Rhône dry climate conditions
TOSNY / BERNIERES Aggregates Eure France
GUERNES/
SANDRANCOURT Aggregates Yvelines France
LLYNCLYS Aggregates Shropshire UK Natural regeneration
WEST DEEPING Aggregates Lincolnshire UK Agriculture
QUATRO BARRAS Aggregate Curitiba Brazil
BAMBURI Cement Mombasa Kenya
VAL D’AZERGUES Cement Rhône France
VILLEVAUDE Gypsum Val d’Oise France Seeding of
intermediate quarry
slopes
RAHMSTORF Roofing Germany
Experts to contact
Name Division/region/sector Country Phone n°
136 Pierre de PREMARE Aggregates France 33 1 44 34 11 11
Bernard BOURGUE Aggregates France 33 4 95 09 45 00
Hervé CHIAVERINI Aggregates France 33 2 32 54 70 75
Ron FOSTER Aggregates UK 44 1 530 241 088
Yves DERREAL Cement France 33 1 49 11 40 40
Pierre MATEU Gypsum France 33 1 60 26 64 04
Stephan NICOLAY Roofing Germany 49 6171 61 24 36
René HALLER Cement Kenya 254 11 486 155
G E O M I N I N G G U I D E
Tree and Shrub Planting
1
2
º
Objective
N
To enable tree and shrub species to develop on reclaimed areas.
E
Planting can be used for landscaping, bio-diversity, commercial forestry,
N
orchards and to develop an amenity, etc.
I
L
Application
E
All quarries, whenever possible.
For natural recolonization see Guideline nº 20.
D
I
Principles
U
Select the indigenous or exotic species, the age of the plant stock and
G
the planting pattern according to:
– the final use and landscape design (distinguish between forestry
and amenity),
– the physical characteristics of the substrate,
– the climate.
Take the planting season into account.
Prepare the soil and subsoil (ripping, weeding, gyro-crushing, plowing,
plant pits) In the case of an ecological objective, opt for a medium-
term reconstitution of a consistent biotope (diversity, edge effects) 137
rather than a massive and immediate reforestation by uniform conifers,
for example.
G E O M I N I N G G U I D E
Tree and Shrub Planting
Costs (forestry)
Plant € 0.7 to 1/unit
Protection € 0.2 to 0.3/unit
Operation € 0.6 to 0.7/unit
Experts to contacts
Name Division/region/sector Country Phone n°
Bernard BOURGUE Aggregates France 33 4 95 09 45 00
Arnaud COLSON Aggregates France 33 1 40 95 69 30
Loïc ROYERE Aggregates France 33 4 72 24 46 25
Pierre MATEU Gypsum France 33 1 60 26 64 04
René HALLER Cement Kenya 254 11 486 155
Georg THOMAS Roofing Germany 49 6171 61 26 42
Jaïr FERNANDES Cement Brazil 55 21 217 31 00
Ron FOSTER Aggregates UK 44 1 530 241 088
G E O M I N I N G G U I D E
Landfilling
2
2
º
Objectives
N
To create landforms by filling in excavations with imported inert landfill
materials while preserving the quality of soil and subsoil.
E
N
Application
I
Any site lacking enough internal fill material to implement the
L
rehabilitation plan.
E
D
Principles
I
• Assess the sources of input and optimize the costs of transport.
• This activity must be compliant with regulations.
U
• Rigourous control of environmental quality.
G
• Assess the geological (hydrogeological & geotechnical) capability
to receive such materials.
Costs
Earthmoving: see Guideline nº 9.
G E O M I N I N G G U I D E
Landfilling
List of show cases for this guideline
Site Division Region/dep. Country Comment
CHEVRIERES Aggregates Oise France Diversified backfill
and run-in backfill
procedures
ST FARGEAU- Aggregates Seine-et-Marne France 60 ha of backfill,
PONTHIERRY 180 villa plots
HILL FARM Aggregates Leicestershire UK
PAULDING Cement Ohio USA CKD site
VILLIERS-ADAM Gypsum Val-d’Oise France Underground mine
filling with
earthworks and
demolition waste
FORCHHEIM Roofing Bavaria Germany 20 ha of backfill
Experts to contact
Name Division/region/sector Country Phone n°
Pierre de PREMARE Aggregates France 33 1 44 34 11 11
Jean-Guy LEVAQUE Cement North America 1 514 738 1202
Pierre MATEU Gypsum France 33 1 60 26 64 04
140
Stephan NICOLAY Roofing Germany 49 61 71 61 24 36
G E O M I N I N G G U I D E
Follow-up Committee
3
2
º
Objective
N
To communicate and publicize achievements and progress with respect
to the rehabilitation plan.
