Part 3 Module 2 Quiz
Part 3 Module 2 Quiz
Question 1
Which of the following is true of project plans? Select all that apply.
0.75 / 1 point
They contain an explanation of why a project may not meet its goals.
They are a living artifact that serves as a roadmap for your team throughout the project.
Correct
A project plan is a living artifact that helps you document the scope, tasks, milestones, and overall
activities of the project. It serves as a roadmap for your team. The schedule is the central piece of a project
plan.
They are a compilation of a project’s documents that the project team uses to carry out project activities.
Correct
A project plan contains links to all of a project’s documentation and serves as a roadmap for the team
throughout the project. The central artifact in a project plan is the project schedule.
2.
Question 2
What are the basic elements that make up a project plan?
1 / 1 point
Correct
What goes into a project plan may vary from company to company, but most plans contain these five basic
elements.
3.
Question 3
As a project manager, you create a project plan. In the plan are tasks with clear descriptions, owners, and
due dates. In which section of the project plan do these tasks reside?
1 / 1 point
Budget
Management plans
Correct
The WBS allows the project manager and teammates to understand who is responsible for which tasks. It
also indicates when the project manager expects each task to be completed.
4.
Question 4
As a project manager, you create a project plan. In the plan are documents that help keep a project
organized and on track, particularly if a risk arises or a change occurs. In which section of the project plan
are these documents linked?
0 / 1 point
Management plans
Budget
Incorrect
The project scope describes the boundaries of a project and the project goals describe the desired
outcome of the project. Management plans, such as the change management plan, risk management plan,
and communication plan, are documents that keep a project organized and on track.