LF90D Manual
LF90D Manual
COMMISSIONING PROCEDURE
DRAFT
Table of contents
1 VISUAL INSPECTION AND OTHER NOTES ............................................................................ 4
2 COMPONENT CLEANING......................................................................................................... 4
3 GREASE THE ITEMS LISTED BELOW ..................................................................................... 4
4 OIL FILTER CHART ................................................................................................................... 5
5 DIESEL ENGINE PREPARATIONS........................................................................................... 5
6 MISCELLANEOUS HYDRAULIC CHECKPOINTS .................................................................... 5
6.1 Oil cooler......................................................................................................................... 5
6.2 Main winch ......................................................................................................................5
6.3 Wire line winch motor...................................................................................................... 7
6.4 Rotation head motor ....................................................................................................... 7
6.5 Traverse cylinder ............................................................................................................ 7
6.6 Mast raise cylinders ........................................................................................................ 7
6.7 Mast dump cylinder......................................................................................................... 7
6.8 Control cabinet................................................................................................................ 7
6.9 Main control valve m4-15 ................................................................................................ 7
6.10 jack leg 4 sPOOL/ Mast raise / Mast dump 8 SPOOL VALVE....................................... 9
6.11 Water pump system ........................................................................................................ 9
6.12 Main control valve ........................................................................................................... 9
6.13 Hand pump ..................................................................................................................... 9
7 MISCELLANEOUS MECHANICAL CHECKPOINTS.................................................................. 9
8 PRIME THE HYDRAULIC PUMPS .......................................................................................... 10
9 LUBRICATING OIL CHART ..................................................................................................... 10
10 SHORT CIRCUIT THE MAIN SUPPLY HOSES OF THE FOLLOWING MOTORS............. 10
11 CONTROL ADJUSTMENT IN PREPARATION FOR FLUSHING........................................ 10
12 FIRST EVER DIESEL START-UP ....................................................................................... 11
13 boost pump setup (high altitude rigs) ................................................................................... 11
14 FLUSHING ........................................................................................................................... 12
14.1 Flushing Table. ............................................................................................................. 12
14.2 Flushing Circuit Pressure Checks................................................................................. 12
15 Pump 6c (Pilot pressure, cooling fan, boost pump) ............................................................. 13
15.1 THIRD STAGE PUMP 6C ............................................................................................. 13
1. Flow & Pressure Regulator Adjustment Procedure (Boost Pump installed).............. 13
2. PILOT Pressure Relief Valve Item 37.2 Adjustment Procedure................................ 14
3. Flow & Pressure Regulator Adjustment Procedure (Boost Pump not installed)........ 14
4.PILOT Pressure Relief Valve Item 37.2 Adjustment Procedure (no boost pump)..... 15 15.2
SECOND STAGE PUMP 6B......................................................................................... 15 15.2.1
Flow Regulator Adjustment Procedure...................................................................... 15 15.2.2
Pressure Relief Valve Item 4 Adjustment Procedure ................................................ 17 15.2.3
Pressure Regulator Adjustment Procedure............................................................... 17 15.3
FIRST STAGE MAIN PUMP 6A.................................................................................... 18
15.3.1 Flow and pressure and main control pressure regulator setting ............................... 19
15.3.2 MAXIMUM FLOW SETTING ..................................................................................... 19
15.3.3 Pump 6A and control valve 24 flow test .................................................................... 20
15.3.4 m4-15 diagram .......................................................................................................... 21
15.3.5 control valve m4-15 pressure relief adjustmet procedure ......................................... 22
16RECONNECT HOSES, PRIME HYDRAULIC MOTORS AND HYDRAULIC OIL TANK
LEVEL............................................................................................................................................. 22
17 Jack legs valve item 46 / 8 spool valve item 59 relief valve adjustment procedure ............. 23
17.1.1 pREPERATION FOR ADJUSTMENT ....................................................................... 23
3
26 COMMISSIONING CHECK POINTS CHECK THE FOLLOWING ....................................... 47
27 SERIAL NUMBERS OF EQUIPMENT ................................................................................. 52
28 SIGNATURE FORM............................................................................................................. 53
4
1 VISUAL INSPECTION AND OTHER NOTES
• Obtain a copy of the production order from the sales department and verify that the rig is
built to the production order.
• Obtain copies of the following drawings for the particular rig and use them as a reference
source;
• Hydraulic Circuit DR/Number 8040 Latest revision
• Water Circuit DR/Number Latest revision
• Fuel System Assembly DR/Number Latest revision
• Electrical Circuit DR/Number Latest revision
• The item numbers on the hydraulic circuit drawing will be used as reference numbers
through out this procedure.
• Refer to the UDR 200D operator’s manual when necessary
• ALL POINTS in this commissioning procedure MUST BE initialled and dated by
commissioning personnel.
• Please initial and date each line in the left- hand margin.
• The following abbreviations will appear throughout this procedure.
• A.P.R. = Acceptable Pressure Range in bar /psi.
• A.T.R. = Acceptable Temperature Range in degrees C.
• A.M.R. = Acceptable Measurement Range in mm / inch.
• A.R.R. = Acceptable Revolution Range in rpm.
• Use these letters for reference to what is an acceptable range to work in.
• While commissioning this rig, the hydraulic oil temp should be between 50°C to 60°C for
• Most of the procedure. Please note the hydraulic oil flow to the cooler has a thermal
valve fitted in the system, which will keep the oil temperature stable.
• The finished procedure must be sighted and signed by sales department and the
production manager following a visual and operational inspection with any points noted by
the sales inspection checked and corrected by production.
2 COMPONENT CLEANING
• Remove the hydraulic oil tank lid and check that the hydraulic tank has been cleaned out.
Thoroughly inspect for perfect cleanliness.
5
4 OIL FILTER CHART
2. MAIN WINCH
•Check all cartridges fitted to the main winch Counter Balance block part no WU11684, do not
have any damaged or missing ‘O’ rings or back up rings.
• Check the cartridges are fitted into the correct cavities in the main winch manifold block,
part no WU11684.
• Check the brake pressure control of the main winch final drive PD22978AL has been
6
preset to 172.41 bar / 2500 psi. This is located on the hydraulic tank facing forward.
• Check the holding valve item 71 has been preset to 278 bar / 4030 psi.
• Check that both shuttle valves item 73, for the following;
• Correctly piped in
• Are free of any debris eg sealing compounds, hose dust.