E
To prevent or resolve crises within the neighborhood.
N
I
Application
L
Any quarry; this concerns both rehabilitation and operation.
E
D
Principles
I
Committee should include representatives of local stakeholders, primarily
U
neighbors and local authorities.
G
Organize meetings on site to inform people regularly about our
activities.
Listen to criticisms in order to improve the implementation details of the
rehabilitation project.
Costs
Site specific.
G E O M I N I N G G U I D E
Follow-up Committee
Braas Dachsysteme GmbH
Records of the project Kiessandtagebau Münchenberg-Wildermann,
roof tile work – Hoppegarten, files stored at the unit.
Product technology and Raw Materials (DP).
Kurt Fleckenstein
Aktuelle Probleme des Rohstoffabbaues. Verlagsgesellschaft Grüter,
Hannover, 121 pages.
Christoph Werner
1998, Akzeptansmanagement,
Journal “Steinbruch und Sandgrube 06/98”, pages 24-26.
B. Wohlrab et. al
1995, Oberflächennahe Rohstoffe. Gustav Fischer Verlag Jena, Stuttgart,
304 pages (ISBN 3-334-60963-4).
Experts to contact
Name Division/region/sector Country Phone n°
Bernard BOURGUE Aggregates France 33 4 95 09 45 00
Hervé CHIAVERINI Aggregates France 33 2 32 54 70 70
Stephan NICOLAY Roofing Germany 49 61 71 61 24 36
Pierre ARDANT Cement France 33 5 45 23 39 15
Jean-Pierre GRASSI Gypsum France 33 4 90 60 71 14
Ron FOSTER Aggregates UK 44 1530 242 151
G E O M I N I N G G U I D E
Open Days, Visits
4
2
º
Objective
N
To improve general relations with site neighbors by presenting our
rehabilitation achievements to a broad public.
E
N
Application
I
Any quarry undergoing rehabilitation
L
E
Principles
D
Organization
I
• Invitation, advertising
U
• Safety
• Site preparation
G
• Internal information
• Formation and training of team.
Content
• Rehabilitation plan
• Rehabilitation techniques
• Monitoring tools
• Guided tours. 143
G E O M I N I N G G U I D E
Open days, visits
Costs
€ 5 to 25 k/day
• Mobilization of Group employees (preparation + day).
• Rental of tents, tour buses, display equipment for exhibition, etc.
graphic communication: production of signs and boards, descriptive
sheets, brochures.
• Promotional gifts.
Experts to contact
Name Division/region/sector Country Phone n°
Dominique EVRARD Aggregates France 33 4 72 24 46 25
Hervé CHIAVERINI Aggregates France 33 2 32 54 70 70
Louis DESCOMBES Cement France 33 4 75 49 60 23
G E O M I N I N G G U I D E
Partnerships with
5
2
Conservation Groups,
º
N
Organizations and
E
Statutory Agencies
N
I
L
E
Objective
To enlist the participation of third parties for the development of
D
quarrying plan and rehabilitation objectives in order to utilize their
I
expertise, take their expectations into account and hear their points of
U
view.
G
Application
Any site in the Group, even in the absence of local pressure, provided
interested parties can be involved.
For instance, when the site represents a scientific – especially natural or
archeological – novelty or is of possible importance for tourism, leisure or
land use.
Principles 145
G E O M I N I N G G U I D E
Partnerships with
Conservation Groups,
Organizations and
Statutory Agencies
Nature Trust, Natural Regional Park where applicable, conservation
organizations, (see Guideline nº 29).
• Lease granted to this type of partner, see also Guideline nº 29.
• Tri-partite agreement between the owners of rented sites the partner
and LAFARGE.
