0% found this document useful (0 votes)
398 views

Base Plate Detail: A B C D

This document provides general notes and specifications for masonry and concrete construction. It specifies that (1) plans and specifications should complement each other, with conflicts referred to the city engineer, (2) construction notes and details apply to all unless otherwise noted, and (3) concrete hollow blocks must not exceed 80 pounds per cubic foot in unit weight. It also provides requirements for lintel beams bearing from wall openings and reinforcement of concrete block walls.

Uploaded by

aj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
398 views

Base Plate Detail: A B C D

This document provides general notes and specifications for masonry and concrete construction. It specifies that (1) plans and specifications should complement each other, with conflicts referred to the city engineer, (2) construction notes and details apply to all unless otherwise noted, and (3) concrete hollow blocks must not exceed 80 pounds per cubic foot in unit weight. It also provides requirements for lintel beams bearing from wall openings and reinforcement of concrete block walls.

Uploaded by

aj
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

GENERAL NOTES & SPECIFICATIONS :

A B C D

A. GENERAL : C. MASONRY AND CONCRETE HOLLOW BLOCK


1. THE PLANS, AND SPECIFICATIONS SHALL BE
F2-C2 F2-C2 F2-C2 F2-C2 CONSIDERED AS COMPLEMENTING TO EACH 1. ALL NON-LOAD BEARING TYPE CONCRETE
OTHER, HOLLOW BLOCKS SHALL HAVE A UNIT WEIGHT
1 SO THAT WHAT IS MENTIONED OR SHOWN IN NOT EXCEED 80PCF
THE OTHER SHALL APPLY TO BOTH, INCASE OF
2 - 75 mm x 75mm x 6.0mm CONFLICT BETWEEN THE TWO, THE SAME 2. LINTEL BEAMS SHALL BEAR AT LEAST 8
ANGLE BAR
SHALL REFERRED TO THE CITY ENGINEER'S INCHES (200mm) FROM THE EDGE OF
2 - 50 mm x 50mm x 6.0mm 2 - 50 mm x 50mm x 6.0mm
ANGLE BAR ANGLE BAR
OFFICE/PROJECT MANAGER FOR OPENINGS ON EACH SIDE OF MASONRY WALL
CLARIFICATION AND SOLUTION. OPENING.
50.00
(ELEV. + 0.80) ANCHOR BOLT ANCHOR BOLT
7.50 7.50
35.00 2. CONSTRUCTION NOTES AND TYPICAL 3. CHB WALL REINFORCEMENTS SHALL BE AS
DETAILS SHALL BE APPLY TO ALL UNLESS FOLLOWS:
20mm THK. x 300mm x 300mm 20mm THK. x 300mm x 300mm
ANCHOR BOLT A36 BASE PLATE A36 BASE PLATE OTHERWISE SHOWN OR NOTED, MODIFY
WALL VERTICAL HORIZONTAL
F2-C2 F2-C2 DETAILS AS DIRECTED TO MEET CONDITIONS.

7.50
THICKNESS REINFORCEMENT REINFORCEMENT
20mm THK. x 300mm x 300mm
A36 BASE PLATE
3. SHOP DRAWINGS FOR ERECTION OF ALL

50.00

35.00
inside outside 4'' (100mm)
2 - 75 mm x 75mm x 6.0mm STRUCTURAL STEEL, MISCELLANEOUS ETC.
2 ANGLE BAR
ANCHOR BOLT ANCHOR BOLT SHALL BE SUBMITTED TO THE PROJECT 4. REINFORCING BARS SHALL BE LAPPED A