• Check the pilot open check valve item 34 has been correctly piped in.
• Check the external hosing is correct by the hydraulic circuit drawing.
•Check the main winch planetary has the external drain and fill points and is filled to the
correct level.
7
3. WIRE LINE WINCH MOTOR
• Check the holding valves item 77 have, been preset to 210 bar / 3045 psi.
• Check the external hosing is correct by the hydraulic circuit drawing.
5. TRAVERSE CYLINDER
• Check the holding valve item 66 has been preset to 207 bar / 3000 psi.
• Check the orifice plate has been removed from the hose burst valve, which is fitted to the
traverse cylinder or the restriction is set for 20LPM.
• Check the external hosing is correct by the hydraulic circuit drawing.
8. CONTROL CABINET
•Check the cartridges items 35, 45 and check valve cartridges item 40, which are fitted to the
float control blocks item 113, 48, 42 do not have any damaged or missing ‘O’ rings or back up
rings.
•Check the pilot control valves items 25 & 26 have the correct pilot control curves (curve 06)
fitted to them.
• Check the rotation pilot control lever has the modified lockable control lever WU9388 has
been correctly fitted to it. And the detent locks the lever when pulled towards the operator.
• Check the pull down minimum back pressure check valve item 29 is a 5 bar / 72.5 psi
cracking pressure check valve and that the cartridge is in the correct location.
• Check the following directional control valve have detents fitted to them
• Micro-feed
• Float
• Check the winch float 3-way ball valve item 27 is correctly piped in.
8
7. Refer to the diagram below which illustrates the valve connections and adjustment points.
9
6.10 JACK LEG 4 SPOOL/ MAST RAISE / MAST DUMP 8 SPOOL VALVE
•Check the primary pressure relief valve of item 46 (4 SPOOL VALVE) has been preset to
200 bar / 2900 psi. Check the primary pressure relief valve of item 59 (8 SPOOL VALVE) has
been preset to 172 bar / 2500 psi.
• Check the mast raise port pressure relief valve cartridge has been preset to 172 bar / 2500
psi (up) and 70 bar / 1015 psi (down).
• Check the mast dump port pressure relief valve cartridge [port “A”], has been preset to 60
bar / 870 psi. This port supplies pressure to lower the mast on the dump slides.
• Check the mast dump port pressure relief valve cartridge [port “B”], has been preset to 70
bar / 1015 psi. This port supplies pressure to raise the mast on the dump slides.
6.11 WATER PUMP SYSTEM
• Check the primary pressure relief valve item 4 has been preset to 200 bar / 2900psi.
•Check the water pump “ON-OFF” ball valve item 32 has been piped correctly in. Check the
lever selector plate to have the lever match the name tags locations.
• Check the water pump fine and coarse speed control items 33 & 36 have been correctly
piped in.
• Check the water pump coarse control ball valve has been correctly piped in, lever “UP” ball
valve is shut.
• Check the external hosing is correct by the hydraulic circuit drawing.
10
8 PRIME THE HYDRAULIC PUMPS
• Open the upper drain port of No.6A-6B-6C of pump assembly. Fill the cases of each pump
with clean hydraulic oil. Ensure that all air has been expelled from each pump case.
NOTE
8. Check the Rotation Head oil cooler lines are full with lubricating oil.
11
• Chuck / clamp / float control lever in the neutral position.
• Rod spin guard interlock valve items 88 & 89 closed (drill position).
• Fit a 100 bar / 1450-psi pressure gauge to the pressure test point item 14 on the pressure
relief valve item 4 (Water Pump).
•Fit a 100 bar / 1450-psi pressure gauge to the pressure test point item 14 on the pilot
pressure control item 37 to check pump 6C pressure.
• Adjust by two full turns out the pressure regulator adjustment screw of pumps 6A-6B-6C
• Connect the “X” port of the rotation head motor to the case drain port via a 0.50 mm
0.019”orifice
• Fully increase the rotation speed control item 37.1.
• Remove the brake release hose from the main winch gearbox and connect the line via a
0.5mm 0.019”orifice to the drain hose of the main winch motor.
• Put the main winch float control item 27.1 into the float position.
• While commissioning this rig, the hydraulic oil temp should be between 50°C to 60°C for
most of the procedure. Please note the hydraulic oil flow to the cooler has a thermal valve
fitted in the system, which will keep the oil temperature stable.
12
14 FLUSHING
Note
1. During flushing no pressure to exceed 60 bar in any circuit.
2. Oil temperature in tank not to exceed 70°C
3. All flushing to be carried out at 2200 rpm A.R.R. 2200-2220
4. Make sure there is pilot pressure at TH6 pilot controls.
5. Pump 6c and item 37.2 pilot pressure relief may need to be set prior to flushing if.
6. Make sure there is at lease 150 lpm flow showing on the flow meter connected to
pump 6A when the rotation lever is fully forward.
ROTATION HEAD ROTATION MAIN WINCH MAIN WINCH WIRE LINE WIRE LINE
FORWARD HEAD RAISE LOWER WINCH RAISE WINCH LOWER
REVERSE
PUMP 6B WATER PUMP
PUMP 6C MUD MIXER
CHECK THE PILOT PRESSURE AT THE ‘P’ PORT OF THE PILOT CONTROL ITEMS 25 & 26
CHECK THAT THE PRESSURE AT THE BOOST PUMP GUAGE REMAINS ABOVE 15 PSI
NOTE: MAIN FILTER BACK PRESSURE AT START OF FLUSHING AND OIL TEMP.
Note
1. Do not operate the mast raise / micro-feed / chuck / clamp / traverse levers
NOTE
1. During flushing check the following:
2. Diesel water temperature
3. Diesel oil pressure
4. Main filter back pressure - max. 2 bar
5. No pressure to exceed 60 bar
6. Note and report any anomalies
7. Hydraulic oil cooler fan speed should be between 630-650 rpm
13
• After 90 mins of operation note main filter back pressure and oil temp (item 25 at
• Panel) and the hydraulic oil cooler fan speed .
14
2. PILOT PRESSURE RELIEF VALVE ITEM 37.2 ADJUSTMENT PROCEDURE
1. Fit the 1500 psi pressure gauge to the pressure test coupling item 14 for item 37.2 pilot
pressure relief valve connected to the drain manifold inside the control cabinet.