• Authorization for research works, such as archaeological or geological
salvage excavations (e.g.: amber deposits at
CHEVRIERES/HOUDANCOURT).
• Archaeology: agreement with the appropriate public structure.
Costs
Extremely variable/main cost is related to time spent in preparing
partnership
146 • Amber: permitting access to deposit by pumping for the Natural
History Museum + participation in financing the research (€ 30 k).
• LPO/FIR Brittany (LAZ site): Arranging nesting facilities.
• CORA Rhône
1999, L’EFFRAIE nº 13 : La Gravière du Garon à Millery, document
available at Millery (France).
• Internal documents
Une découverte scientifique exceptionnelle : ambre de l’Oise – document
available at Issy, Verberie, Sandrancourt, Millery (France).
G E O M I N I N G G U I D E
Partnerships with
2
/
Conservation Groups,
5
2
Organizations and
º
N
Statutory Agencies
E
N
I
List of show cases for this guideline
L
• LAFARGE/WWF Partnership
E
D
Site Division Region/dep. Country Comment
I
HOUDANCOURT Aggregates Oise France Study of fossil
invertebrates in the
U
Sparnacian amber
G
( - 54 My)
LAZ Aggregates Finistère France Monitoring of bird of
prey nesting by
LPO/FIR Brittany
SANDRANCOURT Aggregates Ile-de-France France Agence des Espaces
Verts - Ile-de-France
SANDY Aggregates Bedfordshire UK
BESTHORPE Aggregates Nottinghamshire UK 147
Experts to contact
Name Division/region/sector Country Phone n°
Pierre DE PREMARE Aggregates France 33 1 44 34 11 11
Patrick ROLLAND Aggregates France 33 2 99 47 39 61
Irv MAURER LCM: aggregates USA 1 410 847 32 00
Louis DESCOMBES Cement France 33 4 75 49 60 23
Georg THOMAS Roofing Germany 49 6171 61 26 42
G E O M I N I N G G U I D E
Terminal Cleaning
6
2
º
Objective
N
To prepare for final rehabilitation by removing all disused production
facilities and waste material, before the partial or complete closure of
E
the quarry.
N
I
Application
L
All quarries of the Group ready to be totally or partly rehabilitated.
E
D
Principles
I
• List all necessary cleaning operations.
• Plan for cleaning of site.
U
G
Many site cleaning procedures used during operations can also apply to
terminal cleaning:
• Disposal of any items that have become useless or undesirable for
esthetic or environmental reasons.
• Prior selective sorting on site and storage as required.
• An environmental audit to determine whether there are any issues that
require special attention or cleanup, particularly prior to sale of the site
• Maintenance of sufficient staff and budget until the site is permanently
149
rehabilitated as planned.
Costs
Provide for the following expenses:
– disposal of used oils: free for a sufficient volume;
– dismantling of the installations: see documents below;
– environmental remediation where necessary.
G E O M I N I N G G U I D E
Terminal Cleaning
List of reference documents
Internal documents:
LAFARGE GRANULATS, Direction Environnement et Ressources Minérales
Nov. 1999 – Coûts des travaux de remise en état, provisionnables au
31.12.1999 – document available throughout the LAFARGE GRANULATS
Environment network (France).
LAFARGE GRANULATS
Dismantling and refurbishing of the port of Lyon-Vaise – notes available
at Millery (Rhône, France).
Experts to contact
Name Division/region/sector Country Phone n°
Loïc ROYERE Aggregates France 33 4 72 24 46 25
Louis DESCOMBES Cement France 33 4 75 49 60 23
Philippe CHEVALIER Gypsum France 33 4 90 21 21 81
Georg THOMAS Roofing Germany 49 6171 61 26 42
G E O M I N I N G G U I D E
Site Security
7
2
º
Objective
N
To limit the risks of accident after site closure.
E
Application
N
All quarries.
I
L
Principles
E
• Control all hazardous points (ponds, benches and faces).
D
• Whenever hazards cannot be completely eliminated, access
I
must be forbidden and the area must be enclosed.
U
G
List of proven techniques available
• Fencing: using either barbed wire, impenetrable hedge barriers or wire
netting (except in flood areas).
