PPM-ENG-WMS-043-Instrument Installation
PPM-ENG-WMS-043-Instrument Installation
Tanda
No Tanggal
Uraian tangan /
. / Jam
Nama
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
1 Preface / Pendahuluan................................................................................................4
2 Scope of Works / Lingkup Kerja...................................................................................4
4 Project Definition/Definisi Proyek.................................................................................5
5 Definition of Terms / Definisi Istilah..............................................................................6
6 On-Site Organization Chart / Struktur Organisasi........................................................7
7 Personnel Job & Responsibilty / Tugas & Tanggung Jawab Personil..........................8
7.1 Project Manager..................................................................................................8
7.2 Site Engineer......................................................................................................8
7.3 Superintendent....................................................................................................9
7.4 HSE Supervisor..................................................................................................9
7.5 QC Inspector.....................................................................................................10
7.6 Surveyor............................................................................................................ 10
7.7 Personnel & Training Requirements..................................................................10
8 Planning and Preparation / Perencanaan dan Persiapan...........................................11
8.1 Mandatory Documentation................................................................................11
8.2 Flowchart.......................................................................................................... 12
9 Construction Method / Metode Pelaksanaan..............................................................12
9.1 Preparation.......................................................................................................12
9.2 Instrument Delivery...........................................................................................13
9.3 Instrument Storage............................................................................................13
9.4 Inspection..........................................................................................................13
9.5 Foundation Works & Fixing Anchor Bolt............................................................14
9.6 Instrument Installation Prosedure......................................................................14
8.7. Instrument Testing and Commissioning............................................................20
9. Survey Plan............................................................................................................... 21
a. Work Checklist / Ceklis Pekerjaan....................................................................21
10. Resources / Sumber Daya.........................................................................................21
10.1. Plant & Equipment / Alat...................................................................................21
10.2. Material............................................................................................................. 22
10.3. Manpower......................................................................................................... 23
11. List of Procedures, WI and BDE / Daftar Prosedur, WI dan BDE...............................23
12. Quality Management / Manajemen Kualitas...............................................................24
12.1. Quality Assurance.............................................................................................24
12.2. Quality Control..................................................................................................24
Page 2 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
Page 3 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
1 Preface / Pendahuluan
This method describes the General Instruments Installation carried out in the Makassar
WWTP B1 project.
This work method statement made as a direction for ensure that all works regarding
field Instruments (flow, level, pressure, temperature, analyzer) installation, testing and
commissioning. Installation for Instrumentsation Works shall be done in accordance
with standards and all other applicable international codes and standards.
metode kerja ini dibuat sebagai arahan untuk memastikan bahwa semua pekerjaan
mengenai instrumen lapangan (aliran, tingkat, tekanan, suhu, penganalisis) instalasi,
pengujian dan commissioning. Instalasi untuk Pekerjaan Instrumentasi harus dilakukan
sesuai dengan standar dan semua kode dan standar internasional lainnya yang
berlaku.
Page 4 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
Kontraktor
Page 5 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
JSA (Job Safety Documents that attempt to study / analyze and record each
2. sequence of work steps of a job, followed by the
Analysis)
identification of potential hazards in them, then finalized by
Page 6 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
Page 7 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
Page 8 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
• Menyiapkan metoda kerja yang digunakan sebagai acuan di lapangan berupa alat,
dan material.
• Memeriksa tahapan pekerjaan di lapangan.
• Mempersiapkan gambar kerja.
• Mempersiapkan dokumen material.
• Bekerjasama dengan supervisor terkait melakukan monitoring dan pengadaan
material.
• Melakukan koordinasi teknis dengan pihak subkontraktor terkait.
Page 9 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
7.3 Superintendent
• Ensure all necessary Permits for the work are obtained and current.
• Organize and supervise the work to conform standard and other documentation
such as the Job Safety and Environment Analysis (JSEA).
• Conduct pre-start meetings each day.
• Communicate work plans to everyone involved.
• Raise any concerns or changed conditions to the Site Manager and General
Superintendent.
• Ensure access safe to use for workers and emergency response.
• Record work progress in the daily diary.
• Pastikan semua Izin yang diperlukan untuk pekerjaan diperoleh dan terkini.
• Mengatur dan mengawasi pekerjaan agar sesuai dengan standar dan dokumentasi
lain seperti Job Safety and Environment Analysis (JSEA).
• Lakukan pertemuan pra-mulai setiap hari.
• Komunikasikan rencana kerja kepada semua orang yang terlibat.
• Sampaikan kekhawatiran atau perubahan kondisi apa pun kepada Manajer Lokasi
dan General Superintendend.
• Pastikan akses aman digunakan untuk pekerja dan tanggap darurat.
• Rekam kemajuan pekerjaan dalam buku harian.