11. Adjust the Adjust item 37.2 to achieve 500 psi.
12. Tighten the lock nut and remove the adjustment handle.
15
15.1.4 PILOT PRESSURE RELIEF VALVE ITEM 37.2 ADJUSTMENT PROCEDURE (NO
BOOST PUMP)
2. Fit the 1000 psi pressure gauge to the pressure test coupling item 14 for item 37.2 pilot
pressure relief valve connected to the drain manifold inside the control cabinet.
23. Adjust the Adjust item 37.2 to achieve 650 psi.
24. Tighten the lock nut and remove the adjustment handle.
2. Fit a 40 bar / 580 psi pressure gauge to the pressure test coupling item 14 connected to
the pressure relief valve item 4, which is connected to the pump 6B pressure port.
3. At the control panel set the water pump hydraulic controls as follows:
• Water Pump on-off: “OFF”
• Water Pump fine control: “CLOSED” ( fully clockwise)
• Water Pump coarse control: “CLOSED” (lever up)
4. Start the engine and set the diesel rpm to 1800 to1850 rpm.
5. Operate the water pump on-off control to the “ON” position.
6. Adjust the flow regulator adjustment screw until the pressure gauge reads 14-15 bar /
205-220 psi.
16
Actual flow regulator setting BAR A.P.R 14-15 BAR
PSI A.P.R. 205-220 PSI
Actual diesel rpm RPM A.R.R 1800-1850 RPM
7. Tighten the flow regulator lock nut and replace the cap nut.
8. Check the setting by operating the water pump on-off control “OFF-ON” several times.
Note
1. The flow regulator cannot be set correctly, if pressure relief valve or the water
pump on / off ball valve is faulty.
9. Operate the water pump on-off control to the “OFF” position. Stop the engine.
17
2. PRESSURE RELIEF VALVE ITEM 4 ADJUSTMENT PROCEDURE
1. Refer to the picture on page 21 for the location of the pump regulator setting screws.
1. Remove the pressure regulator cap nut.
2. Loosen the pressure regulator locknut.
3. Using an Allen key, adjust the pressure regulator adjustment screw of pump 6B clockwise
all the way in, then back out the screw by 1/2 turn tighten the locknut.
4. Fit a 250 bar / 3625 psi pressure gauge to the pressure test coupling item 14 at pressure
relief valve item 4, which is connected to the pump pressure port of pump 6B.
5. Remove the hydraulic oil pressure hose from the water pump motor. Cap the fitting and
plug the hose end with steel plugs.
6. Reduce the setting of the pressure relief valve item 4 by turning the adjustment screw out
two full turns.
7. Start the engine and set the diesel rpm to 1800 to1850 rpm.
8. Operate the water pump on-off control to “ON”.
9. Adjust the pressure relief valve adjustment screw until the 200 bar /2900 psi is indicated
on the pressure gauge.
10. Tighten the locknut of the adjustment screw of the pressure relief valve.
11. Check the setting by operating the water pump on-off control “OFF-ON” several times.
Actual pressure relief valve setting BAR / PSI A.P.R 198-200 BAR
A.P.R. 2871-2900 PSI
Actual diesel rpm RPM A.R.R 1800-1850 RPM
12. Operate the water pump on-off control to the “OFF” position. Stop the engine.
13. Refit the pressure hose onto the water pump motor if no further adjustment is required.
3. PRESSURE REGULATOR ADJUSTMENT PROCEDURE
1. Refer to the picture on page 21 for the location of the regulator setting screws.
14. Fit a 250 bar pressure gauge to the pressure test coupling item 4 at the pressure relief
valve item 4, which is connected to the pump 6B pressure port.
15. Remove the pressure hose from the water pump motor. Cap the fitting on the motor and
plug the hose end with steel plugs
16. At the control panel set the water pump hydraulic controls as follows:
• Water Pump on-off: “OFF”
• Water Pump fine control: “CLOSED” (fully counter clockwise)
• Water Pump coarse control: “OPEN” (lever down)
17. Remove the pressure regulator cap nut and loosen the lock nut.
Note
1. When the cap nuts are loosened, a slight oil weep will occur.
18. Start the engine and set the diesel rpm to 1800 to1850 rpm.
19. Using an Allen key set the pump pressure regulator adjustment screw (maximum system
pressure) by turning the adjustment screw as follows.
• Adjusting the pressure regulator setting screw clockwise increases the pressure.
• Adjusting the pressure regulator setting screw counter-clockwise reduces the
pressure.
• One turn of the setting screw corresponds to 50-bar pressure in the range 20 to 250
bar.
20. Observe the pressure reading on the gauge connected to the test coupling.
21. Operate the water pump on-off control to the “ON” position.
18
22. Adjust the pressure setting to 180 bar. Tighten the lock nut and replace the cap nut.
Note
1. Do not exceed the pressure relief valve setting, note that pump pressure regulator
setting is generally 15-20 bar lower than relief valve setting.
2. The pressure regulator cannot be set correctly, if the pressure relief valve or the
water pump on / off ball valve is faulty.
3. Check the setting by operating the water pump on-off control “OFF-ON” several times.
4. Operate the water pump on-off control to the “OFF” position. Stop the engine.
5. Refit the pressure hose onto the water pump motor if no further adjustment is required.
19
1. FLOW AND PRESSURE AND MAIN CONTROL PRESSURE REGULATOR SETTING
1. Check if the pump controls have been preset by the supplier.
2. Refer to the photos on the previous page to locate pump 6A control positions.
3. Check the pilot levers for the main drill functions (main winch, wire line winch, rotation and
traverse) are in the neutral position.
4. Tee a 350 bar / 5000-psi pressure gauge and a pressure test point into the “M” port of
pump 6A.
5.Start the engine and operate at 1800-1850 rpm. 6.
7. Loosen the flow and pressure regulator lock nut.
8. Using an Allen key, adjust the flow regulator adjustment screw fully clockwise.
9. Using an Allen key, adjust the main control valve pressure relief fully clockwise.
10. Using an Allen key, adjust the pressure regulator screw until the pressure gauge at the
“M” port indicates 300 bar / 4350 psi.
11. Using an Allen key, adjust the primary pressure relief valve on Item 24 until the valve
opens and the pressure gauge drops slightly.
