General Arrangment Details of Load Test Minor Bridge at - (CH-442+870)
General Arrangment Details of Load Test Minor Bridge at - (CH-442+870)
SECTION A-A THE TEST VEHICLE SHOULD BE TAKEN OFF THE BRIDGE AND INSTANTANEOUS DEFLECTION RECOVERY AND DEFLECTION
RECOVERY FIVE MINUTES AFTER THE REMOVAL OF THE LOAD SHOULD BE NOTED.
13. NET DEFLECTION OBSERVED SHALL BE CORRECTED WITH DUE CONSIDERATION TO DEFLECTION OF UNLOADED
SCALE 1:100 STRUCTURE AT PARTICULAR TIME.
14. TEMPERATURE TO BE RECORDED AND DATA TO BE USED FOR APPLYING
TEMPERATURE CORRECTION TO DEFLECTION SHALL BE AS PER IRC
A1 A2 SP:-51, APPROPRIATE ROTATION CORRECTION SHALL BE APPLIED TO DEFLECTIONS.
15. TO ACCOUNT FOR BEARING SET. DIAL GAUGE SHALL ALSO BE PLACED
B NEAR EACH BEARING LOCATION UNDER DIAPHRAGMS TO TAKE READINGS.
CL OF EXP. GAP CL OF EXP. GAP THIS IS REQUIRED TO DETERMINE NET DEFLECTION OF SUPERSTRUCTURE.
20000 16. PRIOR TO STARTING OF TESTING, THE THEORETICAL DEFLECTIONS FOR
VARIOUS STAGES OF LOADING SHALL BE CALCULATED AND PLOTTED AT
POINTS OF INTEREST ON THIS GRAPH, THE ACTUALLY OBSERVED
DEFLECTIONS SHALL BE PLOTTED DURING THE PROGRESS OF TESTING.
5000
FOR NEXT 24 HOURS.
Y 17. ACCEPTANCE CRITERIA FOR THE BRIDGE IS THE LEAST OF THE FOLLOWING:-
17.1. THE LOAD CAUSING A DEFLECTION OF 1/800 OF THE SPAN IN ANY OF THE MAIN GIRDERS FOR SIMPLY SUPPORTED
SPANS OR FOR
1930
CANTILEVER SPANS THE LOAD CAUSING THE DEFLECTION OF 1/800
V2A V1A OF THE CANTILEVER SPAN IN ANY OF THE MAIN GIRDERS, THE
ROTATION OF PIER SHOULD BE ACCOUNTED FOR WHILE CALCULATION
(CARRIAGEWAY)
THE DEFLECTION.
(DECK WIDTH)
17.2. THE LOAD CAUSING TENSION CRACKS OF WIDTH MORE THEN 0.3mm IN ANY OF THE GIRDER FOR NORMAL CASES
2100 AND 0.2mm FOR STRUCTURES EXPOSED TO VERY SEVERE AND ADVERSE CONDITIONS.
12000
A A
2000
7000
17.3. THE LOAD CAUSING APPEARANCE OF VISIBLE NEW DIAGONAL CRACKS
OF WIDTH MORE THAN 0.3mm FOR NORMAL CASES AND 0.2mm FOR
STRUCTURES EXPOSED TO VERY SEVERE AND ADVERSE CONDITIONS OR OPENING/WIDENING OF EXISTING CRACKS
CLOSE TO THE
SUPPORTS ON CONCRETE GIRDERS.
17.4. THE LOAD AT WHICH RECOVERY OF DEFLECTION ON REMOVAL OF
1930
V2B V1B TEST LOAD IS NOT LESS THAN 75 PERCENT FOR R.C.C. STRUCTURES,
85 PERCENT PRE-STRESSED CONCRETE STRUCTURES, TEMPERATURE
CORRECTION BE CONSIDERED AS PER PROVISIONS CONTAINED IN IRC:SP:51.
18. THE NEXT INCREMENTAL LOADING SHOULD BE ADDED ONLY AFTER THE DEFLECTION UNDER PERVIOUS LOAD HAVE
5000
2100 STABILES AND ALL STIPULATED OBSERVATIONS ARE COMPLETED.
SCALE 1:100
50 3.18 5.04 5.96 5.26 3.15 17.9 THE LVDT / DIAL GAUGES IS NOT LOST. SPINDLE EXTENSION SHALL BE FIXED TO
COURSE
TAKE CARE OF THIS ASPECT
100 Ø PVC 75 3.24 6.04 7.52 6.35 3.23 18.7
SLOPE 2.5% SLOPE 2.5% PIPE (TYP.)
100 3.35 7.61 9.52 7.96 3.35 18.8
DRAINAGE
SPOUT (TYP.)
1350 3600
G1 G2 G3 G4
OWNER ENGINEERING : SAFETY CONSULTANT : EPC CONTRACTOR: PROOF CONSULTANT: PROJECT: TITLE :
DRAWN BY : ISN GENERAL ARRANGMENT DETAILS OF
KQC GLOBAL CONSULTANTS PVT. LTD.CONSTRUCTION & UPGRADATION OF EXISTING ROAD LOAD TEST MINOR BRIDGE
125m TO 2-LANE WITH PAVED SHOULDERS FROM KM 430.000
DESIGNED BY : SK AT DESIGN CH.442+870
301 Kautilya, Sector 14, Dwarka, TO KM 468.000 OF CHAMOLI TO PAINI (EXCLUDING KM
New Delhi, Delhi 110075 437.625 TO KM 437.775, KM 458.900 TO KM 459.475 AND
KM 464.425 TO KM 464.525) OF NH-07 UNDER APPROVED BY : DK DRG. NO. : KQC_ CP_MN20_ BRIDGE_022
MANOMAV ENGINEERS www.kqcglobalconsultants.com
National Highways & Infrastructure NKG INFRASTRUCTURE LTD. CHARDHAM PARIYOJNA ON EPC BASICS IN THE STATE
Development Corporation Ltd. (NHIDCL) PVT. LTD. MEPL OF UTTRAKHAND (PKG-III) REV. DATE DESCRIPTION SCALE : REVISION : R0 MAR.-2022