• Tinjau Work Method Statement (WMS) ini dan pastikan bahwa Job safety Analysis
(JSA) yang berlaku dibuat (atau sudah ada) yang secara memadai menangani
risiko yang terkait dengan pekerjaan.
• Atur pertemuan toolbox di setiap hari kerja di pagi hari sebelum pekerjaan dimulai.
• Pastikan peralatan, tanda, alat pendukung, platform kerja, dan area kerja
diinspeksi aman untuk digunakan oleh orang yang kompeten.
Page 10 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
7.5 QC Inspector
• Coordinating Work Inspection Request.
• Conduct inspection of work in accordance with the stages mentioned in the
Inspection & Test Plant (ITP) and ensure the results of the work are made and
stored properly.
• Make a report of deviations that occur Non- Conformance Report [NCR] and follow
up.
• Create a working quality report (Request for Inspection (RFI), Inspection & Test
Plant (ITP), Inspection Test Report (ITR) and Documentation).
7.6 Surveyor
• Setout orientation Instrument.
• Setout limits and equipment Instrument.
• Setout access equipment Instrument.
Page 11 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
• This Work Method Statement (WMS) has been approved (all signatures must be
showing on the Approval page).
• All Drawings applicable to the works have been approved and Issued for
Construction.
• The Job Safety Analysis (JSA) applicable to the works have been approved.
• An Employer/ Project Implementation Support Consultant (PISC) Work Permit has
been approved and has not expired.
• All personnel who will be involved in the activities have been briefed about how the
works will be conducted, understand the risks and their responsibilities, and have
signed the briefing attendance record.
• All of the above documents are printed and kept in a folder at the Site Office.
● Hal-hal berikut harus ada sebelum kegiatan di bawah Work Method Statement
(WMS) ini dimulai:
• Work Method Statement (WMS) ini telah disetujui (semua tanda tangan harus
ditunjukkan di halaman Persetujuan).
• Semua gambar yang berlaku untuk pekerjaan telah disetujui dan Diterbitkan untuk
Konstruksi.
• Job Safety Analysis (JSA) yang berlaku untuk pekerjaan tersebut telah disetujui.
• Izin Kerja Pemberi Kerja / Project Implementation Support Consultant (PISC) telah
disetujui dan belum kedaluwarsa.
• Semua personel yang akan terlibat dalam kegiatan telah diberi pengarahan
tentang bagaimana pekerjaan akan dilakukan, memahami risiko dan tanggung
jawab mereka, dan telah menandatangani catatan kehadiran pengarahan.
• Semua dokumen di atas dicetak dan disimpan dalam folder di Site Office.
If any of the Permits listed above have expired, all works must cease until a new
Permit has been issued.
Jika salah satu Izin yang tercantum di atas telah kedaluwarsa, semua pekerjaan harus
berhenti sampai Izin baru dikeluarkan.
If any ground conditions in the field are found to be different to those described in this
WMS, then works must cease and be re-assessed by the General Superintentdent.
Jika ada kondisi lapangan di lapangan yang ditemukan berbeda dengan yang
dijelaskan dalam Work Method Statement (WMS) ini, maka pekerjaan harus dihentikan
dan dinilai ulang oleh General Superintentdent.
Page 12 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
8.2 Flowchart
Page 13 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
Figure 4. Wooden Crate for Instrument Packing and Spare Part Instrument.
Setelah pembuatan Instrument selesai, sebelum pengiriman Instrument akan dikemas
kedalam peti kayu untuk menghindari kerusakan sehingga Instrument dalam kondisi
baik sampai tiba di lokasi proyek WWTP B1 Makassar.
9.4 Inspection
After the Instruments arrive in site project, The Instruments will be inspected by
contractor quality control and engineer quality control according to approved Inspection
Test Plan (ITP) to ensure each material received in good condition.
Setelah Instrument tiba di lokasi proyek, Instrument akan diperiksa oleh tim quality
control dan tim engineer sesuai dengan Inspection Test Plan (ITP) yang disetujui untuk
memastikan setiap material yang diterima dalam kondisi baik.
Page 14 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
2. Measure the distance between the base and make sure them matches according to
approved shop drawing and Instrument installation layout plan.
- Flow Meters in liquid service shall be installed so that meters are always full
of liquid and trapping of gases is avoided and in gas service, liquid trapping
shall be avoided.
- The use of strainers and eliminators shall be considered and evaluated to
protect metering devices.
- Flow Meter installations shall be in accordance with the specified electrical
area classification refer to instrument standard installation.
- Ensure that there are no leaks in the connection between the flow pipe and
the flow meter.
Page 15 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
Page 16 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
Page 17 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
(shown as fig.10).
Do not install the gauge by turning the casing.
Use a wrench or wrench to turn the socket tube.
A shut-off valve should be installed between the gauge and the
process in order to be able to isolate the gauge for inspection or
replacement without shutting down the process.