12. Turn the adjustment clockwise ¼ turn.
13. Using an Allen key, adjust the pressure regulator screw of pump 6A until the pressure
gauge at the “M” port indicates 290 bar / 4200 psi.
14. Using an Allen key, adjust the flow regulator adjustment screw counter clockwise until the
pressure gauge at the “M” port indicates 28 – 28.5 bar / 406 - 413 psi. Note a 500 psi
pressure gauge will need to be installed at the M port of pump 6A for the final adjustment
of this setting.
15. Tighten the flow regulator locknut and replace the cap nut.
16. Recheck the flow regulator pressure setting.
20
pump will have to be adjusted until the maximum flow reading is 200 lpm at 2200 rpm with
the oil at an operating temperature of 45-60 degrees C.
21
15.3.4 M4-15 DIAGRAM
22
5. CONTROL VALVE M4-15 PRESSURE RELIEF ADJUSTMET PROCEDURE
1. Remove hoses for all functions which were previously connected together for the flushing
procedure and plug each end of Rotation, Traverse, and Wire Line winch, Main Winch,
Left and Right Track (If fitted).
2. Refer to the chart below and the Diagram above to set the pressure relief valves for each
function.
3. You will need an assistant to operate each function while this procedure is carried out.
23
17 JACK LEGS VALVE ITEM 46 / 8 SPOOL VALVE ITEM 59
RELIEF VALVE ADJUSTMENT PROCEDURE
1. PREPERATION FOR ADJUSTMENT
1. Remove hoses plug and cap ports for the following functions
1. Mast rise.
2. Mast Dump
3. Upper Breaker.
4. Rod clamp.
5. Chuck
2. MAIN RELIEF VALVE ADJUSTMENT
1. Check that the lines from the auxiliary pump item 85 is connected to the 10.2 cc as per
the hydraulic circuit drawing and the tank line are correctly connected.
2. Check that the relief valves are installed in the correct location corresponding to the
function.
3. Turn counter clockwise 1 full turn the main Pressure relief valve on item 46 (4 spool valve)
and 59 (8 spool valve)
4. Fit a 3000 psi pressure gauge to the pressure test point connected to the p port of valve
item 59.
5. Start the engine and run it at 1800 rpm.
6. Have an assistant operate the chuck lever to the hold position.
7. Adjust the main pressure relief valve on Item 59 fully in (clockwise).
8. Adjust the main pressure relief valve on Item 46 to 200 bar / 2900 psi.
9. Adjust the main pressure relief valve on Item 59 to 172.5 bar / 2500 psi.
10. Operate the chuck lever to neutral.
2. WORK PORT RELIEF VALVE ADJUSTMENT (8 SPOOL VALVE ITEM 59)
1. Follow the chart and steps below for each function to set up the work port pressure relief
valves.
2. Operate the leaver to the up position this allow adjustment to the A port relief valve.
3. Operate the lever to the down position, this will allow adjustment to the B port pressure
relief valve.
4. Return the lever to the neutral position.
5. When Complete reconnect the hoses which were plugged earlier.
24
12.
4. FRONT AND REAR JACK LEGS CYLINDERS (IF FITTED)
1. Raise and lower to ground level only each jack leg cylinder several times, do not raise the
rig, check as follows:
• Correct operation versus name tag drawing.
• Any mechanical fouling
• Any hydraulic oil leaks.
13. Jack the rig up clear of ground, level the rig both front and rear and side to side. Check for
any drift in cylinders, there must not be any drift in 15 minutes. Check during the day.
12. Twice raise the mast to 60° then lower, the third time raise mast fully check as follows:
• Correct operation versus name tag drawing
• Any mechanical fouling
• Any hoses being nipped or pulled
• Any hydraulic oil leaks.
• Check that the mast goes “OVER-CENTRE” smoothly.
• Let mast go into vertical position under its own weight, do not apply pressure
• “LOWER” the mast from vertical position with diesel idling and note pressure
required to initially move it.
• Check at Item 14 at the inlet of valve 59
•
25
ACTUAL PRESSURE BAR APR
PSI APR
13. Lower the mast fully check the mast alignment to the nylon wear pads on the tray.
14. Raise the mast to vertical position.
26
18 ROD CLAMP
1. Connect the “C1” and “C2” ports of the double counter balance valve item 101 together with
a hose. Tee a 200 bar / 2900 psi pressure gauge into the hose.
2. Remove the lock nuts from the pressure adjustments of the valve.
3. Start the engine and operate between 1250-1300 rpm.
4. Operate the rod clamp control lever in both directions and adjust the pressure controls until
77 bar / 1126 psi is indicated on the pressure gauge for both directions of operation.
27
19 HEAD TRAVERSE MICRO FEED, HOLD BACK, PULL DOWN,
MICRO FEED SPEED CONTROL
1. TRAVERSE SYSTEM OPERATIONAL CHECKS
1. With the diesel engine at 800-850 rpm. Operate the traverse lever “UP” and “DOWN”
several times at various lever deflections and check the following;
• Correct operation versus the name tag drawing
• No mechanical fouling as the head moves up / down the mast.
• No hoses connected to the rotation head and traverse cylinder being nipped or pulled
5. Carry out the above test again but with the micro feed lever.
6. Carry out the above test again but with the power float lever.
2. Slowly increase and decrease the pull down pressure control item 39, observe the pull
down gauge readings follows the operation of the pull down control smoothly.
3. Pull down pressure control fully increased. Note the pressure at the pull down gauge item
51 at the panel.
4. Engage the head traverse lever “DOWN”, as well as the micro feed. Note the pressure
reading on the pull down gauge item 51 at the panel.
28
19.4 MICRO FEED SYSTEM
1. Traverse the head to the top of the mast.
2. Pull down pressure control item 39 fully decreased, hold back pressure control item 39 fully
decreased, micro feed speed control item 41 fully increased.
3. Engage the micro feed lever “DOWN”, diesel at 2200 rpm. Slowly increase the pull down
pressure control if required. Note the pressure to just lower the head on the pull down
pressure gauge.
4. Slowly increase the hold back-pressure control and balance, stop the head movement with
the hold back. Note the pressure at the pull down pressure gauge and hydraulic oil temp.
5. As head moves down the mast, play with various hold back; pull down and diesel rpm
settings, the head movement must be smooth.
6. Increase the pull down control to maximum, stop the head movement with hold back
control.
29
7. Balance the rotation head as follows;
• Traverse the head to the top of the mast.