7.50
ENGINEER FOR HIS/HER APPROVAL BEFORE MINIMUM OF 40 BARS DIAMETER, WHERE
F1-C1 F1-C1 2 - 50 mm x 50mm x 6.0mm FABRICATION. SPLICED DOWELS FROM CONCRETE FOOTINGS
ANGLE BAR
SLABS EXTEND INTO THE BLOCK WALL IN
PLAN 4. IT SHALL BE THE CONTRACTOR'S MINIMUM OF 40 BARS DIAMETER, AND DOWEL
RESPONSIBILITY TO PROVIDE ADEQUATE TO MATCH VERTICAL REINFORCEMENT OF
SHORING AND BRACING OF THE STRUCTURE WALL.
FOR ALL LOADS THAT MAYBE IMPOSED DURING
ELEVATION SECTION CONSTRUCTION. 5. DOWEL BARS SHALL BE EXTENDED ATLEAST
40 BAR DIAMETER
3 5. THE CONTRACTOR SHALL VERIFY ALL
DIMENSIONS BEFORE ALL WORK IS TO BEGIN. 6. ALL CONCRETE HOLLOW BLOCKS SHALL BE
F1-C1 F1-C1 CHECK WITH ELECTRICAL CONDUITS, WATER 100mm thk.
AND SANITARY LINE, PIPE SLEEVES ETC. TO BE
BASE PLATE DETAIL EMBEDED IN CONCRETE.
SCALE 1:40M
B. CONCRETE AND REINFORCEMENT D. STEEL NOTES

1. ALL MATERIALS WORKMANSHIP SHALL 1. ALL STRUCTURAL STEEL SHAPES SHALL


CONFORM WITH THE LATEST EDITION OF CONFORM WITH STANDARD MEASUREMENTS
4 AMERICAN CONCRETE INSTITUTE ( ACI - 318 ) OF AISC FOR ASTM A36 STEEL, fy = 248 Mpa

2. ALL CONCRETE SHALL DEVELOP A MINIMUM 2. WELDS SHALL CONFORM WITH AMERICAN
F1-C1 F1-C1
COMPRESSIVE STRENGTH AT THE END OF WELDING STANDARD USING E60XX ELECTRODE
2 - 50 mm, 4 - 150 mm, 4 - 200
100 mm THK Concrete Slab on Fill mm, & REST @ 250 mm TWENTY EIGHT ( 28 ) DAYS WITH
CORRESPONDING MAXIMUM SIZE ft = 96.60 Mpa
mm O.C.B.W. 20 mm THK x 300 mm x 300 mm
A36 BASEPLATE AGGREGATES AND SLUMPS AS FOLLOWS. fv = 69 Mpa
100 mm THK. CONCRETE 28 DAYS
SP. AS SHOWN O.C. B.W SP. AS SHOWN O.C. B.W LOCATION MAX. SLUMP 3. IN ACTUAL FABRICATION OF STEEL TRUSSES,
STRENTH
50 mm THK. COMPACTED
100 mm THK. COMPACTED 100 mm THK. COMPACTED
MEMBERS MEETING AT POINT SHALL HAVE
GRAVEL BASE COLUMN & 24.14Mpa THEIR GRAVITY AXIS INTERSECT AS NEARLY AS
5 GRAVEL BASE GRAVEL BASE
FOUNDATION (3500psi)
4'' (100mm)
PRACTICABLE AT COMMON POINT.

0.80
150 mm THK. COMPACTED

1.10
F1-C1 F1-C1 EARTH FILL
SLAB ON-FILL
20.70Mpa 4'' (100mm) 4. THE CONTRACTOR SHALL PROVIDE

0.10

0.10
WALL FTG. &

0.20

0.20
(3500psi) TEMPORARY ERECTION BRACING AND
OTHERS
SHORING AND MAKE ACTUAL MEASUREMENTS
3. IN GENERAL, THE LATEST EDITION OF ACI - 315 IN THE FIELD PRIOR TO FABRICATION /
1.00

1.00
1.70

MANUAL OF STANDARD PRACTICE DETAILING INSTALLATION OF ALL TRUSSES.