• Stakes: either of wood or metal with anchoring (for hard outcrops).
• Berms: with constraints as to height and direction in flood areas.
• Entrances: either barriers or gates (more costly but more efficient).
• Signage: mark out property limits. 151
• Surveillance: regular checking (monthly or even weekly) of fencing
especially at points accessible to outside vehicles.
A thorn hedge can be planted along the fence, best at the beginning of
mining operations, so as to develop a more lasting and impenetrable
physical obstacle.
Costs
Fencing: € 5/m with wood stakes every 3 m, 6 rows of barbed wire,
€ 15/m with metal stakes every 3 m, 6 rows of barbed wire.
G E O M I N I N G G U I D E
Site Security
List of show cases for this guideline
Many cases on our different operations.
Experts to contact
Legal consequences must not be overlooked, therefore, the legal
department experts should be called upon as needed.
152
G E O M I N I N G G U I D E
Information/Communication with
8
2
Stakeholders on Closing Issues
º
N
Objective
E
To obtain formal approval of authorities, associations and neighbors
N
about the rehabilitation implemented.
I
L
Use the Group’s rehabilitation references to earn broader approval by
E
these stakeholders regarding our activity, including new projects.
D
Application
I
All quarries that have just been totally or partly rehabilitated
U
G
Principles
• Present actual rehabilitation achievements rather than planned
projects (which can sometimes be modified).
• Explain the benefits to the local community of the rehabilitation
program implemented.
• Anticipate the questions and concerns of stakeholders.
• Ensure that the Group has honored its commitments, and highlight
this fact.
153
Costs
• Time devoted to meetings.
• Information panel: 200 to 1 000 €.
G E O M I N I N G G U I D E
Information/Communication with
Stakeholders on Closing Issues
LAFARGE – CSS
1993, Moisson-Freneuse (78) : valorisation forestière et écologique des
terrains réaménagés, 2 pages – available at Issy or Sandrancourt (France).
LAFARGE – CSS
1996, Guernes/Saint-Martin-la-Garenne (78) : un site paysager de valeur
écologique, 2 pages – available at Issy or Sandrancourt (France).
Experts to contact
Name Division/region/sector Country Phone n°
Bernard BOURGUE Aggregates France 33 4 95 09 45 00
Hervé CHIAVERINI Aggregates France 33 2 32 54 70 75
Francis STEPANOFF Aggregates France 33 2 99 14 87 14
Louis DECOMBES Cement France 33 4 75 49 60 23
G E O M I N I N G G U I D E
Finding Solutions to Manage
9
2
Sites Post Rehabilitation
º
N
Objective
E
To find solutions to ensure an acceptable long-term development of the
N
site through an adequate management scheme.
I
To avoid challenges to the future site use and the resulting impact on our
L
image.
E
D
Application
All quarries, especially those whose future use is related to nature
I
conservation, or other purposes of general interest.
U
G
Principles
• Technical conditions of rehabilitation must make it difficult to change
the final use of the site.
• Find an appropriate third party who will ensure long-term
management of the site according to agreed final use.
• If the quarry site is sold, agree on use and site management with future owner.
• Final use of site must be enacted in official documents on urban
planning and land-usage.
155
G E O M I N I N G G U I D E
Finding Solutions to Manage Sites
Post Rehabilitation
• Partnerships with farmers for an environnementally designed farming
(woodlands, hedges, specific agricultural practices…).
Costs
Varied and site specific.
Experts to contact
Name Division/region/sector Country Phone n°
Hervé CHIAVERINI Aggregates France 33 2 32 54 70 75
David DUBOIS Aggregates France 33 5 53 93 46 71
Claire MORICE Aggregates France 33 1 34 97 02 70
Ron FOSTER Aggregates UK 44 1 530 241 088
David PARK Aggregates UK 44 1 740 654 461
Yves DERREAL Cement France 33 1 49 11 40 77
Philippe CHEVALIER Gypsum France 33 4 90 21 81 81
Georg THOMAS Roofing Germany 49 6171 61 26 42
G E O M I N I N G G U I D E
Final Decision on Ultimate Use
0
3
of Quarry
º
N
Objective
E
To identify and implement the after-use project best suited to the
N
surrounding context.