• Fully decrease (turned fully counter-clockwise) the pull down pressure control item 39.
• Fully decrease (turned fully counter-clockwise) the hold back pressure control item 39.
• Micro feed speed control item 41 fully increased.
• Engage the micro feed control lever “DOWN” and balance the mass of head with the
holdback control.
8. Use the head traverse lever to move the head fully down the mast, leave the micro feed
engaged “DOWN” and set the pull down pressure to 100 bar / 1450 psi.
9. Disengage the micro feed lever.
10. Move the head to the top of the mast with the “HEAD TRAVERSE”.
11. Engage the micro feed lever “DOWN”.
12. Let the head come down with the micro feed.
13. Adjust the micro feed speed control item 41 and set the head speed at 50.8mm / 2” per
minute.
14. As the head moves down the mast check for the following;
• Head movement must be smooth.
• No spikes on the pull down pressure gauge to indicate the head is jerky in operation.
• Pull down pressure should be stable through out the travel of the head down the mast.
15. Fully decrease (turned fully clockwise) the micro feed control item 41 and stop the head,
check for zero drift in one minute.
30
• Increasing the pressure setting of item 45 (PBDB-1) will allow the rotation head to move
down the mast.
• Carry out the above at various diesel engine rpm, the power float down operation
should be smooth at all times
2. POWER FLOAT UP SET UP
Note
1. The controls for the power float up operation use item 45 (PBDB-2) and item 35
(RPEC-1).
4. The power float up operation does not require any back pressure to support the
weight of the rotation head or supported drill rods. This means that item 35 (RPEC-1)
is basically set to a nominal setting as described below.
5. The power float up settings of item 45 (PBDB-2) will have to be adjusted to suit the
type of drill rod used.
1. Fully increase (turned fully clockwise) the pull down pressure control item 39.
2. Fully decrease (turned fully counter-clockwise) the pressure setting item35 (RPEC-1) then
turn the adjustment screw clockwise “IN” two full turns. Tighten the lock nut of item 35
(RPEC-1).
3. Traverse the head to the bottom of the mast.
4. Engage the float lever to the “UP” position with the diesel at 1500-1550 rpm.
5. Adjust item 45 (PBDB-2) until the head begins to move up.
6. Disengage the float control lever.
7. Operate the traverse lever and traverse the rotation head to the bottom of the mast.
8. Engage the float lever to the “UP” position.
9. Check the setting by decreasing and increasing the pressure setting of the float control
valve item 45 (PBDB-2).
• Decreasing the pressure setting of item 45 (PBDB-2) should stop movement of the
rotation head.
• Increasing the pressure setting of item 45 (PBDB-2) will allow the rotation head to move
up the mast.
• Carry out the above at various diesel engine rpm, the power float down operation
should be smooth at all times
19.7 CONTROL VALVE STROKE LIMIT ADJUSTMENT
1. Adjust the “B” port stroke limit adjustment until it contacts the spool. Back the adjustment
out 2 full turns.
2. Traverse the head to the bottom of the mast. Mark a line on the mast 1.5 metres from the
top of the carriage.
3. Engage the traverse control “UP” completely with the diesel engine at 2175-2200 rpm.
Check the time to traverse the head 1.5metres “UP” the mast. It should be 3 seconds A.T.M
3-3.5 seconds. Re adjust the “B” port stroke limiter until the correct time is achieved.
Tighten the lock nut on the stroke limit adjustment.
4. Adjust the “A” port stroke limit adjustment until it contacts the spool. Back the adjustment
out 2 full turns.
5. Traverse the head to the top of the mast. Mark a line on the mast 1.5 metres from the
bottom of the carriage.
6. Engage the traverse control “DOWN” completely with the diesel engine at 2175-2200 rpm.
Check the time to traverse the head 1.5metres “DOWN” the mast. It should be 3 seconds
A.T.M 3-3.5 seconds. Re adjust the “A” port stroke limiter until the correct time is achieved.
Tighten the lock nut on the stroke limit adjustment.
31
19.8 TRAVERSE SPEED CHECKS
1. Balance the rotation head as follows;
• Traverse the head to the top of the mast.
• Fully decrease (turned fully counter-clockwise) the pull down pressure control item 39.
• Fully decrease (turned fully counter-clockwise) the hold back pressure control item 39.
• Micro feed speed control item 41 fully increased (turned fully counter-clockwise).
• Engage the micro feed control lever “DOWN” and balance the mass of head with the
holdback control.
• Use the head traverse lever to move the head fully down the mast, leave the micro feed
engaged “DOWN” and set the pull down pressure to 100 bar / 1450 psi.
• Disengage the micro feed lever.
• Move the head to the top of the mast with the “HEAD TRAVERSE”.
• Engage the micro feed lever “DOWN”.
• Let the head come down with the micro feed.
• Adjust the micro feed speed control item 41 and set the head speed at 50.8mm / 2” per
minute.
2. Operate the rig with diesel rpm at 2200. Fill in table.
ACTUAL MEASUREMENTS
Down -
Up -
- Down
- Up
Down - 1 07 60 / 65 20 / 25 45 - 60°C
Up - 0 57 0/5 20 / 25 45 - 60°C
- Down 7 60 / 70 65 / 75 45 - 60°C
- Up 7 0/6 90 / 95 45 - 60°C
32
20 ROTATION
1. MOTOR CONTROL LOCATION
• Refer to photograph below to identify the various motor controls.
• Adjust the height of the maximum speed adjustment screw to 15mm above the maximum
speed screw lock nut.
• Refer to stamped rotation head serial number. Check with the rotation head assembly
section if head has been tested. If not, get a photocopy of test procedure for the rotation
head assembly and test the rotation head.
•Check the rotation head is filled with lube oil to the correct level and the lube oil system
has been primed with oil.
• Fit an external filter to the inlet of the lube oil sight glass at the rotation head.
•Short cut the hoses going to the interlock valve on the side of the mast. This operation
would act as though the rod spin guard is “CLOSED”.
33
2. ROTATION HEAD SPEED CONTROL ITEM 37.1
1. Check the rotation “DRILL/MAKE “lever is in the off position.
2. Fully increase (turned fully clockwise) the “ROTATION TORQUE” control.
3. Leave items 1 & 2 in this position until required to test or adjust the rotation torque control.
4. Tee a 60 bar / 870 psi pressure gauge into the hose connected to the “X” port of the
rotation head motor.