1.35
REINFORCED CONCRETE STRUCTURES SHALL BE
ADHERED TO UNLESS OTHERWISE SHOWN OR 5. FABRICATOR / CONTRACTOR SHALL

0.35
0.40

NOTED. SUBMITTED DETAILED SHOP DRAWINGS PRIOR


6
1.40 TO FABRICATION OF TRUSSES FOR APPROVAL
2.00 OR THE CITY ENGINEER'S OFFICE / PROJECT
4. MAINTAIN MINIMUM CONCRETE COVER FOR
F1-C1 F1-C1 REINFORCING STEEL BARS AS FOLLOWS: MANAGER.
SP. AS SHOWN O.C. B.W
2 - 50 mm, 4 - 150 mm, 4 - 200 2 - 50 mm, 4 - 150 mm, 4 - 200
SP. AS SHOWN O.C. B.W
mm, & REST @ 250 mm mm, & REST @ 250 mm 1.40 SLAB GRADE 1 21" in. (38mm)
E. FOUNDATIONS
BEAMS, STIRRUPS & COLUMN TIES 1 21"in. (38mm)
1. FOUNDATION SHALL REST ON NATURAL SOIL,

0.50

2.00
WHERE CONC. IS EXPOSED TO EARTH UNLESS OTHERWISE NOTED BY THE ENGINEER,
NO PART OF THE FOUNDATION SHALL REST ON

1.40
7 BUT POURED TO FORMS
FILL.
2 in. (50mm)

F1-C1 18.00 F1-C1 WHERE CONC. IS DEPOSITED DIRECTLY TO EARTH


2. THE CONTRACTOR SHALL NOTIFY THE
0.50 ENGINEER AFTER FOOTING EXCAVATION HAVE
3 in. (75mm)
BEEN COMPLETED AND PRIOR TO POURING OF
2.00
PLAN 5. CONTRACTOR SHALL NOTE AND PROVIDE ALL CONCRETE.
MISCELLANEOUS CURBS, SILLS, MECHANICAL
FOUNDATION PLAN FICI F2C2 BASES THAT ARE REQUIRED BY THE
ARCHITECTURAL, ELECTRICAL & MECHANICAL
3. THE CONTRACTOR SHALL BE RESPONSIBLE
TO DEVISED AND IMPLEMENT EXCAVATION
SCALE 1:100M PROCEDURES THAT WILL ENSURE SAFETY ON
DRAWINGS.
FOOTING DETAIL 6. ALL CONCRETE SHALL BE KEPT MOIST FOR A
LIFE AND PROPERTY.

SCALE 1:40M
MINIMUM OF SEVEN (7) CONSECUTIVE DAYS

SEAL CIVIL ENGINEER: TIN: 482-540-005


SEAL CIVIL ENGINEER: TIN: 479-582-556 PROJECT TITLE: RECOMMENDING APPROVAL: APPROVAL: SHEET CONTENTS: DESIGNED BY: SHEET NO.:
( by the Authority of Chairman Michael G. Aguinaldo ) FOUNDATION PLAN
DATE DESIGNED:
BASE PLATE DETAIL
REPUBLIC OF THE PHILIPPINES PROPOSED STANDARD MULTI-PURPOSE FOUNDATION DATAIL

COMMISSION ON AUDIT ENGR. ANBERT JONATHAN C. CAYNA ENGR. CLYDE S. DIVA COVERED COURT BUILDING WITH STAGE
ATTY. USMIN P. DIAMEL ENGR. LUIS S. MEJIA AsComm. DELFIN P. AGUILAR
GENERAL NOTES & SPECIFICATIONS
DRAWN BY:

DATE DRAWN:
S 1
COA CENTRAL OFFICE, COMMONWEALTH AVE., Q.C.
PRC NO. : 0141739 VALIDITY: 8/31/2018 PRC NO. : 0143383 VALIDITY: 10/24/2019
LOCATION: COMMISSION ON AUDIT RO XIII COMPOUND, SOUTH MONTILLA BLVD.,BUTUAN CITY
DIRECTOR IV
REGIONAL DIRECTOR
DIRECTOR IV
GENERAL SERVICES OFFICE
ASSISTANT COMMISSIONER
ADMINISTRATION SECTOR
CHECKED BY:
4/10
PTR NO.: DATE: PLACE: PTR NO.: DATE: PLACE: COMMISSION ON AUDIT - RO XIII COMMISSION ON AUDIT COMMISSION ON AUDIT DATE REVISED

You might also like