I
To maximise the potential of the after-use of the site in the best cost
L
effective manner, if this after-use is different from the initial
E
rehabilitation objective (otherwise, see Guideline nº 2).
D
Application
I
All quarries ready to be partly or totally rehabilitated.
U
G
Principles
• Based on a global approach that considers the site in its context, strive
to seize opportunities for projects able to add value in both economic
and environmental terms.
• Remember: the type of rehabilitation project must take the geological
and hydraulic consequences of quarry operations into account.
• The management costs related to the chosen rehabilitation system, as
well as any additional revenue streams, must be integrated into project
157
economics.
Costs
See Guideline nº 2.
Feasibility studies if necessary (i.e.: water quality for fishing).
G E O M I N I N G G U I D E
Final Decision on Ultimate Use
of Quarry
List of show cases for this guideline
Site Division Region/dep. Country Comment
CHEVRIERES Aggregates Oise France Future fishing center
BROADWATER Aggregates UK Sailing
WATERFORD Aggregates UK (mentioned on
26th June)
GODMANCHESTER Aggregates UK Zoned fishing
KINGSWOOD NNR Aggregates UK Forestry
(Undug land)
Choose between: Aggregates UK Agriculture
PANSHANGER
COLE GREEN
SOMERSHAM
Choose between: Aggregates UK Housing and
FOXHOLES industrial
DOUBLEGATES development
SHALERSVILLE Aggregates USA Local water supply
Housing
development
MARTES Cement France
158
GAGNY Gypsum Seine-St-Denis France Housing and urban
park
MONHEIM Roofing Germany Football pitch
(KIESGRABEN)
Experts to contact
Name Division/region/sector Country Phone n°
Pierre PROY Aggregates France 33 3 44 38 30 00
Pierre DE PRÉMARE Aggregates France 33 1 40 95 69 33
Ron FOSTER Aggregates UK 44 1 530 241 088
Irv MAURER LCM (Aggregates) USA 1 410 847 3200
Louis DECOMBES Cement France 33 4 75 49 60 23
Francis HORTEMEL Corporate France 33 1 44 34 11 11
Stephan NICOLAY Roofing Germany 49 61 71 61 24 36
G E O M I N I N G G U I D E
Maintenance and Monitoring
1
3
º
Objective
N
To ensure the long-term viability of the rehabilitation program both
during and after quarry operations, in order to protect the Group’s
E
image and investment.
N
I
Application
L
This practice must be applied to all reclamation and landscaping work, as
E
long as LAFARGE group keeps control on the rehabilitated site.
D
Principles
I
Maintenance and monitoring are an integral part of any rehabilitation
U
program. Sufficient budgetary and human resources must therefore be
G
allocated to these aspects. They must be defined in a program and
coordinated by a project manager.
Maintenance and monitoring must be practiced to insure that
appropriate corrective measures are executed for all deficiencies that
may impair future uses. In case of sale, suitable information and
requirements must be transmitted to the buyer.
Nature Conservation
a. Produce and follow a management plan.
b. Keep an open mind and seek to enhance the site by further habitat
creation as appropriate.
c. Prepare a database of species and regularly review to identify
changes.
d. Issue periodic reports on the evolution of the site.
e. Seek the help of volunteers and associations to draw up the
inventory.
G E O M I N I N G G U I D E
Maintenance and Monitoring
Forestry & Woodland
a. Produce and follow a woodland management plan.
b. Entrust the management of woodlands to professionals.
Agriculture
a. Produce a 5 year forward plan of agricultural enhancement.
b. This plan is to ensure the soil structure improves and drainage is
effective.
c. Crop selection and management must be defined to improve soil
structure.
The quality of the rehabilitation program must be certified through
an agronomical assessment.
Experts to contact
Name Division/region/sector Country Phone n°
Hervé CHIAVERINI Aggregates France 33 2 32 54 70 70
Ron FOSTER Aggregates UK 44 1 530 241 088
Louis DECOMBES Cement France 33 4 75 49 60 23
Stephan NICOLAY Roofing Germany 49 61 71 61 24 36
G E O M I N I N G G U I D E