5. Start the diesel engine and set the engine speed to 1200-1250 rpm.
6. Slowly increase (turned clockwise) and decrease (turned counter-clockwise) the pressure
setting of rotation speed control item 37 and observe the pressure gauge reading.
7. The gauge reading should follow the change in movement of the rotation speed control and
be smooth in operation.
8. Fully increase (turned fully clockwise) the rotation speed control and note the maximum
reading.
9. Adjust the rotation speed control to a maximum pressure of 35 bar / 508 psi, Shim between
the knob and the lock nut until a maximum of 35 bar is achieved with the rotation speed
control fully increased (turned fully clockwise).
10. Fully decrease (turned fully counter-clockwise) the rotation speed control item 37.1.
34
20.5 ROTATION HEAD OPERATIONAL CHECKS
1. With the diesel engine at 850-875 rpm. Operate the rotation head control lever
“FORWARD” and “REVERSE” and check the following.
• Correct operation versus name tag drawing.
6. Engage the rotation pilot lever into the forward position and check the lube oil system of the
rotation head as follows;
• Lube oil can be seen flowing through the lube oil sight glass.
• Crack each lube hose connection at the nipple nearest to the bearing and check the lube
oil is coming out of each hose.
1. MINIMUM ROTATION HEAD SPEED WITH MAXIMUM PUMP FLOW CHECK
1. Disconnect and plug the “X” port hose from the rotation head motor
2. Rotation head in high gear (3 :1)
3. Rod spin guard “CLOSED” or interlock valve “OPENED” by an override device.
4. Engage the rotation pilot lever into the “FORWARD” position completely
5. Diesel engine at 2200 rpm A.R.R 2195 – 2200
6. Refit the hose to the “X” port of the rotation head motor.
2. MAXIMUM ROTATION HEAD SPEED SETTING
1. Run the rotation head up to maximum speed in stages and hold each stage for 1-2 minutes
to allow the head and rotation motor to warm up to operating temperatures.
2. Check the lube oil sight glass for lube oil flowing through the sight glass
3. Set the maximum rotation speed at 1450 rpm with the following conditions;
• Diesel at 2200 rpm ARR 2195-2200
• Rotation pilot lever engaged “FORWARD”.
• Slowly increase (turned clockwise) the Rotation speed control fully
• Check you can feel the rotation motor piston barrel resting firmly against the maximum
speed adjustment screw as the screw is adjusted.
• Check the rotation head rpm with a hand held tachometer.
35
• = 428 psi A.P.R. 420-428 psi.
• The motor piston barrel has moved away from the maximum speed screw. The adjustment
screw will be easy to turn.
10. Recheck the above by decreasing (turned counter-clockwise) and increasing (turned fully
clockwise) the pressure setting of the rotation speed control item 37.
11. Recheck the maximum rotation forward speed as previously stated, reset if required.
4. REVERSE ROTATION MAXIMUM SPEED
1. Engage the rotation control lever into “REVERSE” and note the rotation speed with the
diesel at 1500 rpm with the rotation speed control item 37 fully decreased.
2. Adjust the “B” port stroke limit adjustment screw until it contacts the spool.
3. Adjust the “B” port stroke limiter adjustment screw until the rotation reverse speed is 100-
105 rpm. Tighten the lock nut of the stroke limit adjustment screw.
4. Check at various diesel rpm that the rotation reverse speed is between 100-105 rpm.
20.5.5 REVERSE ROTATION SPEED INTERLOCK VALVE CHECK PROCEDURE
2. Engage the rotation control lever into “REVERSE” and note the rotation speed with the
diesel at 1500 rpm with the rotation speed control item 37 fully decreased (turned fully
counter-clockwise).
5. Adjust the rotation head speed control item 37 to fully increased (turned fully clockwise).
Note the rotation rpm. There should not be any increase in rotation speed between fully
decreased and fully increased.
20.5.6 ROD SPIN GUARD AND ROTATION FORWARD MINIMUM SPEED
3. Remove the override tool from the rod spin guard valve on the side of the mast. This would
mean that the rod spin guard is “OPEN”.
6. Set the rotation head rpm as follows:
• Rotation speed control item 37 fully decreased (turned fully counter-clockwise). Rotation
head in high gear.
• Diesel at 2000 rpm ARR 1900- 2000 RPM.
• Rotation control lever fully engaged into the “FORWARD” position.
• Adjust item 98 (pressure relief valve) until the rotation head is doing 100-105 rpm.
• Check the setting by disengaging and engaging the rotation control lever several times
7. Refer to MPL10592 and drawing number 10592 (latest revision of each) check the rod spin
guard conforms to these drawings. Check the rod spin guard fits and operates correctly.
8. Check the operation of the guard as follows.
• No mechanical fouling when the head is traversed “UP” or “DOWN” the mast with the
rotation head in the drill position.
•When the guard is “OPEN” the maximum rotation speed is 100 with the diesel at 2200
rpm.
• When the guard is “CLOSED” the maximum rotation speed is 1500 with the diesel at 2200
rpm.
36
7. ROTATION FORWARD PRESSURE CHECK
• Diesel at 2200 rpm ARR 2195-2200
• Rotation pilot lever engaged “FORWARD” completely.
• Slowly increase the Rotation speed control fully
• With diesel at 2200 rpm fill in table.
80/ 85 55/65
1160-1232
ACTUAL LENGTH MM
INCH
37
5. This can be achieved by packing under the rod clamp base with shim material.
6. When the rod clamp base bolts has been torque up, re-inspect for alignment.
11. Fully decrease (turned fully counter-clockwise) the rotation torque pressure control
12. Release the rotation control lever to neutral.
13. Operate the chuck and clamp control levers to the “RELEASE” position and remove the “N”
size drill rod from the chuck and the clamp.
38
10. The rotation head should rotate and the head travel down at the same time. If necessary
adjust the rotation make torque control item 44 until the rod thread shoulders butt up
together. Release the rotation lever and operate the float lever to the “NEUTRAL” position.
11. Operate the chuck control lever into the “RELEASE” position.
12. Break the drill rod apart with a 915mm 36” pipe wrench, but do not screw the rod joint
apart.
13. Check there is a minimum distance of 600mm / 24 inches between the chuck and the rod
clamp.