Page 18 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
1. Instrumen lapangan harus dipasang sesuai gambar yang disetujui dan gambar
detail instalasi atau instruksi pembuatan.
2. Instrumen harus dapat diakses untuk digunakan, dikalibrasi, dan diperbaiki
tanpa memerlukan pelepasan perpipaan, kisi-kisi, atau struktur lainnya.
Persyaratan ini juga berlaku untuk menghilangkan penutup atau perumahan
yang merupakan bagian dari instrumen atau pemasangannya. Pastikan juga
bahwa instalasi tidak akan mengalami guncangan getaran yang berlebihan atau
suhu ekstrem.
3. Penopang, breket, gantungan dll, untuk peralatan dan bahan harus dipasang
agar tidak melemahkan struktur tempat meraka terpasang.
Instrument lapangan terdiri dari:
a. Pemasangan Instrument Flow Meter
- Persyaratan pemasangan pabrikan harus diikuti seminimal mungkin.
- Sebelum pemasangan semua instrument, harus dikalibrasi/pra-
pemasangan kalibrasi.
- Flow meter dipasang sebagaian yang kemudian dipasang berurutan
(lihat gambar 5).
- Flow meter dalam layanan cairan harus dipasang sehingga meter
selalu penuh dengan cairan dan perangkap gas dihindari dan dalam
layanan gas, perangkap cairan harus dihindari.
- Penggunaan saringan dan eliminator harus dipertimbangkan dan di
evaluasi untuk melindungi perangkat pengukuran.
- Pemasangan Flow Meter harus sesuai dengan klasifikasi area
kelistrikan yang ditentukan mengacu pada instalasi standar
instrument.
- Pastikan tidak ada kebocoran pada sambungan antara pipa aliran
dan aliran meter.
b. Pemasangan Pemancar Level (Ultrasonic) Instrumen
- Persyaratan pemasangan pabrikan harus diikuti seminimal mungkin.
- Sebelum pemasangan semua instrument, harus dikalibrasi, pra-
instalasi dikalibrasi.
- Unit instalasi (lihat gambar 6)
Lokasi pemasangan harus jauh dari saluran masuk jika tidak,
indicator meter akan menghasilkan kesalahan keluaran yang
disebabkan oleh fluktuasi cairan pada saluran masuk.
Pasang transduser jauh dari saluran masuk untuk menghindari
gema palsu.
Jangan pasang miring dan jangan pasang ditempat yang akan
menggunakan sensor lebar balok.
Ditangki bawah kerucut, posisikan sensor diatas bagian
terdalam tangka.
Jika memasang pada flensa, pilih flensa dengan utas yang
Page 19 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
Page 20 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
Page 21 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
l. Pemeriksaan Function.
m. Memeriksa dan menguji Komunikasi urutan sistem instrumentasi:
Mode kontrol manual dan otomatis.
Kondisi system normal.
Kondisi kontigensi.
Pengoperasian semua interlock dan permisif.
9. Survey Plan
a. Work Checklist / Ceklis Pekerjaan
The Instrument checklist refers to the approved drawing.
Adapun ceklis Pekerjaan Instrument mengacu pada drawing yang sudah disetujui.
Mesin dan peralatan yang terkait dengan pekerjaan akan berfungsi dengan baik dan
memiliki kapasitas untuk melakukan pekerjaan yang diperlukan dengan aman dan
efisien. Jenis, ukuran dan jumlah mesin yang digunakan akan tergantung pada jumlah
material, penjadwalan dan pembatasan akses. Inspeksi instalasi yang diperlukan dan
penilaian kompetensi operator akan dilakukan sebagai bagian dari Rencana
Manajemen Keselamatan Proyek.
Page 22 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
10.2. Material
Material testing after Factory Acceptance Test (FAT) including material, technical
specifications, relevant standards and manufacturer’s instructions, and internal
calibration.
- Testing/Spesification.
- Material.
- Certificate.
- Shop Drawing.
- Spare Part List.
- Internal Calibration.
- Data.
Pengujian material setelah Factory Acceptance Test (FAT) material yang sesuai,
spesifikasi teknis, standar yang relevan, dan instruksi pabrik, dan kalibrasi internal.
- Uji/Spesifikasi.
- Material.
- Sertifikat.
- Gambar.
- Daftar Spare Part.
- Kalibrasi Internal.
- Data.
Table 3 Material
Specific Material required for the
Type of Works
works:
Instrument Assembly and Installation
10.3. Manpower
The following is an estimate of the workforce that will be used based on the calculation
of existing needs.
Berikut ini merupakan estimasi tenaga kerja yang akan digunakan berdasarkan
perhitungan kebutuhan yang sudah ada.