14. Operate the chuck control lever into the “HOLD” position.
15. Repeat steps 8 to 13, several times and check the operation of the float / rotation system.
16. Leave the drill rod in the chuck and the rod clamp.
2. FLOAT UP TO BREAK OUT A ROD JOINT
1. Operate the chuck control lever into the “RELEASE” position.
2. Operate the float control lever into the “UP” position and adjust item 45 (PBDB-2) on the
float control manifold until the head just moves up.
3. Make up the drill rod joint with a 915mm 36” pipe wrench, until the shoulders on the rod
joint butt up to each other.
4. Operate the chuck lever into the “HOLD” position.
5. Engage the drill / make, control lever item 31 into the “ON” position.
6. Decrease fully (turned fully counter-clockwise) the rotation make torque pressure control
item 44
7. Engage the float control lever into the “UP” position and at the same time engage the
rotation control lever “REVERSE”.
8. The rotation head should rotate and the head travel up at the same time. If necessary
adjust the rotation make torque control item 44 until the rod thread shoulders break away
from each other. Release the rotation lever and operate the float lever to the “NEUTRAL”
position.
9. Operate the chuck control lever into the “RELEASE” position.
10. Make up the drill rod joint with a 915mm 36” pipe wrench, until the shoulders on the rod
joint butt up to each other.
11. Check there is a minimum distance of 600mm / 24 inches between the chuck and the rod
clamp.
12. Operate the chuck control lever into the “HOLD” position.
13. Repeat steps 7 to 12, several times and check the operation of the float / rotation system.
39
21 MAIN WINCH
40
2. BRAKE RELEASE PRESSURE REDUCING VALVE ITEM 72 TEST
1. Connect a 3000 psi pressure gauge at item 72 brake reducing valve.
2. Remove the break pressure line from the main winch gear box.
3. With diesel at 850-875 rpm, check by very slowly engaging the main winch control lever
“UP” and “DOWN”, that a pressure of 172.5 bar / 2500 psi reads on the gauge.
4. Re connect the break release hose to the port on the main winch gear box.
41
11. Remove the tee and the 400bar/ 5800 psi pressure gauge from the “B” port of the main
winch manifold block.
1. Operational Checks
Note
Do not operate the main winch control lever during this test
1. Tee a 100 bar 1450-psi pressure gauge into the brake release pressure port of the main
winch gearbox..
2. Operate the main winch float control item 27 to the “ON” position with the diesel at 850-rpm
A.R.R. 850-875.
3. You should have a 35-40 bar / 507-580 psi reading on the pressure gauge at the brake
port.
4. Check the pressure drains out of the brake cavity and pressure gauge by operating the
winch float control to the “OFF” position.
5. Carry out the above operations several times to check the gauge reading builds to 35-40
bar / 507-580 psi when the winch float control is “ON” and drains when “OFF” and with the
diesel engine at various rpm.
6. Operate the main winch float control item 27 to the “ON” position,
7. Operate the winch float control to the “ON” position. Operate the chuck control lever item
21 to the “RELEASE” position, the pressure reading on the gauge at the brake port should
drain.
8. Operate the rotation head side rack to the out position, the pressure reading on the gauge
at the brake port should drain.
9. Operate the chuck control lever to the “HOLD” position and check the pressure reading at
the gauge at the brake port. It should build to 35-40 bar / 507-580 psi.
10. Carry out the above operations several times to check the gauge readings builds to 35-40
bar / 507-580 bar when the chuck control lever is in the “HOLD” position and drains when
the lever is in the “RELEASE” position and with the diesel engine at various rpm.
11. The main winch rope will need to be connected to the drill head connected to a suitable
hoist plug with a drill rod in the chuck. Engage the micro feed down and slowly increase
the pull down to make sure the float works correctly.
3. MAIN WINCH NO LOAD PRESSURE CHECK
1. Operate the main winch control “UP”-“DOWN”, with no rope fitted and with the diesel at
2200 rpm A.R.R 2195-2205. Fill in the table.
42
• Brake holding, cut diesel, check if weight drifts, beware that if weight drifts that it will free
fall.
43
22 WIRE LINE WINCH
1. WIRE LINE WINCH OPERATIONAL CHECK
1. With the diesel engine at 850-900 rpm, engage the wire line winch control lever “UP” and
“DOWN” slowly, and check the following.
• Correct operation versus the nametag.
• The wire line winch drum slowly starts and stop and is not jerky in operation as the control
lever is slowly engaged and disengaged.
• No mechanical fouling.
• The drum runs reasonable true and does not have any excessive run out.
2. Check that when engaging the wire line winch control lever at any diesel rpm or lever
position combination that no surging continues more than 5 seconds.
3. Check that when engaging the wire line winch control lever at any diesel rpm that there is a
steady increase or decrease in drum rpm especially at the start of control.
44
22.4 WIRE LINE WINCH ROPE
1. Fit the wire line winch rope using the rope pre tension device.
23 WATER PUMP
1. Connect an air-tight suction line to the water pump suction port, and submerge it into a 205
litre drum filled with water.
2. Fit a modified drill rod (water swivel one end and a high pressure ball valve attached to the
other end of the rod) to the Rotation Head.
3. Set the water pressure relief valve at water pump to the minimum setting.
4. Fit a 200 bar / 2900 psi pressure gauge to the pressure test coupling item 14 on pressure
relief valve item 4.
5. Run a suitable sized hose from modified drill rod to the water drum.
6. Set the water valve and the vent valve to the following positions;
• Water Valve - “ON” position
• Vent Valve - “OFF” position
7. Water pressure gauge connected to water manifold.
8. With diesel at 2200 rpm, water “ON-OFF” control valve item 27 in the “OFF” position, water
pump coarse flow control item 36 fully increased, ball valve connected to the drill rod fully
open.
NOTE
1. During this test the water pressure relief valve setting will have to be increased.
2. Check as follows:
• Start and stop the water pump with water pump “ON-OFF” control valve at the control
panel.
• Control the rpm of water pump from maximum to minimum with the water pump fine and
coarse flow controls at the control panel.
• Check for any excessive vibrations at the water pump, which could indicate a
misalignment between the water pump and the motor drive shaft.
• Check for leaks in the water piping, water pump and valves.
• With water pump at max. speed note the following:
3. With the water pump controls set as described above, slowly close the ball valve on starter
rod until 60 bar / 870 psi shows on the water pressure gauge. Check as follows:
• Adjust the water pressure relief valve as required.