Page 23 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
Table 4 Manpower
No Position Total
1 Project Manager 1
2 Site Manager 1
3 HSE Supervisor 1
4 QC Inspector 1
5 Mechanical 1
6 Electrical 1
7 Workers / Tukang 1
8 Helper / Pekerja 3
Semua personil yang tertera di atas telah menjalani dan menyelesaikan training wajib
dari KONTRAKTOR.
11. List of Procedures, WI (Work Infection) and BDE (Basic Design Engineer) /
Daftar Prosedur, WI dan BDE
● BDE/SH/2015/002 – PROTEKSI
● BDE/SH/2015/005 – ALAT LISTRIK
● BDE/SH/2015/008 – APD
● BDE/SH/2015/014 – ALAT BERAT
● BDE/SH/2015/022 – PENGANGKATAN MANUAL
● BDE/SH/2015/024 – MATERIAL BERBAHAYA
Page 24 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
Memberikan Rencana Uji Inspeksi (Inspection Test Plan / ITP) dan memastikan
pemeriksaan internal pekerjaan persiapan telah dilakukan sebelum pekerjaan
dilaksanakan.
● Identify all materials, tools, procedures, resources and management in order to
achieve good work.
Identifikasi semua bahan, peralatan, prosedur, sumber daya dan manajemen agar
bisa mencapai hasil yang baik.
Inspection Test Plan (ITP) documents will be prepared to summarize inspection and
testing protocols. At predetermined stages of works, the appropriate inspections or
tests shall be undertaken and submitted as specified. Subsequent works will then
proceed upon meeting the specified criteria.
Dokumen Inspection Test Plan (ITP) akan disiapkan untuk meringkas protokol inspeksi
dan pengujian. Pada tahap pekerjaan yang telah ditentukan sebelumnya, inspeksi atau
pengujian yang sesuai harus dilakukan dan diserahkan seperti yang ditentukan.
Pekerjaan selanjutnya akan dilanjutkan setelah memenuhi kriteria yang ditentukan.
Page 25 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
2) Work order, potentials that can cause work accidents, both equipment, materials and
work methods must be explained in the initial stages and in the tool box meeting / pre
start meeting. This is outlined in detail in the Job Safety Analysis (JSA).
Urutan kerja, potensi-potensi yang dapat menimbulkan kecelakaan kerja baik
peralatan, material maupun metoda kerja harus dijelaskan dalam tahap awal dan
pada tool box meeting/pre start meeting. Hal ini dituangkan secara detail dalam Job
Safety Analysis (JSA).
3) Everyone involved in the work must wear personal protective equipment while in the
project area. The provision of safety and occupational health signs is always placed
in an appropriate location.
Semua orang yang terlibat dalam pekerjaan harus memakai alat pelindung diri
selama dalam area proyek. Pemberian rambu-rambu keamanan dan kesehatan
kerja selalu ditempatkan pada lokasi yang sesuai.
4) Mechanics together with safety must always check the equipment that is being used
and that will be used in the construction process periodically.
Petugas mekanik bersama safety harus selalu memeriksa peralatan yang sedang
dipakai dan yang akan dipakai dalam proses konstruksi secara berkala.
5) Specific matters requiring attention:
Hal-hal khusus yang memerlukan perhatian:
● Placement of material / Penempatan material.
● Examination of transportation access / Pemeriksaan akses transportasi.
● Lifting equipment is not overloaded / Alat angkat tidak mengalami overload.
● Use slings in good condition, planned length, and in accordance with the lifted
load / Gunakan sling dalam kondisi yang baik, panjang yang direncanakan, dan
sesuai dengan beban yang di angkat.
● Attention is paid specifically to chemical materials (admixture), give a special place
with a special mark / Perhatian ditujukan secara khusus pada material kimia
(admixture), berikan tempat khusus dengan tanda khusus.
● Every supporting material must have a Material Safety Data Sheet (MSDS)/
Setiap material pendukung harus mempunyai Material Safety Data Sheet
(MSDS).
6) Work protection equipment that must be used are:
Peralatan perlindungan kerja yang harus dipergunakan adalah:
● Helm.
● Safety shoe.
● Safety glove.
● Full body harness.
● Safety vest.
● Safety glasses.
Page 26 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
Page 27 of 28
PPM/ENG/WMS/043 Rev: 01
Construction of Wastewater Treatment Plant in Makassar (Makassar WWTP B1)
WMS: Instrument installation
Identifikasi Bahaya & Pengendalian Resiko (IBPR) untuk item pekerjaan ini
mengacu/diambil dari IBPR (Master) pada Project planning sesuai dengan
kebutuhan.
Inspection & Test Plan (ITP) untuk item pekerjaan ini yang mengacu/diambil dari
Inspection & Test Plan (Master) pada Project Planning sesuai dengan kebutuhan.
Page 28 of 28
PPM/ENG/WMS/043 Rev: 01