• Water pressure gauge follows the opening and closing of the ball valve.
• Adjust the water pump speed control from maximum to minimum and back to maximum.
• Any excessive vibrations.
• Leak in the water piping, water pump and valves.
• Fill in the table below
45
NOTE
1. Hydraulic circuit pressure at Item 14 valve 4.
2. During this test the water pressure relief valve setting will have to be increased.
2. Check the rotation head is fully commissioned. Remove the ball valve from the drill rod.
3. Fit a modified drill rod sub, which has a 7/16 JIC nipple on it. To the drill rod.
4. Engage the water pump speed control item 33 and have water running through the 7/16
nipple. Adjust the water pump flow control until 400-600 psi water pressure reads on the
water pressure gauge.
5. Run the rotation head up to maximum rpm Check the following:
• Water swivel for leaks
• Hoses and valves from water pump to water swivel for leaks.
6. Disconnect the water pump test equipment and reduce the water pressure valve setting to
minimum.
46
25 DIESEL LOAD TEST
The engine should hold the load generated by the traverse system, water pump system, mud mixer
system, pilot pressure system and rotation speed control.
The engine may pull down to below 2200 rpm, if it does adjust the rpm to bring it back to 2200 rpm.
With the system set up as above the calculated power requirements is 107kW 143.4hp.
47
26 COMMISSIONING CHECK POINTS CHECK THE FOLLOWING
• Before the rig is handed over to the sales department, check the following list for any items
that may have not been covered or have been forgotten during the commissioning
procedure.
48
Item Description Checked, BY
and When
By When
Diesel Engine 18. Check coolant level
19. No coolant leaks
20. Check radiator inhibitor / antifreeze been put
into the cooling system
21. Check lube oil level
22. No lube oil leaks
23. Alternator and fan drive belt correctly tensioned
24. Correct operation of all engine controls and
gauges
25. Check tightness of all bolts, nuts & hose clamps
26. Emergency shut down operates correctly
27. Battery acid level is correct
28. All electrical connections have been sprayed
with sealant.
29. Check the radiator guard has been fitted
30. Check all components and connections for the
air inlet system of the engine are tight and
correctly fitted
31. Check all components and connections for the
exhaust system of the engine are tight and
correctly fitted
32. Drain any water from fuel filters
49
Item Description Checked, BY
and When
By When
Control Cabinet 44. Correct operation of all functions versus name
tag drawing
45. No oil leaks
46. Check all bolts, nuts & hose ends are tight
47. All pressure gauges are straight
48. All adjustable valves have knobs fitted to the
adjustment screws.
49. All control levers are tight
50. All electrical connections have been sprayed
with sealant
51. Removable sections is easily removed from the
cabinet assembly and is securely pinned in
place when in the cabinet assembly
Mast Assembly 52. Upper section of mast has been fitted to the
lower section.
53. Rod slide has been fitted and operated with the
traverse system of the rig
1. Rod side roller works and the stop rod is fitted
and the threads are covered with anti seize
compound.
2. If the mast is dissembled the correct bolts to
reinstall the mast must be put back and
tightened.
Crown Assembly 3. Check MPL8535-4 MAST CROWN ASSEMBLY
to ensure all components are fitted.
4. Check all bolts, nuts & are tight
5. Wire line sheaves rotate freely and has been
greased
6. Wire line sheave frame (crown
assembly)correctly fitted
7. Main winch sheaves rotate freely and has been
greased
8. Main winch sheave frame (crown assembly)
correctly fitted
Mast Platform 1. Refer to MPL and drawings for the stay rods and
(basket) Assembly check all of the components listed on the MPL
are available and have been trail fitted to the rig.
Platform Stay Rod
2. Make sure all pins are protected with anti seize
Assemblies and
and rotate freely. All the pins must be included
Mast Stay Rods
with the rig and secured.
50
Item Description Checked, BY
and When
By When
Mast Dump Cylinder 3. Correct operation
4. No oil leaks
5. Check all bolts, nuts & hose ends are tight
6. Cylinder pivot pins are correctly secured and
have been greased.
7. Check the “U” bolt supporting the cylinder is
correctly fitted.
8. The mast slides easily up and down on the mast
dump slides with no mechanical fouling as the
mast moves.
Traverse Cylinder 9. Correct operation
10. No oil leaks
11. Check all bolts, nuts & hose ends are tight
12. Cylinder pivot pins are correctly secured
13. Lock nuts fitted where applicable and tight
14. No misalignment of components
51
Item Description Checked, BY
and When
By When
Rod Clamp 27. Correct operation
28. No oil leaks
29. Check all bolts, nuts & hose ends are tight
30. Clamp pivot pins are correctly secured
31. The guard has been fitted over the rod clamp
operating mechanism and clears all
components.
Water Pump 32. Correct lube oil level
33. Correct operation
34. No oil leaks
35. Check all bolts, nuts & hose ends are tight
36. Water relief valve has been reset to the
minimum setting
37. The water pump has been drained of all water
38. Suction fitting has been plugged
General Points 39. Check all standard accessories have been fitted
to the rig and operate correctly
40. Check all standard accessories fit are painted
and in the standard accessories box
41. Match drill all name tags
42. Safety and warning stickers have been fitted
43. Check the rig has the latest up date
modifications fitted
44.
52
27 SERIAL NUMBERS OF EQUIPMENT
CLIENT: RIG NO.:
MIN MAX
1 Rig Engine Type
2 Rig Engine No.
3 Rig Engine Model No.
4 Hydraulic Pump No. 85
5 Hydraulic Pump No. 6A
6 Hydraulic Pump No. 6B
7 Hydraulic Pump No. 6C
8 Rotation Head
9 Rotation Head Motor
10 Main Winch Gearbox
11 Main Winch Motor
12 Wire Line Winch Motor
13 Water Pump
14 Water Pump Motor
15 Rig Hydraulic Oil Cooler
16 Mud Mixer Motor
53
28 SIGNATURE FORM
1. All points in this procedure have been commissioned as per procedure and have been
initialled and dated.
Commissioning Personnel
Name Date
Name Date
28.2 A visual and operational inspection by sales has been done and any points noted by sales
corrected by production.
Name Date
Name Date
3. Production Manager has sighted finished procedure and sales correction list.
Production Manager
Name Date
54
Revision list
55